Edward Farquharson 8 March 2007

22
Edward Farquharson 8 March 2007 Quality Control in Preparing and Managing PPP Projects

description

Quality Control in Preparing and Managing PPP Projects. Edward Farquharson 8 March 2007. Time. Impact. 100%. Gate 5. Benefits Evaluation. Gate 4. Readiness For Service. Gate 3. Ability to Influence Whole Life Cycle Expenditure. Investment Decision. Gate 2. Procurement Strategy. - PowerPoint PPT Presentation

Transcript of Edward Farquharson 8 March 2007

Page 1: Edward Farquharson 8 March 2007

Edward Farquharson8 March 2007

Quality Control in Preparing and Managing

PPP Projects

Page 2: Edward Farquharson 8 March 2007

Impact

100%

Ab

ilit

y t

o I

nfl

uen

ce

Wh

ole

Lif

e C

ycle

E

xpen

dit

ure

Confirm StrategyConfirm

JustificationCompetitive Procurement

In-ServiceConfirm Benefits

Time

Strategic Assessment

Contract Award

0%

Gate 0

Gate 1

Gate 2

Gate 3

Gate 4

Gate 5

ProcurementStrategy

InvestmentDecision

ReadinessFor Service

BenefitsEvaluation

BusinessJustification

Page 3: Edward Farquharson 8 March 2007

Key Lessons From OGC Gateway reviews/ Essentials for Project Success include:

– Effective stakeholder communication

– Sound financial controls

– Market knowledge and procurement advice

– Contract Management and delivery skills

– Benefits realisation process

– Robust business case

– Adequate skills and resources

– Ongoing risk management process

– Clearly defined roles and responsibilities

– Pre-agreed Critical Success Factors

– Project Governance

Page 4: Edward Farquharson 8 March 2007

Tools

• Processes

• Incentives

• Institutions

Queen Elizabeth Bridge, Second Dartford Crossing

Page 5: Edward Farquharson 8 March 2007

Project process

Project identification

Project preparation

•Affordability

•Output specs

•VFM

•Risk allocation

•Managing advisors

•Timing and management

Project operation

•Contract Management

•Feedback mechanisms

Project procurement

•Project Boards

•Contract Standardization

Page 6: Edward Farquharson 8 March 2007

Gate 2 check-list

1. Programme, project, procurement level review (scope, term)

2. Risk Allocation3. Key Terms and Conditions4. Indication of commercial interest5. Affordability6. Suitability of Proposed Advisers7. Indicative Timetable8. Project Team9. Commitment of Sponsors/Users10. Statutory Processes

Value for Money

Assessment

Commercial Interest Assessment

Project Management Assessment

Page 7: Edward Farquharson 8 March 2007

Incentives

• Peer review – PRG

• Guidance

• Central funding conditionality

• Governance – Project Boards

• Central support – e.g. PUK’s role on Project Boards Wolds Remand Prison

Page 8: Edward Farquharson 8 March 2007

Project process

Project identification

Project preparation

•Affordability

•Output specs

•VFM

•Risk allocation

•Managing advisors

•Timing and management

Project operation

•Contract Management

•Feedback mechanisms

Project procurement

•Project Boards

•Contract Standardization

Page 9: Edward Farquharson 8 March 2007

Procurement

• ‘2 stages ahead’ approach

• Bid evaluation methodology and teams

• Single parameter bidding vav quality/price evaluation

• Governance

• Standard contracts and enforcement

British Embassy, Berlin

Page 10: Edward Farquharson 8 March 2007

Project process

Project identification

Project preparation

•Affordability

•Output specs

•VFM

•Risk allocation

•Managing advisors

•Timing and management

Project operation

•Contract Management

•Feedback mechanisms

Project procurement

•Project Boards

•Contract Standardization

Page 11: Edward Farquharson 8 March 2007

Background

• Over 750 signed projects

• Over 500 operational projects

• “Central” focus hitherto predominantly on procurement

– Project management support

– Contract terms

– Bid times and costs

• High profile “issues”:– Contractor distress

– Benchmarking

– Major changes

• Proposition that focus needs to change!

• PUK Review of operational performance for HMT

West Middlesex Hospital

Page 12: Edward Farquharson 8 March 2007

Service Provider Performance

Performance measurement shows that the contract service levels are being achieved...

12%

77%

1% 0%

10%

Always Almost always About half of

the time

Almost never Never

Page 13: Edward Farquharson 8 March 2007

Relationships

Please rate the day-to-day operational relationship between the public and private sector contract management teams

40%

32%

3%0.0%

25%

Very good Good Satisfactory Poor Very poor

Page 14: Edward Farquharson 8 March 2007

User Satisfaction

Did the last user satisfaction assessment find that services were being delivered to an acceptable standard?

14%

65%

1% 0%

20%

Always Almost always About half of

the time

Almost never Never

Page 15: Edward Farquharson 8 March 2007

Were operational problems resolved in the time allowed?

15%

3%

82%

Always or AlmostAlways

Half of the time

Almost never

Never = 0%

Page 16: Edward Farquharson 8 March 2007

Main Findings

• High standards of Performance

• High Levels of Contract Manager Satisfaction

• Good Relationships

• High Levels of User Satisfaction

• Problems Resolved in Time

• Payment Deductions Generally Effective

• Dispute Resolution Rarely UsedForest Enterprise – Ardgartan Site

Page 17: Edward Farquharson 8 March 2007

Operational Taskforce

• To assist the public sector in improving the operational performance of PFI contracts

• To support individual projects in dealing with operational issues

• Run by PUK

Nottingham Trams

Page 18: Edward Farquharson 8 March 2007

Helpdesk and Project Support Services

• Contract Management Strategy and Best Practice

• Benchmarking and Market Testing

• Contract variations

• Contractor difficulties

• Change in ownership

• Mediation

• Insurance costs for insurance reviews

• Refinancing

• Payment mechanismsGCHQ

Page 19: Edward Farquharson 8 March 2007

Programme Delivery Units

• Opportunity created by long term national programmes

• Achieve optimum value and impact from strategic programmes

• Balance needs based prioritisation with deliverability and capacity

• Procurement and contract standardisation

• Removal of repeated bidding (for public and private)

• Strategic partnering drive economies of scale from long term volume Centre Manor Park – Primary Care

Centre

Page 20: Edward Farquharson 8 March 2007

Example: Partnerships for Schools

• National delivery vehicle (DfES/PUK)

• Roll out of national programme across c3500 schools (‘Building Schools for the Future’)

• Delivery model with standard procurement and contractual documentation

• Team to provide local transaction support

• Manage allocations of funding

• Plan timetable of prioritisation, procurement, construction and delivery

• Good practice examples and innovation opportunities/ideas

• Benchmark costs to facilitate long term local partnering

Brentside School

Page 21: Edward Farquharson 8 March 2007

Recap

• Procurements have programme issues

• Quality control is a continuous process

• Critical importance of Gate prior to release to competition

Page 22: Edward Farquharson 8 March 2007

Conclusions

• Gateways

• Governance

• Standardisation

• Incentives

• Importance of operational phase

• Feedback mechanismsHM Treasury