EIA Consultant- Consultant...¢  Premises Snehlataganj, Indore (M.P.) 3. SCOPE OF WORK (i)...

download EIA Consultant- Consultant...¢  Premises Snehlataganj, Indore (M.P.) 3. SCOPE OF WORK (i) Carryout site

of 24

  • date post

    26-Jul-2020
  • Category

    Documents

  • view

    2
  • download

    0

Embed Size (px)

Transcript of EIA Consultant- Consultant...¢  Premises Snehlataganj, Indore (M.P.) 3. SCOPE OF WORK (i)...

  • 1

    RFP 1. INTRODUCTION

    1.1 M.P. Housing & Infrastructure Development Board

    The M.P. Housing & Infrastructure Development Board was

    established as a body corporate under the Madhya Pradesh Griha

    Nirman Mandal Adhiniyam, 1972 which replaced the earlier similar

    Act of 1950. Madhya Pradesh Housing & Infrastructure Development

    Board is one of the very few, perhaps the only, Housing Board in the

    country, not the receive a single rupee as subsidy from the

    Government. All the projects and programmers, including its internal

    cross subsidies, are arranged for by the economics of the project

    itself, in consonance with what the market

    can bear.

    1.2 PROJECT VISION AND ABJECTIVES

    M.P. Housing & Infrastructure Development Board intends to appoint

    EIA Consultant for obtaining Environment Clearance for Madhya

    Pradesh Housing & Infrastructure Development Board’s Housing

    Projects and to prepare report for E.C.

    Following are key objectives of project:

    (i) Filling and submission of form 1 and form 1 A along with necessary

    document (Annexure I) (Page 1 to 16)

    (ii) Carrying out EC as per SEIAA/SEAC Ministry of Environment &

    Forest (MoEF) guidelines.

    (iii) Providing technical assistance and day to day follow up with

    concerning agency to obtaining Environment Clearance from

    SEIAA/SEac (MoEF) and making all presentation required time to

    time in this connection by the authority .

    (iv) Obtaining EC from SEIAA/SEAC/EAC (MoEF) for

    Project.

  • 2

    2. PROJECT Madhya Pradesh Housing & Infrastructure Development Board

    proposed to Construct

    Name of Project:- Development of 3.15 Acre land & construction of

    commercial & Residential complex commercial Block (G+6)

    Residential Block 2 Nos G+12 – 212 Flats at Hope Textile Mill

    Premises Snehlataganj, Indore (M.P.)

    3. SCOPE OF WORK

    (i) Carryout site survey for assessing site condition and collecting

    secondary data for EC.

    (ii) Filling and submission of form 1 & 1 A along with inception report.

    (iii) Conducting primary baseline monitoring and analysis as per

    SEIAA (MoEF).

    (iv) Carrying out impact assessment for environment component as

    per SEIAA (MoFE).

    (v) Developing environment management plan to mitigate the likely

    impact from the propose project.

    (vi) Providing technical assistant in various approvals & presentation

    to regulatory authorities such as

    SEIAA/SEAC (MoEF).

    (vii) Obtaining EC from SEIAA/SEAC/EAC (MoEF) for project.

    4. GENERAL:

    (i) A certificate from the consultant shall be submitted that they have

    been accredited by MoEF (list ‘A’) for Building and construction

    projects.

    (ii) Documents required by SEIAA/SEAC for prior Environment

    clearance shall be detailed as per (Annex-1) the EIA notification

    dated 14th Sep. 2006 issued by MoEF, Delhi.

    (iii) Data for EC should be given for the entire life of the project

    (iv) Detailed feasibility report including the financial, Environmental

    and social costs has to be furnished.

  • 3

    5. GENERAL INFORMATION

    Building construction projects as per the EIA notification of 2006 are

    under category ‘B’ covering an area>20,000 sqmtr. And

  • 4

    and connectivity, demographic aspects, socio, cultural and economic

    aspects, villages, settlements should be given in the map. Details of

    environmentally sensitivity place, land acquisition, rehabilitation of

    communities / villages, and present status of such activities are to be

    mentioned.

    Site Selection and Planning

    The environment impacts of construction and operation are

    established during the early phases of site selection and planning.

