EIPL VENTURES desh. - Welcome to...
-
Upload
trinhhuong -
Category
Documents
-
view
219 -
download
4
Transcript of EIPL VENTURES desh. - Welcome to...
FORM – 1
(Submitted to SEIAA, Telangana)
By
desh.
EIPL VENTURES
(Expansion of Residential Gated Community) Sy. No. 414 (P), 415(P), 416(P), 417(P), 419(P) & 420(P),
Manchirevula Village,
Gandipet Mandal (earlier Rajendra Nagar Mandal),
Ranga Reddy District,
Telangana
6-3-652 | Flat # 7-3 | Dhruvatara Apartments | Amrutha Estates | Erramanjil | Somajiguda | |Hyderabad- 500082|Phone: + 91-40-23314270 / 71| E mail: [email protected]
|www.pioneerenvirolabs.com | PEOPLE | SAVE ENVIRONMENT |
Prepared by
EIPL VENTURES
Expansion of Residential Gated Community FORM – 1
1
APPENDIX I (See paragraph – 6)
FORM - 1
S. No
(I) Basic Information
1 Name of the project EIPL VENTURES
(Expansion of Residential Gated
Community)
2 S. No. in the schedule 8(a)
3 Proposed capacity / area / length /
tonnage to be handled / command area
/ lease area/number of wells to be
drilled
Additional 20 Villas (G + 2) with Built-up area
of 12,327.98 Sq.m
After expansion Total built-up area will be
40,853.38
4 New / Expansion / Modernization Expansion
5 Existing capacity/Area etc. Residential Gated Community with Built up
area of 28,525.4 Sq. m consisting of 55 villas
(G + 2 floors), LIG & EWS (G + 2 floors) and
Amenities (Basement + G + 1 floor).
6 Category of project i.e. ‘A’ or ‘B’. B
7 Does it attract the general condition? If
yes, please specify.
No
8 Does it attract the specific condition? If
yes, please specify.
No
9 Location
Plot/Survey / Khasra No. 414 (P), 415(P), 416(P), 417(P), 419(P) &
420(P)
Village Manchirevula Village
Tehsil / Mandal Gandipet Mandal
District Ranga Reddy District
State Telangana
10 Nearest railway station/airport along
with distance in kms.
Nearest Railway station: Hitech city – 10.5
Kms.
Nearest Airport – Rajiv Gandhi International
Airport – 17.8 Kms
11 Nearest Town, city, District
Headquarters along with distance in
kms
Hyderabad – adjacent to the site
12 Village Panchayats,Zilla Parishad,
Municipal corporation, Local
body(complete postal addresses with
telephone no.s to be given)
The project site falls under HMDA
13 Name of the applicant EIPL VENTURES
14 Registered Address EIPL OFFICE, Sy. No. 476, ORR Gandipet Circle,
EIPL VENTURES
Expansion of Residential Gated Community FORM – 1
2
S. No
Manchirevula (V), Gandipet (M), Hyderabad - 500089
15. Address for correspondence:
Name P.R. SEKHAR REDDY
Designation(owner/partner/CEO) MANAGING DIRECTOR
Address EIPL OFFICE, Sy. No. 476, ORR Gandipet Circle, Manchirevula (V), Gandipet (M), Hyderabad - 500089
Pin code 500089
E-Mail [email protected]
Telephone No. 9000333419
Fax No. ---
16.
Details of Alternative sites examined, if
any. Location of these sites should be
shown on a topo sheet
No alternate sites are considered
17. Interlinked Projects No
18. Whether separate application of
interlinked project has been submitted?
No
19. If yes, date of submission Not applicable
20. If no, reason Not applicable
21. Whether the proposal involves
approval/clearance under; if yes,
details of the same and their status to
be given.
(a) The Forest
(conservation)Act,1980
(b) The
Wildlife(protection)Act,1972
(c) The C.R.Z Notification,1991?
No
22.
Whether there is any a government
order/policy relevant/relating to the
site?
No
23. Forest land involved(hectares) No
24. Whether there is any litigation pending
against the project and/or land in which
the project is propose to be set up?
(a)Name of the court
(b)Case No.
(c) Orders/directions of the court, if any
and its relevance with the proposed
project.
No
EIPL VENTURES
Expansion of Residential Gated Community FORM – 1
3
(II) ACTIVITY
1. Construction, operation or decommissioning of the Project involving actions,
which will cause physical changes in the locality (topography, land use, changes in
water bodies, etc.)
S.No.
