Edward A Bouchet Math & Science Academy...

65
Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd Chicago, IL 60649 This report contains the detailed findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility item by visual observation only; they do not test the operation of equipment or perform destructive testing of walls, ceilings or floors. Each facility item is ranked on a 7-point scale: rank 7 means the item is in new or in good condition and no work is required while rank 1 means the item has failed and has lead to an immediate life safety condition¹. The remaining ranks choices generally mean that the item requires regular maintenance (rank 5 or 6) or full replacement (rank 2, 3 or 4). For additional detail and definition on rank values as they relate to each assessed item, please visit the "CPS Guide to Biennial Facility Assessments" found on the Facilities Standards webpage under CPS Policies and Guidelines at http://www.cps.edu/About_CPS/Policies_and_guidelines/Pages/facilitystandards.aspx. Definitions for Quantity, Unit, Cost and Campus Total can be found at the end of this report. Facility Assessment Report Building Name Year Constructed Building Area (Sq Ft) Assessed Need Number of Floors Campus Summary Main 1903 16,964 $613,702 3 CPC 1996 6,087 $336,549 1 Addition 1 1914 55,927 $2,420,802 3 Addition 2 1922 21,852 $1,261,283 3 Annex 1948 40,499 $1,864,017 3 SITE $568,776 Campus Total $7,065,129 141,329 Building: Main Category: Building Exterior Item - Type Quantity Unit Rank Cost Location Group Comments Entrance Exterior Doors - Exterior Steel Door Door 3 - Southwest 6 EA 3 $1,442 Exterior Stairs - Concrete Door 3 - Southwest 6 LF 9 $736 Foundation Foundation - Masonry Entire Building 7 LF 4,241 $0 Superstructure - Heavy Timber Entire Building 7 SF 16,964 $0 Roof System Coping - Clay Tile Main Roof 6 LF 207 $6,648 Coping - Terra Cotta Main Roof 6 LF 99 $3,180 Downspouts - Exterior Downspouts Main Roof split 4 LF 50 $6,773 Downspouts - Interior Downspouts Main Roof 7 LF 50 $0 Parapet - 16" - 30" Height Main Roof 6 LF 163 $6,513 Parapet - Parapet < 16" Height Main Roof 6 LF 123 $2,621 Roof Structure - Heavy Timber Main Roof 7 SF 4,241 $0 Roof - Modified Bitumen Main Roof 6 SF 4,241 $39,905 Page 1 of 65 BOUCHET Assessment Date: 11/24/15

Transcript of Edward A Bouchet Math & Science Academy...

Page 1: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

This report contains the detailed findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility item by visual observation only; they do not test the operation of equipment or perform destructive testing of walls, ceilings or floors. Each facility item is ranked on a 7-point scale: rank 7 means the item is in new or in good condition and no work is required while rank 1 means the item has failed and has lead to an immediate life safety condition¹. The remaining ranks choices generally mean that the item requires regular maintenance (rank 5 or 6) or full replacement (rank 2, 3 or 4). For additional detail and definition on rank values as they relate to each assessed item, please visit the "CPS Guide to Biennial Facility Assessments" found on the Facilities Standards webpage under CPS Policies and Guidelines at http://www.cps.edu/About_CPS/Policies_and_guidelines/Pages/facilitystandards.aspx. Definitions for Quantity, Unit, Cost and Campus Total can be found at the end of this report.

Facility Assessment Report

Building Name Year Constructed Building Area (Sq Ft) Assessed Need Number of Floors

Campus Summary

Main 1903 16,964 $613,7023

CPC 1996 6,087 $336,5491

Addition 1 1914 55,927 $2,420,8023

Addition 2 1922 21,852 $1,261,2833

Annex 1948 40,499 $1,864,0173

SITE $568,776

Campus Total $7,065,129141,329

Building: Main

Category: Building Exterior

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Entrance

Exterior Doors - Exterior Steel Door Door 3 - Southwest 6EA3 $1,442

Exterior Stairs - Concrete Door 3 - Southwest 6LF9 $736

Foundation

Foundation - Masonry Entire Building 7LF4,241 $0

Superstructure - Heavy Timber Entire Building 7SF16,964 $0

Roof System

Coping - Clay Tile Main Roof 6LF207 $6,648

Coping - Terra Cotta Main Roof 6LF99 $3,180

Downspouts - Exterior Downspouts Main Roof split4LF50 $6,773

Downspouts - Interior Downspouts Main Roof 7LF50 $0

Parapet - 16" - 30" Height Main Roof 6LF163 $6,513

Parapet - Parapet < 16" Height Main Roof 6LF123 $2,621

Roof Structure - Heavy Timber Main Roof 7SF4,241 $0

Roof - Modified Bitumen Main Roof 6SF4,241 $39,905

Page 1 of 65BOUCHET Assessment Date: 11/24/15

Page 2: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Main

Category: Building Exterior

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Walls

Exterior Walls - Brick Entire Building 6SF6,486 $43,592

Exterior Walls - Stone-Cast Entire Building 6SF828 $5,565

Exterior Walls - Stucco Entire Building 6SF1,104 $5,289

Windows

Guard - Guards wire guard Entire Building 6SF405 $5,172

Lintels - Steel Entire Building 7LF116 $0

Lintels - Stone Entire Building 7LF49 $0

Windows - Sash Lexan Entire Building 6SF1,755 $13,100

Building Exterior Subtotal: $140,536

Building: Main

Category: Electrical System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Emergency System

Emergency A/C Power - Corridors and Stairs Entire Building 6SF3,523 $1,058

Emergency Battery Packs - Corridors and Stairs Entire Building (14) exit signs and (1) combination exit and

emergency light.

6EA15 $3,038

Exit Signs - Corridors and Stairs Entire Building 6EA15 $2,246

Security System - CCTV Entire Building Exterior cameras only. 6SF16,964 $5,094

Security System - Intrusion Detection Entire Building 6SF19,694 $5,069

Main Service

Independent Electrical Service for emergency power Fire Pump Room Secondary service for the fire pump. 6EA1 $2,921

PA System Entire Building Serves main, addition 1 and addition 2. Control console is located in addition 1.

6SF16,964 $5,579

Electrical System Subtotal: $25,005

Building: Main

Category: Safty System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Fire Alarm

Fire Alarm_System Entire Building Obsolete technology. Manual pull stations only. Panel located in Addition 1.

4SF16,964 $33,719

Fire Pump Controller Entire Building / Basement 6EA1 $1,823

Page 2 of 65BOUCHET Assessment Date: 11/24/15

Page 3: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Main

Category: Safty System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Pump Room Assembly

Fire Pump - Less than 25hp Fire Pump Room Serves main and both additions. 6EA1 $1,558

Sprinkler System

Dry Sprinkler System Entire Building 6SF16,964 $4,367

Sprinkler Heads Entire Building 7SF16,964 $0

Sprinkler Piping Entire Building 7SF16,964 $0

Safty System Subtotal: $41,467

Building: Main

Category: Mechanical System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Heating Devices

Wall Heater - Electric Entire Building Missing cover, exposed wires. Student toilet. 4EA1 $1,083

Wall Heater - Electric Entire Building 6EA3 $417

Temperature Control

Pneumatic System Entire Building Most pneumatic lines cut. Thermostats are damaged or missing. All building is controlled manually via the boilers. Building gets excessively hot.

3SF16,964 $88,301

Thermostats - Pneumatic Entire Building / 1st Floor Missing or damaged thermostats. 4EA4 $2,949

Thermostats - Pneumatic Entire Building Thermostats are past useful life and cannot control temperature.

4EA4 $2,949

Ventilation

Exhaust Fans- Roof Mounted - 1501 - 8000 CFM Roof 6EA1 $592

Exhaust Fans- Roof Mounted - Less than 500 CFM Roof Motor removed.3EA1 $1,942

Mechanical System Subtotal: $98,233

Building: Main

Category: Plumbing System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Piping

Domestic Piping-Cold Water from Risers to Fixtures Entire Building 6SF16,964 $3,396

Domestic Piping-Cold Water Horizontal Lines Entire Building 6SF16,964 $4,124

Domestic Piping-Cold Water Risers Entire Building 6SF16,964 $3,154

Domestic Piping-Hot Water from Risers to Fixtures Entire Building 6SF16,964 $2,668

Page 3 of 65BOUCHET Assessment Date: 11/24/15

Page 4: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Main

Category: Plumbing System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Piping

Domestic Piping-Hot Water Horizontal Lines Entire Building 6SF16,964 $3,154

Domestic Piping-Hot Water Return Lines Entire Building 6SF16,964 $2,426

Domestic Piping-Hot Water Return Risers Entire Building 6SF16,964 $2,426

Sanitary Piping Entire Building 6SF16,964 $15,525

Storm Piping Entire Building 6SF16,964 $14,798

Vent Piping Entire Building 6SF16,964 $11,402

Plumbing System Subtotal: $63,072

Building: Main

Category: Classrooms

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Classroom #103 (Regular Classroom)

Ceiling - Plaster/Drywall 1st Floor 6SF857 $2,966

Ceiling - Plaster/Drywall 1st Floor crack5SF12 $150

Chalk Board 1st Floor 4LF36 $3,305

Doors - Transom Window 1st Floor 6SF8 $135

Doors - Wood Doors inclu hw 1st Floor 6EA2 $602

Floor - Wood 1st Floor 6SF869 $6,126

Lighting - Pendent/Surface 1st Floor 7EA14 $0

Storage/ Closet 1st Floor 6SF61 $442

Walls - Plaster/Drywall 1st Floor 6SF1,376 $3,798

Classroom #104 (Regular Classroom)

Ceiling - Plaster/Drywall 1st Floor 6SF869 $3,007

Chalk Board 1st Floor 4LF28 $2,571

Doors - Transom Window 1st Floor 6SF8 $135

Doors - Wood Doors inclu hw 1st Floor 6EA1 $301

Floor - Tile 1st Floor 6SF844 $1,847

Floor - Tile 1st Floor damaged5SF25 $144

Lighting - Pendent/Surface 1st Floor 7EA14 $0

Storage/ Closet 1st Floor peeling5SF184 $2,968

Walls - Plaster/Drywall 1st Floor 6SF1,376 $3,798

Classroom #203 (Special Education)

Ceiling - Plaster/Drywall 2nd Floor 6SF869 $3,007

Chalk Board 2nd Floor 4LF12 $1,102

Doors - Transom Window 2nd Floor 6SF8 $135

Page 4 of 65BOUCHET Assessment Date: 11/24/15

Page 5: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Main

Category: Classrooms

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Classroom #203 (Special Education)

Doors - Wood Doors inclu hw 2nd Floor 6EA2 $602

Floor - Tile 2nd Floor 6SF869 $1,901

Lighting - Pendent/Surface 2nd Floor 7EA14 $0

Marker Board 2nd Floor 7LF16 $0

Storage/ Closet 2nd Floor minor peeling6SF184 $1,334

Walls - Plaster/Drywall 2nd Floor 6SF1,376 $3,798

Classroom #303 (Regular Classroom)

Ceiling - Plaster/Drywall 3rd Floor 6SF854 $2,955

Ceiling - Plaster/Drywall 3rd Floor peeling5SF15 $187

Chalk Board 3rd Floor 4LF36 $3,305

Doors - Transom Window 3rd Floor 6SF16 $271

Doors - Wood Doors inclu hw 3rd Floor 6EA2 $602

Floor - Wood 3rd Floor 6SF869 $6,126

Lighting - Pendent/Surface 3rd Floor 7EA14 $0

Storage/ Closet 3rd Floor peeling paint5SF184 $2,968

Walls - Plaster/Drywall 3rd Floor peeling paint5SF1,376 $10,429

Classroom #304 (Regular Classroom)

Ceiling - Plaster/Drywall 3rd Floor 6SF869 $3,007

Chalk Board 3rd Floor 4LF24 $2,203

Doors - Transom Window 3rd Floor 6SF8 $135

Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301

Floor - Wood 3rd Floor 6SF869 $6,126

Lighting - Pendent/Surface 3rd Floor 7EA14 $0

Storage/ Closet 3rd Floor 10' of closet damaged6SF184 $1,334

Walls - Plaster/Drywall 3rd Floor need painting5SF1,376 $10,429

Classrooms Subtotal: $94,554

Building: Main

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Library

Ceiling - Plaster/Drywall Room 204 6SF869 $3,007

Doors - Transom Window Room 204 6SF8 $135

Doors - Wood Doors inclu hw Room 204 split5EA1 $1,174

Floor - Tile Room 204 cracked throughout5SF869 $3,902

Page 5 of 65BOUCHET Assessment Date: 11/24/15

Page 6: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Main

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Library

Lighting - Pendent/Surface Room 204 7EA14 $0

Storage/ Closet Room 204 6SF184 $1,334

Walls - Plaster/Drywall Room 204 needs painting5SF1,376 $10,429

Lunch & Multipurpose Room

Ceiling - Plaster/Drywall Basement - Lunch/office 6SF350 $1,211

Doors - Wood Doors inclu hw Basement - Lunch/office 6EA1 $301

Floor - Tile Basement - Lunch/office 6SF344 $753

Floor - Tile Basement - Lunch/office broken, cracked tile5SF6 $35

Lighting - Lay-in Basement - Lunch/office 7EA4 $0

Walls - Plaster/Drywall Basement - Lunch/office 6SF672 $1,855

Walls - Plaster/Drywall Basement - Lunch/office cracked, water damaged plaster5SF8 $41

Mechanical/ Service Rooms

Mechanical/ Service Rooms Basement Includes Pump rm. 6SF78 $559

Storage Room Basement Includes class rm 4, class rm 56SF850 $6,090

Restroom

Accessories 1st Floor Boy's- By 104 6SF263 $2,426

Ceiling - Plaster/Drywall 1st Floor Boy's- By 104 6SF263 $910

Doors - Wood Doors inclu hw 1st Floor Boy's- By 104 6EA2 $602

Floor Drain 1st Floor Boy's- By 104 6EA1 $1,059

Floor - Tile Ceramic/ Porcelain 1st Floor Boy's- By 104 6SF263 $557

Lavatory 1st Floor Boy's- By 104 6EA2 $639

Lighting - Pendent/Surface 1st Floor Boy's- By 104 6EA5 $619

Partitions 1st Floor Boy's- By 104 6EA4 $1,188

Urinals 1st Floor Boy's- By 104 6EA8 $2,688

Walls - Plaster/Drywall 1st Floor Boy's- By 104 damaged5SF2 $10

Walls - Plaster/Drywall 1st Floor Boy's- By 104 6SF329 $908

Walls - Structural Glazed Tile 1st Floor Boy's- By 104 6SF331 $1,041

Water Closet 1st Floor Boy's- By 104 6EA3 $1,008

Accessories 2nd Floor Boy's- By 204 6SF263 $2,426

Ceiling - Plaster/Drywall 2nd Floor Boy's- By 204 6SF263 $910

Doors - Wood Doors inclu hw 2nd Floor Boy's- By 204 6EA2 $602

Floor Drain 2nd Floor Boy's- By 204 6EA1 $1,059

Floor - Tile Ceramic/ Porcelain 2nd Floor Boy's- By 204 6SF263 $557

Lavatory 2nd Floor Boy's- By 204 6EA2 $639

Lighting - Pendent/Surface 2nd Floor Boy's- By 204 6EA5 $619

Partitions 2nd Floor Boy's- By 204 6EA4 $1,188

Page 6 of 65BOUCHET Assessment Date: 11/24/15

Page 7: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Main

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Restroom

Urinals 2nd Floor Boy's- By 204 6EA8 $2,688

Walls - Plaster/Drywall 2nd Floor Boy's- By 204 6SF331 $914

Walls - Structural Glazed Tile 2nd Floor Boy's- By 204 6SF331 $1,041

Water Closet 2nd Floor Boy's- By 204 6EA3 $1,008

Accessories 3rd Floor Boy's- By 304 6SF263 $2,426

Ceiling - Plaster/Drywall 3rd Floor Boy's- By 304 6SF263 $910

Doors - Wood Doors inclu hw 3rd Floor Boy's- By 304 6EA2 $602

Floor Drain 3rd Floor Boy's- By 304 6EA1 $1,059

Floor - Tile Ceramic/ Porcelain 3rd Floor Boy's- By 304 6SF263 $557

Lavatory 3rd Floor Boy's- By 304 6EA2 $639

Lighting - Pendent/Surface 3rd Floor Boy's- By 304 6EA5 $619

Partitions 3rd Floor Boy's- By 304 6EA4 $1,188

Urinals 3rd Floor Boy's- By 304 6EA8 $2,688

Walls - Plaster/Drywall 3rd Floor Boy's- By 304 6SF331 $914

Walls - Structural Glazed Tile 3rd Floor Boy's- By 304 6SF331 $1,041

Water Closet 3rd Floor Boy's- By 304 6EA3 $1,008

Accessories Basement- Boy's- By Rm 5 6SF217 $2,001

Ceiling - Plaster/Drywall Basement- Boy's- By Rm 5 water damaged5SF10 $125

Ceiling - Plaster/Drywall Basement- Boy's- By Rm 5 6SF207 $716

Doors - Wood Doors inclu hw Basement- Boy's- By Rm 5 6EA2 $602

Floor Drain Basement- Boy's- By Rm 5 6EA1 $1,059

Floor - Tile Ceramic/ Porcelain Basement- Boy's- By Rm 5 6SF217 $459

Lavatory Basement- Boy's- By Rm 5 6EA2 $639

Lighting - Pendent/Surface Basement- Boy's- By Rm 5 6EA4 $496

Partitions Basement- Boy's- By Rm 5 6EA3 $891

Urinals Basement- Boy's- By Rm 5 6EA7 $2,352

Walls - Plaster/Drywall Basement- Boy's- By Rm 5 water damaged5SF35 $179

Walls - Plaster/Drywall Basement- Boy's- By Rm 5 6SF329 $908

Walls - Structural Glazed Tile Basement- Boy's- By Rm 5 6SF231 $727

Water Closet Basement- Boy's- By Rm 5 6EA3 $1,008

Rooms (Other Than Classrooms) Subtotal: $83,944

Building: Main

Category: Building Interior

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Page 7 of 65BOUCHET Assessment Date: 11/24/15

