ELECTRICAL SAFETY INSPECTION REPORT PADMA SWEATERS LTD. Darussalam Road, Mirpur, Gazipur, Dhaka, Bangladesh Factory List: 1. Padma Sweaters Ltd. Inspected by: Younten Jamtsho Report Generated by: Younten Jamtsho Inspected on July 9 th 2014

Transcript of ELECTRICAL SAFETY INSPECTION...

Page 1: ELECTRICAL SAFETY INSPECTION REPORTbangladeshaccord.org/...Electrical-Safety-Inspection-Report.pdf · ELECTRICAL SAFETY INSPECTION REPORT. ... Electrical safety training and awareness

ELECTRICAL SAFETY INSPECTION REPORT

PADMA SWEATERS LTD. Darussalam Road, Mirpur, Gazipur, Dhaka, Bangladesh

Factory List:

1. Padma Sweaters Ltd.

Inspected by: Younten Jamtsho

Report Generated by: Younten Jamtsho

Inspected on July 9th 2014

Page 2: ELECTRICAL SAFETY INSPECTION REPORTbangladeshaccord.org/...Electrical-Safety-Inspection-Report.pdf · ELECTRICAL SAFETY INSPECTION REPORT. ... Electrical safety training and awareness

SUMMARY

Padma Sweaters Ltd. factory building was constructed in 1994 and started production in 2004. The six (G+11) storied building was constructed as an industrial structure with total floor area of 5948.4sqm and 39.62 meters tall. The building is fully occupied by Padma Sweaters Ltd. from ground floor to roof. There are no separate sheds other than the main building. There were 918 workers in the factory during the inspection.

The Factory was surveyed for electrical safety by Woosun Energy and Construction Co., Ltd.

(WEC). The purpose of the survey was to identify significant electrical safety issues and to provide

recommendations for remediation based on applicable standards specified by the Accord. The

scope of this initial electrical safety inspection was limited to the review and identification of major

electrical safety issues. The inspection did not include identification of minor deficiencies, which will

be further addressed as part of follow-up inspections.

Table below summarizes the major electrical safety issues identified during the inspection.

Recommendations have been provided to address each issue.

An implementation schedule shall be developed by the factory to remediate each of the

findings. The specific timing of improvements, including any requested extensions due to

design / installation constraints, shall be submitted to the Accord for approval.

Page 2 of 8 Padma Sweaters Ltd.

Page 3: ELECTRICAL SAFETY INSPECTION REPORTbangladeshaccord.org/...Electrical-Safety-Inspection-Report.pdf · ELECTRICAL SAFETY INSPECTION REPORT. ... Electrical safety training and awareness

FINDINGS AND RECOMMENDATIONS

FINDING NO: E- 1

CATEGORY:DESIGN, DRAWINGS & RECORDS FINDING: 1. Thermo graphic scanning of the entire electrical system has not been performed2. Insulation resistance test of electrical equipment is not performed3. Electric safety program is not initiatedRECOMMENDATION: 1. Thermo graphic scanning of the entire electrical system must be performed on tri-annual basis and recorded 2. Insulation resistant test of all the cables must be performed once every 5 yearcycle and recorded 3. Electrical safety training and awareness program for the electrical personal andworkers must be initiated and recorded PRIORITY: P2 REMEDIATION TIMEFRAME: 10 WEEKS

Page 3 of 8 Padma Sweaters Ltd.

Page 4: ELECTRICAL SAFETY INSPECTION REPORTbangladeshaccord.org/...Electrical-Safety-Inspection-Report.pdf · ELECTRICAL SAFETY INSPECTION REPORT. ... Electrical safety training and awareness

FINDING NO: E- 2

Service line drawn from nearby DESCO feeder pole to substation through wall opening and laid close to generator.

CATEGORY:SERVICE LINE FINDING:

HT service line entering into substation room through wall opening and laid close to the generator without protection. Cable getting heated up due to generator and diesel spillage over the HT cable

RECOMMENDATION:

11kV service UG cable must be properly buried in underground trench 450x600 mm width and height respectively. Fill the trench with dry sand to insulate from generator heat and provide noncombustible metallic trench cover. Built the trench a little higher than the floor level so that oil spills don’t enter into the cable trench.

PRIORITY: P1 REMEDIATION TIMEFRAME: 5 WEEKS

FINDING NO: E- 3

Breather of 100kVA power transformer showing deteriorated silica gel and empty oil cup

CATEGORY:TRANSFORMER ROOM FINDING:

Silica gel in the transformer breather deteriorated and transformer oil in the oil cup dried up.

RECOMMENDATION:

Change the transformer breather with fresh silica gel and fill the Breather oil cup with transformer oil up to the required level as instructed by the manufacturer. Establish a routine maintenance & inspection program for transformer as well as all other electrical equipment to ensure any future repetition of the occurrence. PRIORITY: P2

REMEDIATION TIMEFRAME: 5 WEEKS

Page 4 of 8 Padma Sweaters Ltd.

Page 5: ELECTRICAL SAFETY INSPECTION REPORTbangladeshaccord.org/...Electrical-Safety-Inspection-Report.pdf · ELECTRICAL SAFETY INSPECTION REPORT. ... Electrical safety training and awareness

FINDING NO: E- 4

Transformer compartment located in the ground floor of the building.

CATEGORY: TRANSFORMER ROOM FINDING:

Transformer compartment, transformer, switchgears in electrical room and generator room filled with lint and dust.