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
1.1 Permanent or temporary change in
land use, land cover or topography
including increase in intensity of
land use (with respect to local
land use plan)
No The proposed 20 additional villas will
be constructed in the area acquired
adjacent to the existing site.
The additional area acquired falls
under Multi-purpose zone as per
Metropolitan Development Master
Plan for Moinabad and Rajendranagar
Mandal (G.O M.S No. 33 MA & UD (11)
dated 24-01-2013. Hence there will not
be any change in land use. The
topography of the site is more or less
flat without many undulations.
Greenbelt / greenery will be developed
with in the premises as per the norms.
Hence there will not be any adverse
impact due to the change in land use
pattern due to the proposed
expansion of Residential gated
community
1.2 Clearance of existing land,
vegetation and buildings?
No No clearance of buildings or
vegetation is envisaged in the
additional area acquired for proposed
expansion.
1.3 Creation of new land uses? No No other land use other than
residential will be created in the
additional area acquired for the
proposed expansion.
1.4 Pre-construction investigations e.g.
bore houses, soil testing?
No Investigations have been carried out
for soil and water at the site.
1.5 Construction works?
No No construction work will be taken-up
pertaining to expansion without
obtaining the Prior Environmental
clearance from SEIAA and Consent
For Establishment from SPCB.
1.6 Demolition works?
No Not applicable as no demolition works
are envisaged for the proposed
expansion
1.7 Temporary sites used for Yes Construction workers will be from
EIPL VENTURES
Expansion of Residential Gated Community FORM – 1
4
S.No.
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
construction works or housing of
construction workers?
local area only. Temporary housing is
proposed for construction workers.
1.8 Above ground buildings, structures
or earthworks including linear
structures, cut and fill or
excavations
Yes Most of the structures will be above
the ground. However excavations will
be involved for foundations. Excess
cut will be used for Flooring & internal
road laying
1.9 Underground works including mining
or tunneling?
No No mining and tunneling will be
involved in the proposed expansion
activity.
1.10 Reclamation works?
No No reclamation works are envisaged
in proposed expansion project.
1.11 Dredging?
No No dredging activity will be involved.
1.12 Offshore structures? No No offshore structures are envisaged
in the proposed expansion project.
1.13 Production and manufacturing
processes?
No Not applicable as proposed expansion
project involves construction of
Residential gated community.
1.14 Facilities for storage of goods or
materials?
Yes Raw materials will be stored as per
norms. The raw materials like Cement,
Sand, Bricks, Steel, Wood, Paint &
aggregates will be stored at site only.
Cement & Paint will be stored at
indoors & remaining will be at
outdoors.
1.15 Facilities for treatment or disposal of
solid waste or liquid effluents?
Yes Wastewater generated during the
operation of the Residential gated
community will be treated in sewage
treatment plant. Treated wastewater
will be utilized for non-potable
purposes like Toilet flushing &
Greenbelt development.
Treatment and disposal of wastewater
& solid waste will be in accordance
with the CPCB/SPCB norms.
1.16 Facilities for long term housing of
operational workers?
No No permanent housing will be
provided for the construction
workers.
1.17 New road, rail or sea traffic during
construction or operation?
Yes There will be a slight increase in
traffic volume during construction
and operation of the proposed
Residential gated community.
EIPL VENTURES
Expansion of Residential Gated Community FORM – 1
5
S.No.
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
The proposed Residential gated
community site is well connected by
Narsing – Appa service road
Hence there will not be any adverse
impact on road traffic / rail traffic / sea
traffic due to the proposed Residential
gated community.
1.18 New road, rail, air waterborne or
other transport infrastructure
including new or altered routes and
stations, ports, airports etc?
No No new road / rail / air transport
infrastructure is proposed.
1.19 Closure or diversion of existing
transport routes or infrastructure
leading to changes in traffic
movements?
No No closure or diversion of existing
transport routes is envisaged.
1.20 New or diverted transmission lines
or pipelines?
No Water required for the proposed
expansion of Residential gated
community will be sourced from
ground water
1.21 Impoundment, damming, culverting,
realignment or other changes to the
hydrology of watercourses or
aquifers?
No No culverting, realignment are
envisaged. There will not be any
changes to the hydrology of
watercourses or aquifers.
1.22 Stream crossings? No No stream crossing is involved
1.23 Abstraction or transfers of water
form ground or surface waters?
Yes Water required for the proposed
expansion project will be sourced
from ground water
1.24 Changes in water bodies or the land
surface affecting drainage or run-
off?
