Elect Act 2003 (DRUM)

download Elect Act 2003 (DRUM)

of 38

Transcript of Elect Act 2003 (DRUM)

  • 7/31/2019 Elect Act 2003 (DRUM)

    1/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    1

    S BANERJEE

    A hope of light for all

    ELECTRICITY ACT2003

  • 7/31/2019 Elect Act 2003 (DRUM)

    2/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    Presentation OutlinePresentation Outline

    2

    Institutional frame work- Ajourney through

    last century

    Present status and emergingscenario

    Act - 03 - overview Details of provisions What did not covered by Act-03

    Way ahead

  • 7/31/2019 Elect Act 2003 (DRUM)

    3/38

  • 7/31/2019 Elect Act 2003 (DRUM)

    4/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    BackgroundBackground

    4

    The electricity (supply) act, 1948

    State was made primary unit for planning andimplementation

    of power generation, transmission and distribution

    SEBs functioned as vertically integrated utilities.

    Schedule VI of the E(S) Act prescribed the

    methodology to befollowed for the determination of tariff oflicencees.

    Section 59 of the E(S) Act provided the basis of

    tariffdetermination of the SEBs.

  • 7/31/2019 Elect Act 2003 (DRUM)

    5/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    BackgroundBackground

    5

    Main amendments to the existing Acts 1956 Amendment- to increase role of State Govt

    to monitor SEBs. Amendment in 1964 to enable REBs Amendment in 1975 to enable generation in

    Central sector Amendment to bring in commercial viability in

    the functioning of SEBs Section 59 amended to make the earning

    of a minimum return of 3% on fixedassets a statutory requirement (w.e.f1.4.1985)

    Amendment in 1991 to open generation toprivate sector and establishment of RLDCs

    Amendment in 1998 to provide for privatesector participation in transmission, and also

  • 7/31/2019 Elect Act 2003 (DRUM)

    6/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    BackgroundBackground

    6

    1998 Electricity Regulatory Commissions Act:

    Distance the Government from the functioningof the SEBs

    Independent Regulatory Bodies at Central andState level

    Rationalization of Tariff

    Transparency in policy formulation,

    Promotion of efficient and environmentallybenign policies

    Greater involvement of private participation

  • 7/31/2019 Elect Act 2003 (DRUM)

    7/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    BackgroundBackground

    7

    56 Years after independence, many of Indianhouseholds are unable to access electricity

    Rural areas get power for less than 8 hours a day;

    Theft and corruptions are rampant

    Lawlessness characterizes the power sector

    Governance hijacked; redressal is elusive

    Citizens not free to buy except from monopolies

    Sector is a State monopoly!

  • 7/31/2019 Elect Act 2003 (DRUM)

    8/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    Need for the newlegislation

    8

    Requirement of harmonizing and rationalizing theprovisions in the existing laws to

    Create competitive environment for benchmarkcompetition which will result in enhancing quality andreliability of service to consumer.

    Distancing regulatory responsibilities of Govt.

    Reform legislation by several States separately.

    Obviating need for individual States to enact their own

    reform laws.

    Requirement of introducing newer concepts like powertrading, open access, Appellate Tribunal etc.

    Special provision for the Rural areas.

  • 7/31/2019 Elect Act 2003 (DRUM)

    9/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    Finally....

    9

    Electricity Act, 2003:

    Enactment on 10th June, 2003

    Repeals all previous laws.

    Seeks a more competitive market- removal ofrestrictive barriers

    De-licensing of industry

    Consideration of social interests

    Protection of consumer interests

    Creation of policies consistent with theenvironment friendly objective

  • 7/31/2019 Elect Act 2003 (DRUM)

    10/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    Finally....

    10

    Objective : Competition, Protection of Consumers

    interests & Power for all Areas Creates liberal frameworkfor power development. Creates competitive environment. Facilitates private investment. Delicenses generation except for hydro : Captive

    free from controls. Rural Areas : Stand alone Generation and

    Distribution delicenced Multiple licensing in Distribution. Stringent provisions for controlling theft of

    electricity.

    Focus on revenue recovery in cases of unauthorizeduse of electricity.

    Obliges States to restructure Electricity Boards. Mandates creation ofRegulatory Commissions. Retail tariff to be determined by regulatory

    commissions. Open access in Transmission from outset.

