ELECTRICAL SYSTEM IN MIT
SOURCES
UTILISATION
&
EXPENDITURE
![Page 3: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/3.jpg)
INTRODUCTION
BASIC ELECTRICAL POWER SYSTEMS
&
PRODUCTION OF ELECTRICITY IN KARNATAKA
![Page 4: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/4.jpg)
Power System Components Generation subsystem Transmission subsystem Distribution subsystem Protection & control subsystem
Most complex man made system !!
![Page 5: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/5.jpg)
Basic Power System Structure
![Page 6: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/6.jpg)
STATUS OF ENERY SECTORIN KARNATAKA
State has no deposits of coal or petroleum, and therefore has to import it .
The electricity source for Karnataka has a mix of hydel, thermal and wind and accounts for 56% of the commercial need.
![Page 7: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/7.jpg)
In Karnataka, non-commercial energy sources like firewood, agricultural residues, charcoal and cow dung account for 53.2% which demonstrates a high dependency on biomass to meet rural energy needs.
![Page 8: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/8.jpg)
Power Projects in Karnataka
![Page 9: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/9.jpg)
![Page 10: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/10.jpg)
![Page 11: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/11.jpg)
TRANSMISSION OF POWER
The Karnataka Power Transmission Corporation Limited, also known as KPTCL is the sole electricity transmission and distribution company in state of Karnataka.
KPTCL buys power from power generating companies like Karnataka Power Corporation Limited (KPCL) and other IPPs and sell them to their respective ESCOMS
![Page 12: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/12.jpg)
Bangalore Electricity Supply Company.
Mangalore Electricity Supply Company ( Mescom ).
Hubli Electricity Supply Company. Gulbarga Electricity Supply Company. Chamundeshwari Electricity Supply
Company.
ESCOMS UNDER KPTCL
![Page 13: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/13.jpg)
POWER SOURCE OF MIT
![Page 14: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/14.jpg)
Primary source :- MESCOM (State Supply)
Secondary source :- PRIVATE D.G SETS
![Page 15: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/15.jpg)
POWER HOUSES OF MIT
Heart of the electrical system
![Page 16: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/16.jpg)
Basic function of power house is to synchronize and provide a continuous supply of electrical power.
It takes power from state supply, steps it down and then transmits it to the location of load.
In case of power failure it automatically starts the D.G sets which compensates for the failure of power.
![Page 17: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/17.jpg)
Location:- behind cafeteria
Supplies to:- AB-1,AB-2,AB-3,AB-4 WORKSHOP, LIBRARY.
State Supply :- 200A at 11KV
Generator Capacity:- 4 units of 415V, 500KVA
POWER HOUSE 1:-
![Page 18: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/18.jpg)
POWER HOUSE :- 2
Location :- 9th block
Supplies to:-8th,9th,10th,11th,12th hostel block, Annaporna mess, Waste water plant.
State Supply:- 200 A at 11KV
Generator Capacity:-2 units of 320 KVA, 415 V
![Page 19: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/19.jpg)
POWER HOUSE 3:-
Location:- near Venugopala temple
Supplies to:-Staff quarters, swimming pool, temple,K block hostel
State Supply:-200 A at 11KV Generator Capacity:-320KVA, 415V
![Page 20: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/20.jpg)
POWER HOUSE 4:-
Location:- Food court
Supplies to :-5th,6th,7th,13th block hostel, Food court, AC plant
State Supply:-400A at 11KV
Generator Capacity:-2 units of 500KVA, 415 V
![Page 21: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/21.jpg)
POWER HOUSE 5:- Location :- In front of 16th block
Supplies to:- 14th,15th,16th,17th block hostel, AC plant
State Supply:-400 A at 11 KV Generator Capacity:-2 units 500 KVA,
415 V
![Page 22: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/22.jpg)
POWER HOUSE 6:-
Location :- AB 5
Supplies to:-AB 5, AC plant
State Supply:-200 A at 11KV
Generator Capacity:-2 units of 625 KVA, 415 V
![Page 23: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/23.jpg)
Working of power house
![Page 24: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/24.jpg)
Transmission losses account for 5% of the units consumed.
Power Houses are to maintain an optimum value of power factor so as to minimize the losses , failing to which supply of power by state is stopped automatically.
Unit-KWh number of kilowatts consumed in an hour.
