Earth Wire Snapping

1
SL. NO. DESCRIPTION OF ITEM QTY. Remarks 1 MARKING LEAD (100 M/ 12 MM) 2 NOS 2 CEILING (5M - 16/18/20 MM) AS REQUIRED 3 D-SACKLE (6.5 T) 4 NOS 4 SINGLE SHEAVE PULLY (OPEN) 4 NOS 5 SINGLE SHEAVE PULLY (CLOSE) 3 NOS 6 DOUBLE SHEAVE PULLY 2 NOS 7 KATKA ROPE (2M - WITH 'T' CONNECTION) 4 NOS 8 PP ROPE (18 MM) 1 BUNDLE 9 PP ROPE (20 MM) 1 BUNDLE 10 DISCHARGE ROD 6 NOS 11 FALL ARRESTER 2 NOS 12 SCREW DIVER (BAG TYPE) 2 NOS 13 COME ALONG CLAMP (3 bolt) 2 NOS 14 COME ALONG CLAMP (AUTOMATIC) 2 NOS 15 CEILING (1M - 16 MM) 4 NOS 16 RING SPANNER (24/26) 4 NOS 17 Compresser Machine with Die (Auto) 1 NOS Additional 1 nos Manual as back-up 18 Flat File (8mm) 2 NOS 19 Marking Tape (30m) 1 NOS 20 HEXAFRAME (WITH BLADE) 2 NOS + 2 EXTRA BLADES 1 Earth-Wire Beat As per Requirement MSJ should be 30m away from tower 2 Earth-Wire Dead-End As per Requirement 3 Earth-Wire Jumper Cone with N/B As per Requirement 4 Middle Span Joint As per Requirement MSJ should be 30m away from tower, only 1 MSJ in one span 5 Earth-Wire Vibration Damper As per Requirement 6 Earth-Wire Suspension Clamp As per Requirement 1 Engineer 1 2 Safety Officer 1 3 Supervisor 2 4 Skilled Labour (Fitter) 3 Depends upon Site condition 5 Unskilled labour (Helper) 8 Depends upon Site condition Minimum Requirement of Manpower Emergency Re-installation in case of Earth-Wire snapping Requirement of T&P Requirement of Material

description

Earth Wire Snapping Instructions

Transcript of Earth Wire Snapping

  • SL. NO. DESCRIPTION OF ITEM QTY. Remarks

    1 MARKING LEAD (100 M/ 12 MM) 2 NOS

    2 CEILING (5M - 16/18/20 MM) AS REQUIRED

    3 D-SACKLE (6.5 T) 4 NOS

    4 SINGLE SHEAVE PULLY (OPEN) 4 NOS

    5 SINGLE SHEAVE PULLY (CLOSE) 3 NOS

    6 DOUBLE SHEAVE PULLY 2 NOS

    7 KATKA ROPE (2M - WITH 'T' CONNECTION) 4 NOS

    8 PP ROPE (18 MM) 1 BUNDLE

    9 PP ROPE (20 MM) 1 BUNDLE

    10 DISCHARGE ROD 6 NOS

    11 FALL ARRESTER 2 NOS

    12 SCREW DIVER (BAG TYPE) 2 NOS

    13 COME ALONG CLAMP (3 bolt) 2 NOS

    14 COME ALONG CLAMP (AUTOMATIC) 2 NOS

    15 CEILING (1M - 16 MM) 4 NOS

    16 RING SPANNER (24/26) 4 NOS

    17Compresser Machine with Die (Auto) 1 NOS Additional 1 nos Manual as back-up

    18 Flat File (8mm) 2 NOS

    19 Marking Tape (30m) 1 NOS

    20 HEXAFRAME (WITH BLADE) 2 NOS + 2 EXTRA BLADES

    1Earth-Wire Beat As per Requirement

    MSJ should be 30m away from

    tower

    2 Earth-Wire Dead-End As per Requirement

    3 Earth-Wire Jumper Cone with N/B As per Requirement

    4 Middle Span Joint As per RequirementMSJ should be 30m away from

    tower, only 1 MSJ in one span

    5 Earth-Wire Vibration Damper As per Requirement

    6 Earth-Wire Suspension Clamp As per Requirement

    1 Engineer 1

    2 Safety Officer 1

    3 Supervisor 2

    4 Skilled Labour (Fitter) 3 Depends upon Site condition

    5 Unskilled labour (Helper) 8 Depends upon Site condition

    Minimum Requirement of Manpower

    Emergency Re-installation in case of Earth-Wire snapping

    Requirement of T&P

    Requirement of Material