Ministry of
Communications
&
Information
Technology
e-Government Strategy and
Implementation Plan - Report
January 2011
E-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 2 Confidential
'This report has been prepared for and only for MCIT, Government of Ethiopia, in accordance
with the terms of our contract agreement package no EICTDA/C-09/10 Credit No 3899-ET dated
June 2010 and for no other purpose. We do not accept or assume any liability or duty of care for
any other purpose or to any other person to whom this report is shown or into whose hands it may
come save where expressly agreed by our prior consent in writing.'
© 2010 PricewaterhouseCoopers. All rights reserved. ―PricewaterhouseCoopers‖ refers to the
network of member firms of PricewaterhouseCoopers International Limited, each of which is a
separate and independent legal entity.
E-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 3 Confidential
Document Control
Overview PwC has been engaged as a consultant by MCIT, Government of Ethiopia,
for development of National e-Government Strategy and designing the
Ethiopian e-Government Strategy and Implementation Plan
Document Title Final e-Government and Implementation Plan Report
Document Status Revised Submission based on inputs from Final Workshop
Abstract This document elaborates the strategy and Implementation roadmap of
Federal Government of Ethiopia.
Document Publication History
Date Author Version Remarks
27-September-2010 Avinash Kaushik 1.0 Creation of template
5-October-2010 Raj Kamal Singh, Anurag Johri,
Avinash Kaushik
1.1 Creation of First draft
15-October-2010 Anurag Johri, Avinash Kaushik,
Raj Kamal Singh
1.2 Creation of Second draft
28-October-2010 Nilachal Mishra, Prasad
Unikrishnan, Anurag Johri, Raj
Kamal Singh
1.3 Creation of Third draft
7-Nov-2010 Nilachal Mishra, Prasad
Unikrishnan, Anurag Johri,
1.4 Updated draft based on
MCIT comments
24-Nov-2010 Nilachal Mishra, Prasad
Unikrishnan, Anurag Johri,
1.5 Updated draft based on
MCITcomments
15th December-2010 Nilachal Mishra,
Prasad Unikrishnan,
1.6 Updated draft based on
workshop comments
19th December-2010 Prasad Unikrishnan, 1.8 Revised Report Finalization
13th January, 2011 Nilachal Mishra 1.9 Final Report
Reviewers
Date Reviewers Version Remarks
8-October-2010 Nilachal Mishra 1.1 Review and Comments
18-October-2010 Nilaya Varma 1.2 Review and Comments
30th October -2010 Nilaya Varma 1.3 Final Review
3rd Nov - 2010 Dr Mesfin, Mr Damtew,
MCIT
1.3 Review and comments in
workshop mode
E-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 4 Confidential
15th November -2010 Dr Mesfin, Mr Damtew,
MCIT
1.4 Review and comments
30th November- 2010 Internal Workshop 1.5 Review and comments in
workshop mode
17th December,2010 Nilaya Varma 1.6 Review & Comments
11th January, 2011 Final Workshop 1.7 Discussion and Comments
9th February, 2011 Final workshop Inputs &
Feedback
1.8 Feedback comments
26th February Feedback comments 1.9 Comments of Mr. Damtew
E-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 5 Confidential
Table of Contents
I. Introduction ................................................................................................................................... 14
I. Project Scope ......................................................................................................................................... 14
II. Structure of this report .......................................................................................................................... 15
III. Mapping of the Report to areas to be covered in the contract ................................................................... 16
IV. Project Status ........................................................................................................................................ 17
V. Limitations of the report ........................................................................................................................ 19
II. Executive Summary ........................................................................................................................ 21
I. Outcomes and Targets ........................................................................................................................... 25
II. Strategic Dimensions ............................................................................................................................. 29
III. Governance Structure ..................................................................................................................... 39
I. Drivers for the Governance Structure ..................................................................................................... 39
II. Governance Structure: Options and Recommendations ........................................................................... 40
III. Recommended Governance Structure ..................................................................................................... 44
IV. Strategic Dimension 1 - e-Services Enablement ............................................................................... 57
I. Introduction .......................................................................................................................................... 57
II. Guiding Principles for electronic enablement of Service .......................................................................... 57
III. Recommendations and Targets .............................................................................................................. 58
IV. Agency Priority Projects ......................................................................................................................... 58
V. Agriculture Services ............................................................................................................................... 61
VI. Benefits Management System ................................................................................................................ 65
VII. Education .............................................................................................................................................. 67
VIII. E-Health ............................................................................................................................................... 71
IX. E-Trade ................................................................................................................................................. 74
X. Employment.......................................................................................................................................... 79
XI. Transport .............................................................................................................................................. 82
XII. Tourism ................................................................................................................................................ 86
XIII. Tax........................................................................................................................................................ 91
XIV. e-Court .................................................................................................................................................. 94
XV. Municipalities ....................................................................................................................................... 97
XVI. Passport & Visa ................................................................................................................................... 108
XVII. National Data Set: ............................................................................................................................... 113
XVIII. National Enterprise Service Bus: .......................................................................................................... 114
XIX. National Integrated Authentication Framework: ................................................................................... 116
XX. National Payment Gateway: ................................................................................................................. 118
XXI. Public Key Infrastructure ..................................................................................................................... 120
XXII. Woreda Net ......................................................................................................................................... 122
XXIII. Data Center ......................................................................................................................................... 123
XXIV. National Enterprise Architecture Framework........................................................................................ 125
E-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 6 Confidential
XXV. Common Applications ......................................................................................................................... 128
XXVI. e-Procurement .................................................................................................................................... 128
XXVII. Government wide HRMS ..................................................................................................................... 129
XXVIII. Financial Management Information System .................................................................................. 130
XXIX. eOffice / Document Management ......................................................................................................... 131
XXX. Government wide email system ............................................................................................................ 132
V. Strategic Dimension 2 - Channels ................................................................................................. 134
I. Introduction ........................................................................................................................................ 134
II. Current Status ..................................................................................................................................... 134
III. Summary of the status of the different channels is as below – ................................................................ 135
IV. Guiding Principles for Channels Strategy .............................................................................................. 135
V. Recommendations and Targets ............................................................................................................ 136
VI. e-Government Portal ........................................................................................................................... 137
VII. Contact Center..................................................................................................................................... 140
VIII. Mobile Gateway ................................................................................................................................... 143
IX. Common Service Center ....................................................................................................................... 147
X. Channel Migration Strategy ................................................................................................................. 149
VI. Strategic Dimension 3 - Enablers .................................................................................................. 151
I. Capacity Building ................................................................................................................................ 151
II. Monitoring and Evaluation .................................................................................................................. 161
III. Marketing and Awareness .................................................................................................................... 169
IV. Standards and policies ......................................................................................................................... 182
V. Public Private Partnerships (PPP) ........................................................................................................ 187
VII. Over all Implementation Plan and Timelines................................................................................. 199
I. Overall Implementation Plan ............................................................................................................... 199
II. Sample Detailed Implementation Plan and RACI Chart for Education Priority project ........................... 204
III. Portal Implementation Plan and Timelines ........................................................................................... 210
IV. ICT Center Implementation Plan and Timelines ................................................................................... 213
V. Contact Center Implementation Plan and Timelines ............................................................................. 215
VI. Mobile Implementation Plan and Timelines ......................................................................................... 217
VII. Capacity Building Implementation Plan and Timelines ......................................................................... 219
VIII. Marketing and Awareness Plan and Timelines ...................................................................................... 222
IX. Public Private Partnership - Plan and Timelines.................................................................................... 223
VII. Cost Estimation & Funding ........................................................................................................... 227
I. Budgetary Estimates ............................................................................................................................ 227
II. Funding Framework ............................................................................................................................ 229
III. Program funding Options..................................................................................................................... 231
IV. Fund Management Framework (FMF) .................................................................................................. 233
V. Fund Allocation Process ....................................................................................................................... 236
E-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 7 Confidential
Annexures ........................................................................................................................................... 240
Annexure I: Concept of Service Life Cycle............................................................................................ 240
Annexure II: PMO Staffing Requirements ........................................................................................... 242
Annexure III: Training Courses and Course Levels .............................................................................. 248
Annexure IV: Detailed Marketing and Awareness Strategy ................................................................... 251
Annexure V: Detailed Project Report - Template .................................................................................. 254
Annexure VI: Services Prioritization Framework .................................................................................. 256
Annexure VII: ICT Standing of Ethiopia – Some international Rankings .............................................. 258
Annexure VIII: Risk in E-Government Strategy Implementation .......................................................... 268
Annexure IX: Sample Project Management templates .......................................................................... 269
Annexure X: List of Services ................................................................................................................ 290
Annexure XI: Overview of Stakeholder Assessment .............................................................................. 304
Annexure XII: Scope of work for Baseline Survey Agency ..................................................................... 310
Annexure XIII: Scope of work for Marketing and Awareness Agency .................................................... 314
Annexure XIV: Job Descriptions of the IT Officials at the Ministry ....................................................... 316
Annexure XV: Job Descriptions of the ITSG to support in the Ministries .............................................. 318
Annexure XVI: Key Considerations during Procurement Process ......................................................... 319
Annexure XVII: Costing details of Individual Projects .......................................................................... 321
E-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 8 Confidential
List of Tables
Table 1: Mapping of the Report to areas to be covered in the contract .......................................................... 16 Table 2: Outcomes and Targets ........................................................................................................................ 25 Table 3: Implementation Plan for common applications................................................................................ 33 Table 4: Implementation Plan for Core Projects ............................................................................................. 34 Table 5: e-Services Implementation Plan for the Channels ............................................................................ 36 Table 6: Overall Implementation Plan ............................................................................................................. 37 Table 7: Options for sponsorship ...................................................................................................................... 40 Table 8: High Committee Assessment ............................................................................................................. 41 Table 9: Technical Committee .......................................................................................................................... 41 Table 10: PMO Options ..................................................................................................................................... 42 Table 11: Ownership of IT Initiatives ................................................................................................................ 43 Table 12: Role and Responsibilities of Ministry Level Organization Structure ............................................. 54 Table 13: PMO Support ..................................................................................................................................... 55 Table 14: Agency Priority Projects .................................................................................................................... 58 Table 15: e-Service Enablement of Agency Priority Projects .......................................................................... 59 Table 16: Core Projects .....................................................................................................................................110 Table 17: Core Projects- Implementation Plan ............................................................................................... 111 Table 30: Existing WOREDA Net ................................................................................................................... 122 Table 19: Channel – Current Status................................................................................................................ 135 Table 20: e-Government Portal Implementation .......................................................................................... 138 Table 21: Contact Centre Implementation Options ........................................................................................ 141 Table 22: Middleware required for Wireless Applications............................................................................ 144 Table 23: Mobile Gateway Implementation Options .................................................................................... 145 Table 24: Analysis of Options for ITSG .......................................................................................................... 154 Table 25: Outsourced vs. Individual Recruitments ....................................................................................... 155 Table 26: Target Groups for Training............................................................................................................. 155 Table 16: Training Levels ................................................................................................................................ 156 Table 49: Government transformation index: key indicators ....................................................................... 164 Table 50: Customer satisfaction index: key indicators.................................................................................. 166 Table 30: Marketing and Awareness Brief ..................................................................................................... 172 Table 31: Message Development ..................................................................................................................... 176 Table 32: General Awareness Campaign Overview ........................................................................................ 177 Table 33: Development / Approval Process ................................................................................................... 179 Table 34: Feedback, measurement of effectiveness and improvement ........................................................ 180 Table 35: Regulations, Policies, Guidelines and Standards .......................................................................... 182 Table 36: PPP opportunities and Recommendations .................................................................................... 189 Table 37: ICT Events ....................................................................................................................................... 192 Table 38: PPP Implementation Roadmap ..................................................................................................... 194 Table 39: Guidelines for leveraging PPP ........................................................................................................ 196 Table 40 – Overall Implementation Plan ....................................................................................................... 199 Table 41 – Education Project Implementation Plan......................................................................................204 Table 42 – Portal implementation Plan ......................................................................................................... 210 Table 43 – ICT Centre Implementation Plan ................................................................................................. 213 Table 44 – Contact Center Implementation Plan .......................................................................................... 215 Table 45 – Mobile Implementation Plan ....................................................................................................... 217 Table 46 – Capacity Building Implementation Plan ..................................................................................... 219 Table 47 – Marketing and Awareness Implementation Plan ........................................................................ 222 Table 48 – Public Private Partnership Plan ................................................................................................... 223 Table 48 – e-Government Strategy – Summary of Costs .............................................................................. 227 Table 48 – Funding Options ........................................................................................................................... 231 Table 51 – PPP Options ................................................................................................................................... 232 Table 52: Categories of fund ........................................................................................................................... 235 Table 53: Approval for allocation ................................................................................................................... 235 Table 54: Lifecycle Event Description ............................................................................................................240
E-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 9 Confidential
Table 55: PMO staffing Requirements ........................................................................................................... 242 Table 56: PMO Staffing Requirements ........................................................................................................... 246 Table 46: Training Courses and Course Levels ..............................................................................................248 Table 47: Target Market Segments ................................................................................................................. 251 Table 48: Effectiveness of Media Channels by Marketing Segments ........................................................... 252
E-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 10 Confidential
List of Figures
Figure 1: Project Status...................................................................................................................................... 18 Figure 2 : e-Government Strategy and Goals ................................................................................................... 22 Figure 3: Key Strategic Dimensions ................................................................................................................. 29 Figure 4: e-Service enablement Plan ................................................................................................................ 32 Figure 5: Recommended Structure................................................................................................................... 44 Figure 6: Project Management Office (PMO) Structure.................................................................................. 47 Figure 7: ITSG Structure ................................................................................................................................... 50 Figure 8: Capacity Balancer .............................................................................................................................. 51 Figure 9: Ministry Level IT Organization Structure ........................................................................................ 53 Figure 10: Core Projects ................................................................................................................................... 112 Figure 21: National Enterprise Service Bus .................................................................................................... 115 Figure 22: National Integrated Authentication Framework .......................................................................... 117 Figure 23: National Payment Gateway ............................................................................................................ 119 Figure 24: Public Key Infrastructure (PKI) ..................................................................................................... 121 Figure 23: Proposed Nationwide Data center Layout ................................................................................... 123 Figure 16: The overall EA reference model .................................................................................................... 127 Figure 17: eProcurement ................................................................................................................................. 128 Figure 18: IBEX System .................................................................................................................................. 130 Figure 26: eOffice Components ....................................................................................................................... 131 Figure 8: e-Government Portal ....................................................................................................................... 137 Figure 21: Contact Center ................................................................................................................................ 140 Figure 22: Mobile Gateway ............................................................................................................................. 143 Figure 23: Four tier Architecture for Wireless Application Delivery ........................................................... 144 Figure 11: Common Service Center ................................................................................................................. 147 Figure 25: Capacity Building ............................................................................................................................ 151 Figure 26: ITSG ............................................................................................................................................... 153 Figure 27: Marketing and Awareness Plan .................................................................................................... 169 Figure 28: Continuous Improvement in Communications ........................................................................... 180 Figure 29: Policy/Standards/Guidelines Framework ................................................................................... 185 Figure 30: Implementation Plan for Standards and Policies ........................................................................ 186 Figure 31: Key Options for MOCIT ................................................................................................................. 229 Figure 32: Government Control/Risk ............................................................................................................230 Figure 33: Fund utilization framework .......................................................................................................... 234 Figure 34: Fund allocation prioritization ....................................................................................................... 238 Figure 35: Life-Cycle Services ......................................................................................................................... 241
E-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 11 Confidential
Abbreviations
Sr. No. Acronym Full Form
1. BCP/DR Business Continuity Plan/ Disaster Recovery
2. CAPEX Capital Expenditure
3. CB Capacity Building
4. CDT Common Data Terminals
5. CIO Chief Information Officer
6. CISA Certified Information Security Auditor
7. CISM Certified Information Security Manager
8. CISSP Certified Information Systems Security Professional
9. CoE Centre of Excellence
10. CRTC Computer Refurbishment and Training Center
11. CSC Common Service Centers
12. CTO Chief Technology Officer
13. DSC Digital Signature Certificate
14. e-GIF
Government Information Systems Interoperability
Framework /Standard
15. EICTDA
Ethiopian Information and Communication Technology
Development Agency
16. EMD Earnest Money Deposit
17. ENDC Ethiopian National Data Centre
18. FEMSEDA Federal Micro and Small Enterprise Development Agency
19. GRS Grievances Redressal System
20. GoE Government of Ethiopia
21. HRMS Human Resource Management System
22. IBAS Integrated Budget Accounting System
23. ICT Information and Communication Technology
24. IT Information Technology
25. ITSG Information Technology Services Group
26. JCMS Judicial Case Monitoring System
27. KM Knowledge Management
28. KPI Key Performance Indicator
E-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 12 Confidential
Sr. No. Acronym Full Form
29. KPO Key Performance Objectives
30. M&E Monitoring and Evaluation
31. MIS Management Information System
32. NDC National Data Centre
33. NOC Network Operating Centre
34. PKI Public Key Infrastructure
35. PMO Project Management Office
36. PPP Public Private Partnership
37. PR Public Relations
38. RDC Regional Data Centre
39. RFP Request for Proposal
40. SDLC System Development Life Cycle
41. SLA Service Level Agreement
42. SMS Scheme Management System
43. TCO Total Cost of Ownership
44. TNA Training Need Assessment
45. TVET Technical Vocational Education Training centers
46. VPN Virtual Private Network
47. WAN/MAN Wide Area Network / Metropolitan Area Network
48. WDMS Workflow and Document Management System
Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 14 Confidential
I. Introduction
Ethiopia‘s Information and Communication Technology (ICT) policy is an integral part of the country‘s
larger development goals and objectives. While the goal is to rapidly transform the country‘s subsistence
agricultural-based economy and society into a predominantly knowledge- and information-based
economy and society, the focus of the policy will be on the country‘s ICT development process. To achieve
this objective, the Government of Ethiopia has developed multiple policies, most notable of which are the
National ICT Strategic Plan and the ICT4D Action Plan for the year 2006-2010.
The Ethiopian Information and Communication Technology Development Agency (MINISTRY OF
COMMUNICATIONS & IT) has a mission to develop, deploy and use ICT to improve the livelihood of
Ethiopians and optimize its contribution to the development of the country. The Agency has thus
undertaken a number of e-Government assignments to avail government services online and improve the
access to the general public. The Government Information System Development and Data Centre
Administration team of the Agency is managing projects targeted towards development of integrated
information systems to avail government services online.
However in the current context there was a need to integrate the ICT initiatives undertaken and provide a
strategic direction for e-Government implementation in the country. It is in this context MINISTRY OF
COMMUNICATIONS & IT has engaged PricewaterhouseCoopers Pvt. Ltd. for designing the National e-
Government strategy and implementation plan for the Government of Ethiopia (GoE).
I. Project Scope
The specific activities as agreed in the contract package no EICTDA/C-09/10 and Credit No 3899-ET
include:
Establish a clear vision for e-Government tied up with the Agency‘s mandates and come-up with a
list of priority areas for e-Government program. (Define a vision that represents the priority
objectives and the shared voice of all stakeholders as well as define strategies to communicate the
vision to stakeholders);
Critically evaluate the National ICT Strategic Plan and the ICT4D-2008 e-Government Action
Plan of the country and other policy and strategy related studies that the Agency has undergone;
Assess the country‘s e-Government initiatives pursued in the Government ministries and
implementing agencies;
Develop an approach whereby a clear vision that ensures that key constituents and communities
will buy into and support e-Government programs is developed;
Identify models of e-Government that suits the country‘s socio-economic conditions; and propose
best model for Ethiopia‘s specific case;
Develop a work plan to implement the priority e-Government projects [this work plan may focus
on content development, competency building (training employees at all levels of the bureaucracy
including senior officials), connectivity, cyber-laws, citizen interfaces, and capital plus others];
Propose options for government information and knowledge management schemes;
Define approaches on measuring progresses through e-government development;
Establish mechanisms for the continuing involvement of key stakeholders;
Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 15 Confidential
II. Structure of this report
The report is structured as follows:
Section 1 – Introduction
This section covers the Project Scope, current status of the project, mapping of the contents of the report
to the contractual obligations, and limitations of this report.
Section 2– Executive summary
This section captures the background, Vision, Outcomes and Targets and summarizes the proposed e-
Government Strategy.
Section 3 – Governance Structure
This section covers the proposed Governance structure required for the implementation of the Ethiopian
e-Government Strategy.
Section 4 – Strategic Dimension 1 - e-Services Enablement
This section details the strategic dimension of e-Services enablement of 211 e-services comprising of
seventy seven (77) informational and one hundred thirty four (134) transactional services over a five year
period. The implementation is proposed to be done through twelve (12) priority projects and service
delivery would be through four channels (Portal, Call centre, Mobile devices and Common service centres)
and delivery will be facilitated and strengthened through Six (6) core projects, including National
Payment Gateway, Enterprise Architecture framework, Public Key Infrastructure, National Data Set,
National Enterprise Service Bus and National integrated Authentication Framework.
In addition – common applications which will horizontally cut across all ministries are proposed, which
include initiatives like E-Procurement, Human resource Management System, E-Office, E-Mail and
Financial management & Information System
Section 5 – Strategic Dimension 2 – Channels
This section covers the Implementation details of the service delivery channel enhancement projects that
will enable the implementation of e-Government in Ethiopia
Section 6 – Strategic Dimension 3 - Enablers
This section covers the details of the key enablers to assure successful and timely implementation of the
e-Government strategy and ensure the sustainability of the initiatives
Section 7 – Implementation and Timelines
This section describes the Implementation Plan for the Ethiopian e-Government Strategy along with the
detailed timelines.
Section 8 – Cost Estimates
This section provides the estimates of the costing and funds required for the rollout of the e-Government
Implementation plan.
Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 16 Confidential
Annexure
This section covers the following:
I: Concept of Service Life Cycle
II: PMO Staffing Requirements
III: Training Courses and Course Levels
IV: Detailed Marketing and Awareness Strategy
V: Detailed Project Report - Template
VI: Services Prioritization Framework
VII: ICT Standing of Ethiopia – Some international Rankings
VIII: Risk in E-Government Strategy Implementation
IX: Sample Project Management templates
X: List of Services
XI: Overview of Stakeholder Assessment
XII: Scope of work for Baseline Survey Agency
XIII: Scope of work for Marketing and Awareness Agency
XIV: Job Descriptions of the IT Officials at the Ministry
XV: Job Descriptions of the ITSG to support in the Ministries
XVI: Key Considerations during Procurement
XVII: Costing details of individual Components
III. Mapping of the Report to areas to be covered in the contract
The table placed below maps the areas to be covered under the contract with the sections which cover
those areas:
Table 1: Mapping of the Report to areas to be covered in the contract
S.No. Areas Coverage in Report
1 Informational Needs and Transactional
requirements of selected Ministry‘s
Customers
The Stakeholder Requirements have been captured
through workshops and Survey of Stakeholders and
have been presented in the VMO Report and the
Stakeholder Assessment report. This information
has been the source for formulation of the Strategy
and Implementation plan presented in this report.
2 Accessibility of Citizen Services Section 5 addresses the accessibility and the
delivery channels for providing the Citizen Services.
5.4.1 e-Government Portal
5.4.2 Contact Center
5.4.3 Mobile Gateway
5.4.4 Common Service Center
5.4.5 Channel Migration Strategy
3 Business Applications to be e-enabled Section 6.7 addresses the business applications to
be enabled to provide the citizen services
Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 17 Confidential
S.No. Areas Coverage in Report
6.7 Common Applications
6.7.1 e-Procurement
6.7.2 Government wide HRMS
6.7.3 Financial Management Information System
6.7.4 e-Office / Document Management
6.7.5 Government wide email system etc.
4 Integration of People, Process and
technology using web to transform
business models and maintain
interoperability
Section 6 addresses the enablers which would be
used to transform business models and maintain
interoperability
6.1 Capacity Building
6.2 Monitoring and Evaluation
6.3 Marketing and Awareness
6.4 Standards and policies
6.5 Public Private Partnerships (PPP)
5 Standards and guidelines for all services
and processes
Section 6.4 covers the Standards and guidelines for
all services and processes
6 Effective and efficient Utilization of
Government Resources- Network
Infrastructure necessary for providing
e-services
Section 6 addressed the strategy for effective and
efficient utilization of the Government resources.
6.6 Core Projects
6.6.1 National Data Set
6.6.2 National Enterprise Service Bus
6.6.3 National Integrated Authentication
Framework:
6.6.4 National Payment Gateway:
6.6.5 Public Key Infrastructure
6.6.6 Woreda Net
6.6.7 Data Center
IV. Project Status
The e-Government Strategy and Implementation project was initiated on 16th July 2010, with the kick off
meeting, where senior members of MoCIT and PwC were present. As committed in the kick off meeting,
PwC team has submitted the detailed Inception report covering Work Plan, Timelines of deliverables,
Deployment Plan and Activities. Vision, Mission and Objective (VMO) workshop was conducted on 5th
Aug 2010 to ascertain the vision and objectives of the e-Government Strategy. The PwC team also
conducted a dip-stick study of 13 ministries and 11 agencies and a customer survey to understand the
expectations and aspiration of the stakeholders from the e-Government Strategy. A draft report has been
discussed with MoCIT Officials and a workshop was conducted on 30th November, 2010 where the report
has been presented to all the MoCIT officials. Further the final workshop was held between the Ministries
and Agencies to seek inputs for finalization of the Strategy. This report is a culmination of these efforts
and presents the final recommendations and implementation plan based on the study
The figure1 overleaf shows the activities undertaken till date and the present status of the project.
Development of e-Government Strategy and Implementation Plan Inception Report
Confidential Page 18 of 361 PricewaterhouseCoopers Page 18 Confidential
Figure 1: Project Status
V. Limitations of the report
The recommendations of the e-Government Strategy are based on the Assessment study of 13
Ministries and 11 Agencies that have participated in the study. The sample size of
Ministries/Agencies was finalized during the inception Stage.
The information presented in the report is based on the inputs received through questionnaires
and interactions with the Ministries/Agencies. No separate field validation study has been done
on the data received from Ministries/Agencies.
The assessment study was done during the Months of August –September, 2010 and Undertaken
by the Government was designed thereafter. However there has been an Organization Re-
structuring of Ministries/Agencies in Ethiopia in Month of October, 2010, which has resulted in
changes in the Strategy. PwC has captured the inputs on revised Governance Structure, during
design of this report, however it may not be reflective of all the changes under the Government.
While, the strategy takes into account all common e-Government initiatives in the country and
those in the participating organizations, there are bound to be independent and isolated
initiatives that do not form part of the study and thus do not reflect in the strategy. However, this
should not restrict the government to pursue other initiatives, as long as they are in conformance
with the overall e-Government program.
The Voice of Customer (VoC) Survey was conducted based on sample size agreed between
MINISTRY OF COMMUNICATIONS & IT and PwC in the contract and also during the inception
stage, and it should be noted that it is a dip stick study and the findings are only indicative and
not representative of the entire country.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 20 Confidential
Section 2 –
EXECUTIVE
SUMMARY
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 21 Confidential
II. Executive Summary
The Ethiopian Information and Communication Technology Development Agency (MINISTRY OF
COMMUNICATIONS & IT) has a mission to develop, deploy and use ICT to improve the livelihood of
Ethiopians and optimize its contribution for the development of the country. Towards this end, the agency
has undertaken a number of e-Government initiatives to improve the internal efficiencies within the
government organizations and to improve the access to government services for the general public.
MINISTRY OF COMMUNICATIONS & IT realizes the need to integrate these initiatives to provide a
strategic direction for e-Government implementation in the country. It is in this context that the e-
Government strategy for Ethiopia has been designed, with a focus on facilitating effective delivery of
government services to customers (residents, businesses and visitors).
The strategy envisages implementation of 219 e-services comprising of seventy seven (79)
informational and one hundred thirty four (140) transactional services over a five year
period. The implementation is proposed to be done through twelve (12) priority projects and
service delivery would be through four channels (Portal, Call centre, Mobile devices and
Common service centres) and delivery will be facilitated and strengthened through Six(6) core
projects, including National Payment Gateway, Enterprise Architecture framework, Public Key
Infrastructure, National Data Set, National Enterprise Service Bus and National integrated Authentication
Framework.
In addition – common applications which will horizontally cut across all ministries are proposed, which
include initiatives like E-Procurement, Human resource Management System, E-Office, E-Mail and
Financial management & Information System
The Strategy has been design keeping the following guiding principles of e-Government
E-Government is focussed in creating a SMART (Simple Moral Accountable, Responsive and
Transparent) Government;
E-government promotes causes of e-citizen and e-democracy;
E-Government is not translating processes, however transforming processes;
E-Government necessitates Capacity building within the Government;
E-government aims networked and integrated government;
E-government is citizen-centric;
E-government provides multi-channel delivery of public services;
E-Government aims in providing convenient access of information to all, and improving service
access & delivery;
E-Government enables development & participation of all segments of population to reap benefits of
IT and also participate in the Governance process and be able to voice their opinions more effectively;
and
E-Government supports in development and inclusion of Private Sector in public service delivery.
The e-Government strategy has a customer-centric focus so as to facilitate the delivery of services and
information through alternate channels in a manner that is convenient for the citizens and is in line with
their expectations and aspirations. Life cycle based representation of services is a powerful tool towards
this end and therefore, the strategy envisages the use of life-cycle events while electronically enabling the
services.