    Some important factors for development, which should be addressed

    are:

    � Status of ownership of land

    � The boundaries of the project area

    � A map that identifies the locations of all proposed development

    activities; and

    � Proximity to local communities.

    � Proximity to sensitive surface or ground water bodies

    � Compatibility with local building regulations

    � Existing drainage pattern

    5.3 Description of the Environment

    Environment data to be considered in relation to building Construction

    would be:

    (a) Land (b) ground water, surface water (c) air (d) biological

    Environment (e) noise (f) socio economic environment (g) sewage (h)

    transportation.

    Study area:

    Map of the study area clearly delineating the location of various

    monitoring stations (air/water, soil and noise) superimposed with

    location of habitats are to be shown. Monitoring should be done as

    per CPCB/MoEF guidelines. Primary data should be collected for one

    season except rainy season. Monitoring of the parameters should be

    carried out within the study area.

  • 5

    5.4 Land Environment The first feature which should influence the development of a new project is the existing land use pattern of the neighborhood of the project, whether the proposed development conforms to the development for the area or not. Geographical latitude and microclimatic factor such as solar access and wing loads have a major impact. The following parameters have to be addressed under the baseline data for land environment. a. Soil � type of characteristics � Porosity and permeability 5.5 Air Environment Climatologically data is to obtained from nearest India Metrological Department (IMD) station for one season. Micro metrological data consisting of wind speed, wind direction, temperature, humidity, rainfall (peak and average daily rainfall) and wind rose patterns, from primary and secondary sources in the study area. Baseline data of air pollutant parameters extending an area 5 kms from the project should be monitored at a number of locations. Description of base line date of ambient air parameters namely RSPM Nitrogen dioxide, Sulphur dioxide and Carbon dioxide are to be collected one season date is to be monitored other than monsoon as per the CPCB/MoEF norms. Sampling locations are to be located as per CPCB/MoEF norms. 5.6 Noise Environment Construction equipment and road traffic are the major sources of noise. Baseline data of noise in the project area and the Neighborhood habitat areas are to be ascertained. Daytime and Nighttime data should be collected. 5.7 Water Environment Identify project activities, including construction phase, which may affect surface water of groundwater. Estimate water intake requirement and identify the sources of water to be used. Describe how water will be taken from the surface water/river and conveyed to the site. Rainwater harvesting has to be detailed out. Details for feanas and flora to be included.

  • 6

    5.8 Socio Economic & Health Environment Baseline data at the project area should including the demography, particularly on settlements, existing infrastructure facilities in the propose area and area of impact due to the proposed activity. Present employment and live hood of these populations, awareness of the population about the proposed activity should also be included. 5.9 Soil Waste Solid wastes from construction sector can be categorized into two phases i.e. during construction & during operation. Details of the following are to be given: � Construction or demolition waste, i.e. massive and inert waste � Municipal waste qualification and characterization i.e.,

    Biodegradable and recyclable waste and disposal facility Details of authorized municipal solid waste facilities, biomedical treatment facilities and hazardous waste disposal facilities in the area should be included.

    6.0 Anticipated Environmental Impact Mitigation Measures 6.1 Prediction of Impact: This should describe the likely impact of the project on each of the environmental parameters, methods adopted for assessing the Impact , empirical methos , reference to existing similar situations mitigation methods proposed to reduce adverse effects of the project best environment practices, conservation of natural resources, environmental management plan; post project environmental monitoring program in the project. Land Environment Anticipated Impacts: Some of the anticipated impacts, which need to be addressed, are Estimation of anticipated impacts on the surrounding land use pattern, on infrastructure like housing, road net work, environmentally sensitivity places etc. Proper mitigation measures have to be suggested improved road network infrastructure to handle the increase in traffic. Selection of suitable local plant species for green belt development in and around the sites.

  • 7

    Air Environment Anticipated impacts:

    Impact on air quality during the construction and operation phase

    should be predicted. The existing surrounding features of the study

    area and impact on them should be addressed separately. It is

    necessary to predict the following if any. Prediction of point source

    emissions Mitigating Measures: Mitigative measures are to be

    proposed during the construction stage as well as the operational