Page 8: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Main

Category: Building Interior

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Corridor

Ceiling - Plaster/Drywall 1st Floor 6SF705 $4,365

Drinking Fountains - Single Water Cooler 1st Floor 6EA2 $633

Floor - Tile/Sheet 1st Floor 6SF705 $383

Lighting - Pendent/Surface 1st Floor 7EA4 $0

Walls - Plaster/Drywall 1st Floor 6SF1,222 $5,417

Ceiling - Plaster/Drywall 2nd Floor 6SF705 $4,365

Drinking Fountains - Single Fountain 2nd Floor 6EA2 $551

Floor - Tile/Sheet 2nd Floor 6SF705 $383

Lighting - Pendent/Surface 2nd Floor 7EA4 $0

Walls - Plaster/Drywall 2nd Floor 6SF1,222 $5,417

Ceiling - Plaster/Drywall 3rd Floor 6SF705 $4,365

Drinking Fountains - Single Fountain 3rd Floor 6EA2 $551

Floor - Tile/Sheet 3rd Floor 6SF705 $383

Lighting - Pendent/Surface 3rd Floor 7EA4 $0

Walls - Plaster/Drywall 3rd Floor 6SF1,222 $5,417

Ceiling - Exposed Basement 6SF799 $1,188

Drinking Fountains - Single Fountain Basement 6EA2 $551

Floor - Tile Ceramic/ Porcelain Basement 6SF94 $262

Floor - Tile/Sheet Basement 6SF705 $383

Lighting - Pendent/Surface Basement 7EA5 $0

Walls - Metal Panel Basement 6SF1,222 $9,122

Walls - Structural Glazed Tile Basement 6SF318 $1,000

Walls - Structural Glazed Tile Basement efflorescence5SF5 $319

Safety

Security Cameras 6EA2 $388

Security Cameras 6EA1 $194

Stairs

Ceiling - Plaster/Drywall South 6SF842 $6,165

Floor - Tile South 6SF609 $331

Handrails South 6LF212 $1,837

Lighting - Pendent/Surface South 7EA5 $0

Stairs - Asphalt South 5LF60 $2,539

Stairs - Asphalt South asphalt covered in VCT & Metal Treads6LF23 $213

Walls - Plaster/Drywall South 6SF3,661 $10,104

Walls - Plaster/Drywall South cracked5SF10 $62

Page 8 of 65BOUCHET Assessment Date: 11/24/15

Page 9: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Main

Category: Building Interior

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Building Interior Subtotal: $66,892

Total Building Cost $613,702

Building: CPC

Category: Building Exterior

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Entrance

Exterior Doors - Exterior Steel Door Door 1 - Southwest 6EA1 $481

Exterior Doors - Exterior Steel Door Door 2 - Northwest 6EA1 $481

Exterior Doors - Exterior Steel Door Door 3 - North 6EA1 $481

Exterior Doors - Exterior Steel Door Door 4 - North 6EA1 $481

Exterior Doors - Exterior Steel Door Door 5 - North mech damaged/missing hardware5EA1 $1,341

Exterior Doors - Exterior Steel Door Door 6 - East 6EA2 $961

Exterior Doors - Exterior Steel Door Door 7 - South 6EA1 $481

Exterior Doors - Exterior Steel Door Door 8 - South 6EA1 $481

Foundation

Foundation - Concrete Entire Building 7LF330 $0

Superstructure - Concrete Entire Building 7SF6,087 $0

Lighting

Exterior Lighting - Wall Mounted Entire Building 6EA6 $1,732

Roof System

Chimney - Metal Flue Main Roof 7LF3 $0

Coping - Metal Main Roof 6LF330 $10,599

Downspouts - Interior Downspouts Main Roof 7LF26 $0

Parapet - Parapet < 16" Height Main Roof 6LF330 $7,031

Roof Structure - Steel / Metal Deck/ Concrete Topping Main Roof 7SF60,778 $0

Roof - Asphalt Gravel Ballast Main Roof 5SF6,078 $143,497

Walls

Exterior Walls - Concrete Block Entire Building 7SF4,290 $0

Windows

Guard - Guards wire guard Entire Building 6SF630 $8,045

Lintels - Steel Entire Building 7LF195 $0

Windows - Sash Aluminum Entire Building 7SF630 $0

Page 9 of 65BOUCHET Assessment Date: 11/24/15

Page 10: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: CPC

Category: Building Exterior

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Building Exterior Subtotal: $176,091

Building: CPC

Category: Electrical System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Emergency System

Emergency Battery Packs - Corridors and Stairs Entire Building Emergency lights. 6EA10 $2,025

Emergency Battery Packs - Corridors and Stairs Entire Building Exit signs.6EA7 $1,418

Exit Signs - Corridors and Stairs Entire Building Includes classroom exit signs. 6EA7 $1,048

Security System - Intrusion Detection Entire Building 6SF6,087 $1,567

Main Service

Main Electrical Service - 800 A and Less than 120/208/3PH Mechanical Room 6EA1 $3,398

Power Distribution

Lighting and Power Panels - 100 A Entire Building / Electrical Room Fuses.6EA1 $299

Lighting and Power Panels - 100 A Entire Building / Electrical Room 6EA1 $299

Lighting and Power Panels - Above 100 A Entire Building / Electrical Room 6EA1 $497

Electrical System Subtotal: $10,551

Building: CPC

Category: Safty System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Fire Alarm

Fire Alarm Panel Entire Building / Mechanical Room 6EA1 $6,406

Fire Alarm Strobe Lights Entire Building 6SF6,087 $2,176

Fire Alarm_System Entire Building 6SF6,087 $2,959

Sprinkler System

Sprinkler Heads Entire Building 7SF6,087 $0

Sprinkler Piping Entire Building 6SF6,087 $1,132

Wet Sprinkler System Entire Building 6SF6,087 $1,567

Safty System Subtotal: $14,240

Building: CPC

Category: Mechanical System

Page 10 of 65BOUCHET Assessment Date: 11/24/15

Page 11: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Category: Mechanical System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Air Conditioning

Condensing Unit- Roof Mounted - 5-10 tons Roof 6EA1 $3,334

Condensing Unit- Roof Mounted - 5-10 tons Roof 5EA1 $9,590

Condensing Unit- Roof Mounted - 5-10 tons Roof 5EA1 $9,590

Condensing Unit- Roof Mounted - Less than 5 tons Roof 5EA2 $14,757

Heating Devices

Fin Tube - Electric 1st Floor 6LF3 $28

Gas/ Natural Draft Furnace - Less than 100 MBH Mechanical Room 6EA2 $1,208

Gas/ Natural Draft Furnace - Less than 100 MBH Mechanical Room 6EA2 $1,208

Gas/ Natural Draft Furnace - Less than 100 MBH Mechanical Room 6EA2 $1,208

Unit Heater - Gas Mechanical Room 6EA1 $278

Wall Heater - Electric Entry Vestibule 6EA1 $139

Temperature Control

Electric Controls Entire Building / 1st Floor 6SF6,087 $0

Electric Thermostat Entire Building / 1st Floor 6EA6 $0

Ventilation

Exhaust Fans- Indoor - 1501 - 8000 CFM Mechanical Room 6EA1 $592

Mechanical System Subtotal: $41,932

Building: CPC

Category: Plumbing System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Hot Water

Electric Heater - Less than 20 KW 1st Floor 6EA2 $1,364

Piping

Domestic Piping-Cold Water from Risers to Fixtures Entire Building 6SF6,087 $1,219

Domestic Piping-Cold Water Horizontal Lines Entire Building 6SF6,087 $1,480

Domestic Piping-Hot Water from Risers to Fixtures Entire Building 6SF6,087 $957

Domestic Piping-Hot Water Horizontal Lines Entire Building 6SF6,087 $1,132

Domestic Piping-Hot Water Return Lines Entire Building 6SF6,087 $870

Sanitary Piping Entire Building 6SF6,087 $5,571

Storm Piping Entire Building 6SF6,087 $5,310

Vent Piping Entire Building 6SF6,087 $4,091

Plumbing System Subtotal: $21,994

Building: CPC

Page 11 of 65BOUCHET Assessment Date: 11/24/15

Page 12: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: CPC

Category: Classrooms

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Classroom #103 (Pre School)

Casework 1st Floor 6LF34 $859

Ceiling - Exposed 1st Floor 6SF580 $863

Doors - Steel Doors incl hw 1st Floor 6EA1 $301

Doors - Wood Doors inclu hw 1st Floor 6EA2 $602

Floor - Tile 1st Floor 6SF580 $1,269

Lighting - Pendent/Surface 1st Floor 7EA12 $0

Storage/ Closet 1st Floor 6SF38 $276

Walls - Concrete Block 1st Floor 6SF489 $1,434

Walls - Plaster/Drywall 1st Floor 6SF589 $1,626

Work Sink 1st Floor 6EA1 $379

Classroom #104 (Pre School)

Casework 1st Floor 6LF34 $859

Ceiling - Exposed 1st Floor 6SF580 $863

Doors - Steel Doors incl hw 1st Floor 6EA1 $301

Doors - Wood Doors inclu hw 1st Floor 6EA2 $602

Floor - Tile 1st Floor 6SF576 $1,260

Floor - Tile 1st Floor cracked tiles5SF4 $23

Lighting - Pendent/Surface 1st Floor 7EA12 $0

Storage/ Closet 1st Floor 6SF38 $276

Walls - Concrete Block 1st Floor 6SF489 $1,434

Walls - Plaster/Drywall 1st Floor 6SF589 $1,626

Work Sink 1st Floor 6EA1 $379

Classroom #135 (Pre School)

Casework 1st Floor 6LF60 $1,515

Ceiling - Exposed 1st Floor 6SF1,120 $1,666

Chalk Board 1st Floor 4LF12 $1,102

Doors - Steel Doors incl hw 1st Floor 6EA1 $301

Doors - Wood Doors inclu hw 1st Floor 6EA2 $602

Floor - Tile 1st Floor 6SF1,102 $2,411

Floor - Tile 1st Floor cracked tiles5SF8 $46

Lighting - Pendent/Surface 1st Floor 7EA30 $0

Storage/ Closet 1st Floor 6SF38 $276

Walls - Concrete Block 1st Floor 6SF716 $2,099

Walls - Plaster/Drywall 1st Floor 6SF876 $2,418

Work Sink 1st Floor 6EA1 $379

Classroom #136 (Pre School)

Casework 1st Floor 6LF60 $1,515

Page 12 of 65BOUCHET Assessment Date: 11/24/15

Page 13: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: CPC

Category: Classrooms

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Classroom #136 (Pre School)

Ceiling - Exposed 1st Floor 6SF1,120 $1,666

Chalk Board 1st Floor 4LF12 $1,102

Doors - Steel Doors incl hw 1st Floor 6EA1 $301

Doors - Wood Doors inclu hw 1st Floor 6EA2 $602

Floor - Tile 1st Floor 6SF1,120 $2,450

Lighting - Pendent/Surface 1st Floor 7EA30 $0

Storage/ Closet 1st Floor 6SF38 $276

Walls - Concrete Block 1st Floor 6SF716 $2,099

Walls - Plaster/Drywall 1st Floor 6SF876 $2,418

Work Sink 1st Floor 6EA1 $379

Classrooms Subtotal: $40,849

Building: CPC

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Administrative Suites/Offices

Ceiling - Exposed 1st Floor 6SF151 $225

Doors - Wood Doors inclu hw 1st Floor door damaged, needs replacement5EA1 $1,174

Floor - Tile/Sheet 1st Floor 6SF151 $151

Lighting - Pendent/Surface 1st Floor 7EA2 $0

Power Distribution 1st Floor 7EA10 $0

Walls - Concrete Block 1st Floor 6SF663 $1,944

Lunch & Multipurpose Room

Ceiling - Exposed 1st Floor 6SF1,801 $2,678

Doors - Steel Doors incl hw 1st Floor 6EA6 $1,806

Floor - Tile 1st Floor 7SF1,801 $0

Lighting - Pendent/Surface 1st Floor 7EA31 $0

Walls - Concrete Block 1st Floor 6SF2,332 $6,836

Mechanical/ Service Rooms

Mechanical/ Service Rooms 1st Floor 6SF222 $1,590

Restroom

Accessories 103B 6SF40 $369

Ceiling - Exposed 103B 6SF40 $59

Doors - Wood Doors inclu hw 103B 6EA1 $301

Page 13 of 65BOUCHET Assessment Date: 11/24/15

Page 14: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: CPC

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Restroom

Floor Drain 103B 6EA1 $1,059

Floor - Tile 103B 6SF40 $88

Hand Dryer 103B 6EA1 $230

Lavatory 103B 6EA1 $320

Lighting - Pendent/Surface 103B 7EA1 $0

Walls - Plaster/Drywall 103B 6SF310 $856

Water Closet 103B 6EA1 $336

Accessories 104B 6SF40 $369

Ceiling - Exposed 104B 6SF40 $59

Doors - Wood Doors inclu hw 104B 6EA1 $301

Floor Drain 104B 6EA1 $1,059

Floor - Tile 104B 6SF40 $88

Hand Dryer 104B 6EA1 $230

Lavatory 104B 6EA1 $320

Lighting - Pendent/Surface 104B 7EA1 $0

Walls - Plaster/Drywall 104B 6SF310 $856

Water Closet 104B 6EA1 $336

Accessories Room 135B 6SF40 $369

Ceiling - Exposed Room 135B 6SF40 $59

Doors - Wood Doors inclu hw Room 135B 6EA1 $301

Floor Drain Room 135B 6EA1 $1,059

Floor - Tile Room 135B 6SF40 $88

Hand Dryer Room 135B 6EA1 $230

Lavatory Room 135B 6EA1 $320

Lighting - Pendent/Surface Room 135B 7EA1 $0

Walls - Plaster/Drywall Room 135B 6SF302 $833

Walls - Plaster/Drywall Room 135B cracked, water damage5SF8 $41

Water Closet Room 135B 6EA1 $336

Accessories Room 136B 6SF40 $369

Ceiling - Exposed Room 136B 6SF40 $59

Doors - Wood Doors inclu hw Room 136B 6EA1 $301

Floor Drain Room 136B 6EA1 $1,059

Floor - Tile Room 136B 6SF40 $88

Hand Dryer Room 136B 6EA1 $230

Lavatory Room 136B 6EA1 $320

Lighting - Pendent/Surface Room 136B 7EA1 $0

Walls - Plaster/Drywall Room 136B 6SF310 $856

Page 14 of 65BOUCHET Assessment Date: 11/24/15

Page 15: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: CPC

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Restroom

Water Closet Room 136B 6EA1 $336

Rooms (Other Than Classrooms) Subtotal: $30,892

Total Building Cost $336,549

Building: Addition 1

Category: Building Exterior

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Entrance

Entrance Control - Audio and Video Door 1 - East 7EA1 $0

Exterior Doors - Exterior Steel Door Door 1 - East 6EA4 $1,922

Exterior Doors - Exterior Steel Door Door 2 - Southeast 7EA1 $0

Exterior Doors - Exterior Steel Door Door 6 - North auditorium 6EA4 $1,922

Exterior Doors - Exterior Steel Door Door 7 - Fire escape 6EA1 $481

Exterior Doors - Exterior Steel Door Door 8 - North 6EA2 $961

Exterior Doors - Exterior Steel Door Door 9 - North boiler 6EA1 $481

Exterior Doors - Transom Lite Door 1 - East 6EA4 $1,253

Exterior Doors - Transom Lite Door 2 - Southeast 7EA1 $0

Exterior Doors - Transom Lite Door 6 - North auditorium 6EA4 $1,253

Exterior Doors - Transom Lite Door 8 - North 6EA2 $627

Exterior Doors - Transom Lite Door 9 - North boiler 6EA1 $313

Exterior Stairs - Concrete Door 1 - East 6LF14 $1,145

Exterior Stairs - Concrete Door 1 - East 5LF4 $438

Exterior Stairs - Concrete Door 2 - Southeast 7LF60 $0

Exterior Stairs - Concrete Door 6 - North auditorium 6LF12 $981

Exterior Stairs - Concrete Door 8 - North 6LF16 $1,308

Ramp Handrail - Steel_Ramp Handrail Door 2 - Southeast 7LF40 $0

Fire Escape

Fire Escape Entire Building 6LF42 $26,534

Foundation

Foundation - Concrete Entire Building / Boiler Room 7LF180 $0

Foundation - Masonry Entire Building 7LF5,300 $0

Superstructure - Steel with Clay Tile Arch Entire Building 7SF55,927 $0

Page 15 of 65BOUCHET Assessment Date: 11/24/15

Page 16: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 1

Category: Building Exterior

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Lighting

Exterior Lighting - Wall Mounted Entire Building 6EA12 $3,465

Roof System

Chimney - Brick Chimney- Concrete/ Mortar Liner Roof 4 6LF90 $85,921

Coping - Clay Tile Roof 4 6LF109 $3,501

Coping - Stone Roof 4 6LF112 $3,597

Coping - Terra Cotta Roof 1 6LF330 $10,599

Coping - Terra Cotta Roof 2 6LF45 $1,445

Coping - Terra Cotta Roof 3 6LF32 $1,028

Coping - Terra Cotta Roof 5 6LF220 $7,066

Downspouts - Exterior Downspouts Roof 3 6LF11 $366

Downspouts - Exterior Downspouts Roof 4 6LF54 $1,795

Downspouts - Exterior Downspouts Roof 5 6LF110 $3,656

Downspouts - Interior Downspouts Roof 1 7LF183 $0

Downspouts - Interior Downspouts Roof 2 6LF24 $798

Downspouts - Interior Downspouts Roof 4 7LF30 $0

Parapet - 16" - 30" Height Roof 1 6LF80 $3,196

Parapet - 16" - 30" Height Roof 2 6LF45 $1,798

Parapet - 16" - 30" Height Roof 3 6LF32 $1,279

Parapet - 16" - 30" Height Roof 5 6LF220 $8,790

Parapet - Parapet < 16" Height Roof 1 6LF125 $2,663

Parapet - Parapet < 16" Height Roof 4 7LF109 $0

Parapet - Parapet > 30" Roof 1 6LF125 $7,990

Parapet - Parapet > 30" Roof 4 6LF112 $7,159

Roof Structure - Steel with Clay Tile Arch Roof 1 7SF9,451 $0

Roof Structure - Steel with Clay Tile Arch Roof 2 7SF260 $0

Roof Structure - Steel with Clay Tile Arch Roof 3 7SF250 $0

Roof Structure - Steel with Clay Tile Arch Roof 4 7SF6,006 $0

Roof Structure - Steel with Clay Tile Arch Roof 5 7SF5,767 $0

Roof - Modified Bitumen Roof 1 6SF9,451 $88,928

Roof - Modified Bitumen Roof 2 6SF260 $2,446

Roof - Modified Bitumen Roof 3 6SF250 $2,352

Roof - Modified Bitumen Roof 4 6SF6,006 $56,513

Roof - Modified Bitumen Roof 5 6SF5,767 $54,264

Walls

Exterior Walls - Brick Entire Building 6SF24,408 $164,046

Exterior Walls - Stone-Cast Entire Building 6SF2,658 $17,864

Page 16 of 65BOUCHET Assessment Date: 11/24/15

Page 17: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 1

Category: Building Exterior

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Walls

Exterior Walls - Stucco Entire Building 6SF1,155 $5,533

Windows

Guard - Guards wire guard Entire Building 6SF2,255 $28,796

Lintels - Brick Entire Building 6LF16 $0

Lintels - Steel Entire Building 6LF450 $13,063

Lintels - Stone Entire Building 6LF150 $0

Windows - Decorative Entire Building 6SF60 $448

Windows - Sash Lexan Entire Building 6SF6,600 $49,266

Building Exterior Subtotal: $679,251

Building: Addition 1

Category: Electrical System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Emergency System

Automatic Transfer Switch Kitchen Storage Room Serves main and both additions. 6EA1 $408

Automatic Transfer Switch Kitchen Storage Room Serves main and both additions. 6EA1 $408

Emergency A/C Power - Corridors and Stairs Entire Building 6SF9,746 $2,927

Emergency A/C Power - Lunchrooms Entire Building / Basement 6SF1,152 $428

Emergency Battery Packs - Auditoium and Aisle Lighting Entire Building / 1st Floor Exit signs.6EA4 $810

Emergency Battery Packs - Corridors and Stairs Entire Building (38) exit signs and (2) combination exit sign/emergency light.