As per the life cycle based concept, all services for a particular event, for e.g. ‗starting a business‘ should be
available under a single umbrella and the customer should not be required to have multiple touch points
for the same. In addition to classifying and prioritizing services, services must be integrated at the back-
end based on customer lifecycle approach. The services can be grouped by their customer base, and these
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 22 Confidential
can further be mapped onto the various customer lifecycle events, where they each respond to a particular
need of the customer at a given time. Hence existing services can be identified based on life-cycle services
approach for the various customer groups— citizens/residents, businesses, visitors and government
employees. Life-cycle of events for the citizens/residents, business, visitors and government
employees is discussed in detail in Annexure I.
In line with the above, Vision, Outcomes, targets and strategic plan for the Government of Ethiopia has
been pictorially depicted in the figure overleaf. Each of the components depicted in the figure overleaf are
further detailed in the next few pages. A brief of the proposed implementation plan for the strategy is also
mentioned – thus encapsulating the complete E-Government Strategy and its implementation – in this
chapter.
Figure 2 : e-Government Strategy and Goals
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 23 Confidential
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 24 Confidential
The vision of the e-Government strategy has four key elements:
1. Bring the Government closer to the people: The e-Government strategy aims to increase the
awareness levels of the people regarding the services offered by the Government and their rights as
customers and also make it easier for the customers to influence and participate in design of
Government policies and schemes. This participation is expected to create a sense of ownership and a
culture of higher compliance leading to closer ties between the government and the people.
2. Effective governance: The implementation of the e-Government strategy will lead to backend
automation and adherence to a common set of policies and standards leading to better integration
and information sharing amongst them and resulting in making the government organizations more
effective and efficient in discharging their services and duties. Furthermore, capacity building to
impart training to public servants on skills that will enable them to serve the customers in a more
effective manner is an integral part of the overall e-Government strategy.
3. Improved service delivery: The sine qua non of the e-Government Strategy is the electronic
enablement of 219 services to be delivered through alternate channels such as the internet, mobile,
call centre and the citizen facilitation centres. The introduction of these alternate channels will
empower the people with the choice of how, when and where they interact with the government to
facilitate a ―no-wrong door policy‖ which will further improve the customer satisfaction levels with
the government services. It is also envisaged that electronically enabled services would be not only
faster, and easier to demand and avail but will also have pre-defined and published service levels
thereby leading to a visible enhancement in quality of service delivery.
4. Socio-Economic growth: The implementation of the e-Government program will benefit through
participation of the private sector and deployment of its resources, entrepreneurship and competence.
At the same time, the private sector would also benefit through the e-Government program as
government services will be delivered faster and at a lower cost to the customers thereby resulting in
lower cost of doing business. This is likely to foster a symbiotic environment that would promote
economic growth and sustainability of the e-Government initiatives.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 25 Confidential
I. Outcomes and Targets
In order to measure and manage progress, it is imperative to define key outcomes and targets that would
enable realization of the vision. Also linkages with the National ICT policy Goals have been provided in
the table below:
Table 2: Outcomes and Targets
Outcomes and Targets Description
Element of Vision: Bring government closer to the people
Outcome 1: Customer participation in Government policy/scheme design
Target 1 - Ethiopia to be amongst the top 30 countries in the world in the e-
Participation index of UN by the year 2015 (Ranked 135 in 2010): Most countries are using
electronic channels to understand firsthand the views, expectations and aspirations of their people.
UN‘s e-Participation index measures the progress made by all the member countries in doing the
same. It is envisaged that the e-Government portal as well as other alternate service delivery channels
will facilitate the citizens in putting forth their feedback and preferences on national issues.
Target 2: Customer Feedback Mechanism available on all Government Channels: A
comprehensive Grievance redressal mechanism and a process to inculcate feedback from various
stakeholders would be established so that existing Government policies and schemes can be modified
and new schemes created as per customers‘ feedback.
Outcome 2: High awareness regarding all Government Schemes/Services
Target 3: More than 70% of Customers aware of the e-Government program: An integral
element of the implementation of the strategy would be a high decibel marketing and awareness
campaign at the federal as well as regional levels to create awareness regarding the e-Government
program and the benefits of availing e-Services. E.g. The customers need not travel to Addis Ababa or
any other regional centre to seek information and services – such facilities would be made available
within their immediate community. This will not only present the government in positive light as
working towards the benefits of the customers but will also facilitate in higher take-up of new
channels.
Linkage to National ICT Policy Goal: To ensure access to ICT by Ethiopia‘s rural population.( It
is also linked to Vision of Improved Service Delivery across different Channels)
Element of Vision: Effective Governance
Outcome 3: Improved turnaround time for service delivery
Target 4 – At least 30% improvement on Government Transformation Index (GTI) from
2010 to 2015: Government Transformation Index (GTI) helps to assess impact of the e-Government
program on Government based on parameters such transparency, accountability, responsiveness and
quality of delivery of services. It aims to measure the beneficial impact of projects in transforming
government practices at a program level. This tool will also build a review mechanism to assess the
impact of implementation of e-Government strategy in enhancing the effectiveness of the
government. The target is to improve government efficiency by at least 30% from 2010 to 2015.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 26 Confidential
Outcomes and Targets Description
Outcome 4: Joined-Up Government
Target 5- Integration of Ministries /Agencies through common applications, standards
and policies: The e-Government Strategy mandates the implementation of common applications,
standards and policies to improve government efficiency and costs through facilitation of better
coordination amongst the government departments. Towards this end, two key imperatives would be:
Core projects which include, Data Centre, Woreda Network, National Dataset, Payment Gateway,
Enterprise Architecture and PKI would be implemented to provide the requisite foundational
infrastructure upon which service enablement can be accomplished
Along with the core infrastructure, common applications need to be made available across the
Ministries and Agencies to enable smooth functioning and provide focus on implementation of
the priority projects by reducing the effort required. The common applications would also
facilitate collaboration and consistency across common processes such as procurement, HR
management, Financial Management etc.
Outcome 5: Customer friendly and Accountable Government
Target 6 – Capacity building of all officials on IT and Customer behaviour: Capacity
building is an integral part of the e-Government strategy and is envisaged to be a tool for change
management, imparting relevant IT skills to government personnel and to re-orient the customer
facing staff in terms of customer etiquette and quality of service. By 2015, all the officials should have
received training relevant to their job which will enable them to discharge their responsibilities in a
more effective and efficient manner.
Linkage to National ICT Policy Goals:
Establish highly skilled ICT human resource base for transforming Ethiopia into a
knowledge- and information-based society and economy.( Through Capacity Building
Initiatives detailed in further sections)
Promote infrastructure development including physical and telecommunications and
communications infrastructure as a backbone for ICT development.( Core Projects and
Common Applications which will help in delivery of public services)
Element of Vision: Improved Service Delivery
Outcome 6: All services accessible within the community
Target 7 - Electronic enablement of 219 services: Electronic enablement of the 211 service
‗transactions‘ to enable services across Life Cycle Events for businesses and citizens/residents. All
services that can be provisioned electronically will be made available through alternate channels.
Procedural information and support for services that are not amenable for electronic delivery will be
provisioned through alternate channels.
Additionally, a Grievance Redressal System will be developed during the first year of the program, i.e.
2011. Procedural information about all the services that may not be amenable for electronic delivery
will also be made available through electronic channels. (Definition of Life Cycle Events and
transactions has been provided in Annexure I).
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 27 Confidential
Outcomes and Targets Description
Target 8 – All the 4 Channels established with more than 50% uptake for alternate
service delivery channels: The customers should be able to interact with the government at a time
and place of their liking. To facilitate this endeavour, the access to government services and
information would be provisioned through internet, m-Government and contact centre so that
citizens can connect with government 24*7. Further, common services centres would be leveraged to
provide all government services within the community. All the channels are envisaged to be
functional by 2012 albeit with different number and maturity of services. All identified services to the
maximum possible depth to be provided through all channels by 2015. Uptake of services through
alternate channels is the best indicator to test the success of these channels and therefore all efforts
would be made to ensure that at least 50% of the transactions with the government are conducted
through the alternate channels. This would reflect the efficacy of reaching out to all customers and the
effectiveness of the alternate channels created as part of the strategy.
Outcome 7: Improvement in Customer Satisfaction
Target 9 – 60% customer satisfaction: The Customer Satisfaction Index would use mechanisms
like e-Poll, Feedbacks, e-Consultation, surveys, etc, to assess customer satisfaction levels with delivery
of government services. Comprehensive reviews will be undertaken to take corrective measures
wherever satisfaction rating falls below 50% of all customers. The target is to achieve 60% customer
satisfaction rate by 2015.
Target 10 - Published Customer Charters for all services provided by government
organizations by 2015: Customer charter is a published document that announces the service
levels such as the turnaround time for service, escalation mechanism in case of unsatisfactory quality
of service, requirements for availing services etc. The target is to put in place a Customer Charter in
place for all services provided to citizens, businesses, government employees and visitors. This is
likely to increase customer satisfaction levels due to higher transparency and accountability in
provisioning services.
Linkage to National ICT Policy Goals:
Deliver efficient and effective public and civil service to all citizens.( Through Multiple
Channels, enablement of e-Services and customer charters for transparency)
Ensure that ICT as an integral part of education and training at all levels.(Education is one of
the 12 Priority Projects being implemented as part of the Strategy)
Modernize and expand improved health services coverage using ICT. (Health is one of the 12
Priority Projects being implemented as part of the Strategy)
Modernize agriculture and radically increase output and productivity. (Agriculture is one of
the 12 Priority Projects being implemented as part of the Strategy)
Element of Vision: Socio-Economic Growth
Outcome 8: Improve Business Climate
Target 11 – Amongst top 75 in Doing Business rankings of World Bank for ease of doing
business in the country (Ranked 116 in 2009): Doing Business is an annual report
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 28 Confidential
Outcomes and Targets Description
investigating the regulations that enhance business activity and those that constrain it. It presents
quantitative indicators on business regulations and the protection of property rights that can be
compared across 181 economies. The delivery of services through alternate channels is likely to
simplify business processes and reduce the cost of doing business and compliance with regulations.
Outcome 9: Growth of ICT entrepreneurship/Industry
Target 12 – Investment of > 10% of Budget of e-Government Program through PPP:
Experience of other countries illustrates that a number of industries such as banking, education,
Information Technology, Telecommunication etc. get positively impacted due to large scale e-
Government implementations. The players in these sectors invest not only as part of their Corporate
Social Responsibility (CSR) initiatives but also to create goodwill and awareness regarding their
products through advertisement and association with the e-Government program. It is envisaged that
such partnerships will facilitate in accrual of 10% of the total funds required for the implementation
of the e-Government strategy.
Linkage to National ICT Policy Goal:
Develop an efficient and globally competitive ICT industry( Through Private sector
Involvement and Growth)
Ensure Ethiopia‘s effective participation in national, regional and global trade( Trade portal is
one of the 12 Priority Projects being implemented as part of the Strategy)
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 29 Confidential
II. Strategic Dimensions
In order to achieve the above outcomes and targets leading to the realization of the vision, strategic
components and an action plan for the implementation of these strategic dimensions has been defined.
The figure below presents the key Strategic dimensions:
Figure 3: Key Strategic Dimensions
As can be seen from the figure above, the key dimension of the e-Government strategy for Ethiopia are
Services enablement through the implementation of 12 Agency priority projects, delivery of services
through 4 alternate channels of services delivery and the enablers which will facilitate the creation of a
sustainable ecosystem for the implementation of the e-Government strategy. All these dimensions are
shrouded in the Governance structure to highlight the key role that the governance
mechanism for the e-Government program is envisaged to play in ensuring that each of the
strategic dimensions gets implemented in a way that furthers the overall implementation of the e-
Government program. The strategic components are explained as follows:
Strategic Dimension 1 -Service enablement
1. Agency Priority Projects - 219 services through implementation of 12 Agency Priority Projects that
will facilitate service enablement of these services based on lifecycle based service requirements of
customers. The key priority projects are mentioned in brief below:
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 30 Confidential
i. Agriculture Services - Given this overwhelming significance of Agriculture in the Ethiopian
economy, it is imperative to leverage ICT to facilitate services provided for the agricultural sector.
This project would be undertaken under the ownership of the Ministry of Agriculture and Rural
Development.
ii. Benefits Management - Benefits are offered to Citizens by various agencies and departments.
To improve satisfaction with the services, it is essential that the customers are able to get
information about their eligibility for different schemes and file a single request to avail all the
benefits. Such a common interface also enables better management and improved service levels of
the services offered by such benefit schemes. This project would be undertaken under the
ownership of the Social Security Agency or Ministry of Labour & Social Affairs and would also
involve Addis Ababa city administration.
iii. Education - Education is one of the priority areas for the development of Ethiopia. Education
related services have huge potential for leveraging ICT. The field of education is apt for initiating
such a project as it has a direct impact on the future development of the country. This project
would be undertaken under the ownership of Ministry of Education.
iv. E-Health - Health is also one of the focus areas for the government of Ethiopia. It is imperative
that the field of health is IT enabled not only to improve the efficiency and the effectiveness of the
Hospitals and labs but also to build a base for gaining access to future advancements in medical
science. The field of health is also a prime candidate for leveraging ICT for better service delivery
to the citizens of Ethiopia. This project would be undertaken under the ownership of Ministry of
Health.
v. Trade Portal - The portal would serve the business community‘s need for information and
services such as business registration, licensing, loans, penalties etc. Also investment related
regulations and processes would be facilitated through the G2B Portal. The portal is also a
medium of interaction and feedback on Government policies and regulations. It is imperative for
the G2B space to be e-enabled for sustained economic growth of Ethiopia. This project would be
undertaken under the ownership of Ministry of Trade and Investment.
vi. Employment - Generation of adequate employment opportunities is imperative for the
prosperity of Ethiopia. This project envisages facilitating the same through better information
dissemination amongst the unemployed and by providing a forum for the companies and the
individuals to interact. This will also help the businesses find the right people. This project would
be undertaken under the ownership of the Ministry of Labour.
vii. Transport - This project would facilitate the electronic enablement of the services provided by
the Ministry of Transport and Communication and the Transport Authority. Most of these
services such as the services related to Drivers License and Registration of vehicles are high
volume, high impact services that would improve the service experience of a large number of
people. This project would be undertaken under the ownership of the Ministry of Transport and
Communications.
viii. Tourism - The government is keen to leverage the same to enhance the contribution of the
tourism sector in the national economy. This priority project is envisaged to be a facilitator
towards this end. This project would be undertaken under the ownership of the Ministry of
Culture and Tourism and participation of Ministry of Foreign Affairs.
ix. Tax - The Government of Ethiopia has launched an ambitious government transformation plan
aiming at double digit growth of the economy for the next 5 years. In order to support such a
voracious growth, a huge number of resources need to be mobilized. In order to generate these
resources, it is imperative to ensure that the cost of compliance to tax system in Ethiopia is
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 31 Confidential
lowered so that tax collections may be enhanced. This project aims to facilitate the same. This
project would be undertaken under the ownership of the Revenue and Customs Authority.
x. e-Court - e-Court project envisages leveraging ICT to facilitate the delivery of services provided
by the judiciary. This project would be undertaken under the ownership of the Ministry of Justice.
Services of the Federal Supreme court would also be covered under the project.
xi. Municipalities - This project envisages leveraging ICT to facilitate the delivery of services
provided by the Municipalities. This project would be undertaken under the ownership of the
Addis Ababa City Administration.
xii. Passport & Visa – This project envisages automation of services relating to issuance of
passports and visa and the services would include application/renewal /replacement of passport,
visa processing and ID Card issuance for Foreign Nationals. The project would be undertaken by
Ministry of Foreign Affairs
The electronic enablement of services will be undertaken in a phase wise manner. It
is expected that while all information services, grievance redressal mechanism and
most information services will be provided electronically by the end of year 1 (2011),
transactional services will be enabled progressively over the course of next 5 years
(2015).
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 32 Confidential
The e-Services enablement plan for 219 services through the priority projects is provided below in figure
Figure 4: e-Service enablement Plan
Agency Priority Projects Year 1 Year 2 Year 3 Year 4 Year 5 Total
Agricultural Services
15
29 6 8
Benefits Management system
2
5 3
Education
5
13 3 5
Health
4
14 10
e-Trade
6
18 5 7
Employment
3
7 12
Transport
6
14 8
Tourism
4
14 2 4 4
Tax
7
13 6
e-Court
11 4 7
e-Municipality
25
62 13 19 5
e-Passport
2
11 4 5
Yearly Services 35 73 64 30 9
Total Services ( 79 Informational,140 Transactional) 219
Transactional
Informational
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 33 Confidential
2. Common Applications: Common applications need to be made available across the Ministries and
Agencies to enable smooth functioning and provide focus on implementation of the priority projects
by reducing the effort required. The common applications would also facilitate collaboration and
consistency across common processes such as procurement, HR management, Financial Management
etc. The details of the common applications include
i. e-Procurement: Provide businesses and ministries with common platform to transact with
features such as Demand aggregation, catalogue based procurement, dynamic pricing engine,
etc
ii. HRMS - Government wide HRMS application to handle all functions related to leave,
transfer, payroll, recruitment etc.
iii. E-office- To eliminate the paper-based interactions even within the government across
different agencies by using a single solution
iv. FMIS - Enhancement of the existing Integrated Budget and Expenditure System (IBEX)
addressing the core functions of public financial management
v. Email Management System: Email can be used as a very effective medium for the inter-
office and intra-office communication. Since the email system will be common across the
departments, the common system can be used across with the standardization in email
addresses.
The implementation plan for the common applications is provided below:
Table 3: Implementation Plan for common applications
Yr. v/s Project
Implementation plan
Year 1 Year 2 Year 3 Year 4 Year 5
e-Procurement
HRMS
e-Office
FMIS
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 34 Confidential
3. Core Projects: The core projects, as mentioned are proposed to be implemented in the 1st three
years of implementation of the strategy implementation, considering the fact that they would be
building blocks/ or the facilitators for the priority project implementation.
I. National Data set: Provisioning a national level data set of commonly used data elements
across ministries, that can be used by all inter-ministerial applications as well as channels of
delivery (national portal, mobile portal, CSC, NCC etc.) for delivering eServices
II. National Enterprise Service Bus (NESB): Provisioning a platform for seamless
integration of ministry / agency applications and database at the back end; integrating all
front end channels to deliver eServices
III. National Integrated Authentication Framework(NIAF): Provisioning of a unique
identity based login to individuals for accessing the various electronic channels of
government (National Portal, Mobile Portal, Common Service Centre (CSC) and National
Contact Centre (NCC) & other ministry applications
IV. National Payment Gateway: Provisioning of a national payment gateway for Ethiopia to
enable all modes of electronic payments to be transacted through all the electronic channels
of delivery
V. PKI : Provisioning of PKI based identification, integrity and non-repudiation for online
transactions related to the e-Government projects in Ethiopia
VI. Woreda Network: Provisioning of high bandwidth connectivity between ministries and
agencies for sharing data, voice and video communication throughout the country
VII. National data Centre: It is proposed that the Ethiopian National Data Centre (ENDC)
would consolidate services, applications and infrastructure to provide efficient electronic
delivery of G2G, G2C and G2B services. ENDC infrastructure shall provide adequate space to
house ICT assets of various departments and Government agencies within the country in an
environment that meets the need for reliability, availability, scalability, security and
serviceability.
VIII. National enterprise Architecture: Unified architecture adoption across ministries
enabling better integration of ministry applications
The implementation plan for the common applications is provided in the table below:
Table 4: Implementation Plan for Core Projects
Yr. v/s Project
Implementation plan
Year 1 Year 2 Year 3 Year 4 Year 5
National Data Set
National Enterprise Service Bus
National Integrated Authentication Framework
National Payment Gateway
Public Key Infrastructure
Enterprise Architecture * WoredaNet and National data Centre is already being implemented by MINISTRY OF
COMMUNICATIONS & IT
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 35 Confidential
Strategic Dimension 2- Channel Enablement:
Implementation of the following four service delivery channel enhancement projects that will enable the
customers to demand and avail services as per their choice and convenience:
1. e-Government portal where customers can use internet to request and avail services, search
information, make payments, etc the national e-Government portal of Ethiopia – www.ethiopia.gov.et
needs to be updated and enriched with the electronic enablement of 219 services over the next 5 years.
Currently Ethiopia‘s e-Portal is managed in-house. Based on the current assessment of the existing
portal and websites of various departments, it is suggested that the government continue with the ―in-
house portal‖ model. However, the portal must be enhanced to be able to provide eServices.
Additionally, the Government must consider options to allow private sector participation in the
provision of related value-added services through the e-Government portal.
2. Phone (Call Center) where customers can call up to request services and information and access
the same through call center agents and ‗Interactive Voice Response‘ technologies. Government of
Ethiopia has set up an in-house government call center. Since the exiting set-up is very basic and not a
full-fledged call center, it is suggested that as part of the e-Government strategy implementation, the
government establish an ―Outsourced Call Center‖ to facilitate e-Services. It is planned to provide
around 77 Informational and 40 transactional services through the call centre channel.
3. Mobile Gateway where customers can request services and information through mobile phones and
hand-held digital personal assistants. The departments can send customers regular alerts through
SMS. It is recommended that the Government of Ethiopia should review options of Outsourced
Mobile gateway and ASP model (vendor managed) gateway for its services as current number of
transactions may not warrant a dedicated in-house mobile gateway. It is planned to provide around 77
Informational and 40 transactional services through the Mobile channel.
4. Common Service Centers (CSC) where services like Information dissemination, acceptance of
service requests and delivery of services is provided to the customers at a single point of service
delivery. It is recommended that the 92 existing ICT Community Centres and the proposed 42 Unified
Billing Centres are leveraged as CSCs for offering government services. In addition it is proposed to
set-up around 800 centres (equal to approx. number of Woredas) on a PPP model. These centres
would provide access to the 219 services – across the country.
Given the high cost of ownership of internet, PC and mobiles and the relatively low
ICT literacy in Ethiopia, Common Services Centers are expected to be the primary
vehicles of electronic services delivery during the initial part of the implementation of
the e-Government Strategy. Mobile channel is also expected to become a key
channel for delivery of services over the next 5 years if the projection of the number
of subscribers of mobiles in Ethiopia were to be realized.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 36 Confidential
The implementation for e-Services through the channels is provided below
Table 5: e-Services Implementation Plan for the Channels
Channel Year I Year II Year III Year IV Year V
Portal 35 73 64 30 9
Contact Centre
35 42 20 20
Mobile 35 42 20 20
ICT Centres 35 73 64 30 9
Strategic Dimension 3- Enablers:
It is essential that the various components of the e-Government strategy are supported by the following
Five key enablers to assure successful and timely implementation of the e-Government strategy and
ensure the sustainability of the initiatives:
Common standards and policies would enable an integrated and connected Government and
facilitate standardization and efficiency across all key elements of the e-Government Components
Capacity building activities such as training, career planning and change management would
ensure the availability of personnel resources and skill sets required to achieve the strategy
Marketing and awareness campaigns are key enablers in generating awareness and
communicating with external and internal stakeholders to generate sufficient demand for the
electronic services and reduce possible resistance to e-Government
Monitoring and evaluation would enable the High Committee/Technical Committee, through the
project office, to monitor progress, customer satisfaction and government transformation which
would be important in assessing if the desired outcomes are being achieved
Public Private Partnership models facilitate private sector participation for effective and efficient
delivery of services
Overall Cost Estimates: Budgetary estimates for the implementation of the Strategy over a period of
five years are approx. 3328.18 Mil. Birr or approx. 201.46 Mil USD. Details are provided in section 8 of
the Report.
Overall Implementation Plan: The E Government Strategy along with all its components is to be
implemented and monitored and assessed over a period of five years.
The components essentially comprise of the core projects – which are the infrastructure projects, the
identified twelve priority projects and the Enablers. The enablers would actually be implemented over a
period of 1 year – but they will be used on a recurring basis for the entire five year period.
The brief of the proposed overall implementation plan is provided below. The details of the
implementation are in chapter 7.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 37 Confidential
Table 6: Overall Implementation Plan
S No. Project Implementation Plan
Year 1 Year 2 Year 3 Year 4 Year 5
Core Projects
1 National Data Set
2 National Enterprise Service Bus
3 National Integrated Authentication Framework
4 National Payment Gateway
5 Public Key Infrastructure
6 Enterprise Architecture
Priority Projects
1 Agriculture services
2 Benefits Management System
3 Education
4 Ehealth
5 G2B Portal
6 Employment
7 Transport
8 Tourism
9 Tax
10 Ecourts
11 Municipality
12 Passport & Visa
Enablers
1 Marketing & Awareness Campaign
2 Capacity Building
3 Monitoring & Evaluation
4 Standards & Policies
Common Applications
E-Procurement
HRMS
E-Office
FMIS
E Mail
These components of the e-Government Strategy must be looked at in totality and the dynamic nature of
the same must be acknowledged. Towards this end, the Governance Structure put forward in this
document would provide an institutional mechanism responsible for coordinating and monitoring the
implementation of the strategy and ensuring benefit realization. The following chapters detail out
the recommendations for the Governance Structure and implementation of these strategic
dimensions.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 38 Confidential
Section 3 –
GOVERNANCE
STRUCTURE
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 39 Confidential
III. Governance Structure
This section describes the Governance Structure that should be established to oversee and facilitate the
Ethiopian e-Government Strategy implementation process. Some of the key factors that have been
considered while drafting the governance structure are:
Ownership and Accountability for success of implementation of the e-Government program needs
to be established;
Focus on realization of the strategic dimensions identified in the strategy needs to be maintained;
Ethiopian e-Government Strategy is a Government wide strategy that cuts across Ethiopia‘s
different Ministries/Agencies, it is not meant for any specific Ministry/Agency or sector.
Therefore, a forum needs to be established to facilitate coordination amongst all stakeholders;
and
Government priorities, frameworks, processes and organization structures.
Based on the Assessment done the following gaps have been identified:
Lack of a holistic coordination and cooperation across the Government for properly developing and
utilizing IT;
IT organization structures, roles, and responsibilities are not properly defined nor approved, resulting
in IT organizations in the Government Entity with varying levels of maturity in terms of design and
resourcing;
Lack of a clear program and project management framework and tools to ensure all e-Government
initiatives apply the same controls and quality measures and proper planning is in place for IT
development;
Lack of knowledge sharing and resources sharing which can speed the process of IT implementations
in common domains; and
IT expenditure is not recognized among the Ministries/Agencies budget, in addition, there is no
allocation of a central fund to support central IT projects implementation.
I. Drivers for the Governance Structure
To guide the program towards achieving its objectives, the development of the program governance
should take into consideration the nature of the program and the surrounding circumstances and factors
that will influence and drive the program in the long and short terms. The Ethiopia e-Government
Strategy Governance Structure drivers include the following:
The e-Government Strategy is for the Government as a whole;
A large program with many projects needs to be coordinated and managed;
A high number of stakeholders in different locations to be managed;
A proper level of trust and confidence around the program need to be established;
Standardization of approach and use of standards need to be enforced;
Interdependency and conflicts need to be managed;
Continuous monitoring and course correction is required;
Ongoing alignment to business objectives is mandatory;
Funding and spending critical decisions need to be tackled timely and properly; and
A long term investment that require proper controls.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 40 Confidential
II. Governance Structure: Options and Recommendations
For the successful implementation of e-Government Strategy, the owners for various functions as well as
their relationship with each other needs to be defined clearly. The various roles envisaged and the options
available are analyzed in the following section. Various areas considered are as follows:
Overall sponsorship of program
Need for High Committee
Need for the Technical Committee
PMO as part of Ministry of Communications & IT
Ownership of initiatives in entities
Overall Sponsorship of Program
Considering the scope of e-Government Strategy and its impact, it is imperative that the ultimate
ownership of project rests with a high level authority. The sponsor of program will own the functions
related to funding and strategic directions. In the table below the options of having Council of Ministers
under the Prime Minister or a Board under the Council of Ministers as program sponsor has been
analyzed.
Table 7: Options for sponsorship
Options Advantages Disadvantages
Council of Ministers
under the Prime
Minister
• Highest ownership in policy level decisions
• Establishment of the identity and importance of the program
• Easy co-ordination between Ministries/Agencies
• Quicker conflict resolution
• Sustainability of program will be ensured
• Decisions may be delayed
• Prime Minister may not be able to regularly monitor the progress of the Program
A Board under
the Council of
Ministers as the
sponsor
• Quick decision making • Multiple stakeholders in board with different roles
• No ownership at individual level
• Insufficient level of support
Need for a High Committee
The best governance practices globally recommend the formation of a High Committee for large scale IT
Strategy implementation. The role of this committee will be focused on providing guidance for the
strategic directions and coordinating at the highest level. The available options for constituting the High
Committee are analyzed in the table provided overleaf:
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 41 Confidential
Table 8: High Committee Assessment
Options Advantages Disadvantages
High Committee
chaired by Minister of
Communications & IT
• High visibility of program
• Co-ordination and conflict resolution mechanism amongst Ministries
• Program could become a part of high priority agenda of the Council of Ministers
• The legal and policy level issues can be managed
• Members may not be available to meet too often which may result in delays in decision making process
No High Committee –
Recommendations
made by Technical
Committee
• Availability of members to meet and discuss
• Authority to enforce decisions across the Government is weak
• Decisions on Ministry level have to go through a higher level (the Minister)
Need for a Technical Committee
The best practices globally recommend the formation of a Technical Committee for Strategy
implementation. The role of this committee will be to coordinate, monitor the progress and establish
standards for implementation. The advantages and disadvantages of constituting a Technical Committee
are placed in the table below:
Table 9: Technical Committee
Options Advantages Disadvantages
Technical Committee
chaired by
Representative –
Ministry of
Communication & IT
• Co-ordination between Ministries
• Regular monitoring of the project progress
• Faster resolution of technical issues
• The organization structure may have too many committees and delays in decision making process
• The Technical Committee is not empowered to undertake policy decisions
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 42 Confidential
Project Management Office (PMO) under e-Government Directorate of Ministry of Communications & IT or separate Directorate or separate Entity
In the new structure, the role of the Project Management Office (PMO) is focused on monitoring,
compliance and supporting the central as well as entity level initiatives. PMO will also be playing a critical
role in the capacity building and knowledge management across various Ministries/Agencies. The option
of having the PMO as part of Ministry of Communications & IT or as an independent entity was evaluated,
considering the scope of PMO.
