E. IhloffFebruary 8, 2008
FNPB-UCN building usage by nEDM
E. IhloffFebruary 8, 2008
People involved in Building Layout
• Rick Allen – ORNL SNS Lead Engineer FNPB
• Walter Sondhiem – LANL Integration Engineer
• Jan Boissevain – Chief nEDM Engineer
• Ernie Ihloff – MIT
• John Ramsey - LANL
• Martin Cooper – LANL nEDM Project Leader
• Geoff Greene – ORNL
• Vince Cianciolo – ORNL
• David Hasse and Paul Huffman – NCSU
• Jlab Cryogenic experts – Rao Ganni, Dana Arenius, Jonathon Creel
• George Mulholland – ACT Cryogenic Consultant
E. IhloffFebruary 8, 2008
ORNL-SNS Layout Complete
E. IhloffFebruary 8, 2008
Status as of February 2008
• nEDM and SNS engineers agreed on documents to go to an A & E firm for design of building - December 2007
• Meeting at Jlab to discuss cryogenic layout- Oct 2007
• Preliminary phone meetings with Linde and Cryogenic consultant George Mulholland on system design
• Goal to have cryogenic layout done by A&E review at SNS
E. IhloffFebruary 8, 2008
Location of FNPB Build at SNS
E. IhloffFebruary 8, 2008
Questions still to be addressed
• Satisfy DOE that design is function and safe
• Water cooling in FNPB building
• Make sure we claim external space we need
• Clean power requirements in hall
• Best use of Cryogenic consultants
• …other things ??