6EA40 $8,100

Emergency Battery Packs - Gym Entire Building / 2nd Floor Exit signs.6EA3 $608

Emergency Battery Packs - Lunchrooms Entire Building / Basement Exit signs.6EA2 $405

Exit Signs - Auditoium Entire Building / 1st Floor 6EA4 $599

Exit Signs - Corridors and Stairs Entire Building 6EA40 $5,990

Exit Signs - Gym Entire Building / 2nd Floor 6EA3 $472

Exit Signs - Lunchroom Entire Building / Basement 6EA2 $299

Security System - CCTV Entire Building 6SF55,927 $16,795

Security System - Intrusion Detection Entire Building 6SF55,927 $14,396

UPS - Less than 30 KW Electrical Room Emergency power system. Serves main and two additions.

5EA1 $33,979

Main Service

Main Electrical Service - 1200 A 120/208/3PH Electrical Room Serves main and both additions.6EA1 $5,078

Main Electrical Service - 2001 to 3000 A 120/208/3PH Electrical Room Serves main and both additions.6EA1 $10,867

PA System Entire Building Serves main, addition 1 and addition 2. Control console is located in addition 1.

6SF55,927 $18,394

Page 17 of 65BOUCHET Assessment Date: 11/24/15

Page 18: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 1

Category: Electrical System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Main Service

Power Distribution

Lighting and Power Panels - 100 A Entire Building / 1st Floor 6EA1 $299

Lighting and Power Panels - 100 A Entire Building / Mechanical Room 6EA1 $299

Lighting and Power Panels - 100 A Entire Building / Mechanical Room 6EA1 $299

Lighting and Power Panels - Above 100 A Entire Building / Electrical Room 6EA1 $497

Lighting and Power Panels - Above 100 A Entire Building / Electrical Room 6EA1 $497

Lighting and Power Panels - Above 100 A Entire Building 6EA4 $1,988

Main Distribution Panels - 400 - 600 amp Entire Building 6EA5 $2,639

Electrical System Subtotal: $127,482

Building: Addition 1

Category: Safty System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Fire Alarm

Fire Alarm Panel Entire Building / Boiler Room Obsolete technology.3EA1 $49,477

Fire Alarm_System Entire Building Obsolete technology. Manual pull stations only. 4SF55,927 $111,166

Sprinkler System

Dry Sprinkler System Entire Building Fire pump located in Main. 6SF55,927 $14,396

Sprinkler Heads Entire Building 7SF55,927 $0

Sprinkler Piping Entire Building 7SF55,927 $0

Safty System Subtotal: $175,038

Building: Addition 1

Category: Mechanical System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Air Handling Systems

Air Handling Unit- Built Up-Multi Zone- Steam Coils - 25001 - 35000 Mechanical Room Serves the main building, addition 2, the gym and

auditorium.

5EA1 $78,608

Air Handling Unit- Built Up-Multi Zone- Steam Coils - 25001 - 35000 Mechanical Room Serves Addition 1. 5EA1 $78,608

Air Intake Mechanical Room / Roof 6EA1 $5,765

Air Intake Mechanical Room / Roof 6EA1 $5,765

Auxiliaries - 25001 - 35000 cfm Mechanical Room 5EA1 $16,577

Auxiliaries - 25001 - 35000 cfm Mechanical Room 5EA1 $16,577

Page 18 of 65BOUCHET Assessment Date: 11/24/15

Page 19: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 1

Category: Mechanical System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Air Handling Systems

Return Duct Work - Indoor- Vertical Shaft and Ducts Mechanical Room / Entire Building 7LF100 $0

Return Duct Work - Indoor- Vertical Shaft and Ducts Mechanical Room / Entire Building 7LF100 $0

Zone Dampers Mechanical Room Actuator pneumatic lines have been cut. All

dampers operated manually.

6EA24 $19,993

Zone Dampers Mechanical Room Actuator pneumatic lines have been cut. All dampers operated manually.

6EA20 $16,661

Boiler Systems

Boiler Auxiliary- Scotch Marine- Steam Low Pressure Boiler - 101 - 150 HP

Boiler Room 5EA1 $12,173

Boiler Auxiliary- Scotch Marine- Steam Low Pressure Boiler - 151 - 200

HP

Boiler Room 5EA1 $17,017

Chemical Feed System Boiler Room / Mechanical Room 6EA1 $1,078

Chemical Feeder Boiler Room / Mechanical Room 6EA1 $1,078

Combustion Dampers Boiler Room 6EA2 $818

Condensate Pump Boiler Room / Mechanical Room 6EA2 $4,042

Feed Water Pumps and Tank Boiler Room / Mechanical Room 4 pumps. 6EA1 $2,545

Non Condensing- Fire Tube- Scotch Marine- Steam- Low Pressure

Boiler - 101 - 150 HP

Boiler Room Serves main and two additions.6EA1 $2,545

Non Condensing- Fire Tube- Scotch Marine- Steam- Low Pressure

Boiler - 151 - 200 HP

Boiler Room Serves main and two additions.6EA1 $2,545

Piping - Condensate Pipe- Steel Boiler Room / Entire Building 6LF1,000 $1,888

Piping - Steam Pipe- Steel Boiler Room / Entire Building 6LF1,000 $1,888

Steam Traps Boiler Room / Entire Building 60' of fintube heaters and (2) AHU's.5EA22 $28,928

Heating Devices

Unit Heater - Gas Boiler Room With an electric wall thermostat. 6EA1 $278

Wall Heater - Electric Entire Building 6EA4 $556

Temperature Control

Electric Thermostat Entire Building Unit heater and electrical room exhaust fan. 6EA2 $0

Pneumatic System Entire Building Most pneumatic lines cut. Thermostats are

damaged or missing. All building is controlled

manually via the boilers. Building gets excessively

hot.

3SF55,927 $291,111

Thermostats - Pneumatic Entire Building Missing cover, internal components exposed. 4EA4 $2,949

Thermostats - Pneumatic Entire Building Thermostat has been removed from wall and

pneumatic lines left exposed.

4EA6 $4,423

Thermostats - Pneumatic Entire Building Thermostats are past useful life and cannot control temperature.

4EA17 $12,533

Page 19 of 65BOUCHET Assessment Date: 11/24/15

Page 20: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 1

Category: Mechanical System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Ventilation

Exhaust Fans- Indoor - 500 - 1500 CFM Entire Building / Electrical Room With electric wall thermostat. 6EA1 $592

Exhaust Fans- Roof Mounted - 1501 - 8000 CFM Entire Building / Roof 6EA1 $592

Exhaust Fans- Roof Mounted - Less than 500 CFM Entire Building / Lower Roof 6EA1 $296

Mechanical System Subtotal: $628,430

Building: Addition 1

Category: Plumbing System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Hot Water

Gas Heater - 150000 - 300000 BTU/HR Boiler Room Serves main and both additions. 7EA1 $0

Piping

Domestic Piping-Cold Water from Risers to Fixtures Entire Building 6SF55,927 $11,197

Domestic Piping-Cold Water Horizontal Lines Entire Building 6SF55,927 $13,596

Domestic Piping-Cold Water Risers Entire Building 6SF55,927 $10,397

Domestic Piping-Hot Water from Risers to Fixtures Entire Building 6SF55,927 $8,797

Domestic Piping-Hot Water Horizontal Lines Entire Building 6SF55,927 $10,397

Domestic Piping-Hot Water Return Lines Entire Building 6SF55,927 $7,998

Domestic Piping-Hot Water Return Risers Entire Building 6SF55,927 $7,998

Sanitary Piping Entire Building 6SF55,927 $51,184

Storm Piping Entire Building 6SF55,927 $48,785

Vent Piping Entire Building 6SF55,927 $37,589

Pumps

Pumps - Sump-Simplex Boiler Room 6EA1 $745

Plumbing System Subtotal: $208,682

Building: Addition 1

Category: Classrooms

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Classroom #106 (Regular Classroom)

Casework 1st Floor 6LF20 $505

Ceiling - Plaster/Drywall 1st Floor 6SF820 $2,838

Ceiling - Plaster/Drywall 1st Floor peeling5SF10 $125

Chalk Board 1st Floor 4LF20 $1,836

Page 20 of 65BOUCHET Assessment Date: 11/24/15

Page 21: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 1

Category: Classrooms

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Classroom #106 (Regular Classroom)

Doors - Transom Window 1st Floor 6SF1 $17

Doors - Wood Doors inclu hw 1st Floor 6EA2 $602

Floor - Tile 1st Floor 6SF830 $1,816

Lighting - Pendent/Surface 1st Floor 7EA14 $0

Marker Board 1st Floor 7LF8 $0

Storage/ Closet 1st Floor peeling5SF61 $984

Walls - Plaster/Drywall 1st Floor 6SF1,355 $3,740

Classroom #109 (Computer Lab)

AC Units 1st Floor improper bracing5EA2 $3,652

Casework 1st Floor 6LF20 $505

Ceiling - Plaster/Drywall 1st Floor 6SF955 $3,305

Chalk Board 1st Floor 4LF16 $1,469

Doors - Steel Doors incl hw 1st Floor 6EA1 $301

Doors - Transom Window 1st Floor 6SF8 $135

Floor - Tile 1st Floor cracked throughout5SF955 $4,288

Lighting - Pendent/Surface 1st Floor 7EA16 $0

Storage/ Closet 1st Floor 6SF72 $522

Walls - Plaster/Drywall 1st Floor 6SF1,355 $3,740

Classroom #110 (Fitness Room)

Casework 1st Floor 6LF9 $227

Ceiling - Plaster/Drywall 1st Floor 6SF826 $2,858

Ceiling - Plaster/Drywall 1st Floor peeling5SF4 $50

Chalk Board 1st Floor 4LF24 $2,203

Doors - Transom Window 1st Floor 6SF1 $17

Doors - Wood Doors inclu hw 1st Floor 6EA1 $301

Floor - Weight/ Fitness Room Floor Matting 1st Floor 6SF830 $4,344

Lighting - Pendent/Surface 1st Floor 7EA14 $0

Storage/ Closet 1st Floor 6SF61 $442

Walls - Plaster/Drywall 1st Floor 6SF1,355 $3,740

Walls - Plaster/Drywall 1st Floor water damaged5SF2 $10

Classroom #206 (Regular Classroom)

Casework 6LF10 $253

Ceiling - Plaster/Drywall need painting5SF830 $7,608

Chalk Board 4LF36 $3,305

Doors - Transom Window 6SF8 $135

Doors - Wood Doors inclu hw 6EA1 $301

Page 21 of 65BOUCHET Assessment Date: 11/24/15

Page 22: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 1

Category: Classrooms

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Classroom #206 (Regular Classroom)

Floor - Tile 6SF826 $1,807

Floor - Tile cracked5SF4 $23

Lighting - Pendent/Surface 7EA14 $0

Storage/ Closet 6SF61 $442

Walls - Plaster/Drywall need painting5SF1,355 $10,270

Classroom #207 (Regular Classroom)

Casework 2nd Floor 6LF10 $253

Ceiling - Plaster/Drywall 2nd Floor needs painting5SF830 $7,608

Chalk Board 2nd Floor 4LF36 $3,305

Doors - Transom Window 2nd Floor 6SF8 $135

Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301

Floor - Tile 2nd Floor 6SF826 $1,807

Floor - Tile 2nd Floor damaged5SF4 $23

Lighting - Pendent/Surface 2nd Floor 7EA14 $0

Storage/ Closet 2nd Floor needs painting5SF61 $984

Walls - Plaster/Drywall 2nd Floor needs painting5SF1,355 $10,270

Classroom #208 (Regular Classroom)

Casework 2nd Floor 6LF10 $253

Ceiling - Plaster/Drywall 2nd Floor 6SF822 $2,845

Ceiling - Plaster/Drywall 2nd Floor peeling5SF8 $100

Chalk Board 2nd Floor 4LF36 $3,305

Doors - Transom Window 2nd Floor 6SF8 $135

Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301

Floor - Tile 2nd Floor 6SF830 $1,816

Lighting - Pendent/Surface 2nd Floor 7EA14 $0

Storage/ Closet 2nd Floor 6SF61 $442

Walls - Plaster/Drywall 2nd Floor need painting5SF1,355 $10,270

Classroom #209 (Regular Classroom)

Casework 2nd Floor 6LF10 $253

Ceiling - Plaster/Drywall 2nd Floor 6SF824 $2,852

Ceiling - Plaster/Drywall 2nd Floor peeling5SF6 $75

Chalk Board 2nd Floor 4LF28 $2,571

Doors - Transom Window 2nd Floor 6SF8 $135

Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301

Floor - Tile 2nd Floor 6SF830 $1,816

Lighting - Pendent/Surface 2nd Floor 7EA14 $0

Page 22 of 65BOUCHET Assessment Date: 11/24/15

Page 23: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 1

Category: Classrooms

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Classroom #209 (Regular Classroom)

Storage/ Closet 2nd Floor 6SF61 $442

Walls - Plaster/Drywall 2nd Floor peeling5SF1,355 $10,270

Classroom #210 (Store Room)

Casework 2nd Floor 6LF10 $253

Ceiling - Plaster/Drywall 2nd Floor peeling5SF830 $7,608

Chalk Board 2nd Floor 6LF36 $803

Doors - Transom Window 2nd Floor 6SF8 $135

Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301

Floor - Tile 2nd Floor chipped throughout5SF830 $3,727

Lighting - Pendent/Surface 2nd Floor 7EA10 $0

Lighting - Pendent/Surface 2nd Floor dont work4EA4 $2,163

Storage/ Closet 2nd Floor 6SF61 $442

Walls - Plaster/Drywall 2nd Floor peeling5SF1,355 $10,270

Classroom #305 (Special Education)

Casework 3rd Floor 6LF10 $253

Ceiling - Plaster/Drywall 3rd Floor 6SF830 $2,872

Chalk Board 3rd Floor 4LF36 $3,305

Doors - Transom Window 3rd Floor 6SF8 $135

Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301

Floor - Tile 3rd Floor 6SF830 $1,816

Lighting - Pendent/Surface 3rd Floor 7EA14 $0

Storage/ Closet 3rd Floor 6SF61 $442

Walls - Plaster/Drywall 3rd Floor 6SF1,355 $3,740

Classroom #306 (Regular Classroom)

Casework 3rd Floor 6LF10 $253

Ceiling - Plaster/Drywall 3rd Floor 6SF830 $2,872

Chalk Board 3rd Floor 4LF18 $1,653

Doors - Transom Window 3rd Floor 6SF8 $135

Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301

Floor - Wood 3rd Floor 6SF830 $5,851

Lighting - Pendent/Surface 3rd Floor 7EA14 $0

Marker Board 3rd Floor 6LF6 $129

Storage/ Closet 3rd Floor peeling5SF61 $984

Walls - Plaster/Drywall 3rd Floor 6SF1,355 $3,740

Page 23 of 65BOUCHET Assessment Date: 11/24/15

Page 24: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 1

Category: Classrooms

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Classroom #307 (Science Classroom)

Casework 3rd Floor 6LF10 $253

Ceiling - Plaster/Drywall 3rd Floor 6SF830 $2,872

Chalk Board 3rd Floor 4LF18 $1,653

Doors - Transom Window 3rd Floor 6SF8 $135

Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301

Floor - Wood 3rd Floor 6SF830 $5,851

Lighting - Pendent/Surface 3rd Floor 7EA14 $0

Storage/ Closet 3rd Floor 6SF61 $442

Walls - Plaster/Drywall 3rd Floor need painting5SF1,355 $10,270

Classroom #308 (Store Room)

Casework 3rd Floor 6LF10 $253

Ceiling - Plaster/Drywall 3rd Floor 6SF830 $2,872

Chalk Board 3rd Floor 4LF36 $3,305

Doors - Transom Window 3rd Floor 6SF8 $135

Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301

Floor - Wood 3rd Floor 6SF830 $5,851

Lighting - Pendent/Surface 3rd Floor 7EA14 $0

Storage/ Closet 3rd Floor 6SF61 $442

Walls - Plaster/Drywall 3rd Floor peeling, need painting5SF1,355 $10,270

Classroom #309 (Regular Classroom)

Casework 3rd Floor 6LF10 $253

Ceiling - Plaster/Drywall 3rd Floor 6SF828 $2,865

Ceiling - Plaster/Drywall 3rd Floor peeling5SF2 $25

Chalk Board 3rd Floor 4LF36 $3,305

Doors - Transom Window 3rd Floor 6SF8 $135

Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301

Floor - Wood 3rd Floor 6SF830 $5,851

Lighting - Pendent/Surface 3rd Floor 7EA14 $0

Storage/ Closet 3rd Floor 6SF61 $442

Walls - Plaster/Drywall 3rd Floor 6SF1,346 $3,715

Walls - Plaster/Drywall 3rd Floor cracked5SF9 $46

Classroom #310 (Special Program)

Casework 3rd Floor 6LF10 $253

Ceiling - Plaster/Drywall 3rd Floor 6SF830 $2,872

Chalk Board 3rd Floor 4LF36 $3,305

Doors - Transom Window 3rd Floor 6SF8 $135

Page 24 of 65BOUCHET Assessment Date: 11/24/15

Page 25: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 1

Category: Classrooms

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Classroom #310 (Special Program)

Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301

Floor - Wood 3rd Floor 6SF830 $5,851

Lighting - Pendent/Surface 3rd Floor 7EA14 $0

Storage/ Closet 3rd Floor peeling5SF61 $984

Walls - Plaster/Drywall 3rd Floor peeling & cracking5SF1,355 $10,270

Classrooms Subtotal: $272,182

Building: Addition 1

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Administrative Suites/Offices

AC Unit 1st Flr- Asst Principal's Office #1 not braced properly5EA1 $1,826

Ceiling - Lay-in 1st Flr- Asst Principal's Office #1 6SF154 $462

Doors - Wood Doors inclu hw 1st Flr- Asst Principal's Office #1 6EA1 $301

Floor - Wood 1st Flr- Asst Principal's Office #1 6SF154 $1,086

Lighting - Lay-in 1st Flr- Asst Principal's Office #1 7EA4 $0

Power Distribution 1st Flr- Asst Principal's Office #1 7EA8 $0

Walls - Plaster/Drywall 1st Flr- Asst Principal's Office #1 6SF450 $1,242

Ceiling - Lay-in 1st Flr- Asst Principal's Office #2 6SF121 $363

Doors - Wood Doors inclu hw 1st Flr- Asst Principal's Office #2 6EA1 $301

Floor - Wood 1st Flr- Asst Principal's Office #2 6SF121 $853

Lighting - Lay-in 1st Flr- Asst Principal's Office #2 7EA4 $0

Power Distribution 1st Flr- Asst Principal's Office #2 7EA8 $0

Walls - Plaster/Drywall 1st Flr- Asst Principal's Office #2 6SF420 $1,159

AC Unit 1st Flr- Principal's Office not braced properly5EA1 $1,826

Ceiling - Lay-in 1st Flr- Principal's Office 6SF162 $486

Doors - Wood Doors inclu hw 1st Flr- Principal's Office 6EA1 $301

Floor - Wood 1st Flr- Principal's Office 6SF162 $1,142

Lighting - Lay-in 1st Flr- Principal's Office 7EA4 $0

Power Distribution 1st Flr- Principal's Office 7EA8 $0

Walls - Plaster/Drywall 1st Flr- Principal's Office 6SF464 $1,281

Ceiling - Lay-in Engineer's Office 6SF291 $874

Doors - Wood Doors inclu hw Engineer's Office 6EA1 $301

Floor - Tile/Sheet Engineer's Office 6SF291 $291

Lighting - Lay-in Engineer's Office 7EA2 $0

Power Distribution Engineer's Office 7EA6 $0

Page 25 of 65BOUCHET Assessment Date: 11/24/15

Page 26: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 1

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Administrative Suites/Offices