Table 10: PMO Options
Options Advantages Disadvantages
PMO as part of e-
Government
Directorate
Ministry of
Communications &
IT
• High maturity level as organization
• Office infrastructure is in place
• Availability of skilled manpower
• Ministry of Communications & IT will enable a structured reporting mechanism & process
• All conflicts related to IT implementation can be resolved easily
• The implementation will require the ownership from different Ministries/Agencies and co-operation will require continuous & efficient co-ordination
PMO as a Separate
Directorate
Ministry of
Communications &
IT
• Office infrastructure is in place
• Dedicated team to implement the e-Government Strategy
• All conflicts related to IT implementation can be resolved easily
• Recruitment of all the officials of the Directorate needs to be dome
• Coordination with the e-Government Directorate with conflicting roles
• Reporting structure needs to be established
PMO as an
independent Entity
under independent
implementation
agency – like
erstwhile EICTDA
• PMO will be Entity-independent • PMO need to co-ordinate with various sub-committees within implementation agency
• PMO will need empowerment and support from Government officials
• A new Entity that will need to undergo different levels of maturity to reach the right shape
• The new reporting structure needs to be carefully designed and approved
* Please note that the role of implementation agency for e-Government implementation within
MoC&IT may be finalized after structure of the MoC&IT is finalized.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 43 Confidential
Ownership of IT initiatives in entity
Implementation of all the central initiatives will be owned by the implementation agency but the
ownership of initiatives at the Ministries‘ level needs to be clearly defined to avoid any conflict in scope
and responsibilities. The options available in this area are analyzed below:
Table 11: Ownership of IT Initiatives
Options Advantages Disadvantages
Implementation
Agency owns the
implementation of
Ministries/Agencies
initiatives
• Central control on the implementation
• Easy to enforce standards and procedures
• Lack of ownership by Ministries/Agencies
• No domain expertise, as a result providing direction will be difficult
• Funding will be done by entity so ownership can be questioned
Ministries/Agencies
owns the
implementation
• Faster implementation and better control
• Scope of project can be defined considering the requirements of the entity
• Sustainability resulting from ownership
• Compliance with standards and procedures may be impacted
The recommendations based on analysis of the various options are as follows
o The Council of Ministers headed by Prime Minister should be the Program sponsor
o High Committee under the Minister of Communications & IT is needed in the overall structure for
effective implementation of the strategy
o Technical Committee is needed in the overall structure
o PMO will be under e-Government Directorate of Ministry of Communications & IT
o Ministry/Agency initiatives will be owned by the respective Ministries/Agencies and will be
supported by the PMO while core and common initiatives will be owned by the Ministry of
Communications & IT
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 44 Confidential
III. Recommended Governance Structure
In light of the recommendations above, envisaged governance structure is placed below:
Figure 5: Recommended Structure
As shown in the figure above, the ultimate responsibility for the implementation of the Ethiopian e-
Government program lies with the Council of Ministers under the Ethiopian Prime Minister. The High
Committee will be assisted by the PMO in Ministry of Communications & IT for monitoring, coordinating
and directly following up the execution of IT initiatives. Ministries and other Government Agencies are
the owners of their respective core and cross Government projects and will get the support for delivering
these projects from the PMO.
In addition, Ministries and other Government Agencies are responsible for developing their vertical IT
Strategies and implementation plans in coordination and under the direct supervision of the Technical
Committee, in line with the e-Government Strategy and are responsible for deploying their
Ministry/Agencies specific IT vertical projects. The Technical Committee will report on the progress and
the issues of the strategy implementation to the High Committee.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 45 Confidential
Progress on vertical plans execution will be reported to the PMO to ensure alignment amongst all e-
Government initiatives. All work initiated and conducted by Ministries/Agencies should be in compliance
with the approved Strategic Directions. Any deviation – during implementation – from the directions
provided in the Strategy document should be pre approved by the High Committee.
Description of the Entities presented in the Governance Structure
1. Overall Sponsor: The e-Government Strategy Sponsor is the council of Ministers under his
Excellency, the Prime Minister. Ownership at this level is mandatory to ensure that the program
receives sufficient support, which is necessary to ensure the success of the Program taking into
consideration the size and nature of the change to take place. It is envisaged that the Prime minister
as the Program owner will sponsor the program across the Government, push for change and
resources, publicly take ―ownership‖ of the projects and commit his time on a sustained basis.
2. The High committee chaired by Minister of Communications & IT will have the following
members:
1. The Minister of Finance and Economic Development
2. The Minister of Labor and Social Affairs
3. The Minister of Transport
4. The Minister of Agriculture
5. The Minister of Education
6. The Minister of Trade
7. The Minister of Industry
8. The Minister of Foreign Affairs
9. The Minister of Works and Urban Development
10. The Minister of Justice
11. The Minister of Civil Services
12. Representative(s), PMO
13. DG, Social Security Agency
The High Committee would be responsible to:
Agree on priorities among Program initiatives;
Lead the implementation of the e-Government Strategy across the Government covering all tracks
defined within the Strategy and the implementation Roadmap. This includes submitting
strategies for final approval by the High Committee, initiatives and projects approval and the
monitoring and control activities;
Harmonize the Strategy implementation across all the components and manage
interdependencies; and
Specify required funding and administer the allocated funds as part of Program management
activities.
3. The Technical Committee is responsible for the Program implementation management through
initiatives implementation management and provides Program integration, interdependency
management and delivery assurance. The Technical Committee will report to the High Committee
and will contain IT heads from the following Ministries/Agencies:
1. Ministry of Minister of Communications & IT
2. Ministry of Finance and Economic Development
3. Ministry of Labor and Social Affairs
4. Ministry of Transport
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 46 Confidential
5. Ministry of Education
6. Ministry of Agriculture
7. Ministry of Education
8. Ministry of Trade
9. Ministry of Industry
10. Ministry of Foreign Affairs
11. Ministry of Works and Urban Development
12. Ministry of Justice
13. Ministry of Civil Service
14. Social Security Agency
15. Head of PMO
The Technical Committee will be responsible for the following:
Identify technical assistance requirement at project implementation units;
Assist in developing program level training schedule for project teams, general IT skills,
technology etc ;
Identify competent technical as well as administrative resources (within the Government and
externally) for specific requirements of stakeholders;
Lead the development of IT related policies and standards and submit drafts for High Committee
sign-off;
Lead the development of IT related regulations and submit drafts for High Committee sign-off;
Lead the discussions with the private sector organization; and
Support resolving conflicts whenever they arise and escalate conflicts to High Committee
whenever resolution is not possible.
4. Ministry of Communications & IT will own the implementation of e-Government Strategy with
support from Programme Governing Body or PMO. Some of the important functions of Ministry of
Communications & IT and the PMO are as follows:
Specify required funding and administer the allocated funds as part of e-Government Strategy
activities;
Lead the development of IT related policies and standards and submit drafts for High Committee
sign-off;
Lead the development of IT related regulations and submit drafts for High Committee sign-off
Lead the discussions with the private sector organizations; and
Facilitate implementation of the IT initiatives across the Ministries/Agencies.
5. The Project Management Office (PMO) will be part of the E-Government Directorate of
Ministry of Communications & IT and will support the e-Government Strategy implementation
through monitoring projects delivery, controlling the relation with vendors, managing the
procurement process, ensuring compliance with policies and standards, auditing projects at hand
over, knowledge management and sharing for areas related to project management. The PMO will
play the following roles:
Monitoring the implementation of the e-Government Program on the different aspects (technical,
administrative and financial);
Project Addition/Deletion Approval
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 47 Confidential
Supporting with evaluating requests received from the different Ministries/Agencies for
implementations, and Supporting projects execution tasks through the identification and
allocation of required resources; and
Knowledge sharing for experiences gained through executing the different Program components
Procurement and contracting process management.
The organization structure of the PMO (described in diagram in next page) was developed based on
the above mandate, where the following key departments will have the core teams tasked to deliver
listed roles:
Project Coordination
Knowledge Management
Appraisal
ITSG (IT Services Group)
Marketing & Awareness
Monitoring & Evaluation
Cadre Control
The core teams will be supported by the following support teams which will report to the respective
departments in the MoC&IT
Financial Control
Procurement
The PMO will contain a pool of resources that can be assigned different tasks depending on work load,
projects nature and projects level of maturity. Accordingly, one team member can play several roles that
can be of monitoring, support, and knowledge or procurement nature. The details regarding PMO
Staffing requirements have been provided in Annexure II. The recommended structure for the
Project Management Office (PMO) is provided in the figure below:
Figure 6: Project Management Office (PMO) Structure
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 48 Confidential
Core Team of PMO
The details of the Core team of the PMO are provided in the following sections:
Project Co-ordination Team
This team will contain experts in infrastructure, applications, business process and information security
and control requirements. It will be mainly responsible for the following:
1. Liaise with the implementing Ministries/Agencies closely and provide necessary coordination in
order to ensure the realization of the Program targets and to facilitate the integration of the projects
outputs with the e-Government Strategy;
2. Manage and monitor the implementation of the Program by assisting the Ministries/Agencies and
other stakeholders;
3. Gather and review work plans from implementing Ministries/Agencies, and monitor the
implementation of the different tasks defined in the plan;
4. Periodically report projects‘ progress to the Program Governance Board with detailed analysis of
status and deliverables;
5. Review projects‘ deliverables and ensure deliverables specifications and quality meet those agreed in
the contract signed with the service or technology provider;
6. In addition to monitoring projects, the Project Coordination team will also be involved in reviewing
service level agreements for maintenance and operation contracts to validate compliance versus
agreed terms and conditions from technical perspective;
Knowledge Management Team
It is mandatory to apply the same standards on the different projects within the e-Government Strategy
Program; this includes applying the same procedures, using the same templates, and following the same
controls. In addition, there will be similar implementations rolled out across the Government; the
knowledge gained in one implementation will need to be shared among others.
The Knowledge Management team will be responsible for the following:
1. Develop knowledge management objectives and plan on annual basis
2. Ensure the same project management standards are applied across the e-Government Program
3. Define the broad contours of the Knowledge Management Portal to be developed as part of the
Capacity Building Initiative.
4. Maintain a central database of references, templates, projects documentation and other details
5. Provide project managers in the different Ministries with access to the central database
6. Conduct awareness sessions on approved project management frameworks and standards for the
different stakeholders
7. Ensure project managers provide proper documentation on their projects at project conclusion
Appraisal Team
To properly manage requests for implementations (and associate funding), all requests will be
accompanied by a Detailed Project Report which will contain technical and financial information about
the requested change. The Appraisal team will handle the evaluation of all received requests and will
perform technical and financial reviews to ensure received requests are in line with the Strategy and
within the approved budget allocations. The purpose of the technical review and the financial review are
described below:
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 49 Confidential
Technical Review
The technical review will target ensuring the following:
Alignment of project with the Strategy
No overlap with approved, core and common initiatives
A proper utilization of shared and central facilities
The scope of work is defined clearly
A proper functional description is in place
A proper technical description is in place
Potential risk identified for the initiative and risk mitigation plan.
Details about the dependency of initiative on other initiatives (core, common or Ministry/Agencies
specific)
Post implementation support plan is described properly
Financial Review
Financial review activities target ensuring the following:
Details about the fund required with sufficient break down are included in the request submitted by
the Ministries
Financial analyses including CAPEX and TCO are covered in the request
Adherence with Procurement policy
Availability of funds
Identification of funding options/resources
ITSG (IT Services Group)
To support the different projects that are part of the Program, resources will be needed to perform project
management, technical activities and administrative activities. The need for resources will be assessed on
a case by case basis to ensure projects are neither over staffed nor under staffed. The ITSG Resources
team will play the role of Capacity Balancing by identifying resource requirements and allocating
necessary resources accordingly. The source of these resources can be contracting with third parties.
Option 1 – Ethiopia Internal Resources
The resources with required skills can be deployed for short term from MoC&IT or any other
Ministries/Agencies. This will ensure a proper utilization of in-house capacity and will lead to the
development of a pool of Government experts who are specialized in technical and functional domains.
This option is the preferred option and will be more predominant once capacity has developed properly to
meet the targets established under capacity building domain.
Option 2– External Resources
In the initial phase the mobilization of resources from within the Ethiopia will be a challenge, as a result
experts can be hired from third parties. Consulting, outsourcing and managed services companies can be
contracted to provide technical and project management experts. While mobilizing resources from
external resources, it is important to have a system for knowledge transfer to support internal capacity
building on the long term. The technical areas where experts will be needed can include; Database
Administration and Management, Networking, Solutions Architectures and Integration, Software
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 50 Confidential
Development, Computer Hardware, Financial Analysis, Business Analysis and Re-engineering, and
Organizational Development.
Option 3- Fresh graduates and interns
It‘s very important to employ fresh graduates and interns for suitable supporting roles in various
Directorates in Ministries. ITSG will co-ordinate the hiring of qualified resources from the institutes in
region and will be taking care of mobilization to various Ministries. This will help in building the future
capacity for various positions where consultants will be hired initially. Graduates in Computer Science/IT,
Engineering, Finance, HR and Management will form the part of this pool of resources. ITSG team will
organize annual campus visits as part of internship program to identify such resources.
The indicative structure of ITSG required at the Ministries/Agencies is provided in the figure below (The details regarding ITSG qualifications requirements have been provided in Annexure XV)
Figure 7: ITSG Structure
Capacity Balancer
Capacity Balancer role will be handled by the ITSG within the PMO who will play the expert role in
supplementing the efforts of the project implementation teams of the initiatives on request.
For a proper execution of the strategy, technical and administrative resources should be available where
and when needed. It is expected to have a lack of sufficient resources in all Ministries/Agencies especially
at the early stages of the Program implementation. To ensure this gap is managed properly a ―Capacity
Balancer‖ – which is one of the main roles of the PMO – will support in allocating the right resources to
support initiatives, these resources can be from within Strategy or through contracting with third parties.
This would integrate seamlessly across the centre and Ministry/Agencies departments to ensure
capacities exist within the implementation units to prepare/undertake initiatives.
The Program Governance Structure is designed to have a structured mechanism to assess individual
Ministries capacities and their gaps and then devising the right intervention to help fill these gaps. This
mechanism would supplement the Ministry/Agencies‘ capacity and equip them to effectively
prepare/undertake initiatives.
The Capacity Balancer would need to address both long term capacity creations such as CIO, IT
Management skills within the Ministry, etc. It would address both long term requirements either by
implanting CIO from existing organizations for longer duration as internal staff and creating skill sets for
the Ministry/Agencies staff. Short term requirements could be addressed by hiring private organizations
or individuals with the required skill sets.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 51 Confidential
The work of the Capacity Balancer is illustrated in the diagram below. For example, Ministry- A may have
internal capabilities in project preparation and design but may not have the necessary know-how in Bid-
Process Management, Budgeting or the resources for Project Management. In such cases, the
Ministry/Agencies may approach the ITSG unit of the PMO, which would in-turn help the Ministry to
identify and engage appropriate resources for a given period to initially undertake the project and
simultaneously build the required capacities. Ministry on the other hand, is fully equipped to undertake a
project and thus would see no significant advantage in requesting support from the PMO
Figure 8: Capacity Balancer
Monitoring & Evaluation Team
This team of the PMO will play a very important role – in terms of development & implementation of
program monitoring tools, implementation of a Monitoring & Evaluation framework consisting of project
progress tracking measures, benefits measurement and impact assessment. This team will also be
responsible for implementation of Government Transformation Index (GTI) and Customer satisfaction
index (CSI).
Marketing & Awareness Team
This team of the PMO will be responsible for all publicity, marketing and advertising activities, which will
ensure that there is a wide awareness among all stakeholders about the program and accordingly the
demand and uptake of the different services is increased.
Cadre Control
This is another important part of the PMO which will oversee the identification, deployment, progression
and capacity building of a central pool of Government IT resources – who will play an important role in
the implementation
Support Team
The details of the support team of PMO are provided in the following sections. The support teams will be
reporting to the respective directorate/division of the MoC&IT, which will also decide the structure and
number of resources of the teams.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 52 Confidential
Financial Control Team
As the implementation of Strategy will involve huge investments, the strategy budget need to be managed
through a comprehensive fund tracking mechanism. The Financial Control team will be responsible for
the following:
1. Monitor the financial status of the program and report any deviation from the approved budget;
2. Perform financial analysis as part of evaluating requests received for new projects from the different
Ministries; and
3. Develop the estimates for the Program annual budget.
The Financial Control team will do ongoing periodic reviews of active projects and will also be involved in
reviewing service level agreements for maintenance and operation contracts to validate compliance versus
agreed terms and conditions from financial perspective.
Procurement Team
As the execution of the e-Government Program will involve large number of procurements in the form of
services, hardware and software, central control over procurement is mandatory to properly control
acquisitions and ensure the standards are applied consistently.
The Procurement team will handle the following tasks:
1. Manage the tendering cycle for core and common initiatives;
2. Prepare purchase orders of IT products like computers, servers, peripherals, networking and any
hardware requirements; and
3. Monitor purchase orders, release of payments, stock entries, billings, deliveries, utilization certificates
related to all IT products;
4. Estimate expenditure details and manage correspondence with suppliers and
departments/organizations after orders placement;
5. Manage framework contracts; and
6. Maintain vendor‘s short list.
The Procurement team will manage the Service Level Agreements (SLAs) with the different providers and
will ensure the following:
SLAs are signed on time;
The terms within SLAs cover the required services;
The providers are complying with their respective SLAs; and
Compliance reviews are conducted by the Coordination team and the Financial Control team.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 53 Confidential
Temporary Capacity Sourcing Agencies
Since implementation of the Strategy would require experts from different domains as mentioned above,
there is a need to have a Temporary capacity Sourcing Agencies who could provide resources with desired
qualifications for a specified contract period. Human Resource Development, Capacity Building, Research
and Consultancy Directorate of MoC&IT could be responsible for empanelment of such agencies and then
procure resources based on the Ministerial/Agency project requirements.
IT Organization Structure at Ministry/Project Level
Each Ministry/Agency will have a dedicated IT department to manage the operations and support of the
IT infrastructure and system implemented within the entity. Currently, the Ministry level IT department
may not have requisite staff and skill set. The profile of the people, their experience and attitude are
critical success factors for the successful implementation of IT initiatives. Given this, it is recommended
that only experts in the respective domains be sourced. Leveraging expertise of resources from the private
sector is a good option in this context. The strategy to have the best quality for a reasonable cost will be to
hire people from the market in the initial phase, get the systems and processes in place. Simultaneously
the senior government officials with sufficient experience and interest will be identified and trained over a
period to take over their positions. This way, over a period of time, there will be systems and processes in
place and people with the right skill-set to take the challenge of achieving the objectives.
Taking cognizance of the above as well as the gaps identified in the present mechanism during current
state assessment of all Ministry/Agency level the recommended minimum composition of the Ministry
level IT Department is given in the following figure
Figure 9: Ministry Level IT Organization Structure
Role of CIO/Head of Department
The key to the long term success of the e-Government Strategy lies in the creation of effective Information
Technology Managers within the Government Ministries. While project implementation along with
associated process improvements could be considered as a onetime activity, the continuous improvement
in processes and technology is an activity for which capacities need to be created within the individual
Ministries/Agencies. International experience indicates that creation of CIOs has been extensively used by
countries to sustain and increase the pace of IT development.
The first step towards creating such capabilities is to create an appropriate position with the identified
responsibility of information management within the Government. Across the globe, this is being
achieved through the role of the Chief Information Officers (CIO)
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 54 Confidential
The governance structure proposed here briefly introduces the concept of CIOs. It is an important
position and can play a significant role. This section highlights the concept and functioning of CIOs, in
addition to describing the structures of IT departments within Ministries, the size of these departments
will vary depending on Entity size and Entity level of dependency on information technology.
The primary role of the CIO/IT Head is to act as the IT manager of the Ministry. He or she would be the
person responsible for Ministry IT strategy development and maintenance, further entity capacity
building, sponsor of IT initiatives within the Ministry, and up keeping and maintaining the IT
infrastructure.
The role of other officials is provided in the table below. (Detailed Qualifications of the Officials in
provided in Annexure IV)
Table 12: Role and Responsibilities of Ministry Level Organization Structure
Department Roles and Responsibilities
Project
Champion
• Project prioritization within Ministry • Identification and resolution of interdependencies • Annual projects budgeting • Preparing Project Detailed Reports for submission to PMO • Ministry projects management at all stages • Implementing and using a Project Management Information System • Track project progress with respect to desired outcomes and outputs and report
the same to senior stakeholders
IT Capacity
Building
Expert
• Design a Capacity Building Strategy for the Ministry • Design the Training Plan • Conduct Trainings of the officials • Monitor the trainings • Procurement of experts from Outsourced agencies for providing training
Government
Process Re-
engineering
Expert
• Monitor the BPR reforms implementation in the Ministry • Monitor the service levels • Identify further BPR opportunities for improvement in service levels • Implement the BPR recommendations
Domain
Experts
• Monitor the BPR reforms implementation in the Ministry • Monitor the service levels • Identify further BPR opportunities for improvement in service levels • Implement the BPR recommendations
IT
Infrastructure
Expert
• Design IT infrastructure requirements • Support in Bid Process Management for procurement of IT infrastructure • Test the IT infrastructure procured • Support in Hardware and Software installation
IT Security
Expert
• Design IT Security Requirements • Implementation of IT Security requirements • Review the Security Controls
Application
Expert
• Design Application architecture • Design the Application Controls • Monitor the Software Development • User Acceptance Testing
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 55 Confidential
PMO Support – Tools and Infrastructure Support
Table 13: PMO Support
Function Tools and Infrastructure Support
Programme Management Technology Tools: Project Tracking, Document Management,
Knowledge Management, Planning and Tracking Tool, Report Writer,
risk management, change management, progress recording
Methodologies : Project Management, Risk Management,
Communication Management, Change Management, Training, Capacity
Building, Project Assessment, Project Proposal and creation, etc.
Infrastructure: Network connectivity, Mail Management, all office suit
products and other office management products like projectors, visual
boards, Video Conferencing facilities, etc.
Fund Management Fund Management System, Financial Management System,
Management Information System, Guidelines for project procurement
and bid evaluation
Technical Assistance /
Capacity Balancer
Standard template for capability gap assessment, guidelines for
processing technical assistance support
HR / Training Standard template and assessment methodology for training need
assessment; formal linkages with select national/international training
institutes for actual delivery
Communication Appointment of a Public Relations (PR) and an advertising agencies to
manage communication – internal and external
Policies / Standard Setting Representation on standard setting working groups, Regular training
and study tours on new technology and applications
Centre of
Excellence/Knowledge
Management
Strong knowledge management tools; Data mining
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 56 Confidential
Section 4 –
STRATEGIC
DIMENSION 1 –
SERVICES
ENABLEMENT
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 57 Confidential
IV. Strategic Dimension 1 - e-Services Enablement
I. Introduction
A service is defined as an interaction or a set of interactions that involve exchange of information /
documents between customers and the government. There are two types of services as enunciated below:
i) Informational Services: includes those services that solely provide information to customers and
do not involve processing of any transactions or documents. For example, providing procedural
information for requesting a service / facility, providing status update of applications for availing
services etc. Informational services have relatively simple back-office operations and can be easily
electronically enabled.
ii) Transactional Services: includes those services where customers require specific actions to be
taken by the department. For example, issue of a driving license is a transactional service.
Transactional services mandate a higher degree of customer interaction and more complex delivery
operations than informational services
II. Guiding Principles for electronic enablement of Service
Focus on designing eServices around citizen needs
Any service should be electronically enabled only after business process has been re-
engineered for that particular service.
Electronic enablement of services should result in visible enhancement of customer
experience in terms of faster turnaround time, lesser visits to government offices and / or
lesser cost of availing services (cost should not be confused with fees)
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 58 Confidential
Page 58
III. Recommendations and Targets
Based on the above guiding principles, 219 services have been considered for phase-wise electronic
enablement. (This list of services is however not static and could vary at time of actual project
implementation as- Ministries, Agencies may have added or modified their services or even make changes
at time of finalizing the application requirements & functionality, for their services.)
Some of the other recommendations are:
1. The Services should be presented on the e-Government portal as per the services life-cycle (explained
in detail in Annexure I) so that the customers can access services intuitively.
2. The services for various groups such as businesses, individuals, government employees, visitors
should be segregated to facilitate easy and fast navigation.
3. In order to implement the services in an integrated manner, bundle of services should be grouped as
priority projects (discussed later).
4. Clear-cut service levels must be defined for electronically enabled services. The services should be
designed such that breach of service levels is escalated to the higher levels so as to fix accountability
for delays.
5. Electronic enablement of a service does not mean that no further work is required to be done
regarding that service. It is imperative to provide robust maintenance support to facilitate acceptable
uptime and performance of the eServices. Features of eServices should also be improved with
technological improvements and based on feedback from users.
IV. Agency Priority Projects
The electronic enablement of services will be realized through the implementation of Twelve (12) Agency
Priority projects. The underlying idea is that the services can be electronically enabled in a sustainable
manner only when the organization that offers the respective services takes ownership of the electronic
enablement.
Each of these 12 projects is detailed out in the next few pages. The service enablement across the priority
projects is provided in the table below
Table 14: Agency Priority Projects
S.No. Agency Priority
Projects Year 1 Year 2 Year 3 Year 4 Year 5 Total
1 Agricultural Services 15 6 8 0 0 29
2 Benefits Management system 0 2 3 0 0 5
3 Education 5 3 5 0 0 13
4 Health 0 4 10 0 0 14
5 E Trade 0 6 5 7 0 18
6 Employment 1 6 0 0 7
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 59 Confidential
Page 59
S.No. Agency Priority
Projects Year 1 Year 2 Year 3 Year 4 Year 5 Total
7 Transport 6 8 0 0 0 14
8 Tourism 0 4 2 4 4 14
9 Tax 7 6 0 0 0 13
10 e-Court 0 4 7 0 0 11
11 e-Municipality 0 25 13 19 5 62
12 Passport & Visa 2 4 5
11
Total Services 35 73 64 30 9 211
The e-Service enablement across the 12 priority projects is provided in the table below
Table 15: e-Service Enablement of Agency Priority Projects
Agency Priority Projects Year 1 Year 2 Year 3 Year 4 Year 5 Total
Agricultural Services
15
29 6 8
Benefits Management system
2
5 3
Education
5
13 3 5
Health
4
14 10
e-Trade
6
18 5 7
Employment
1
7 6
Transport
6
14 8
Tourism
4
14 2 4 4
Tax
7
13 6
e-Court
11 4 7
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 60 Confidential
Page 60
e-Municipality
25
62 13 19 5
e-Passport
2
11 4 5
Yearly Services 35 73 64 30 9
Total Services ( 77 Informational,134 Transactional) 211
Transactional
Informational Details of each of the Agency Priority Project is provided in further sections
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 61 Confidential
Page 61
V. Agriculture Services
Initiative name e-Agriculture
Objective To provide information & services to all stakeholders in the Agriculture sector (farmers, importers, exporters, investors, Government/regulatory agencies, research & support institutions) efficiently using ICT, and enable all stakeholders to contribute & participate in the development of the Agriculture Sector.
Outcomes expected
Improvement in Agriculture services provided by Government
Provide access & improve access to informational & transactional services to all stakeholders across the country
Improve Government administration and supervision of the Agriculture sector by using ICT
Improve overall quality & productivity/yield in Agriculture sector in the country by providing timely access to information on agriculture techniques, practices, cropping, weather, markets etc
Strengthening of Agrinet project
Coverage Ministry of Agriculture
Departments of – Agriculture development, Agriculture marketing, Natural Resource, Disaster prevention, preparedness & food security (DPPA), Animal & Plant health, Plan & Program, Human resource dev., women affairs, Information & tec. Management, Procurement, finance & property admin and Public relations
Regional Agriculture Bureaus
Subordinate organizations including DPPA, EIARP (Ethiopian institute of Agr. Research), EGTE – Ethiopian Grain trading enterprise, NVI – Veterinary Institute and IBC – Biodiversity centre
List of major components to be addressed
Agriculture portal – with separate sections for each of the stakeholders (farmers, Government and support institutions) or separate portals and including services for all stakeholders
Agriculture information & management system
Services that will be delivered
Service Major component
Ca
teg
or
y
Se
rv
ice
Ty
pe
Ch
an
ne
ls
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 62 Confidential
Page 62
Initiative name e-Agriculture
Information services 1. Provision of data on the Agro-
processing Industry. 2. Crop Failure Reports 3. Provision of information on Enabling
Environment, Financing, and Infrastructure in the agro-processing industry.