![Page 25: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/25.jpg)
![Page 26: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/26.jpg)
Inside a power house
![Page 27: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/27.jpg)
Mescom Supply-stepped down by transformer.
![Page 28: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/28.jpg)
D.G set – from outside
![Page 29: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/29.jpg)
Inside a D.G set- the diesel engine
![Page 30: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/30.jpg)
Instrument panel
![Page 31: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/31.jpg)
Instrument panel
![Page 32: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/32.jpg)
Cooling Tank
![Page 33: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/33.jpg)
Exhaust Pipe
![Page 34: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/34.jpg)
TRANSMISSION
![Page 35: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/35.jpg)
CONSUMPTION
![Page 36: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/36.jpg)
Consumption of power is calculated into three different categories :-
1.Hostel
2.College
3.Quarters
Total units consumed is calculated as the sum total of units taken from state supply, total units generated from D.G sets and units lost during transmission.
![Page 37: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/37.jpg)
MONTHLY MESCOM AND D.G POWER CONSUMPTION LOG SHEET
Sl NO
R.R NO : HT 4 -MIT COLLEGE YEAR : 2008-09
Cost paid for the HT energy recived from MESCOM
D.G Set Running Cost.
Recorded Energy (MESCOM+DG) Units.
5% (on MESCOM
+ D.G Units )
for accounting Line losses
Total Consum
ed Energy Units.
Total Cost (MESCOM+DG) Rs/.
Per Unit in Rs/-
MonthRecorded Demand
(KVA)
HT consumption in Units
Amount Paid to
MESCOM in Rs/-
D.G Units
D.G Set Fuel
consumption in Liters
Fuel-(Diesel& oil
) & maintenan
ce Cost Rs/-
2 3 4 5 6 7 8 9=4+610=9*5
% 11=9-10 12=5+8 13=12/11
1 ,APR-08 1348 387600 208669019548 1840 65173
407148 20357.4 386791 2151863 INR 5.56
2 ,MAY-08 1272 371840 22020871443 410 14522
373283 18664.2 354619 2216609 INR 6.25
3 ,JUNE-08 1122 252200 155513416564 2460 99458
268764 13438.2 255326 1654592 INR 6.48
4 ,JULY-08 1224 259960 159709627154 8116 309869
287114 14355.7 272758 1906965 INR 6.99
5 ,AUG-08 1330 322900 19484179341 2860 109481
332241 16612.1 315629 2057898 INR 6.52
6 ,SEPT-08 1284 333180 61664531537 2185 83642
364717 18235.9 346481 700287 INR 2.02
7 ,OCT-08 1346 338100 203380313175 3865 147952
351275 17563.8 333711 2181755 INR 6.54
8 ,NOV-08 1274 279560 170308348814 14280 515222
328374 16418.7 311955 2218305 INR 7.11
9 ,DEC-08 1166 259060 159222912876 3700 14164
271936 13596.8 258339 1606393 INR 6.22
10 ,JAN-09 1162 272100 16627434112 1380 49790
276212 13810.6 262401 1712533 INR 6.53
11 ,FEB-09 1294 303500 18363297165 2260 76569
310665 15533.3 295132 1912898 INR 6.48
12 ,MARCH-09 1350 306100 163793314405 4280 145006
320505 16025.3 304480 1782939 INR 5.86
![Page 38: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/38.jpg)
YEAR : 2008-09
MonthRecorded Demand
(KVA)
HT consumption in Units
Amount Paid to MESCOM in
Rs/-
D.G Units
D.G Set Fuel consumption
in Liters
Fuel-(Diesel& oil ) &
maintenance Cost Rs/-
2 3 4 5 6 7 8 9=4+6 10=9*5% 11=9-10 12=5+8 13=12/11
1 ,APR-08 848 432000 19204093464 1250 42350
435464 21773.2 413690.8 1962759 INR 4.74
2 ,MAY-08 834 446300 2176745 3164 755 25579 449464 22473.2 426990.8 2202324 INR 5.16
3 ,JUNE-08 520 164380 903876 4628 1770 63862 169008 8450.4 160557.6 967738 INR 6.03
4 ,JULY-08 900 275900 1407389 6281 6470 247672 282181 14109.05 268072 1655061 INR 6.17
5 ,AUG-08 1024 479820 2328087 11748 2725 98318 491568 24578.4 466989.6 2426405 INR 5.20
6 ,SEPT-08 1044 493260 1033727 4928 1415 54166 498188 24909.4 473278.6 1087893 INR 2.30
7 ,OCT-08 1252 532780 2576484 13498 4050 155034 546278 27313.9 518964.1 2731518 INR 5.26
8 ,NOV-08 1246 540680 2611081 58252 17290 661861 598932 29946.6 568985.4 3272942 INR 5.75
9 ,DEC-08 1118 319040 1602166 4166 2445 93350 323206 16160.3 307045.7 1695516 INR 5.52
10 ,JAN-09 1112 439500 2146043 3144 1971 79688 442644 22132.2 420511.8 2225731 INR 5.29
11 ,FEB-09 1226 492700 23908829280 3225 114230
501980 25099 476881 2505112 INR 5.25
12 ,MARCH-09 1260 577780 2553123 12760 4638 164278 590540 29527 561013 2717401 INR 4.84
Per Unit
in Rs/-
MONTHLY MESCOM AND D.G POWER CONSUMPTION LOG SHEET
Sl NO
R.R NO : HT 24-MIT HOSTEL
Cost paid for the HT energy recived from
MESCOMD.G Set Running Cost.
