E07-007/E08-025 (DVCS status report)

13
E07-007/E08-025 (DVCS status report) J. Roche Ohio University Hall A collaboration meeting June 9-10, 2011

description

E07-007/E08-025 (DVCS status report). J. Roche Ohio University Hall A collaboration meeting June 9-10, 2011. In a nutshell:. Goals: -To measure the DVCS cross-sections as a function of Q 2 and two different beam energies for both LH2 and LD2 - PowerPoint PPT Presentation

Transcript of E07-007/E08-025 (DVCS status report)

Page 1: E07-007/E08-025 (DVCS status report)

E07-007/E08-025 (DVCS status report)J. Roche

Ohio University

Hall A collaboration meeting June 9-10, 2011

Page 2: E07-007/E08-025 (DVCS status report)

In a nutshell:

Goals:-To measure the DVCS cross-sections as a function of Q2 and two

different beam energies for both LH2 and LD2-To perform an L/T separation of these as a function of Q2

• Data taking took place in the fall of 2010 (Oct-Dec) • 80% of the expected data were taken (though at modified kinematics)

• Successfully used and read out the expanded calorimeter (ready for 12 GeV experiments – C. Hyde’s talk this afternoon)

• Analysis just started

Page 3: E07-007/E08-025 (DVCS status report)

d5σ = |BH |2 +(BH • DVCS)+ |DVCS |2

x=0.36, Q2=2.3 GeV2 t=-0.28 GeV2

PRL 97: 262002 (2006)

BH2, DVCS2 and BH-DVCS interferenceall contribute significantly to the totalcross-section.

Goal of E07-007 and E08-025:To separate the BH.DVCS interference contribution from the DVCS2 contribution

Measure each Q2 point at two different beam energies. For LH2 measure 3 Q2 while for LD2 measure only 1 Q2.

Page 4: E07-007/E08-025 (DVCS status report)

Actual kinematicsProposal assumed a 6 GeV beam energy (at 5 pass).

Actual kinematic had to be adjusted to accommodate the low energy requirement of QWEAK (5.5 GeV at 5 pass)

Impact:• Reduced lever arm in Q2: 1.5- 2.0

GeV2 (instead of 1.5-2.3 GeV2)

• The lowest Q2-setting (at 1.5 GeV2) will be closer to the nucleon resonance region W2=3.55 GeV2 (instead of 3.78 GeV2)

• Larger background noise => Poorer resolution, less statistic.

A long commissioning period and trigger issues limited our DAQ rate at the beginning of the experiment. The problem was fully resolved by the end of the experiment.

Page 5: E07-007/E08-025 (DVCS status report)

Improved dedicated equipment: expanded calorimeter and ancillary electronics

Expanded calorimeter (from 132 to 208 blocks)- less radiation damage than previously (selection of blocks and better shielding)

1 GHz sampling electronic (ARS) with better transfer speed- used VME320 protocol (16 times faster) and buffering of the FIFO

New coincidence trigger module- reduces data rate by selecting clusters above a threshold in the calorimeter- ran successfully during the last 8 days of the experiment

Page 6: E07-007/E08-025 (DVCS status report)

Improved dedicated equipment: Coincidence trigger module

For each LHRS trigger (S2L+Cer), the coinc-trigger module computes the signal amplitude of all 2*2 towers of the 208 blocks. A DVCS trigger is issued if one tower is above a given threshold.

We received a lot of help from the Jlab DAQ group during the experiment.Thanks to all and especially to D. Abbot and Ben Raydo.

The DVCS trigger becomes operational

Page 7: E07-007/E08-025 (DVCS status report)

Online Data quality

Page 8: E07-007/E08-025 (DVCS status report)

Thank you all for a successful data taking:– Hall A /Jlab engineers, techs and staff,– Run coordinators and– Shift workers.

We have started the offline analysis.

Collaboration meeting March 2011

Page 9: E07-007/E08-025 (DVCS status report)

Analysis just started: BCM calibrations

Run range U10 U3 U1 D10 D3 D1

6960-8334* 1.5 1.5 1.5 1.5 1.5 1.5

8334-8665 1 1 1 1 1 1

8667-9454 1.01 1.01 1.01 0.91 0.92 0.92

9456-9869 1.01 1.02 1.02 0.96 0.97 0.98

9456-9869 1.02 1.02 1.02 0.95 0.96 0.98

* BCMs not thermally regulated : analysis still in progress

We experienced two sudden jumps in the gain of the downstream BCM.So far the source of the jumps is unknown.

Page 10: E07-007/E08-025 (DVCS status report)

Analysis just started: Coincidence timing

e (p, e’ g) p

L-HRS DVCS calorimeter

t (ns)

1 GHz ARS(Analog Ring Sampler)

Analysis so far (LHRS side):-correct for paddle offsets-correct for hit position in the scintillator-correct for slewing as a function of amplitude

Results so far: -sigma 1ns -for last experiment, it went down to 0.6 ns

Page 11: E07-007/E08-025 (DVCS status report)

Analysis just started: Spectrometer pointing

Page 12: E07-007/E08-025 (DVCS status report)

Analysis just started: Polarimetry

Period Horizontal Wien Angle Equivalent (estimated)

A 29B 5C 26.8D 29

Run the g-detector Compton when tune allowed (~ 30% of the time)

Page 13: E07-007/E08-025 (DVCS status report)

Status of E07-007/ E08-025 in summary:

Goals:-To measure the DVCS cross-sections as a function of Q2 and two

different beam energies for both LH2 and LD2-To perform an L/T separation of these as a function of Q2

• Data taking took place in the fall of 2010 (Oct-Dec) • 80% of the expected data were taken (though at modified kinematics)

• Successfully used and read out the expanded calorimeter (ready for 12 GeV experiments – C. Hyde’s talk this afternoon)

• Analysis just started