    El t i it A t 2003El t i it A t 2003

  • 7/31/2019 Elect Act 2003 (DRUM)

    11/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    Electricity Act 2003Electricity Act 2003

    (Contents)(Contents)

    11

    I : Preliminary - Sections 1-2II : National Electricity Policy & Plan-

    Sections

    3-6III : Generation of Electricity-

    Sections 7-11IV : Licensing- Sections 12-24

    V : Transmission of Electricity-Sections

    25-41VI : Distribution of Electricity-

    Section42-60

    18 parts and 185 sections18 parts and 185 sections

    El t i it A t 2003El t i it A t 2003

  • 7/31/2019 Elect Act 2003 (DRUM)

    12/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    Electricity Act 2003Electricity Act 2003

    (Contents)(Contents)

    12

    VII : Tariff- Sections 61-66VIII: Works- Sections 67-69IX : Central Electricity Authority-

    Sections 70-75X : Regulatory Commissions-

    Sections 76-109XI : Appellate Tribunal-

    Sections 110-125XII: Investigation & Enforcement-

    Sections 126-130

    El t i it A t 2003El t i it A t 2003

  • 7/31/2019 Elect Act 2003 (DRUM)

    13/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    Electricity Act 2003Electricity Act 2003

    (Contents)(Contents)

    13

    XIII : Reorganization of Board-Sections

    131-134

    XIV: Offence and Penalties-Sections 135-152

    XV: Special Courts- Sections 153-157

    XVI: Dispute Resolution-Sections 158

    XVII: Other provisions-Sections

    159-165XVIII: Miscellaneous Sections

  • 7/31/2019 Elect Act 2003 (DRUM)

    14/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    Detailed provisionDetailed provision

    14

    National Electricity Policy and Plan

    Central Govt. to prepare National Electricity Policy and

    Tariff Policy in consultation with State Govt. and Central

    Electricity Authority. (Clause 3(1)).

    National Electricity Plan for a period of 5 years to be

    issued by Authority in accordance with National Electricity

    Policy (Clause 3(4)).

    National Policy on rural electrification including stand

    alone systems to be issued by Central Government in

    consultation with State Government (Clause 4 & 5).

    Role of GovernmentRole of Government

  • 7/31/2019 Elect Act 2003 (DRUM)

    15/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    Detailed provisionDetailed provision

    15

    Central Govt. to formulate a National Policy in

    consultation with the concerned State Govts. for bulk

    purchase of power and management of local distribution

    through Users Association, Cooperatives, Franchisees and

    Panchayat Institutions etc. (Section 5). Govt. to endeavor to extend supply of electricity to all

    villages/hamlets. (Section 6)

    No requirement of licence if a person intends to generate

    and distribute power in rural area. (Section 14) Commission is also required to advise government on the

    matters of policy.? Slide 30

    Role of GovernmentRole of Government

  • 7/31/2019 Elect Act 2003 (DRUM)

    16/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    Detailed provisionDetailed provision

    16

    Generation

    Generation free from licensing. (Section 7)

    Requirement of TEC for non-hydro generation done away with. (Section 7)

    Captive Generation is free from controls. Open access to Captive

    generating plants subject to availability of transmission facility. (Section 9)

    Clearance of CEA for hydro projects required. Necessary due to concern of

    dam safety and inter-State issues. (Section 8)

    Generation from Non-Conventional Sources / Co-generation to bepromoted. Minimum percentage of purchase of power from renewables

    may be prescribed by Regulatory Commissions. (Section 61(h),86 (1) (e))

  • 7/31/2019 Elect Act 2003 (DRUM)

    17/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    Detailed provisionDetailed provision

    17

    There would be Transmission Utility at the Centre and in the States toundertake planning & development of transmission system. (Sections 38 &

    39)

    Load despatch to be in the hands of a govt company/organisation. Flexibility

    regarding keeping Transmission Utility and load despatch together or

    separating them. Load Despatch function critical for grid stability andneutrality vis a vis generators and distributors. Instructions to be binding on

    both. (Sections 26, 27,31, 38, 39) Private transmission companies to be licensed by the Appropriate

    Commission after giving due consideration to the views of the Transmission

    Utility. (Sections 15 (5) (b))

    The Load Despatch Centre/Transmission Utility / Transmission Licensee not

    to trade in power. Facilitating genuine competition between generators.

    (Sections 27, 31, 38, 39,41)

    Transmission

  • 7/31/2019 Elect Act 2003 (DRUM)

    18/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    Detailed provisionDetailed provision

    18

    Requires licensing (Clause 12). Commission can issue two or more licenses for

    distribution of electricity through their own distribution

    system in the same area (Clause(14)).

