Early Delivery System

16
http://nodal.ercot.com 1 Lead from the front Texas Nodal Early Delivery System Testing Planning – Involving Market Participants TPTF May 22, 2007

description

Early Delivery System. Testing Planning – Involving Market Participants. TPTF May 22, 2007. Objectives for today’s presentation. Discuss EDS 3 Plan document TPTF comments Get acceptance of the EDS Timeline plan as a baseline - PowerPoint PPT Presentation

Transcript of Early Delivery System

Page 1: Early Delivery System

http://nodal.ercot.com 1Lead from the front

Texas Nodal

Early Delivery System

Testing Planning – Involving Market Participants

TPTF

May 22, 2007

Page 2: Early Delivery System

http://nodal.ercot.com 2Lead from the front

Texas Nodal

Objectives for today’s presentation

• Discuss EDS 3 Plan document TPTF comments• Get acceptance of the EDS Timeline plan as a baseline• Get agreement on additional MP involvement and the

concept of the MP Handbook • Share the focus and content for the first EDS 3 MP

Workshop on 24th May

Page 3: Early Delivery System

http://nodal.ercot.com 3Lead from the front

Texas Nodal

Market Trials Approach No Longer Valid

• This document was presented to TPTF twice in November 2006

• Not approved due to insufficient detail

• Document contained approaches and dates no longer valid

• This document has been archived on the Nodal site, please disregard and do not use as a reference

Page 4: Early Delivery System

http://nodal.ercot.com 4Lead from the front

Texas Nodal

EDS 3 Plan - Response Approach & Main Comment Categories

Comments responded to were included in the document and the necessary responses included in the spreadsheet

Comment category Action

Timeline – July vs. October What is mandatory?

A table was added to Section 1.4 of the document clearly explaining each phase as defined by ERCOT

Further detail required

Testing process

Data inputs and outputs

Entry & exit criteria

MP Readiness activities and timing

Further detail added where available.

The remaining detail will be gathered at the EDS Planning Workshops

ERCOT will compile draft white papers –SCED details and gaps will be addressed and the document finalized from the EDS Planning Workshop with MPs

Present to TPTF for approval

Market Participant Handbook clarification

Explanation of MP Handbook added to Section 1.5

This document will be further explained and refined to at the workshop

Suggestions for content

General punctuation

Insertion of content/clarity

Document updated accordingly.

Registration & qualification activities These activities are covered in the relevant Registration /Qualification documents.

An explanation to be added to the introduction in this document for clarity

Request for joint planning workshops going forward

A section added to the document explaining the proposed workshops.

First workshop scheduled for May 24th to discuss SCED testing

Page 5: Early Delivery System

http://nodal.ercot.com 5Lead from the front

Texas Nodal

EDS 3 Plan - Summary of pending issues and plan of action

Comment category Action

Methodology for submitting offers

ERCOT will compile a draft white paper - any details and gaps will be addressed at the first EDS Planning Workshop with MPs on May 24th

SCED input data questions

SCED SMEs will be available at the first EDS Planning Workshop on May 24th to address issues

Interface criteria for SCED Web Services developers will be available at the first EDS Planning Workshop on May 24th to address issues

LFC testing issues EDS Planning Workshop to be scheduled to define solutions with ERCOT SMEs and MPs

All comments in the pending category related to the requirement for further detail and were classified as pending. These areas will be explored further during ongoing planning forums.

Page 6: Early Delivery System

http://nodal.ercot.com 6Lead from the front

Texas Nodal

Planning & MP Involvement Approach

Page 7: Early Delivery System

http://nodal.ercot.com 7Lead from the front

Texas Nodal

Ongoing EDS Planning Process

Planning Phase or Artifact

EDS Approach EDS Plan MP Planning Workshops and WebEX Meetings

MP Handbooks Pre EDS Test Scripts

Content Document defining the phases and artifacts from ERCOT for EDS planning and execution.

Detailed plan defining sufficient detail for MPs to begin planning system functionality and implementation sequence.

Detailed planning sessions to build consensus on data, test cycles, test scenarios, entry and exit criteria to be included in the MP Handbook.

Consolidated agreed content from MP workshops

Calendar, test cycles, contact information, data requirements, test scenarios & scripts etc.

Detailed scenarios and data input requirements for two weeks of testing. To be provided in rolling two week intervals.

Timing November 2006 May 2007 June to September 2007

June to September 2008

July 2007 to Sept 2008

Frequency Once Once Weekly to Monthly by MP type

Complete prior to EDS start. Calendar / Data updates during execution.

Initial release prior to EDS start. Updates & additions during execution.

