El Compas Project Monthly Photo Update · El Compas Timeline 3 GROWTH WITH INTEGRITY EL Compas 29 5...

16
El Compas Project Monthly Photo Update January 2018 Crushing Fine Ore Bins Laboratory Administration Ball Mill Housing Flotation Housing Thickener Warehouse Concentrate Storage & Filtering

Transcript of El Compas Project Monthly Photo Update · El Compas Timeline 3 GROWTH WITH INTEGRITY EL Compas 29 5...

Page 1: El Compas Project Monthly Photo Update · El Compas Timeline 3 GROWTH WITH INTEGRITY EL Compas 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27

El Compas Project Monthly Photo Update

January 2018

Crushing

Fine Ore Bins

LaboratoryAdministration

Ball Mill Housing

Flotation Housing

Thickener

WarehouseConcentrate Storage & Filtering

Page 2: El Compas Project Monthly Photo Update · El Compas Timeline 3 GROWTH WITH INTEGRITY EL Compas 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27

January Project Highlights

GROWTH WITH INTEGRITY2

No lost time accidents

Mine portal infrastructure to main access ramp complete

Old Mine dewatering (rainwater) underway

Plant refurbishment 90% complete

Mine access road 75% complete

Mine access ramp advanced 63m to 233m total

Explosives permit still delayed

Initial production rescheduled for April

Page 3: El Compas Project Monthly Photo Update · El Compas Timeline 3 GROWTH WITH INTEGRITY EL Compas 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27

El Compas Timeline

GROWTH WITH INTEGRITY3

EL Compas

29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27 3

4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9

22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52

Mine Explosives Magazine Permitting

Mine Access Road

Mine Powerline, Offices, Fencing

Mine development using Pyroblast

Mine development using Explosives

Mine Ore Supply

Plant powerline

Plant procurement

Plant Construction

Plant Commissioning/Operation Sales Commence

Tailings Design

Tailings Construction

March April MayNovember December January February

ACTIVITY

% Complete (beyond plan)Actual (beyond plan)

Page 4: El Compas Project Monthly Photo Update · El Compas Timeline 3 GROWTH WITH INTEGRITY EL Compas 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27

Mine Safety

GROWTH WITH INTEGRITY4

Safety signage installation in the mine

underway.

Safety procedures and training.

Page 5: El Compas Project Monthly Photo Update · El Compas Timeline 3 GROWTH WITH INTEGRITY EL Compas 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27

Environmental Program

GROWTH WITH INTEGRITY5

Environmental programs continue with replanting activities, rescue of species and

water monitoring.

Page 6: El Compas Project Monthly Photo Update · El Compas Timeline 3 GROWTH WITH INTEGRITY EL Compas 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27

Ramp Advance

GROWTH WITH INTEGRITY6

Main ramp advance including loading bays was 63 meters, totaling 233 meters at the

end of the month

Page 7: El Compas Project Monthly Photo Update · El Compas Timeline 3 GROWTH WITH INTEGRITY EL Compas 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27

Portal Services and the Haulage Road

GROWTH WITH INTEGRITY7

Construction of the ore haulage road

is 75% completeMain mine portal is complete for

services

Page 8: El Compas Project Monthly Photo Update · El Compas Timeline 3 GROWTH WITH INTEGRITY EL Compas 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27

Mine Service Entry

GROWTH WITH INTEGRITY8

Classic vuggy banded epithermal

quartz vein texture typical of bonanza

orebodies like El Compas

The old mine is being dewatered from a barge

presently and a dewatering borehole will be

completed to dewater the mine further

Page 9: El Compas Project Monthly Photo Update · El Compas Timeline 3 GROWTH WITH INTEGRITY EL Compas 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27

Crushing Circuit

GROWTH WITH INTEGRITY9

Conveyor #6 complete - awaiting arrival of the mobile crushing units.

Page 10: El Compas Project Monthly Photo Update · El Compas Timeline 3 GROWTH WITH INTEGRITY EL Compas 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27

Ball Mill

GROWTH WITH INTEGRITY10

Ring gear grease unit and oil warning

system are both completed, no-load tests

finalized. Guards and service entry added.

Cyclones and service platform installed.

Page 11: El Compas Project Monthly Photo Update · El Compas Timeline 3 GROWTH WITH INTEGRITY EL Compas 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27

Regrind Ball Mill & Flotation Air Supply

GROWTH WITH INTEGRITY11

The regrind mill was mounted on bearings. The blower and compressor were mounted

and electrically connected.

Page 12: El Compas Project Monthly Photo Update · El Compas Timeline 3 GROWTH WITH INTEGRITY EL Compas 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27

Flotation Cells & MCC

GROWTH WITH INTEGRITY12

Mill MCC complete and fully tested. Flotation

MCC to the right continuing to completion.All three main rougher flotation cells are

complete, calibration in process.

Page 13: El Compas Project Monthly Photo Update · El Compas Timeline 3 GROWTH WITH INTEGRITY EL Compas 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27

Flotation Cleaner Cells & Underdeck

GROWTH WITH INTEGRITY13

Sump concrete divisions installed. Piping

installation continues.Cleaner flotation cells complete, motor and

cell controls installed.

Page 14: El Compas Project Monthly Photo Update · El Compas Timeline 3 GROWTH WITH INTEGRITY EL Compas 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27

Concentrate Filtering and Storage Area

GROWTH WITH INTEGRITY14

Concentrate drum filter is ready to be

mounted.Filter and concentrate thickener MCC

connected to mains power.

Page 15: El Compas Project Monthly Photo Update · El Compas Timeline 3 GROWTH WITH INTEGRITY EL Compas 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27

Tailings & Concentrate Thickeners

GROWTH WITH INTEGRITY15

Tailings thickener ready for water testing.Motor Transmission installation complete on

concentrate thickener tanks, ready for water

testing.

Page 16: El Compas Project Monthly Photo Update · El Compas Timeline 3 GROWTH WITH INTEGRITY EL Compas 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27

Key Deliverables for February

GROWTH WITH INTEGRITY16

• No lost time injury accidents

• Obtain explosives license and commence use

• Complete wet plant trials

• Complete tailings construction

• Complete mine access road at 95%

• Complete all plant construction except for mobile

crushing circuit.

• Mobile Crushing unit is expected to be on site in March