    Distribution licensee can engage a franchisee toundertake distribution in his area of supply (Clause(14)).

    All supply would need to be metered within 2 years.

    However, State Commission may extend this period for

    completing the task of metering (Clause 55(1)).

    Distribution

  • 7/31/2019 Elect Act 2003 (DRUM)

    19/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    Detailed provisionDetailed provision

    19

    Every distribution licensee shall establish a forum for

    redressal of grievances of the consumers within six months

    as per guidelines of the commission (Clause42(5)).

    Distribution licensee to provide supply within the period asspecified by the commission or else a penalty upto Rs. 1000

    per day to be paid (Clause 43(3)). Disconnection of supply in case of default of payment after

    giving 15 days notice (Clause 56(1)). Provision for suspension/revocation of licence by Regulatory

    Commission as it is an essential service which can not be

    allowed to collapse. (Sections 19, 24)

    Distribution

  • 7/31/2019 Elect Act 2003 (DRUM)

    20/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    Detailed provisionDetailed provision

    20

    Open access to the transmission lines to be provided to

    distribution licensees, generating companies. (Sections 38-40) This would generate competitive pressures and lead to gradual

    cost reduction. Open access in distribution to be allowed by SERC in phases

    and to provide open access to all consumers having requirementof 1 MW or more within 5 year(Sections 42)

    In addition to the wheeling charges provision for surcharge if

    open access is allowed before elimination of cross subsidies, to

    take care of

    Current level of cross subsidy Licensees obligation to supply. (Section 42)

    This would give choice to customer.

  • 7/31/2019 Elect Act 2003 (DRUM)

    21/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    Detailed provisionDetailed provision

    21

    Surcharge & cross subsidy to be progressively eliminated (Clause 42).

    In case of captive generating plant carrying the electricity to the

    destination of his own use, no surcharge shall be leviable (Clause 42).

    Open AccessOpen Access

  • 7/31/2019 Elect Act 2003 (DRUM)

    22/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    Detailed provisionDetailed provision

    22

    Trading/ Market development

    Trading distinct activity permitted with licencing. (Section )11

    Regulatory Commission may fix ceiling on trading margin to

    avoid artificial price volatility.(Sections ( ) (b) & ( ) (b))111 111

    The Regulatory Commission to promote development of market

    including trading. (Section )11

  • 7/31/2019 Elect Act 2003 (DRUM)

    23/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    Detailed provisionDetailed provision

    23

    State Electricity Regulatory Commission to beconstituted within six months. (Section 82)Provision for Joint Commission by more than oneState/UT. (Section 83)Provision for constitution of Appellate Tribunal

    consisting of Chairman and three Members.(Section 110, 112)Appellate Tribunal to hear appeals against theorders of CERC/SERC, and also to exercise generalsupervision and control over the Central/State

    Commissions. (Section 111)Appeal against the orders of Appellate Tribunal tolie before the Supreme Court. (Section 125)Appellate Tribunal considered necessary to-

    Reduce litigation and delay in decisions

    through High Court.Provide technical expertise in decision on

    egulatory Commissions/Appellate Tribunalegulatory Commissions/Appellate Tribunal

  • 7/31/2019 Elect Act 2003 (DRUM)

    24/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    Detailed provisionDetailed provision

    24

    CEA to continue as the main technical Advisor of the

    Govt. of India/ State Government with the responsibility

    of overall planning. (Section 70)

    CEA to specify the technical standards for electricalplants and electrical lines. (Section 73)

    CEA to be technical adviser to CERC as well as SERCs.

    (Section 73)

    CEA to specify the safety standards. (Section 53)

    Central Electricity AuthorityCentral Electricity Authority

  • 7/31/2019 Elect Act 2003 (DRUM)

    25/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    Detailed provisionDetailed provision

    25

    Regulatory Commission to determine tariff for supply of electricityby generating co. on long/medium term contracts. (Section 62)

    No tariff fixation by regulatory commission if tariff is determined

    through competitive bidding or where consumers, on being allowed

    open access enter into agreement with generators/traders.

