Earned Schedule_Walt Lipke

download Earned Schedule_Walt Lipke

of 12

Transcript of Earned Schedule_Walt Lipke

  • 8/9/2019 Earned Schedule_Walt Lipke

    1/27

    1International Metrics Congress

    2007

    Earned Schedule …a n em e r g i n g e n h a n c e m e n t t o E VM  

    Walt Lipkebrought to you by the PMI MetSIG and Cheetah Learning 

  • 8/9/2019 Earned Schedule_Walt Lipke

    2/27

    2International Metrics Congress

    2007

    Brought To You By

      Cheetah Learning is Global Leader in PMP Examprep and PM Training with classes covering theglobe from the U.S. and Canada to SouthAmerica, Europe, New Zealand and Australia,India and Asia, the Middle East and Africa.

      Our accelerated learning techniques speedlearning and retention and drive our 97% passrate on the PMP exam.

      Michelle LaBrosse, Founder & Chief Cheetah,recently named one of 25 Influential Women inPM in the world.

      Cheetah Learning strives to raise the profile of PM with our webinars and our Know HowNetwork column which is published in over 200publications around the world.

  • 8/9/2019 Earned Schedule_Walt Lipke

    3/27

    3International Metrics Congress

    2007

    Objective

    • Introduce the Earned Schedule Concept

    • Develop the Schedule Indicators

    • Apply to Project Duration Prediction

    • Apply to Schedule Analysis

  • 8/9/2019 Earned Schedule_Walt Lipke

    4/27

    4International Metrics Congress

    2007

    Earned Value Basics

    Time

    $$

    PVEVSPI

    ACEVCPI

    BAC

    PV

    AC

    EV

    SV

    CV

  • 8/9/2019 Earned Schedule_Walt Lipke

    5/27

    5International Metrics Congress

    2007

    EVM Schedule Indicators

    • SV & SPI behave erratically for projects behind schedule

     –   SPI im pro ves and equals 1.00 at end of pr oject  

     –   S V im p r o v e s an d c o n c lu d e s a t $0 v ar ia n c e  

    • Schedule indicators lose predictive ability over the last third

    of the project

  • 8/9/2019 Earned Schedule_Walt Lipke

    6/27

    6International Metrics Congress

    2007

    EVM Schedule Indicators

    • Why does this happen?

     – SV = EV – PV

     – SPI = EV / PV

    • At planned completion PV = BAC

    • At actual completion EV = BAC• When actual > planned completion

     – SV = BAC – BAC = $000

     – SPI = BAC / BAC = 1.00

    Regardless of lateness !!

  • 8/9/2019 Earned Schedule_Walt Lipke

    7/27

    7International Metrics Congress

    2007

    Earned Schedule Concept

    The cumulative value of ES is

    found by using EV to identify 

    in which increment of PV the

    cost value occurs.

    7 months gone by, but the project only has “Earned Schedule” to Month 5W h i c h S V “A n s w e r s th e ma i l ? ” $ b eh i n d o r 2 mo n th s b e h i n d s c h e d u l e ?  

    $

    5

    Σ PV

    Σ EV

    Time Now

    71   2 3 4 6 8 9   10

    A

    B

    SVc

    SVtES

  • 8/9/2019 Earned Schedule_Walt Lipke

    8/27

    8International Metrics Congress

    2007

    Earned Schedule Metric

    • Required measures

     – Performance Measurement Baseline (PMB) – thetime phased planned values (PV) from project start tocompletion

     – Earned Value (EV) – the planned value which has

    been “earned” – Actual Time (AT) - the actual time duration from the

    project beginning to the time at which project status isassessed

    • All measures available from EVM

  • 8/9/2019 Earned Schedule_Walt Lipke

    9/27

    9International Metrics Congress

    2007

    Earned Schedule Calculation

    • ES (cumulative) is the:Number of completed PV time increments EV exceeds +the fraction of the incomplete PV increment

    • ES = C + I  where:C = number of time increments for EV   PV

    I = (EV – PVC) / (PVC+1 – PVC)

  • 8/9/2019 Earned Schedule_Walt Lipke

    10/27

    10International Metrics Congress

    2007

    Interpolation Calculation

    $$

    I /1 mo = p / q

    I = (p / q)    1 mo

    p = EV – PVCq = PVC+1 – PVC

    I =    1moEV – PVC

    PVC+1 – PVC

    PVC+1

    ES(calc)

    EV

    PVC

    ES

    JulyJuneMay

    1 mo

    I

    p

    q

    Time

  • 8/9/2019 Earned Schedule_Walt Lipke

    11/27

    11International Metrics Congress

    2007

    Earned Schedule Indicators

    • Schedule Variance:

    SV(t) = ES – AT

    • Schedule Performance Index:

    SPI(t) = ES / AT

    where AT is “Actual Time” – the duration from start to time now

    • SV(t) and SPI(t) are time-based (months, weeks …)

  • 8/9/2019 Earned Schedule_Walt Lipke

    12/27

    12International Metrics Congress

    2007

    Earned Schedule Indicators

    • What happens to the ES indicators, SV(t) & SPI(t), when theplanned project duration (PD) is exceeded (PV = BAC)?