No No changes in water bodies, drainage
and land surface are anticipated as
the site is more or less flat without
many undulations. Separate storm
water drains will be provided.
1.25 Transport of personnel or materials
for construction, operation or
decommissioning?
Yes There will be a slight increase in
traffic volume during construction
and operation of the proposed
Residential gated community.
The proposed Residential gated
community site is well connected by
Narsingi - Appa service road. The
existing road can handle this
additional increase in vehicular traffic.
Hence there will not be any adverse
impact on road traffic / rail traffic / sea
EIPL VENTURES
Expansion of Residential Gated Community FORM – 1
6
S.No.
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
traffic due to the proposed Residential
gated community.
1.26 Long-term dismantling or
decommissioning or restoration
works?
No No such works are envisaged
1.27 Ongoing activity during
decommissioning which could have
an impact on the environment?
No No such works are envisaged
1.28 Influx of people to the area either
temporarily or permanently?
No Temporary labour required for the
construction activity will be met from
the local places.
1.29 Introduction of alien species? No No such activity is envisaged
1.30 Loss of native species or genetic
diversity?
No As a part of greenbelt/greenery
development plan native species that
are suitable to that soil condition will
be developed.
1.31 Any other actions? No Nil
EIPL VENTURES
Expansion of Residential Gated Community FORM – 1
7
2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply)
S.No.
Information/checklist confirmation
Yes/No
Details thereof (with approximate quantities /rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha)
Yes The proposed 20 additional villas will
be constructed in the area acquired
adjacent to the existing site.
Additional acquired for the proposed
expansion project falls under Multi-
purpose zone as per Metropolitan
Development Master Plan for
Moinabad and Rajendranagar
Mandal (G.O M.S No. 33 MA & UD
(11) dated 24-01-2013). Hence there
will not be any change in land use.
The topography of the site is more or
less flat without many undulations.
Total land acquired for the proposed
expansion of Residential gated
community is 6.3 Acres. Total land
after proposed expansion project
will be 14.33 acres.
2.2
Water (expected source &
competing users) unit: KLD
Yes Water required for the proposed
project will be sourced through
Ground water resources during
operation & construction of the
Project. Total water demand is about
1 KLD during Construction of
additional 20 villas & 78 KLD during
operation of the gated community
after expansion. Net water
requirement after recycling of
treated waste water will be 42 KLD
2.3 Minerals (MT) Yes Sand - 25000 Cum
2.4 Construction material – stone,
aggregates, sand / soil (expected
source – MT)
Yes All construction materials such as
Ready mix Concrete, Cement, Sand,
Aggregate, Aerated Auto clave,
Concrete Brick (nos.),
Reinforcement Steel, Wood material,
Painting material, Flooring Material,
Sanitary Material, Electrical Material,
Plumbing material are available
locally.
EIPL VENTURES
Expansion of Residential Gated Community FORM – 1
8
S.No.
Information/checklist confirmation
Yes/No
Details thereof (with approximate quantities /rates, wherever possible) with source of information data
2.5 Forests and timber (source – MT) No Wood material required for Windows
& Doors of Imported Quality will be
procured locally.
2.6 Energy including electricity and fuels
(source, competing users) Unit: fuel
(MT), energy (MW)
Yes The total energy requirement for the
proposed expansion project will be
200 KvA (Maximum peak demand). It
will be taken from TSSPDCL.
DG set will be provided for
emergency Backup Power Supply.
2.7 Any other natural resources (use
appropriate standard units)
No Not applicable
EIPL VENTURES
Expansion of Residential Gated Community FORM – 1
9
3. Use, storage, transport, handling or production of substances or materials, which
could be harmful to human health or the environment or raise concerns about
actual or perceived risks to human health
S.No.
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
3.1 Use of substances or materials,
which are hazardous (as per
MSIHC rules) to human health or
the environment (flora, fauna, and
water supplies)
Yes The hazardous wastes like empty
containers of paints, petroleum
products, thinners, adhesives will be
given to authorized recyclers. All the
hazardous materials will be stored
as per HWM rules.
3.2 Changes in occurrence of disease
or affect disease vectors (e.g.
insect or water borne diseases)
No Not Applicable
3.3 Affect the welfare of people e.g. by
changing living conditions?
No Not Applicable as the proposed
expansion of Residential gated
community will create direct /
indirect employment opportunities
in the area and thereby contributing
in the improvement of socio-
economic status of people in the
area. Land prices will increase
substantially.