    Consumer tariff should progressively reduce cross subsidies andmove towards actual cost of supply. (Section 61 (g))

    State Government may provide subsidy in advance through the

    budget for specified target groups if it requires the tariff to be lower

    than that determined by the Regulatory Commission. (Section 65)

    Regulatory Commissions may undertake regulation including

    determination of multi-year tariff principles, which rewards

    efficiency and is based on commercial principles. (Section 61 (e), (f))

    Regulatory Commission to look at the costs of generation,

    transmission and distribution separately. (Section 62 (2))

    Tariff PrinciplesTariff Principles

  • 7/31/2019 Elect Act 2003 (DRUM)

    26/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    Detailed provisionDetailed provision

    26

    Consumer to be given connection within stipulated time.

    (Section 43(1))

    Penalty in the event of failure to give connection (Section

    43(3))

    Payment of interest on security deposit. (Section 47(4))Regulatory commission to specify Electricity supply code

    to be followed by licensees. (Section 50)

    No sum due from consumers recoverable after a period of

    two years unless the same was shown recoverablecontinuously. (Section 56(2))

    Consumer Protection

  • 7/31/2019 Elect Act 2003 (DRUM)

    27/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    Detailed provisionDetailed provision

    27

    Redressal forum for redressal of grievances of consumers, to be

    appointed by every distribution licensee within six months. Ombudsman

    scheme (Section 42 )Standards of performance

    Licensees required to meet standards of performance specified byRegulatory Commission. Failure to meet standards makes them

    liable to pay compensation to affected person within ninety days.Licensee to furnish to the Commission periodical information on

    standards of performance (Section 57)District level committee - (a) to coordinate and review extension of

    electrification in each district; (b) to review quality of power supply and

    consumer satisfaction, etc. (Section 166 (5))

    Consumer Protection

  • 7/31/2019 Elect Act 2003 (DRUM)

    28/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    Detailed provisionDetailed provision

    28

    Restructuring of SEBs

    Provision for transfer scheme to create one or more

    companies from SEB. (Section )111

    Provision for continuance of SEBs (Section )111

    States given flexibility to adopt reform model/path.

  • 7/31/2019 Elect Act 2003 (DRUM)

    29/38

    DEVELOPMENTTHROUGHINTERNATIONAL PARTNERSHIPS

    THANK YOU

    29

    Electricity Act 2003

  • 7/31/2019 Elect Act 2003 (DRUM)

    30/38

    30

    National Electricity Policy

    Objectives:

    Availability of electricity to all households in five yearsAs per 2001 Census, 45% households do not have

    access to households

    Demand to be fully met by 2012.Energy and peaking

    shortages to be overcome and spinning reserve to be

    available.Reliability and quality of power to be of international

    standard by 2012.Raising the per capita consumption to 1000 units by

    2012.Minimum lifeline consumption of 1 unit per household

    per day.

    Protection of consumer's interests

  • 7/31/2019 Elect Act 2003 (DRUM)

    31/38

    31

    Salient features of National Electricity Policy

    CEA to notify first National Electricity Plan in six months

    with a perspective up to year 2017. The Plan prepared byCEA to be used by prospective generating companies and

    transmission licensees as reference document

    Development of Rural Electrification Distribution

    backbone (REDB).

    1At least one 33/11(66/11) kV substation in each blockFrom REDB, one distribution transformer in at least

    each village settlement

    Financial support in terms of capital subsidy & soft longterm debt to States for rural electrification.Special preference to Dalit Bastis, Tribal Areas and

    other weaker sections for rural electrification

  • 7/31/2019 Elect Act 2003 (DRUM)

    32/38

    32

    Salient features of National Electricity Policy

    Creation of adequate generation capacity

    Capacity addition of 1,00,000 MW during the period 2002-2012. Availability

    of installed capacity at 85%, with a spinning reserve of at least 5% by 2012

    for grid security.Full development of hydro potential.

    50,000 MW hydro initiatives already launched to be vigorously pursued.

    Choice of fuel for thermal generation to be based on economics ofgeneration and supply of electricity.Imported coal based thermal power stations, particularly at coastal

    locations, would be encouragedA National Gas Grid would facilitate development of Gas Turbines/

    Combined Cycle Gas Turbine Technologies

    Public-private partnership in Nuclear Plants would be facilitated.All existing Generation capacity should be brought to minimum acceptable

    standards.

    R&M on well defined plan with cost-benefit analysis to be taken up

    The captive generation to be harnessed for meeting shortages particularly for

    load periods.

  • 7/31/2019 Elect Act 2003 (DRUM)

    33/38

    33

    Salient features of National Electricity Policy

    Development of National Grid.Network expansion should be planned and implemented

    keeping in view the anticipated transmission needs thatwould be incident on the system in the open access regime.

