Earned Value Management - Tutorials Point · Earned Value Management (EVM) is a technique that is...

15

Transcript of Earned Value Management - Tutorials Point · Earned Value Management (EVM) is a technique that is...

Earned Value Management

i

About the Tutorial

Earned Value Management (EVM) is a technique that is used to track the progress

and status of a project and forecast its likely future performance.

This is a brief tutorial that acquaints the reader with the basics of EVM and explains

how to utilize it for better project management.

Audience

If you are a project manager or planning to become one, then it is important for

you to learn EVM.

Prerequisites

This is a basic tutorial and there are no prerequisites as such, however it would

help you understand the concepts faster if you have a basic knowledge of project

tracking and overall project management.

Copyright & Disclaimer

Copyright 2015 by Tutorials Point (I) Pvt. Ltd.

All the content and graphics published in this e-book are the property of Tutorials

Point (I) Pvt. Ltd. The user of this e-book is prohibited to reuse, retain, copy,

distribute or republish any contents or a part of contents of this e-book in any

manner without written consent of the publisher.

We strive to update the contents of our website and tutorials as timely and as

precisely as possible, however, the contents may contain inaccuracies or errors.

Tutorials Point (I) Pvt. Ltd. provides no guarantee regarding the accuracy,

timeliness or completeness of our website or its contents including this tutorial. If

you discover any errors on our website or in this tutorial, please notify us at

[email protected]

Earned Value Management

ii

Table of Contents

About the Tutorial ..................................................................................................................................... i

Audience .................................................................................................................................................... i

Prerequisites .............................................................................................................................................. i

Copyright & Disclaimer .............................................................................................................................. i

Table of Contents ...................................................................................................................................... ii

1. OVERVIEW ............................................................................................................................ 1

2. BASIC ELEMENTS ................................................................................................................... 2

Planned Value ........................................................................................................................................... 2

Actual Cost ................................................................................................................................................ 2

Earned Value ............................................................................................................................................. 2

% Completed Planned ............................................................................................................................... 3

% Completed Actual .................................................................................................................................. 3

3. COST VARIANCE .................................................................................................................... 4

Cost Variance % ........................................................................................................................................ 4

Cost Performance Indicator ...................................................................................................................... 5

To Complete Cost Performance Indicator.................................................................................................. 5

4. SCHEDULE VARIANCE ............................................................................................................ 6

Schedule Variance % ................................................................................................................................. 6

Schedule Performance Indicator ............................................................................................................... 7

To Complete Schedule Performance Indicator .......................................................................................... 7

5. MISCELLANEOUS FORMULA .................................................................................................. 8

Budget at Completion ............................................................................................................................... 8

Estimate to Complete ............................................................................................................................... 8

Earned Value Management

iii

Estimate at Completion ............................................................................................................................ 8

Variance at Completion ............................................................................................................................ 9

% Completed Planned ............................................................................................................................... 9

% Completed Actual .................................................................................................................................. 9

6. EVM EXAMPLES .................................................................................................................. 10

Earned Value Management

1

Earned Value Management (EVM) is a project management technique that

objectively tracks physical accomplishment of work.

More elaborately:

EVM is used to track the progress and status of a project and forecasts the likely future performance of the project.

EVM integrates the scope, schedule, and cost of a project.

EVM answers a lot of questions to the stakeholders in a project related to

its performance.

EVM can be used to show the past and the current performance of a project

and predict the future performance of the project by the use of statistical techniques.

Good planning coupled with effective use of EVM will reduce a lot of issues arising out of schedule and cost overruns.

EVM has emerged as a financial analysis specialty in United States Government

programs in the 1960s, but it has since become a significant branch of project

management.

In the late 1980s and early 1990s, EVM emerged as a project management

methodology to be understood and used by managers and executives, not just

EVM specialists. Today, EVM has become an essential part of every project

tracking.

1. OVERVIEW

Earned Value Management

2

EVM consists of the following three basic elements:

Planned Value

Actual Cost

Earned Value

All the three elements are captured on a regular basis as of a reporting date.

Planned Value

Planned value (PV) is also referred to as Budgeted Cost of Work Scheduled

(BCWS). PV or BCWS is the total cost of the work scheduled/planned as of a

reporting date.

It is calculated as:

PV or BCWS = Hourly Rate × Total Hours Planned or Scheduled

NOTE: Hourly Rate is the rate at which effort will be valued.

Actual Cost

Actual cost (AC) is also referred to as Actual Cost of Work Performed (ACWP). AC

or ACWP is the total cost taken to complete the work as of a reporting date.