4. Provision of Information on Market Fragmentation and Investment Potential.
5. Provision of Information on Quality Standard Implementation and Certification.
6. Provision of Information on Competition Indicators in the Agricultural sector.
7. Provision of Information on Investment Incentives in the Agro-processing Industry.
8. Information on prices of Fertilizers, Pesticides, Seeds, and Crops.
9. Technical services and support for farmers.
10. Irrigation Request by farmers. 11. Information on livestock disease
control & surveillance 12. Information on animal infrastructure
distribution & personnel 13. Information on quarantine inspection
and certification 14. Information on rural land admin.
Policies, procedure & guidelines 15. Information on natural resources
conservation
Portal, Agriculture Information & Management system
G2
C, G
2G
, G2
B
Info
rmatio
na
l
Na
tion
al W
eb p
orta
l, Min
istry p
orta
l, Mo
bile, IC
T C
enters
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 63 Confidential
Page 63
Initiative name e-Agriculture
Transactional services Agricultural Product Inspection and Certification Services:
For Investors or any Business man who is engaged in import and/or export of plant and animals products for commercial purpose Application for python sanitary inspection on export and import. Application for the import or export pesticide for commercial purpose Application for plant import permit, etc
Services relating to provision of Farm Land to Investors : Local or Foreign Investors who need Agricultural land for Investment, the following requirements and services are given by MoA.
Application form to obtain the land Provision of Information on the potential Agricultural land Technical and Administration support Continuous follow-up and support on the land use, Land management
Other transactional services Custom clearance certificate for agriculture imports Certificate of competence on agriculture Certificate of import & export of animal & crop products
Portal, Agriculture Information & Management system
G2
C, G
2B
Tra
nsa
ction
al
Na
tion
al W
eb p
orta
l, Min
istry p
orta
l, Mo
bile, IC
T C
enters
Implementation plan Yr. v/s
Project
Implementation Plan
Year 1 Year 2 Year 3 Year 4 Year 5
Sp
re
ad
of
su
b-
pr
oje
cts
Portal Development
AIMS Continuous improvement /updation of policy and regulatory framework ensuring the safety, authenticity, integrity and availability of the envisaged services across all the delivery channels & Expansion & Strengthening of Agrinet
Budget
33.86 Mil. Birr
Pre-Requisites The above mentioned initiative is a comprehensive project envisaging a complete end to end automation of some of the core functions of the ministry and agencies. For end to end automation of the service delivery, it will be important that core
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 64 Confidential
Page 64
Initiative name e-Agriculture
infrastructure projects run in parallel and are completed on time. Following core projects will have to be executed on time for successful implementation of the initiative
National Data Set (NDS) National Enterprise Service Bus (NESB) National Integrated Authentication Framework (NIAF) National Payment Gateway (NPG) Public key infrastructure (PKI) National Wide Area Network (WOREDANET) Implementation of the Network Master Plan
Apart from the key core projects to be undertaken for the successful implementation of the initiative the success of the health initiative will directly depend of the how successfully Ethiopia achieves high level of Internet and Mobile penetration and how successfully private hospitals are integrated into the system.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 65 Confidential
Page 65
VI. Benefits Management System Initiative name
Social Benefits Management System
Objective Provisioning of major informational and transactional services related to transport
ministry through electronic channels thereby improving the service delivery‘s
quality and efficiency.
Outcomes
expected Better awareness about benefit schemes due to single source of information
Higher satisfaction of beneficiaries with benefit schemes due to a single
interface to access these schemes and faster turnaround times
The service delivery can be monitored centrally for all benefit schemes
making it easy to access the impact and benefits of the various schemes
Better controls to check leakages in the system
Coverage Ministry of Labor and Social Affairs
Social Security Agency
Department of Postal services
Addis Ababa City Administration
List of major
components
to be
addressed
Benefit Schemes Portal (BSP)
Pension Management System (PMS)
e-Municipality
Services that
will be
delivered
Service Major component C
ate
go
ry
Se
rv
ice
Ty
pe
Channels
Web-based information
publishing
Benefit
Schemes
Portal (BSP)
G2
C
Info
rmatio
n
al National Web
portal, Ministry
portal, Mobile, ICT
Centers, call center
Benefits eligibility
calculator
Benefit
Schemes
Portal (BSP)
G2
C
Info
rmatio
na
l National Web
portal, Ministry
portal, ICT Centers,
call center
Applications for
availing benefits
Benefit
Schemes
Portal (BSP)
G2
C
Tra
nsa
ction
a
l National Web
portal, Ministry
portal, ICT Centers,
call center
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 66 Confidential
Page 66
Pension Services
(Pensioner registration,
and pension payment)
Pension
Management
System (PMS)
G2
C
Tra
nsa
ction
al
National Web
portal, Ministry
portal, Mobile, ICT
Centers
Support Letter (for
unemployment; free
health treatment,
scholarships) e-Municipality
G2
C
Tra
nsa
ction
al
National Web
portal, Mobile,
Ministry portal,
ICT Centers
Implementati
on plan
Yr. v/s Project
Implementation plan
Year 2 Year 3 Year 4
Sp
re
ad
of
su
b-p
ro
jec
ts PMS
SBP
Integration of various subprojects into a seamless and single Social Benefits Management System
Continuous improvement / updation of policy and regulatory framework to ensure that benefits reach the intended beneficiaries through all available service delivery channels.
Budget
33.63 Mil. Birr
Pre-
Requisites
This initiative is a comprehensive project that would integrate all the welfare
programs of the Government of Ethiopia. For end to end automation of the delivery
of the welfare programs, it will be important that core infrastructure projects run in
parallel and are completed on time. Following core projects will have to be executed
on time for successful implementation of the initiative
National Data Set (NDS)
National Enterprise Service Bus (NESB)
National Integrated Authentication Framework (NIAF)
Public key infrastructure (PKI)
National Wide Area Network (WOREDANET)
Implementation of the Network Master Plan
Apart from the key core projects to be undertaken for the successful
implementation of the initiative, the success of the project will also depend on the
success of marketing and awareness activities as the target group - underprivileged
section of the society, is the least aware about new schemes and policies.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 67 Confidential
Page 67
VII. Education Initiative name e-Education
Objective To provide information & services to all stakeholders in the Education sector (students, teachers, Government/regulatory agencies, and educational institutions) efficiently using ICT, and enable all stakeholders to contribute & participate in the development of the Education Sector.
Outcomes expected
Improvement in education services provided by Government
Provide access to education across the country
Improve teaching standards by providing on-line access to latest teaching aids, material, techniques
Improve Government administration and supervision of the education sector by using ICT
Improve overall quality of education in the country through distance learning, E-learning, computer based training (CBT)
Strengthening of Schoolnet project
Coverage Ministry
General Education, Higher Education & Technical & Vocational Education Training (TVET) departments
Regional Education Bureaus
List of major components to be addressed
Education portal – with separate sections for each of the 3 depts. (general, Higher and TVET) or three separate portals.
Student management system – including registration, admission and complete student records – for government schools & colleges
Examination management system
Education Institutes (schools, colleges, etc) administration system, including internal work-flow management system for the ministry, to provide services electronically
Providing, facilitating internet connectivity with adequate bandwidth to schools & other educational institutions
Services that will be delivered
Service Major component Ca
teg
or
y
Se
rv
ice
Ty
pe
Channels
National Exam results
Examination management system
G2
C
Info
rmatio
na
l
National Web portal, Ministry portal, Mobile, ICT Centers
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 68 Confidential
Page 68
Initiative name e-Education
Student placement results
G2
C
Info
rmatio
na
l
National Web portal, Ministry portal, Mobile, ICT Centers
Teacher placement results
G2
C
Info
rmatio
na
l National Web portal, Ministry portal, Mobile, ICT Centers
Student registration
Education administration system and Student management system
G2
C
Tra
nsa
ction
al
National Web portal, Ministry portal, Mobile, ICT Centers
Certificate for completion of high school (original & replacement)
G2
C
Tra
nsa
ction
al
National Web portal, Ministry portal, Mobile, ICT Centers
Certificate for completion of degree (original & replacement)
G2
C
Tra
nsa
ction
al National Web
portal, Ministry portal, Mobile, ICT Centers
Publish education statistics
G2
G &
G2
C
Info
rmatio
na
l National Web portal, Ministry portal, Mobile, ICT Centers
Report student performance results
G2
G &
G2
C
Info
rmatio
na
l
National Web portal, Ministry portal, Mobile, ICT Centers
National exam candidate registration
Examination Management system
G2
C
Tra
nsa
ction
al National Web
portal, Ministry portal, Mobile, ICT Centers
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 69 Confidential
Page 69
Initiative name e-Education
Teaching permit – for employment
Education Administration system
G2
C
Tra
nsa
ction
al
National Web portal, Ministry portal, Mobile, ICT Centers
Education certificate – to be sent abroad
Student management system and Education Administration System
G2
C
Tra
nsa
ction
al National Web
portal, Ministry portal, Mobile, ICT Centers
Scholarships Student management system and Education Administration System
G2
C
Tra
nsa
ction
al National Web
portal, Ministry portal, Mobile, ICT Centers
Implementation plan
Yr. v/s Project
Implementation Plan
Year 1 Year 2 Year 3 Year 4 Year 5
Sp
rea
d o
f su
b-p
roje
cts
Exam Management System
Student Management System
Education administration System
Integration of various core projects and various channels
Continuous improvement /updation of policy and regulatory framework ensuring the safety, authenticity, integrity and availability of the envisaged services across all the delivery channels & Schoolnet project
Budget
48.70 Mil. Birr
Pre-Requisites The above mentioned initiative is a comprehensive project envisaging a complete end to end automation of some of the core functions of the ministry and agencies. For end to end automation of the service delivery, it will be important that core infrastructure projects run in parallel and are completed on time. Following core projects will have to be executed on time for successful implementation of the initiative
National Data Set (NDS)
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 70 Confidential
Page 70
Initiative name e-Education
National Enterprise Service Bus (NESB) National Integrated Authentication Framework (NIAF) National Payment Gateway (NPG)
Public key infrastructure (PKI) National Wide Area Network (WOREDANET) Implementation of the Network Master Plan Expansion & Strengthening of Schoolnet project
Apart from the key core projects to be undertaken for the successful implementation of the initiative the success of the E-Education initiative will directly depend of the how successfully Ethiopia achieves high level of Internet and Mobile penetration and how successfully all education sector stakeholders are integrated into the system.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 71 Confidential
Page 71
VIII. E-Health Initiative name e-Health
Objective Provisioning of major informational and transactional services related to Health through electronic channels thereby improving the service delivery‘s quality and efficiency.
Outcomes expected
Convenience to the general public , healthcare institutions( hospitals and pharmacies) for informational and transactional services
Improvement in the service levels of health ministry‘s services leading to timely medical aid to the citizens thereby improving the overall health scenario in the country
Uniform and transparent licensing process leading to efficient health care service delivery
Convenient and accurate monitoring of certification and license status of health care institutions
Putting HSDP project on a fast track and aligning the e governance objectives with the 8 project components of HSDP project
Coverage Ministry
Government Hospital
Regional Health Bureaus
Woreda Health offices
Agencies
Pharmacies
Private Hospitals
List of major components to be addressed
Health Ministry Portal (HMP)
Hospital Information Management System (HMIS)
Drug Information Management System (DIMS)
Integration of hospitals(Public and Private), Pharmacies
National Payment gateway
Services that will be delivered
Service Major component Ca
teg
or
y
Info
/ T
ra
ns
ac
tion
al
Channels
Issuance of Drug Marketing license
DMIS
HMP
NPG
NIAF
G2
B
Tra
nsa
ction
al
National Web portal, Ministry portal, Mobile, ICT Centers
Issuance and renewal of Certificates of competence to drug establishments
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 72 Confidential
Page 72
Initiative name e-Health
Issuance, Renewal and cancellation of drug registration certificate
Issuance of certificate of competence to health professionals
HMIS
HMP
NIAF
NPG G
2B
Tra
nsa
ction
al
National Web portal, Ministry portal, Mobile, ICT Centers
Issuance of licenses to hospitals
Issuance, Renewal and cancellation of license to conduct clinical trials
Booking of Appointments
G2
C
Tra
nsa
ctio
na
l
National Web portal, Ministry portal, Mobile, ICT Centers
Notification of Test results
Hospital Information HMIS G2
C
Info
rmatio
na
l National Web portal, Ministry portal, Mobile, ICT Centers
Drug pricing information
DMIS G2
C
G2
B
Info
rmatio
na
l National Web portal, Ministry portal, Mobile, ICT Centers
Drug Availability Information
DMIS G2
C
G2
B
Info
rmatio
na
l National Web portal, Ministry portal, Mobile, ICT Centers
Doctors profile information
HMIS G2
C
G2
B
Info
rmatio
na
l National Web portal, Ministry portal, Mobile, ICT Centers
Implementation plan
Yr. v/s Project
Implementation Plan
Year 1 Year 2 Year 3 Year 4 Year 5
Sp
re
ad
of
su
b-
pr
oje
cts
HMP
HMIS
DMIS
Integration of various
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 73 Confidential
Page 73
Initiative name e-Health
core projects and various channels
Continuous improvement /updation of policy and regulatory framework ensuring the safety, authenticity, integrity and availability of the envisaged services across all the delivery channels.
Pre-Requisites The above mentioned initiative is a comprehensive project envisaging a complete end to end automation of some of the core functions of the ministry and agencies. For end to end automation of the service delivery, it will be important that core infrastructure projects run in parallel and are completed on time. Following core projects will have to be executed on time for successful implementation of the initiative
National Data Set (NDS) National Enterprise Service Bus (NESB) National Integrated Authentication Framework (NIAF) National Payment Gateway (NPG) Public key infrastructure (PKI)
National Wide Area Network (WOREDANET) Implementation of the Network Master Plan
Apart from the key core projects to be undertaken for the successful implementation of the initiative the success of the health initiative will directly depend of the how successfully Ethiopia achieves high level of Internet and Mobile penetration and how successfully private hospitals are integrated into the system.
Budget 46.87 Mil. Birr
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 74 Confidential
Page 74
IX. E-Trade
Initiative name e-Trade
Objective Provisioning of major informational and transactional services related to Trade
and Industry through electronic channels thereby improving the service delivery‘s
quality and efficiency.
Outcomes
expected Convenience to the Industries, Businesses ,Large, Medium, Small and
Micro Enterprises, Investors and the general public for informational and
transactional services
Improvement in the service levels of Trade and Industry ministry‘s
services leading to timely Business aid to the citizens thereby improving
the overall Economic scenario in the country
Uniform and transparent licensing process leading to efficient Trade and
Industrial service delivery
Convenient and accurate monitoring of certification and license status of
Business institutions
Putting SMME Development project on a fast track and aligning the e
governance objectives with the Agencies and Bureaus
Facilitating and developing the Import and Export Trade linkages
Coverage Ministry of Trade
Ministry of Works and Urban development
Public Sector Undertaking(PSU)
Regional Trade and Industry Bureaus
Woreda Trade and Industry offices
Agencies
Large Industries
Small Micro and Medium Enterprises (SMME)
Foreign and Domestic Investors
International Relations
Sectoral Growth
List of major
components to
be addressed
Trade and Industry Portal
Works & Urban Development Application (WUD)
Enterprise(SMME & Large Industries) Management System (EMS)
Trade (Import/Export) Management System (TMS)
Investors Management System(IMS)
Integration of Domestic(Public and Private) Enterprise Linkages
Sector and Business specific ICT Infrastructure and Applications Support
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 75 Confidential
Page 75
Initiative name e-Trade
Services that
will be
delivered
Service Major
component
Ca
teg
or
y
Info
/
Tr
an
sa
ctio
na
l
Channels
Provision of
Investor
Information
IMS
G2
B
Info
rmatio
na
l
National
Web portal,
Ministry
portal,
Mobile, ICT
Centers
Policies on
Business Loans
G2
B
Info
rmatio
na
l
National
Web portal,
Ministry
portal,
Mobile, ICT
Centers
Trade name and
trade mark
registration and
renewal
G2
B
Tra
nsa
ction
al
National
Web portal,
Ministry
portal,
Mobile, ICT
Centers
Collection of fines
if businesses
operate without
license or
outdated license
G2
B
Tra
nsa
ction
al
National
Web portal,
Ministry
portal,
Mobile, ICT
Centers
Requesting for
Business area
G2
B
Tra
nsa
ction
al
National
Web portal,
Ministry
portal,
Mobile, ICT
Centers
Provision of
Export/Import
Trade Information
to the business
community
TMS
G2
B
Info
rmatio
na
l
National
Web portal,
Ministry
portal,
Mobile, ICT
Centers
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 76 Confidential
Page 76
Initiative name e-Trade
Dissemination of
market research to
Exporters for
investing in
existing as well as
new markets
G2
B
Info
rmatio
na
l
National
Web portal,
Ministry
portal,
Mobile, ICT
Centers
Application for
Subsidies and
Duty relaxations
G2
B
Tra
nsa
ction
al
National
Web portal,
Ministry
portal,
Mobile, ICT
Centers
Provision of
Information on
SMMEs and Large
Industries
EMS
G2
C
Info
rmatio
na
l
National
Web portal,
Ministry
portal,
Mobile, ICT
Centers
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 77 Confidential
Page 77
Initiative name e-Trade
- Licensing and
Registration
services(Issuance,
Renewal and canc
ellation),
- Licensing of
Professional,
contractors
- Licensing of
construction
machines
Agency for Government Housing: -Request for
Rental Housing
Service include
Residential
Housing request
by customers
-Request for
renewal of
housing lease
contract by
tenants.
-Request for
maintenance
-Request for
transfer of right
-Various
notifications
WUD
G2
B
Tra
nsa
ction
al
National
Web portal,
Ministry
portal,
Mobile, ICT
Centers
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 78 Confidential
Page 78
Initiative name e-Trade
Implementation
plan
Yr
v/s
P
rojs
Implementation Plan
Year 2 Year 3 Year 4 year 5
Sp
re
ad
of
su
b-P
ro
jects
Ministry Portal
WUD, IMS
TMS
EMS
Industry Linkages
Hosting Business Specific Applications Core Infrastructure
EMS, TMS and IMS Management Systems shall be purely informational in
Year 1 with web interfaces. These systems shall be developed for specific
workflow applications in Year 2 and Year 3.
Industry Linkages are initiatives to explore and implement synergies between the sectors/Industries and also between SMME and Large industries
Customized Business specific ICT Applications and Infrastructure shall be developed and hosted for usage by the Local industries. These could be implemented in collaboration with the Private sector on appropriate PPP Models.
Budget – 9.83 Mil. Birr
Pre-Requisites The above mentioned initiative is a comprehensive project envisaging a complete
end to end automation of some of the core functions of the ministry and agencies.
For end to end automation of the service delivery, it will be important that core
infrastructure projects run in parallel and are completed on time. Following core
projects will have to be executed on time for successful implementation of the
initiative
National Data Set (NDS)
National Enterprise Service Bus (NESB)
National Integrated Authentication Framework (NIAF)
National Payment Gateway (NPG)
Public key infrastructure (PKI)
National Wide Area Network (WOREDANET)
Implementation of the Network Master Plan
Agrinet
Apart from the key core projects to be undertaken for the successful
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 79 Confidential
Page 79
Initiative name e-Trade
implementation of the initiative the success of the e-Trade initiative will directly
depend on how successfully Ethiopia achieves high level of Internet and Mobile
penetration and how successfully SMMEs are integrated into the system.
ICT Support to Domestic Industries:
ICT support in terms of Infrastructure, Information and Linkages through ICT shall be extended to the
local Industries and Small Micro and Medium Enterprises (SMMEs) in particular. Specific Software
solutions shall be built for the SMME sector in view of the Growth and Transformation Plan of Ethiopia as
follows.
Developing the micro and small-scale enterprises sector so that it contributes, to the development of
the industrial sector as a whole serve as the basis, and contributes to the development of the
agricultural sector and create employment opportunities.
Enabling all industries to utilize their full capacity in order to increase production and productivity.
o Enable the sector to develop strong linkage with the agricultural, medium and large scale
industrial sector.
o Improving SMES management skills in a coordinated and networked manner with the
existing extension systems.
o Working in collaboration with TVET and other appropriate institutions in expanding and
strengthening the urban industrial extension programs.
o Providing credit facilities and develop saving culture for MSEs.
X. Employment
Initiative name
Employment Management System
Objective Provisioning of major informational and transactional services related to Employment to the ministry of Labour through electronic channels thereby improving the service delivery‘s quality and efficiency.
Outcomes expected
Management of Unemployment in the country
Issuance and certification for unemployment
Integration and licensing of the Agencies
Issuance and renewal of work permit
Coverage Ministry of Labor and Social Affairs
Addis Ababa City Administration
List of major components to be addressed
Employment Information Portal
Employment Management System
Services that will be delivered
Service Major component
Ca
teg
or
y
Se
rv
ice
Ty
pe
Channels
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 80 Confidential
Page 80
Unemployment
Registration/
Unemployment
Certificate
Employment Information
Portal Employment Management
System
G2
C
Tra
nsa
ction
al
National Portal, Ministry of Labour Portal, ICT centers.
Overseas employment
registration for
Ethiopian Nationals
G2
C, G
2G
National Portal, Ministry of Labour Portal, ICT centers.
Employment Agency
License Renewal Employment Management
System
G2
B
Tra
nsa
ction
al
National Portal, Ministry of Labour Portal, ICT centers.
Employment Agency
Licensing (New)
Employment Management
System
G2
B
Tra
nsa
ction
al National Portal,
Ministry of Labour Portal, ICT centers.
Foreign Nationals work
permit Employment Management
System
G2
C, G
2G
Tra
nsa
ction
al
National Portal, Ministry of Labour Portal, ICT centers.
Job Matching, Labour
Market Information Employment Information
Portal
G2
C
Info
rmatio
n National Portal,
Ministry of Labour Portal, ICT centers.
Registration of –
Labour Unions
Employment Unions
Work Places
Collective Agents
Safety & Health
Committees
Work place accidents
Institution & Partner
Organisations
Employment Information
Portal Employment Management
System
G2
C, G
2B
Tra
nsa
ction
al
National Portal, Ministry of Labour Portal, ICT centers
Implementation plan
Yr. v/s Project
Implementation Plan
Year 2 Year 3 Year 4 Year 5
Sp
re
ad
of
su
b-
pr
oje
cts
Employment Portal
Employment Management System
Integration with other systems
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 81 Confidential
Page 81
Pre-Requisites
This initiative is a comprehensive project that would integrate all the programs of the Ministries , agencies involved. For end to end automation & delivery of the programs, it will be important that core infrastructure projects run in parallel and are completed on time. Following core projects will have to be executed on time for successful implementation of the initiative
National Data Set (NDS) National Enterprise Service Bus (NESB) National Integrated Authentication Framework (NIAF) Public key infrastructure (PKI) National Wide Area Network (WOREDANET) Implementation of the Network Master Plan
Apart from the key core projects to be undertaken for the successful implementation of the initiative, the success of the project will also depend on the success of marketing and awareness activities as the target group - underprivileged section of the society, is the least aware about new schemes and policies.
Budget 35.04 Mil. Birr
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 82 Confidential
Page 82
XI. Transport Initiative name e-Transport
Objective Provisioning of major informational and transactional services related to transport ministry through electronic channels thereby improving the service delivery‘s quality and efficiency.
Outcomes expected
Convenience to the general public, business community, other ministries for informational and transactional services
Improvement in the service levels of transport ministry‘s services leading to efficient delivery of licenses, information and other services
Uniform and transparent licensing process leading to efficient service delivery
Convenient and accurate monitoring of certification and licenses and other vehicle registration information
Coverage Ministry
Government transport agencies
Roads Authority
Embassies
Ministry of Foreign Affairs
Private Transport/ Travel agencies
Regional Transport Authorities
List of major components to be addressed
Transport Ministry Portal (TMP)
Vehicle Registration Information System (VRIS)
Online ticket booking System (TBS)
Government Vehicle Insurance Management System (IMS)
Integration of various ministries (Ministry of Transport, Ministry of Foreign Affairs, Insurance companies, Embassies, Roads Authority)
National Payment gateway
Services that will be delivered
Service Major component
Ca
teg
or
y
Info
/ T
ra
ns
ac
tion
al
Channels
Issuance/ Renewal of drivers license (National/ International)
TMP VRIS NPG
G2
C, G
2B
Tra
nsa
ction
al National Web
portal, Ministry portal, Mobile, ICT Centers
Application for change of ownership of vehicles
TMP VRIS NPG
G2
C
Tra
nsa
ction
al National Web
portal, Ministry portal, Mobile, ICT Centers
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 83 Confidential
Page 83
Initiative name e-Transport
Application and renewal of vehicle Insurance
TMP VRIS IMS
G2
C
Tra
nsa
ction
al
National Web portal, Ministry portal, Mobile, ICT Centers
Application for request of special numbers
TMP VRIS
G2
C
Tra
nsa
ction
al
National Web portal, Ministry portal, Mobile, ICT Centers
Online notification and collection of fines for traffic violation
VRIS NPG
G2
C
Tra
nsa
ction
al
National Web portal, Ministry portal, Mobile, ICT Centers
Online booking of tickets for inter state government transport
TMP NPG TBS
G2
C
Tra
nsa
ction
al
National Web portal, Ministry portal, Mobile, ICT Centers
Generic information on the application process, work flow, timelines, documents needed, ministry offices, work timings
TMP G2
C
Info
rmatio
na
l
National Web portal, Ministry portal, Mobile
Notification of expiry/ renewal of insurance, licenses
TMP VRIS
G2
C
Info
rmatio
na
l
National Web portal, Ministry portal, Mobile
Information on Public transport timings, tickets availability, routes, stops etc.
TMP TBS
G2
C
Info
rmatio
na
l
National Web portal, Ministry portal, Mobile
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 84 Confidential
Page 84
Initiative name e-Transport
Information on the traffic movement, special events, road works, Parking areas, detour information etc.
TMP G2
C
Info
rmatio
na
l
National Web portal, Ministry portal, Mobile
Notification of traffic violations and penalties
TMP VRIS
G2
C
Info
rmatio
na
l National Web portal, Ministry portal, Mobile
Information on regulation, policies, and import duty for vehicles
TMP G2
C
G2
B
Info
rmatio
na
l
National Web portal, Ministry portal, Mobile
Implementation plan
Yr. v/s Project
Implementation Plan Year 1 Year 2 Year 3 Year 4 Year 5
Sp
re
ad
of
su
b-p
ro
jec
ts
TMP
VRIS
TBS
IMS
Integration with Other Ministries
Integration of various core projects and various channels
Continuous improvement /updation of policy and regulatory framework ensuring the safety, authenticity, integrity and availability of the envisaged services across all the delivery channels.
Pre-Requisites The above mentioned initiative is a comprehensive project envisaging a complete end to end automation of some of the core functions of the ministry and agencies. For end to end automation of the service delivery, it will be important that core infrastructure projects run in parallel and are completed on time. Following core projects will have to be executed on time for successful implementation of the initiative
National Data Set (NDS) National Enterprise Service Bus (NESB)
National Integrated Authentication Framework (NIAF) National Payment Gateway (NPG) Public key infrastructure (PKI) National Wide Area Network (WOREDANET) Implementation of the Network Master Plan
Apart from the key core projects to be undertaken for the successful
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 85 Confidential
Page 85
Initiative name e-Transport
implementation of the initiative the success of the e transport initiative will directly depend of the how successfully Ethiopia achieves high level of Internet and Mobile penetration and how successfully other related government agencies and ministries are integrated into the system.
Budget 41.44 Mil. Birr
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 86 Confidential
Page 86
XII. Tourism Initiative name
e-Tourism
Objective Provisioning of major informational and transactional services related to Tourism through electronic channels thereby improving the service delivery‘s quality and efficiency. Ethiopia has great scenic beauty and tourist spots. The government is keen to leverage the same to enhance the contribution of the tourism sector in the national economy. This priority project is envisaged to be a facilitator towards this end. This project would be undertaken under the ownership of the Ministry of Culture and Tourism and participation of Ministry of Foreign Affairs. The long-term vision of the Government is to make Ethiopia one of the top ten tourist destinations in Africa by the year 2020, with an emphasis on maximizing the poverty-reducing impacts of tourism, and utilizing tourism to transform the image of the country .The number of tourists who visited the country in 2009 was 412,341, obtaining $211.5 million in revenue. Ethiopia has announced plans to attract around one million tourists. Ethiopia has unique sites to attract tourists and eight of its heritages are inscribed by UNESCO as world heritage sites. Various projects are currently being carried out to expand the tourism industry with $35 million loan obtained from the World Bank in 2009.
Outcomes expected
Convenience to the Tourists and the general public for informational and transactional services
Improvement in the service levels of Tourism ministry‘s services leading to timely aid to the citizens thereby improving the overall Culture and Tourism scenario in the country
Convenient and accurate monitoring of certification and license status of Businesses in the Tourism sector.
