East Tennessee Technology Park...Size - $2.6 Billion • Partners-URS Energy & Construction, Inc....
Transcript of East Tennessee Technology Park...Size - $2.6 Billion • Partners-URS Energy & Construction, Inc....
1
East Tennessee Technology Park ETEBA
Tim MelbergManager, Supply Chain ManagementFebruary 25, 2016
UCOR Contract at a Glance
Contract Information• Size - $2.6 Billion• Partners
-URS Energy & Construction, Inc. (Primary)-CH2M HILL Constructors, Inc.
• Contract Duration and Specifics-August 1, 2011, through July 31, 2020
ETTP Contract Scope of Work and Primary Mission/Role at Site• Decontamination & Demolition (D&D) of the major facilities at the East Tennessee Technology Park
(ETTP)-K-25 and K-27 Uranium Enrichment Plants -Other facilities such as the Centrifuge, TSCA Incinerator, and K-1037 Barrier Plant
• Environmental remediation of contaminated soils• Significant waste management activities – disposal of radioactive waste both onsite and offsite• Perform surveillance, maintenance and operations activities at DOE EM owned facilities at ETTP, Oak
Ridge National Laboratory, and Y-12 National Security Complex3
UCOR FY2016 Work Plan• K-27 Demolition
– Demolition will be completed in CY16
• K-1037 Deactivation• Poplar Creek Deactivation
4
K-27
K-1037
Centrifuge
UCOR FY2016 Work Plan: LGWO Life Extension
5
3039 Stack ORNL
3608 ORNL
3544 ORNL
UCOR FY2016 Work Plan
• Projects– Outfall 200 Mercury Treatment Facility
(OF200)– Historic Preservation activities– Environmental Management Disposal
Facility (EMDF)
6
EMWMF and Proposed EMDF site shown
National Historic Preservation Museum
Photo PhotoPhoto
Photo Photo PhotoPhoto
UCOR FY16 Work Plan: Excess Facilities Priorities
73042 Decommissioning
Alpha 4 COLEX equipment removal
Building 3026 risk reduction ORNL Building 7500 cleanup action
Building 3038 risk reduction
Y-12 ORNL ORNL ORNL
Biology complex Alpha 4 roof repair Building 3029 and 3028 risk reduction
Y-12 Y-12 ORNL
PhotoPhoto
PhotoPhoto
UCOR FY16 Work Plan: Waste Disposition Priorities
8
K-27 Building
Spent Filters at 7862 DUO Sea/Land to be moved to ORNL
Sodium shields MSRE TDEC commitments
ORNL ETTP ORNL / ETTP ORNL
MSRE probe Overpack/dispose 19 containers at 3505
Disposition of 3026 legacy waste at 3044 pad
Dioxins & furans STP (K-1065 containers)
ORNL ORNL ORNL ETTP
2016 Work Plan
• UCOR is currently preparing several technical and cost proposals to be submitted to DOE. Once incorporated in the prime contract, any subcontracting opportunities will be identified.
9
UCOR Small Business ProgramUCOR’s 4-Point Plan to Increase Opportunities & Results for our Small Business Partners:1. Identify more task-based subcontracts (defined period of performance and
scope) 2. Identify and approve an additional mentor-protégé subcontractor3. Identify and pursue future large scope subcontracts4. Continue to provide focus on meeting UCOR goals on underutilized
categories (HUB Zone, SDVOSB)
10
2016 Small Business Opportunities• FY16 Projects in the General Plant Project Areas:
– Cooling Tower Piping Modifications– 4001 Sump Overflow Piping Modifications– Heat Trace Control Panel Replacements– Fence Repairs/Replacements– Motor Control Center Replacement– Concrete Dike Resealing and Painting– 3608 Process Waste Facility Upgrade– Mercury Field Research Facility
116
Small Business Program Opportunities
• Request for Proposal has been issued & evaluating. Awaiting funding release from DOE:
– Cooling Tower Piping Modifications– 4001 Sump Overflow Piping Modifications– Heat Trace Control Panel Replacements– Fence Repairs/Replacements
127
Small Business Program Opportunities
13
UCOR is reviewing upcoming subcontract and commodity blanket agreement expiration dates and will identify scopes to re-compete in alignment with option period
• Potential areas suitable for small business• Radiological supplies• Clean fill dirt• Aggregate, rock, and gravel• Compressed gases• Bottled water and Sports Drink• Respirator equipment• Bagged Ice
Small Business Program Opportunities
14
Subcontracted Scope• Staff Augmentation
• Currently 9 SA subcontracts.• May break out separate Technical and Professional subcontracts• May break out a separate Project Planning and Controls subcontract
Data Source: Puridiom
Stated as percentage of Total Dollars (Large + Small)BASE:Large: $10,130,253.51 Small: $73,826,933.07 Total: $83,957,186.58
y
0%
20%
40%
60%
80%
SB SDB WOB HUBZONE VETERAN DISABLEDVETERAN
88%
19%14%
1%
19%
3%
Perc
enta
ge
FY To Date10/1/2015 - 1/31/2016SB Goal = 65%
YTD: $73.83M (87.9%)
SDB Goal = 10%YTD: $15.74M (18.8%)
WOB Goal = 10%YTD: $12.03M (14.3%)
SDV Goal = 4%YTD: $2.69M (3.2%)
HUB Goal = 4%YTD: $0.67M (0.8%)
VOSB Goal = 4%YTD: $15.69M (18.7%)
15
Percentage of Subcontract Dollars Placed with Socioeconomic Firms
Summary FY16
Data Source: BPS/PaymentNet/Puridiom
Stated as percentage of Total Dollars (Large + Small)BASE:Large: $143,239,160.01 Small: $509,782,743.88 Total: $653,021,903.89
p
0%
20%
40%
60%
80%
SB SDB WOB HUBZONE VETERAN DISABLEDVETERAN
78%
20%
28%
6%
13%
4%
Perc
enta
ge
8/1/2011 - 1/31/2016SB Goal = 65%
TD: $509.78M (78.1%)
SDB Goal = 10%TD: $127.71M (19.6%)
WOB Goal = 10%TD: $183.19M (28.1%)
SDV Goal = 4%TD: $23.07M (3.5%)
HUB Goal = 4%TD: $39.25M (6.0%)
VOSB Goal = 4%TD: $83.52M (12.8%)
16
Percentage of Subcontract Dollars Placed with Socioeconomic Firms
Inception to date
Small Business Program Opportunities
17
UCOR Procurement 90 Day Forecast http://info.ettp.energy.gov/90day/index.html