Walls - Plaster/Drywall Engineer's Office Walls are covered with wood paneling6SF510 $1,408

AC Unit Rm 105- Main Office improper bracing5EA2 $3,652

Ceiling - Plaster/Drywall Rm 105- Main Office 6SF722 $2,499

Doors - Transom Window Rm 105- Main Office 6SF8 $135

Doors - Wood Doors inclu hw Rm 105- Main Office 6EA3 $903

Floor - Tile Rm 105- Main Office 6SF722 $1,580

Lighting - Pendent/Surface Rm 105- Main Office 7EA18 $0

Power Distribution Rm 105- Main Office 7EA8 $0

Storage/ Closet Rm 105- Main Office 6SF251 $1,820

Walls - Plaster/Drywall Rm 105- Main Office 6SF1,357 $3,745

AC Unit Room 108- Teachers Resource Center not braced properly5EA2 $3,652

Ceiling - Plaster/Drywall Room 108- Teachers Resource Center peeling5SF830 $7,608

Doors - Transom Window Room 108- Teachers Resource Center 6SF8 $135

Doors - Wood Doors inclu hw Room 108- Teachers Resource Center 6EA1 $301

Floor - Tile Room 108- Teachers Resource Center 6SF830 $1,816

Lighting - Pendent/Surface Room 108- Teachers Resource Center 7EA14 $0

Power Distribution Room 108- Teachers Resource Center 7EA23 $0

Walls - Plaster/Drywall Room 108- Teachers Resource Center 6SF1,355 $3,740

Ceiling - Plaster/Drywall Room 205- Nurse/Social Worker/Psychologist

needs painting5SF830 $7,608

Doors - Transom Window Room 205- Nurse/Social

Worker/Psychologist

6SF8 $135

Doors - Wood Doors inclu hw Room 205- Nurse/Social

Worker/Psychologist

6EA1 $301

Floor - Tile Room 205- Nurse/Social Worker/Psychologist

6SF830 $1,816

Lighting - Pendent/Surface Room 205- Nurse/Social Worker/Psychologist

7EA14 $0

Power Distribution Room 205- Nurse/Social Worker/Psychologist

7EA23 $0

Walls - Plaster/Drywall Room 205- Nurse/Social

Worker/Psychologist

needs painting5SF1,355 $10,270

Kitchen

Ceiling - Plaster/Drywall Basement 6SF1,292 $4,471

Doors - Wood Doors inclu hw Basement 6EA2 $602

Floor - Tile Basement 6SF1,292 $2,827

Lighting - Pendent/Surface Basement 7EA27 $0

Storage/ Closet Basement 6SF120 $870

Walls - Masonry Basement 6SF1,566 $4,927

Page 26 of 65BOUCHET Assessment Date: 11/24/15

Page 27: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 1

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Kitchen

Lunch & Multipurpose Room

Ceiling - Plaster/Drywall Basement 6SF18 $62

Doors - Side-lite Basement 6SF16 $267

Doors - Transom Window Basement 6SF8 $135

Doors - Wood Doors inclu hw Basement 6EA1 $301

Floor - Tile Basement 6SF1,140 $2,494

Floor - Tile Basement cracked tile5SF12 $69

Lighting - Pendent/Surface Basement 7EA18 $0

Serving Line Basement 6LF8 $476

Walls - Masonry Basement 6SF1,542 $4,851

MDF_IDF

AC Unit 1st Flr- Inside of Rm 109 improper bracing5EA1 $1,826

Doors - Steel Doors incl hw 1st Flr- Inside of Rm 109 6EA1 $301

Finishes 1st Flr- Inside of Rm 109 old water damage on walls5SF134 $2,163

Mechanical/ Service Rooms

Janitor's Closet 1st Floor 6SF15 $107

Mechanical/ Service Rooms 1st Floor 6SF18 $129

Storage Room 1st Floor 6SF18 $129

Janitor's Closet 2nd Floor 6SF13 $93

Mechanical/ Service Rooms 2nd Floor 6SF18 $129

Storage Room 2nd Floor 6SF18 $129

Janitor's Closet 3rd Floor door needs new hinges6SF13 $93

Mechanical/ Service Rooms 3rd Floor 6SF18 $129

Storage Room 3rd Floor 6SF18 $129

Air Tunnel Basement 6SF310 $1,919

Boiler Room Basement 6SF1,415 $10,137

Coal Room Basement Now Storage space6SF978 $7,007

Mechanical/ Service Rooms Basement 6SF1,454 $10,417

Storage Room Basement 6SF1,681 $12,043

Restroom

Accessories 1st Floor Girl's- Next to 108 6SF303 $2,795

Ceiling - Plaster/Drywall 1st Floor Girl's- Next to 108 6SF303 $1,049

Doors - Transom Window 1st Floor Girl's- Next to 108 6SF16 $271

Doors - Wood Doors inclu hw 1st Floor Girl's- Next to 108 6EA4 $1,204

Floor Drain 1st Floor Girl's- Next to 108 6EA1 $1,059

Page 27 of 65BOUCHET Assessment Date: 11/24/15

Page 28: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 1

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Restroom

Floor - Tile Ceramic/ Porcelain 1st Floor Girl's- Next to 108 6SF303 $641

Lavatory 1st Floor Girl's- Next to 108 6EA2 $639

Lighting - Pendent/Surface 1st Floor Girl's- Next to 108 7EA4 $0

Partitions 1st Floor Girl's- Next to 108 6EA4 $1,188

Walls - Plaster/Drywall 1st Floor Girl's- Next to 108 some FRP behind toilets6SF384 $1,060

Walls - Structural Glazed Tile 1st Floor Girl's- Next to 108 6SF384 $1,208

Water Closet 1st Floor Girl's- Next to 108 6EA5 $1,680

Accessories 2nd Floor Girl's- Next to 208 6SF303 $2,795

Ceiling - Plaster/Drywall 2nd Floor Girl's- Next to 208 6SF303 $1,049

Doors - Transom Window 2nd Floor Girl's- Next to 208 6SF16 $271

Doors - Wood Doors inclu hw 2nd Floor Girl's- Next to 208 6EA4 $1,204

Floor Drain 2nd Floor Girl's- Next to 208 6EA1 $1,059

Floor - Tile Ceramic/ Porcelain 2nd Floor Girl's- Next to 208 6SF303 $641

Lavatory 2nd Floor Girl's- Next to 208 6EA2 $639

Lighting - Pendent/Surface 2nd Floor Girl's- Next to 208 7EA4 $0

Partitions 2nd Floor Girl's- Next to 208 6EA4 $1,188

Walls - Plaster/Drywall 2nd Floor Girl's- Next to 208 some FRP behind toilets6SF384 $1,060

Walls - Structural Glazed Tile 2nd Floor Girl's- Next to 208 6SF384 $1,208

Water Closet 2nd Floor Girl's- Next to 208 6EA5 $1,680

Accessories 3rd Floor Girl's- Next to 308 6SF303 $2,795

Ceiling - Plaster/Drywall 3rd Floor Girl's- Next to 308 6SF303 $1,049

Doors - Transom Window 3rd Floor Girl's- Next to 308 6SF16 $271

Doors - Wood Doors inclu hw 3rd Floor Girl's- Next to 308 6EA4 $1,204

Floor Drain 3rd Floor Girl's- Next to 308 6EA1 $1,059

Floor - Tile Ceramic/ Porcelain 3rd Floor Girl's- Next to 308 6SF303 $641

Lavatory 3rd Floor Girl's- Next to 308 6EA2 $639

Lighting - Pendent/Surface 3rd Floor Girl's- Next to 308 7EA4 $0

Partitions 3rd Floor Girl's- Next to 308 6EA4 $1,188

Walls - Plaster/Drywall 3rd Floor Girl's- Next to 308 some FRP behind toilets6SF384 $1,060

Walls - Structural Glazed Tile 3rd Floor Girl's- Next to 308 6SF384 $1,208

Water Closet 3rd Floor Girl's- Next to 308 6EA5 $1,680

Accessories Engineer's Office 6SF19 $175

Ceiling - Plaster/Drywall Engineer's Office 6SF19 $66

Doors - Wood Doors inclu hw Engineer's Office 6EA1 $301

Floor - Tile/Sheet Engineer's Office 6SF19 $19

Lavatory Engineer's Office 6EA1 $320

Lighting - Wall Mounted Engineer's Office 7EA1 $0

Page 28 of 65BOUCHET Assessment Date: 11/24/15

Page 29: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 1

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Restroom

Showers Engineer's Office 6EA1 $311

Walls - Plaster/Drywall Engineer's Office Walls are covered with wood paneling6SF125 $345

Water Closet Engineer's Office 6EA1 $336

Accessories In Boiler Room 6SF89 $821

Ceiling - Plaster/Drywall In Boiler Room 6SF89 $308

Doors - Wood Doors inclu hw In Boiler Room 6EA1 $301

Floor - Tile/Sheet In Boiler Room 6SF89 $89

Lavatory In Boiler Room 6EA1 $320

Lighting - Pendent/Surface In Boiler Room 7EA1 $0

Walls - Concrete Block In Boiler Room 6SF325 $953

Water Closet In Boiler Room 6EA1 $336

Accessories In Main Office 6SF35 $323

Ceiling - Plaster/Drywall In Main Office 6SF35 $121

Doors - Wood Doors inclu hw In Main Office 6EA1 $301

Floor - Tile Ceramic/ Porcelain In Main Office 6SF35 $74

Lavatory In Main Office 6EA1 $320

Lighting - Pendent/Surface In Main Office 7EA1 $0

Partitions In Main Office 6EA1 $297

Walls - Plaster/Drywall In Main Office FRP on lower 4'6SF125 $345

Water Closet In Main Office 6EA1 $336

Accessories In Room 109 6SF71 $655

Ceiling - Plaster/Drywall In Room 109 peeling5SF71 $651

Doors - Wood Doors inclu hw In Room 109 6EA1 $301

Floor Drain In Room 109 6EA1 $1,059

Floor - Tile In Room 109 6SF71 $155

Lavatory In Room 109 6EA1 $320

Lighting - Pendent/Surface In Room 109 7EA1 $0

Partitions In Room 109 6EA1 $297

Walls - Plaster/Drywall In Room 109 upper walls peeling5SF455 $3,448

Water Closet In Room 109 6EA2 $672

Rooms (Other Than Classrooms) Subtotal: $189,507

Building: Addition 1

Category: Building Interior

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Page 29 of 65BOUCHET Assessment Date: 11/24/15

Page 30: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 1

Category: Building Interior

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Corridor

Ceiling - Plaster/Drywall 1st Floor 6SF2,150 $13,313

Drinking Fountains - Single Fountain 1st Floor 6EA1 $276

Floor - Tile/Sheet 1st Floor 6SF2,150 $1,168

Lighting - Pendent/Surface 1st Floor 7EA8 $0

Walls - Plaster/Drywall 1st Floor 6SF2,940 $13,033

Ceiling - Plaster/Drywall 2nd Floor 6SF2,150 $13,313

Drinking Fountains - Single Fountain 2nd Floor 6EA2 $551

Floor - Tile/Sheet 2nd Floor 6SF2,150 $1,168

Lighting - Pendent/Surface 2nd Floor 7EA8 $0

Walls - Plaster/Drywall 2nd Floor 6SF2,940 $13,033

Ceiling - Plaster/Drywall 3rd Floor 6SF2,150 $13,313

Drinking Fountains - Single Fountain 3rd Floor 6EA2 $551

Floor - Tile/Sheet 3rd Floor 6SF2,150 $1,168

Lighting - Pendent/Surface 3rd Floor 7EA8 $0

Walls - Plaster/Drywall 3rd Floor 6SF2,940 $13,033

Ceiling - Exposed Basement 6SF1,950 $2,900

Ceiling - Plaster/Drywall Basement peeling5SF200 $2,974

Ceiling - Plaster/Drywall Basement 6SF651 $4,031

Doors - Transom Window Basement 6EA34 $576

Doors - Wood Doors include hw Basement 6EA8 $2,408

Drinking Fountains - Single Fountain Basement 6EA2 $551

Floor - Tile Ceramic/ Porcelain Basement damaged5SF10 $209

Floor - Tile Ceramic/ Porcelain Basement 6SF207 $577

Floor - Tile/Sheet Basement 6SF2,584 $1,404

Lighting - Pendent/Surface Basement 7EA11 $0

Lighting - Wall Mounted Basement 7EA3 $0

Walls - Plaster/Drywall Basement peeling5SF300 $3,012

Walls - Plaster/Drywall Basement 6SF3,390 $15,028

Walls - Structural Glazed Tile Basement 6SF360 $1,133

Safety

Camera Viewing Station Principal has viewing access6EA1 $683

Security Cameras 6EA2 $388

Security Cameras 6EA1 $194

Stairs

Ceiling - Plaster/Drywall East 6SF729 $5,337

Floor - Tile East 6SF308 $167

Page 30 of 65BOUCHET Assessment Date: 11/24/15

Page 31: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 1

Category: Building Interior

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Stairs

Floor - Tile East damaged5SF3 $17

Handrails East 6LF212 $1,837

Lighting - Pendent/Surface East 7EA8 $0

Stairs - Asphalt East 5LF60 $2,539

Stairs - Asphalt East asphalt covered in VCT & Metal Treads6LF23 $213

Walls - Plaster/Drywall East 6SF3,671 $10,132

Building Interior Subtotal: $140,231

Total Building Cost $2,420,802

Building: Addition 2

Category: Building Exterior

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Entrance

Entrance Control - Audio and Video Door 4 - West 7EA1 $0

Exterior Doors - Exterior Steel Door Door 4 - West 6EA3 $1,442

Exterior Doors - Exterior Steel Door Door 5 - North 6EA4 $1,922

Exterior Stairs - Concrete Door 4 - West 6LF9 $736

Exterior Stairs - Concrete Door 5 - North 6LF12 $981

Foundation

Foundation - Masonry Entire Building 7LF5,463 $0

Superstructure - Steel with Clay Tile Arch Entire Building 7SF21,852 $0

Roof System

Chimney - Brick Chimney- Concrete/ Mortar Liner Main Roof 6LF3 $2,864

Coping - Clay Tile Main Roof 6LF172 $5,524

Coping - Terra Cotta Main Roof 6LF127 $4,079

Downspouts - Exterior Downspouts Main Roof 6LF3 $100

Downspouts - Exterior Downspouts Main Roof fallen off4LF3 $406

Parapet - 16" - 30" Height Main Roof 6LF127 $5,074

Parapet - Parapet < 16" Height Main Roof 7LF172 $0

Roof Structure - Steel with Clay Tile Arch Main Roof 7SF5,463 $0

Roof - Modified Bitumen Main Roof 5SF5,463 $114,916

Walls

Exterior Walls - Brick Entire Building 6SF8,584 $57,693

Page 31 of 65BOUCHET Assessment Date: 11/24/15

Page 32: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 2

Category: Building Exterior

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Walls

Exterior Walls - Stone-Cast Entire Building 6SF1,032 $6,936

Exterior Walls - Stucco Entire Building 6SF1,376 $6,592

Exterior Walls - Stucco Entire Building / East Façade 6SF500 $2,803

Windows

Guard - Guards wire guard Entire Building 6SF550 $7,023

Lintels - Steel Entire Building 7LF56 $0

Lintels - Stone Entire Building 7LF165 $0

Windows - Sash Aluminum Entire Building 6SF2,365 $17,654

Building Exterior Subtotal: $236,745

Building: Addition 2

Category: Electrical System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Emergency System

Emergency A/C Power - Auditoium and Aisle Lighting Entire Building / Basement 6SF4,821 $2,551

Emergency A/C Power - Corridors and Stairs Entire Building 6SF8,927 $2,681

Emergency A/C Power - Gym Entire Building / 3rd Floor 6SF4,620 $1,718

Emergency Battery Packs - Corridors and Stairs Entire Building (24) exit signs and (4) combination exit

sign/emergency light.

6EA28 $5,670

Exit Signs - Corridors and Stairs Entire Building 6EA28 $4,193

Security System - CCTV Entire Building Exterior cameras only. 6SF21,852 $6,562

Security System - Intrusion Detection Entire Building 6SF21,852 $5,625

Main Service

PA System Entire Building Serves main, addition 1 and addition 2. Control console is located in addition 1.

6SF21,852 $7,187

Power Distribution

Lighting and Power Panels - Above 100 A Entire Building / 1st Floor Fuses, emergency power. 6EA1 $497

Lighting and Power Panels - Above 100 A Entire Building 6EA2 $994

Electrical System Subtotal: $37,677

Building: Addition 2

Category: Safty System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Page 32 of 65BOUCHET Assessment Date: 11/24/15

Page 33: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 2

Category: Safty System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Fire Alarm

Fire Alarm_System Entire Building Obsolete technology. Manual pull stations only.

Panel located in Addition 1.

4SF21,852 $43,435

Sprinkler System

Dry Sprinkler System Entire Building Fire pump located in Main. 6SF21,852 $5,625

Sprinkler Heads Entire Building 7SF21,852 $0

Sprinkler Piping Entire Building 7SF21,852 $0

Safty System Subtotal: $49,060

Building: Addition 2

Category: Mechanical System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Boiler Systems

Piping - Condensate Pipe- Steel Entire Building Boilers located in Addition 1. 6LF100 $189

Piping - Steam Pipe- Steel Entire Building Boilers located in Addition 1.6LF100 $189

Steam Traps Entire Building 5EA12 $15,779

Heating Devices

Fin Tube - Steam Entire Building 6LF60 $566

Wall Heater - Electric Entire Building Missing covers, exposed wires. 4EA2 $2,165

Wall Heater - Electric Entire Building 6EA5 $695

Temperature Control

Pneumatic System Entire Building Most pneumatic lines cut. Thermostats are damaged or missing. All building is controlled manually via the boilers. Building gets excessively hot.

3SF21,852 $113,744

Thermostats - Pneumatic Entire Building Damaged internals and housing. 4EA2 $1,474

Thermostats - Pneumatic Entire Building Thermostats are past useful life and cannot control temperature.