Putting Heritage Development project on a fast track and aligning the e governance objectives with the Agencies and Bureaus
To enhance the capacity of national authorities & local communities through the development of a comprehensive & centralized database of the cultural industries
Coverage Ministry
Heritage Sites
Artifacts
Hospitality Industry (Hotels, Resorts, Traditional Accommodations, Camping Sites, Hostels, Guest Houses)
Travel Agencies
Tour Operators
Tourism Information
Travel Visa
Disaster Alert
International Relations
Sector Growth
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 87 Confidential
Page 87
Initiative name
e-Tourism
List of major components to be addressed
Culture and Tourism Portal
Hospitality Management System(HMS)
Tour Management System (TMS)
Disaster Management System(DMS)
Travel Licenses Management System(TLMS)
Resource Management System(RMS) – (Natural and Cultural Resources, Heritage Sites, Artifacts)
Geographic Information System(GIS)
Services that will be delivered
Service Major compone
nt
Ca
teg
or
y
Se
rv
ice
Ty
pe
Channels
Registration of private tour operators
TMS
G2
B
Tra
nsa
ction
al National Web
portal, Ministry portal, Mobile, ICT Centers
Information on Tour Operators, Travel Packages, Itinerary, Fee
G2
C
Info
rmatio
na
l National Web portal, Ministry portal, Mobile, ICT Centers
Registering for a Tour G2
C
Tra
nsa
ction
al
National Web portal, Ministry portal, Mobile, ICT Centers
Registration of Hotels, Resorts, Guest Houses and Local Accommodations
HMS
G2
B
Tra
nsa
ction
al
National Web portal, Ministry portal, Mobile, ICT Centers
Information about the Accommodations
G2
C
Info
rmatio
na
l
National Web portal, Ministry portal, Mobile, ICT Centers
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 88 Confidential
Page 88
Initiative name
e-Tourism
Booking a Hotel, Resort etc
G2
C
Tra
nsa
ction
al National Web
portal, Ministry portal, Mobile, ICT Centers
Registering with the DMS for alerts
DMS G2
C
Tra
nsa
ction
al National Web
portal, Ministry portal, Mobile, ICT Centers
Supporting letter for film-makers ,Tourists to go abroad
TLMS G2
B,G
2C
Tra
nsa
ction
al
National Web portal, Ministry portal, Mobile, ICT Centers
Application for Tourist VISA on Arrival
G2
C
Tra
nsa
ction
al National Web
portal, Ministry portal, Mobile, ICT Centers
Driving license equivalence for foreign citizens
G2
C
Tra
nsa
ction
al National Web
portal, Ministry portal, Mobile, ICT Centers
ID card issuance for foreign nationals
G2
C
Tra
nsa
ction
al National Web
portal, Ministry portal, Mobile, ICT Centers
Issuing diplomatic and service visas
G2
C
Tra
nsa
ction
al
National Web portal, Ministry portal, Mobile, ICT Centers
Issuing Birth, Death and Marriage Certificates to foreign nationals
G2
C
Tra
nsa
ction
al
National Web portal, Ministry portal, Mobile, ICT Centers
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 89 Confidential
Page 89
Initiative name
e-Tourism
Information regarding various resources , Cultural and heritage centers
RMS G2
C,G
2B
Info
rmatio
na
l National Web portal, Ministry portal, Mobile, ICT Centers
Permission to visit Heritage sites
G2
C,G
2B
Tra
nsa
ction
al National Web
portal, Ministry portal, Mobile, ICT Centers
Information on Various GIS Mapping statistics
GIS G2
C,G
2B
Info
rmatio
na
l National Web portal, Ministry portal, Mobile, ICT Centers
Implementation plan
Year 2 Year 3 Year 4 Year 5
Ministry
Portal
Sp
read
of
su
b P
roje
cts
Yr
v/s
Pro
js Implementation Plan
DMS
Core Infrastructure
TMS
GIS
TLMS
HMS
Pre-Requisites The above mentioned initiative is a comprehensive project envisaging a complete
end to end automation of some of the core functions of the ministry and agencies. For end to end automation of the service delivery, it will be important that core infrastructure projects run in parallel and are completed on time. Following core projects will have to be executed on time for successful implementation of the initiative
National Data Set (NDS)
National Enterprise Service Bus (NESB) National Integrated Authentication Framework (NIAF) National Payment Gateway (NPG) Public key infrastructure (PKI) National Wide Area Network (WOREDANET)
Implementation of the Network Master Plan
Agrinet Apart from the key core projects to be undertaken for the successful implementation of the initiative the success of the e-Trade initiative will directly depend on how successfully Ethiopia achieves high level of Internet and Mobile penetration and how successfully SMMEs are integrated into the system.
Budget 36.34 Mil. Birr
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 90 Confidential
Page 90
Strategic Direction
The Priority projects are aligned with the cultural policy that targets to create a favorable condition to the
languages, cultural, historical and natural heritage, fine arts, handicrafts, oral literature, customs and
other cultural elements of the nations, nationalities and peoples of Ethiopia, receive equal recognition.
The Ethiopian Tourism policy focuses on identifying the country‘s historical, cultural, wildlife and natural
resources to develop responsible and sustainable tourism through the participation of the private sector,
local community. Moreover, the wildlife conservation policy is to create conducive environment whereby
the country‘s wildlife and their habitats are protected and developed in a sustainable manner.
Disaster Management System
Ethiopia‘s major cities like Addis Ababa, Nazret, Dire Dawa and Awassa are very near main fault lines
such as the Wonji fault, the Nazret fault, the Addis-Ambo-Ghedo fault, and the Fil Woha fault lines along
which numerous earthquakes of varying magnitude have occurred over the years. Other cities like Arba
Minch, Dessie, and Mekele are also located in some of the most seismically active areas in the country.
Hence the Government needs to constantly monitor and alert the citizens against Flood risk, Epidemic
risk, Earthquake Risk, Volcanic Activity Risk etc. The Disaster Management System serves as a Disaster
Alert and Coordination System provides near real-time alerts about natural disasters around the Country
and tools to facilitate response coordination. It shall also provide linkages for provision of stand-by
emergency centers and mobile sub-stations.
Geographic Information System (GIS)
Geographic information system (GIS) integrates hardware, software, and data for capturing, managing,
analyzing, and displaying all forms of geographically referenced information.GIS systems are used in
cartography, remote sensing, land surveying, Forest cover/ Population density mapping, hydrographs,
public utility management, natural resource management, precision agriculture, photogrammetric,
geography, urban planning, emergency arrangement, navigation, aerial video, and localized search
engines. It integrates stores, edits, analyzes, shares, and displays geographic information for informing
decision making. GIS applications are tools that allow users to create interactive queries (user-created
searches), analyze spatial information, edit data, maps, and present the results of all these operations.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 91 Confidential
Page 91
XIII. Tax
Initiative name Tax
Objective Provisioning of major informational and transactional services related to Tax through electronic channels thereby improving the service delivery‘s quality and efficiency.
Outcomes expected
Timely and effectively tax revenues generated efficient collections
Simplifying administration of tax and providing better control over compliance
Timely tracking of late-files and late-payers
Over all view of all taxpayer liabilities and payments
Ensure that tax payer data collected is valid and provides an easy-to use assessment calculation method
Improvement in customer satisfaction levels regarding tax related services.
Coverage Revenue and Custom Authority including the Business Processes and Directorates
Regional Branch Offices
Customs Authority Coordination offices
List of major components to be addressed
Upgradation of Standard Integrated Government Tax Administration System (SIGTAS) to Tax Management and Information System(TMIS)
National data set(NDS)
Custom and Revenue Authority Portal(Portal)
National Enterprise Service Bus (NESB)
National Payment gateway (NPG)
PKI Framework(PKI)
Services that will be delivered
Service Major component
Ca
teg
or
y
Se
rv
ice
Ty
pe
Channels
Online application of
Registration as a Taxpayer
Upgradation of
SIGTAS
TMIS
G2
C a
nd
G2
B
Tra
nsa
ction
al
National Web portal, Authority portal, ICT Centers
Online filling of Tax Return
(Land tax, Rental Housing
tax (paid by owner),
Turnover tax, TV tax, VAT,
and Excise tax)
G2
C a
nd
G2
B
Tra
nsa
ction
al
National Web portal, Ministry portal, ICT Centers
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 92 Confidential
Page 92
Initiative name Tax
File a declaration
G2
C a
nd
G2
B
Tra
nsa
ction
al
National Web portal, Ministry portal, ICT Centers
View Pending messages
G2
C a
nd
G2
B
Info
rmatio
na
l National Web portal, Ministry portal, Mobile, ICT Centers
View Registration Data
G2
C a
nd
G2
B
Info
rmatio
na
l National Web portal, Ministry portal, Mobile, ICT Centers
View Field assessments
G2
C a
nd
G2
B
Info
rmatio
na
l National Web portal, Ministry portal, Mobile, ICT Centers
View list of decelerations not
filed
G2
C a
nd
G2
B
Info
rmatio
na
l National Web portal, Ministry portal, Mobile, ICT Centers
List previous Tax returns
G2
C a
nd
G
2B
Info
rmatio
na
l National Web portal, Ministry portal, Mobile, ICT Centers
Show filed declaration
G2
C
G2
B
Info
rmatio
na
l National Web portal, Ministry portal, Mobile, ICT Centers
Tax clearance certificate
G2
C
G2
B
Tra
nsa
ction
al National Web
portal, Ministry portal, ICT Centers
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 93 Confidential
Page 93
Initiative name Tax
TIN Number Registration
G2
C
G2
B
Tra
nsa
ction
al
National Web portal, Ministry portal, ICT Centers
Implementation plan
Yr
v/s
P
rojs
Implementation Plan
Year 1 Year 2 Year 3 Year 4 year 5 S
pr
ea
d o
f S
ub
-P
ro
jec
ts Portal
TMIS
Integration of various Sub Projects and various channels
Continuous improvement /updation of policy and regulatory framework ensuring the safety, authenticity, integrity and availability of the envisaged Tax related services across all the delivery channels
Pre-Requisites The above mentioned initiative is a comprehensive project envisaging a complete end to end automation of some of the core functions of the Authority. For end to end automation of the service delivery, it will be important that core infrastructure projects run in parallel and are completed on time. Following core projects will have to be executed on time for successful implementation of the initiative
National Data Set (NDS) National Enterprise Service Bus (NESB)
National Payment Gateway (NPG)
Public key infrastructure (PKI) Up gradation of National Wide Area Network (WOREDANET)
Apart from the key core projects to be undertaken for the successful implementation of the initiative the success of the Tax initiative will directly depend of the how successfully Ethiopia achieves high level of Internet and Mobile penetration and how successfully all the Branch and coordination offices s are integrated into the system.
Budget 43.37 Mil. Birr
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 94 Confidential
Page 94
XIV. e-Court Initiative name e-Court Management System
Objective Provisioning of major informational and transactional services related to Court to Ministry of justice, Federal Supreme Courte and Regional Courts through electronic channels thereby improving the service delivery‘s quality, tracking and efficiency.
Outcomes expected
Better awareness about functioning and processes of the Ministry of Justice, Federal Supreme Court.
Digitized copy of the Law, Acts and case Documents.
Applications for the Case filling, Property Details etc.
Coverage Ministry of Justice
Federal Supreme Court
Regional Court
List of major components to be addressed
E-Court Portal
Property and Land management system
Case Management Application
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 95 Confidential
Page 95
Services that will be delivered
Service Major component Ca
teg
or
y
Se
rv
ice
typ
e
Channels
Buying & Selling
Property
Agreement e-Court Portal, Property and Land
Management System G
2C
,G2
B, G
2G
T
ran
sactio
na
l National Portal,
ICT Centers
Land Ownership
Land transfer
Property
Registration
Application for a
Pleading
e-Court portal, Case management Application
G2
C,G
2B
, G2
G
Tra
nsa
ction
al
National Portal, ICT Centers Document
Transfer
Case Filing
Adjourning Cases G2
C,G
2B
, G2
G
Tra
nsa
ction
al
National Portal, ICT Centers
Implementation plan
Yr. v/s Project
Implementation Plan
Year 2 Year 3 Year 4 Year 5
Sp
rea
d o
f su
b-p
roje
cts
e-Court informational Portal
Case Management System
Property and Land Management System
Integration with Regional Court and Property Systems
Pre-Requisites This initiative is a comprehensive project that would integrate all the programs of the Justice Ministry. For end to end automation of the delivery of the programs, it will be important that core infrastructure projects run in parallel and are completed on time. Following core projects will have to be executed on time for successful implementation of the initiative
National Data Set (NDS)
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 96 Confidential
Page 96
National Enterprise Service Bus (NESB) National Integrated Authentication Framework (NIAF) Public key infrastructure (PKI) National Wide Area Network (WOREDANET)
Implementation of the Network Master Plan Apart from the key core projects to be undertaken for the successful implementation of the initiative, the success of the project will also depend on the success of marketing and awareness activities as the target group - underprivileged section of the society, is the least aware about new schemes and policies.
Budget 31.80 Mil. Birr
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 97 Confidential
Page 97
XV. Municipalities Initiative
name
e-Municipality Management System
Objective Provisioning of the e-services to ensure a safe and clean environment for a healthy
and productive society with improved access to social services and physical
infrastructure.
Outcomes
expected Institute good governance with efficiency, transparency and accountability to
the residents.
Overall citizen satisfaction by providing convenience and improved service delivery.
Provide decision support system to the Addis Ababa city administration Cabinet, Bureaus, Authorities and Agencies for better planning, development and management.
Improve the quality of Citizen Service Delivery System and offer these services with optimal effectiveness and transparency.
Allow data sharing across different departments, thus bringing about the efficiency in administration functioning.
Help different departments to improve their revenue collection efficiency.
Harness the use of technology to create sense of achievement amongst employees and citizens.
Coverage All Urban Local bodies of federal and Regional
List of major
components
to be
addressed
Municipal Portal
Certificate generation module
Payment / Tax collection Module
Accounts Module
Licenses Module
Project Systems (for Water/Sewerage / Roads /Building etc.)
GIS Application
Grievance Information System
Human Resource Management System
Document & Workflow Management System
e-Procurement
Asset Management System
Material Management System
Fleet Management System
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 98 Confidential
Page 98
Implementati
on Plan
Agency Service Ma
jor
Co
mp
on
en
t
Ca
teg
or
y
Se
rv
ice
Ty
pe
Channels
A.A. City
Administra
tion
Communic
ation
Affairs
Bureau
Information
Provision
about A.A.
City
Administrat
ion
Ad
dis A
ba
ba
City
Info
rmatio
n
Po
rtal
All
Info
rmatio
na
l
Portal
A.A Mass
Media
Agency
Request for
Archives of
News,
Television
Programs,
Radio
Programs
Po
rtal, S
tora
ge S
erver, G
rieva
nces red
ressed sy
stem
G2
G
Tra
nsa
ction
al
Portal
Download
of Radio
Program
All
Info
rmatio
na
l Portal,
Mobile
Download
of News
All
Info
rmatio
na
l
Portal,
Mobile
Application
for
sponsorship
of News,
Communica
tions
G2
B
Tra
nsa
ction
al
Portal, ICT
centre
Request to
post News
G2
B
Tra
nsa
ction
al
Portal, ICT
centre
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 99 Confidential
Page 99
Request for
Advertising
different
bids and
names etc.
G2
B
Tra
nsa
ction
al
Portal, ICT
centre
Information
on
determinati
on of design
standards
and
preparation
of design for
construction
of roads
G2
B
Info
rmatio
na
l
Portal
Appeal to
damaged
roads
G2
C
Tra
nsa
ction
al
Portal, ICT
centre,
Mobile
Requests for
the
permission
of blocking
of the road
temporarily
G2
G,G
2C
Tra
nsa
ction
al
Portal, ICT
Centers
A.A. City
Courts
Application
for change
of name.
Complete
Backend
applicati
on in
synchron
ize with
front
end.
Digital
certificat
es
G2
C
Tra
nsa
ction
al
Portal, ICT
Centers
Application
for
declaration
of absence.
G2
C
Tra
nsa
ction
a
l Portal, ICT
Centers
Application
for
succession
Certificate.
G2
C
Tra
nsa
ction
a
l Portal, ICT
Centers
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 100 Confidential
Page 100
Application
for marriage
certificate.
G2
C
Tra
nsa
ction
a
l ICT Centre
Application
for
certificate of
guardianshi
p.
G2
C
Tra
nsa
ction
a
l Portal, ICT
Centre
Give
information
about court
case such as
adjournmen
t date.
G2
B, G
2C
Info
rmatio
na
l
Portal,
Mobile
A.A. acts
and Civil
Status
Documents
Registratio
n Office
Issuance of
Resident ID
Portal
with full
back end
applicati
on
processin
g and
Digital
Certificat
e
G2
C
Tra
nsa
ction
al
Portal, ICT
Centers
Issuance of
Marriage
Certificate
G2
C
Tra
nsa
ction
al
Portal, ICT
Centers
Issuance of
Divorce
Certificate
G2
C
Tra
nsa
ction
al
Portal, ICT
Centers
Issuance of
Birth
Certificate
G2
C
Tra
nsa
ction
al
Portal, ICT
Centers
Issuance of
Non-
Married
Certificate
G2
C
Tra
nsa
ction
al
Portal, ICT
Centers
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 101 Confidential
Page 101
Issuance of
Death
Certificate
G2
C
Tra
nsa
ction
al
Portal, ICT
Centers
A.A. City
Administra
tion
Environme
nt
Protection
Authority
Information
on creating
awareness
for
protecting
the city
from
different
pollution
and natural
resource
degradation
Portal,
Payment
Gateway,
Backend
Applicati
on
Integrati
on A
ll
Info
rmatio
na
l
Portal, ICT
Centers
Issuance of
license for
mining
G2
B
Tra
nsa
ction
al
Portal, ICT
Centers
Environmen
tal Impact
Assessment
Permit.
G2
B
Tra
nsa
ction
a
l Portal, ICT
Centers
Request for
environmen
tal Lab test
G2
B
Tra
nsa
ction
al
Portal, ICT
Centers
A.A City
Administra
tion
Cleansing
Manageme
nt Agency
Request for
disposal of
solid waste
Grievanc
es
Redresse
d system,
Call
Centers
G2
C
Tra
nsa
ction
al
Portal, Call
Centers, ICT
Centers
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 102 Confidential
Page 102
Addis
Ababa Civil
Service
Agency
Distributing
Organizatio
nal
Structure
for sub
cities and
center
Offices
Informati
onal
Portal,
HRMS,
Call
Centre
G2
G
Info
rmatio
na
l
Portal, Call
Centers
Distributing
directives,
guidance,
rules and
regulation
concerning
with
promotion,
allowance,
transfer,
requirement
of
employment
discipline.
G2
G
Info
rmatio
na
l
Portal, Call
Centers
Collect data
about
employees
profile form
all offices
G2
G
Info
rmatio
na
l
Portal, Call
Centers
Provision of
statistical
analysis
about
employees‘
profile.
G2
G
Info
rmatio
na
l
Portal, Call
Centers
Receiving
appeals
from
employees
(Administra
tive court)
G2
G
Tra
nsa
ction
al
Portal
Recruit new
employees
for all sub
cities and
center
offices
G2
G,G
2C
Tra
nsa
ction
al
Portal
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 103 Confidential
Page 103
Addis
Ababa City
Administra
tion justice
bureau
Distribution
of laws
Portal,
Call
Centers
All
Info
rmatio
na
l
Portal, Call
Centers
Registration
of
complaints
investigatio
n and
litigation
sub process
All
Tra
nsa
ction
al
Portal, Call
Centers
Registration
of Tax
appeal
G2
B
Tra
nsa
ction
al
Portal, Call
Centers, ICT
Centers
Addis
Ababa
Water and
sewerage
authority
Request for
new water
line
Internet
Portal
with
Backend
processin
g,
Payment
Gateway,
MIS
All
Tra
nsa
ction
al
Portal, Call
Centre, ICT
Centers
Request for
maintenanc
e of
Water/Sewe
rage lines
All
Tra
nsa
ction
al
Portal, Call
Centre, ICT
Centers
Request for
sewerage
service
All
Tra
nsa
ction
al
Portal, Call
Centre, ICT
Centers
Bill
collection
All
Tra
nsa
ction
al
Portal, Call
Centre, ICT
Centers
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 104 Confidential
Page 104
Addis
Ababa
Educationa
l Bureau
Educational
managemen
t
information
for
researchers
Portal,
Payment
Gateway,
Digital
Certificat
es
All
Info
rmatio
na
l
Portal
Information
on how to
get
examinee ID
All
Info
rmatio
na
l Portal, Call
Centers
Registration
of Private
ECLSE
examinees
G2
B
Tra
nsa
ction
al
Portal,
Payment
Gateway,
ICT Centers
Request for
summer
course
registration
G2
C
Tra
nsa
ction
al
Portal, ICT
Centers
Request for
grade 8
report card
when they
lost it
G2
C
Tra
nsa
ction
a
l Portal, ICT
Centers
City council
of Addis
Ababa
News
Release
Portal,
Grievanc
es
redressed
system,
Digital
certificati
on
All
Info
rmatio
na
l Portal, ICT
Centers
Press
Release
All
Info
rmatio
na
l Portal, ICT
Centers
Documentat
ion and
disseminati
on of
information
All
Info
rmatio
na
l Portal, ICT
Centers
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 105 Confidential
Page 105
Disseminati
on of
declaration
ratified by
the council
All
Info
rmatio
na
l Portal, ICT
Centers
Request for
buying laws
G2
B, G
2C
Tra
nsa
ction
a
l Portal, ICT
Centers
Receiving
appeal
G2
B, G
2C
Tra
nsa
ction
a
l Portal, ICT
Centers
A.A Urban
Plan and
Informatio
n Institute.
Preparing
Structural
Plan
Portal,
Backend
applicati
on, GIS,
Payment
Gateway,
ICT
Centers
G2
G
Tra
nsa
ction
al
Application
Preparing
Local
developmen
t Plan
G2
G
Tra
nsa
ction
al
Application
Collecting
land and
land related
data
G2
G
Tra
nsa
ction
a
l Application
Request for
land and
land related
data (has
transaction
fee)
G2
B, G
2C
Tra
nsa
ction
al
Portal, ICT
centers
A.A Fire
and
emergency
service
Information
on safety
inspection
and
certification
Portal,
Call
Centers
All
Info
rmatio
na
l Portal,
Mobile
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 106 Confidential
Page 106
Information
on safety
consultancy
All
Info
rmatio
na
l Portal,
Mobile
Information
on training
and
awareness
All
Info
rmatio
na
l Portal,
Mobile
A.A
beautificati
on park
and
symmetry
Request for
park and
recreation
center/hall
Portal,
Payment
Gateway,
Call
Centers
G2
B, G
2C
Tra
nsa
ction
al
Portal, ICT
Centre,
Payment
Gateway
Information
on how to
get funeral
service
All
Info
rmatio
na
l Portal,
Mobile
Information
on the
provision of
ornamental
seedlings
All
Info
rmatio
na
l
Portal,
Mobile
Information
on green
area
adoption
and
outsource
service
All
Info
rmatio
na
l
Portal,
Mobile
Information
on public
relation
mobilization
and
awareness
All
Info
rmatio
na
l
Portal,
Mobile
Implementati
on Plan Yr. v/s
Project
Implementation Plan
Modules
Yea
r 2
Yea
r 3
Yea
r 4
Year 5
Sp
rea
d o
f
core
an
d
sub
-
pro
ject
s
Municipal Portal
Certificate generation module
Payment / Tax collection
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 107 Confidential
Page 107
Module
Accounts Module
Licenses Module
Project Systems (for
Water/Sewerage / Roads
/Building etc.)
GIS Application
Grievance Information System
Human Resource Management
System
Document & Workflow
Management System
e-Procurement
Asset Management System
Material Management System
Fleet Management System
Pre-
Requisites
This initiative is a comprehensive project that would integrate all the programs of
the City Administration of Addis. For end to end automation of the delivery of the
programs, it will be important that core infrastructure projects run in parallel and
are completed on time. Following core projects will have to be executed on time for
successful implementation of the initiative
National Data Set (NDS)
National Enterprise Service Bus (NESB) National Integrated Authentication Framework (NIAF) Public key infrastructure (PKI) National Wide Area Network (WOREDANET) Implementation of the Network Master Plan
Apart from the key core projects to be undertaken for the successful
implementation of the initiative, the success of the project will also depend on the
success of marketing and awareness activities as the target group - underprivileged
section of the society, is the least aware about new schemes and policies.
Budget 37.97 Mil. Birr
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 108 Confidential
Page 108
XVI. Passport & Visa
Initiative name Passport & Visa Management System
Objective Automation of services provided with respect to issue, renewal of passports and visa services of Ministry of Foreign Affairs
Outcomes expected
Better functioning and processes of the Ministry of Foreign Affairs
Faster & more efficient issue and management of applications and documents
Reduction in opportunities for fraudulent applications
Coverage Ministry of Foreign Affairs
Immigration Offices
International Airport
List of major components to be addressed
Passport & Visa Management Application
Status check facility on channels (Portal, call centre, etc)
Services that will be delivered
Service Major component Ca
teg
or
y
Se
rv
ice
typ
e
Channels
Application
Passport & Visa Management system
G2
C,G
2B
, G2
G
Tra
nsa
ction
al
National Portal, ICT Centers
Renewal
Replacement
Visa Application,
Processing & Issue
ID Card issue to
Foreign Nationals
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 109 Confidential
Page 109
Implementation plan
Yr. v/s Project
Implementation Plan
Year 1 Year 2 Year 3 Year 4
Sp
rea
d o
f su
b-
pro
ject
s
Passport & Visa Management System
Pre-Requisites This initiative is a comprehensive project that would integrate the programs of the Foreign Affairs Ministry in passport and visa areas. For end to end automation & delivery of the program, it will be important that core infrastructure projects run in parallel and are completed on time. Following core projects will have to be executed on time for successful implementation of the initiative
National Data Set (NDS) National Enterprise Service Bus (NESB) National Integrated Authentication Framework (NIAF) Public key infrastructure (PKI) National Wide Area Network (WOREDANET) Implementation of the Network Master Plan
Apart from the key core projects to be undertaken for the successful implementation of the initiative, the success of the project will also depend on the success of marketing and awareness activities as the target group - underprivileged section of the society, is the least aware about new schemes and policies.
Budget 31.80 Mil. Birr
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 110 Confidential
Page 110
Core Projects Introduction:
The e-Government strategy for Ethiopia has identified several strategic priority projects. These projects
when implemented would deliver electronic services. As these projects cut across ministries and also if
these projects are to deliver fully transactional services over the various electronic channels, it is
absolutely essential to develop a robust infrastructure on which these projects should be hosted. This
infrastructure would include the following to be implemented during the first 3 years of the strategy
implementation.
Table 16: Core Projects
S.No. Core Projects Strategy Alignment Current
Status
Owner
Ministry
Estimated
Cost
1 National Data
Set (NDS)
This infrastructure is required
at a National Level to provide
a commonly used master
database which can be shared
across ministries
Need to set up MoCIT 367 Mil.
Birr
2 National
Enterprise
Service Bus
(NESB)
This infrastructure is required
at the National Level to act a
platform for exchanging data
between ministries on a
common platform
Need to set up MoCIT 20.60 Mil.
Birr
3 National
Integrated
Authentication
Framework
(NIAF)
This infrastructure is required
at the National Level to
authenticate users on the
various electronic channels.
This facility will provide
secure user login based on
certain credentials
Need to set up MoCIT 36 Mil. Birr
4 National
Payment
Gateway (NPG)
This infrastructure is required
for providing a unified
payment system for all
ministries / agencies to
deliver payment related
eServices through the
identified channels
Need to set up MoCIT 28.08 Mil.
Birr
5 Public Key
Infrastructure
(PKI)
This infrastructure is required
both to facilitate electronic
transactions and provide
required security for the
same.
Project in
progress,
alignment
required as
per the
strategy
MoCIT 124.75 Mil.
Birr
6 Enterprise
Architecture
(EA)
Development of EA for all
Ministries in line with the
National framework
Needs to be
done
MoCIT 6.30 Mil.
Birr
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 111 Confidential
Page 111
7 National Data
Centre (NDC)
This infrastructure provides
the common hosting facility
for all government
applications, core projects etc.
