Electricity for a Better Life
INDONESIA STATE OWNED ELECTRICITY CORP. ( PLN )
PLANS FOR RENEWABLE ENERGY DEVELOPMENT
Presented by:Presented by:NASRI SEBAYANG DIRECTOR OF CONSTRUCTION PT PLN ( PERSERO )
THE 2nd CLEAN POWER ASIA CONFERENCE & EXPO 2012BALI INTERNATIONAL CONFERENCE CENTRE
May 14-16, 2012 , Bali , Indonesia
Electricity for a Better Life
CURRENT CONDITIONCURRENT CONDITION
Hal 2
Electricity for a Better Life
ENERGY PRODUCTION ENERGY PRODUCTION 20112011
1. ENERGY PRODUCTION COMPOTITION BASED ON POWER SOURCES
Lease Gas; 0,98%
IPP; 20,86%
2 ENERGY PRODUCTION COMPOTITION BASED ON PRIMARY ENERGY
Owned ; 71,34%
Lease Fuel Oil; 6,82%
2. ENERGY PRODUCTION COMPOTITION BASED ON PRIMARY ENERGYFuel oil, 23.%Geothermal
and other, 5.%
BBM
Hydro, 7%Coal, 44%
Air
Gas Alam
Batubara
PB + LL
Hal 3
Nat.Gas, 21%
Disajikan terbatas untuk RDP Komisi VII DPR RI - PLN, 7 Maret 2012
Electricity for a Better Life
Generation Capacity (type and ownership)
Existing Total Capacity 34,928 MW
440695Geothermal
Operational Data 2008 12,170
3,503
3,142
347
Coal STPP
HEPP
Operational Data 2008
2,871
8,112
477
285
GTPP
CCPP
2,756130
0 2,000 4,000 6,000 8,000 10,000 12,000 14,000
Diesel PP
Hal 4
IPP (MW) PLN (MW)
Electricity for a Better LifeNAD
89,79% SumutK lti
Kategori :
> 60 %Kepri
ELEELECCTRIFITRIFICCAATTIION RATIO ON RATIO 20122012
84,41%
Riau 80,16% Kalbar
76,32%
Kalteng77,37%
Kaltim70,92%
Sulut83,36%Gorontalo
66 50%
Malut75,84%
41 - 60 %
20 - 40 %
93,98%
Sumbar81,85%
Sumsel74,95%
66,50%
Sulteng73 99%
Sulbar74,60%
Papua Barat65,17%
Bengkulu
Babel89,71%
Jakarta
Jambi86,22%
BaliKalsel
73,99%
Sultra68,12% MalukuBengkulu
77,38%
Lampung76,75%
100%
Banten69,81%
Bali76,90%
83,44%Sulsel78,77%
a u u78,76%
Papua34,64%
RENCANA (Tahun)REALISASI (Tahun)
Jabar70,82%
Jateng77,85%
DIY75,98%
Jatim72,32%
NTB57,50%
NTT45,47%
Hal 5
2006 2007 2008 2009 2010 2011 2012 2013 2014Rasio Elektrif ikasi
63% 64,3% 65,15% 65,79% 67,15% 72,95% 75,30% 77,65% 80,0%
Electricity for a Better Life
FUTURE CONDITIONFUTURE CONDITION
Hal 6
Electricity for a Better Life350 000 300 000
ELECTRIC DEMAND PROJECTION 2011-2020 (GWh)
I d t i200 000
250,000
300,000
350,000
Indonesia
200,000
250,000
300,000
Jawa‐Bali
Residensial
BisnisPublik
Industri
50,000
100,000
150,000
200,000
Residensial
BisnisPublik
Industri
50,000
100,000
150,000
0
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Residensial
0
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
35,00060,000
PublikIndustri20,000
25,000
30,000
Indonesia Timur
blikIndustri
30 000
40,000
50,000
Indonesia Barat
Residensial
Bisnis
Publik
5,000
10,000
15,000
Residensial
BisnisPublik
10,000
20,000
30,000
Hal 7
0
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
0
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Electricity for a Better Life
Target of National Energy Mix -2025
• Presidential Decree No 5/2006 regarding National Energy Policy
Bio-fuel 5 %
Coal 33 %
N®eothermal 5 %
OilOil
Gas 30 %Gas 30 %N&RE17 %
Biomass, Nuclear,Hydro Solar Power
20 %20 %Hydro, Solar Power,Wind Power 5 %
Coal Liquefaction 2 %
Hal 8
Electricity for a Better Life
Projected Demand : 2011-2020
IB 10 2%
24 TWh
55 TWh
IB : 10,2%
13 TWh
31 TWh
IT : 10,8%
125 TWh
241 TWh
JB : 7,9%
Average growht of Indonesia Electricity demand 8,46% annually2011 2020
Hal 9
Electricity for a Better Life
Fuel Mix Indonesia 2011-2020
G
LNGHSD
21% 19% 17% 15% 12% 8% 8% 8%4%
3%5% 6% 5% 7% 9% 9% 8%
2%
1.1%0% 0% 0% 0% 0% 0% 0%
16.12%8.57%
3.93%1.81% 0.99% 0.88% 0.77% 0.70% 0.70% 0.71%
90%
100%
Gas
MFO 17%21%
21% 19%
0%
5%
60%
70%
80%
Coal
61% 63%63% 64% 64% 65% 64% 64%
40%
50%
60%
50% 54%
20%
30%
Geothermal
Hydro
6% 6% 6% 5% 5% 6% 6% 6% 6% 6%
5% 4% 4% 5% 8% 8% 10% 11% 12% 12%
0%
10%
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Hal 10
Hydro
Share of RE plan to increase from 11 % (2011) to 18 % ( 2020 )