Output Medium

MS Word posted on Nodal.ercot.com

MS Word posted on Nodal.ercot.com

MS Word posted on Nodal.ercot.com

MS Word posted on Nodal.ercot.com

MS Word posted on Nodal.ercot.com

TPTF Purpose

Informational Informational Informational Approval Approval

Page 8: Early Delivery System

http://nodal.ercot.com 8Lead from the front

Texas Nodal

EDS Testing Artifacts

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecE

DS

3

LMP Data ValidationRegUpload OffersRel 5

Rel 7

Rel 6

6 month LMP Posting

CRR Data Validation Trial Ops of CRR

LFC COMs TestingEDS

EDS 3

LFC Testing

ED

S 4

RTM Go-Live

DAM Go-Live

Legend

Settlements Statements

Upload Bids

Test Settlements

Outages DAM, RUC, SASMFull Nodal Functionality

24*7 Operation 168 Hr Test

EDS

Go-LiveActivities

EDS 4

MP Interface Spec

Major milestones

EDS Preparation Milestones

Rel 8

Rel 9

EDS Approach

EDS 3 Plan

SCED Handbook

LFC Handbook

EDS 4 Plan

CRR Handbook

S&B Handbook

DAM Handbook

168 Hour Test

Handbook

Go-Live Handbook TPTF Approval

TPTF Information

ERCOT & MP Readiness Reporting

EDS Testing Status Reporting

Page 9: Early Delivery System

http://nodal.ercot.com 9Lead from the front

Texas Nodal

The Nodal timeline contains early EDS phases to ensure ERCOT & MP readiness …

ED

S 4

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Alarms Processing

FAT

EMS 2A

ED

S 1

ED

S 2

ED

S 3

FAT – Rel 3

EMS 2B EDW 1

FAT – Release 4

NMMS 1 NMMS 2 EIP 1

FAT – Release 5

REG 1 MMS 1

EMS 2C

EIP 2 S&B 1MIS 1EIP 3

EDW 2

FAT – Release 6

EMS 3EDW 3

EIP 4

FAT – Release 7

EDW 4CRR 1CMM 1 EIP 5

FAT – Release 8

MMS 2S&B 2

EDW 5 EIP 6

FAT – Release 9

MMS 2S&B 2

OS

NMMS 3 EMS 4EDW 6

EIP 7EMS 5 DIS

P2P Checkout

SE Verification

ITEST

RTM Go-Live

DAM Go-Live

EDS 2 Release 3: SE VerEMS- State Estimator & Tel Perf Stds,NSA, SPS/RAP, SCADA and DynRatings for Single Model

EDW– SE Statistics

EDS 2 Release 4: NM VerNMMS- Network Model, NOMCR

EMS- EMS /NMMS Interface

EIP

EDS 3 Release 5: LMPsMMS– SCED

EMS- NSA, RLC

COMS- S&B (FIP, FOP,Ver Costs)- Registration

EIPMISEDW

EDS 3 Release 6: LFC TestingEMS- LFC

EIPEDW

EDS 3 Release 7: CRRCRRCOMS- CMM

EIPEDW

EDS 4 Release 8: RT SettlementsMMS- RT Settlements InterfaceS&BEIP, EDWEDS 4 Release 9: DAM, RUCMMS- All Markets- OSEMS – Load Forecast, Out EvalNMMSS&BEIP, EDW

ITEST

ITEST

LegendIntegration TestingProject FAT Activities

Settlements Statements

Upload Bids

Test Settlements

Outages DAM, RUC, SASMFull Nodal Functionality

24*7 Operation 168 Hr Test

NOMCR Chk out Network Model Verification

Rel 1

Rel 2

EDS 1 Release 1:EMS COTS

EDS 1 Release 2:ICCP Upgrade

Rel 3

FAT

EDS

FAT

ITEST

EDS

FAT

ITEST

EDS

SCED TestingRegUpload Offers

Rel 4

Rel 5

Rel 7

Rel 6

6 month LMP Posting

CRR Data Validation Trial Ops of CRR

LFC Comms Testing

ITEST

EDS

FAT

FAT

EDS

ITEST

ED

S 4 Go-Live

Activities

EDS 1 EDS 2 EDS 3 EDS 4

MP Interface Spec

Start of EDS activities

FAT milestones

EDS Preparatory Milestones

Rel 8

Rel 9

LFC Testing

ReadinessDeclaration

Readiness Declarations

Early Start

Page 10: Early Delivery System

http://nodal.ercot.com 10Lead from the front

Texas Nodal

Participation in the EDS 3 Testing Phases (Section 1.4 – EDS 3 Plan)

