EE590 Oct 13-2008 Step 3-Dale Osborn

35
EE 590 Transmission Planning with Significant Energy Resources Dale Osborn Significant Energy Resources Midwest ISO October 13, 2008 [email protected]

description

EE590 Oct 13-2008 Step 3-Dale Osborn

Transcript of EE590 Oct 13-2008 Step 3-Dale Osborn

  • EE 590Transmission Planning with

    Significant Energy ResourcesDale Osborn

    Significant Energy Resources

    Midwest ISOOctober 13, 2008

    [email protected]

  • Historical Methods

    Clairs presentationL l ti t l l l d d dLocal generation to serve local load-expanded on NERC or local reliability criteriaInterties built for reliability, power purchaseInterties built for reliability, power purchase opportunities, economics are a plus

    LOLE, LOLP reduce the amount of generation that must be constructedconstructedContingency for major transmission loss- ice stormsAlso sell capacity and energy-power purchase would justify the line in early yearsSell economy energy

  • Transmission Planning Methods

    Traditional Reliability Planning-David DuebnerDuebner

    Find a problemFind the best solution

    Energy ( Economic) Planning-Dale OsbornFind the opportunityDesign a system that would capture an g y peconomic share of the opportunity

  • New Factors that Require Changes in the Planning Methods

    Open Access Transmission TariffsRTOs- breadth and speed of decision options greatly expandedg y

    Generation Queue processesSingle transmission sourceEnergy MarketsReliability decisions on a wide area and not the sum of individualReliability decisions on a wide area and not the sum of individual decisions-State Estimator Model, Outage Coordination, AFC calcuations,Reliability Coordination, SettlementsUtility focused planning still required-RTOs fit the pieces together, they do not define the piecesdo not define the pieces

    Energy MarketsAncillary Service Markets and Balancing Area consolidationWind Energy- RPSgyCarbon reductionsEnvironmental restrictionsLoad response

  • Transmission Design

    Present transmission systems were not designed to run in multi-RTO energy market environments.gyGeneration generally was planned to serve load in a utility area.Interconnections were used to increase reliability byInterconnections were used to increase reliability by pooling generation reserves and for economic energy and power exchanges.Transmission could be designed to make the multiple energy markets efficient in the Eastern Interconnection. Capacity would still be planned locally for reliability p y p y ypurposes.

  • Design Criteria

    What do you wish to have the transmission capable of doing?g

    Peak power delivery- reliabilityEconomic energy delivery- Benefit/Cost ratioBoth- assignment of capabilitiesBoth- assignment of capabilitiesExporting of wind energy diversity

    Who would pay for it?I t t d AC d iIntegrated AC designHVDC to separate the desing

    How would they pay for it?Where would it be constructed?Sequencing- can you get from here to there?

  • What is needed to plan a transmission system

    Stakeholder participation- Clair-scope of studyModels transmission generation loads DavidModels-transmission, generation, loads-David DuebnerGeneration Forecasts- John LawhornGe e at o o ecasts Jo a oCriteria- present, future

    Political willEconomic performance criteria-order mattersReliability performance critieriaE l ti dEvaluation procedure

    Merit evaluation definition

  • ISO-NE

    MISO

    ISO NE

    OverlayNYISO

    Hub

    SPPPJM

    TVA

    EntergySouthern

  • Transmission Plan Based on Economic Studies

    Paper 08TD0721 SlidesDale Osborn, Zheng Zhou

    Paper 08TD0721 Slides

    Midwest ISOApril, 2008p

    [email protected]@midwestiso.org@ g

  • MISO PJMJ i dJoint and CommonMarket

  • WWW.JCSPSTUDY.ORG

  • Potential Congestion Relief $M/yr

    IMO, $1,143

    MISO, $5,808SE, $4,288

    SPP, $1,162

    NYISO $2 908

    PJM, $6,679MAPP, $1,131

    NYISO, $2,908

  • 240,000 MW of Wind Generation

  • Market Flow

  • West to East Interface Flows OH-PA

    25000

    20000

    15000

    M

    W

    5000

    10000

    0

    5000

    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

    0 720 1440 2160 2880 3600 4320 5040 5760 6480 7200 7920 8640

    Hour of the Year

  • West to East Flow with HVDC

    25000

    15000

    20000

    W

    )

