http://nodal.ercot.com 1Lead from the front
Texas Nodal
Early Delivery System
Testing Planning – Involving Market Participants
TPTF
May 22, 2007
http://nodal.ercot.com 2Lead from the front
Texas Nodal
Objectives for today’s presentation
• Discuss EDS 3 Plan document TPTF comments• Get acceptance of the EDS Timeline plan as a baseline• Get agreement on additional MP involvement and the
concept of the MP Handbook • Share the focus and content for the first EDS 3 MP
Workshop on 24th May
http://nodal.ercot.com 3Lead from the front
Texas Nodal
Market Trials Approach No Longer Valid
• This document was presented to TPTF twice in November 2006
• Not approved due to insufficient detail
• Document contained approaches and dates no longer valid
• This document has been archived on the Nodal site, please disregard and do not use as a reference
http://nodal.ercot.com 4Lead from the front
Texas Nodal
EDS 3 Plan - Response Approach & Main Comment Categories
Comments responded to were included in the document and the necessary responses included in the spreadsheet
Comment category Action
Timeline – July vs. October What is mandatory?
A table was added to Section 1.4 of the document clearly explaining each phase as defined by ERCOT
Further detail required
Testing process
Data inputs and outputs
Entry & exit criteria
MP Readiness activities and timing
Further detail added where available.
The remaining detail will be gathered at the EDS Planning Workshops
ERCOT will compile draft white papers –SCED details and gaps will be addressed and the document finalized from the EDS Planning Workshop with MPs
Present to TPTF for approval
Market Participant Handbook clarification
Explanation of MP Handbook added to Section 1.5
This document will be further explained and refined to at the workshop
Suggestions for content
General punctuation
Insertion of content/clarity
Document updated accordingly.
Registration & qualification activities These activities are covered in the relevant Registration /Qualification documents.
An explanation to be added to the introduction in this document for clarity
Request for joint planning workshops going forward
A section added to the document explaining the proposed workshops.
First workshop scheduled for May 24th to discuss SCED testing
http://nodal.ercot.com 5Lead from the front
Texas Nodal
EDS 3 Plan - Summary of pending issues and plan of action
Comment category Action
Methodology for submitting offers
ERCOT will compile a draft white paper - any details and gaps will be addressed at the first EDS Planning Workshop with MPs on May 24th
SCED input data questions
SCED SMEs will be available at the first EDS Planning Workshop on May 24th to address issues
Interface criteria for SCED Web Services developers will be available at the first EDS Planning Workshop on May 24th to address issues
LFC testing issues EDS Planning Workshop to be scheduled to define solutions with ERCOT SMEs and MPs
All comments in the pending category related to the requirement for further detail and were classified as pending. These areas will be explored further during ongoing planning forums.
http://nodal.ercot.com 6Lead from the front
Texas Nodal
Planning & MP Involvement Approach
http://nodal.ercot.com 7Lead from the front
Texas Nodal
Ongoing EDS Planning Process
Planning Phase or Artifact
EDS Approach EDS Plan MP Planning Workshops and WebEX Meetings
MP Handbooks Pre EDS Test Scripts
Content Document defining the phases and artifacts from ERCOT for EDS planning and execution.
Detailed plan defining sufficient detail for MPs to begin planning system functionality and implementation sequence.
Detailed planning sessions to build consensus on data, test cycles, test scenarios, entry and exit criteria to be included in the MP Handbook.
Consolidated agreed content from MP workshops
Calendar, test cycles, contact information, data requirements, test scenarios & scripts etc.
Detailed scenarios and data input requirements for two weeks of testing. To be provided in rolling two week intervals.
Timing November 2006 May 2007 June to September 2007
June to September 2008
July 2007 to Sept 2008
Frequency Once Once Weekly to Monthly by MP type
Complete prior to EDS start. Calendar / Data updates during execution.
Initial release prior to EDS start. Updates & additions during execution.