Market Participant Type Activities Timeframe Expectation

QSEs with resources planning on utilizing API’s in production

MP Development Connectivity Testing (Sandbox)

July - September Strongly Recommended

MP Connectivity Testing (EDS Environment)

July - September Strongly Recommended

MP Connectivity Testing (EDS Environment)

October Mandatory *

MP Input Validation – SCED Aug – September Strongly Recommended

MP Input Validation – SCED October Mandatory *

MP Input using SCED User Interface October Recommended **

All QSEs with resources

MP Input using SCED User Interface July – September Recommended **

MP Input for SCED Execution October – December Mandatory for designated EDS testing days

MP Input for 6 month LMP Period January – June 2008 Mandatory based on define scenarios and methodology

QSEs with resources not planning on utilizing API’s in production

MP Input using SCED User Interface October Mandatory *

* Starting in October Market Participant involvement is critical to begin producing “Reasonable” LMPs. During this period the Market Participants should have a partial EDS system in place to support the activities and functionality being demonstrated. The EDS team will provide workshops during this time to support Market Participants. Required Market Participants that are not able to participate will have to still perform these activities by requesting a ‘make-up’ workshop prior to involvement in later EDS activities. There will be limited opportunities for support due to focus on other EDS functionality.** The EDS team recommends that all QSEs with resources schedule some time to get familiar with the SCED user interface even if they are planning on utilizing APIs in production. This will help ensure that Market Participants have a second method for accessing the EDS systems if their APIs are not functioning correctly.

Page 11: Early Delivery System

http://nodal.ercot.com 11Lead from the front

Texas Nodal

Texas Nodal

SCED Workshop – 24th May 2007SME Support Requirement Scenario

10 May 2007

Page 12: Early Delivery System

http://nodal.ercot.com 12Lead from the front

Texas Nodal

Workshop Objective and Future Plans

• Share the draft Market Participant Handbook for SCED testing• Answer any planning and testing questions from MPs present• Target MPs at the workshop will be QSEs with resources• The workshop will take place at MET Center and WebEx

facilities will be available throughout• The Market Notice and a reminder has already been sent (see

slide #4)• Answers to the questions provided at the workshop will be

included in the MP Handbook to be used by the MPs during testing

• This workshop will be the first in the series of either monthly meetings or WebEx’s to prepare ERCOT and the MPs for Market Trials which begin in July 2007 – Frequency?

Page 13: Early Delivery System

http://nodal.ercot.com 13Lead from the front

Texas Nodal

*******TEXAS NODAL MARKET NOTICE*******

• NOTICE DATE: May 8, 2007• NOTICE TYPE: General – EDS 3 Planning Workshop• SHORT DESCRIPTION: ERCOT will host the first in a series of EDS 3 Planning Workshops on Thursday, May 24, 2007.• INTENDED AUDIENCE: NTPM and EDS 3 Technical Contacts• DAY AFFECTED: May 24, 2007• LONG DESCRIPTION: To ensure both ERCOT and Market Participants can maximize the benefits of the EDS, ERCOT will be hosting EDS Planning Workshops as well as

ongoing conference calls to complete the details required for EDS 3 execution. This test planning workshop will provide early details on submittal of resource data elements, test preparation, testing scenario review and development, testing calendars, and specific exit criteria for EDS 3.

• The first EDS 3 Planning Workshop is scheduled on Thursday, May 24, 2007 from 9:00 a.m. until 4:00 p.m. This workshop is targeted to Nodal Transition Project Managers and EDS technical planning team members involved in Security Constrained Economic Dispatch (SCED) input and validation testing. The agenda for this workshop will be distributed with all workshop materials prior to the meeting date.

• The agenda topics for the first EDS 3 Planning Workshop include: • EDS 3 Readiness Activities• Walkthrough EDS 3 SCED workshop materials, which will be distributed to participants prior to the workshop

– Phase 1 – July through September Activities– Phase 2 – October through December Activities – Input data methodology– Participant feedback, comments, key issues

• Technical Questions and Answers with Project Subject Matter Experts on the MMS and EIP• EDS 3 Entry & Exit Criteria Discussion – Per Phase• Open Question & Answer period

