Transcript of ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.
![Page 1: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/1.jpg)
ELDAS 2nd progress meeting
ELDAS 2nd progress meeting
INM Madrid, 10 & 11 dec 2003
![Page 2: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/2.jpg)
ELDAS 2nd progress meeting
Goal of meeting
• Information on progress• Finetuning of 2004 workplan
– Revised wp’s• BALTEX & GLDAS wp’s• Rhine wp• UK flooding wp• Demonstration for crop prediction (not formal ELDAS)
• Exchange of information– New fellows– Travel plans– Contributions to progress report, TIP, URD
![Page 3: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/3.jpg)
ELDAS 2nd progress meeting
Program 10 dec• 9:00 Coffee and welcome • 9:30 Introduction and agenda BartStatus of forcings• 9:45 Precipitation Paul/Franz• 10:30 Radiation and heating rates Bart• 11:15 Coffee break • 11:30 Database for 2003 Bart• 11.45 MARS storage issues Pedro• 12:30 Remaining Database issues to be resolved all• 13:00 Lunch break Data assimilation progress and overview of past and future
experiments • 14:00 The scm-experiments at ECMWF Pedro/Janneke• 15:00 The CNRM assimilation system Gianpaolo• 16:00 Break • 16:30 Status of the DWD data assimilation Werner/Martin• 17:30 Discussion all• 18:00 Day closure
![Page 4: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/4.jpg)
ELDAS 2nd progress meeting
Program 11 decFurther progress and workplans • 9:00 NWP experiments Ernesto• 10:00 Offline simulations over Europe: workplan and
goals (GLDAS & BALTEX wp's) Bart• 10:30 Progress in the Baltex WP Phil• 11:00 Break• 11:30 Results and future experiments in the
Rhone-workpackage Jean-Christophe• 12:00 Progress on the pointwise validation Cor• 12:45 lunch break• 13:45 Scm-experiments with the microwave radiation
model and SSM/I evaluation Henning• 14:30 The flooding experiments in the UK Eleanor• 15:00 The Rhine WP Bart• 15:10 Discussion• 16:00 breakClosing session• 16:30 Comments by Advisory board members • 17:15 Summary of conclusions Bart• 17:30 (Administrative) input request Bart• 18:00 Closure
![Page 5: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/5.jpg)
ELDAS 2nd progress meeting
Toulouse interim meeting
Forcings:– Precip
• daily files: done• 3hrly: in progress
– Radiation: done– Heating rates:
• 1st release: done• Additional info: in progress
– Atm forcings: in progress• MARS storage: not yet
![Page 6: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/6.jpg)
ELDAS 2nd progress meeting
Toulouse interim meeting• Soil moisture production
– CNRM:• Done by now (?)• No direct use of precipitation & radiation
– DWD:• Started soon (?)• Direct use of precip & radiat planned
– ECMWF• Trial column simulation: in progress• First release: mid 2004
• Slower than expected (!)– Request for contract extension not
approved
![Page 7: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/7.jpg)
ELDAS 2nd progress meeting
2004 activities• Most of validation & demonstration work !• EGU special session on land data assimilation
– Nice, 25-30 April• Closing workshop & meeting
– 2.5 days sessions, 1.5 days discussion, 1 day final ELDAS meeting
– ECMWF, 8-12 nov 2004• Forcings (incl landsaf Tskin)• Assimilation methods• Applications (incl seasonal forecasting)• Validation (including N/GLDAS)• Outlook: biomass (GEOLAND) and new landuse maps
(ECOCLIMAP)• CAHMDA workshop Princeton, 1-5 nov
![Page 8: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/8.jpg)
ELDAS 2nd progress meeting
![Page 9: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/9.jpg)
ELDAS 2nd progress meeting
Radiation and heating rates
• ELDORADO– Database delivered to ECMWF &
Alterra– Paper (Meetschen et al) submitted– KNMI Preprint
![Page 10: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/10.jpg)
ELDAS 2nd progress meeting
Heating rates workplan
• Gisela’s scm-study MUREX:– METEOSAT info consistent with local Tskin
measurements, but too low sampling frequency
![Page 11: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/11.jpg)
ELDAS 2nd progress meeting
Heating rates workplan
• Gisela’s scm-study MUREX:– METEOSAT info consistent with local Tskin
measurements, but too low sampling frequency• 2000 database prepared
– Additional info on obs.error stil to be added• Case study with 2003 in progress
– 3 months (May-July)– METEOSAT and MSG– Simple data assimilation in RACMO– If successful & feasible: ECMWF will use 2000
database
![Page 12: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/12.jpg)
ELDAS 2nd progress meeting
Database for 2003• Originally intended for MSG demonstration• No full data assimilation experiments
foreseen within ELDAS• However: forcings database will enable
future heating rate pilot exps prior to operational implementation: presence in MARS very helpful!