Output Medium
MS Word posted on Nodal.ercot.com
MS Word posted on Nodal.ercot.com
MS Word posted on Nodal.ercot.com
MS Word posted on Nodal.ercot.com
MS Word posted on Nodal.ercot.com
TPTF Purpose
Informational Informational Informational Approval Approval
http://nodal.ercot.com 8Lead from the front
Texas Nodal
EDS Testing Artifacts
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecE
DS
3
LMP Data ValidationRegUpload OffersRel 5
Rel 7
Rel 6
6 month LMP Posting
CRR Data Validation Trial Ops of CRR
LFC COMs TestingEDS
EDS 3
LFC Testing
ED
S 4
RTM Go-Live
DAM Go-Live
Legend
Settlements Statements
Upload Bids
Test Settlements
Outages DAM, RUC, SASMFull Nodal Functionality
24*7 Operation 168 Hr Test
EDS
Go-LiveActivities
EDS 4
MP Interface Spec
Major milestones
EDS Preparation Milestones
Rel 8
Rel 9
EDS Approach
EDS 3 Plan
SCED Handbook
LFC Handbook
EDS 4 Plan
CRR Handbook
S&B Handbook
DAM Handbook
168 Hour Test
Handbook
Go-Live Handbook TPTF Approval
TPTF Information
ERCOT & MP Readiness Reporting
EDS Testing Status Reporting
http://nodal.ercot.com 9Lead from the front
Texas Nodal
The Nodal timeline contains early EDS phases to ensure ERCOT & MP readiness …
ED
S 4
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Alarms Processing
FAT
EMS 2A
ED
S 1
ED
S 2
ED
S 3
FAT – Rel 3
EMS 2B EDW 1
FAT – Release 4
NMMS 1 NMMS 2 EIP 1
FAT – Release 5
REG 1 MMS 1
EMS 2C
EIP 2 S&B 1MIS 1EIP 3
EDW 2
FAT – Release 6
EMS 3EDW 3
EIP 4
FAT – Release 7
EDW 4CRR 1CMM 1 EIP 5
FAT – Release 8
MMS 2S&B 2
EDW 5 EIP 6
FAT – Release 9
MMS 2S&B 2
OS
NMMS 3 EMS 4EDW 6
EIP 7EMS 5 DIS
P2P Checkout
SE Verification
ITEST
RTM Go-Live
DAM Go-Live
EDS 2 Release 3: SE VerEMS- State Estimator & Tel Perf Stds,NSA, SPS/RAP, SCADA and DynRatings for Single Model
EDW– SE Statistics
EDS 2 Release 4: NM VerNMMS- Network Model, NOMCR
EMS- EMS /NMMS Interface
EIP
EDS 3 Release 5: LMPsMMS– SCED
EMS- NSA, RLC
COMS- S&B (FIP, FOP,Ver Costs)- Registration
EIPMISEDW
EDS 3 Release 6: LFC TestingEMS- LFC
EIPEDW
EDS 3 Release 7: CRRCRRCOMS- CMM
EIPEDW
EDS 4 Release 8: RT SettlementsMMS- RT Settlements InterfaceS&BEIP, EDWEDS 4 Release 9: DAM, RUCMMS- All Markets- OSEMS – Load Forecast, Out EvalNMMSS&BEIP, EDW
ITEST
ITEST
LegendIntegration TestingProject FAT Activities
Settlements Statements
Upload Bids
Test Settlements
Outages DAM, RUC, SASMFull Nodal Functionality
24*7 Operation 168 Hr Test
NOMCR Chk out Network Model Verification
Rel 1
Rel 2
EDS 1 Release 1:EMS COTS
EDS 1 Release 2:ICCP Upgrade
Rel 3
FAT
EDS
FAT
ITEST
EDS
FAT
ITEST
EDS
SCED TestingRegUpload Offers
Rel 4
Rel 5
Rel 7
Rel 6
6 month LMP Posting
CRR Data Validation Trial Ops of CRR
LFC Comms Testing
ITEST
EDS
FAT
FAT
EDS
ITEST
ED
S 4 Go-Live
Activities
EDS 1 EDS 2 EDS 3 EDS 4
MP Interface Spec
Start of EDS activities
FAT milestones
EDS Preparatory Milestones
Rel 8
Rel 9
LFC Testing
ReadinessDeclaration
Readiness Declarations
Early Start
http://nodal.ercot.com 10Lead from the front
Texas Nodal
Participation in the EDS 3 Testing Phases (Section 1.4 – EDS 3 Plan)
Market Participant Type Activities Timeframe Expectation
QSEs with resources planning on utilizing API’s in production
MP Development Connectivity Testing (Sandbox)
July - September Strongly Recommended
MP Connectivity Testing (EDS Environment)
July - September Strongly Recommended
MP Connectivity Testing (EDS Environment)
October Mandatory *
MP Input Validation – SCED Aug – September Strongly Recommended
MP Input Validation – SCED October Mandatory *
MP Input using SCED User Interface October Recommended **
All QSEs with resources
MP Input using SCED User Interface July – September Recommended **
MP Input for SCED Execution October – December Mandatory for designated EDS testing days
MP Input for 6 month LMP Period January – June 2008 Mandatory based on define scenarios and methodology
QSEs with resources not planning on utilizing API’s in production
MP Input using SCED User Interface October Mandatory *
* Starting in October Market Participant involvement is critical to begin producing “Reasonable” LMPs. During this period the Market Participants should have a partial EDS system in place to support the activities and functionality being demonstrated. The EDS team will provide workshops during this time to support Market Participants. Required Market Participants that are not able to participate will have to still perform these activities by requesting a ‘make-up’ workshop prior to involvement in later EDS activities. There will be limited opportunities for support due to focus on other EDS functionality.** The EDS team recommends that all QSEs with resources schedule some time to get familiar with the SCED user interface even if they are planning on utilizing APIs in production. This will help ensure that Market Participants have a second method for accessing the EDS systems if their APIs are not functioning correctly.
