El Compas Project Monthly Photo Update
January 2018
Crushing
Fine Ore Bins
LaboratoryAdministration
Ball Mill Housing
Flotation Housing
Thickener
WarehouseConcentrate Storage & Filtering
January Project Highlights
GROWTH WITH INTEGRITY2
No lost time accidents
Mine portal infrastructure to main access ramp complete
Old Mine dewatering (rainwater) underway
Plant refurbishment 90% complete
Mine access road 75% complete
Mine access ramp advanced 63m to 233m total
Explosives permit still delayed
Initial production rescheduled for April
El Compas Timeline
GROWTH WITH INTEGRITY3
EL Compas
29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27 3
4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9
22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52
Mine Explosives Magazine Permitting
Mine Access Road
Mine Powerline, Offices, Fencing
Mine development using Pyroblast
Mine development using Explosives
Mine Ore Supply
Plant powerline
Plant procurement
Plant Construction
Plant Commissioning/Operation Sales Commence
Tailings Design
Tailings Construction
March April MayNovember December January February
ACTIVITY
% Complete (beyond plan)Actual (beyond plan)
Mine Safety
GROWTH WITH INTEGRITY4
Safety signage installation in the mine
underway.
Safety procedures and training.
Environmental Program
GROWTH WITH INTEGRITY5
Environmental programs continue with replanting activities, rescue of species and
water monitoring.
Ramp Advance
GROWTH WITH INTEGRITY6
Main ramp advance including loading bays was 63 meters, totaling 233 meters at the
end of the month
Portal Services and the Haulage Road
GROWTH WITH INTEGRITY7
Construction of the ore haulage road
is 75% completeMain mine portal is complete for
services
Mine Service Entry
GROWTH WITH INTEGRITY8
Classic vuggy banded epithermal
quartz vein texture typical of bonanza
orebodies like El Compas
The old mine is being dewatered from a barge
presently and a dewatering borehole will be
completed to dewater the mine further
Crushing Circuit
GROWTH WITH INTEGRITY9
Conveyor #6 complete - awaiting arrival of the mobile crushing units.
Ball Mill
GROWTH WITH INTEGRITY10
Ring gear grease unit and oil warning
system are both completed, no-load tests
finalized. Guards and service entry added.
Cyclones and service platform installed.
Regrind Ball Mill & Flotation Air Supply
GROWTH WITH INTEGRITY11
The regrind mill was mounted on bearings. The blower and compressor were mounted
and electrically connected.
Flotation Cells & MCC
GROWTH WITH INTEGRITY12
Mill MCC complete and fully tested. Flotation
MCC to the right continuing to completion.All three main rougher flotation cells are
complete, calibration in process.
Flotation Cleaner Cells & Underdeck
GROWTH WITH INTEGRITY13
Sump concrete divisions installed. Piping
installation continues.Cleaner flotation cells complete, motor and
cell controls installed.
Concentrate Filtering and Storage Area
GROWTH WITH INTEGRITY14
Concentrate drum filter is ready to be
mounted.Filter and concentrate thickener MCC
connected to mains power.
Tailings & Concentrate Thickeners
GROWTH WITH INTEGRITY15
Tailings thickener ready for water testing.Motor Transmission installation complete on
concentrate thickener tanks, ready for water
testing.
Key Deliverables for February
GROWTH WITH INTEGRITY16
• No lost time injury accidents
• Obtain explosives license and commence use
• Complete wet plant trials
• Complete tailings construction
• Complete mine access road at 95%
• Complete all plant construction except for mobile
crushing circuit.
• Mobile Crushing unit is expected to be on site in March