3.4 Vulnerable groups of people who
could be affected by the project e.g.
hospital patients, children, the
elderly etc.,
No Approach roads to the gated
community is already paved
Speed of the vehicle will be
reduced
Greenbelt will be developed
By following the above the dust
generation will be minimized.
The Solid waste in the form of
garbage will be segregated at each
section distinguishing Recyclable &
Non- recyclable garbage and will be
taken away by Municipal
Corporation.
Wastewater generated from the
gated community will be treated in
sewage treatment plant and treated
waste water will be utilized for non-
potable purposes like flushing and
Green belt development plan
Hence there will not be any adverse
impact on vulnerable groups.
3.5 Any other causes No Not Applicable
EIPL VENTURES
Expansion of Residential Gated Community FORM – 1
10
4. Production of solid wastes during construction or operation or decommissioning
(MT/month)
S.No.
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
4.1 Spoil, overburden or mine wastes Yes The dug soil during excavation will
be used for filling of low lying areas.
4.2 Municipal waste (domestic and or
Residential wastes)
Yes Municipal solid waste generated
during construction phase of the
project will be given to the Municipal
Corporation.
The Solid waste generated during
operation phase will be mainly in the
form of garbage, paper waste,
plastic waste and e-waste from the
individual homes.
The garbage will be segregated at
each section distinguishing
Recyclable & Non- recyclable
garbage and will be taken away by
Municipal Corporation.
4.3 Hazardous wastes (as per
Hazardous Waste
Management Rules)
Yes Used batteries & Waste oil will be
given to SPCB approved vendors
4.4 Other industrial process wastes No Not Applicable as there will not be
any industrial operations in the
Gated community
4.5 Surplus product Yes Surplus raw materials after
construction will be given to the
suppliers.
4.6 Sewage sludge or other sludge
from effluent treatment
Yes Sewage sludge generated will be
stored in HDPE bags and will be
used as manure.
4.7 Construction or demolition wastes Yes At the time of construction of the
proposed expansion project, there
will be some recyclable material like
Steel, metal, Plastic material, Wood
etc., will be sent to reuse / recycle
and other wastes like Bricks,
cement waste will be used for
leveling. The disturbed slopes shall
be well stabilized before the onset of
the monsoon.
EIPL VENTURES
Expansion of Residential Gated Community FORM – 1
11
S.No.
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
The site for proposed expansion of
project is sparsely vegetated
without any buildings, hence there
will not be any demolition waste
from the proposed expansion of
Residential gated community
project
4.8 Redundant machinery or equipment No No redundant machinery will be kept
in the premises after construction of
the Residential gated community
4.9 Contaminated soils or other
materials
No During the construction phase of
the expansion Project, all
precautionary measures will be
taken to prevent the spillage of oil,
paints on to the ground to prevent
the contamination of soil.
4.10 Agricultural wastes No Not applicable
4.11 Other solid wastes Yes E-waste generated will be given
Authorized recyclers approved by
SPCB.
EIPL VENTURES
Expansion of Residential Gated Community FORM – 1
12
5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)
S.No.
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
5.1 Emissions from combustion of
fossil fuels from stationary or
mobile sources
Yes During the operation phase of the
Residential gated community,
emissions will be mainly PM, NMHC,
NOx & CO due to vehicular traffic
and from D.G. sets provided for
Backup power supply.
All the internal roads will be
paved. Hence the dust emissions
due to the vehicles will be very
low
Good greenbelt will be
developed in the gated
community premises which will
further help in mitigating the
emission levels.
Stack of adequate height will be
provided to the DG set for
effective dispersion of gases into
the atmosphere.
Hence there will not be any much
impact on surrounding environment
due to the proposed Residential
gated community.
5.2 Emissions from production
processes
No Not applicable.
5.3 Emissions from materials handling
including storage or transport
No Not applicable as there will not be
any storage or transportation of raw
materials
5.4 Emissions from construction
activities including plant and
equipment
Yes During construction phase, there
will be dust emissions during raw
material handling and transportation
of raw materials. To mitigate the
dust emissions
Raw materials will be brought to
the site through covered trucks /
EIPL VENTURES
Expansion of Residential Gated Community FORM – 1
13
S.No.
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
Trolleys.
Minimum water spraying will be
done to mitigate the dust
emanation
All the materials will be properly
covered to prevent the dust
emissions during high winds
Hence there will not be any
significant dust emissions due to
raw material storage &
transportation during construction
phase of the project.