RECOMMENDATION:

Transformer compartment, transformer, switchgears in electrical room must be dust and lint free. Regular cleaning and maintenance must be incorporated strictly. PRIORITY: P3

REMEDIATION TIMEFRAME: 2 WEEKS

FINDING NO: E- 5

Transformer, generator and main system earthing looped together and exposed. It is located at the transformer compartment in the ground floor beside generator room.

CATEGORY:EARTHING SYSTEM FINDING:

Main earth bus exposed without proper bus bar chamber. RECOMMENDATION:

All earth looping must be made from proper sized bus installed in metallic bus-bar chamber. The bus must be insulated with noncombustible material after branch loop tapping. Bus-bar chamber or the enclosure shall be located not less than 1ft. above the finished floor level. PRIORITY: P1

REMEDIATION TIMEFRAME: 5 WEEKS

Page 5 of 8 Padma Sweaters Ltd.

Page 6: ELECTRICAL SAFETY INSPECTION REPORTbangladeshaccord.org/...Electrical-Safety-Inspection-Report.pdf · ELECTRICAL SAFETY INSPECTION REPORT. ... Electrical safety training and awareness

FINDING NO: E- 6

MCCB circuit breaker for generator room lighting fixed directly on wall (top) and MCB for winding machine control at production floor (bottom )

CATEGORY:DISTRIBUTION PANELS FINDING:

Circuit breakers (MCCB, MCB) and motor control devices fixed on wooden plank flushed to wall without protection enclosure. RECOMMENDATION:

All protective and control devices must be fixed and protected in non-combustible enclosures made of metallic enclosure of minimum 20 SWG thickness and the panel body must be connected to main system earthing.

PRIORITY: P1

REMEDIATION TIMEFRAME: 5 WEEKS

FINDING NO: E-7

Surface conduit for LT cables (top), surface and exposed cable generator room (bottom)

CATEGORY:CABLE & SUPPORTS FINDING:

Surface and exposed wiring in generator room encased in flexible PVC hose without proper support and laid in haphazard arrangements.

RECOMMENDATION:

Permanent wiring encased in flexible PVC conduit must be supported with rigid conduits/cable trays or noncombustible battens attached to vertical walls at orthogonal angles and clamped at regular interval of 600mm. Exposed wirings must be encased in rigid GI or PVC conduits

PRIORITY: P2

REMEDIATION TIMEFRAME: 5 WEEKS

Page 6 of 8 Padma Sweaters Ltd.

Page 7: ELECTRICAL SAFETY INSPECTION REPORTbangladeshaccord.org/...Electrical-Safety-Inspection-Report.pdf · ELECTRICAL SAFETY INSPECTION REPORT. ... Electrical safety training and awareness

FINDING NO: E- 8

Distribution panel in production floor with live and exposed bus bar along with multiple wire termination in single lug. (Typical)

CATEGORY:DISTRIBUTION PANELS FINDING:

Bus bars not insulated and multiple cables/wires terminated in single lug. Panel enclosure earthing and door earth bond not provided. (typical in most of the panels)

RECOMMENDATION:

Live bus-bars in the panel must be adequately insulated with noncombustible insulating material. Multiple wire/cable termination in single lug must be removed and cable//wire must be provided with independent lug and connection point at bus. Panel enclosure and door should be connected to main earthing system and ensure zero potential all the time.

PRIORITY: P1

REMEDIATION TIMEFRAME:10 WEEKS

FINDING NO: E- 9

Generator batteries placed on a wooden stanchion beside generator room

CATEGORY:GENERATOR ROOM FINDING:

Generator battery placed on a wooden stanchion and the terminal poles not covered.

RECOMMENDATION:

Provide an acid proof battery stand for holding the batteries and ensure sufficient space around it for easy maintenance and periodic inspection and the battery terminal poles must be covered with acid proof insulation. PRIORITY: P2

REMEDIATION TIMEFRAME: 3 WEEKS

Page 7 of 8 Padma Sweaters Ltd.

Page 8: ELECTRICAL SAFETY INSPECTION REPORTbangladeshaccord.org/...Electrical-Safety-Inspection-Report.pdf · ELECTRICAL SAFETY INSPECTION REPORT. ... Electrical safety training and awareness

FINDING NO: E- 10

Cable trays filled with lint and dust in production floor 2nd, 3rd and 4th floor.

CATEGORY:CABLE & SUPPORTS FINDING:

The cable ducts are filled with excessive lint and dusts.

RECOMMENDATION:

Cable duct/trays must be neat and clean all the time. Establish a routine cleaning program to keep the channels run over the production floor neat and clean. Provide channel covering with noncombustible metallic sheet. The metallic tray must be connected to main earth at one point to ensure zero potential every time.

PRIORITY: P3

REMEDIATION TIMEFRAME: 5 WEEKS

FINDING NO: E- 11

PFI panel placed temporarily on floor in substation room

CATEGORY:CABLE & SUPPORTS FINDING:

Steam line touching overhead cable duct and the steel cable tray is heated up to 141 degree centigrade.

RECOMMENDATION:

Steam line must be adequately heat insulated and a minimum of 1 ft. air gap between external heat sources and electrical system must be maintained at all times. PRIORITY: P1

REMEDIATION TIMEFRAME: 1 WEEK

Page 8 of 8 Padma Sweaters Ltd.