4EA7 $5,161

Ventilation

Exhaust Fans- Roof Mounted - 1501 - 8000 CFM Roof 6EA1 $592

Mechanical System Subtotal: $140,554

Building: Addition 2

Category: Plumbing System

Page 33 of 65BOUCHET Assessment Date: 11/24/15

Page 34: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Category: Plumbing System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Piping

Domestic Piping-Cold Water from Risers to Fixtures Entire Building 6SF21,852 $4,375

Domestic Piping-Cold Water Horizontal Lines Entire Building 6SF21,852 $5,312

Domestic Piping-Cold Water Risers Entire Building 6SF21,852 $4,062

Domestic Piping-Hot Water from Risers to Fixtures Entire Building 6SF21,852 $3,437

Domestic Piping-Hot Water Horizontal Lines Entire Building 6SF21,852 $4,062

Domestic Piping-Hot Water Return Lines Entire Building 6SF21,852 $3,125

Domestic Piping-Hot Water Return Risers Entire Building 6SF21,852 $3,125

Sanitary Piping Entire Building 6SF21,852 $19,999

Storm Piping Entire Building 6SF21,852 $19,061

Vent Piping Entire Building 6SF21,852 $14,687

Plumbing System Subtotal: $81,246

Building: Addition 2

Category: Classrooms

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Classroom #101 (Multi Purpose Room)

AC Units 1st Floor improper bracing, both are old, 1 missing cover4EA2 $12,173

Casework 1st Floor 6LF7 $177

Ceiling - Plaster/Drywall 1st Floor 6SF815 $2,820

Chalk Board 1st Floor 4LF24 $2,203

Doors - Transom Window 1st Floor 6SF7 $119

Doors - Wood Doors inclu hw 1st Floor 6EA1 $301

Floor - Tile 1st Floor 6SF815 $1,783

Lighting - Pendent/Surface 1st Floor 7EA14 $0

Storage/ Closet 1st Floor 6SF61 $442

Walls - Plaster/Drywall 1st Floor 6SF1,340 $3,698

Walls - Plaster/Drywall 1st Floor peeling5SF4 $20

Classroom #102 (Regular Classroom)

Casework 1st Floor 6LF5 $126

Ceiling - Plaster/Drywall 1st Floor peeling 5SF815 $7,471

Chalk Board 1st Floor 4LF22 $2,020

Doors - Transom Window 1st Floor 6SF8 $135

Doors - Wood Doors inclu hw 1st Floor 6EA1 $301

Floor - Tile 1st Floor 6SF815 $1,783

Lighting - Pendent/Surface 1st Floor 7EA14 $0

Storage/ Closet 1st Floor peeling 5SF61 $984

Walls - Plaster/Drywall 1st Floor peeling 5SF1,344 $10,186

Page 34 of 65BOUCHET Assessment Date: 11/24/15

Page 35: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 2

Category: Classrooms

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Classroom #201 (Special Education)

Casework 2nd Floor 6LF5 $126

Ceiling - Plaster/Drywall 2nd Floor 6SF815 $2,820

Chalk Board 2nd Floor 4LF22 $2,020

Doors - Transom Window 2nd Floor 6SF8 $135

Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301

Floor - Tile 2nd Floor 6SF815 $1,783

Lighting - Pendent/Surface 2nd Floor 7EA14 $0

Storage/ Closet 2nd Floor 6SF61 $442

Walls - Plaster/Drywall 2nd Floor lower 5' needs painting5SF1,344 $10,186

Classroom #202 (Regular Classroom)

Casework 2nd Floor 6LF5 $126

Ceiling - Plaster/Drywall 2nd Floor 6SF803 $2,779

Ceiling - Plaster/Drywall 2nd Floor cracked5SF12 $150

Chalk Board 2nd Floor 4LF36 $3,305

Doors - Transom Window 2nd Floor 6SF8 $135

Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301

Floor - Tile 2nd Floor 6SF815 $1,783

Lighting - Pendent/Surface 2nd Floor 7EA14 $0

Marker Board 2nd Floor 7LF36 $0

Storage/ Closet 2nd Floor 6SF61 $442

Walls - Plaster/Drywall 2nd Floor needs painting5SF1,344 $10,186

Classroom #301 (Store Room)

Casework 3rd Floor 6LF5 $126

Ceiling - Plaster/Drywall 3rd Floor 6SF805 $2,786

Ceiling - Plaster/Drywall 3rd Floor peeling5SF10 $125

Chalk Board 3rd Floor 4LF22 $2,020

Doors - Transom Window 3rd Floor 6SF8 $135

Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301

Floor - Tile 3rd Floor 6SF811 $1,774

Floor - Tile 3rd Floor damaged5SF4 $23

Lighting - Pendent/Surface 3rd Floor 7EA14 $0

Storage/ Closet 3rd Floor peeling5SF61 $984

Walls - Plaster/Drywall 3rd Floor peeling5SF1,344 $10,186

Classroom #302 (Art Room)

Casework 3rd Floor 6LF7 $177

Ceiling - Plaster/Drywall 3rd Floor 6SF795 $2,751

Page 35 of 65BOUCHET Assessment Date: 11/24/15

Page 36: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 2

Category: Classrooms

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Classroom #302 (Art Room)

Ceiling - Plaster/Drywall 3rd Floor cracked5SF20 $250

Chalk Board 3rd Floor 4LF22 $2,020

Doors - Transom Window 3rd Floor 6SF8 $135

Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301

Floor - Tile 3rd Floor chipped throughout5SF815 $3,660

Lighting - Pendent/Surface 3rd Floor 7EA14 $0

Storage/ Closet 3rd Floor peeling5SF61 $984

Walls - Plaster/Drywall 3rd Floor 6SF1,344 $3,709

Walls - Plaster/Drywall 3rd Floor cracked5SF6 $31

Classroom #331 (Special Education)

Ceiling - Plaster/Drywall 3rd Floor 6SF521 $1,803

Ceiling - Plaster/Drywall 3rd Floor water damaged5SF10 $125

Chalk Board 3rd Floor 4LF24 $2,203

Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301

Floor - Tile 3rd Floor damaged throughout5SF531 $2,384

Lighting - Pendent/Surface 3rd Floor 7EA7 $0

Storage/ Closet 3rd Floor 6SF100 $725

Walls - Plaster/Drywall 3rd Floor 6SF1,080 $2,981

Walls - Plaster/Drywall 3rd Floor water damaged5SF10 $51

Classrooms Subtotal: $126,817

Building: Addition 2

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Administrative Suites/Offices

Ceiling - Plaster/Drywall Rm 100- Counselors Office peeling5SF46 $575

Ceiling - Plaster/Drywall Rm 100- Counselors Office 6SF426 $1,474

Doors - Side-lite Rm 100- Counselors Office 6SF10 $167

Doors - Transom Window Rm 100- Counselors Office 6SF8 $135

Doors - Wood Doors inclu hw Rm 100- Counselors Office 6EA1 $301

Floor - Tile Rm 100- Counselors Office 6SF462 $1,011

Floor - Tile Rm 100- Counselors Office damaged5SF10 $58

Lighting - Pendent/Surface Rm 100- Counselors Office 7EA3 $0

Lighting - Pendent/Surface Rm 100- Counselors Office cover missing6EA1 $124

Power Distribution Rm 100- Counselors Office 7EA8 $0

Page 36 of 65BOUCHET Assessment Date: 11/24/15

Page 37: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 2

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Administrative Suites/Offices

Storage/ Closet Rm 100- Counselors Office 6SF32 $232

Walls - Plaster/Drywall Rm 100- Counselors Office 6SF1,177 $3,248

Ceiling - Plaster/Drywall Rm 200- Multi Purpose Rm 6SF472 $1,633

Doors - Transom Window Rm 200- Multi Purpose Rm 6SF8 $135

Doors - Wood Doors inclu hw Rm 200- Multi Purpose Rm 6EA1 $301

Floor - Tile Rm 200- Multi Purpose Rm cracked5SF6 $35

Floor - Tile Rm 200- Multi Purpose Rm 6SF466 $1,020

Lighting - Pendent/Surface Rm 200- Multi Purpose Rm 7EA9 $0

Power Distribution Rm 200- Multi Purpose Rm 7EA8 $0

Walls - Plaster/Drywall Rm 200- Multi Purpose Rm 6SF1,177 $3,248

Ceiling - Plaster/Drywall Rm 300- Reading specialist 6SF472 $1,633

Doors - Transom Window Rm 300- Reading specialist 6SF8 $135

Doors - Wood Doors inclu hw Rm 300- Reading specialist 6EA1 $301

Floor - Tile Rm 300- Reading specialist 6SF472 $1,033

Lighting - Pendent/Surface Rm 300- Reading specialist 7EA4 $0

Power Distribution Rm 300- Reading specialist 7EA8 $0

Walls - Plaster/Drywall Rm 300- Reading specialist 6SF1,177 $3,248

Ceiling - Plaster/Drywall Teacher's Lounge in Basement 6SF887 $3,070

Doors - Wood Doors inclu hw Teacher's Lounge in Basement 6EA1 $301

Floor - Tile Teacher's Lounge in Basement Floor needs to be replaced, badly worn and cracked throughout

5SF887 $3,983

Lighting - Pendent/Surface Teacher's Lounge in Basement 7EA4 $0

Power Distribution Teacher's Lounge in Basement 7EA4 $0

Walls - Plaster/Drywall Teacher's Lounge in Basement 6SF1,495 $4,126

Auditorium & Theater

Ceiling - Plaster/Drywall Basement needs painting5SF3,994 $92,525

Doors - Wood Doors inclu hw Basement 6EA10 $3,010

Floor - Wood Basement 6SF3,994 $28,157

Lighting - Pendent/Surface Basement 7EA12 $0

Lighting - Wall Mounted Basement 7EA10 $0

Main Floor Seating Basement 6EA498 $86,610

Sound System Basement 6EA1 $10,721

Stage Basement 6SF650 $3,755

Stage Curtain Basement 6EA4 $0

Stage Lighting System Basement 7EA1 $0

Stage-Stairs - Wood Basement 6LF10 $117

Stairs - Wood Basement 6LF10 $117

Page 37 of 65BOUCHET Assessment Date: 11/24/15

Page 38: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 2

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Auditorium & Theater

Walls - Plaster/Drywall Basement needs painting5SF6,708 $58,034

Gymnasia

Bleacher Seating 2nd Floor 6EA30 $868

Ceiling - Plaster/Drywall 2nd Floor 6SF4,608 $25,435

Ceiling - Plaster/Drywall 2nd Floor damaged5SF12 $240

Doors - Transom Window 2nd Floor 6SF32 $542

Doors - Wood Doors inclu hw 2nd Floor delaminating5EA1 $1,174

Doors - Wood Doors inclu hw 2nd Floor 6EA3 $903

Floor - Sport Flooring 2nd Floor 6SF4,620 $9,976

Lighting - Metal Halide/ High Pressure Sodium 2nd Floor 7EA20 $0

Scoreboards 2nd Floor 6EA2 $4,489

Walls - Plaster/Drywall 2nd Floor damaged5SF40 $204

Walls - Plaster/Drywall 2nd Floor FRP applied to lower portion of wall6SF5,800 $16,007

Mechanical/ Service Rooms

Janitor's Closet 3rd Floor 6SF18 $129

Storage Room Basement includes Storage rm 36SF695 $4,979

Restroom

Accessories 1st Flr Girl's- Across from Gym 6SF220 $2,029

Ceiling - Plaster/Drywall 1st Flr Girl's- Across from Gym 6SF220 $761

Doors - Wood Doors inclu hw 1st Flr Girl's- Across from Gym 6EA4 $1,204

Floor Drain 1st Flr Girl's- Across from Gym 6EA1 $1,059

Floor - Tile 1st Flr Girl's- Across from Gym damaged5SF10 $58

Floor - Tile 1st Flr Girl's- Across from Gym 6SF210 $459

Lavatory 1st Flr Girl's- Across from Gym 6EA2 $639

Lighting - Pendent/Surface 1st Flr Girl's- Across from Gym 7EA4 $0

Partitions 1st Flr Girl's- Across from Gym 6EA6 $1,782

Walls - Plaster/Drywall 1st Flr Girl's- Across from Gym 6SF378 $1,043

Walls - Structural Glazed Tile 1st Flr Girl's- Across from Gym 6SF378 $1,189

Water Closet 1st Flr Girl's- Across from Gym 6EA6 $2,016

Accessories 1st Flr- In Rm 100 6SF31 $286

Ceiling - Plaster/Drywall 1st Flr- In Rm 100 6SF31 $107

Doors - Wood Doors inclu hw 1st Flr- In Rm 100 6EA1 $301

Floor - Tile 1st Flr- In Rm 100 6SF31 $68

Lavatory 1st Flr- In Rm 100 6EA1 $320

Lighting - Pendent/Surface 1st Flr- In Rm 100 7EA1 $0

Partitions 1st Flr- In Rm 100 6EA1 $297

Page 38 of 65BOUCHET Assessment Date: 11/24/15

Page 39: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 2

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Restroom

Walls - Plaster/Drywall 1st Flr- In Rm 100 FRP on lower 3'6SF173 $477

Water Closet 1st Flr- In Rm 100 6EA1 $336

Accessories 1st Flr- Teachers Toilet by 100 6SF59 $544

Ceiling - Plaster/Drywall 1st Flr- Teachers Toilet by 100 6SF59 $204

Doors - Wood Doors inclu hw 1st Flr- Teachers Toilet by 100 6EA1 $301

Floor - Tile 1st Flr- Teachers Toilet by 100 6SF59 $129

Lavatory 1st Flr- Teachers Toilet by 100 6EA1 $320

Lighting - Pendent/Surface 1st Flr- Teachers Toilet by 100 7EA1 $0

Partitions 1st Flr- Teachers Toilet by 100 6EA1 $297

Walls - Plaster/Drywall 1st Flr- Teachers Toilet by 100 6SF390 $1,076

Water Closet 1st Flr- Teachers Toilet by 100 6EA1 $336

Accessories 2nd Flr Girl's- Across from Gym 6SF220 $2,029

Ceiling - Plaster/Drywall 2nd Flr Girl's- Across from Gym 6SF220 $761

Doors - Wood Doors inclu hw 2nd Flr Girl's- Across from Gym 6EA4 $1,204

Floor Drain 2nd Flr Girl's- Across from Gym 6EA1 $1,059

Floor - Tile 2nd Flr Girl's- Across from Gym 6SF220 $481

Lavatory 2nd Flr Girl's- Across from Gym 6EA2 $639

Lighting - Pendent/Surface 2nd Flr Girl's- Across from Gym 7EA4 $0

Partitions 2nd Flr Girl's- Across from Gym 6EA6 $1,782

Walls - Plaster/Drywall 2nd Flr Girl's- Across from Gym 6SF378 $1,043

Walls - Structural Glazed Tile 2nd Flr Girl's- Across from Gym 6SF378 $1,189

Water Closet 2nd Flr Girl's- Across from Gym 6EA6 $2,016

Accessories 2nd Flr- Teachers Toilet Across from Gym

6SF59 $544

Ceiling - Plaster/Drywall 2nd Flr- Teachers Toilet Across from

Gym

6SF34 $118

Ceiling - Plaster/Drywall 2nd Flr- Teachers Toilet Across from Gym

water damaged5SF25 $269

Doors - Wood Doors inclu hw 2nd Flr- Teachers Toilet Across from Gym

6EA1 $301

Floor - Tile 2nd Flr- Teachers Toilet Across from Gym

6SF59 $129

Lavatory 2nd Flr- Teachers Toilet Across from Gym

6EA1 $320

Lighting - Pendent/Surface 2nd Flr- Teachers Toilet Across from

Gym

7EA1 $0

Partitions 2nd Flr- Teachers Toilet Across from Gym

6EA1 $297

Walls - Plaster/Drywall 2nd Flr- Teachers Toilet Across from Gym

6SF385 $1,063

Page 39 of 65BOUCHET Assessment Date: 11/24/15

Page 40: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 2

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Restroom

Walls - Plaster/Drywall 2nd Flr- Teachers Toilet Across from

Gym

water damaged5SF5 $26

Water Closet 2nd Flr- Teachers Toilet Across from Gym

6EA1 $336

Accessories 3rd Flr Girl's- Next to 300 6SF220 $2,029

Ceiling - Plaster/Drywall 3rd Flr Girl's- Next to 300 6SF220 $761

Doors - Wood Doors inclu hw 3rd Flr Girl's- Next to 300 6EA4 $1,204

Floor Drain 3rd Flr Girl's- Next to 300 6EA1 $1,059

Floor - Tile 3rd Flr Girl's- Next to 300 6SF220 $481

Lavatory 3rd Flr Girl's- Next to 300 6EA2 $639

Lighting - Pendent/Surface 3rd Flr Girl's- Next to 300 7EA4 $0

Partitions 3rd Flr Girl's- Next to 300 6EA4 $1,188

Partitions 3rd Flr Girl's- Next to 300 missing doors5EA2 $1,502

Walls - Plaster/Drywall 3rd Flr Girl's- Next to 300 6SF378 $1,043

Walls - Structural Glazed Tile 3rd Flr Girl's- Next to 300 6SF378 $1,189

Water Closet 3rd Flr Girl's- Next to 300 6EA6 $2,016

Accessories 3rd Flr- Teachers Toilet by 300 6SF59 $544

Ceiling - Plaster/Drywall 3rd Flr- Teachers Toilet by 300 6SF59 $204

Doors - Wood Doors inclu hw 3rd Flr- Teachers Toilet by 300 6EA1 $301

Floor - Tile 3rd Flr- Teachers Toilet by 300 6SF51 $112

Floor - Tile 3rd Flr- Teachers Toilet by 300 damaged5SF8 $39

Lavatory 3rd Flr- Teachers Toilet by 300 6EA1 $320

Lighting - Pendent/Surface 3rd Flr- Teachers Toilet by 300 7EA1 $0

Partitions 3rd Flr- Teachers Toilet by 300 6EA1 $297

Walls - Plaster/Drywall 3rd Flr- Teachers Toilet by 300 6SF385 $1,063

Walls - Plaster/Drywall 3rd Flr- Teachers Toilet by 300 peeling5SF5 $26

Water Closet 3rd Flr- Teachers Toilet by 300 6EA1 $336

Accessories Basement Girl's- Across from Auditorium 6SF220 $2,029

Ceiling - Plaster/Drywall Basement Girl's- Across from Auditorium 6SF220 $761

Doors - Wood Doors inclu hw Basement Girl's- Across from Auditorium 6EA4 $1,204

Floor Drain Basement Girl's- Across from Auditorium 6EA1 $1,059

Floor - Tile Ceramic/ Porcelain Basement Girl's- Across from Auditorium 6SF220 $466

Lavatory Basement Girl's- Across from Auditorium 6EA2 $639

Lighting - Pendent/Surface Basement Girl's- Across from Auditorium 7EA4 $0

Partitions Basement Girl's- Across from Auditorium 6EA6 $1,782

Walls - Plaster/Drywall Basement Girl's- Across from Auditorium 6SF378 $1,043

Walls - Structural Glazed Tile Basement Girl's- Across from Auditorium 6SF378 $1,189