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Impor Biomass Surya/Hybrid HSD MFO LNG Gas Batubara Geothermal Hydro
Electricity for a Better Life
Plan of Additional Plants Expansion
5,583
6,877
5,941
7,164
6,436
6,000
7,000
8,000
4,971
4,271 4,181
5,034 4,882
3 000
4,000
5,000
1,000
2,000
3,000
‐
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
PLTU PLTA PLTP PLTGU PLTG PLT Lain Total
New Plants Expansion up to 2020: 55,3 GW• Coal : 35,6 GW• Hydro : 5,7 GW
• Geothermal:: 6,2 GW
Hal 11
• Combine Cycle: 3,3 GW• Gas Turbine: 4,1 GW
• Others: 0.4 GW
Electricity for a Better Life
RENEWABLE (GREEN ) AND NEW ENERGY OUTLOOKRENEWABLE (GREEN ) AND NEW ENERGY OUTLOOK
Hal 12
Electricity for a Better LifePLN h l d h d it l hi t i i f it
Green Energy in PLN Perspective
• PLN has already had a quite long history in using green energy for itselectricity generation,
• The use of green and new energy is further encouraged since theThe use of green and new energy is further encouraged since theenactment of Presidential Decree No.5/2006 regarding the NationalEnergy Policy,
P id ti l D N 5/2006 t t th t t f d• Presidential Decree No.5/2006 sets out the target of green and newenergy mix in 2025 to be 17% (from ~ 5% in 2006) of the total energyconsumption in the country.
• Along with the government policy, PLN keeps seeking to increase itsgreen energy mix for electricity generation by including the scenario inits General Plan of Electricity Facility Development (RUPTL) for 2011‐2020.
• Development of Green energy will be progressed intensively depend ontechnology development and economic viability .
Hal 13
Electricity for a Better Life
ALTERNATIVE & RENEWABLE ENERGY RESOURCE POTENTIAL
No RESOURCES Potential
1 Hydro 75,000 MWy ,
2 Biomass 50 GW
3 Mini/Microhydro 500 MW
4 S l 4 8 kWh/ 2/d4 Solar 4,8 kWh/m2/day
5 Wind 3 - 5 m/s
6 Geothermal 29,000 MW
7 N l 3 GW i 11
Hal 14
7 Nuclear 3 GW in 11 year
Electricity for a Better Life
RENEWABLE ENERGY MIX ROADMAP
2010Non-ReNEW Hydro Geothermal
12%
2020Non-ReNEW Hydro Geothermal
12% 3%6%
12%
85% 82%
• The development of Green Energy Power Plants is part of PLN scenario for securing the electricity supply for the country which as a whole will require huge financing capability.
• 18 % green energy mix will improve National Average Grid Emission Factor
Hal 15
from 0.778 kgCO2/kWh in 2011 to 0.756 kgCO2/kWh in 2020.
Electricity for a Better Life
DEVELOPMENT PLAN OF POWER GENERATION CAPACITY (INCL. GREEN & NEW ENERGY DEVELOPMENT)
Tahun 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 TotalPLN
Coal STPP 3,774 4,112 2,971 1,426 1,570 250 1,110 898 1,404 1,522 19,036 Comb. Cy. PP 444 743 116 - - - - - 750 750 2,803 Gas TPP 222 405 1,030 790 140 30 85 480 75 630 3,887 Diesel PP - 1 33 41 41 22 - 22 17 18 194 Geo. PP 24 63 55 13 235 83 20 20 20 220 752 Mi i HEPP 4 17 30 49 7 3 5 5 2 2 123
PLN
Mini HEPP 4 17 30 49 7 3 5 5 2 2 123 HEPP 8 20 - 4 242 1,598 541 279 744 950 4,385
Total PLN 4,477 5,360 4,234 2,323 2,234 1,985 1,761 1,704 3,012 4,092 31,179
Coal STPP 924 1,029 102 1,521 2,719 4,582 3,675 1,110 425 450 16,537 Comb. Cy. PP 150 130 180 - - - - - - - 460
IPP
Gas TPP - 104 102 - - - - - - - 206 Diesel PP - - - - - - - - - - - Geo. PP - - 60 245 855 343 937 1,270 1,590 195 5,495 Mini HEPP 16 22 204 90 44 1 1 - - - 378 HEPP 10 200 8 45 70 246 40 83 - 135 837
Total IPP 1,100 1,485 656 1,901 3,688 5,172 4,653 2,463 2,015 780 23,913
Coal STPP 4,698 5,141 3,073 2,947 4,289 4,832 4,785 2,008 1,829 1,972 35,573 Comb. Cy. PP 594 873 296 - - - - - 750 750 3,263 Gas TPP 222 509 1,132 790 140 30 85 480 75 630 4,093 Diesel PP - 1 33 41 41 22 - 22 17 18 194 Geo. PP 24 63 115 258 1,090 426 957 1,290 1,610 415 6,247
PLN+IPP
Mini HEPP 20 38 234 139 51 4 6 5 2 2 501 HEPP 18 220 8 49 312 1,844 581 362 744 1,085 5,222