5.5 Dust or odours from handling of
materials including construction
materials, sewage and waste
Yes Adequate precautionary measures
will be taken up to control the Odour
from the Construction materials like
Paint material & Sewage.
5.6 Emissions from incineration of
waste
No Not applicable
5.7 Emissions from burning of waste in
open air (e.g. slash materials,
construction debris)
No All such wastes will be disposed
along with Municipal Solid Waste.
5.8 Emissions from any other sources No Nil
EIPL VENTURES
Expansion of Residential Gated Community FORM – 1
14
6.0 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No.
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data with
source of information data
6.1 From operation of equipment e.g.
engines, ventilation plant,
crushers
Yes Main source of Noise generation will
be DG sets and Motor pumps for
supply of water.
The D.G. Sets & Motor pumps
manufactured in accordance with the
noise level standards stipulated by
MOEF vide notification dated 14-02-
2000, only will be used in the Gated
community.
Hence there will not be much increase
in Noise levels in the surrounding
areas.
6.2 From industrial or similar
processes
Yes The sources of noise generation in the
proposed expansion project will be
DG set. DG sets manufactured as per
OSHA / MOEF guidelines will be
procured. Ambient noise levels will be
in accordance with MOEF notification
dated 14-02-2000 i.e. noise levels will
be <55 dBA during daytime and < 45
dBA during night time.
6.3 From construction or demolition Yes Construction equipment will cause
some noise. Ear plugs will be
provided to construction workers who
work near the noise generating
equipment.
6.4 From blasting or piling No No such operations are involved.
6.5 From construction or operational
traffic
Yes There will be slight increase in traffic
noise during construction and
operation of the proposed Residential
gated community.
Speed of the vehicles will be
reduced
Greenbelt will be developed
By following above control measures
noise levels will be minimized.
6.6 From lighting or cooling systems No Not applicable
6.7 From any other sources No Not applicable
EIPL VENTURES
Expansion of Residential Gated Community FORM – 1
15
7. Risks of contamination of land or water from releases of pollutants into the
ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No.
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
7.1 From handling, storage, use or
spillage of hazardous materials
Yes Good housekeeping practices will
be followed to prevent any spillage
of hazardous materials.
7.2 From discharge of sewage or other
effluents to water or the land
(expected mode and place of
discharge)
No Wastewater generated during the
operation of the Residential gated
community will be treated in
sewage treatment plant and treated
wastewater will be utilized for non-
potable purposes like Toilet
flushing & Gardening
7.3 By deposition of pollutants emitted
to air into the land or into water
No During construction phase, there
will be dust emissions during raw
material handling and
transportation of raw materials. To
mitigate the dust emissions
Raw materials will be brought to
the site through covered trucks /
Trolleys.
Minimum water spraying will be
done to mitigate the dust
emanation
All the materials will be properly
covered to prevent the dust
emissions during high winds
Dust curtains will be provided
around the project site
Hence there will not be any
significant dust emissions due to
raw material storage &
transportation during construction
phase of the project.
During the operation phase of the
Residential gated community,
emissions will be mainly PM, CO
and NOx due to vehicular traffic
and from D.G. sets provided for
Backup power supply.
EIPL VENTURES
Expansion of Residential Gated Community FORM – 1
16
All internal roads will be paved.
Hence the dust emissions due
to the vehicles will be very low
Good greenbelt will be
developed in the gated
community premises which will
further help in mitigating the
emission levels.
Stack of adequate height will be
provided to the DG set for
effective dispersion of gases
into the atmosphere.
Hence there will not be any much
impact on surrounding
environment due to the proposed
Residential gated community.
7.4 From any other sources No Not applicable
7.5 Is there a risk of long term build up
of pollutants in the environment
from these sources?
No Not applicable
EIPL VENTURES
Expansion of Residential Gated Community FORM – 1
17
8. Risk of accidents during construction or operation of the Project, which could
affect human health or the environment
S.No.
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
8.1 From explosions, spillages, fires etc
from storage, handling, use or
production of hazardous
substances
Yes Good housekeeping practices will
be followed during Construction
and Operation phase of the
Residential gated community.
All precautionary measures will be
taken to prevent the spillage of oil,
paint etc.
D.G sets will be operated only
during power failure. Hence
storage of Diesel will be very low.
Hence the occurrence of explosion
due to the storage of Diesel will be
low.
All the rules and regulations as per
the Fire & Safety Department,
Andhra Pradesh will be followed
strictly to prevent the Fire
accidents in the gated community
8.2 From any other causes Yes Earthquakes & Natural disasters
8.3 Could the project be affected by
natural disasters causing
environmental damage (e.g.
floods, earthquakes, landslides,
cloudburst etc)?