Water Closet Basement Girl's- Across from Auditorium 6EA6 $2,016

Page 40 of 65BOUCHET Assessment Date: 11/24/15

Page 41: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 2

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Restroom

Accessories Basement- Teachers Toilet Across from

Auditorium

6SF59 $544

Ceiling - Plaster/Drywall Basement- Teachers Toilet Across from Auditorium

6SF59 $204

Doors - Wood Doors inclu hw Basement- Teachers Toilet Across from Auditorium

6EA1 $301

Floor - Tile Ceramic/ Porcelain Basement- Teachers Toilet Across from Auditorium

6SF59 $125

Lavatory Basement- Teachers Toilet Across from Auditorium

6EA1 $320

Lighting - Pendent/Surface Basement- Teachers Toilet Across from

Auditorium

7EA1 $0

Partitions Basement- Teachers Toilet Across from Auditorium

rusting5EA1 $751

Walls - Plaster/Drywall Basement- Teachers Toilet Across from Auditorium

water damaged5SF10 $51

Walls - Plaster/Drywall Basement- Teachers Toilet Across from Auditorium

6SF380 $1,049

Water Closet Basement- Teachers Toilet Across from Auditorium

6EA1 $336

Rooms (Other Than Classrooms) Subtotal: $444,989

Building: Addition 2

Category: Building Interior

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Corridor

Ceiling - Plaster/Drywall 1st Floor peeling & water damage5SF56 $977

Ceiling - Plaster/Drywall 1st Floor 6SF1,944 $12,037

Drinking Fountains - Single Fountain 1st Floor 6EA2 $551

Floor - Tile/Sheet 1st Floor 6SF2,000 $1,087

Lighting - Pendent/Surface 1st Floor 7EA10 $0

Walls - Plaster/Drywall 1st Floor cracks & water damage5SF25 $251

Walls - Plaster/Drywall 1st Floor 6SF3,446 $15,276

Ceiling - Plaster/Drywall 2nd Floor 6SF1,800 $11,145

Ceiling - Plaster/Drywall 2nd Floor peeling5SF200 $3,489

Drinking Fountains - Single Fountain 2nd Floor 6EA2 $551

Floor - Tile/Sheet 2nd Floor damaged5SF11 $63

Floor - Tile/Sheet 2nd Floor 6SF1,989 $1,081

Lighting - Pendent/Surface 2nd Floor 7EA10 $0

Page 41 of 65BOUCHET Assessment Date: 11/24/15

Page 42: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 2

Category: Building Interior

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Corridor

Walls - Plaster/Drywall 2nd Floor 6SF3,441 $15,254

Walls - Plaster/Drywall 2nd Floor peeling5SF30 $301

Ceiling - Plaster/Drywall 3rd Floor 6SF1,973 $12,217

Ceiling - Plaster/Drywall 3rd Floor damaged5SF27 $471

Drinking Fountains - Single Fountain 3rd Floor 6EA2 $551

Floor - Tile/Sheet 3rd Floor 6SF1,985 $1,079

Floor - Tile/Sheet 3rd Floor damaged5SF15 $86

Lighting - Pendent/Surface 3rd Floor 7EA10 $0

Walls - Plaster/Drywall 3rd Floor 6SF3,456 $15,320

Walls - Plaster/Drywall 3rd Floor damaged5SF15 $151

Ceiling - Exposed Basement 6SF2,000 $2,974

Ceiling - Plaster/Drywall Basement 6SF279 $1,728

Ceiling - Plaster/Drywall Basement water damaged5SF40 $595

Doors - Side-lite Basement 6EA12 $201

Doors - Wood Doors include hw Basement delaminating5EA3 $3,522

Doors - Wood Doors include hw Basement 6EA4 $1,204

Drinking Fountains - Single Fountain Basement 6EA2 $551

Floor - Concrete Basement 6SF159 $84

Floor - Tile Ceramic/ Porcelain Basement 6SF160 $446

Floor - Tile/Sheet Basement 6SF2,000 $1,087

Lighting - Pendent/Surface Basement 7EA14 $0

Walls - Plaster/Drywall Basement 6SF3,471 $15,387

Walls - Structural Glazed Tile Basement 6SF816 $2,567

Safety

Security Cameras 6EA2 $388

Security Cameras 6EA1 $194

Stairs

Ceiling - Plaster/Drywall North 6SF836 $6,121

Ceiling - Plaster/Drywall North water damaged5SF7 $143

Floor - Tile North 6SF607 $330

Floor - Tile North damaged5SF2 $12

Handrails North 6LF212 $1,837

Lighting - Pendent/Surface North 7EA5 $0

Stairs - Asphalt North 5LF60 $2,539

Stairs - Asphalt North asphalt covered in VCT & Metal Treads6LF23 $213

Walls - Plaster/Drywall North 6SF3,671 $10,132

Page 42 of 65BOUCHET Assessment Date: 11/24/15

Page 43: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Addition 2

Category: Building Interior

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Building Interior Subtotal: $144,195

Total Building Cost $1,261,283

Building: Annex

Category: Building Exterior

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Entrance

Entrance Control - Audio and Video Door 1 - East 7EA1 $0

Entrance Control - Audio and Video Door 4 - Northwest 7EA1 $0

Exterior Doors - Exterior Steel Door Door 1 - East 6EA2 $961

Exterior Doors - Exterior Steel Door Door 2 - Southwest 6EA2 $961

Exterior Doors - Exterior Steel Door Door 3 - Northwest kitchen 6EA1 $481

Exterior Doors - Exterior Steel Door Door 4 - Northwest 6EA2 $961

Exterior Doors - Exterior Steel Door Door 4.2 - North 6EA1 $481

Exterior Doors - Exterior Steel Door Door 4.4 - North 6EA1 $481

Exterior Doors - Exterior Steel Door Door 5 - East 6EA2 $961

Exterior Doors - Exterior Steel Door Door 5.5 - Near door 1 6EA1 $481

Exterior Doors - Transom Lite Door 1 - East 7EA1 $0

Exterior Stairs - Concrete Door 2 - Southwest 6LF6 $491

Exterior Stairs - Concrete Door 4 - Northwest 6LF6 $491

Exterior Stairs - Concrete Door 4.2 - North 6LF3 $245

Exterior Stairs - Concrete Door 4.4 - North 6LF3 $245

Exterior Stairs - Concrete Door 5 - East 6LF7 $572

Foundation

Foundation - Concrete Entire Building 7LF586 $0

Superstructure - Concrete Entire Building 7SF40,499 $0

Lighting

Exterior Lighting - Parapet or Roof Mounted Entire Building 6EA9 $4,829

Exterior Lighting - Wall Mounted Entire Building 5EA6 $2,564

Roof System

Coping - Metal Annex roof 1 6LF436 $14,003

Coping - Metal Annex roof 2 6LF271 $8,704

Downspouts - Interior Downspouts Annex roof 1 6LF111 $3,689

Downspouts - Interior Downspouts Annex roof 2 6LF48 $1,595

Page 43 of 65BOUCHET Assessment Date: 11/24/15

Page 44: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Annex

Category: Building Exterior

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Roof System

Roof Structure - Steel / Metal Deck/ Concrete Topping Annex roof 1 7SF10,525 $0

Roof Structure - Steel / Metal Deck/ Concrete Topping Annex roof 2 7SF5,931 $0

Roof - Asphalt Gravel Ballast Annex roof 1 blisters, cracking4SF10,525 $294,995

Roof - Asphalt Gravel Ballast Annex roof 2 Blisters, cracks, ballast raked back4SF5,931 $166,234

Walls

Exterior Walls - Precast Panel Wall Entire Building Failing sealant throughout5SF18,950 $156,900

Exterior Walls - Precast Panel Wall Entire Building / East Façade Cracked, damaged, exposed rebar5SF10 $112

Windows

Curtain wall - Louver Entire Building 6SF230 $2,579

Windows - Casement Lexan Entire Building 6SF875 $6,532

Windows - Decorative Entire Building 6SF1,820 $13,586

Building Exterior Subtotal: $684,132

Building: Annex

Category: Electrical System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Emergency System

Automatic Transfer Switch Electrical Room Nearing end of useful life. 6EA1 $408

Emergency A/C Power - Corridors and Stairs Entire Building 6SF6,003 $1,803

Emergency A/C Power - Gym Entire Building / 1st Floor 6SF2,919 $1,085

Emergency A/C Power - Lunchrooms Entire Building / 1st Floor 6SF1,045 $389

Emergency Battery Packs - Corridors and Stairs Entire Building Emergency light.6EA11 $2,228

Emergency Battery Packs - Corridors and Stairs Entire Building Exit sign.6EA37 $7,493

Emergency Battery Packs - Gym Entire Building / 1st Floor Exit sign.6EA2 $405

Emergency Battery Packs - Gym Entire Building / 1st Floor Emergency light.6EA5 $1,013

Emergency Battery Packs - Lunchrooms Entire Building / 1st Floor Emergency light.6EA3 $608

Emergency Battery Packs - Lunchrooms Entire Building / 1st Floor Exit sign.6EA2 $405

Emergency Battery Packs - Students Toilets Entire Building / 3rd Floor Missing cover and wires are exposed. Emergency light.

4EA1 $579

Emergency Battery Packs - Students Toilets Entire Building Emergency light.6EA5 $1,013

Exit Signs - Corridors and Stairs Entire Building / 1st Floor No battery back-up.2EA3 $1,636

Exit Signs - Corridors and Stairs Entire Building 6EA37 $5,541

Exit Signs - Gym Entire Building / 1st Floor 6EA2 $315

Exit Signs - Lunchroom Entire Building / 1st Floor 6EA2 $299

Security System - Intrusion Detection Entire Building 6SF40,499 $10,424

Page 44 of 65BOUCHET Assessment Date: 11/24/15

Page 45: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Annex

Category: Electrical System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Main Service

Independent Electrical Service for emergency power Electrical Room 6EA1 $2,921

Main Electrical Service - Greater than 3000 A 120/208/3PH Electrical Room 6EA1 $16,381

PA System Entire Building Serves the Annex only. Control console still

functional but needs to be upgrade. Utilizes a

tape deck.

6SF40,499 $13,320

Power Distribution

Lighting and Power Panels - 100 A Entire Building 6EA1 $299

Lighting and Power Panels - 100 A Entire Building 6EA3 $897

Lighting and Power Panels - Above 100 A Entire Building 6EA3 $1,491

Main Distribution Panels - 400 - 600 amp Entire Building 6EA1 $528

Main Distribution Panels - 400 - 600 amp Entire Building 6EA5 $2,639

Main Distribution Panels - Greater than 600 amp Entire Building 6EA1 $730

Electrical System Subtotal: $74,848

Building: Annex

Category: Safty System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Fire Alarm

Fire Alarm Panel Electrical Room Obsolete technology past useful life. 3EA1 $49,477

Fire Alarm_System Electrical Room Obsolete technology past useful life. Manual pull stations only.

4SF40,499 $80,500

Safty System Subtotal: $129,977

Building: Annex

Category: Mechanical System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Air Conditioning

Condensing Unit- Roof Mounted - 11-20 tons Roof / Lower Roof Serves the Lunchroom AHU. 5EA1 $11,065

Condensing Unit- Roof Mounted - 11-20 tons Roof / Lower Roof Serves the Gym AHU. 5EA1 $11,065

Condensing Unit- Roof Mounted - 5-10 tons Roof Hasn't run in 15 years, needs full replacement. Space has been operated without cooling. Serves main office.

2EA1 $14,893

Air Handling Systems

Air Handling Unit- Package Single Zone- Indoor- Electric and DX Cooling Coil - 4000-8000 cfm

Mechanical Room Serves the gym and a computer room. Near or past useful life.

5EA1 $26,442

Page 45 of 65BOUCHET Assessment Date: 11/24/15

Page 46: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Annex

Category: Mechanical System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Air Handling Systems

Air Handling Unit- Package Single Zone- Indoor- Electric and DX

Cooling Coil - Less than 4000 cfm

Mechanical Room Serves the Lunchroom. Unit is near or past useful

life.

5EA1 $20,373

Air Intake Mechanical Room / Roof 7EA1 $0

Air Intake Mechanical Room / Roof 7EA1 $0

Auxiliaries - 4000-8000 cfm Mechanical Room 5EA1 $0

Auxiliaries - Less than 4000 cfm Mechanical Room 5EA1 $0

Fan Coil Unit- Celing Mounted - Electric Main Office Storage Room No nameplate on unit. Refer to condensing unit section for additional information.

6EA1 $820

Heating Devices

Fin Tube - Electric 1st Floor 6LF20 $189

Wall Heater - Electric Entire Building 6EA27 $3,751

Temperature Control

Electric Controls Entire Building 5SF5,202 $0

Electric Thermostat Entire Building 5EA3 $0

Unit Ventilation

Unit Ventilators- Floor Mounted- Electric Heating & DX Cooling Coil W/ Self Contained Compressor

Entire Building / 3rd Floor Past useful life and not operating. With integral thermostats.

2EA2 $45,878

Unit Ventilators- Floor Mounted- Electric Heating & DX Cooling Coil W/ Self Contained Compressor

Entire Building / 3rd Floor Past useful life. Running but missing cover. With integral thermostats.

4EA1 $22,939

Unit Ventilators- Floor Mounted- Electric Heating & DX Cooling Coil W/

Self Contained Compressor

Entire Building With integral thermostats. 6EA24 $29,945

Ventilation

Exhaust Fans- Roof Mounted - 1501 - 8000 CFM Entire Building / Roof 6EA3 $1,777

Exhaust Fans- Roof Mounted - Greater than 8000 CFM Entire Building / Roof 6EA1 $592

Type II Exhaust Hood- Warming Kitchen Entire Building / 1st Floor Diahwasher and warming oven hoods. 6EA2 $1,840

Mechanical System Subtotal: $191,570

Building: Annex

Category: Plumbing System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Hot Water

Electric Heater - 20 - 50 KW Kitchen, Closet 7EA1 $0

Electric Heater - Less than 20 KW Kitchen, Closet Dishwasher booster heater. 6EA1 $682

Page 46 of 65BOUCHET Assessment Date: 11/24/15

Page 47: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Annex

Category: Plumbing System

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Piping

Domestic Piping-Cold Water from Risers to Fixtures Entire Building 6SF40,499 $8,108

Domestic Piping-Cold Water Horizontal Lines Entire Building 6SF40,499 $9,845

Domestic Piping-Cold Water Risers Entire Building 6SF40,499 $7,529

Domestic Piping-Hot Water from Risers to Fixtures Entire Building 6SF40,499 $6,370

Domestic Piping-Hot Water Horizontal Lines Entire Building 6SF40,499 $7,529

Domestic Piping-Hot Water Return Lines Entire Building 6SF40,499 $5,791

Domestic Piping-Hot Water Return Risers Entire Building 6SF40,499 $5,791

Sanitary Piping Entire Building 6SF40,499 $37,065

Storm Piping Entire Building 6SF40,499 $35,327

Vent Piping Entire Building 6SF40,499 $27,219

Plumbing System Subtotal: $151,258

Building: Annex

Category: Classrooms

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Classroom #111 (Regular Classroom)

Ceiling - Lay-in 1st Floor water damage5SF20 $160

Ceiling - Lay-in 1st Floor 6SF300 $901

Chalk Board 1st Floor 4LF8 $734

Doors - Wood Doors inclu hw 1st Floor 6EA1 $301

Floor - Tile 1st Floor cracked and broken tiles5SF12 $69

Floor - Tile 1st Floor 6SF308 $674

Lighting - Lay-in 1st Floor 7EA6 $0

Walls - Metal Panel 1st Floor 6SF475 $3,546

Classroom #112 (Regular Classroom)

Ceiling - Lay-in 1st Floor 6SF900 $2,703

Chalk Board 1st Floor 4LF16 $1,469

Doors - Wood Doors inclu hw 1st Floor 6EA5 $1,505

Floor - Tile 1st Floor 6SF900 $1,969

Lighting - Lay-in 1st Floor 7EA12 $0

Marker Board 1st Floor 6LF10 $214

Storage/ Closet 1st Floor 6SF135 $979

Walls - Metal Panel 1st Floor 6SF1,800 $13,436

Classroom #113 (Kindergarten)

Casework 1st Floor 6LF20 $505

Page 47 of 65BOUCHET Assessment Date: 11/24/15

Page 48: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Annex

Category: Classrooms

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Classroom #113 (Kindergarten)

Ceiling - Lay-in 1st Floor 6SF990 $2,973

Chalk Board 1st Floor 4LF16 $1,469

Doors - Wood Doors inclu hw 1st Floor 6EA1 $301

Floor - Tile 1st Floor 6SF990 $2,166

Lighting - Lay-in 1st Floor 7EA14 $0

Marker Board 1st Floor 7LF8 $0

Walls - Concrete Block 1st Floor 6SF200 $586

Walls - Concrete Block 1st Floor cracked concrete5SF14 $197

Walls - Metal Panel 1st Floor 6SF812 $6,061

Work Sink 1st Floor 6EA1 $379

Classroom #114 (Kindergarten)

Casework 1st Floor 6LF20 $505

Ceiling - Lay-in 1st Floor 6SF990 $2,973

Chalk Board 1st Floor 4LF16 $1,469

Doors - Wood Doors inclu hw 1st Floor 6EA1 $301

Floor - Tile 1st Floor 6SF990 $2,166

Lighting - Lay-in 1st Floor 7EA14 $0

Marker Board 1st Floor 7LF8 $0

Walls - Concrete Block 1st Floor 6SF192 $563

Walls - Concrete Block 1st Floor concrete wall damage5SF8 $113

Walls - Metal Panel 1st Floor 6SF812 $6,061

Work Sink 1st Floor 6EA1 $379

Classroom #115 (Regular Classroom)

Ceiling - Lay-in 1st Floor 6SF704 $2,114

Ceiling - Lay-in 1st Floor water damage5SF6 $48

Chalk Board 1st Floor 4LF16 $1,469

Doors - Wood Doors inclu hw 1st Floor 6EA1 $301

Floor - Tile 1st Floor 6SF710 $1,553

Lighting - Lay-in 1st Floor 7EA10 $0

Walls - Metal Panel 1st Floor 6SF350 $2,613

Walls - Plaster/Drywall 1st Floor cracking and water damage5SF12 $61

Walls - Plaster/Drywall 1st Floor 6SF1,100 $3,036

Classroom #116 (Regular Classroom)

Ceiling - Lay-in 1st Floor 6SF710 $2,132

Chalk Board 1st Floor 4LF16 $1,469

Doors - Wood Doors inclu hw 1st Floor 6EA1 $301

Page 48 of 65BOUCHET Assessment Date: 11/24/15

Page 49: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Annex

Category: Classrooms

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Classroom #116 (Regular Classroom)

Floor - Tile 1st Floor 6SF710 $1,553

Lighting - Lay-in 1st Floor 7EA10 $0

Walls - Metal Panel 1st Floor 6SF350 $2,613

Walls - Plaster/Drywall 1st Floor 6SF1,100 $3,036

Work Sink 1st Floor 6EA1 $379

Classroom #211 (Regular Classroom)

Casework 2nd Floor 6LF20 $505

Ceiling - Lay-in 2nd Floor 6SF710 $2,132

Ceiling - Lay-in 2nd Floor water damage5SF10 $80

Chalk Board 2nd Floor 4LF16 $1,469

Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301

Floor - Tile 2nd Floor 6SF708 $1,549

Floor - Tile 2nd Floor Cracked tiles5SF12 $69

Lighting - Lay-in 2nd Floor 7EA10 $0

Storage/ Closet 2nd Floor 6SF60 $435

Walls - Concrete Block 2nd Floor 6SF104 $305

Walls - Metal Panel 2nd Floor 6SF549 $4,098

Work Sink 2nd Floor 6EA1 $379

Classroom #212 (Store Room)

Casework 2nd Floor 6LF20 $505

Ceiling - Lay-in 2nd Floor 6SF710 $2,132

Ceiling - Lay-in 2nd Floor water damage5SF10 $80

Chalk Board 2nd Floor 4LF16 $1,469

Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301

Floor - Tile 2nd Floor 6SF720 $1,575

Lighting - Lay-in 2nd Floor 7EA10 $0

Walls - Concrete Block 2nd Floor 6SF104 $305

Walls - Metal Panel 2nd Floor 6SF549 $4,098

Classroom #213 (Regular Classroom)

