ELECTRICAL AND I&C CODES AND INSPECTION · Quality Assurance Program Requirements Student Activity...
Transcript of ELECTRICAL AND I&C CODES AND INSPECTION · Quality Assurance Program Requirements Student Activity...
ELECTRICAL AND I&CCODES AND INSPECTION
1Numark Associates, Inc.
Day 1
Day 1
Introductory Sessions:
1. Introduction
2 Q alit Ass rance Program
2Numark Associates, Inc.
2. Quality Assurance Program Requirements
Student Activity
3. 10 CFR Part 50 Technical Requirements
1. Introduction
• Purpose
3Numark Associates, Inc.
• Objectives
• Approach
Purpose
• An adequate understanding of the overall purpose and scope of selected electrical and I&C codes and standards
4Numark Associates, Inc.
standards
• An adequate focus to perform inspections of electrical and I&C structures, systems, and components important to safety
Objectives
• Overview of selected electrical and I&C standards
5Numark Associates, Inc.
• Discuss references to guidance used for acceptable methods of applying standards
• Discuss how standards relate to new reactor inspection
Approach
• Lectures and discussions on selected codes and standards
6Numark Associates, Inc.
• Introduce “Critical Attributes”
• Student Activities
Overview of NRC
7Numark Associates, Inc.
Website References
NRC Website References
• Code of Federal Regulations(10 CFR)
• Generic Communications
8Numark Associates, Inc.
• Generic Communications• Inspection Manual • Regulatory Guides• Technical Libraries• Operating Experience Community
ACMUI Federal Register Notices (NRC) Memoranda of Understanding
ACNW&M Forms News Releases
ACRS For the Record NUREGS (NRC Reports)
ASLBP Generic Communications OMB Exhibit 300s
Commission Generic Issues Personal Identity Verification
Electronic Reading Room Document Collections
9Numark Associates, Inc.
y
Congressional GILS Previous Site Additions
E-Gov Human Factors Information System Regulations (10 CFR)
Enforcement Inspection Manual Regulatory Guides
Enforcement Petition Inspector General Reports Rulemaking Documents
Events, Reports Interim Staff Guidance
Fact Sheets and Brochures Management Directives
Code of Federal Regulations (10 CFR)
• Part 50 - Watts Bar Unit 2
• Part 52 - New reactors
10Numark Associates, Inc.
• Part 50, Appendix A – General Design Criteria
• Part 50, Appendix B – QA Criteria
Generic Communications
• Information Notices
• Generic Letters
11Numark Associates, Inc.
• Generic Letters
• Regulatory Information Summaries
• Part 21 Submittals (see Events/Reports)
Inspection Manual
• Manual Chapter 1252 – Construction Inspector Training
12Numark Associates, Inc.
• Manual Chapter 2503 – Construction Inspection Program
Regulatory Guides
Division 1 – Power Reactors
13Numark Associates, Inc.
• Current and historical regulatory guides
• Draft regulatory guides
Internal NRC Web Page
Access restricted by password
14Numark Associates, Inc.
Technical Library
• IEEE Standards (IEEE Xplore Digital Library)
15Numark Associates, Inc.
• IHS Standards (IEEE, ASME, ANSI, ASTM, ISA, NEMA, etc.)
Operating Experience Community
• Electrical power
16Numark Associates, Inc.
• Emergency diesel generator
• Instrumentation and control
2 Quality Assurance Program
17Numark Associates, Inc.
2. Quality Assurance Program Requirements
2. Quality Assurance ProgramRequirements Objectives
• Identify the major QA program requirements
P id l i f th
18Numark Associates, Inc.
• Provide a general overview of the purpose of these requirements
• Discuss how these requirements relate to new reactor inspection
2. Quality Assurance Program Requirements
• 10 CFR Part 50, Appendix B
19Numark Associates, Inc.
• Other quality assurance documents
10 CFR Part 50, Appendix B
20Numark Associates, Inc.
18 Criteria
10 CFR Part 50, Appendix B, 18 Criteria
I. Organization
II Q lit A P
21Numark Associates, Inc.
II. Quality Assurance Program
III. Design Control
10 CFR Part 50, Appendix B, 18 Criteria
IV. Procurement Document Control
V I t ti P d d
22Numark Associates, Inc.
V. Instructions, Procedures, and Drawings
VI. Document Control
10 CFR Part 50, Appendix B, 18 Criteria
VII. Control of Purchased Material, Equipment, and Services
23Numark Associates, Inc.
VIII. Identification and Control of Materials, Parts, and Components
IX. Control of Special Processes
10 CFR Part 50, Appendix B, 18 Criteria
X. Inspection
XI T t C t l
24Numark Associates, Inc.
XI. Test Control
XII. Control of Measuring and Test Equipment
10 CFR Part 50, Appendix B, 18 Criteria
XIII. Handling, Storage, and Shipping
XIV. Inspection, Test, and Operating St t
25Numark Associates, Inc.
Status
XV. Nonconforming Materials, Parts, or Components
10 CFR Part 50, Appendix B, 18 Criteria
XVI. Corrective Action
26Numark Associates, Inc.
XVII. Quality Assurance Records
XVIII. Audits
Other Quality Assurance Documents
• 10 CFR 50.34(b)(6)(ii)
27Numark Associates, Inc.
• ANSI N45.2
• ASME NQA-1
ANSI N45.2 Program Daughter Documents in Original 1979 NQA-1
• N45.2.6-1978, Qualifications of I&T Personnel
• N45.2.9-1979, Quality Assurance Records
28Numark Associates, Inc.