    They Still Work …Correctly!!• ES will be  PD, while AT > PD

     – SV(t) will be negative (time behind schedule) – SPI(t) will be < 1.00

    Reliable Values from Start to Finish !!

  • 8/9/2019 Earned Schedule_Walt Lipke

    13/27

    13International Metrics Congress

    2007

    Schedule Variance Comparison

    -400

    -300

    -200

    -100

    0

    J F M A M J J A S O N D J F M

    -3

    -2

    -1

    0

    0

    20

    40

    60

    80

    100

    J F M A M J J A S O N D J F M

    0

    0.2

    0.4

    0.6

    0.8

    1

    SV($) SV(t)

    Early Finish Project

    Late Finish Project

    $   Mo

    $   Mo

  • 8/9/2019 Earned Schedule_Walt Lipke

    14/27

    14International Metrics Congress

    2007

    Schedule Index Comparison

    0.98

    1.00

    1.02

    1.04

    1.06

    1.08

    1.10

    1.12

    J F M A M J J A S O N D J F M

    0.70

    0.80

    0.90

    1.00

    1.10

    1.20

    1.30

    J F M A M J J A S O N D J F M

    SPI($) SPI(t)

    Early Finish Project

    Late Finish Project

  • 8/9/2019 Earned Schedule_Walt Lipke

    15/27

    15International Metrics Congress

    2007

    Commercial IT Infrastructure Expansion Project Phase 1

    Cost and Schedule Variances

    at Project Projection: Week Starting 15th July xx

    -160

    -140

    -120

    -100

    -80

    -60

    -40

    -20

    0

    20

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 1 5 16 17 18 19 20 21 22 23 24 25 26 27 2 8 29 30 31 32 33 34

    Elapsed Weeks

         D    o     l     l    a    r    s     ( ,     0     0     0     )

    -16

    -14

    -12

    -10

    -8

    -6

    -4

    -2

    0

    2

         W    e    e     k    s

    CV cum SV cum Target SV & CV SV (t) c um

    Stop wk 19

    Re-start wk 26Sched wk 20

    Late Finish Project

  • 8/9/2019 Earned Schedule_Walt Lipke

    16/27

    16International Metrics Congress

    2007

    Earned Schedule – Key Points

    • ES Indicators constructed to behave in an analogousmanner to the EVM Cost Indicators, CV and CPI

    • SV(t) and SPI(t)

     – Not constrained by PV calculation reference

     – Provide duration based measures of schedule

    performance – Valid for entire project, including early and late finish

    • Facilitates integrated Cost/Schedule project management

    (using EVM with ES)

  • 8/9/2019 Earned Schedule_Walt Lipke

    17/27

    17International Metrics Congress

    2007

    Schedule Prediction

    • Can the project be completed as planned? – TSPI = Plan Remaining / Time Remaining

    = (PD – ES) / (PD – AT)where PD is the planned duration (time at BAC)

    (PD – ES) = PDWRPDWR = Planned Duration for Work Remaining

    • …completed as estimated? – TSPI = (PD – ES) / (ED – AT)

    where ED = Estimated Duration

    Not Achievable 1.10 Achievable 1.00

    Predicted OutcomeTSPI Value

  • 8/9/2019 Earned Schedule_Walt Lipke

    18/27

    18International Metrics Congress

    2007

    Schedule Forecasting

    • Long time goal of EVM …Prediction of total project durationfrom present schedule status

    • Independent Estimate at Completion (time)

     – IEAC(t) = PD / SPI(t)

     – IEAC(t) = AT + (PD – ES) / PF(t)where PF(t) is the Performance Factor (time)

     – Analogous to IEAC used to predict final cost

    • Independent Estimated Completion Date (IECD)

     – IECD = Start Date + IEAC(t)

  • 8/9/2019 Earned Schedule_Walt Lipke

    19/27

    19International Metrics Congress

    2007

    Earned Schedule Terminology

    at Completion (time)

    Independent Estimate

    Performance Index

    To Complete Schedule

    Schedule PerformanceIndex

    Schedule Variance

    Actual Time

    Earned Schedule

    IEAC(t) = AT + (PD– ES) / PF

    IEAC(t) = PD / SPI(t)IEAC(t)Predictors

    TSPI(t) = (PD – ES) / (ED – AT)

    TSPI(t) = (PD – ES) / (PD – AT)TSPI(t)