Project in
progress,
alignment
required as
per the
strategy
MoCIT
8 National Wide
Area Network
(WOREDANET)
This infrastructure is required
to provide the back bone
connectivity for all ministries
and agencies to be in a
common wide area network
Project in
progress,
alignment
required as
per the
strategy
MoCIT
Implementation Plan for the Core Projects – The core projects, as mentioned are proposed to be implemented in the 1st three years of implementation
of the strategy implementation, considering the fact that they would be building blocks/ or the facilitators
for the priority project implementation. Broad level implementation plan of the core projects is as below –
Table 17: Core Projects- Implementation Plan
Yr. v/s Project
Implementation plan
Year 1 Year 2 Year 3 Year 4 Year 5
National Data Set
National Enterprise Service Bus
National Integrated Authentication Framework
National Payment Gateway
Public Key Infrastructure
Enterprise Architecture
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 112 Confidential
Page 112
BusinessEmployee
CitizenCu
sto
me
rs
Private Agencies
Mobile kioskServ
ice
De
live
ry
Ch
ann
els
Ministry Portal
National Enterprise Service Bus(Integration Layer)
Application
Database
Ministry 2
Application
Database
NIAF
Application
Database
Ministry 1
Application
Database
National
Payment Gateway
Operational Applications / Databases @ Ministries
NCC National Portal
Application
Database
NDS
Application
Database
Public Key
Infrastructure
WOREDANET
NDC
The details of these initiatives are provided in the coming sections. A logical diagram of these
infrastructures is provided below for reference:
Figure 10: Core Projects
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 113 Confidential
Page 113
XVII. National Data Set:
Initiative name National Data Set
Objective Provisioning a national level data set of commonly used data elements across ministries, that can be used by all inter-ministerial applications as well as channels of delivery (national portal, mobile portal, CSC, NCC etc.) for delivering eServices
Outcomes expected A database system to support all business requirements of the government
A nation-wide metadata standard for creating and maintaining data repositories for any kind of information in government
A common database for data sharing, data integrity, data redundancy, database security between ministries
Support standardized nomenclature and value for common data across ministries
Assist in better integration of services and applications across ministries
Drive the National Meta Data standards
Reduce the dependency of applications, channels, interacting with multiple master data bases
Coverage The coverage of NDS would be the following: All ministries and agencies of Ethiopia
List of major components to be addressed
Build a central read-only repository of most commonly required master data that can be shared to all the data consumers (government ministries as well as private) as a single source of truth
Develop and Maintain Metadata Standards (data owner, data source system, data type, data width, standard values, etc.) for uniform understanding of the data among the data providers and data consumers
Services that will be delivered
Data sharing and validation by the respective entities
Project duration The expected project duration is 1.5 to 2 years. The project may be initiated within 6 months of the start of the eGovernment strategy implementation
Critical Success Factors
Clearly articulated Data ownership responsibility
Data sharing policy and guidelines
Communication infrastructure for data sharing (ESB)
Development of data architecture
Dedicated project teams during implementation
Dedicated team for operations and maintenance
Implementation options
As these projects involve specialized software and hardware, this should be implemented as a turnkey solution.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 114 Confidential
Page 114
XVIII. National Enterprise Service Bus: Initiative name National Enterprise Service Bus (NESB)
Objective Provisioning a platform for seamless integration of ministry / agency applications and database at the back end; integrating all front end channels to deliver eServices
Outcomes expected Increasing business agility: NESB enables enterprise to respond quickly to new business changes, develop distinctive new capabilities and leverage existing services for true responsiveness.
Simpler systems: NESB are based on industry standards and loosely coupled integration will reduce complexity when compared with integrating systems on a solution-by-solution API-based integration basis.
Standards: Service-oriented architectures make it possible for organizations to develop, implement and reuse processes that are technically enabled and integrated through the use of web services standards such as XML, SOAP and WSDL
Process/Data High Availability: NESB would provide high availability for business process runtime and process data, without any complex hardware and configuration.
Ensure better scalability, reducing integration expense, and lowering maintenance costs.
Coverage All ministry and agency applications identified in the eGovernment strategy
List of major components to be addressed
Develop a nation-wide SOA and governance model for service delivery Set up of hardware and software for NESB
Services that will be delivered
The NESB will act as an interconnection to bridge various component services provided by ministries for exchange of information. This would include the following:
Seamless integration of applications and databases of ministries / agencies to deliver eServices
Create SOA based service architecture
Act as a framework for routing or mediating the information that flows between ministries, transforming the messages between requestors and providers
Project duration The expected project duration is 1.5 to 2 years. The project may be initiated within 6 months of the start of the eGovernment strategy implementation
Critical Success Factors
Identify the list of all business services for integration
Alignment of SOA for developing services
Existence of Data sharing policy and guidelines
Dedicated project teams during implementation
Dedicated team for operations and maintenance
Implementation options
As these projects involve specialized software and hardware, this should be implemented as a turnkey solution.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 115 Confidential
Page 115
NIAF
NSEB
A logical diagram of the NESB describing the various components and interaction is provided below:
Figure 11: National Enterprise Service Bus
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 116 Confidential
Page 116
XIX. National Integrated Authentication Framework: Initiative name National Integrated Authentication Framework - NIAF
Objective Provisioning of a unique identity based login to individuals for accessing the various electronic channels of government (National Portal, Mobile Portal, Common Service Centre (CSC) and National Contact Centre (NCC) & other ministry applications.
Outcomes expected Single authentication facility for individuals, business and government to be used across all ministries and agencies
Assist in building other capabilities on the electronic channels like personalization
Can be offered as an authentication management solution for private sector like banks, business offices etc.
Coverage The IAF is envisaged to be utilized by the following: Applications: All government electronic Channels- National portal,
Ministry websites (Intranet and internet), Mobile, CSC, NCC, all ministry back end applications
Usage: To be provided to all citizens and legal residents of Ethiopia List of major components to be addressed
Set up the NIAF infrastructure Provisioning of all levels of authentication Integration with channels and eServices
Services that will be delivered
A national authentication framework – IAF to have the following levels of authentication Level 1: Username & password Level 2: Username & password + Biometric Level 3: Username & password + Biometric +Token (RSA, PKI)
Project duration The expected project duration is 1.5 to 2 years. The project may be initiated within 6 months of the start of the eGovernment strategy implementation
Critical Success Factors
The above mentioned initiative is a comprehensive project envisaging the complete end to end automation of authenticating all individuals of Ethiopia to use the various electronic services provisioned on electronic channels. The pre-requisites are:
A nation-wide unique identity number (UIN) for all citizens and residents of Ethiopia
Data base of the Unique id Infrastructure for high end authentication – chip based (smart card)
for all (UIN), PKI certificates
Availability of an Nation-wide enterprise service bus to integrate the NAG services to all requestors
Dedicated project teams during implementation
Dedicated team for operations and maintenance
Implementation options
As these projects involve specialized software and hardware, this should be implemented as a turnkey solution.
A logical diagram of the National Integrated Authentication Framework describing the various
components and interaction is provided below:
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 117 Confidential
Page 117
Figure 12: National Integrated Authentication Framework
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 118 Confidential
Page 118
XX. National Payment Gateway: Initiative name National Payment Gateway
Objective Provisioning of a national payment gateway for Ethiopia to enable all modes of electronic payments to be transacted through all the electronic channels of delivery
Outcomes expected Single, unified electronic payment solution across all government entities.
Enable all government payment services under one umbrella; making it easy, convenient and secure payment process for all its citizens, businesses and the government.
Provide for greater payment flexibility, features & methods Enables all modes of payment -Card based payments, Direct Debit &
eBanking, eWallet
Coverage All transactional payment eServices All electronic channels that accept electronic payments
List of major components to be addressed
Set up the National Payment Gateway infrastructure Provisioning of all payment types
Integration with channels and eServices
Services that will be delivered
Set up the payment gateway infrastructure with payment mechanisms such as - Credit cards, Direct Debits, Net Banking, ePurse, eWallet, eVouchers and/or, Any other payments that is currently available in the proposed product by the respondent need to be included in the solution
Project duration The expected project duration is 1.5 to 2 years. The project may be initiated within 6 months of the start of the eGovernment strategy implementation
Critical Success Factors
Availability of eTransaction laws to support electronic payment Availability of infrastructure at the financial institution levels e.g. Banks
to become Payment Service Providers (Card acquires, card issuers, merchant banks etc.)
Compliance with international laws and practices for enabling electronic payments like PCIDSS
Dedicated project teams during implementation Dedicated team for operations and maintenance
Implementation options
As these projects involve specialized software and hardware, this should be implemented as a turnkey solution.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 119 Confidential
Page 119
A logical diagram of the National Payment Gateway describing the various components and interaction is
provided below:
Figure 13: National Payment Gateway
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 120 Confidential
Page 120
XXI. Public Key Infrastructure
Initiative name Public Key Infrastructure (PKI)
Objective Provisioning of PKI based identification, integrity and non-repudiation for online transactions related to the eGovernment projects in Ethiopia
Outcomes expected Ensuring safe and reliable online transactions for government, public and private
Support the use of other online systems line Payment Gateway, Authentication Framework, eServices, document signing etc.
Coverage Nationwide initiative for issuance and use of PKI for all electronic transactions for government and private
List of major components to be addressed
Set up of the PKI environment Provisioning the PKI services Create suitable laws for support and use of PKI in online transactions
Services that will be delivered
Data encryption services for government and private
Identity verification using digital keys
Provide end users with eSignature, time stamping, etc.
Integration with eServices and applications for use
Project duration The expected project duration is 1 to 1.5 years. The project may be initiated within 6 months of the start of the eGovernment strategy implementation
Critical Success Factors
Availability of electronic signature act, decree or ordinance Availability of eTransaction laws to support electronic payment Availability of infrastructure at the institution levels for using the PKI
Readiness of applications and systems to use PKI based authentication Compliance with international laws and practices for enabling electronic
payments like PCIDSS
High skilled man power in the PKI area
Increased PKI awareness level in ministries/agencies
Create high bandwidth and ICT penetration
Good telecommunications infrastructure
Dedicated project teams during implementation
Dedicated team for operations and maintenance
Implementation options
As these projects involve specialized software and hardware, this should be implemented as a turnkey solution.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 121 Confidential
Page 121
Figure 14: Public Key Infrastructure (PKI)
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 122 Confidential
Page 122
XXII. Woreda Net
Initiative name Woreda-net
Objective Provisioning of high bandwidth connectivity between ministries and agencies for sharing data, voice and video communication throughout the country
Outcomes expected Create / establish a government wide area network
Create single unified, reliable, robust and secure Intranet for the
Government thereby facilitating effective communication and creating
less paper environment.
Provide connectivity to all the e-Government applications.
Coverage All the participating ministries, agencies, regional and local government offices to be covered in the Woreda-net
Services that will be delivered
216 services would be delivered
Project duration Phase I: Ethiopia has already covered 13 ministries with fiber optic connectivity and 700 Woredas with terrestrial and VSAT connectivity. Phase II: This phase would cover additional 10 Ministries and 175 woredas in the next 1 Year. Over a period of 5 years all the participating ministries, agencies, regional and local government offices to be covered in the Woreda-net
Critical Success Factors
Availability of telecom provider to enable high bandwidth Availability of infrastructure at the institution levels High skilled man power for maintenance of the WAN Good telecommunications infrastructure
Availability of High security infrastructure Dedicated project teams during implementation Dedicated team for operations and maintenance
Implementation options
As these projects involve specialized software and hardware, this should be implemented as a turnkey solution.
The current status of the existing WOREDA Net is provided below: (WOREDA is the administrative
equivalent of a District)
Table 18: Existing WOREDA Net
S. No. Region/Site Name Total no of site
(connectivity)
Connectivity
VPN VSAT
1 Federal Office 3 3 -
2 Addis Ababa Region 11 11 -
3 Tigray Region 39 5 34
4 Amhara Region 116 7 110
5 Oromia Region 199 3 195
6 Somalia Region 46 1 45
7 Beneshangul Gumuz Region 21 21 21
8 SNNP Region 106 3 103
9 Afar Region 37 37 37
10 Gambella Region 10 10 10
11 Harari Region 1 1 -
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 123 Confidential
Page 123
S. No. Region/Site Name Total no of site
(connectivity)
Connectivity
VPN VSAT
12 Dir Dawa Region 1 1 -
Total 590 36 554
XXIII. Data Center
The Ethiopian National Data Centre (ENDC), under the management of MOCIT, aims to provide reliable
ICT Infrastructure and storage facilities to all Government ministries and departments by hosting
required hardware, software and applications in a centralized, secure environment, connecting National
Data Center and Regional Data Centers (RDC) through fiber optics. 260 terra bytes (TB) and 60 TB of
storage capacity is available at ENDC and RDC respectively.
Ethiopian National Data
Centre
Regional Data
Centre
National Disaster
Recovery Centre
Regional Data
Centre
Regional Data
Centre
Regional Data
Centre
Regional Data
Centre
Regional Data
Centre
ETC
Regional DR site
Regional DR site
Regional DR site
Regional DR site
Regional DR site
Regional DR site
Figure 15: Proposed Nationwide Data center Layout
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 124 Confidential
Page 124
It is proposed that the Ethiopian National Data Centre (ENDC) would consolidate services, applications
and infrastructure to provide efficient electronic delivery of G2G, G2C and G2B services. ENDC
infrastructure shall provide adequate space to house ICT assets of various departments and Government
agencies within the country in an environment that meets the need for reliability, availability, scalability,
security and serviceability. Various applications and some of the functionalities envisaged at the ENDC
include Secure Central Data Repository of Ethiopian e-government, Core Application Servers, Service
Delivery Gateway, Citizen Information/Services Portal, Government Intranet Portal, Remote
Management and Service Integration facility.
Ethiopian National Data Centre will act as a mediator and convergence point between open unsecured
public domain and sensitive government environment. The ENDC is equipped to host / co-locate systems
such as Web Servers, Application Servers, Database Servers, SAN, and NAS etc.
Recommendations:
1) Presently the data centre is not available on 24/7/365 basis – though the infrastructure and facilities
to provide on 24/7 basis have been created. The NDC is now operating on a single 8 hour shift. Hence
there is a need to have 24x7 Team of trained resources at the Data Centres with well defined roles and
responsibilities for each team member.
2) Reporting structure of the Data Centre Resouces should be published and shared with the respective
Ministires and other government Agencies.
3) Complete Catalog of the inventory (Hardware/ Software) needs to be maintianed and updated
regularly along with the vendor details.
4) A detailed Service catalog has to be maintained for each of the service that are being delivered
through the Data Centres e.g: IP phone, V-Con, Web, Portal / Application hosting, e-Mail Etc..
5) Currently services being provided by NDC need to be fully used by the various ministries, agencies –
e.g Though e-mail server and DNS are available and official mail ids can be used by all government
personnel, this is not happening due to lack of a directive from the government making it mandatory
for all govt. bodies to use official e-mail/domain. And most of govt. currently uses personal mail ids
for govt. correspondence.
6) Domain(.gov..et) has to be created for all Ministries, Agencies and Federal Government to bring them
all under that domain umbrella.
7) The infrastructure (Storage, IP Addresses and Connectivity etc.) for each of the Ministries, Agency at
the National and Regional Data Centres should be planned, allocated and made available.
Presently NDC does have block of IP addresses and also provides facilities for server co-location,
provision of dedicated or shared servers for the various ministries. However these facilities should be
provided in a planned and organised manner, as per the Governments‘ own ICT implementation
plans as well as per the plans of the individual ministries and agencies.
8) The Network capacity of the National Portal needs to be upgraded, considering that E-services will be
implemented fully within couple of years. Further, the govt. also plans to migrate the portal to an
open source platform.
9) Presently the connectivity between NDC and RDCs is through fibre links. There is a need to build in
redundancy and provide back-up connectivity through other media like VSAT, RF etc..
10) DR sites (13 in number) are in process of being implemented. Good practices for establishment of
Disaster Recovery Centres such as building the DRC in a seismic zone different from where the Data
Centre is hosted should be adhered to.
11) Capacity utilisation of NDC should be improved. E.g Though NDC is in a position to provide around
100 servers for the various ministries, agencies, only around 30 servers are being used.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 125 Confidential
Page 125
XXIV. National Enterprise Architecture Framework Initiative name National Enterprise Architecture Framework (NEAF)
Objective Developing enterprise architectures for all Ministries in alignment with the NEAF
Outcomes expected Unified architecture adoption across ministries enabling better integration of ministry applications
Identification and implementation of proper governance mechanism for IT implementation across the country
Unified standards, guidelines, taxonomies and processes for IT implementation (including software, hardware, interoperability standards)
Identification of core and common projects which will act as an enabler for eGovernment implementation
Reducing the cost of IT implementation by minimizing the duplicity, increasing re-usability, thereby providing better RoI.
Coverage Nationwide initiative for all ministries and agencies
List of major components to be addressed
Develop an EA for each ministry in line with the NEAF and eGovernment Strategy
Identification of core and common projects to be implemented across the country
Set up of the EA governance framework for continuous monitoring and adoption
Services that will be delivered
NEAF is a framework to be used by all ministries to develop the various architectures proposed. This architecture would form the base for eGovernment strategy implementation i.e. the services and strategic priority initiatives proposed.
Identification of ministry specific, core and common projects to be implemented
Defining the roles and responsibilities for implementation
Project duration Since EA is a pre-requisite for any Business-IT implementation alignment, it would be appropriate to develop the EA for all ministries during the initial phase of eGovernment strategy implementation i.e. in the first year of strategy implementation. The ministry wise EA would be considered as the strategy implementation blueprint.
Critical Success Factors
Buy-in from High level (ministers of all ministries) for EA adoption
Availability of required trained man power in each ministry on NEAF
Set up of EA governance body
Provision of suitable technical bodies at a national level to guide EA development, consolidation of EA of all ministries and also manage the EA implementation.
Provisioning a good EA tool for knowledge management
Continuous training for the ministerial staff on EA adoption
Dedicated project teams during implementation Implementation options
There are two options for EA implementation: 1. In-house development: EA development is a continuous activity and
therefore, training the internal teams in ministries and agencies to develop their own EA would be the most sustainable model for
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 126 Confidential
Page 126
Initiative name National Enterprise Architecture Framework (NEAF)
Ethiopia. However, this option would be time consuming, as providing training to all the key employees and then developing EA would take considerable time thereby delaying the eGovernment strategy implementation.
2. Consultant supported: In this model, an EA consultant may support the ministries to develop the first version of EA. The ministries and agencies should dedicate a core team to work with the consultants during the EA development. This would ensure that the ministry team acquires the ability to develop EA as an on-the-job training. This option would consume less time for completion.
As a part of the strategy recommendation, we suggest option 2 as the involved in this case would be less and also provide on-the-job training.
Alignment of EA and eGovernment strategy
Ethiopia has already developed an EA framework for the country. This framework is all encompassing and has considered the various elements of the Ethiopia IT initiatives. The alignment of the EA with the eGovernment strategy is provided below depicting the major components:
NEAF Reference Components
eGovernment Strategy Alignment
Government Services Architecture
Strategy has identified the various business services that have to be delivered to the customers and also the channels of delivery. However, the EA framework need to be used to develop the processes, KPIs, etc to develop the business life cycle processes of each of these ministry / agency services
Application Architecture
The eGovernment strategy has identified most of the core, common and ministry specific applications required for supporting the eGovernment strategy. However, EA may re-validate the same during the EA development. Each ministry will identify the list of applications required to support the government service delivery. This will consolidated at the national level and then the core, common and ministry specific applications will be duly allocated with roles and responsibilities for implementation.
Data Architecture The strategy has identified National Data Set as a core project. During the EA implementation, the NDS has to be further elaborated technically to include the data elements, data structure, metadata etc.
Technology architecture
The components related to technology – hardware, software, integration platforms, security, GDN (Woreda-net) etc has been identified at a high level by the eGovernment strategy. These projects need to be further elaborated from the technology adoption side while developing the Technology architecture.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 127 Confidential
Page 127
The overall EA reference model is provided below:
Figure 16: The overall EA reference model
GOVERNMENT SERVICE ARCHITECTURE
APPLICATIONS ARCHITECTURE
DATA ARCHITECTURE
TECHNOLOGY ARCHITECTURE
APPLICATION , TECHNOLOGY, DATA AND SECURITY STANDARDS, GUIDELINES, SPECIFICATIONS
LEG
AL
& R
EGU
LATO
RY
FR
AM
EWO
RK
GO
VER
NA
NC
E F
RA
MEW
OR
K DELIVERY CHANNELS
SERVICES PROVISIONING
CORE APPLICATIONS
COMMONAPPLICATIONS
MINISTRY SPECIFICAPPLICATIONS
COMMON NATIONAL DATA SET
METADATA REPOSITORY
ENTERPRISE INFORMATION MANAGEMENT
HARDWARE / SYSTEM SOFTWARE
INTEGRATION PLATFORMS
SECURITY
GOVERNMENT WIDE AREA NETWORK
Every aspect of Ethiopian life is ICT assisted
ICT infrastructure development
Human resource development
ICT for egovernance service delivery
ICT for agriculture modernization
ICT for improved health
ICT in the education sector
ICT in Industry and Private sector
ICT for research and development
Vision
StrategicInitiatives
ETHIOPIAN ENTERPRISE ARCHITECTURE REFERENCE MODEL
BUSINESS DRIVERS FOR ENTERPRISE ARCHITECTURE
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 128 Confidential
Page 128
XXV. Common Applications Common applications need to be made available across the Ministries and Agencies to enable smooth
functioning and provide focus on implementation of the priority projects by reducing the effort required.
The common applications would also facilitate collaboration and consistency across common processes
such as procurement, HR management, Financial Management etc.
S.No. Common Applications Owner Ministry Estimated Cost
1 E-Procurement MoFED 16.03 Mil. Birr
2 HRMS Ministry of Civil
Services
22.13 Mil. Birr
3 E-office MoCIT 16.03 Mil. Birr
4 Financial management
Information System (FMIS)
MoFED 4.03 Mil. Birr
Proposed Implementation Plan for Common Applications
Yr. v/s Project
Implementation plan
Year 1 Year 2 Year 3 Year 4 Year 5
e-Procurement
HRMS
e-Office
FMIS
XXVI. e-Procurement
Given the high percentage of government procurement as a percentage of total procurement in the
economy, a comprehensive eProcurement solution can substantially improve efficiency and cost
effectiveness of government
procurement. eProcurement
system will provide businesses and
ministries with a common
platform to transact. With
features such as demand
aggregation, catalogue based
procurement, dynamic pricing
engine, etc; the system is expected
to cut down the transaction costs
for not only the government, but
also suppliers. It is envisaged that
training will be provided to small
and medium enterprises so that
they can also benefit from the
solution.
Back-end / Legacy Systems
Government e-Procurement Meta-site Homepage
User/Dept. Specific View (Personalisation)
Back-end Application Integration & External Interfaces
Data Analysis (Spend and Demand)
Core Transaction Platform; Content
Catalog Based
Procurement,
eRFX,
eTenders
Search, Yellow
Pages,
Advertisements,
Business News,
Announcements
Supplier
Self-Service
Zone
Dynamic
Pricing Engine
(Auctions,
Reverse
Auctions,
Negotiations)
Multi-Channel Delivery
AdvertisersAgency/
BuyersGovt.
Employees
Suppliers
External
Service
Providers
Other
eProc.
Portals
Suppliers
Government
Co-operative
Enterprise
eProcurement
Portals
Back-end / Legacy Systems
Government e-Procurement Meta-site Homepage
User/Dept. Specific View (Personalisation)
Government e-Procurement Meta-site Homepage
User/Dept. Specific View (Personalisation)
Back-end Application Integration & External Interfaces
Data Analysis (Spend and Demand)
Back-end Application Integration & External Interfaces
Data Analysis (Spend and Demand)
Core Transaction Platform; Content
Catalog Based
Procurement,
eRFX,
eTenders
Search, Yellow
Pages,
Advertisements,
Business News,
Announcements
Supplier
Self-Service
Zone
Dynamic
Pricing Engine
(Auctions,
Reverse
Auctions,
Negotiations)
Multi-Channel Delivery
AdvertisersAgency/
BuyersGovt.
Employees
Suppliers
External
Service
Providers
Other
eProc.
Portals
SuppliersSuppliers
External
Service
Providers
Other
eProc.
Portals
Suppliers
Government
Co-operative
Enterprise
eProcurement
Portals
Figure 17: eProcurement
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 129 Confidential
Page 129
e-Procurement solution will take care of the end-to-end procurement process, including:
Vendor management
Catalogue management
Bid process management
Auctions
Payment management
Contract management
Main benefits that should accrue due to implementation of the e-Procurement system include:
Transparency and accountability in procurements
Reduction in cost of procurement for government due to increased competition and demand
aggregation
Reduction in cost of bidding by 50%
Improve turnaround time for payments
Following key activities need to be undertaken to establish an e-Procurement system for the Government
of Ethiopia:
As part of the project, the following key activities are required to be undertaken:
1. Reengineering and streamlining the complete public procurement process
2. Development of the eProcurement solution with the requisite functionalities
3. Procurement of hardware for hosting the application
4. Develop a meta-site homepage dedicated to eProcurement that can also be accessed through the
eGovernment portal
5. Vendor development programme
XXVII. Government wide HRMS
The efficient management of government resource personnel is imperative to bring in efficiency and
improve productivity. A government wide Human Resource Management System is a compelling tool for
this purpose. It is recommended that Government wide HRMS solution is commissioned across all
government agencies under the leadership of Ministry of Civil Services. As per the assessment study, some
work has already been undertaken in this regard. At a minimum following steps need to be undertaken to
bring this to fruition:
1. Analysis of the management information needs of the Civil Services Agency and the HR
departments of the ministries
2. Decision regarding development of a new software or purchase of a Commercial-off- the- shelf
(COTS) HRMS solution. COTS solution is faster to procure and also has good practices embedded
within, so using a COTS HRMS with minimum customizations can potentially yield higher
performance improvements.
3. User training and awareness campaign to build support and uptake is required.
Following benefits are envisaged from this project:
Employee empowerment
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 130 Confidential
Page 130
Enhancement of computer usage skills of employees as they are likely to use the system for
availing services
Efficient and effective management of the government workforce
XXVIII. Financial Management Information System
An Integrated Budget and Expenditure System (IBEX) is an integrated financial management information system (IFMIS) addressing the core functions of public financial management with the flexibility to include other non-core functions has been developed by Ministry of Finance and Economic Development. It is a custom built solution using industry standard products and open source frameworks that has been developed to support public financial management reforms in Ethiopia. The IBEX web application is deployed on the country‘s WoredaNET infrastructure.
IBEX is an integrated budget and accounts financial application, which provides the framework for core public financial management functions and has the following core modules
Budget Module: This module executes all the budget preparation activities performed by government financial offices.
Account Module: This module executes all the budget execution activities of government budgetary institutions. More specifically, the accounts module records the financial transactions of the budgetary institutions, records the aggregated monthly accounting reports and provides accounting reports for ledgers, financial statements, management reports, transactions, expenditures and revenues.
Budget Adjustment Module: This module provides the functionality to address changes to the approved budget during budget execution. It specifically enables the recording of budget transfers and budget supplements and the subsequent production of the adjusted budget.
Budget Control Module: This module manages the activities of recording budget commitments and disbursement payments in order to enable budgetary control over expenditures.
Account Consolidation Module: This module consolidates the budget and accounting data for the entire country. This module allows for the generation of regional and national consolidated reports.
Disbursement Module: This module manages the public treasury functions associated with cash management and disbursing funds between public financial institutions.
Administration Module: This module provides an interface to manage users and user‘s profiles that interact with the IBEX system.
Figure 18: IBEX System
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 131 Confidential
Page 131
eOffice
Enterprise Content Management
Role and Group
Management
Content Collection
and Creation
Content
Transformation
Library
Services
Metatagging WorkflowMulti-
Language
Document & Records Management
Digital Asset Management
Collaboration
Knowledge Management
Under the e-Government Strategy it is envisaged to upgrade this system by undertaking the following
initiatives:
Implementation of the IBEX application across all the Regions in the Country
Standardization of process and workflow for using IBEX across different Ministries/Agencies to
simply the process of data compilation
Hosting of the IBEX application in the National Data Centre
XXIX. eOffice / Document Management
As more public constituents demand instant access to public information, government agencies need an
efficient, affordable and accessible solution that eliminates paper work and provides a simple, searchable
and secure way to publish documents on an intranet or the Internet. Going forward, the idea is to
eliminate the paper-based interactions even within the government across different agencies by using a
single solution. Document Management addresses the life cycle of documents (workflow), provides library
services (versioning, security, audit trails), maintains components of documents (compound documents)
and manages the long-term archives (records management). Managing documents typically involves
structured business processes that are document-centric, and often involve lengthy and complex
documents; examples include legal or regulatory documents (e.g., land records, applications, and
standard operating procedures), contracts and proposals. A document management system helps in
streamlining the internal processes to create a paperless office by ensuring an effective migration of old
documents from legacy systems to the archives.
This strategic initiative is envisaged to provide the following benefits:
Communications management through digital registration and routing of government
communications
Efficiency in receipt,
processing & output
Performance
management through
standardization and
automation of
repetitive processes
Knowledge
management
Transparency and
accountability in
operations
Cost-effectiveness
Responsive to customers
Figure 19: eOffice Components
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 132 Confidential
Page 132
Following are the broad steps required for implementing the solution:
1. Analysis
a. Scope/definition of the system
b. Analysis of requirements
c. Analysis of the IT infrastructure
d. Envisioning of the system
2. Design
a. Definition of requirements
i. Solution evaluation
ii. IT infrastructure definition
iii. Data migration
b. Definition of documentation and training
c. Transition planning
d. Implementation design
3. Development
a. Vendor selection
b. IT development
c. User documentation
d. Testing
4. Implementation
a. System implementation
b. IT support
c. User training
5. Roll out of the solution.
XXX. Government wide email system
Email can be used as a very effective medium for the inter-office and intra-office communication. Though
some of the departments use the commonly used web-based mailing services, it is limited by internet
access. The email-ids must be created for the important functionaries in the department. Since the email
system will be common across the departments, the common system can be used across with the
standardization in email addresses.