No Not applicable
EIPL VENTURES
Expansion of Residential Gated Community FORM – 1
18
9. Factors which should be considered (such as consequential development) which
could lead to environmental effects or the potential for cumulative impacts with
other existing or planned activities in the locality
S. No.
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
9.1 Lead to development of supporting
utilities, ancillary development or
development stimulated by the
project which could have impact
on the environment e.g.:
• Supporting infrastructure
(roads, power supply, waste or
waste water treatment, etc.)
• housing development
• extractive industries
• supply industries
• other
No
No such activities are envisaged
9.2 Lead to after-use of the site, which
could have an impact on the
environment
No Not applicable
9.3 Set a precedent for later
developments
Yes With the improvement in the socio-
economic status of the people in
the area, later developments are
expected.
9.4 Have cumulative effects due to
proximity to other existing or
planned projects with similar
effects
No Not applicable
EIPL VENTURES
Expansion of Residential Gated Community FORM – 1
19
(III) Environmental Sensitivity
S.No.
Areas
Name/
Identity
Aerial distance
(within 15 km.)
proposed project
location boundary
1 Areas protected under international
conventions, national or local legislation
for their ecological, landscape, cultural
or other related value
Birla Mandir
Quli Qutub Shah
Tombs
13.4 Kms
5.7 Kms
2 Areas which are important or sensitive for
ecological reasons - Wetlands,
watercourses or other water bodies,
coastal zone, biospheres, mountains,
forests
KVR Botanical
garden
7.9 Kms
KBR National
park
8.5 Kms
Mrugavani
National park
2.0 Kms
Musi river 0.3 Kms
Osman sagar 3.0 Kms
Himayat sagar 4.2 Kms
Hussain sagar 13.4 Kms
Kokapet lake 2.9 Kms
Manikonda
cheruvu
4.6 Kms
Khajaguda lake 4 Kms
& many other
ponds
Within 15 Km radius
3 Areas used by protected, important or
sensitive species of flora or fauna for
breeding, nesting, foraging, resting, over
wintering, migration
Nehru Zoological
park
10.9
4 Inland, coastal, marine or underground
waters
Underground
water
Available at the site
5 State, National boundaries
---- No inter-state
boundary, No
international
boundary.
6 Routes or facilities used by the public for
access to recreation or other tourist,
pilgrim areas
No Not applicable
7 Defense installations Yes 5.5
8 Densely populated or built-up area Yes Project is proposed
comes under
Hyderabad
EIPL VENTURES
Expansion of Residential Gated Community FORM – 1
20
S.No.
Areas
Name/
Identity
Aerial distance
(within 15 km.)
proposed project
location boundary
jurisdiction
9 Areas occupied by sensitive man-made
land uses (hospitals, schools, places of
worship, community facilities
Many schools &
Hospitals exits
Within 15 Km radius
10 Areas containing important, high quality or
scarce resources
(ground water resources, surface
resources, forestry, agriculture, fisheries,
tourism, minerals)
Osman sagar 3.0 Kms
Himayat sagar 4.2 Kms
& many other
water bodies
Within 15 Km radius
11 Areas already subjected to pollution or
environmental damage. (those where
existing legal environmental standards
are exceeded)
--- Not applicable
12 Areas susceptible to natural hazard which
could cause the project to present
environmental problems
(earthquakes, subsidence, landslides,
erosion, flooding or extreme or adverse
climatic conditions)
--- Based on the
historical data, the
site is not likely to
prone to
earthquakes, floods,
etc.
EIPL VENTURES
Expansion of Residential Gated Community FORM – 1
21
(IV). PROPOSED TERMS OF REFERENCE FOR EIA STUDIES
As the proposed project is a construction project with built up area is below 1,50,000 Sq.m., no
terms of reference for EIA studies is proposed. However we are here with enclosing Conceptual
Management Plan for your kind reference. The Conceptual Management Plan consists the
following
Air emission management
Effluent treatment & disposal
Solid waste generation, storage & disposal
Greenbelt development plan
Rain water harvesting
“I hereby given undertaking that the data and information given in the application and enclosures
are true to the best of my knowledge and belief and I am aware that if any part of the data and
information submitted is found to be false or misleading at any stage, the project may be rejected
and clearance given, if any to the project will be revoked at our risk and cost.
Date: 13-10-2017
Place: Hyderabad