Early Completion Schedules
Click here to load reader
-
Upload
chris-carson -
Category
Business
-
view
1.484 -
download
0
description
Transcript of Early Completion Schedules
SEI Scheduling
SCHEDULING COMMUNITY OF PRACTICE
Scheduling Excellence Initiative
Featuring
Early Completion SchedulesSchedulingExcellence Initiative
Early Completion Schedules
Chris Carson, PSP
Corporate Director of Project Controls
Alpha Corporation
757-342-5524
SEI Scheduling
SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE
SEI Update
• Best Practices & Guidelines for Scheduling
– Releasing first draft to start peer review
– Available at 2011 Annual Meeting
– Goal is to complete by end of 2011
• Best Practices & Guidelines for Schedule SchedulingExcellence Initiative
• Best Practices & Guidelines for Schedule
Impact Analysis, Volume 1
– Producing work product
– Need volunteers to help develop topics
– Goal is to release peer review draft end of 2012
• Joint Collaborative Project with AACEi
– Developing study - Quality Control Metrics
� Percentage of CP activities, Ratio of relationships to
activities, etc.PMI College of Scheduling
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.2
SEI Scheduling
SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE
SEI Update
• Best Practices & Guidelines for Scheduling
– Copy of Table of Contents available on SCoP website – “Share – Documents – Document Exchange – Documents – SEI – SM”
– “2010-06-04 BPG Volume 1 Final Outline”SchedulingExcellence Initiative
• Best Practices & Guidelines for Schedule
Impact Analysis
– Copy of Table of Contents available on SCoP website – “Share – Documents – Document Exchange – Documents – SEI – SIA”
– “2008-03-01 SIA Outline – Volume I”
– “2008-04-30 SIA Outline – Volume II” (future effort)
PMI College of Scheduling
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.3
SEI Scheduling
SCHEDULING COMMUNITY OF PRACTICE
SEI PublicationsSEI Publications
PMI College of Scheduling
Best Practices
& Guidelines
Best Practices
& Guidelines
Project Planning
And Scheduling
Project Planning
And Scheduling
Volume IVolume I
PMI College of Scheduling
Best Practices
& Guidelines
Best Practices
& Guidelines
Project Planning
And Scheduling
Project Planning
And Scheduling
Volume IVolume I
SchedulingExcellence Initiative
SEI Scheduling
SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE
Best Practices & Guidelines
• Topic authors and reviewers must answer six
basic questions about each topic:
– Definition
� What is it?
– PurposeSchedulingExcellence Initiative
– Purpose
� Why is it used?
– Default Condition
� When & under what conditions is it used?
– Best Practices
� What are acceptable implementations?
– Recommended Practice
� Is there a preferred implementation?
– Admonitions & Advisories
� What should be avoided? 5
SEI Scheduling
SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE
SEI Update
• SEI Core Team
– Chris Carson, Managing Director, SEI
– Pete Oakander, Deputy Director, SEI
– Craig Relyea, Editorial Team Leader, SEI
• Best Practices & Guidelines for SchedulingSchedulingExcellence Initiative
• Best Practices & Guidelines for Scheduling
– Laura Williams, Volume Manager
– Recipient of the 2011 award for “Contribution to College of Scheduling/SCoP”
• Best Practices and Guidelines for Schedule
Impact Analysis
– Mark Sanders, Volume Co-Manager
– Mark Nagata, Volume Co-Manager
PMI College of Scheduling
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.6
SEI Scheduling
SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE
Early Completion Schedules
� Copies of the Early Completion Schedules
draft documents available on website� “Share – Documents – Document Exchange – Documents –
SEI Webinar BPG Topics
� Early Completion SchedulesSchedulingExcellence Initiative
PMI College of Scheduling
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.7
� Defined as submission of an as-planned schedule showing earlier completion than contractually mandated
� Early Completion Schedules
� Inadvertent
� Intentional
SEI Scheduling
SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE
Early Completion Schedules
� Inadvertent Early Completion Schedules� Usually not done intentionally
� May be missing scope
� May be rushed and just not finished
� May not have involved full PM team
� Not done for a specific reasonSchedulingExcellence Initiative
PMI College of Scheduling
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.8
� Not done for a specific reason
� Intentional Early Completion Schedules� Developed to minimize time on project
� Developed to provide a “buffer” for completion
� Expects to be allowed to complete early
� Expects to be paid extended GC for owner delays
from early date, not just contract completion date
� May or may not provide notification of intent to finish
early
SEI Scheduling
SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE
Early Completion Schedules
� Inadvertent Early Completion Schedules
� Owner perspective
� Should prompt careful review� Verify reasonableness
� Verify full scope of work
� Verify inclusion of all non-work activities that might SchedulingExcellence Initiative
PMI College of Scheduling
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.9
� Verify inclusion of all non-work activities that might
drive the schedule
� Determine if schedule represents full PM team
participation
� Verify resource planning and logic/sequencing
� Verify inclusion of reasonable weather planning
� Determine use of risk management
� Review coordination and owner-responsible activities
carefully
SEI Scheduling
SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE
Early Completion Schedules
� Inadvertent Early Completion Schedules
� Owner perspective
� Share review results with contractor
� Recommend revision to accommodate missing items
SchedulingExcellence Initiative
PMI College of Scheduling
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.10
� Once contractor has verified quality control and reasonable schedule, resubmission still requires careful secondary review
� Generally when owner questions contractor’s schedule, providing feedback in detail, revised schedule consumes more of the project duration
SEI Scheduling
SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE
Early Completion Schedules
� Inadvertent Early Completion Schedules
� Contractor perspective
� Should prompt careful QC review� Verify resource planning and logic/sequencing
� Verify inclusion of reasonable weather planning
� Ensure use of risk management, particularly SchedulingExcellence Initiative
PMI College of Scheduling
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.11
� Ensure use of risk management, particularly
identifying high risk activities and processes
� Provide careful Written Narrative to ensure that all
assumptions and requirements of the owner are
identified
