Ed Williams, PMP Director of Post Delivery Support
description
Transcript of Ed Williams, PMP Director of Post Delivery Support
![Page 1: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/1.jpg)
Ed Williams, PMPDirector of Post Delivery Support
Project Management in the Shipbuilding Industry
![Page 2: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/2.jpg)
Agenda
NeeAustal USA History
• The Beginning• Austal Today• Expansion
Contracts• LCS• JHSV
Program Management Processes & Tools • Initiating• Planning • Executing• Monitoring and Controlling• Closing
![Page 3: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/3.jpg)
1998
Austal USA - The Beginning
2004
Land total- 10 acres Manufacturing Space- 45,000 sq ft
![Page 4: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/4.jpg)
Austal USA - The Beginning
2007
2010
Land total- 11 acres Manufacturing Space- 153,000 sq ft
Land total- 115 acres Manufacturing Space- 503,000 sq ft
![Page 5: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/5.jpg)
Land total- 164 acres Manufacturing Space- 962,000 sq ft
Austal USA - Today
![Page 6: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/6.jpg)
Expansion - Vessel Completion Yard
![Page 7: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/7.jpg)
Joint High Speed Vessel (JHSV)
![Page 8: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/8.jpg)
Littoral Combat Ship (LCS)
![Page 9: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/9.jpg)
Shipbuilding at AUSA
• Portfolio• Government Contracts
• Program• JHSV• LCS• Post Delivery
• Projects• Individual hulls
• JHSV 1-10• LCS 2,4,6-24• IPDA, PSAs and IDIQ contracts
![Page 10: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/10.jpg)
Initiating
• Identify Key Stakeholders• ASN, CNO, Warfighter
• Competitive Bids• Contract Negotiation• Ship Construction contracts
• Firm Fixed Price• Block Buy
![Page 11: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/11.jpg)
Planning
• Determine Scope• Create WBS• Estimate Costs• Estimate Durations• Develop Schedule
• Primavera P6• Logic Links• LLTM• Milestones
![Page 12: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/12.jpg)
Planning
![Page 13: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/13.jpg)
Planning
![Page 14: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/14.jpg)
Executing
• Conduct Procurements• GFI• Major Subcontractor
• GDAIS Mission Systems• Execute Work Packages
• Fabrication, Machinery, Electrical, Pipe, Fitout
• Distribute Information• SPPC- Ship’s Production Performance
Conference
![Page 15: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/15.jpg)
Executing-Modular Manufacturing
![Page 16: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/16.jpg)
Monitoring & Controlling
• Earned Value Management• CPRs required on DoD contracts >$20M
• Quality Control• ABS Survey Requirements
• Accuracy Control• i.e. Module erection
• Change Control • CCB held in Washington, D.C.
![Page 17: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/17.jpg)
Monitoring & Controlling
≥ $50M REQUIREDIncludes: Contracts for highly classified, foreign, and in-house programs. o Must use ANSI/EIA-748 compliant and validated management
system. o CPR (all formats) is required.o Integrated Master Schedule is required.o Schedule Risk Assessment (SRA) is required
Not required for: Firm-fixed price contracts. (Business case analysis and MDA approval required.)
Not recommended for: Contracts less than 12 months in duration.
May not be appropriate for: Non-schedule based contract efforts, e.g., level of effort.
≥ $20M but < $50M REQUIREDIncludes: Contracts for highly classified, foreign, and in-house programs.
o Must use ANSI/EIA-748 compliant management system. No validation.
o CPR Formats 1 and 5 are required.o Integrated Master Schedule is required.
Not required for: Firm-fixed price contracts. (Requires business case analysis and MDA approval.)
Not recommended for: Contracts less than 12 months in duration. OPTIONAL
May not be appropriate for: Non-schedule based contract efforts, e.g., level of effort.
o CPR Formats 2, 3, and 4 are optional.o Schedule Risk Assessment is optional.
< $20M OPTIONAL - USE JUDGMENT
Evaluate management needs carefully to ensure only minimum information needed for effective management control is requested.
o ANSI/EIA-748 compliance is discretionary and should be based on risk.
o CPR Formats 1 and 5 are recommended.o Integrated Master Schedule is optional.
Requires cost-benefit analysis and PM approval.
Not recommended for: Contracts less than 12 months in duration.
May not be appropriate for: Non-schedule based contract efforts, e.g., level of effort.
![Page 18: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/18.jpg)
Monitoring & Controlling
![Page 19: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/19.jpg)
Monitoring & Controlling
![Page 20: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/20.jpg)
Closing
• Vessel Delivery• Builder’s Trials• Acceptance Trials• Crew Familiarization• Deliver to Navy
• DD-250• Warranty
• Contract End
![Page 21: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/21.jpg)
Backup
![Page 22: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/22.jpg)
Shipyards in Henderson, Western Australia, Mobile, Alabama and Balamban, Philippines
Ideally positioned to support vessels in critical areas of WESTPAC, Indian Ocean and Mediterranean.
