Early Completion Schedules

21

Click here to load reader

description

An Early Completion Schedule is Defined as submission of an as-planned schedule showing earlier completion than contractually mandated

Transcript of Early Completion Schedules

Page 1: Early Completion Schedules

SEI Scheduling

SCHEDULING COMMUNITY OF PRACTICE

Scheduling Excellence Initiative

Featuring

Early Completion SchedulesSchedulingExcellence Initiative

Early Completion Schedules

Chris Carson, PSP

Corporate Director of Project Controls

Alpha Corporation

[email protected]

757-342-5524

Page 2: Early Completion Schedules

SEI Scheduling

SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE

SEI Update

• Best Practices & Guidelines for Scheduling

– Releasing first draft to start peer review

– Available at 2011 Annual Meeting

– Goal is to complete by end of 2011

• Best Practices & Guidelines for Schedule SchedulingExcellence Initiative

• Best Practices & Guidelines for Schedule

Impact Analysis, Volume 1

– Producing work product

– Need volunteers to help develop topics

– Goal is to release peer review draft end of 2012

• Joint Collaborative Project with AACEi

– Developing study - Quality Control Metrics

� Percentage of CP activities, Ratio of relationships to

activities, etc.PMI College of Scheduling

“PMI” is a registered trade and service mark of the Project Management Institute, Inc.2

Page 3: Early Completion Schedules

SEI Scheduling

SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE

SEI Update

• Best Practices & Guidelines for Scheduling

– Copy of Table of Contents available on SCoP website – “Share – Documents – Document Exchange – Documents – SEI – SM”

– “2010-06-04 BPG Volume 1 Final Outline”SchedulingExcellence Initiative

• Best Practices & Guidelines for Schedule

Impact Analysis

– Copy of Table of Contents available on SCoP website – “Share – Documents – Document Exchange – Documents – SEI – SIA”

– “2008-03-01 SIA Outline – Volume I”

– “2008-04-30 SIA Outline – Volume II” (future effort)

PMI College of Scheduling

“PMI” is a registered trade and service mark of the Project Management Institute, Inc.3

Page 4: Early Completion Schedules

SEI Scheduling

SCHEDULING COMMUNITY OF PRACTICE

SEI PublicationsSEI Publications

PMI College of Scheduling

Best Practices

& Guidelines

Best Practices

& Guidelines

Project Planning

And Scheduling

Project Planning

And Scheduling

Volume IVolume I

PMI College of Scheduling

Best Practices

& Guidelines

Best Practices

& Guidelines

Project Planning

And Scheduling

Project Planning

And Scheduling

Volume IVolume I

SchedulingExcellence Initiative

Page 5: Early Completion Schedules

SEI Scheduling

SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE

Best Practices & Guidelines

• Topic authors and reviewers must answer six

basic questions about each topic:

– Definition

� What is it?

– PurposeSchedulingExcellence Initiative

– Purpose

� Why is it used?

– Default Condition

� When & under what conditions is it used?

– Best Practices

� What are acceptable implementations?

– Recommended Practice

� Is there a preferred implementation?

– Admonitions & Advisories

� What should be avoided? 5

Page 6: Early Completion Schedules

SEI Scheduling

SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE

SEI Update

• SEI Core Team

– Chris Carson, Managing Director, SEI

– Pete Oakander, Deputy Director, SEI

– Craig Relyea, Editorial Team Leader, SEI

• Best Practices & Guidelines for SchedulingSchedulingExcellence Initiative

• Best Practices & Guidelines for Scheduling

– Laura Williams, Volume Manager

– Recipient of the 2011 award for “Contribution to College of Scheduling/SCoP”

• Best Practices and Guidelines for Schedule

Impact Analysis

– Mark Sanders, Volume Co-Manager

– Mark Nagata, Volume Co-Manager

PMI College of Scheduling

“PMI” is a registered trade and service mark of the Project Management Institute, Inc.6

Page 7: Early Completion Schedules

SEI Scheduling

SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE

Early Completion Schedules

� Copies of the Early Completion Schedules

draft documents available on website� “Share – Documents – Document Exchange – Documents –

SEI Webinar BPG Topics

� Early Completion SchedulesSchedulingExcellence Initiative

PMI College of Scheduling

“PMI” is a registered trade and service mark of the Project Management Institute, Inc.7

� Defined as submission of an as-planned schedule showing earlier completion than contractually mandated