� Schedule should provide reasonable expectation of
meeting project milestones, not overly optimistic or
pessimistic
� Revise as necessary and submit
SEI Scheduling
SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE
Early Completion Schedules
� Intentional Early Completion Schedules
� Owner perspective
� Proactive steps
� Address in contract documents
� Require as-planned schedule shows contractual
completionSchedulingExcellence Initiative
PMI College of Scheduling
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.12
completion
� Require constraint on contractual milestones
� Forbid float in as-planned schedule
� Simply state that early completion schedules will
not be accepted
� Provide change order to reduce the contractual
completion to the early completion date
� Allow a contingency activity prior to Substantial
Completion – mandate joint ownership of
contingency time (float)
� Provide incentive contingency activity
SEI Scheduling
SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE
Early Completion Schedules
� Intentional Early Completion Schedules
� Owner perspective
� Raises specific risks� Check to see that schedule does not impose
additional requirements on owner
� Short review timesSchedulingExcellence Initiative
PMI College of Scheduling
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.13
� Short review times
� Early equipment delivery
� Other project coordination issues
� Owner will pick up maintenance and operating
charges from early completion date
� End user might have to occupy early
� Salaries will start early
� Third party coordination may be more difficult
� If the early completion schedule is too aggressive,
there is uncertainty in completion predictions
SEI Scheduling
SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE
Early Completion Schedules
� Intentional Early Completion Schedules
� Owner perspective
� Legal risks may occur
� Failure to notify and/or spec language
precluding early completion may not be an
absolute bar to damages recovery when owner SchedulingExcellence Initiative
PMI College of Scheduling
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.14
absolute bar to damages recovery when owner
causes delays
SEI Scheduling
SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE
Early Completion Schedules
� Intentional Early Completion Schedules
� Contractor perspective
� Contractor needs to identify true need for early completion schedule
� Due to limited general conditions costs, should
document and follow early completion requirementsSchedulingExcellence Initiative
PMI College of Scheduling
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.15
document and follow early completion requirements
� Due to attempt to limit risk of late completion, should
discuss with owner and negotiate some buffer solution
� Due to limited resource availability, verify and choose
solution to support the risk
� With true need identified, contractor can take
measures to limit risks
SEI Scheduling
SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE
Early Completion Schedules
� Intentional Early Completion Schedules
� Contractor perspective
� Owner ability to simply move completion date to early completion schedule date could result in liquidated damages based on early date
SchedulingExcellence Initiative
PMI College of Scheduling
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.16
� Float will likely still belong to project so owner-responsible changes might use up float
� Contractor could be required to stay on project beyond
early completion date to handle changes with no
additional general conditions costs
� This is still a risk with good production when the
project is ahead of schedule – owner changes could
still force contractor to remain on job
� But bid would have included full term GC costs
SEI Scheduling
SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE
Early Completion Schedules
� Intentional Early Completion Schedules
� Contractor perspective
� In order to recover damages from delayed early completion, contractor must show:
� Always intended to finish early
� Had the ability to finish earlySchedulingExcellence Initiative
PMI College of Scheduling
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.17
� Had the ability to finish early
� Would have finished early but for owner actions
� Without these conditions, contractor likely will not
prevail with an early completion claim in litigation
� Could also notify owner that project was bid with only
general conditions for the early completion duration
� Jurisdictional differences in litigation make resolution
uncertain for both parties
� Ownership of float could be problematic if owner
attempts to retain
SEI Scheduling
SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE
Early Completion Schedules
� Intentional Early Completion Schedules
� General recommendations
� Quality of as-planned schedule must be validated
before deciding on ability to finish early
� Risk management should be incorporated into
schedule to raise the probability of meeting SchedulingExcellence Initiative
PMI College of Scheduling
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.18
schedule to raise the probability of meeting
scheduled completion
� Both parties should negotiate early completion
� Look at contingency options to provide some
protection
� Adjust contractual completion date
� If conditions work for owner, agree, and adjust contractual completion to early date
� If contractor is comfortable about schedule predictions, agree to adjust contractual completion
SEI Scheduling
SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE
SEI Best Practices and Guidelines for Scheduling
• Plans for published volume
– Working to get universities that provide CM education involved with peer review
– Plan to get copies into CM education departments as reference book
SchedulingExcellence Initiative
– Goal is to have volume reviewed, correlated, and published by 2012
• Opportunities for volunteers
– BP&G for Scheduling
� Develop remaining work product
� Opportunities for peer review
– BP&G for Schedule Impact Analysis
� Develop primary work product
� Influence best practice recommendations 19
SEI Scheduling
SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE
Early Completion Schedules
Questions?
Recommendations?
War Stories?SchedulingExcellence Initiative
PMI College of Scheduling
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.20
War Stories?
Gripes?
SEI Scheduling
SCHEDULING COMMUNITY OF PRACTICESCHEDULING COMMUNITY OF PRACTICE
Chris Carson, PSP
BP&G for Scheduling
Early Completion Schedules
SchedulingExcellence Initiative
PMI College of Scheduling
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.21
Chris Carson, PSP
Corporate Director of Project Controls
Alpha Corporation
101 West Main Street, Suite 7100
Norfolk, VA 23510
757-533-9368 Office
757-342-5524 Mobile