• Anticipated period: 1 May-1 Aug 2003– Precip?– ELDORADO: ok– Heating rates: ok
![Page 13: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/13.jpg)
ELDAS 2nd progress meeting
Selected subregions and domain
![Page 14: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/14.jpg)
ELDAS 2nd progress meeting
Heating rates of low vegetation and data
coverage
![Page 15: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/15.jpg)
ELDAS 2nd progress meeting
Results from RACMO control run
![Page 16: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/16.jpg)
ELDAS 2nd progress meeting
![Page 17: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/17.jpg)
ELDAS 2nd progress meeting
New GLDAS/BALTEX workplans
• GLDAS-wp (4300):– Original: Evaluate ELDAS over US basins– New: over 2000 Europe:
• GLDAS: offline VIC-simulation (well-calibrated hydrologically oriented surface scheme)
• ELDAS1: offline TESSEL-simulation• ELDAS2: assimilated run• Optional: use GLDAS precip dataset (currently not
yet available for 2000)– ELDAS1 – GLDAS: 2 surface schemes driven
as in GLDAS (no data assimilation)– ELDAS2 – ELDAS1: added value of data
assimilation
![Page 18: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/18.jpg)
ELDAS 2nd progress meeting
New GLDAS/BALTEX workplans
• Baltex wp (5400)– Original: use 18-year dataset to compare
to ELDAS climatology (unfeasible)– New: as in previous wp: use both offline
& full simulations to compare to discharge dataset, assessing• Intermodel differences• Added value of data assimilation• Added value of high resolution precip forcing
![Page 19: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/19.jpg)
ELDAS 2nd progress meeting
New GLDAS/BALTEX workplans
• Required:– Offline forcing over Europe (ALMA netCDF
standard)• From MARS-archive• To be compiled by SMHI
– Offline simulation of VIC• To be carried out by SMHI in context of workvisit UW
– Offline simulation of TESSEL• To be carried out by KNMI
– Analyses: as planned• GLDAS-wp: KNMI• BALTEX-wp: SMHI
![Page 20: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/20.jpg)
ELDAS 2nd progress meeting
![Page 21: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/21.jpg)
ELDAS 2nd progress meeting
New Rhine workplan
• Originally: demonstrate ELDAS for Rhine flooding
• New: demonstrate ELDAS for discharge & soil water storage annual cycle
![Page 22: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/22.jpg)
ELDAS 2nd progress meeting
Info on soil hydrological memory from reanalysis
& discharge• P – E = R + dS/dt
– P – E: from ERA40 convergence
– R: from river discharge
– dS/dt: budget closure
Hirschi et al, ETH Zurich, 2003
![Page 23: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/23.jpg)
ELDAS 2nd progress meeting
Time series of soil water
Will ELDAS observations be closer to large scale estimate?
![Page 24: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/24.jpg)
ELDAS 2nd progress meeting
![Page 25: ELDAS 2nd progress meeting INM Madrid, 10 & 11 dec 2003.](https://reader036.fdocuments.net/reader036/viewer/2022062302/5a4d1b217f8b9ab0599958f7/html5/thumbnails/25.jpg)
ELDAS 2nd progress meeting
Additional requests• Cost statements & progress reports• Travels
– AGU jan 2004 (Cor Jacobs)– ?
• Technical Implementation Plan– See http://etip.cordis.lu/ (eldas_tip/tipeldas)
• User Requirements Document– See eldas-website
• All publications & presentations