http://nodal.ercot.com 11Lead from the front
Texas Nodal
Texas Nodal
SCED Workshop – 24th May 2007SME Support Requirement Scenario
10 May 2007
http://nodal.ercot.com 12Lead from the front
Texas Nodal
Workshop Objective and Future Plans
• Share the draft Market Participant Handbook for SCED testing• Answer any planning and testing questions from MPs present• Target MPs at the workshop will be QSEs with resources• The workshop will take place at MET Center and WebEx
facilities will be available throughout• The Market Notice and a reminder has already been sent (see
slide #4)• Answers to the questions provided at the workshop will be
included in the MP Handbook to be used by the MPs during testing
• This workshop will be the first in the series of either monthly meetings or WebEx’s to prepare ERCOT and the MPs for Market Trials which begin in July 2007 – Frequency?
http://nodal.ercot.com 13Lead from the front
Texas Nodal
*******TEXAS NODAL MARKET NOTICE*******
• NOTICE DATE: May 8, 2007• NOTICE TYPE: General – EDS 3 Planning Workshop• SHORT DESCRIPTION: ERCOT will host the first in a series of EDS 3 Planning Workshops on Thursday, May 24, 2007.• INTENDED AUDIENCE: NTPM and EDS 3 Technical Contacts• DAY AFFECTED: May 24, 2007• LONG DESCRIPTION: To ensure both ERCOT and Market Participants can maximize the benefits of the EDS, ERCOT will be hosting EDS Planning Workshops as well as
ongoing conference calls to complete the details required for EDS 3 execution. This test planning workshop will provide early details on submittal of resource data elements, test preparation, testing scenario review and development, testing calendars, and specific exit criteria for EDS 3.
• The first EDS 3 Planning Workshop is scheduled on Thursday, May 24, 2007 from 9:00 a.m. until 4:00 p.m. This workshop is targeted to Nodal Transition Project Managers and EDS technical planning team members involved in Security Constrained Economic Dispatch (SCED) input and validation testing. The agenda for this workshop will be distributed with all workshop materials prior to the meeting date.
• The agenda topics for the first EDS 3 Planning Workshop include: • EDS 3 Readiness Activities• Walkthrough EDS 3 SCED workshop materials, which will be distributed to participants prior to the workshop
– Phase 1 – July through September Activities– Phase 2 – October through December Activities – Input data methodology– Participant feedback, comments, key issues
• Technical Questions and Answers with Project Subject Matter Experts on the MMS and EIP• EDS 3 Entry & Exit Criteria Discussion – Per Phase• Open Question & Answer period
– Discuss Ongoing Planning Forums• ACTION REQUIRED: Please RSVP by replying to this notice or sending an email to [email protected]. Please provide the Market Participant company
you are representing as well as additional attendees and their email addresses. If you wish to designate an alternate in your place, please indicate so in your RSVP.• ADDITIONAL INFORMATION: The seminar will be held on Thursday, May 24, 2007 from 9:00 a.m. until 4:00 p.m. CDT at:• ERCOT Austin• 7620 Metro Center Drive• Room 206• Austin, Texas 78744• 512-225-7000• A map and driving directions can be found at http://www.ercot.com/about/locations/map_austin.html.• To participate in the workshop using WebEx, follow the steps below: • 1. Go to https://ercot.webex.com/ercot/j.php?ED=1609438&UID=0 • 2. Enter your name and email address. • 3. Enter the meeting password: EDS3123!! • 4. Click "Join". • 5. You will be provided a dial-in telephone number upon joining the WebEx.• CONTACT: If you have any questions, please contact your ERCOT Account Manager. You may also call the general ERCOT Client Services phone number at (512) 248-
3900 or contact ERCOT Client Services via e-mail at [email protected].• If you are receiving e-mail from an ERCOT distribution list that you no longer wish to receive, please follow this link in order to unsubscribe from this list. • (http://lists.ercot.com/cgi-bin/majordomo?module=)
http://nodal.ercot.com 14Lead from the front
Texas Nodal
Typical Questions (Not all MMS or SCED related)
• What are ERCOT’s expectations of hardware on the MP side? Does ERCOT expect MP’s to have “go-live” hardware installations in place by July?