It is calculated as:

AC or ACWP = Hourly Rate × Total Hours Spent

Earned Value

Earned value (EV) is also referred to as Budgeted Cost of Work Performed (BCWP).

EV or BCWP is the total cost of the work completed/performed as of a reporting

date.

It is calculated as:

EV or BCWP = Baselined Cost × % Complete Actual

2. BASIC ELEMENTS

Earned Value Management

3

All these three elements can be derived from Work Breakdown Structure by

associating the costs to each of the tasks. For a big project, it will be a tedious

task to calculate these elements manually. Scheduling software tools like Microsoft

Project is used to calculate these three elements.

NOTE: % Completed Planned and % Completed Actual are defined below.

% Completed Planned

The percentage of work which was planned to be completed by the Reporting Date.

It is calculated using the following formula:

% Completed Planned = PV / BAC

% Completed Actual

The percentage of work which was actually completed by the Reporting Date. It is

calculated using the following formula:

% Completed Actual = AC / EAC

Earned Value Management

4

Cost Variance (CV) is a very important factor to measure project performance. CV

indicates how much over- or under-budget the project is.

CV can be calculated using the following formula:

Cost Variance (CV) = Earned Value (EV) – Actual Cost (AC)

OR

Cost Variance (CV) = BCWP – ACWP

The formula mentioned above gives the variance in terms of cost.

Positive CV indicates the project is under-budget.

Negative CV indicates the project is over-budget.

Cost Variance %

Cost Variance % indicates how much over- or under-budget the project is in terms

of percentage.

Cost Variance % can be calculated using the following formula:

CV % = Cost Variance (CV) / Earned Value (EV)

OR

CV % = CV / BCWP

The formula mentioned above gives the variance in terms of percentage.

Positive Variance % indicates % under budget.

Negative Variance % indicates % over budget.

3. COST VARIANCE

Earned Value Management

5

Cost Performance Indicator

Cost Performance Indicator (CPI) is an index showing the efficiency of the

utilization of the resources on the project. CPI can be calculated using the following

formula:

CPI = Earned Value (EV) / Actual Cost (AC)

OR

CPI = BCWP / ACWP

The formula mentioned above gives the efficiency of the utilization of the resources allocated to the project.

A CPI value above 1 indicates the efficiency of utilizing the resources

allocated to the project is good.

A CPI value below 1 indicates the efficiency of utilizing the resources

allocated to the project is not good.

To Complete Cost Performance Indicator

To Complete Cost Performance Indicator (TCPI) is an index showing the efficiency

at which the resources on the project should be utilized for the remainder of the

project. It can be calculated using the following formula:

TCPI = ( Total Budget – EV ) / ( Total Budget – AC )

OR

TCPI = ( Total Budget – BCWP ) / ( Total Budget – ACWP )

The formula mentioned above gives the efficiency at which the project team should be utilized for the remainder of the project.

A TCPI value above 1 indicates the utilization of the project team for the remainder of the project can be stringent.

A TCPI value below 1 indicates the utilization of the project team for the

remainder of the project should be lenient.

Earned Value Management

6

Schedule Variance (SV) indicates how much ahead or behind the schedule a

project is running.

It can be calculated using the following formula:

Schedule Variance (SV) = Earned Value (EV) – Planned Value (PV)

OR

Schedule Variance (SV) = BCWP – BCWS

The formula mentioned above gives the variance in terms of cost which

indicates how much cost of the work is yet to be completed as per schedule or how much cost of work has been completed over and above the scheduled cost.

A positive SV indicates we are ahead of schedule.

A negative SV indicates we are behind schedule.

Schedule Variance %

Schedule Variance % indicates how much ahead or behind the schedule a project

is running in terms of percentage.

Schedule Variance % can be calculated using the following formula:

SV % = Schedule Variance (SV) / Planned Value (PV)

OR

SV % = SV / BCWS

The formula mentioned above gives the variance in terms of percentage which indicates how much percentage of work is yet to be completed as per

schedule or how much percentage of work has been completed over and above the scheduled cost.

Positive Variance % indicates % ahead of schedule.

4. SCHEDULE VARIANCE

Earned Value Management

7

Negative Variance % indicates % behind of schedule.

Schedule Performance Indicator

Schedule Performance Indicator (SPI) is an index showing the efficiency of the

time utilized on the project. SPI can be calculated using the following formula:

SPI = Earned Value (EV) / Planned Value (PV)

OR

SPI = BCWP / BCWS

The formula mentioned above gives the efficiency of the project team in utilizing the time allocated for the project.