Casework 2nd Floor 6LF20 $505

Ceiling - Lay-in 2nd Floor 6SF720 $2,162

Chalk Board 2nd Floor 4LF32 $2,938

Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301

Floor - Tile 2nd Floor 6SF720 $1,575

Lighting - Lay-in 2nd Floor 7EA10 $0

Walls - Concrete Block 2nd Floor 6SF104 $305

Page 49 of 65BOUCHET Assessment Date: 11/24/15

Page 50: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Annex

Category: Classrooms

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Classroom #213 (Regular Classroom)

Walls - Metal Panel 2nd Floor 6SF549 $4,098

Classroom #214 (Regular Classroom)

Casework 2nd Floor 6LF20 $505

Ceiling - Lay-in 2nd Floor 6SF705 $2,117

Ceiling - Lay-in 2nd Floor water damage5SF15 $120

Chalk Board 2nd Floor 4LF32 $2,938

Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301

Floor - Tile 2nd Floor 6SF720 $1,575

Lighting - Lay-in 2nd Floor 7EA10 $0

Walls - Concrete Block 2nd Floor 6SF104 $305

Walls - Metal Panel 2nd Floor 6SF549 $4,098

Classroom #215 (Regular Classroom)

Casework 2nd Floor 6LF20 $505

Ceiling - Lay-in 2nd Floor 6SF708 $2,126

Ceiling - Lay-in 2nd Floor water damage5SF12 $96

Chalk Board 2nd Floor 4LF16 $1,469

Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301

Floor - Tile 2nd Floor 6SF720 $1,575

Lighting - Lay-in 2nd Floor 7EA10 $0

Walls - Concrete Block 2nd Floor 6SF104 $305

Walls - Metal Panel 2nd Floor 6SF549 $4,098

Work Sink 2nd Floor 6EA1 $379

Classroom #216 (Regular Classroom)

Casework 2nd Floor 6LF20 $505

Ceiling - Lay-in 2nd Floor 6SF1,440 $4,324

Ceiling - Lay-in 2nd Floor water damage5SF12 $96

Chalk Board 2nd Floor 4LF16 $1,469

Doors - Wood Doors inclu hw 2nd Floor 6EA2 $602

Floor - Tile 2nd Floor 6SF1,440 $3,151

Lighting - Lay-in 2nd Floor 7EA20 $0

Walls - Concrete Block 2nd Floor 6SF2,040 $5,980

Walls - Metal Panel 2nd Floor (Folding wall, closed away)6SF549 $4,098

Work Sink 2nd Floor 6EA1 $379

Classroom #218 (Regular Classroom)

Casework 2nd Floor 6LF20 $505

Page 50 of 65BOUCHET Assessment Date: 11/24/15

Page 51: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Annex

Category: Classrooms

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Classroom #218 (Regular Classroom)

Ceiling - Lay-in 2nd Floor 6SF720 $2,162

Chalk Board 2nd Floor 4LF32 $2,938

Doors - Wood Doors inclu hw 2nd Floor 6EA1 $301

Floor - Tile 2nd Floor 6SF708 $1,549

Floor - Tile 2nd Floor cracked tiles5SF12 $69

Lighting - Lay-in 2nd Floor 7EA10 $0

Walls - Concrete Block 2nd Floor 6SF274 $803

Walls - Metal Panel 2nd Floor 6SF379 $2,829

Classroom #312 (Regular Classroom)

Casework 3rd Floor 6LF20 $505

Ceiling - Lay-in 3rd Floor 6SF1,440 $4,324

Chalk Board 3rd Floor 4LF16 $1,469

Doors - Wood Doors inclu hw 3rd Floor 6EA2 $602

Floor - Tile 3rd Floor 6SF1,440 $3,151

Lighting - Lay-in 3rd Floor 7EA20 $0

Walls - Concrete Block 3rd Floor 6SF1,850 $5,423

Walls - Metal Panel 3rd Floor folding partition6SF549 $4,098

Classroom #314 (Regular Classroom)

Casework 3rd Floor 6LF20 $505

Ceiling - Lay-in 3rd Floor 6SF711 $2,135

Ceiling - Lay-in 3rd Floor water damage5SF9 $72

Chalk Board 3rd Floor 4LF32 $2,938

Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301

Floor - Tile 3rd Floor 6SF720 $1,575

Lighting - Lay-in 3rd Floor 7EA10 $0

Walls - Concrete Block 3rd Floor 6SF1,100 $3,225

Walls - Metal Panel 3rd Floor 6SF549 $4,098

Classroom #315 (Regular Classroom)

Casework 3rd Floor 6LF20 $505

Ceiling - Lay-in 3rd Floor 6SF720 $2,162

Chalk Board 3rd Floor 4LF16 $1,469

Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301

Floor - Tile 3rd Floor 6SF720 $1,575

Lighting - Lay-in 3rd Floor 7EA10 $0

Walls - Concrete Block 3rd Floor 6SF104 $305

Walls - Metal Panel 3rd Floor 6SF549 $4,098

Page 51 of 65BOUCHET Assessment Date: 11/24/15

Page 52: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Annex

Category: Classrooms

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Classroom #315 (Regular Classroom)

Work Sink 3rd Floor 6EA1 $379

Classroom #317 (Regular Classroom)

Casework 3rd Floor 6LF20 $505

Ceiling - Lay-in 3rd Floor 6SF1,440 $4,324

Chalk Board 3rd Floor 4LF32 $2,938

Doors - Wood Doors inclu hw 3rd Floor 6EA2 $602

Floor - Tile 3rd Floor 6SF1,440 $3,151

Floor - Tile 3rd Floor cracked tile5SF12 $69

Lighting - Lay-in 3rd Floor 7EA20 $0

Walls - Concrete Block 3rd Floor 6SF1,860 $5,453

Walls - Metal Panel 3rd Floor folding partition 6SF549 $4,098

Work Sink 3rd Floor 6EA1 $379

Classroom #318 (Store Room)

Casework 3rd Floor 6LF20 $505

Ceiling - Lay-in 3rd Floor 6SF720 $2,162

Chalk Board 3rd Floor 4LF16 $1,469

Doors - Wood Doors inclu hw 3rd Floor 6EA1 $301

Floor - Tile 3rd Floor 6SF720 $1,575

Lighting - Lay-in 3rd Floor 7EA10 $0

Storage/ Closet 3rd Floor 6SF97 $703

Walls - Concrete Block 3rd Floor 6SF104 $305

Walls - Metal Panel 3rd Floor 6SF549 $4,098

Classroom #319 (Store Room)

Casework 3rd Floor 6LF20 $505

Ceiling - Lay-in 3rd Floor 6SF720 $2,162

Chalk Board 3rd Floor 4LF16 $1,469

Doors - Wood Doors inclu hw 3rd Floor 6EA2 $602

Floor - Tile 3rd Floor 6SF705 $1,542

Floor - Tile 3rd Floor cracked tiles5SF15 $86

Lighting - Lay-in 3rd Floor 7EA10 $0

Storage/ Closet 3rd Floor 6SF265 $1,921

Walls - Concrete Block 3rd Floor 6SF104 $305

Walls - Metal Panel 3rd Floor 6SF549 $4,098

Classrooms Subtotal: $259,294

Page 52 of 65BOUCHET Assessment Date: 11/24/15

Page 53: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Annex

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Administrative Suites/Offices

Ceiling - Lay-in Assistant Principal's Office in Main

Office

6SF175 $526

Doors - Wood Doors inclu hw Assistant Principal's Office in Main Office

6EA2 $602

Floor - Tile Assistant Principal's Office in Main Office

6SF175 $383

Lighting - Lay-in Assistant Principal's Office in Main Office

7EA2 $0

Power Distribution Assistant Principal's Office in Main Office

7EA6 $0

Storage/ Closet Assistant Principal's Office in Main

Office

6SF10 $73

Walls - Metal Panel Assistant Principal's Office in Main Office

6SF460 $3,434

Walls - Metal Panel Assistant Principal's Office in Main Office

water damage wall5SF10 $400

Ceiling - Lay-in Gym Office 6SF116 $348

Doors - Wood Doors inclu hw Gym Office 6EA1 $301

Floor - Tile/Sheet Gym Office 6SF116 $116

Lighting - Lay-in Gym Office 7EA1 $0

Power Distribution Gym Office 7EA4 $0

Walls - Metal Panel Gym Office 6SF385 $2,874

Ceiling - Lay-in Kitchen Manager Office 6SF72 $216

Doors - Wood Doors inclu hw Kitchen Manager Office 6EA1 $301

Floor - Tile Kitchen Manager Office 6SF72 $158

Lighting - Lay-in Kitchen Manager Office 7EA1 $0

Power Distribution Kitchen Manager Office 7EA4 $0

Walls - Concrete Block Kitchen Manager Office 6SF184 $539

Ceiling - Lay-in Library Office 6SF90 $270

Ceiling - Lay-in Library Office water damage5SF6 $48

Doors - Wood Doors inclu hw Library Office 6EA1 $301

Floor - Carpet Library Office 6SF96 $205

Lighting - Lay-in Library Office 6EA1 $119

Power Distribution Library Office 7EA4 $0

Walls - Metal Panel Library Office 6SF172 $1,284

Ceiling - Lay-in Main Office 6SF518 $1,556

Doors - Wood Doors inclu hw Main Office 6EA2 $602

Floor - Tile Main Office 6SF518 $1,133

Lighting - Lay-in Main Office 7EA10 $0

Power Distribution Main Office 7EA12 $0

Page 53 of 65BOUCHET Assessment Date: 11/24/15

Page 54: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Annex

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Administrative Suites/Offices