• Does the previously published SLA apply to the “Early” EDS testing of July – September?• When will MP’s receive the testing scripts referenced in 2.2.1? Also, in the same section, there is a reference
to a Communication Process/Tool. Is this in place and documented or is it referring to the SLA?• On the EDS 3 Staffing Organizational Chart (7.2), can you please include names where possible? This is
shown on the EDS 1 Chart and we have found it very helpful.• Please elaborate on “Mock Settlement Statements” and what this means (Section 5). We need more detail on
what “Mock Settlement” looks like and what software we need to have in place to be ready. More importantly, our vendors need to have more clarity.
• When will the “Error Notification API” be delivered (2.2)? This API is a crucial deliverable for effective testing and debugging of software problems.
• Note: how do MPs see the data which have been accepted by ERCOT?• Execution of SCED utilizing Real-Time ICCP data – October 07 - does this step include the ability to create
proxy curves?• SCED MIS Reporting – November 07 – can MPs see their Resource HASLs, LASLs, SURAMPs, SDRAMPs,
HDLs, LDLs via MIS?• QSE Interactions with Interface Testing – is this required to access MIS and/or to use Machine-to-Machine
interface?• Each Resource’s responses will be measured against the regulation signals - will LFC ability to calculate and
issue Emergency Base Point be tested? • The QSE under test will be asked to submit resource level base points to match its schedule for the test hour.
The base points provided should be at 5 min intervals - can QSEs send their resource Base Points to ERCOT via ICCP?
• SCED (for base points) - which function calculates the proxy curves? Is it part of this package?
http://nodal.ercot.com 15Lead from the front
Texas Nodal
Agenda - AM
Agenda for EDS 3 Planning Workshop Thursday – May 24, 2007- 9:00pm-4:00pmLocation: ERCOT Austin MetCenterWebEx Conference (https://ercot.webex.com/ercot) Teleconference: TBD Meeting number: TBD Meeting password: TBD
Thursday May 24th
1. Meeting KickoffoReview AgendaoMeeting LogisticsoTeam IntroductionoEDS Overview
J. Hall 9:00 am
2. EDS Readiness ActivitiesoNodal SandboxoQualification
M. Mereness 9:15 am
3. Walkthrough of Market Participant Handbook (EDS 3 initial draft)oEDS July - September ActivitiesoParticipant Handbook feedback & commentsoInput data methodologyoGroup questions and discussions
K. KasparianK. Sumanam
9:30 am
4. Break 10:45 am
5. Walkthrough of Market Participant Handbook (EDS 3 initial draft)oEDS October - December ActivitiesoParticipant Handbook feedback & commentsoInput data methodologyoGroup questions and discussions
J. HallC. Gamoke
11:00 am
6. Lunch Break (60 min)
http://nodal.ercot.com 16Lead from the front
Texas Nodal
Agenda - PM
6. Lunch Break (60 min)
7. Technical Questions & AnswersoMMS Project TeamsoExternal Web ServicesoRequested topics
Project SMEs 1:00 pm
8. EDS 3 Entry & Exit Criteria Discussion – Per Phase C. Gamoke 2:30 pm
9. Open Question & Answer periodoReview Questions from Handbook FeedbackoDiscuss Written Questions from Audience
EDS Team 3:30 pm
10. Discuss Ongoing Planning ForumsoIdentify ItemsoWebX & conference call datesoFuture Workshops
J. Hall 3:30 pm
Adjourn
End by 4pm