Earned Value Analysis by John Cornman For Details -- Lewis, Ch 10

17
Earned Value Analysis by John Cornman For Details -- Lewis, Ch 10

description

Earned Value Analysis by John Cornman For Details -- Lewis, Ch 10. Introduction. “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its completion date and final cost, and provide schedule and budget variances along the way. - PowerPoint PPT Presentation

Transcript of Earned Value Analysis by John Cornman For Details -- Lewis, Ch 10

Page 1: Earned Value Analysis by John Cornman For Details --   Lewis, Ch 10

Earned Value Analysisby

John Cornman

For Details -- Lewis, Ch 10

Page 2: Earned Value Analysis by John Cornman For Details --   Lewis, Ch 10

Introduction

• “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its completion date and final cost, and provide schedule and budget variances along the way.

• Based on just 3 data points, it can provide consistent, numerical indicators with which you can evaluate and compare projects.

Page 3: Earned Value Analysis by John Cornman For Details --   Lewis, Ch 10

The 3 fundamental metrics

• Budgeted Cost of Work Performed.

• Budgeted Cost of Work Scheduled.

• Actual Cost of Work Performed.

Page 4: Earned Value Analysis by John Cornman For Details --   Lewis, Ch 10

Budgeted Cost of Work Performed

• This is the “Earned Value.”• Abbreviated as BCWP.• For completed work, it is the cost originally

budgeted to accomplish that work.• “How much work was actually done?”

Page 5: Earned Value Analysis by John Cornman For Details --   Lewis, Ch 10

Budgeted Cost of Work Scheduled

• Abbreviated BCWS.• It is the total budgeted cost up to the

analysis date.• Approximated by the total budget

multiplied by the fraction of total project duration at the analysis date.

• “How much work should have been done?”

Page 6: Earned Value Analysis by John Cornman For Details --   Lewis, Ch 10

Actual Cost of Work Performed

• Abbreviated ACWP.• What it actually cost to accomplish all the

work completed as of the analysis date.• “What did the work that was actually done

actually cost?”

Page 7: Earned Value Analysis by John Cornman For Details --   Lewis, Ch 10

Derived Metrics

• Schedule Variance (SV)• Schedule Performance Index (SPI)• Cost Variance (CV)• Cost Performance Index (CPI)

Page 8: Earned Value Analysis by John Cornman For Details --   Lewis, Ch 10

A Few More Acronyms

• BAC - Budget At Completion • = Total Original Budgeted Cost• Same as BCWS at completion

• EAC - Estimate At Completion• = Cumulative Actuals + Estimate-To-Complete

• VAC - Variance At Completion• = Forecast of final cost variance

Page 9: Earned Value Analysis by John Cornman For Details --   Lewis, Ch 10

Doing The Math• SV = BCWP - BCWS

• Negative means Behind Schedule

• SPI = BCWP / BCWS• Less than 1.00 means Behind Schedule

• CV = BCWP - ACWP• Negative means Over Budget

• CPI = BCWP / ACWP• Less than 1.00 means Over Budget

• EAC = BAC / CPI

Page 10: Earned Value Analysis by John Cornman For Details --   Lewis, Ch 10

An Example: Lemonade

• Make 1,000 cups over 50 days• Steady rate of 20 cups per day• Budgeted cost per cup is $0.50• Total project budget is $500

Page 11: Earned Value Analysis by John Cornman For Details --   Lewis, Ch 10

Lemonade Progress

• At end of day 10:• 150 cups have been made• Total actual cost is $90 (ACWP)

Page 12: Earned Value Analysis by John Cornman For Details --   Lewis, Ch 10

Lemonade Status

• BCWS = $100• 10 days x 20 cups per day x .50/cup budget

• BCWP = $75 (Earned Value)• 150 cups x .50/cup budget

• SV = BCWP - BCWS = -$25• SPI = BCWP / BCWS = 0.75• CV = BCWP - ACWP = $75 - $90 = -$15• CPI = BCWP / ACWP = 0.833

Page 13: Earned Value Analysis by John Cornman For Details --   Lewis, Ch 10

Lemonade Forecast

• EAC = BAC / CPI = $500 / 0.833 = $600• VAC = BAC - EAC = $500 - $600 = $100

(unfavorable)• Schedule at Completion =

50 / SPI = 50 / 0.75 = 66.67 days

Page 14: Earned Value Analysis by John Cornman For Details --   Lewis, Ch 10

MS Project 98 Support

ID Task Name BCWS BCWP ACWP SV CV EAC BAC VAC1 MS Project 98 Example $1,920.00 $840.00 $960.00 ($1,080.00) ($120.00) $2,760.00 $2,400.00 $360.00

F S SNo

Page 15: Earned Value Analysis by John Cornman For Details --   Lewis, Ch 10

Five Simple Criteria forEarned Value Applications

1.Define (scope) the project. . .with a WBS2.Plan and schedule the project scope3.Budget cost account plans to functions4.Establish and maintain a performance

baseline5.Monitor performance and forecast final

resultsFleming & Hoppleman. 1996. Earned Value Management. PMI

Page 16: Earned Value Analysis by John Cornman For Details --   Lewis, Ch 10
Page 17: Earned Value Analysis by John Cornman For Details --   Lewis, Ch 10

Earned Value Management

http://www.acq.osd.mil/pm/