ERCOT Monthly Operational Overview (January 2015) ERCOT Public February 15, 2015.
Emergency Demand Response Concept Overview and Examples Presented to: ERCOT December 3, 2004...
-
Upload
kenneth-franklin -
Category
Documents
-
view
212 -
download
0
Transcript of Emergency Demand Response Concept Overview and Examples Presented to: ERCOT December 3, 2004...
Emergency Demand Response Concept Overview and Examples
Presented to:ERCOT
December 3, 2004
Presented by:Neenan Associates
2Confidential 30-Nov-04
ISO Demand Response Programs
Spot EnergyMarket
Price Price
Real Time
Day Ahead
Price Following
Scheduled Curtailments
PJM
PJM
NY
NE
NY
NE
PJM 1020
108
377
Resources 2004
• Very low activity in NYISO day-ahead (low prices)• More real-time activity, but questions about value
3Confidential 30-Nov-04
ISO Demand Response Programs
Capacity
ReliabilityReliability
PJM
PJM
Sp
otForward
Emergency Op Reserves
ICAP Resource
Dispatched Operating Reserves
NY
NY
NE
NY
NE
PJM 1783
249
1562
Resources 2004
• Emergency program heavily marketed in NY, ICAP• ICAP increasing in importance• Ancillary services market participation is a new initiative
4Confidential 30-Nov-04
Need for Emergency DR
Operating reserves ensure that the loss of a major transmission line or large generator(s) does not imperil the entire system
If a deficiency is extreme enough, load shedding is undertaken to protect the overall system integrity
Well orchestrated load curtailments help mitigate, or avoid operating reserve deficiencies and their consequences…
Without disrupting spot market price formation Only the ISO can effectively dispatch such
resources – reliability is a social good
5Confidential 30-Nov-04
ISO Emergency DR Programs Emergency DR Programs provide system operators with
unique reserves Resources indigenous to the market Fully synchronized to the system, Short notice (2 hours) High availability rate, diverse and reliable No capacity payment required – pay for performance only
NYISO
PJM
ISO-NE
Start Date 2001
May 2001
May 2001
June 2001
292 / 425
17 / 62
12 / 6
2002
1,711 / 668
61 / 629
79 / 113
2003
1,231 / 879
99 / 629
106 / 249
Reg. Sites / Subscr. MW
Source : NERA Dec. 2003
About the same
2004
About the same
Slightly higher
6Confidential 30-Nov-04
NYISO EDRP Registration Requirements
To participate, customers must: Register at least 100 kW of load curtailment and/or
output from on-site generator
Have an interval meter
Small-customer aggregations HVAC controls, pool pumps, etc. can employ statistical method for determining performance
Program registration options Load Serving Entity (LSE)
Curtailment Service Provider (CSP)
As a Direct or Limited Customer of the NYISO
Currently, almost all
participants register through a default service
utility
7Confidential 30-Nov-04
NYISO EDRP Dispatch Rules
NYISO can dispatch EDRP resources at the zonal level, on an as-needed basis
EDRP invoked when In-Day Peak Hour Forecast indicates an 30-Min operating reserve shortage and/or Major Emergency state is declared
Sometimes a non-binding advisory notice is provided a day-ahead
Once operating reserve shortage is verified in-day, curtailment event is declared with at least two (2) hour’s notice of event
Four (4) hour minimum event durationConcession to
customers
8Confidential 30-Nov-04
NYISO EDRP Customer Baseline Load (CBL) Methodology
Uses most recent ten (10) days hourly interval-metered usage values1. Calculate each day’s total usage during event hours
2. Choose the resulting five (5) highest days
3. Average the interval usage data by hour over those five days to get an hourly CBL value
Optional adjustment for weather can be applied CBL is adjusted(up & down) relative to
conditions 2 hours prior to the start of the event
9Confidential 30-Nov-04
NYISO EDRP Payment
Participation in any event is voluntary No requirement to notify the NYISO of their intent
to participate in an EDRP event in order to be paid
Payment is for any measured level of curtailment
Payment is the higher of $500/MWh or LBMP NYISO pays the registration agent, not
participants Unregulated Agents’ contract terms are
proprietary
NYPSC requires regulated LSEs pass along at least 90% of payment
Price has generally
lower
10Confidential 30-Nov-04
Emergency DR Program Benefits
Reliability Benefits – curtailments reduce the probability of an outage due to operating reserve shortfalls
Value is defined as product of: Expected Unserved Energy VOLL
Program is operated to avoid any unintended consequences on on real-time spot market prices If the DR reserves turn out to be needed, then they can
set real-time LBMP, but only if price otherwise is below $500
Adopted because initially the dispatch of large DR resources appeared to cause RT price to crash
11Confidential 30-Nov-04
NYISO EDRP Historical Program Benefits
2001
2002
2003
8,159
6,632
7,734
EDRP Curtailed
MWHs
20.1
4.8
32.3
Reliability Benefits
($M)
4.2
3.3
3.9
Program
Payments ($M)
~ 5
~ 1.5
~ 9.5
B/C
Ratio
12Confidential 30-Nov-04
EDRP Reliability Benefits during Northeast Blackout of 2003
Recovering System State (August 15) Change in LOLP=1.0, High VOLL=$5,000/MW, Load At
Risk=DR Recovered System State (August 16)
Change in LOLP=0.2, Low VOLL=$2,500/MW, Load At Risk=Only DR Needed to meet 30-Minute Reserve Margin
Date System State Benefit Payment Ratio
Aug. 15 Recovering $31.6M $3.2M 9.5
Aug. 16 Recovered $0.7M $0.7M 1.0
Total $32.3M $3.9M 8.3
13Confidential 30-Nov-04
Some Observations
• Participation in NYISO grew to over 800 MW in three years
• Only about 10% of registered resources are DG• Diverse participation contributes to availability• Constant and reliable curtailment performance
• Level stable over 5-6 hour events• On average, curtailment is about 1/3 of CBL
• Vital early role for Curtailment Service Providers• Vital agency role
• PSC tariffs and jawboning• NYSERDA outreach and technology support