� Early Completion Schedules

� Inadvertent

� Intentional

Page 8: Early Completion Schedules

SEI Scheduling

SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE

Early Completion Schedules

� Inadvertent Early Completion Schedules� Usually not done intentionally

� May be missing scope

� May be rushed and just not finished

� May not have involved full PM team

� Not done for a specific reasonSchedulingExcellence Initiative

PMI College of Scheduling

“PMI” is a registered trade and service mark of the Project Management Institute, Inc.8

� Not done for a specific reason

� Intentional Early Completion Schedules� Developed to minimize time on project

� Developed to provide a “buffer” for completion

� Expects to be allowed to complete early

� Expects to be paid extended GC for owner delays

from early date, not just contract completion date

� May or may not provide notification of intent to finish

early

Page 9: Early Completion Schedules

SEI Scheduling

SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE

Early Completion Schedules

� Inadvertent Early Completion Schedules

� Owner perspective

� Should prompt careful review� Verify reasonableness

� Verify full scope of work

� Verify inclusion of all non-work activities that might SchedulingExcellence Initiative

PMI College of Scheduling

“PMI” is a registered trade and service mark of the Project Management Institute, Inc.9

� Verify inclusion of all non-work activities that might

drive the schedule

� Determine if schedule represents full PM team

participation

� Verify resource planning and logic/sequencing

� Verify inclusion of reasonable weather planning

� Determine use of risk management

� Review coordination and owner-responsible activities

carefully

Page 10: Early Completion Schedules

SEI Scheduling

SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE

Early Completion Schedules

� Inadvertent Early Completion Schedules

� Owner perspective

� Share review results with contractor

� Recommend revision to accommodate missing items

SchedulingExcellence Initiative

PMI College of Scheduling

“PMI” is a registered trade and service mark of the Project Management Institute, Inc.10

� Once contractor has verified quality control and reasonable schedule, resubmission still requires careful secondary review

� Generally when owner questions contractor’s schedule, providing feedback in detail, revised schedule consumes more of the project duration

Page 11: Early Completion Schedules

SEI Scheduling

SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE

Early Completion Schedules

� Inadvertent Early Completion Schedules

� Contractor perspective

� Should prompt careful QC review� Verify resource planning and logic/sequencing

� Verify inclusion of reasonable weather planning

� Ensure use of risk management, particularly SchedulingExcellence Initiative

PMI College of Scheduling

“PMI” is a registered trade and service mark of the Project Management Institute, Inc.11

� Ensure use of risk management, particularly

identifying high risk activities and processes

� Provide careful Written Narrative to ensure that all

assumptions and requirements of the owner are

identified

� Schedule should provide reasonable expectation of

meeting project milestones, not overly optimistic or

pessimistic

� Revise as necessary and submit

Page 12: Early Completion Schedules

SEI Scheduling

SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE

Early Completion Schedules

� Intentional Early Completion Schedules

� Owner perspective

� Proactive steps

� Address in contract documents

� Require as-planned schedule shows contractual

completionSchedulingExcellence Initiative

PMI College of Scheduling

“PMI” is a registered trade and service mark of the Project Management Institute, Inc.12

completion

� Require constraint on contractual milestones

� Forbid float in as-planned schedule

� Simply state that early completion schedules will

not be accepted

� Provide change order to reduce the contractual

completion to the early completion date

� Allow a contingency activity prior to Substantial

Completion – mandate joint ownership of

contingency time (float)

� Provide incentive contingency activity

Page 13: Early Completion Schedules

SEI Scheduling

SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE

Early Completion Schedules

� Intentional Early Completion Schedules

� Owner perspective

� Raises specific risks� Check to see that schedule does not impose

additional requirements on owner

� Short review timesSchedulingExcellence Initiative

PMI College of Scheduling

“PMI” is a registered trade and service mark of the Project Management Institute, Inc.13