An SPI value above 1 indicates the project team is very efficient in utilizing

the time allocated to the project.

An SPI value below 1 indicates the project team is less efficient in utilizing

the time allocated to the project.

To Complete Schedule Performance Indicator

To Complete Schedule Performance Indicator (TSPI) is an index showing the

efficiency at which the remaining time on the project should be utilized. It can be

calculated using the following formula:

TSPI = ( Total Budget - EV ) / ( Total Budget - PV )

OR

TSPI = ( Total Budget - BCWP ) / ( Total Budget - BCWS )

The formula mentioned above gives the efficiency at which the project team should utilize the remaining time allocated for the project.

A TSPI value below 1 indicates the project team can be lenient in utilizing

the remaining time allocated to the project.

A TSPI value above 1 indicates the project team needs to work harder in utilizing the remaining time allocated to the project.

Earned Value Management

8

Budget at Completion

Budget at Completion (BAC) is the total budget allocated to the project.

BAC is generally plotted over time. For example, periods of reporting

(Monthly, Weekly, etc.)

BAC is used to compute the Estimate at Completion (EAC), explained in the next section.

BAC is also used to compute the TCPI and TSPI.

BAC is calculated using the following formula:

BAC = Baselined Effort-hours × Hourly Rate

Estimate to Complete

Estimate to Complete (ETC) is the estimated cost required to complete the remainder of the project.

ETC is calculated and applied when the past estimating assumptions become invalid and a need for fresh estimates arises.

ETC is used to compute the Estimation at Completion (EAC).

Estimate at Completion

Estimate at Completion (EAC) is the estimated cost of the project at the end of the project.

There are three methods to calculate EAC:

o Variances are typical - This method is used when the variances at the current stage are typical and are not expected to occur in the

future.

o Past estimating assumptions are not valid - This method is used

when the past estimating assumptions are not valid and fresh estimates are applied to the project.

5. MISCELLANEOUS FORMULA

Earned Value Management

9

o Variances will be present in the future - This method is used when the assumption is that the current variances will continue to be

present in the future.

The formulas for calculation of the three methods are as given below:

o AC + (BAC - EV)

o AC + ETC (Estimate To Complete)

o AC + (BAC- EV) / CPI

Variance at Completion

Variance at completion (VAC) is the variance on the total budget at the end of the

project.

This is the difference between what the project was originally expected (baselined)

to cost versus what it is now expected to cost.

VAC is calculated using the following formula:

VAC = BAC - EAC

% Completed Planned

The percentage of work which was planned to be completed by the Reporting Date.

It is calculated using the following formula:

% Completed Planned = PV / BAC

% Completed Actual

The percentage of work which was actually completed by the Reporting Date. It is

calculated using the following formula:

% Completed Actual = AC / EAC

Earned Value Management

10

To illustrate the concept of EVM and all the formulas, assume a project that has

exactly one task. The task was baselined at 8 hours, but 11 hours have been spent

and the estimate to complete is 1 additional hour. The task would have been

completed already.

Assume an Hourly Rate of $100 per hour.

Using this information:

PV or BCWS = Hourly Rate × Total Hours Planned or Scheduled

PV = $100 * 8 hours = $800

AC or ACWP = Hourly Rate × Total Hours Spent

AC = $100 * 11 hours = $1100

EV or BCWP = Baselined Cost × % Complete Actual

EV = baseline of $800 * 91.7% complete = $734

(NOTE % Complete Actual (below) to get the 91.7%)

BAC = Baselined Effort-hours × Hourly Rate

BAC = 8 hours * $100 = $800

EAC = AC + ETC

EAC = 1100 + 100 = $1200

VAC = BAC - EAC

VAC = $800 – $1200 = –$400

% Completed Planned = PV / BAC

% Complete Planned = $800 PV / $800 BAC = 100%

6. EVM EXAMPLES

Earned Value Management

11

% Completed Actual = AC / EAC

% Complete Actual = $1100 AC / $1200 EAC = 91.7%

SV = Earned Value (EV) - Planned Value (PV)

SV = $734 EV – $800 PV = –$66

SPI = Earned Value (EV) /Planned Value (PV)

SPI = $734 EV / $800 PV = 0.91

CV = Earned Value (EV) - Actual Cost (AC)

CV = ($734 EV - $1100 AC) = –$366*

*indicates a cost overrun

CPI = Earned Value (EV) /Actual Cost (AC)

CPI = $734 EV / $1100 AC = 0.66*

*indicates over-budget