    80% of Maximum Loading

    10000

    15000

    l

    o

    w

    (

    M

    W

    5000

    F

    01 1008 2015 3022 4029 5036 6043 7050 8057

    Hours

  • 765 2200 2600-4500

  • 345 kV - 765 kv Delivery Capacitywith a 5% voltage drop

    on a losseles lineon a losseles line

    3

    3.5

    2

    2.5

    3

    L

    1

    1.5

    2

    P

    U

    S

    I

    L

    0

    0.5

    1

    00 50 100 150 200 250 300 350

    Miles

  • Transmission and Substation Costs per Mw-mile by Transmission Voltage And Type of Construction

    3 2003,6004,000

    2,4002,8003,200

    M

    i

    l

    e

    Lowest cost options

    1 2001,6002,000

    $

    /

    M

    w

    -

    M

    400800

    1,200

    0345 kVSteel

    WoodedA

    2-345kkVon Steel

    500 kV 765 kV 765 HSIL 800 kV GIL 1200 mile-800kVHVDC

    Areas600 1200 1300 2600 5400 5300 6400Target typical planned loading Mw, use economics to choose voltage

  • HVDC Advantages

    Lower cost per Mw-mileSmaller ROW- higher power densityD t i t f ith il d tiDoes not interfere with railroad operationsCan be undergrounded for water crossings for longer distances- Norway to the Netherlands is the longest -420 milesProvides unique dynamic characteristics to spread a disturbance over a large generation base quickly in a parallel manner Can link New Jersey to North Dakotageneration base quickly in a parallel manner. Can link New Jersey to North Dakota. No short circuit contributionsNo intermediate reactive control substations needed- if you need a tap use ACCombined with AC systems for contingent operation-5,000 Mw contingency designSchedulableSchedulable

    Power flowPrice differencesFrequencyWind variabilityContingency responseMinimize loop flow

  • 4,00016,000

  • 63,000 MW of wind mandates

  • 765 kV

    800 kV HVDC

    6400 MVA

  • Generation Connection Capability

    240,000 MW of wind generation modeled as connected to the transmission systemas connected to the transmission system including the overlay180 000 MW f ti l ti180,000 MW of conventional generation modeled as connected to the transmission

    t i l di th lsystem including the overlayThe overlay provides a place to connect generation and deliver the energy

  • 1200/1600 MVA

    +800 kV

    1200/1600 MVA

    400 kV+800 kV

    1200/1600 MVABi Polar Transmission line

    1200/1600 MVA -800 kV

    -400 kV

    1200/1600 MVA

    -800 kV

    400 MW can be connected per terminal, 1600 Mw total per line with a radial AC backup system

    3 HVDC Lines would have 12 terminals at the source and12 terminals at the sinks 14 400 MW self contingentA

    backup system

    12 terminals at the sinks-14,400 MW self contingentAC

  • Advantage of looping transmission

    For standard 2600 MW rated765 kV lines 2600 MW can bedelivered to the HVDC line

    To HVDC

    Which is rated at 4800 MW

    Series capacitors, double circuits,HSIL construction all could doubleHSIL construction all could doubleThe delivery capability and thus Increase the generation Connection and delivery capability

  • To HVDC

    Advantage of looping transmission

    2600 MWCross links to a terminal or terminals can

    2600 MW

    double the delivery to the HVDC terminal

    2600 Mwterminal

    5200 MW for

    standard d 765 kVrated 765 kV

  • Determine FuturesRenewable Future20% Wind Energy

    +Environmental

    $25/Ton CarbonTax

    Wind Hourly Data

    Power System Conceptual Design

    $25/Ton CarbonTax+..

    Generation Forecastand

    Generation Location

    Transmission Development

    Wind Data from

    Evaluation of other Futureswith this Futures

    Transmission

    Selection of A Robust

    Wind Data fromSeconds to Hours

    Transmission Conceptwith Future Specific

    Transmission Expansions

    Reliability Studyy y

    Wind Integration StudySimulations to DetermineAdequacy of GenerationControls to Fit the Short

    Term

    LOLE

    Real Time Simulation