� Short review times

� Early equipment delivery

� Other project coordination issues

� Owner will pick up maintenance and operating

charges from early completion date

� End user might have to occupy early

� Salaries will start early

� Third party coordination may be more difficult

� If the early completion schedule is too aggressive,

there is uncertainty in completion predictions

Page 14: Early Completion Schedules

SEI Scheduling

SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE

Early Completion Schedules

� Intentional Early Completion Schedules

� Owner perspective

� Legal risks may occur

� Failure to notify and/or spec language

precluding early completion may not be an

absolute bar to damages recovery when owner SchedulingExcellence Initiative

PMI College of Scheduling

“PMI” is a registered trade and service mark of the Project Management Institute, Inc.14

absolute bar to damages recovery when owner

causes delays

Page 15: Early Completion Schedules

SEI Scheduling

SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE

Early Completion Schedules

� Intentional Early Completion Schedules

� Contractor perspective

� Contractor needs to identify true need for early completion schedule

� Due to limited general conditions costs, should

document and follow early completion requirementsSchedulingExcellence Initiative

PMI College of Scheduling

“PMI” is a registered trade and service mark of the Project Management Institute, Inc.15

document and follow early completion requirements

� Due to attempt to limit risk of late completion, should

discuss with owner and negotiate some buffer solution

� Due to limited resource availability, verify and choose

solution to support the risk

� With true need identified, contractor can take

measures to limit risks

Page 16: Early Completion Schedules

SEI Scheduling

SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE

Early Completion Schedules

� Intentional Early Completion Schedules

� Contractor perspective

� Owner ability to simply move completion date to early completion schedule date could result in liquidated damages based on early date

SchedulingExcellence Initiative

PMI College of Scheduling

“PMI” is a registered trade and service mark of the Project Management Institute, Inc.16

� Float will likely still belong to project so owner-responsible changes might use up float

� Contractor could be required to stay on project beyond

early completion date to handle changes with no

additional general conditions costs

� This is still a risk with good production when the

project is ahead of schedule – owner changes could

still force contractor to remain on job

� But bid would have included full term GC costs

Page 17: Early Completion Schedules

SEI Scheduling

SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE

Early Completion Schedules

� Intentional Early Completion Schedules

� Contractor perspective

� In order to recover damages from delayed early completion, contractor must show:

� Always intended to finish early

� Had the ability to finish earlySchedulingExcellence Initiative

PMI College of Scheduling

“PMI” is a registered trade and service mark of the Project Management Institute, Inc.17

� Had the ability to finish early

� Would have finished early but for owner actions

� Without these conditions, contractor likely will not

prevail with an early completion claim in litigation

� Could also notify owner that project was bid with only

general conditions for the early completion duration

� Jurisdictional differences in litigation make resolution

uncertain for both parties

� Ownership of float could be problematic if owner

attempts to retain

Page 18: Early Completion Schedules

SEI Scheduling

SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE

Early Completion Schedules

� Intentional Early Completion Schedules

� General recommendations

� Quality of as-planned schedule must be validated

before deciding on ability to finish early

� Risk management should be incorporated into

schedule to raise the probability of meeting SchedulingExcellence Initiative

PMI College of Scheduling

“PMI” is a registered trade and service mark of the Project Management Institute, Inc.18

schedule to raise the probability of meeting

scheduled completion

� Both parties should negotiate early completion

� Look at contingency options to provide some

protection

� Adjust contractual completion date

� If conditions work for owner, agree, and adjust contractual completion to early date

� If contractor is comfortable about schedule predictions, agree to adjust contractual completion

Page 19: Early Completion Schedules

SEI Scheduling

SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE

SEI Best Practices and Guidelines for Scheduling

• Plans for published volume

– Working to get universities that provide CM education involved with peer review

– Plan to get copies into CM education departments as reference book

SchedulingExcellence Initiative

– Goal is to have volume reviewed, correlated, and published by 2012

• Opportunities for volunteers

– BP&G for Scheduling

� Develop remaining work product

� Opportunities for peer review

– BP&G for Schedule Impact Analysis

� Develop primary work product

� Influence best practice recommendations 19

Page 20: Early Completion Schedules

SEI Scheduling

SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE

Early Completion Schedules

Questions?

Recommendations?

War Stories?SchedulingExcellence Initiative

PMI College of Scheduling

“PMI” is a registered trade and service mark of the Project Management Institute, Inc.20

War Stories?

Gripes?

Page 21: Early Completion Schedules

SEI Scheduling

SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE

Chris Carson, PSP

BP&G for Scheduling

Early Completion Schedules

SchedulingExcellence Initiative

PMI College of Scheduling

“PMI” is a registered trade and service mark of the Project Management Institute, Inc.21

Chris Carson, PSP

Corporate Director of Project Controls

Alpha Corporation

101 West Main Street, Suite 7100

Norfolk, VA 23510

757-533-9368 Office

757-342-5524 Mobile

[email protected]