    Prior agreement with the beneficiaries would not be a pre-condition for network expansion.

    A national transmission tariff framework, sensitive todistance, direction and related to quantum of flow, needs tobe implemented. As far as possible, consistency needs to bemaintained in transmission pricing framework in inter-Stateand intra-State systems.

    The National Load Despatch Centre (NLDC) would be notifiedwithin three months

    Salient features of National Electricity Policy

  • 7/31/2019 Elect Act 2003 (DRUM)

    34/38

    34

    Salient features of National Electricity Policy

    Crux of the sectors financial viability lies in the efficient managemenof Distribution Sector.

    The Central Government would assist the States, which develop a clearroadmap for proper restructuring, in arranging transition financing from

    various sources.

    Performance based regulation through Multi-Year Tariff (MYT)

    framework is an important structural incentive.

    Private sector participation in distribution to be encouraged for achievingthe requisite reduction in Transmission and Distribution losses and

    improving the quality of service to the consumers.

    State Govts. may restructure distribution zones. a revenue district, a

    Municipal Council as the minimum area for second and subsequent

    license. The second and subsequent licensee for distribution in the

    same area shall have obligation to supply to all consumers. The State Regulatory Commissions to put in place independent third

    party meter testing arrangement.Support for adoption of IT system for ensuring correct billing to

    consumers.

    Speedy implementation of stringent measures againsttheft of electricity

  • 7/31/2019 Elect Act 2003 (DRUM)

    35/38

    35

    Salient features of National Electricity Policy

    Cost of recovery of service from consumers at tariff reflecting

    efficient costs to ensure financial viability of the sector.

    Consumers below poverty line may be provided life-line supply

    subsidy, say 30 units per month. Tariffs for such designated group

    of consumers will be at least 50 % of the average (overall) cost of

    supply.

    The existing cross-subsidies for other categories of consumers

    would need to be reduced progressively and gradually.

    Efficient technologies, like super critical technology, coalgasification etc. would be gradually introduced for generation of

    electricity. .A suitable funding mechanism would be evolved for promoting

    R& D in the Power Sector

    The Government will facilitate establishment of a major Technology

    Center

  • 7/31/2019 Elect Act 2003 (DRUM)

    36/38

    36

    Salient features of National Electricity PolicyPart of new generating capacities may be sold competitively to promotemarket development targeted to reduce prices and benefit consumers.

    Availability based tariff (ABT) to be extended to State level for better griddiscipline through economic signaling. Increasingly higher electricity to be made available for sale through market.

    To meet the objective of "power for all" including household electrification, itis estimated that an investment of the order of Rs.9,000,000 crores would berequired to finance generation, transmission, sub-transmission, distribution

    and rural electrification projects.

    It would be imperative that an appropriate surplus is generated through returnon investments and, at the same time, depreciation reserve created so as tofully meet the debt service obligation.

    Conducive fiscal regime for attracting investment in the power sector. TheState Governments also advised for reviewing tax structure at their level forreducing the cost of electricity.

    Steps would also be taken to address the need for regulatory certainty togenerate investors confidence.

  • 7/31/2019 Elect Act 2003 (DRUM)

    37/38

    37

    Salient features of National Electricity Policy

    Demand side management through energy conservation measures.

    Labels regarding energy efficiency to be displayed on appliances. Efficient agricultural pump sets and efficient lighting technologies to be

    promoted. Appropriate tariff structure for managing the peak load, differential tariff

    structure for peak & off-peak supply.

    Environmental concerns would be suitably addressed by way of

    comprehensive Environmental Impact Assessment and implementation ofEnvironment Action Plan (EAP).

    Setting up of coal washeries will be encouraged.

    Boost to renewable and non-conventional energy sources

    A prescribed percentage of power to be purchased from such sources ofenergy.

    To be made applicable for the tariffs to be determined by the SERCs from 1stApril, 2005.

  • 7/31/2019 Elect Act 2003 (DRUM)

    38/38

    Salient features of National Electricity Policy

    Necessary regulations and appointing Ombudsman forredressal of consumers' grievances to be in place in sixmonths.

    Reliability Index (RI) of supply of power to consumers

    should be indicated by the distribution licensee.

    The Central Government, the State Governments andElectricity Regulatory Commissions should facilitatecapacity building of consumer groups and their effective

    representation before the Regulatory Commissions

    Detailed provision