Storage/ Closet Main Office 6SF8 $58

Walls - Concrete Block Main Office 6SF354 $1,038

Walls - Plaster/Drywall Main Office 6SF459 $1,267

Ceiling - Lay-in Media Room in Library 6SF773 $2,321

Ceiling - Lay-in Media Room in Library water damage5SF30 $239

Doors - Wood Doors inclu hw Media Room in Library 6EA1 $301

Floor - Tile Media Room in Library 6SF803 $1,757

Lighting - Lay-in Media Room in Library 7EA12 $0

Power Distribution Media Room in Library 7EA44 $0

Walls - Metal Panel Media Room in Library 6SF1,368 $10,212

Ceiling - Lay-in Room 310:Planning Room 6SF395 $1,186

Doors - Wood Doors inclu hw Room 310:Planning Room 6EA1 $301

Floor - Carpet Room 310:Planning Room 6SF395 $842

Lighting - Lay-in Room 310:Planning Room 7EA6 $0

Power Distribution Room 310:Planning Room 7EA16 $0

Walls - Concrete Block Room 310:Planning Room 6SF145 $425

Walls - Metal Panel Room 310:Planning Room 6SF530 $3,956

Ceiling - Lay-in Room 311: Teacher's Lounge 6SF480 $1,441

Doors - Wood Doors inclu hw Room 311: Teacher's Lounge 6EA1 $301

Floor - Tile Room 311: Teacher's Lounge 6SF480 $1,050

Lighting - Lay-in Room 311: Teacher's Lounge 7EA6 $0

Power Distribution Room 311: Teacher's Lounge 7EA8 $0

Walls - Concrete Block Room 311: Teacher's Lounge 6SF94 $276

Walls - Concrete Block Room 311: Teacher's Lounge cracked concrete5SF10 $141

Walls - Metal Panel Room 311: Teacher's Lounge 6SF559 $4,173

Ceiling - Lay-in Teachers Lunch room 6SF71 $213

Doors - Wood Doors inclu hw Teachers Lunch room 6EA2 $602

Floor - Tile Teachers Lunch room 6SF71 $155

Lighting - Lay-in Teachers Lunch room 7EA1 $0

Power Distribution Teachers Lunch room 7EA4 $0

Walls - Metal Panel Teachers Lunch room 6SF245 $1,829

Gymnasia

Ceiling - Lay-in 1st Floor 6SF2,905 $8,724

Ceiling - Lay-in 1st Floor water damage5SF14 $112

Doors - Steel Doors incl hw 1st Floor 6EA8 $2,408

Floor - Tile 1st Floor 6SF2,919 $6,386

Lighting - Pendent/Surface 1st Floor 7EA40 $0

Page 54 of 65BOUCHET Assessment Date: 11/24/15

Page 55: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Annex

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Gymnasia

Storage/ Closet 1st Floor 6SF180 $1,305

Walls - Concrete Block 1st Floor 6SF2,214 $6,490

Walls - Concrete Block 1st Floor cracked concrete5SF12 $169

Walls - Metal Panel 1st Floor 6SF2,226 $16,616

Kitchen

Ceiling - Lay-in 1st Floor 6SF734 $2,204

Doors - Wood Doors inclu hw 1st Floor 6EA3 $903

Floor - Tile 1st Floor 6SF724 $1,584

Floor - Tile 1st Floor cracked tiles5SF10 $58

Lighting - Lay-in 1st Floor 7EA12 $0

Serving Line 1st Floor 6LF20 $1,190

Storage/ Closet 1st Floor 6SF115 $834

Walls - Plaster/Drywall 1st Floor 6SF1,124 $3,102

Library

Ceiling - Lay-in Room 219 6SF2,063 $6,195

Doors - Steel Doors incl hw Room 219 6EA4 $1,204

Floor - Carpet Room 219 6SF2,063 $4,396

Lighting - Lay-in Room 219 7EA28 $0

Walls - Metal Panel Room 219 6SF1,982 $14,795

Locker/Shower Room

Accessories In Kitchen 6SF76 $298

Ceiling - Lay-In In Kitchen 6SF76 $228

Doors - Wood Doors inclu hw In Kitchen 6EA1 $301

Floor - Tile/Sheet In Kitchen 6SF76 $76

Lavatory In Kitchen 6EA1 $320

Lighting - Pendent/Surface In Kitchen 7EA2 $0

Student Lockers - One Tier In Kitchen 6EA5 $464

Walls - Plaster/Drywall In Kitchen 6SF325 $897

Water Closet In Kitchen 6EA2 $672

Lunch & Multipurpose Room

Ceiling - Lay-in 1st Floor 6SF1,045 $3,138

Doors - Steel Doors incl hw 1st Floor 6EA8 $2,408

Floor - Tile 1st Floor 6SF1,015 $2,221

Floor - Tile 1st Floor cracked tile5SF30 $173

Lighting - Lay-in 1st Floor 7EA28 $0

Page 55 of 65BOUCHET Assessment Date: 11/24/15

Page 56: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Annex

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Lunch & Multipurpose Room

Walls - Plaster/Drywall 1st Floor 6SF1,578 $4,355

MDF_IDF

AC Unit 2nd Floor 6EA1 $496

Doors - Steel Doors incl hw 2nd Floor 6EA1 $301

Mechanical/ Service Rooms

Janitor's Closet 1st Floor 6SF66 $473

Mechanical/ Service Rooms 1st Floor Includes Yard Storage6SF190 $1,361

Storage Room 1st Floor 6SF97 $695

Janitor's Closet 2nd Floor 6SF38 $272

Mechanical/ Service Rooms 2nd Floor 6SF1,735 $12,430

Storage Room 2nd Floor 6SF86 $616

Janitor's Closet 3rd Floor 6SF45 $322

Restroom

Accessories 1st Floor Boy's Room 6SF214 $1,974

Ceiling - Lay-in 1st Floor Boy's Room 6SF214 $643

Ceiling - Lay-in 1st Floor Boy's Room water damage5SF10 $80

Doors - Wood Doors inclu hw 1st Floor Boy's Room 6EA4 $1,204

Floor Drain 1st Floor Boy's Room 6EA1 $1,059

Floor - Tile Ceramic/ Porcelain 1st Floor Boy's Room 6SF214 $453

Lavatory 1st Floor Boy's Room 6EA2 $639

Lighting - Lay-in 1st Floor Boy's Room 7EA2 $0

Partitions 1st Floor Boy's Room 6EA2 $594

Urinals 1st Floor Boy's Room 6EA2 $672

Walls - Metal Panel 1st Floor Boy's Room 6SF486 $3,628

Water Closet 1st Floor Boy's Room 6EA2 $672

Accessories 1st Floor Girl's Room 6SF258 $2,380

Ceiling - Lay-in 1st Floor Girl's Room 6SF248 $745

Ceiling - Lay-in 1st Floor Girl's Room water damage5SF10 $80

Doors - Wood Doors inclu hw 1st Floor Girl's Room 6EA4 $1,204

Floor Drain 1st Floor Girl's Room 6EA1 $1,059

Floor - Tile Ceramic/ Porcelain 1st Floor Girl's Room 6SF258 $546

Lavatory 1st Floor Girl's Room 6EA2 $639

Lighting - Lay-in 1st Floor Girl's Room 7EA2 $0

Partitions 1st Floor Girl's Room 6EA4 $1,188

Walls - Metal Panel 1st Floor Girl's Room 6SF532 $3,971

Water Closet 1st Floor Girl's Room 6EA4 $1,344

Page 56 of 65BOUCHET Assessment Date: 11/24/15

Page 57: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Annex

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Restroom

Accessories 1st Floor Men's Room 6SF35 $323

Ceiling - Lay-in 1st Floor Men's Room 6SF35 $105

Doors - Wood Doors inclu hw 1st Floor Men's Room 6EA1 $301

Floor - Tile Ceramic/ Porcelain 1st Floor Men's Room 6SF35 $74

Lavatory 1st Floor Men's Room 6EA1 $320

Lighting - Pendent/Surface 1st Floor Men's Room 6EA1 $124

Walls - Metal Panel 1st Floor Men's Room 6SF145 $1,082

Water Closet 1st Floor Men's Room 6EA1 $336

Accessories 1st Floor Women's Room 6SF35 $323

Ceiling - Lay-in 1st Floor Women's Room 6SF35 $105

Doors - Wood Doors inclu hw 1st Floor Women's Room 6EA1 $301

Floor - Tile Ceramic/ Porcelain 1st Floor Women's Room 6SF35 $74

Lavatory 1st Floor Women's Room 6EA1 $320

Lighting - Pendent/Surface 1st Floor Women's Room 7EA1 $0

Walls - Metal Panel 1st Floor Women's Room 6SF240 $1,792

Water Closet 1st Floor Women's Room 6EA1 $336

Accessories 2nd Floor Boy's Room 6SF214 $1,974

Ceiling - Lay-in 2nd Floor Boy's Room 6SF198 $595

Ceiling - Lay-in 2nd Floor Boy's Room water damage5SF16 $128

Doors - Wood Doors inclu hw 2nd Floor Boy's Room 6EA4 $1,204

Floor Drain 2nd Floor Boy's Room 6EA1 $1,059

Floor - Tile Ceramic/ Porcelain 2nd Floor Boy's Room 6SF214 $453

Lavatory 2nd Floor Boy's Room 6EA2 $639

Lighting - Lay-in 2nd Floor Boy's Room 6EA214 $25,461

Partitions 2nd Floor Boy's Room 6EA2 $594

Urinals 2nd Floor Boy's Room 6EA2 $672

Walls - Metal Panel 2nd Floor Boy's Room 6SF486 $3,628

Water Closet 2nd Floor Boy's Room 6EA2 $672

Accessories 2nd Floor Girl's Room 6SF258 $2,380

Ceiling - Lay-in 2nd Floor Girl's Room 6SF258 $775

Doors - Wood Doors inclu hw 2nd Floor Girl's Room 6EA4 $1,204

Floor Drain 2nd Floor Girl's Room 6EA1 $1,059

Floor - Tile Ceramic/ Porcelain 2nd Floor Girl's Room 6SF250 $529

Floor - Tile Ceramic/ Porcelain 2nd Floor Girl's Room cracked tile5SF8 $167

Lavatory 2nd Floor Girl's Room 6EA2 $639

Lighting - Lay-in 2nd Floor Girl's Room 6EA2 $238

Partitions 2nd Floor Girl's Room 6EA4 $1,188

Page 57 of 65BOUCHET Assessment Date: 11/24/15

Page 58: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Annex

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Restroom

Walls - Metal Panel 2nd Floor Girl's Room 6SF532 $3,971

Walls - Metal Panel 2nd Floor Girl's Room water damage5SF16 $639

Water Closet 2nd Floor Girl's Room 6EA4 $1,344

Accessories 2nd Floor Men's Room 6SF35 $323

Ceiling - Lay-in 2nd Floor Men's Room 6SF35 $105

Doors - Wood Doors inclu hw 2nd Floor Men's Room 6EA1 $301

Floor - Tile Ceramic/ Porcelain 2nd Floor Men's Room 6SF35 $74

Lavatory 2nd Floor Men's Room 6EA1 $320

Lighting - Pendent/Surface 2nd Floor Men's Room 7EA1 $0

Walls - Metal Panel 2nd Floor Men's Room 6SF240 $1,792

Water Closet 2nd Floor Men's Room 6EA1 $336

Accessories 2nd Floor Women's Room 6SF35 $323

Ceiling - Lay-in 2nd Floor Women's Room 6SF29 $87

Ceiling - Lay-in 2nd Floor Women's Room water damage5SF6 $42

Doors - Wood Doors inclu hw 2nd Floor Women's Room 6EA1 $301

Floor - Tile Ceramic/ Porcelain 2nd Floor Women's Room 6SF29 $61

Floor - Tile Ceramic/ Porcelain 2nd Floor Women's Room broken tile5SF6 $111

Lavatory 2nd Floor Women's Room 6EA1 $320

Lighting - Pendent/Surface 2nd Floor Women's Room 7EA1 $0

Walls - Plaster/Drywall 2nd Floor Women's Room 6SF240 $662

Water Closet 2nd Floor Women's Room 6EA1 $336

Accessories 3rd Floor Boy's Room 6SF214 $1,974

Ceiling - Lay-in 3rd Floor Boy's Room 6SF214 $643

Doors - Wood Doors inclu hw 3rd Floor Boy's Room 6EA4 $1,204

Floor Drain 3rd Floor Boy's Room 6EA1 $1,059

Floor - Tile Ceramic/ Porcelain 3rd Floor Boy's Room 6SF214 $453

Lavatory 3rd Floor Boy's Room 6EA2 $639

Lighting - Lay-in 3rd Floor Boy's Room 6EA2 $238

Partitions 3rd Floor Boy's Room 6EA2 $594

Urinals 3rd Floor Boy's Room 6EA2 $672

Walls - Metal Panel 3rd Floor Boy's Room 6SF480 $3,583

Walls - Metal Panel 3rd Floor Boy's Room water damage5SF6 $240

Water Closet 3rd Floor Boy's Room 6EA2 $672

Accessories 3rd Floor Girl's Room 6SF258 $2,380

Ceiling - Lay-in 3rd Floor Girl's Room 6SF258 $775

Doors - Wood Doors inclu hw 3rd Floor Girl's Room 6EA4 $1,204

Floor Drain 3rd Floor Girl's Room 6EA1 $1,059

Page 58 of 65BOUCHET Assessment Date: 11/24/15

Page 59: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Annex

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Restroom

Floor - Tile Ceramic/ Porcelain 3rd Floor Girl's Room 6SF258 $546

Lavatory 3rd Floor Girl's Room 6EA2 $639

Lighting - Lay-in 3rd Floor Girl's Room 7EA2 $0

Partitions 3rd Floor Girl's Room 6EA4 $1,188

Walls - Metal Panel 3rd Floor Girl's Room 6SF516 $3,852

Walls - Metal Panel 3rd Floor Girl's Room dented, damaged walls5SF14 $559

Water Closet 3rd Floor Girl's Room 6EA4 $1,344

Accessories 3rd Floor Men's Room 6SF35 $323

Ceiling - Lay-in 3rd Floor Men's Room 6SF35 $105

Doors - Wood Doors inclu hw 3rd Floor Men's Room 6EA1 $301

Floor - Tile Ceramic/ Porcelain 3rd Floor Men's Room 6SF35 $74

Lavatory 3rd Floor Men's Room 6EA1 $320

Lighting - Pendent/Surface 3rd Floor Men's Room 6EA1 $124

Walls - Metal Panel 3rd Floor Men's Room 6SF240 $1,792

Water Closet 3rd Floor Men's Room 6EA1 $336

Accessories 3rd Floor Women's Room 6SF35 $323

Ceiling - Lay-in 3rd Floor Women's Room 6SF35 $105

Doors - Wood Doors inclu hw 3rd Floor Women's Room 6EA1 $301

Floor - Tile Ceramic/ Porcelain 3rd Floor Women's Room 6SF35 $74

Lavatory 3rd Floor Women's Room 6EA1 $320

Lighting - Pendent/Surface 3rd Floor Women's Room 7EA1 $0

Walls - Metal Panel 3rd Floor Women's Room 6SF240 $1,792

Water Closet 3rd Floor Women's Room 6EA1 $336

Accessories In Main Office 6SF27 $249

Ceiling - Lay-in In Main Office 6SF27 $81

Doors - Wood Doors inclu hw In Main Office 6EA1 $301

Floor - Tile Ceramic/ Porcelain In Main Office 6SF27 $57

Lavatory In Main Office 6EA1 $320

Lighting - Pendent/Surface In Main Office 7EA1 $0

Walls - Metal Panel In Main Office 6SF200 $1,493

Water Closet In Main Office 6EA1 $336

Accessories In Mechanical space 6SF22 $203

Ceiling - Lay-in In Mechanical space 6SF22 $66

Doors - Wood Doors inclu hw In Mechanical space 6EA1 $301

Floor - Tile Ceramic/ Porcelain In Mechanical space 6SF22 $47

Lavatory In Mechanical space 6EA1 $320

Lighting - Lay-in In Mechanical space 7EA1 $0

Page 59 of 65BOUCHET Assessment Date: 11/24/15

Page 60: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Annex

Category: Rooms (Other Than Classrooms)

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Restroom

Walls - Metal Panel In Mechanical space 6SF185 $1,381

Water Closet In Mechanical space 6EA1 $336

Accessories In Room 113 6SF30 $277

Ceiling - Lay-in In Room 113 6SF30 $90

Doors - Wood Doors inclu hw In Room 113 6EA1 $301

Floor - Tile Ceramic/ Porcelain In Room 113 6SF30 $63

Lavatory In Room 113 6EA1 $320

Lighting - Pendent/Surface In Room 113 7EA1 $0

Walls - Metal Panel In Room 113 6SF200 $1,493

Water Closet In Room 113 6EA1 $336

Accessories In Room 114 6SF30 $277

Ceiling - Lay-in In Room 114 6SF30 $90

Doors - Wood Doors inclu hw In Room 114 6EA1 $301

Floor - Tile Ceramic/ Porcelain In Room 114 6SF30 $63

Lavatory In Room 114 6EA1 $320

Lighting - Pendent/Surface In Room 114 6EA1 $124

Walls - Metal Panel In Room 114 6SF200 $1,493

Water Closet In Room 114 6EA1 $336

Rooms (Other Than Classrooms) Subtotal: $291,966

Building: Annex

Category: Building Interior

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Corridor

Ceiling - Lay-in 1st Floor 6SF2,067 $6,207

Ceiling - Lay-in 1st Floor water damage5SF30 $268

Doors - Steel Doors incl hw 1st Floor 6EA2 $602

Drinking Fountains - Double Fountain 1st Floor 6EA1 $336

Floor - Tile/Sheet 1st Floor 6SF2,065 $1,122

Floor - Tile/Sheet 1st Floor cracking5SF32 $184

Lighting - Lay-in 1st Floor 7EA6 $0

Walls - Plaster/Drywall 1st Floor 6SF2,588 $11,473

Walls - Plaster/Drywall 1st Floor water damage5SF12 $120

Ceiling - Lay-in 2nd Floor 6SF2,248 $6,751

Drinking Fountains - Double Fountain 2nd Floor 6EA1 $336

Floor - Tile/Sheet 2nd Floor cracked tile5SF24 $138

Page 60 of 65BOUCHET Assessment Date: 11/24/15

Page 61: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Building: Annex

Category: Building Interior

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Corridor

Floor - Tile/Sheet 2nd Floor 6SF2,224 $1,209

Lighting - Lay-in 2nd Floor 7EA6 $0

Walls - Plaster/Drywall 2nd Floor 6SF2,782 $12,333

Walls - Plaster/Drywall 2nd Floor water damage5SF18 $181

Ceiling - Lay-in 3rd Floor 6SF1,400 $4,204

Drinking Fountains - Double Fountain 3rd Floor 6EA1 $336

Floor - Tile/Sheet 3rd Floor 6SF1,400 $761

Lighting - Lay-in 3rd Floor 7EA6 $0

Walls - Plaster/Drywall 3rd Floor 6SF1,824 $8,086

Stairs

Ceiling - Lay-in East Stairwell 6SF327 $982

Ceiling - Lay-in East Stairwell water damage5SF12 $107

Floor - Terrazzo East Stairwell 6SF156 $1,309

Handrails East Stairwell 6LF80 $693

Lighting - Lay-in East Stairwell 7EA3 $0

Stairs - Terrazzo East Stairwell 6LF40 $371

Walls - Plaster/Drywall East Stairwell 6SF2,100 $5,796

Ceiling - Lay-in North Stairwell water damage5SF6 $54

Ceiling - Lay-in North Stairwell 6SF250 $751

Floor - Tile North Stairwell 6SF102 $55

Handrails North Stairwell 6LF60 $520

Lighting - Lay-in North Stairwell 6EA3 $357

Stairs - Terrazzo North Stairwell 6LF30 $278

Walls - Metal Panel North Stairwell dented walls5SF30 $1,199

Walls - Metal Panel North Stairwell 6SF1,856 $13,854

Building Interior Subtotal: $80,973

Total Building Cost $1,864,017

SITE

Category: Site

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Civil/Drainage

Civil/ Drainage - Catch Basin Entire Site 7EA11 $0

Civil/ Drainage - Site Manhole Entire Site 7EA7 $0

Page 61 of 65BOUCHET Assessment Date: 11/24/15

Page 62: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

SITE

Category: Site

Item - Type Quantity Unit Rank Cost LocationGroup Comments

Civil/Drainage

Fencing

Fencing - Chain Link Entire Site 6LF1,471 $27,619

Fencing - New Standard Ornamental Entire Site 7LF442 $0

Landscape

Benches Entire Site 6EA7 $3,010

Parkway trees Entire Site 7EA18 $0

Planting Beds/ Area Entire Site 7SF1,458 $0

Play Area - Asphalt/ Hardscape Entire Site Wear and tear5SF14,000 $63,864

Play Area - Asphalt/ Hardscape Entire Site cracks and ponding4SF1,552 $16,445

Retaining Wall - Masonry Entire Site 7SF315 $0

Trash Receptacles Entire Site 7EA2 $0

Parking Lot

Concrete Curbs Entire Site 5LF128 $3,361

Surface - Asphalt Entire Site cracks and ponding5SF62,147 $283,496

Surface - Concrete Entire Site cracks and ponding5SF2,133 $19,948

Trash Compactor Entire Site 6EA1 $0

Vehicular Screening Entire Site 7LF128 $0

Playground

Equipment - Combo 3-12 NE site 5EA1 $95,838

Surface - Wood Chips NE site 5SF4,332 $16,292

Sidewalks

Sidewalks - Internal Walks Entire Site 6LF676 $8,120

Sidewalks - Perimeter Sidewalks Entire Site 6SF13,819 $27,468

Signage

Flag Pole - Flag Pole Entire Site 6EA2 $3,314

Marquee - Free Standing Back Lighted Entire Site 6EA1 $0

Site Subtotal: $568,776

Total Site Cost $568,776

Campus Total ² ³ $7,065,129

Page 62 of 65BOUCHET Assessment Date: 11/24/15

Page 63: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

² As stated above, Total Assessed Campus Need does not include the addition of features not already in a particular facility, such as programmatic improvements, school-wide ADA compliance, air conditioning, space reconfiguration or construction to alleviate overcrowding; these items are treated as separate capital needs. The Total Assessed Campus Need includes current deficiencies and is based on current unit cost estimates;

it does not reflect a complete project cost.

³ The overall condition of different items can change after an assessment date due to many variables, including newly occurring deficiencies, renovation or repairs and cost changes. These dollar figures in this report are

estimates only and are based solely on the data that was collected as of the assessment date in the footer below.

¹ It is very rare for assessors to find a feature in this condition. If assessors do, they are required to report it immediately to CPS, and CPS addresses it immediately. Thus, no features will be ranked “1” in this report;

by the time the report is compiled, they have been resolved.

Definitions

● Quantity

● Unit

means a basic estimate for each item needing some level of repair or replacement. Cost does not include all expenses that would be necessary to complete a repair or replacement project. This is because,

depending on the item and on the overall scope of a construction project, repair/replacement projects can include additional costs such as destructive testing, environmental needs, discovered conditions, and

additional work triggered by building codes.

means, for each item, the total number (or amount) of that item that exists and was evaluated.

means the generally accepted standard unit of measure for each item. Some items, like doors, are measured individually and use the unit of measurement “EA” for “each.” Other items, like

chimneys, are measured in terms of linear feet (“LF”). Still other items, like flooring, are generally measured in square feet (“SF”).

● Cost

● For the same reason, the Total Campus Need listed at the end of this report reflects only a portion of what it would actually cost to repair/replace all of the listed features.

● Campus Total also does not reflect features that do not yet exist at a particular facility, such as: programmatic improvements, school-wide ADA compliance, air conditioning, space reconfiguration, or construction to

alleviate overcrowding; these are viewed as separate capital needs.

Page 63 of 65BOUCHET Assessment Date: 11/24/15

Page 64: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Classroom Summary

Smart-

Board

Power

Strip

Window

Stop

Operable

Window

Area

Glazed

Window

Area

Noise

Level

Elect.

Outlets

Data

Outlets

Voice

Outlets

Area (SF)Floor Plan

Room

Number

Room

Number

Intended UsageCurrent Usage Room

Location

Main

NNN40801802381869103103Regular ClassroomRegular Classroom 1st Floor

NNN40801802381869104104Regular ClassroomRegular Classroom 1st Floor

NNN40801802381869303303Regular ClassroomRegular Classroom 3rd Floor

NNN40801802381869304304Art RoomRegular Classroom 3rd Floor

NNN40801802381869203203Regular ClassroomSpecial Education 2nd Floor

CPC

NNN4040100820580103103Pre SchoolPre School 1st Floor

NNN4040100820580104104Pre SchoolPre School 1st Floor

NNN40641608201,120105135Pre SchoolPre School 1st Floor

NNN40641608201,120106136Pre SchoolPre School 1st Floor

Addition 1

YNN408018064531955109109KindergartenComputer Lab 1st Floor

NNN40801802381830110110Regular ClassroomFitness Room 1st Floor

NNN40801802381830106106Regular ClassroomRegular Classroom 1st Floor

NNN40801802381830206206Regular ClassroomRegular Classroom

NNN40801802381830207207Regular ClassroomRegular Classroom 2nd Floor

NNN40801802381830208208Regular ClassroomRegular Classroom 2nd Floor

NNN40801802381830209209Regular ClassroomRegular Classroom 2nd Floor

NNN40801802381830306306Regular ClassroomRegular Classroom 3rd Floor

NNN40801802381830309309Regular ClassroomRegular Classroom 3rd Floor

NNN40801802381830307307Regular ClassroomScience Classroom 3rd Floor

NNN40801802381830305305Regular ClassroomSpecial Education 3rd Floor

NNN40801802381830310310Regular ClassroomSpecial Program 3rd Floor

NNN40801802381830210210Regular ClassroomStore Room 2nd Floor

NNN40801802381830308308Regular ClassroomStore Room 3rd Floor

Addition 2

NNN40801802381815302302Regular ClassroomArt Room 3rd Floor

NNN40801802381815101101Regular ClassroomMulti Purpose Room 1st Floor

NNN40801802381815102102Regular ClassroomRegular Classroom 1st Floor

NNN40801802381815202202Regular ClassroomRegular Classroom 2nd Floor

NNN40801802381815201201Regular ClassroomSpecial Education 2nd Floor

NNN403264601531311331OfficeSpecial Education 3rd Floor

NNN40801802381815301301Regular ClassroomStore Room 3rd Floor

Page 64 of 65BOUCHET Assessment Date: 11/24/15

Page 65: Edward A Bouchet Math & Science Academy ESschoolreports.cps.edu/Assessment_PDF_Detail_2015/2430D.pdf · 2016-03-09 · Edward A Bouchet Math & Science Academy ES 7355 S Jeffery Blvd

Edward A Bouchet Math & Science Academy ES7355 S Jeffery Blvd Chicago, IL 60649

Classroom Summary

Smart-

Board

Power

Strip

Window

Stop

Operable

Window

Area

Glazed

Window

Area

Noise

Level

Elect.

Outlets

Data

Outlets

Voice

Outlets

Area (SF)Floor Plan

Room

Number

Room

Number

Intended UsageCurrent Usage Room

Location

Annex

NYN400105800990108113KindergartenKindergarten 1st Floor

NYN400105800990110114KindergartenKindergarten 1st Floor

NNN40060811320Teachers Lounge111OfficeRegular Classroom 1st Floor

NNN400801001900104112Regular ClassroomRegular Classroom 1st Floor

NYN40052801710109115Regular ClassroomRegular Classroom 1st Floor

NYN40052801710107116Regular ClassroomRegular Classroom 1st Floor

NYN400105800720204211Regular ClassroomRegular Classroom 2nd Floor

NYN400105800720208213Regular ClassroomRegular Classroom 2nd Floor

NYN400105800720210214Regular ClassroomRegular Classroom 2nd Floor

NYN400105800720209215Regular ClassroomRegular Classroom 2nd Floor

NYN4001058001,440207216Regular ClassroomRegular Classroom 2nd Floor

NYN400105800720200218Regular ClassroomRegular Classroom 2nd Floor

NYN4001058001,440306312Regular ClassroomRegular Classroom 3rd Floor

NYN400105800720310314Regular ClassroomRegular Classroom 3rd Floor

NYN400105800720309315Regular ClassroomRegular Classroom 3rd Floor

NYN4001058001,440305317Regular ClassroomRegular Classroom 3rd Floor

NYN400105800720206212Regular ClassroomStore Room 2nd Floor

NYN400105800720303318Regular ClassroomStore Room 3rd Floor

NYN400105800720302319Regular ClassroomStore Room 3rd Floor

Page 65 of 65BOUCHET Assessment Date: 11/24/15