Recorded
Energy
(MESCOM+DG)
Units.
5% (on
MESCOM +
D.G Units )
for
accounting
Line losses
Total
Consume
d Energy
Units.
Total Cost
(MESCOM
+DG) Rs/.
MANIPAL UNIVERCITY .MANIPAL.FORMAT-1
![Page 39: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/39.jpg)
YEAR : 2008-09
MonthRecorded Demand (KVA)
HT consumption
in Units
Amount Paid to MESCOM in
Rs/-D.G Units
D.G Set Fuel consumption
in Liters
Fuel-(Diesel& oil
) & maintenance Cost Rs/-
2 3 4 5 6 7 8 9=4+6 10=9*5% 11=9-10 12=5+8 13=12/11
1 ,APR-08 194 82948 2629321600 370 13105
84548 4227.4 80320.6 276037 INR 3.44
2 ,MAY-08 186 88744 317920 320 105 3719 89064 4453.2 84610.8 321639 INR 3.80
3 ,JUNE-08 130 45016 170994 2080 490 19811 47096 2354.8 44741.2 190805 INR 4.26
4 ,JULY-08 167 52844 197296 7200 1425 54407 60044 3002.2 57041.8 251703 INR 4.41
5 ,AUG-08 183 78840 284642 2240 485 18566 81080 4054 77026 303208 INR 3.94
6 ,SEPT-08 177 80672 200090 3840 780 29858 84512 4225.6 80286.4 229948 INR 2.86
7 ,OCT-08 179 88496 317087 3360 660 25265 91856 4592.8 87263.2 342352 INR 3.92
8 ,NOV-08 196 77552 281155 19520 3515 126821 97072 4853.6 92218.4 407976 INR 4.42
9 ,DEC-08 290 64844 252526 3040 625 23925 67884 3394.2 64489.8 276451 INR 4.29
10 ,JAN-09 174 69648 253757 1280 280 10102 70928 3546.4 67381.6 263859 INR 3.92
11 ,FEB-09 181 74876 271323 2720 540 18295 77596 3879.8 73716.2 289618 INR 3.93
12 ,MARCH-09 192 87456 278730 4480 885 29984 91936 4596.8 87339.2 308714 INR 3.53
MONTHLY MESCOM AND D.G POWER CONSUMPTION LOG SHEET
Sl NO
R.R NO : HT- 92 ,MIT QUARTERS
Cost paid for the HT energy recived from
MESCOMD.G Set Running Cost.
Recorded
Energy
(MESCOM+DG)
Units.
5% (on
MESCOM +
D.G Units )
for
accounting
Line losses
Total
Consumed
Energy
Units.
Total
Cost
(MESCOM
+DG) Rs/.