The Government has already undertaken commencement of this initiative and this may be speeded up
and completed quickly, so as to help in the Strategy implementation.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 133 Confidential
Page 133
Section 4 –
STRATEGIC
DIMENSION 2 –
CHANNELS
PricewaterhouseCoopers Page 134 Confidential
Page 134
V. Strategic Dimension 2 - Channels
I. Introduction
The term channel connotes the means through which services are delivered to the customers. Channel
Strategy represents a set of business-driven choices about how and through what means services will be
delivered to customers.
The central theme of the e-Government strategy is to enhance public service delivery through the phased
electronic enablement of services. However, provisioning services through electronic means is only useful
if it facilitates the customers to access services anytime and anywhere in a more convenient manner.
Identifying channels of customers‘ preference is a critical success factor for effective eGovernment, as the
choice of delivery channels has a major impact on the following:
Technology infrastructure required to support the channel such as hardware, software and
networking.
Standard procedures and guidelines required to operate the channel.
Organization structure required to manage and deliver the electronic services such as skills, roles and
alliances.
Convenience and satisfaction for the customers in availing public services.
II. Current Status
Based on the assessment study conducted during the formulation of the eGovernment Strategy, following
observations need to be highlighted:
Ethiopian eGovernment Portal is already operational, albeit with limited functionality.
Government information portals for around 15 Entities including Ministries and other institutions
have been hosted presently and still more are under development.
All regions and federal institutions are to develop and implement websites with basic level public
service delivery information as per the existing policy of government. 69 websites have been
developed for regional bureaus to make information accessible to the public.
A call centre has been established by MINISTRY OF COMMUNICATIONS & IT with participation of 4
government entities - Transport Authority, Addis Ababa Transport Branch Office; City Government of
Addis Ababa, Land Administration; Document Authentication and Registration Office and Social
Security Agency.
Three Services (weather forecast, currency exchange rates and Electricity) are likely to be provided
through the mobile channel in the next 1 month.
92 ICT community centres have been established across the country. These centres are well equipped
and could be leveraged as Common Services Centres (CSCs) in future.
PricewaterhouseCoopers Page 135 Confidential
Page 135
Channel strategy should support wider government policies on universal access,
modernizing government and social inclusion.
Channel strategy should ensure social inclusion, providing coverage for the
underprivileged and people with special needs for accessing services.
Channel strategy must ensure a “no wrong door policy” – citizens should be able to
conduct different steps of the same transaction through different channels in a
seamless manner.
The agencies should adopt channel strategies in a coordinated manner so as to
leverage synergies and economies of scale to deliver integrated services in a cost
effective manner.
Channel strategy should be focused towards providing clear benefits to both customers
and agencies.
A coherent and clear Channel migration strategy must be implemented to promote
uptake of new channels
Channel strategy should ensure integration – an applicant should be able to perform
different steps for availing the service through different channels
III. Summary of the status of the different channels is as below –
Table 19: Channel – Current Status
Sr. No Channel Status
1 National Portal Portals for around 15 entities including Ministries and other
institutions have been hosted presently and still more are
under development.
Few Information services are present -27 Informational
Services
Channel uptake has been very low
2 Call centre Four Agencies with around nine agents now providing
information
Approx. 700 calls answered per day
But there is more demand existing - around 4000 calls are
attempted every day
3 ICT Service
Centres Approx. 92 existing ICT Community centres
Set up by ICTAD
4 Mobile Under design
Three Services (weather forecast, currency exchange rate and
electricity bill information are likely to be provided shortly
IV. Guiding Principles for Channels Strategy
PricewaterhouseCoopers Page 136 Confidential
Page 136
V. Recommendations and Targets
Based on the technological choices available today, readiness levels of participating organizations,
customer preferences and an overwhelming preference of key decision makers for integrated service
delivery, the following channels present themselves as viable alternatives for delivering government
services alongside traditional government offices:
1. eGovernment Portal: where customers can use internet to request and avail services, search
information, make payments, etc
2. Phone (Call Center): where customers can call up to request services and information and
access the same through call center agents and ‗Interactive Voice Response‘ technologies.
3. Mobile Gateway; where customers can request services and information through mobile
phones and hand-held digital personal assistants. The departments can send customers regular
alerts through SMS.
4. Common Service Centers (CSC): where services like Information dissemination, acceptance
of service requests and delivery of services is provided to the customers at a single point of service
delivery. CSC includes self-service kiosks, utility bill payment centers, ICT community centers etc.
Furthermore, the Government in Ethiopia is about to commence implementation of the Unified
Billing System (UBS) in a Public-Private Partnership (PPP) mode in Addis Ababa. This project
will establish 70 billing centres (for payment of power, telephone & water bills, to begin with),
with all required IT Infrastructure. These may be considered for upgradation as CSCs by
facilitating delivery of all e-Services. It is also planned to expand the UBS project to more cities.
The options of the various channels and the factors of convenience and choice to the customers make it
imperative to develop a comprehensively defined strategy for the enablement of service delivery channels.
Each of these channels and their implementation plan is discussed in greater detail in the following pages.
PricewaterhouseCoopers Page 137 Confidential
Page 137
Implementation model
• Existing “in-house” model for portal management
• Portal design based on customer
segments and life events
Outcomes
• One stop-shop for all e-Services• Service improvement through
customer feedback
Critical Success Factors
• Introduction of eServices as per the schedule • Content management processes for updating content• High uptime
• Standards and policies for integration and security of data• Marketing and awareness campaign
VI. e-Government Portal
Government Portal is envisaged to be the primary electronic channel for providing eServices to the
customers. There are several advantages that can accrue to the government through the use of
eGovernment Portal as the primary service delivery channel.
The portal can be the integration point and a one stop shop for all government services. It can also act
as a linkage between the other delivery channels.
User friendly – all services available at a single location for anywhere, anytime access.
The use of internet helps in reducing load on physical infrastructure of the government by reducing
the need for customers to visit government offices.
It requires minimal human intervention and enables interactive service delivery.
Easier to remember 1 URL than a number of different URL‘s for each department
Presents single face of the government
Leads to higher usage of web services as users of already existing services get information regarding
new eServices while transacting
Internet is a cost effective and convenient means for providing information about services, rules and
regulations etc.
Implementation Imperatives
Ethiopian eGovernment Portal is already operational, albeit with limited functionality. The Government
of Ethiopia needs to consider the following implementation imperatives for further development of the
eGovernment portal as a delivery channel for Government services:
Mandate a common look and feel for user interface for all government websites of Ethiopia
The enablement of services for online/ electronic delivery channels would require:
o Changes to departmental IT systems: The existing IT systems are designed to cater to the
backend functioning of the departments only, hence would need modification for service
delivery through the portal.
Figure 20: e-Government Portal
PricewaterhouseCoopers Page 138 Confidential
Page 138
o Regulatory changes: The new process redesign for online delivery may also require changes to
the regulations governing the service.
Well defined content management processes to ensure that the content published on the portal is
relevant and up-to-date.
A capable team and robust processes and systems for network and portal maintenance to ensure
acceptable uptime and resolution of issues impacting services delivery 24*7.
A Monitoring and Evaluation framework for measuring the effectiveness of service delivery through
the portal and to identify opportunities for further improvement.
Innovative measures such as Common Services Centers to ensure that the limitation of high cost of
computer equipment and internet access does not result in low uptake of the portal.
Single Government portal can only be successful if it has the backing of all the ministries and
agencies. Therefore, it is imperative that an inter-ministerial group is constituted to oversee portal
development and maintenance
Marketing and awareness campaign for creating awareness regarding the benefits of availing services
through the portal. This is extremely important – considering that presently the usage of the portal is
very poor (approx. 1000 hits per month).
98% uptime of the portal and eServices should be ensured through stringent service levels.
Introduction of eServices as per the schedule to keep the momentum
Standards and policies for integration and security of data to facilitate delivery of services that span
across ministries
Options Analysis
The various options available for enhancing the e-Government Portal along with their implications are as
follows:
Table 20: e-Government Portal Implementation
Option Implication
In-house Portal Large up-front cost
Difficult to implement stringent service levels
Outsourced Portal Ownership of servers, data and basic project management team
with government
Outsource development, operation and maintenance of the portal
Lower up-front cost and overheads
ASP Model (Vendor-
managed) Vendor gets paid based on the number of transactions
No extra capacity created
Recommendation
Currently Ethiopia‘s e-Portal is managed in-house. Based on the current assessment of the existing portal
and websites of various departments, it is suggested that
The government may continue with the ―in-house portal‖ model in the immediate term (next one
Year) with enhanced infrastructure to be able to provide eServices. However it needs to Outsource
PricewaterhouseCoopers Page 139 Confidential
Page 139
development & maintenance – keeping ownership with Government, so that the portal is able to
provide all services – End to End, as they are developed.
Enhancement of Portal – to provide ‗End-to End‘ delivery of identified 216 E-Services - including
facilities of online authentication, digital signatures, payment, etc
Establish Governance Framework and portal management processes, to ensure continuous updation
and improvement and provide more relevant content & facilities for online Citizen participation in
Governance & development – this will help increase uptake of the channel
Consider options to allow private sector participation in the provision of related value-added services
through the portal
Government should also consider options to allow private sector participation in the provision of
related value-added services through the e-Government portal
As mentioned above Government should consider outsourcing the development & maintenance of the
portal, while retaining ownership. This will help ensure that the development of the portal is able to
simultaneously develop as the various projects of E-Government Strategy are implemented. The Vendor
would be responsible for ensuring that the usability and technical capacity of the portal are up to date –
while Government would focus on making different services available through this channel and the
Governance and management processes, so that Content is always updated and is relevant to the needs of
the different stakeholders.
It is proposed that the outsourced operations of the portal will commence by year 3. Total
estimated cost for the portal is 29.06 Mil. Birr.
Outcomes
Ethiopia should drive the implementation of the eGovernment portal by taking into account of outcomes
such as
E-Government portal to be the one-stop-shop for all Government services
All possible Government services to be delivered completely through the eGovernment Portal.
Availability of services on portal should be in line with their implementation, which will make the
following number of services available through the portal channel, over five years -:
o Year 1: 35
o Year 2: 73
o Year 3: 64
o Year 4: 30
o Year 5: 9
Visible enhancement in the customer experience and reduced cost of availing services
Reduction in per transaction cost for the Government
Provide 98% uptime for all online services
All informational services, downloadable forms, grievance redressal and status tracking for
applications to be provided online.
Online feedback mechanism to be established to facilitate participation of customers in improving
the services delivery
PricewaterhouseCoopers Page 140 Confidential
Page 140
VII. Contact Center
A Contact Center can be an effective means of obtaining service related information, delivery of some
services, and grievance redress. The call center provides the following advantages:
Figure 21: Contact Center
It provides an element of human interface to the process of information dissemination / complaints
recording
It is a cost effective means to disseminate information to the customer in an interactive way.
It reduces the need for the citizens to visit the government office for information, thereby helping in
reduction of the load on the physical infrastructure of the government departments.
Most inclusive alternate channel as telephone is much more pervasive than internet and the number
of people who can use telephones is much higher than those that use internet. A testimony to this is
the fact that the present call center with participation of only 4 ministries is attracting over 800 calls a
day.
The record of all interactions with the customer can be maintained and analyzed for continuous
improvement in service delivery.
It can be used as an outbound centre to promote specific government schemes to target customer
segments and pro-actively provide information to the customers.
The Contact centre will essentially provide support for all government services. It shall serve as a first
point of contact for most customers exploring alternate delivery channels. The call centre would also
provide information on all government services with certain value added services like status checking, and
grievance redressal for all services. The call centre is expected to provide multi-lingual support.
Implementation Imperatives
Following implementation imperatives need to be considered for the development of the Call centre as an
effective delivery channel for Government services:
Learning‘s from the in-house call center established at MINISTRY OF COMMUNICATIONS & IT
must be documented and utilized for better performance.
Multilingual support in English, Amharic and identified regional languages must be provided.
Increasing capacity to meet growing demand
Adherence to service levels and Standard Operating Procedures.
Implementation model
• Outsource Call Center operations to third party
• Outbound calls for targeted promotion
and push services
Outcomes
• A single national toll free number for all information services, status checks and complaints
Critical Success Factors
• Bilingual support in English and Amharic• Adherence to service levels and Standard Operating Procedures• Integration with other channels especially the eGovernment portal
• Marketing and awareness campaign
PricewaterhouseCoopers Page 141 Confidential
Page 141
Integration with other channels especially the e-Government portal
Marketing and awareness campaign to raise awareness regarding the existence of call center and
benefits that accrue by using the channel for availing services.
Design the database of expected FAQ‘s from customers on services to facilitate call center operations.
These would need to be updated continually.
Design of efficient IVR system to resolve maximum queries through self-service by callers.
Implementation of a CRM analytics system for analyzing the calls received.
Options Analysis
The various options available for implementing the Call centre along with their implications are as
follows:
Table 21: Contact Centre Implementation Options
Recommendation
Government of Ethiopia has set up an in-house government call center. Since the current set-up is very
basic and not a full-fledged call center, it is suggested that as part of the e-Government strategy
implementation, the government should establish an ―Outsourced Call Center‖ to facilitate e-Services.
This is further necessiated by the fact that the Call Centre channel requires expertise of different domains,
including IT and Communications infrastructure, operations, human resource management and training
and service delivery excellence. However a dedicated team to continuously monitor the service levels and
lead further improvements in services delivery must be established. So Government should consider –
Implementing outsourced call centre model
This channel would be able to provide 77 informational and around 40 transactional services
(estimate of 30% of the transactional services identified)
Option Implication
In-house Call
centre Large up-front investment
Hard to scale down in case up-take is weak
Maximum control of government and data security
Outsourced Call
Centre Servers, data, and basic project management team belongs to the
government
Call centre infrastructure and operations by private party
Lower up-front cost
May take some time as call center industry is not very mature in
Ethiopia
Vendor-managed
Call centre
(transaction-based
payment)
Vendor gets paid based on number of calls handled
No extra capacity created
Least control of the government
Concerns over data privacy
PricewaterhouseCoopers Page 142 Confidential
Page 142
The Call centre would also provide facilities for outgoing calls, emails, live chat, integration
(connecting to live databases of Ministries)
It is proposed that a 100 seat facility (including 80 agents and support staff), be established
– which would take care of increased number of services as well as be able to serve calls
from regions. Outsourced operations would start from year 3. Total estimated cost is at
164.57 Mil. Birr.
Call centre outsourcing can be a PPP business model – wherein there would be toll-free service for
services like information and transaction services like payments etc, may be through paid calls.
Private partner would be paid on number of calls and the services.
Outcomes
Desired outcomes of implementing the Call centre as a delivery channel are:
A single national toll free number for all information services, status checks and complaints with
Multi-lingual (English, Amharic and popular regional languages) support.
The services rollout proposed through the call centre channel, over a period of 4 years
is
o Year 1: 35
o Year 2: 42
o Year 3: 20
o Year 4: 20
Visible enhancement in the customer experience and reduced cost of availing services
Improvement in Service turnaround time
Proactive service delivery (push services) by leveraging the Call Center.
30% of grievance resolved on call and 90% resolution of all grievances received within 5 working days.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 143 Confidential
Implementation model
• Outsource Call Center operations to third party
• Outbound calls for targeted promotion
and push services
Outcomes
• All informational, status checking and payment services to be available through mobiles.
Critical Success Factors
• Cooperation and support of the Ethiopian Telecommunication Company• Redesign of content and formatting for mobiles• Identification of services amenable for delivery through mobiles
• Integration with other channels especially the eGovernment portal• Marketing and awareness campaign
VIII. Mobile Gateway
Mobiles are used world-wide for providing Government service due to their high penetration. Some of the
advantages of the mobile Gateway as a service delivery channel are:
A mobile gateway helps in providing services to customers on the move.
Reduction in cost of delivering and availing services.
Anytime, anywhere access to information and select public services
It reduces the need for the citizens to visit the Government office for information, thereby helping in
reduction of the load on the physical infrastructure of the government departments.
The mobile penetration is increasing at a fast rate, so this channel is likely to become the most
pervasive service delivery channel in the future.
Using the mobile gateway, a number of select services can be delivered such as:
Payment services;
Information services;
Currency converter;
Flight Information
Weather information
Status checks
Information regarding important / emergency numbers
Proactive delivery of services, i.e. push services (services such as intimation regarding renewal of
licence which is due in future etc.).
The Government of Ethiopia has already awarded a pilot project for the enablement of 3 services
(Currency rates, weather information and Electricity bill information).
The high-level diagram below illustrates the different functions in end-to-end solutions of the various
components of mobile middleware required to for delivering eGovernment services.
Figure 22: Mobile Gateway
Cooper
Web Application
Server / Agency
Applications
Table 22: Middleware required for Wireless Applications
Architectural Layer Middleware Required
Tier 1 Device integration/drivers; Browsers
Tier 2 Wireless gateways
Tier 3 Web and wireless application servers; Wireless commerce
servers
Tier 4 Enterprise application integration (via application
connectors)
Implementation Imperatives
Following implementation imperatives need to be considered for the development of the mobile channel
as an effective delivery channel for Government services:
Identification of services amenable for delivery through mobiles
Redesign of content and formatting for mobiles
Support and cooperation of Ethiopian Telecommunication Company (ETC) must be solicited.
Mobile interface / application connectors need to be developed for the e-Government Portal and
applicable agency applications.
Adherence to service levels and Standard Operating Procedures.
Integration with other channels especially the e-Government portal.
Marketing and awareness campaign to raise awareness regarding the existence of call center and
benefits that accrue by using the channel for availing services.
Figure 23: Four tier Architecture for Wireless Application Delivery
Cooper
Options Analysis
The various options available for implementing mobile gateway along with their implications are as
follows:
Table 23: Mobile Gateway Implementation Options
Option Implication
In-house Mobile Gateway Large up-front cost
Difficult to implement stringent service levels
Lack of in-house expertise in government will require
extensive recruitment for the purpose which may be time
consuming
Maximum control and data privacy
Outsourced Mobile Gateway Ownership of servers, data and basic project management
team with government
Outsource development, operation and maintenance of
Mobile Gateway
Lower up-front cost and overheads
Faster implementation
ASP model (vendor-managed) Vendor gets paid based on number of transactions handled
No extra capacity created
WAP server and content converter provided by vendor
Integration effort also carried out by vendor
Fast implementation
Recommendation
It is recommended that the Government of Ethiopia should consider options of Outsourced Mobile
gateway and ASP model (vendor managed) gateway for its services. This would involve
• Set-up of Mobile gateway and creation of content for the Mobile channel
• Provision of 77 informational services and around 40 transactional services
The business model option can be PPP implementation – with the private partner responsible for
development & maintenance and payment would be based on number of transactions/uptake of the
channel.
It is proposed that outsourcing of the mobile channel commence from year 2 and the total
estimated cost at 19.25 Mil. Birr
Cooper
Outcomes
Desired outcomes of implementing the mobile gateway are:
All payment services and services related to status queries of applications for availing services to be
made available through mobile.
Availability of 77 informational and around 40 transactional services
The services rollout through the Mobile channel, over 4 years proposed is
o Year 2: 35
o Year 3: 42
o Year 4: 20
o Year 5: 20
Visible enhancement in the customer experience and reduced cost of availing services.
Wherever possible, proactive service delivery such as reminders for deadlines etc. to be enabled
through mobiles.
At a later stage, services such as mobile parking solutions in busy areas to be introduced.
Cooper
IX. Common Service Center
Common Service centers would facilitate single window multiple services delivery. This means that
Common service centers though similar to departmental counters, would provide services of multiple
departments. Key drivers for Common Service Centres are:
Customer Preference for human interaction
Some government services may require manual signatures on documents
A wide array of services of multiple departments could be provided to customers from a single point
Common Service Centres are an inclusive means of service delivery as service delivery is not
dependent on technology requirements, and technical knowledge on part of the customer is not
required.
Further, the CSC transcend the problem of low literacy and low PC and internet penetration by
leveraging ICT to reach the masses and also providing a human interface to facilitate the delivery of
services.
Ethiopia has successfully implemented fully functional 65 ICT community Centres that cover nearly
95% of the country‘s population. These Centres along with the Unified Billing Centres could be
utilized for delivery of eServices.
Common Service Centers (CSC) can either be set up at existing government premises (government
agency counters) or other locations such as the ICT Community Centers and Unified Billing Centers.
CSC shall provide all portal based services and other services requiring physical presence.
It would also provide payment related services, along with form distribution and submission for all
government services.
For customers who do not have Internet access, there would be an information help desk for
assistance, and self-service (or facilitated) kiosks for accessing the Internet to avail government
services.
Implementation model
• Leverage existing ICT Community Centres and proposed Unified Billing Centres as CSCs
Outcomes
• Single window multiple service delivery
• All government services to be
available in the locality
Critical Success Factors
• Training of staff at the CSCs• Authority and empowerment of the staff at the CSCs• Integration with other channels especially the eGovernment portal
• Adherence to Service levels and standard operating procedures• Marketing and awareness campaign
Figure 24: Common Service Center
Cooper
Implementation Imperatives
Some of the implementation imperatives for successfully setting up CSCs as service delivery channels are:
Framing processes and guidelines to facilitate the delivery of departmental services through CSCs
including
o Process design, including clearly laid out roles and responsibilities for the people involved
o Identification of process owner
o Changes/upgrade in department IT systems
o Design and monitoring of SLAs, along with escalation and problem resolution in case of
breach
Utilizing 92 existing ICT Community Centers and the proposed 40+ Unified Billing Centers for
offering government services
Customer orientation training and functional training regarding the services to staff at the CSCs
Monitoring and Evaluation framework for measuring effectiveness of service delivery
Recommendation
It is recommended that the 92 existing ICT Community Centres and the proposed 40+ Unified
Billing Centres are leveraged as CSCs for offering government services immediately.
The number of CSCs needs to be increased as per the demand for services across the country and
also to facilitate easy access to government information and services even in interior and remote
areas, in the longer run.
It is recommended that additional 800 CSCs be set up in Partnership with the private sector on a
PPP business model. This would cover all the Woredas in the country. Spreading the CSCs till
Kebele level could subsequently be taken up by respective regions, based on need and demand.
The CSCs would charge transaction charges for services availed by citizens – which would not
only include Government services but also others like photocopy, basic DTP services, etc.
However it may be expected that around 50 % of the CSCs could be self-sustainable, in terms of
being able to meet operational expenditure and recover capital investment to some extent.
Remaining CSCs may need provision of subsidy and support from Government, in order to be
viable.
It is estimated that an investment of approx. 2206.21 Mil. Birr would be needed over a period of
five years for the CSC project. However, the project is expected to start only from Year 2 on PPP
model – after required tendering and finalisation.
Broad level estimate at this stage, of the support needed from Government would be around 50%
of the investment i.e. 2206.21/2 = 1103.11 Mil.Birr. The remaining investment is proposed to be
provided by the private partner.
Outcomes
Government of Ethiopia should drive implementation of Common Service Centers by taking into account
outcomes such as:
CSC to offer service of all government departments
Availability of services through CSCs would be in line with availability on National
Portal, which will make the following number of services available through the portal
channel, over five years -:
o Year 1: 35
Cooper
o Year 2: 73
o Year 3: 64
o Year 4: 30
o Year 5: 9
Visible enhancement in the customer experience and reduced cost of availing services
No need for citizens to visit departments for services related to submitting applications, making
payments, requests for duplicates, etc and to be provided from CSC
All services offered through the portal to be available at the CSC
Defined and published service levels for all services to be delivered through CSC
Self-service kiosks also to be established
ISO certification for processes at Common Service Centers
X. Channel Migration Strategy
The introduction of alternate channels needs to be augmented with channel migration initiatives to
increase the uptake of electronic channels. Some of the recommended initiatives towards this end are:
Promotion of benefits of eServices: To promote uptake, it is essential to educate customers of
the benefits of using the e-Services. The customers would use the new channels if there is a
perceptible advantage to them in terms of cost, time or convenience. Hence, specific campaigns to
highlight advantages of availing services through alternate channels should be conducted.
Targeted promotion of service: The Government can identify specific high-value services for
targeted utilization improvement.
Incentives such as Differential pricing and faster turnaround times: Financial incentives
including lesser fees for availing services through electronic channels could be useful incentives for
promoting usage of electronic channels. Similarly, turnaround time for services demanded
electronically could be reduced as compared to the services demanded through conventional channels
to provide incentives to the early adopters.
Adding value through information and expertise: Government needs to focus on ‗pulling‘
customers to more efficient channels by making the informational services more useful and attractive.
Possible compulsion for channel shift: Government has the option of implementing compulsory
channel shift, focusing initially on the more sophisticated audiences of business and intermediaries.
One of the ways of compelling the users for channel shift is to offer some services exclusively through
the electronic channels. This is one of the most difficult ways of implementing channel shift, but
provides maximum benefit as closure of inefficient channels results in savings and enhanced
efficiency for the Government.
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 151 Confidential
VI. Strategic Dimension 3 - Enablers
I. Capacity Building
E-Government projects are not equivalent to conventional IT projects. The focus of the e-Government
strategy is on service, service levels and
sustainability; not on software and hardware.
Capacity building seeks to address the skill gaps in
the current system and people. Capacity building
in the context of this strategy refers to the need to
adjust policies and regulations, to strengthen
institutions, to modify working procedures and
coordination mechanisms, to enhance the skills
and qualifications of people, to change value
systems and attitudes in a way that meets the
demands and prerequisites of implementing the
eGovernment strategy.
The adjacent figure depicts the journey towards
developing a Capacity Building Strategy for
Ethiopia. The Strategy emphasizes the need to not
only strategize in terms of identifying and
developing CB initiatives but also to sustain the
capacity that has been developed. A structured Capacity Building framework has been developed as part
of the Strategy. The report presents in detail this framework and each of its components. It also lists down
the Capacity Building initiatives in each component and how they contribute to achieving objectives laid
down for this objective area.
Summary of the Current Capacity Building Initiatives undertaken
Ethiopia in the past few years has undertaken significant Capacity Building initiatives such as
Technical Vocational Education Training (TVET) centers have been created and around 576
teachers have been trained on ICT to effectively deliver education to students. Around 15 ICT training
labs in all the regions have been established for providing training to the TVET teachers.
Four Business Incubation Centers to help entrepreneurs‘ in ICT related businesses has been
established. A total of 43 private ICT start-ups have entered into business under these established
centers. In addition 18 Virtual Incubation in Addis Ababa have been established to support the ICT
start-ups and create business opportunities.
645 SME operators have been trained on computer maintenance, basics of computing and
database by training institutions such as FEMSEDA and PIC.
The ICT Centre of Excellence has been established in Addis Ababa University for research and
development of ICT solutions.
Computer Refurbishment and Training Center (CRTC) has been established to provide
hands on training on computer refurbishment and technical and business training. The key activity
included refurbishing donated computers to provide affordable computers to schools, health centers
and communities.
Training to the Experts: 931 members trained in basic IT skill, 203 members trained in Interactive
and Dynamic Webpage Development, 1180 members trained in Advanced Network Management, 103
in IT Security, 80 in IT Security & Cyber crime, 100 members trained in Business (IT) Continuity and
Figure 25: Capacity Building
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 152 Confidential
Disaster Recovery, 60 members trained in C# with dot.net Frame work, 33 in CCSP, 112 members
trained in Database Management.
Seven Community Radios have been implemented and operationalized which helps in
information dissemination and Capacity Building in rural communities.
Some of the improvement opportunities identified during the assessment study include:
Almost all the ministries and agencies acknowledge that the biggest challenge to implement e-
Government in Ethiopia is the non-availability of the technical manpower and Capacity Building
Lack of established communication between all the Capacity Building organizations for monitoring
and evaluating the Capacity Building programs
Limited number of IT professionals to support Ministries/Agencies in future plans and initiatives
Lack of qualified employees and technical experts (the education and experience of some of the IT
personnel are not relevant)
Capacity Building Objectives
Objectives identified for IT Capacity Building are:
Create appreciation and understanding of eGovernment projects amongst the decision makers
Increased computer literacy among Government staff
Re-orientation of the government staff to focus on customer service delivery
Enhancement in capacities of the ministries to undertake e-Government Projects
Development of skill sets amongst customers
Effective government wide knowledge sharing and coordination
Change Management Plan
Framework for Capacity Building
The Capacity building initiative for the e-Government program should work towards the following:
1. Enhancement of required skills within the government to implement and run e-Government
program
2. Development of skill sets amongst customers
The Strategy for accomplishing the above is enunciated below
Enhancement of required skills within the Government
This will be accomplished through the following initiatives:
Initiative 1: Creation of Information Technology Services Group
Initiative 2: Training Needs Assessment and Preparation of Training curriculum
Initiative 3: Strengthening of IT Training Infrastructure including development of a
Knowledge Management Portal and e-learning facilities
Initiative 4: Conduct Seminars, workshops and study tours
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 153 Confidential
Initiative 5: Standardization of structure of IT Department across the Ministries and
Agencies – for smooth & effective implementation of the priority projects.
Initiative 6: Incentivize employees to build capacity
Initiative 7: Establishment of Common Data Terminals (CDTs) in each Ministry/Agencies
Initiative 1: Creation of Information Technology Services Group
Our experience shows that governments across the world face the following issues in retaining talented IT
staff due to the following reasons:
IT directorates / divisions within ministries are too small to offer any career path to IT professionals
As IT divisions are small, even minor attrition has a high impact. Reactive hiring to fill up the
resource gap leads to compromise in quality of new staff.