Austal’s Global Presence
![Page 23: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/23.jpg)
![Page 24: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/24.jpg)
1998
2004
Land total- 10 acres Manufacturing Space- 45,000 sq ft
Austal USA- The Beginning
![Page 25: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/25.jpg)
2007
2009
Land total- 11 acres Manufacturing Space- 153,000 sq ft
Land total- 115 acres Manufacturing Space- 503,000 sq ft
Austal USA- Expansion Phase 1
![Page 26: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/26.jpg)
“Anapaula” & “Veronica”2 x 45 meter Crew/Supply BoatDelivered - 2002
“Biscayne Lady”34 meter Dinner Cruise CatamaranDelivered - 2003
“Zephyr”44 meter Passenger Catamaran
Delivered - 2003
“Cloud Nine”41 meter Dinner Cruise YachtDelivered - 2003
Austal USA Building Construction - 2000
2002 2003 2004
HSV
Austal USA- Vessel Deliveries
![Page 27: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/27.jpg)
“Lake Express”58 meter Vehicle-Passenger CatamaranDelivered - 2004
107 meter “Alakai”Vehicle-Passenger
CatamaranDelivered - 2007
“Independence”127 meter Littoral Combat Ship
Launched – 2008Delivered- 2009
“Patriot”26 meter Passenger catamaranDelivered - 2003
2004 2006 2008
113 meter “Huakai”Vehicle-Passenger CatamaranDelivered - 2009
HSV HSV
HSV
HSV
LCS
2009
Austal USA- Vessel Deliveries
![Page 28: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/28.jpg)
Austal USA- Vessel Deliveries
USNS SpearheadDelivered Dec 2012
First Navy Vessel Delivered As Prime Contractor!
![Page 29: Ed Williams, PMP Director of Post Delivery Support](https://reader035.fdocuments.net/reader035/viewer/2022062423/56814c16550346895db914f1/html5/thumbnails/29.jpg)
1988 1992 1996 2000 2004 2008 2012
Spoilsport1989: 1st of 60 deliveries to Australia
Tong Zhou1990: First of 52 deliveries to China, Hong Kong and Macau
Aksemseddin1995: 1st of 10 delivery to Turkey
Ono-ono1994: 1st of 5 deliveries to French Polynesia
Speeder1995: 1st delivery to Japan
Cat-Link III1996: 1st vehicle-passenger ferry
Flying Dolphin 20001998: 1st of 5 deliveries to Greece
Jade Express1998: 1st delivery to the Caribbean
Carmen Ernestina1999: 1st delivery to South America
Bay Class Patrol Boats1999: 1st of 8 delivered to Australian Customs
Police Patrol Boats2000: 1st of 9 delivered to New South Wales Water Police
Euroferrys Pacifica2001: 101 meter; 1st delivery to Spain
Fares al Salam 2002: 1st delivery to Middle East
WestPac Express2001: 1st delivery to US military
Anapaula2002: 1st Austal USA delivery
Spirit of Ontario 12004: 1st Delivery to Great Lakes
Benchijigua Express2005: 1st Trimaran delivery
Yemen MOD Patrol Boats2005: 1st of 10 delivered to Yemen Ministry of Defence
Armidale Class Patrol Boat2005: 1st of 14 delivered to Royal Australian Navy
Police Patrol Boats2006: 1st of 6 for New South Wales Water Police
CotaiJet2007: 1st of 14 delivered to Macau
Kuwait Coast Guard2006: 4 x 22m patrol boats
Shinas2008: World's fastest vehicle ferry to Oman (56kts)
PCU Independence2009: 1st CS christened
USS Independence2010: 1st LCS commissioned
TTCG Patrol Boats2009: 1st of 6 for Trinidad and Tobago Coast Guard
AFM Patrol Boats2009: 1st defence deliveries to Europe
Police Patrol Boats2009: 1st of 3 delivered to Queensland Police Service
Alakai2007: 1st of 2 Hawaii Superferries
Leonora Christina2011: Austal’s largest catamaran (113m)
Wind Express Trimaran2012: Production begins at Philippines Shipyard
Cape Class Patrol Boat2012: Keel laying for 1st of 8 for Australian Customs
Def
ense
Com
mer
cial
Villum Clausen2000: World 24 hour distance record
Hawaii Superferries2012: Austal commences conversion for US Navy
NIDCO2010: Four 41m water Taxis to Trinidad
Aremiti Ferry 22012: Work begins on 82m medium-speed ferry
Wind Express2012: 1st Wind Farm boat delivery
248 Vessels Delivered or in Construction
Since 1988
Kurnai Tide1990: 1st Work boat, 1st Monohull
USNS JHSV Class2012: 1st of 10 christened