Per Unit in
Rs/-
MANIPAL UNIVERCITY .MANIPAL.FORMAT-1
![Page 40: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/40.jpg)
CATEGORY
MESCOM UNITS CONSUMED IN A YEAR
D.G UNITS CONSUMED IN A YEAR
HOSTEL 51,94,140 1,35,313
COLLEGE 36,16,800 2,06,134
QUARTERS 8,91,936 51,680
CATEGORY TOTAL
HOSTEL 53,29,453
COLLEGE 38,22,934
QUARTER 9,43,616
![Page 41: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/41.jpg)
CATEGORY TRANSMISSION LOSSES (5% of total units)
(UNITS)
HOSTEL 2,66,472.65
COLLEGE 1,91,146.7
QUARTERS 47,180.8
CATEGORY TOTAL UNITS CONSUMED
HOSTEL 55,95,925.65
COLLEGE 40,14,080.7
QUARTERS 9,90,796.8
TOTAL 1,06,00,803.15
![Page 42: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/42.jpg)
EXPENDITURE
![Page 43: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/43.jpg)
Hostel, college and quarters come under different categories of billing and hence they are billed at different rates , highest being the college.
Overall expenditure includes the electricity bill and cost of running D.G sets and the transmission losses & electricity tax on the electricity bill.
![Page 44: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/44.jpg)
Cost per unit of electrical energy ranges from Rs 3 per unit to Rs 7 per unit.
D.G sets consume 70-85 liters of diesel per hour of running.
![Page 45: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/45.jpg)
CATEGORY AMOUNT PAID TO MESCOM
(Rs)
AMOUNT SPENT ON D.G SETS
(Rs)
CATEGORY COST(Rs)
HOSTEL 2,36,50,012 18,00,388 2,54,50,400
COLLEGE 2,04,72,189 16,30,848 2,21,03,037
QUARTERS 30,88,452 3,73,858 34,62,310
TOTAL 4,72,10,653 38,05,094 5,10,15,747
GRAND TOTAL(Rs)
5,10,15,747
![Page 46: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/46.jpg)
CONCLUSION
![Page 47: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/47.jpg)
![Page 48: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/48.jpg)
![Page 49: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/49.jpg)
![Page 50: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/50.jpg)
![Page 51: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/51.jpg)
Environmental policy of Manipal University
![Page 52: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/52.jpg)
![Page 53: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/53.jpg)
A Step Ahead….. The Manipal University (MU), has embarked on a joint project with the
Advisory Services in Environmental Management to develop the MU campus into an Eco-City.
ASEM is a joint programme of the German Technical Cooperation (GTZ) and the Indian Ministry of Environment and Forests
The identified goals are, alignment to ISO 14001 and trainings on energy conservation, sustainable design and Eco-budgeting
A training centre on Urban Sustainability Management would also be established to provide courses on Urban and Environmental Management.
The project takes a two-winged approach: on the one hand, promoting the establishment of an ISO 14001 certified environmental management system on campus will directly impact the academy’s resource use and environmental performance, while on the other hand, catalysing the setup of a study scheme on environmental management via international university partnerships serves to multiply environmental management capacities beyond the campus itself.
![Page 54: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/54.jpg)
Efforts made by MIT a) Up gradation of air-conditioning system
It includes replacement of old air-conditioning units with power efficient water cooled screw chillers, cooling tower upgrades, unitary air-conditioner controls, implementation of building automation system, with sensors installed in entire building for efficient cooling, automatic switching ON/OFF based on occupancy and fixed time schedule, use of R -138 gas system (environment friendly).
![Page 55: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/55.jpg)
b) Solar Water heaters
Since the coastal belt of Karnataka is blessed with bright and sunny days almost throughout the year excepting the monsoon season, solar energy is in abundance and can be captured to meet our heating needs.
![Page 56: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/56.jpg)
Awards and Recognition
2008-2009 : - Certified as an ISO 14001:2004
Organisation 2004-2005 : - Rajiv Gandhi Parisara
State Award 2002-2004 : - District Award for
Environment- first prize 1999-2000 : - District Award for
Environment- first prize
![Page 57: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/57.jpg)
![Page 58: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/58.jpg)
Let start a new beginning…..
with hope of a new and smarter world….
THANK YOU.
![Page 59: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/59.jpg)
BIBLIOGRAPHY
Maintenance Department MIT Power House in charges KPTCL website :- www.kptcl.com KPCL website:- www.kpcl.com Manipal university website:-
www.manipal.edu Google search engine.
![Page 60: Electrical system in MIT, Manipal University, India](https://reader033.fdocuments.net/reader033/viewer/2022061212/54959330b47959677d8b460f/html5/thumbnails/60.jpg)
TEAM MEMBERS
ABHISHEK ANAND ANIRUDH GATTANI ANIRUDDH KHERA VIVEK JAJODIA