    SPI(t) = ES / ATSPI(t)Indicators

    SV(t) = ES - ATSV(t)

    AT = number of periods executedATcum

    ES = C + I number of completeperiods (C) plus an incompleteportion (I)

    EScumMetrics

    at Completion (time)

    Independent Estimate

    Performance Index

    To Complete Schedule

    Schedule PerformanceIndex

    Schedule Variance

    Actual Time

    Earned Schedule

    IEAC(t) = AT + (PD– ES) / PF(t)

    IEAC(t) = PD / SPI(t)IEAC(t)Predictors

    TSPI(t) = (PD – ES) / (ED – AT)

    TSPI(t) = (PD – ES) / (PD – AT)TSPI

    SPI(t) = ES / ATSPI(t)Indicators

    SV(t) = ES - ATSV(t)

    AT = number of periods executedATcum

    ES = C + I number of completeperiods (C) plus an incompleteportion (I)

    EScumMetrics

  • 8/9/2019 Earned Schedule_Walt Lipke

    20/27

    20International Metrics Congress

    2007

    Independent Confirmation

    • SPI(t) & SV(t) do portray the real schedule performance• At early & middle project stages pre-ES & ES forecasts of 

    project duration produce similar results

    • At late project stage ES forecasts outperform all pre-ESforecasts

    • The use of the SPI(t) in conjunction with the TSPI(t) hasbeen demonstrated to be useful for managing the schedule

    Stephan Vandevoorde – Fabricom Airport Systems, Belgium

  • 8/9/2019 Earned Schedule_Walt Lipke

    21/27

    21International Metrics Congress

    2007

    Schedule Analysis with EVM?

    • Most practitioners analyze schedule from the bottom upusing the network schedule, independent from EVM

    ….“It is the only way possible.”

     – Analysis of the Schedule is overwhelming

     – Critical Path is used to shorten analysis(CP is longest path of the schedule)

    • Duration prediction using Earned Schedule provides amacro-method similar to the method for estimating Cost

     –  A significant advance in practice

    •   But, there’s more that ES facilitates ….

  • 8/9/2019 Earned Schedule_Walt Lipke

    22/27

    22International Metrics Congress

    2007

    Facilitates Drill-Down Analysis

    • ES can be applied to any level of the WBS, to include taskgroupings, such as the Critical Path (CP) – Requires creating PMB for the area of interest

     – EV for the area of interest is used to determine its ES

    • Enables comparison of forecasts, total project (TP) to CP

     – Desired result: forecasts are equal

     – When TP forecast > CP forecast, CP has changed

     – When CP > TP, possibility of future problems

  • 8/9/2019 Earned Schedule_Walt Lipke

    23/27

    23International Metrics Congress

    2007

    ES Bridges EVM to the Schedule

    $$

    Time

    PV

    BAC

    PD

    EV

    ES   AT AT

    SV(t)

  • 8/9/2019 Earned Schedule_Walt Lipke

    24/27

    24International Metrics Congress

    2007

    How Can This Be Used?

    • Tasks behind – possibility of impediments or constraints canbe identified

    • Tasks ahead – a likelihood of future rework can be identified

    • The identification is independent from schedule efficiency

    • The identification can be automated

    PMs can now have a schedule analysis toolconnected to the EVM Data!!

  • 8/9/2019 Earned Schedule_Walt Lipke

    25/27

    25International Metrics Congress

    2007

    Current Usage & Recognition

    • EVM Instructors – Performance Management Associates, Management Technologies,

    George Washington University, University of Florida …

    • Boeing Dreamliner , Lockheed Martin, US StateDepartment, Secretary of the Air Force

    • Several Countries - Australia, Belgium, United Kingdom,

    USA ….(Japan, Switzerland, Sweden, Spain, Brazil, India, …)• Applications across weapons programs, construction,

    software development, …• Range of project size from very small and short to extremely

    large and long duration• Inclusion of Emerging Practice Insert into PMI - EVM

    Practice Standard (2004)

  • 8/9/2019 Earned Schedule_Walt Lipke

    26/27

    26International Metrics Congress

    2007

    Summary

    • Derived from EVM data … only• Provides time-based schedule indicators

    • Indicators do not fail for late finish projects

    • Application is scalable up/down, just as is EVM

    • Schedule prediction is better than any other EVM methodpresently used

    • Application is growing in both small and large projects

    • Practice recognized as “Emerging Practice”

    • Facilitates bridging EVM analysis to include the Schedule

  • 8/9/2019 Earned Schedule_Walt Lipke

    27/27

    27International Metrics Congress

    2007

    Thank You!

    Walt Lipke

    Email: [email protected]

    Thank You from the MetSIG…TheInformation Highway For the Metricsof the World