Records
• N45.2.10-1973, QA Terms and Definitions
• N45.2.11-1974, Quality Assurance for Design
ANSI N45.2 Program Daughter Documents in Original 1979 NQA-1 (cont’d)
• N45.2.12-1977, Auditing of QA Programs
• N45.2.13-1976, Control of Procurement
29Numark Associates, Inc.
Procurement
• N45.2.23-1978, Qualification of QA Program Audit Personnel
ANSI N45.2 Task Daughter Documents in Original 1983 NQA-2
• N45.2.1-1980, Cleaning of Fluid Systems
• N45.2.2-1978, Packaging, Shipping, Receiving, Storage, and Handling
30Numark Associates, Inc.
Receiving, Storage, and Handling
• N45.2.3-1978, Housekeeping During Construction
• N45.2.5-1978, Installation, Inspection, and Testing of Structural Concrete, Steel, Foundations
ANSI N45.2 Task Daughter Documents in Original 1983 NQA-2 (cont’d)
• N45.2.8-1980, Installation, Inspection, and Testing of Mechanical Equipment and Systems
• N45 2 15 1981 Hoisting Rigging
31Numark Associates, Inc.
• N45.2.15-1981, Hoisting, Rigging, and Transporting
• N45.2.20-1979, Subsurface Investigations
ASME NQA-1Combined Document 1994
Part I - Requirements for QA Programs
Part II - Requirements for Tasks
32Numark Associates, Inc.
Part III - Non-Mandatory Guidance
Part IV - NQA position papers and application matrices
Part I - Requirements for QA Programs
The 18 requirements of NQA-1, Part 1 are the same as the 18 requirements of 10 CFR Part 50
33Numark Associates, Inc.
requirements of 10 CFR Part 50, Appendix B.
Part II – Requirements for Tasks
• Subpart 2.4, Quality Assurance Requirements for the Installation, Inspection, and Testing Requirements for Power, Instrumentation, and Control Equipment at Nuclear Facilities – Invokes IEEE Std 336-1985
34Numark Associates, Inc.
• Subpart 2.7 Quality Assurance Requirements for Computer Software for Nuclear Facility Applications– Software Lifecycle - Acquisition, development, operation,
maintenance, and retirement of software– References IEEE Std 7-4.3.2-1993
• Subpart 2.16, Calibration and Control of Test Equipment – Invokes IEEE Std 498-1990
10 CFR Part 50, Appendix B
• Design and Engineering
• Procurement and Manufacturing
• Installation and Testing
35Numark Associates, Inc.
• Startup Acceptance
• Problem Identification and Resolution
• Record Keeping
Student Activity
QA Requirements for
36Numark Associates, Inc.
Different Stages of Construction
QA Requirements for Different Stages of Construction
Construction StagesDesign Manufacture Install/Testing Startup PI&R Records
The 18 Criteria of Appendix B and NQA-1
1 Organization2 Quality Assurance Program3 Design Control4 Procurement Document Control5 Instructions, Procedures, and Drawings6 Document Control7 Control of Purchased Material,
E i t d S i
37Numark Associates, Inc.
Equipment, and Services8 Identification and Control of
Materials, Parts, and Components9 Control of Special Processes10 Inspection11 Test Control12 Control of Measuring and Test Equipment13 Handling, Storage, and Shipping14 Inspection, Test, and Operating Status15 Nonconforming Materials,
Parts, or Components16 Corrective Action17 Quality Assurance Records18 Audits
3. 10 CFR Part 50T h i l R i t
38Numark Associates, Inc.
Technical Requirements
3. 10 CFR Part 50 Technical Requirements Objectives
• Identify the location of the major electrical and I&C technical requirements in 10 CFR Part 50
39Numark Associates, Inc.
• Provide a general overview of the purpose of these technical requirements
• Discuss how these technical requirements relate to new reactor construction and inspection
3. 10 CFR Part 50
Technical Requirements
• Code requirements in 10 CFR
Part 50
40Numark Associates, Inc.
• Appendix A, General Design Criteria
Code Requirements in 10 CFR Part 50
• 50.2, Definitions• 50.36, Technical Specifications• 50.48, Fire Protection• 50 49 Equipment Qualification
41Numark Associates, Inc.
• 50.49, Equipment Qualification• 50.55a, Codes and Standards• 50.63, Station Blackout• 50.65, Maintenance Rule• Appdx. A, General Design Criteria
Appendix A
General Design Criteria
• Quality Products
• Environmental
42Numark Associates, Inc.
• Electrical
• I & C
• Systems Support
Quality Products
• GDC 1 Quality Standards and Records
– Commensurate with the Importance to
43Numark Associates, Inc.
Commensurate with the Importance to Safety
– Safety Related vs Important to Safety
– Generally Recognized Codes and Standards
Environmental
• GDC 2, Natural Phenomenon
44Numark Associates, Inc.
• GDC 3, Fire Protection
• GDC 4, Environmental
Electrical
• GDC 17, Electric Power
45Numark Associates, Inc.
• GDC 18, Inspection & Testing
I & C
• GDC 13, I&C
• GDC 19, Control Room
46Numark Associates, Inc.
,
• GDC 20-24, Protection Systems
• GDC 25-27, Reactivity Control Systems
Systems Support
• GDC 33, Reactor Coolant Makeup
• GDC 34 Residual Heat Removal
47Numark Associates, Inc.
• GDC 34, Residual Heat Removal
• GDC 35, Emergency Core Cooling
• GDC 38, Containment Heat Removal
Systems Support (contd.)
• GDC 41, Containment Atmosphere Cleanup
48Numark Associates, Inc.
• GDC 44, Cooling Systems
• GDC 50, Containment Design
QUESTIONS ?
49Numark Associates, Inc.