– Discuss Ongoing Planning Forums• ACTION REQUIRED: Please RSVP by replying to this notice or sending an email to [email protected]. Please provide the Market Participant company

you are representing as well as additional attendees and their email addresses. If you wish to designate an alternate in your place, please indicate so in your RSVP.• ADDITIONAL INFORMATION: The seminar will be held on Thursday, May 24, 2007 from 9:00 a.m. until 4:00 p.m. CDT at:• ERCOT Austin• 7620 Metro Center Drive• Room 206• Austin, Texas 78744• 512-225-7000• A map and driving directions can be found at http://www.ercot.com/about/locations/map_austin.html.• To participate in the workshop using WebEx, follow the steps below: • 1. Go to https://ercot.webex.com/ercot/j.php?ED=1609438&UID=0 • 2. Enter your name and email address. • 3. Enter the meeting password: EDS3123!! • 4. Click "Join". • 5. You will be provided a dial-in telephone number upon joining the WebEx.• CONTACT: If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-

3900 or contact ERCOT Client Services via e-mail at [email protected].• If you are receiving e-mail from an ERCOT distribution list that you no longer wish to receive, please follow this link in order to unsubscribe from this list. • (http://lists.ercot.com/cgi-bin/majordomo?module=)

Page 14: Early Delivery System

http://nodal.ercot.com 14Lead from the front

Texas Nodal

Typical Questions (Not all MMS or SCED related)

• What are ERCOT’s expectations of hardware on the MP side? Does ERCOT expect MP’s to have “go-live” hardware installations in place by July?

• Does the previously published SLA apply to the “Early” EDS testing of July – September?• When will MP’s receive the testing scripts referenced in 2.2.1? Also, in the same section, there is a reference

to a Communication Process/Tool. Is this in place and documented or is it referring to the SLA?• On the EDS 3 Staffing Organizational Chart (7.2), can you please include names where possible? This is

shown on the EDS 1 Chart and we have found it very helpful.• Please elaborate on “Mock Settlement Statements” and what this means (Section 5). We need more detail on

what “Mock Settlement” looks like and what software we need to have in place to be ready. More importantly, our vendors need to have more clarity.

• When will the “Error Notification API” be delivered (2.2)? This API is a crucial deliverable for effective testing and debugging of software problems.

• Note: how do MPs see the data which have been accepted by ERCOT?• Execution of SCED utilizing Real-Time ICCP data – October 07 - does this step include the ability to create

proxy curves?• SCED MIS Reporting – November 07 – can MPs see their Resource HASLs, LASLs, SURAMPs, SDRAMPs,

HDLs, LDLs via MIS?• QSE Interactions with Interface Testing – is this required to access MIS and/or to use Machine-to-Machine

interface?• Each Resource’s responses will be measured against the regulation signals - will LFC ability to calculate and

issue Emergency Base Point be tested? • The QSE under test will be asked to submit resource level base points to match its schedule for the test hour.

The base points provided should be at 5 min intervals - can QSEs send their resource Base Points to ERCOT via ICCP?

• SCED (for base points) - which function calculates the proxy curves? Is it part of this package?

Page 15: Early Delivery System

http://nodal.ercot.com 15Lead from the front

Texas Nodal

Agenda - AM

Agenda for EDS 3 Planning Workshop Thursday – May 24, 2007- 9:00pm-4:00pmLocation: ERCOT Austin MetCenterWebEx Conference (https://ercot.webex.com/ercot) Teleconference: TBD Meeting number: TBD Meeting password: TBD

Thursday May 24th

1. Meeting KickoffoReview AgendaoMeeting LogisticsoTeam IntroductionoEDS Overview

J. Hall 9:00 am

2. EDS Readiness ActivitiesoNodal SandboxoQualification

M. Mereness 9:15 am

3. Walkthrough of Market Participant Handbook (EDS 3 initial draft)oEDS July - September ActivitiesoParticipant Handbook feedback & commentsoInput data methodologyoGroup questions and discussions

K. KasparianK. Sumanam

9:30 am

4. Break 10:45 am

5. Walkthrough of Market Participant Handbook (EDS 3 initial draft)oEDS October - December ActivitiesoParticipant Handbook feedback & commentsoInput data methodologyoGroup questions and discussions

J. HallC. Gamoke

11:00 am

6. Lunch Break (60 min)

Page 16: Early Delivery System

http://nodal.ercot.com 16Lead from the front

Texas Nodal

Agenda - PM

6. Lunch Break (60 min)

7. Technical Questions & AnswersoMMS Project TeamsoExternal Web ServicesoRequested topics

Project SMEs 1:00 pm

8. EDS 3 Entry & Exit Criteria Discussion – Per Phase C. Gamoke 2:30 pm

9. Open Question & Answer periodoReview Questions from Handbook FeedbackoDiscuss Written Questions from Audience

EDS Team 3:30 pm

10. Discuss Ongoing Planning ForumsoIdentify ItemsoWebX & conference call datesoFuture Workshops

J. Hall 3:30 pm

Adjourn

End by 4pm