Total PLN+IPP 5,577 6,844 4,890 4,224 5,922 7,157 6,414 4,167 5,027 4,872 55,092 SMALL SCALE GREEN & NEW ENERGY PP
7 32 81 51 22 7 23 14 7 10 253
Hal 16
• Total Capacity of Green & New Energy PP to be built in the period is 12,222 MW(total capacity of Geothermal PPs, Hydro Electric PPs-HEPP, Mini HEPPs, and Small Scale Green & New Energy PP)
• 55% of the total capacity of Green Energy PP will be expected from IPPs
Electricity for a Better Life
DEVELOPMENT PLAN OF SMALL SCALE POWER GENERATION UTILIZING GREEN & NEW ENERGY
No RE Plant unit
Year
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 TOTAL
1 Mini Hydro MW 23 37 198 126 46 193 203 214 225 235 1500
2 Solar PV MWp*) 2 30 50 60 70 70 75 75 80 80 5922 Solar PV MWp ) 2 30 50 60 70 70 75 75 80 80 5923 Wind Power MW 0 0 10 10 15 15 20 20 25 25 1404 Biomass MW 16 33 35 35 35 40 40 45 45 50 3745 Sea Current MW 0 0 2 0 0 5 5 5 5 5 276 Bi F l MW**) 10 1 1 14 8 8 96 Bio-Fuel MW**) - 10 15 15 14 8 7 7 8 9 93
7 Coal Gassification MW 6 32 81 43 22 7 22 14 6 10 243
TOTAL MW 47 142 391 289 202 338 372 380 394 414 2 969TOTAL MW 47 142 391 289 202 338 372 380 394 414 2,969
Hal 17
Electricity for a Better Life
CURRENT INTENSIVE RE DEVELOPMENT PROGRAM
2nd FAST TRACK PROGRAM
PV 100 ISLANDS
3967 Mw of Geothermal and 1200 Mw HydroIn year 2016
20 Mwp capacity operated in 2012
PV 1000 ISLANDS
p p y p
225 Mwp capacity between 2013-2015
SOLAR HOME SYSTEM
SOLAR THERMAL 5 Mw capacity in 2015 ( R & D )
400 000 Houses on 2014SOLAR HOME SYSTEM
MICRO AND MINIHYDRO Currently 163 IPPs, 665 Mw (operating 36 Mw )
400.000 Houses on 2014
BIO MASS Currently 19 Projects, 91 Mw ( operate 61 Mw )
Hal 18
SEA CURRENT 2 Mw in planning ( R & D )
Electricity for a Better Life
MAJOR CHALLENGES OF GREEN ENERGY DEVELOPMENT
Major Challenges faced by PLN in utilizing green & new energy for electricity generation, i.e.:
1 The Electricity demand grow fast while about 1/3 of1. The Electricity demand grow fast while about 1/3 of the country is not yet electrified,
2. The country needs relatively low electricity price to be able to support economic growth,
3. Electricity price from Green Energy PP still relatively higher than Conventional Energy PPhigher than Conventional Energy PP,
4. The limited financing capability of PLN,
5. Providing attractively cooperative schemes to encourage5. Providing attractively cooperative schemes to encourage participation of private investor in Green Energy Development.
Hal 19
Electricity for a Better Life
IPP SCHEME FOR GREEN ENERGY DEVELOPMENT
• PLN as a electricity single buyer from IPP Power Plant
• PLN concern to capacity, energy production, energyPLN concern to capacity, energy production, energyprice, availability and continuity
• IPP Provider/Developer responsible to the Power• IPP Provider/Developer responsible to the PowerPlant, the Technology of PP, O&M
• As far as no other developer at a certain proposed PP• As far as no other developer at a certain proposed PPlocation, bidding process by direct appointment (for up to25 MW)
• Great opportunity for private to make a Power PurchaseAgreement with PLN in IPP Scheme
Hal 20
Electricity for a Better Life
CONCLUSION
• Electricity demand in Indonesia is growing fast to cope withthe economic growth and the effort for electrifying entireareas of Indonesia,
• Utilization of Green Energy in Power Generation has beenconsidered to be part of PLN scenario in securing electricityp g ysupply for the country, and also for PLN becoming anenviromentally friendly enterprise,
• Government of Indonesia plays very essential role forencouraging optimum utilization of Green Energy for PowerGeneration.
• Green energy is and will develop intensively and playing thevital role as an future energy sources in Indonesia
Hal 21
gy
Electricity for a Better Life
Hal 22TerimaTerima kasihkasih