Due to small IT staff size within ministries, available skill sets are not diverse, as a result evaluating
and working on diverse technologies and solutions is difficult.
Pay scales of trained IT staff in government are perceived as low as compared to prevailing rates for
IT professionals in the private sector
Some of the highly qualified staff such as software architects are either too expensive for the
ministries to afford or even if they hire them, they are unable to utilize their services to the fullest as
the amount of work a typical IT department handles only requires such specialized expertise
sporadically.
In order to overcome these difficulties, a recommended course of action is the establishment of a
government wide Information Technology Services Group (ITSG) to create a pool of IT resources
available for all the government organizations on a need basis. Such an agency would be the responsible
for central repository and exchange of all systems and software, would recommend and monitor external
IT contracts, develop IT curricula and training models for use throughout government and provide a
knowledge base for all IT needs linked to a central knowledge management repository. The detailed
structure of ITSG is provided in Section-3 Governance structure. The existing Human Resource
Development, Capacity Building, Research and Consultancy Directorate should be enhanced to provide
support as envisaged from the ITSG group
Following benefits will be realized through the ITSG (as
depicted in Fig 13):
Capacity Balancer: ITSG would act as a capacity balancer
for Ministries at different stages of IT maturity. While some
Ministries may not require any outside support, others
might require additional IT resources to accomplish time
bound projects. ITSG would help the Ministries that need
additional support through the provisioning of resources for
completion of the IT projects undertaken by them.
Focus on outcomes and timelines: As the ITSG staff
will be deployed in any Ministry/Agencies for a fixed time to
complete a project; there would be a higher focus to
complete the projects on time.
Better staff retention and career planning: The size of the Figure 26: ITSG
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 154 Confidential
proposed ITSG will be large enough to provide a defined career path and growth opportunities to IT
resources. Though the IT resources could work on projects in different Ministries / departments, they
would report to the managers in the ITSG and have a deeper career path in the ITSG.
Diverse skill sets: Due to the aggregation of resources, diverse skills sets would be available within
the ITSG to undertake projects. This will enable the group to use most appropriate people and
technologies to provide solutions.
There are three options for the organizational set up of the proposed ITSG:
Table 24: Analysis of Options for ITSG
Analysis of Options for setting up ITSG
Options Positive Negative
Option 1: Established
as part of MOCIT
This option is the quickest way for
establishing the group, as some of
the IT staff from various
Ministries may be deputed to the
group.
However the issue of attrition due to
lower wages than the market may not
be addressed through this option.
Option 2:
Incorporation as a
separate company
wholly/partially owned
and controlled by the
government
This option will allow private
participation in provisioning IT
human resources without
relinquishing the control of the
Government. This option will
facilitate the linking of salaries to
market rates and bring in higher
efficiencies and productivity
associated with the private sector.
This will however, tie up the
government with a private partner who
may get an opportunity to cast undue
influence over the e-Government
programme.
Option 3: Outsourcing
to private sector with
the IT staff of the
government being
transferred to the
private partner‘s
payrolls
This option will allow the
Government to cap its IT Human
Resource expenditure and define
strict service level criteria while
also making the Government
leaner.
This option would be the most difficult
to implement due to various reasons
such as lack of availability of private
players in the local market, resistance
from Ministries / employees against
outsourcing.
Based upon the analysis of the options and current circumstances, option 2 appears to the preferred
option. The broad modalities for implementing the concept are as follows:
Resources: - To initiate the project, a group of 1-2 resources from each Ministry/Agencies will be
identified. It is expected that over a period of time 100+ resources across the three levels (project
managers, IT managers and analyst) and multiple skills (technical platforms, change management,
project management, vendor management, etc) will be required. For expanding the ITSG, a private sector
company can be hired to provide IT resources. The following table provides the advantages and
disadvantages of directly engaging and outsourcing it to a private sector company.
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 155 Confidential
Table 25: Outsourced vs. Individual Recruitments
Individual Recruitments Outsourced Agency
Advantages
Cost Effective Ensures availability at all times
Cuts down the time required for following the procedures
of recruitment
One stop solution
Saves time and effort
Disadvantages
Risk of attrition
Delays in recruitment
Risk of not finding the right
manpower
Comparatively higher cost
Funding: - A small budget for setting up of the ITSG and its core team will be required. The operation
cost of the group would be centrally funded on behalf of Ministry/Agency depending on the IT projects.
Management: - The ITSG will be managed by Programme Management Office (PMO) being set up as a
separate initiative under e-Government directorate of MoC&IT
Initiative 2: Training Need Assessment and Preparation of Training curriculum
For the successful implementation of the e-Government program, it is imperative to ensure that the
government employees are provided training so as to re-orient them for customer centric service delivery
and educate them to utilize ICT for delivering the envisaged benefits to customers. An indicative list of
training areas is provided below:
Technology Management
Project Management
Change Management (including process reforms)
Financial Management
Soft Skills
However, it is imperative that a comprehensive training needs assessment exercise is undertaken to
ensure that suitable course curriculum is designed. In this regard, owing to the different needs of officials
at different positions / levels in the government hierarchy it is recommended that officials with similar
duties / requirements are clubbed together for training purposes. The various Target Groups for training
purposes are:
Table 26: Target Groups for Training
Groups Responsibilities
Group A Leadership( Ministers and DGs)
Group B Directors
Group C Senior Experts
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 156 Confidential
Group D Middle and Junior Level experts
Group E Support Functions Staff
Group F Clerical Staff
Group G Custodian Services
The training needs of these groups will be aligned to specific training areas and courses. A sample of the
same is provided as part of Annexure III.
The Training Needs Assessment aims to elicit the views of the target groups (Ethiopia employees at
various levels) addressing the capacity requirement of handling IT implementation in their own
functional domain. It also focuses on addressing the general skill levels and educational background of the
target groups. The TNA is to be administered across Ministries at every level. The nodal agency to drive
this will be MOCIT.
Training Need Assessment will provide inputs for preparation of training curriculum as well. Training
courses will be identified for the training areas used in assessing the employees. We feel to cater to
different levels of Government staff the training should be offered at three levels. The training levels are
described as in the following table:
Table 27: Training Levels
Basic Level The basic level courses would enable the participants to gain an
Understanding of the concepts and issues related to the topic
It would create an awareness of the range of possible approaches
and able to do the task in a simple environment, or with supervision
Intermediate Level The intermediate level courses would enable the participant to
undertake the task in a medium complexity environment.
It would also enable decision making and choose an approach where
several approaches are available.
Advanced Level
1.1.1
The advanced level courses would enable the participant an in-
depth understanding of the topic; it would enable training and
managing others performing the task
It would enable application of the learning in a complex
environment;
Advanced level may count towards professional or academic
qualifications (to be arranged with higher/further education
institutions).
The training courses for each of the levels are provided in Annexure III. 15 ICT training
labs in all the regions /Private Training Institutions/COE can refer to this course list and
supporting course content may be provided to implement a comprehensive training program for
Government employees of Ethiopia.
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 157 Confidential
Initiative 3: Strengthening of IT Training Infrastructure
Development of the Ethiopian Government Knowledge Management Portal
Ethiopian Government Knowledge Management Portal accessible to all employees through Woreda-net
should be established within the first year of strategy implementation. It is envisaged that this portal will
act as a one stop repository for documentation of different initiatives across the e-Government program to
facilitate dissemination and sharing of knowledge in the form of learning‘s and good practices. This is
expected to facilitate faster implementation while preventing wastage of effort and resources on
reinventing the wheel.
Towards this end, a Knowledge Management database needs to be developed to store all the information
and be accessible through the Knowledge Management portal. This would help in the creation of the
initial database but for the sustainability of this initiative and to increase its usefulness it is imperative
that the employees are encouraged to share their learning on the portal and utilize others‘ learning while
working on new projects. eLearning modules would also be developed as part of this initiative so that the
government employees can take up online learning at a time of their choice without compromising on
their allocated duties and responsibilities. The PMO being set-up as part of the e-Government strategy
will assist in defining the contours of this portal.
Enhancing the existing Regional Training Labs
The Regional ICT labs need to be equipped to train the employees in the courses provided in Annexure
III. It is imperative to ensure that adequate facilities and infrastructure is created to provide practical
hands on training at these labs as well as online training for government employees at remote locations.
Tie-up with the ICT community centers
The Community ICT Centers across different regions could also be mandated to provide training to the
employees in the regions. A tie up between MOCIT and the ICT community centers should be established
to provide training to the Government employees in the region. A business model should be established
for long term sustainability of such trainings through the ICT centers.
Partnering with Private Training Institutes
Partnership with Private Training institutes is meant to tap the availability of physical infrastructure and
other resources at these institutes. Another important dimension for IT Training is the access to the pool
of specialized IT Training experts at Partner Private Training Institutes. To start the initiative, a list of all
private Training Institutes operating in the region will be prepared and a study will be conducted to find
out their ability to provide training to Ethiopia staff.
Initiative 4: Conduct workshops, seminars and study tours
Organization of Seminars and Workshops
Organization of Seminars and Workshops will enable the knowledge and Skills transfer to a large number
of Government employees in shorter period of time. This will also bring a group of experts from diverse
experiences sharing them with a group of participants with different roles on a same platform. The
content of these seminars and workshops in form of audio, video and printed material will be shared on
knowledge gateway.
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 158 Confidential
As part of this initiative, it is proposed to conduct two seminars each year that will include key-note
address by 3 speakers on different emerging technologies across the globe. The seminar will also include
panel discussion on these emerging technologies where Government officials will get a chance to interact
with elite technology experts from across the globe and gain valuable experience.
In addition to these seminars, it is also proposed to conduct two workshops each year where leaders from
elite global IT corporations will create awareness amongst the CIOs and CTOs of all Ethiopia Ministries
about new technology trends that will enable in improving efficiency of IT functions in their respective
Ministries.
These seminars and workshops will support various IT initiatives in the region and help in creating a
knowledge management system and culture. They will not only enable sharing of information and content
but also create awareness amongst Ethiopia Ministries and its employees.
Study tours and exchange programmes for the government employees
Our experience suggests that Study tours and exchange programmes for senior government officials play
an effective role in facilitating a mindset change and to illustrate the fruits of success of the e-Government
program thereby building buy-in for the program.
It is proposed to select 5 senior Government officials every year for study tours and exchange programmes
that will spend a specified amount of time either with the Government of another country or attend
relevant courses at reputed places such as the Kennedy school of government, National School of
government etc. Such programs are also useful in building networks with other organizations to bring
good practices and leading technologies to Ethiopia.
Besides visits to leading countries and schools by Ethiopian government functionaries, foreign experts
could also be invited to visit Ethiopia to work on specific assignments on various IT initiatives in Ethiopia.
The idea here is two-fold: one to gain access to the knowledge of foreign experts in the short term and
second to develop skills and expertise amongst the Government staff which will act as a building block for
long term implementation of IT initiatives in the Ethiopia
Initiative 5: Standardization of structure of IT Department across the Ministries and
Agencies – for smooth & effective implementation of the priority projects.
For the effective implementation of the E-Government Strategy, it is important that a minimum capacity
be available, created in the various ministries and agencies. Further, a common organization structure
should also be prevalent across Ministries and agencies to facilitate smooth interaction and coordination
during implementation and monitoring of the priority projects. The recommended organization structure
is provided in the Governance Structure section of this document in section 3.
Initiative 6: Incentivise employees to build capacity
Encouragement to take up certification courses
Employees will be encouraged to augment their skills through third party certifications such as a
Microsoft certified systems engineer, a Cisco certified network associate, and a project management
professional etc. The encouragement will be in the form of leaves for preparation of exams, payment of
examination fees provided the employee clears the exam or any other support that can be provided by the
Ministry/Agencies.
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 159 Confidential
These certifications can be made mandatory for some promotions so as to encourage employees willing to
undertake certification courses. In addition to certifications they can be rewarded by their
Ministry/Agencies on excellent performance in the exams leading to certifications. However, to keep
checks and balances in place, a two member committee will be set up comprising of 1 representative each
from the Ministry/Agencies concerned and the MINISTRY OF COMMUNICATIONS & IT that will
evaluate the need of the certification for running the business of the Ministry/Agencies and future growth
of employee in the Ministry/Agencies in order to avoid any misuse of this policy by the government staff.
Encouragement to get trained on various courses provided by IT Academy
Letter of recommendations for promotions and salary increments will be linked to successful completion
of Trainings and also to employees who perform exceptionally well in IT training.
Letter of recommendation will be on following lines:
Best performer of the year in all IT training courses – Recommendation Letter by Prime
Minister
Maximum number of credits through IT training courses in a year – Recommendation Letter
by the Minister
Best Performer for each Ministry/Agencies – Recommendation Letter by DG
Best Performer of each sub-Ministry/Agencies – Recommendation Letter by IT head
Encouragement to become Trainers
High performing individuals will be provided an opportunity to take up Training of Trainer courses with
special benefits from their Ministry/Agencies. They will become Training Champions in their own
Ministry/Agencies and provide training to as many employees as possible. Such individuals will be eligible
for Recommendation from Minister / Prime Minister and also for out of turn promotions in exceptional
cases.
Encouragement to take up eLearning modules
The employees will be encouraged to take up eLearning modules for training where they don‘t have to
attend classes and can take up online assessment at designated evaluation centres to complete training
and earn credits for various courses.
Initiative 6: Establishment of Common Data Terminals (CDTs) in each Ministry/Agencies
Self-service data terminals will be set up at all the Ministries to promote usage of Technology and
familiarity with Computer Systems. This will enable the government staff to learn the use of systems and
build awareness amongst them about computer literacy. These data terminals will be used by government
employees who do not require computer use in their day to day functioning but would like to get familiar
and acquainted with IT environment.
These Data Terminals will be operated and run by an outsourced private company. This company will set
up a small training centre in each Ministry/Agencies which will be responsible for training
Ministry/Agencies staff to become end users of these common data terminals. The training managed by
the outsourced private company will be paid based on successful completion (PPP). Provided in Table
below is a indicative list of companies who can provide training to government staff in the Ethiopia
Ministries
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 160 Confidential
List of Companies (Illustrative only)
S.No. Name of the Company
1 Microsoft
2 IBM Corporation
5 Learning Tree
6 Microlearning
Development of skill sets amongst customers
This will be accomplished through the following initiatives:
Initiative 1: Promotion of ICT education and e-Government in Schools
Initiative 2: Marketing and awareness campaign
Initiative 3: Targeted training of businesses
Initiative 1: Promotion of ICT Education and e-Government in Schools
The course curriculum in schools must have modules on ICT education and e-Government. As Ethiopia
has a high proportion of its population in schools, this is the most sustainable way of creating capacities
amongst the customers. Moreover, children can help their parents in not only accessing services but also
in informing them of the introduction of new services. It must be ensured that every school has Internet
access facilities for children.
Initiative 2: Targeted Training for Businesses
Ethiopia has a high number of small and medium scale enterprises which may not have the resources to
train the staff in using online services, e-Procurement etc., It is therefore critical to run elaborate training
programs that will create awareness and capability amongst the businesses in using e-Services and
electronic channels. This will also make the industry in the country more competitive.
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 161 Confidential
II. Monitoring and Evaluation
The Government would need to keep a track on the progress and assure all stakeholders that the
Government‘s time and financial resources are being spent in an optimal manner. Taking into account the
unique challenges of e-Government services from their delivery modes and expectations perspectives, new
performance measures need to be developed to provide accountability for various e-Government efforts.
The Monitoring and Evaluation (M&E) mechanism must not only provide information about the
performance of Government policies, programs and projects. It must be able to identify what works, what
does not, and the reasons why. The real value of Monitoring and Evaluation doesn‘t come from just
conducting this exercise but from using the results of this exercise to improve performance of the e-
Government program.
The objective of the M&E framework is to enhance the effectiveness of the e-Government strategy by
establishing clear metrics to measures the success of the e-Government initiatives in delivering services to
its stakeholders.
The advantage resulting from the e-Government monitoring and evaluation is:
e-Government initiatives, most of the times lead to change in the process and delivery modes for the
service, hence it is essential to develop new performance measures for e-Government programs
The e-Government programs also require significant investment from Government. Some of these
cannot be measured in simple financial terms and need to be evaluated on such parameters
o Improvement of service standards,
o Increase satisfaction level of stakeholders
o Increased authenticity and security of information
Provide supporting evidence in policy making in the context of defining Government priorities
amongst the competing demands from citizens and society
Enhance transparency and support accountability relationships within and outside the Government
Recommendation
Implementation of the monitoring & evaluation framework will include
1. Establishment of the PMO to monitor the Programme implementation
2. Development and implementation of a Programme Monitoring Tool
3. Implementation of M & E framework by PMO consisting of:
• Project progress tracking measures
• Benefits measurement
• Impact assessment
4. Implementation of Government Transformation Index (GTI)
5. Implementation of Customer Satisfaction Index (CSI)
The Monitoring and Evaluation framework essentially has four components and the above mentioned
measures will facilitate the monitoring of the E-Government Strategy implementation through -
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 162 Confidential
1. Monitoring physical progress of the projects
2. Monitoring financial progress of the projects
3. Monitoring and evaluating the program outputs
4. Assessing impact of the program
Component 1: Monitoring physical progress of the project
Physical progress of the project will be tracked based upon implementation status of the project. Based
upon the current status of the project, indicators are required to be defined for tracking the progress of
the project in a particular stage. The indicators for the various stages along with a conformance index
would be defined to track the progress of the projects.
The e-Government Project stages broadly include:
1. Conceptualization stage: During this stage, project description document for the project is under
preparation. Indicators include:
a. Conducting requirement analysis for the project
b. Identifying a project leader and a team
c. Identifying services to be covered
d. Conducting stakeholder analysis
e. Risks and issues envisaged and a mitigation plan to address the same
2. Design and Approval Stage: After the project description document has been prepared and
Request for Proposal (RFP) for vendor selection has been released, the progress milestones for
tracking progress would include:
a. Appointment of an implementing agency
b. Definition of core services and service levels
c. Definition of target customer base
d. Appointment of a project leader and a team
e. Formulation of a plan for process re-engineering, if required
f. Formal approval of the project
3. Pilot and Implementation Stage: In this stage, the Project design would have been approved and
the funds released for implementation. The project tracking would be performed on meeting the
following milestones.
a. Status of Government Process Re-engineering
b. Channel coverage
c. Appointment of external vendor
d. Key milestones definition and adherence to them
e. Integration with other agencies/projects
f. Technology architecture
g. Adherence to defined standards and policies
h. Capacity Building plan and roadmap
Component 2: Monitoring the financial progress of the project
Measuring the financial progress of the projects is an essential component of the monitoring and
evaluation framework. The key indicators identified for tracking the financial progress include:
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 163 Confidential
Total financial outlay of the project
Total funds disbursed till date
Expenditure incurred till date
Committed expenses
Yearly allocation of funds
Yearly expenditure
Total percentage of funds utilized
Additional funds required
Component 3: Monitoring and evaluating the program outputs
Overall program outputs/outcomes would be measured along the parameters as envisaged in the e-
Government vision for the project. The indicators definition would be one of the key components of the
program design.
Component 4: Assessing impact of the program
Since feedback of the customers is essential for effective implementation of the Monitoring and
Evaluation framework and also for facilitating in mid-course correction steps, the Monitoring and
Evaluation framework proposes to measure customer satisfaction levels every year to provide
recommendations for improvement. This will also enable the Government of Ethiopia in assessing the
incremental improvements in services delivery and perceptions of the customer base as a result of the e-
Government initiatives.
This would include the following:
Customer satisfaction surveys
Report on the uptake of the envisaged services in the project
Outcomes
The following are the broad expected outcomes from the Monitoring and evaluation exercise.
Quarterly user satisfaction survey on e-Services( Scope of work for an external agency to conduct
baseline survey is provided in Annexure XII)
Monthly reports tracking project implementation
Monthly reports tracking citizen usage of electronic channels to interact with the Government
100% of projects to identify KPI/KPO as part of project design and parameters for measuring
success
100% of projects to be evaluated against KPI/KPO by independent agency
Award for e-Government programs in Ethiopia, instituted for departments/ individuals
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 164 Confidential
Monitoring and Evaluation – GTI and CSI
Government Transformation Index
Detailed methodology for calculation of Government transformation index is provided below:
Table 28: Government transformation index: key indicators
S. No. Overall government transformation index
(Assuming the maximum score to be 1000)
Rating Final score
1. Efficiency of service delivery H1 122
a. Increase in number of transactions handled H 47
b. Reduction in pending/backlog cases H 47
c. Integrated services provided to customers M 28
2. Quality of services provided H1 122
a. Accuracy of reports H 47
b. Relevant services provided to customers H 47
c. Reduction of redundant information in application forms M 28
3. Increase in the capacity of the Government
officials (awareness, knowledge, satisfaction)
H1 122
a. Increase in the awareness of the eGovernment initiatives H 55
b. Increase in the ICT usage of the officials H 55
c. Number of trained officials L 11
4. Grievance redressal system M1 73
a. Redressal of grievances within the defined service levels H 37
b. Measures taken to prevent high frequency grievances H 37
5. Accountability and reliability H1 122
a. Presence of audit trail activities M 33
b. Status tracking mechanism H 55
c. Ability to identify the owner of an activity / result M 33
6. Capacity to deliver services H1 122
a. eGovernment portal H 47
b. Number of common service centres H 47
c. Number of additional alternate channels created for
delivering services
M 28
7. Digitization of the Government operations H1 122
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 165 Confidential
a. Degree of data digitization of manual records M 61
b. Process reforms to deliver services through the
computerized system
M 61
8. Responsiveness M1 73
a. Timeliness of delivery of services H 46
b. Availability of MIS reports for decision making M 27
9. Private sector participation H1 122
a. PPP models established for delivery of services H 68
b. Number of private services delivery through CSCs M 41
c. Total number of services which are currently
being delivered by PPP operators
L 14
Note:
For the top-level parameters, the three ratings are H1 for high, M1 for medium and L1 for low
For the parameters, the three ratings are H for high, M for medium and L for low
The weights are indicative and have been assigned based on our experience of conducting similar
exercises in the past with various Governments and Government agencies
Maximum score is 1000
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 166 Confidential
Customer Satisfaction Index
Detailed Methodology for calculation of customer satisfaction index is given in Table 50
Table 29: Customer satisfaction index: key indicators
S.
No.
Overall customer satisfaction Index
(Assuming the maximum score to be 1000)
Rating Final
score
1. Awareness about the availability of eServices H1 119
a. Awareness of the e-Government portal, common service centres and
other new delivery channels
H 40
b. Extent of the customer awareness programmes H 40
c. Awareness of the customers about the online services H 40
2. Ease of accessibility of Government services H1 119
a. Adequacy of the number of delivery centres on which information is
available
M 32
b. Location of service touch points H 54
c. Reduction of redundant information in the application forms M 32
3. Usage of eServices H1 119
a. Number of transactions by the users on the alternate channels H 74
b. Number of visits for information versus transaction services M 45
4. Time savings of the customers for using eServices M1 71
a. Reduction in time taken to deliver the services H 27
b. Reduction the number of visits to avail the services H 27
c. Reduction in travel time in availing services M 16
5. Cost savings of the customers for using eServices H1 119
a. Cost of transactions for using services online versus offline H 74
b. Satisfaction with fee given for availing the services M 45
6. Quality of services - informational and transactional H1 119
a. Number of visits reduced to the agency counters H 46
b. Quality of helpdesk and telephonic support M 27
c. Hassle free mechanism for payment H 46
7. Relevance of services to the customers M1 71
a. Satisfaction with range of services provided H 45
b. Relevance of information asked for in application form(s) M 27
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 167 Confidential
8. Effectiveness of grievance redressal mechanism H1 119
a. Reduction in time taken for resolution of grievance H 46
b. Grievance redressal within the service levels H 46
c. Satisfaction of the quality of the grievance responses M 27
9. Ease of usage of the system M1 71
a. Services provided in Arabic and English L 5
b. Ease of navigation (number of 'clicks' required) M 16
c. Security of interface/ data transfer H 27
d. User friendliness of the applications M 16
e. Comprehensive help facility, guidelines for using the system L 5
10. Attitude towards Government M1 71
a. Customer perception towards Government: bureaucratic or customer-
centric
H 45
b. Customer perception on the Government working:
authoritative or participatory
M 27
Note:
For the top level parameters, the three ratings are H1 for high, M1 for medium and L1 for low
For the parameters, the three ratings are H for high, M for medium and L for low
The weights are indicative have been assigned based on our experience of conducting similar
exercises in the past with various Governments and Government agencies
Maximum score is 1000
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 168 Confidential
Survey for CSI and GTI
Objective
The objective is to assess the awareness and reach of the e-Government projects amongst the customers
and to determine satisfaction and impact amongst stakeholders and users of services offered by the e-
Government programme.
Approach
It is suggested that a bi-modular approach be adopted for conducting the assessment exercise. The first
module would involve qualitative in-depth interviews with key stakeholders and the second module would
consist of quantitative survey with the beneficiaries.
Target Respondents
Module 1 – Qualitative stakeholder assessment
Since it is necessary to conduct an assessment from various perspectives, the target respondents would
have to represent the stakeholders from both the service delivery as well as service access aspects. The
target respondents for this module have been suggested keeping in mind the above.
Agency officials involved in the delivery of eGovernment initiatives.
Agency officials not directly related to eGovernment.
Common service centres / point of service delivery – These could be located at post offices,
governorates etc. Interviews would be done with the person in charge of interaction with
beneficiaries as well as overall supervision of the e-service delivery at the centres.
Key influencers / opinion leaders – These would constitute people who are in a position to have
access to, are medium of information or influence the knowledge, attitudes and decisions at a
community /population sub group level. These could be community leaders or other accepted
motivators.
The qualitative module would help identify the parameters to be used for the quantitative module. Also it
would give a good understanding of the existing practices.
Module 2 – Quantitative
In this module, face-to-face quantitative interviews would be conducted with the stakeholders and
persons who are eligible as a beneficiary for a particular service. The questionnaire to be administered in
the quantitative survey would be based on the findings from the qualitative module and data gathered
from secondary sources like CIO surveys, similar studies by World Bank, etc. Once the first draft is ready,
a round of pilot interviews would be done. With the inputs gathered from this phase and a revision of the
questionnaire, the same would be administered to a larger sample. The scales to be used in the
questionnaire would be 5 point Likert scale. Information like awareness/satisfaction might be captured as
the top 2 / bottom 2 box score on the 5 point scale.
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 169 Confidential
III. Marketing and Awareness
A national awareness, education and marketing campaign is essential to ensure that potential customers
know about the e-Government services being rolled out, aspire to use them and are able to conveniently
use them. Raising awareness through informational and educational support is an ongoing activity, but
specially designed and timed campaigns will be needed, for example, to coincide with the launch of
specific services or to target a particular customer group. Such campaigns must serve the overall goal of
changing customer attitudes and, critically, their behaviour in favour of using e-Government services. A
common central strategy is needed to guide the Government-wide branding and marketing initiative
within which more focused and short-lived campaigns can be accommodated. In this regard it is
extremely important to
- Institutionalize marketing and awareness as part of the formal organizational structure of the
MoC&IT. The detailed structure and role is provided in Section 4 - Governance structure.
- Undertake Selection of a Marketing and PR agency to be involved throughout the program, so as
to effectively communicate developments at every stage to stakeholders( Scope of work of a
Marketing & PR Agency is provided in Annexure XII)
The summary and components of the overall marketing and awareness plan is presented in figure below
and explained in detail subsequently.
Figure 27: Marketing and Awareness Plan
Design of the marketing and awareness campaign will include 6 key components, each of which should be
defined and described in as much detail as possible during the planning and design stage:
Target market
Channel (media mix) selection
Essential to ensure that customers know about the eGovernment services being rolled
out, aspire to use them and are able to conveniently use them
Target
Segments
• Businesses
• Citizens
• Residents
• Visitors
• Government
Employee
Channels wrt
Target Segments
• Billboard
• Newspaper
• Social
Groups
• Internal
Communicati
on Newsletter
• Mosques
• TV
Messages
“It’s easy,
cheap,
beneficial and
smart to use
eGovernment
services”
“You can save
a lot of time
and
convenience
by renewing
your driving
license on-
line, just like
Mahmood.”
Timing
• Pre-launch
• Launch
• Year 1, 2 and
3
Development /
Approval Process
•
Empanelment
of an agency
• Creation of a
cross agency
marketing
Committee
• PR and
marketing
manager
under the
program
office
Feedback /
Review
• Data
Collection
• Analysis
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 170 Confidential
Message development based upon audience skills and education
Timing
Development/approval process
Feedback/review
In addition to the above, internal communication aimed at Government employees would also need to
form part of the marketing and awareness strategy
Target Market
One marketing medium cannot reach all segments of the diverse community that makes up Ethiopia.
Marketing campaigns do best when they define specific target markets and deliver a tailored marketing
programme for each market. At a finer level of granularity, within the residential segment there are
several specific segments of Ethiopian population that are traditionally harder to reach:
Elderly
Uneducated
Socially underprivileged
People with special needs
In the case of both specific residential and business segments, the country should consider using specially
targeted media. For example, a greater use of personal communications channels, such as outreach
through community organizations, working with opinion leaders, and developing word-of-mouth, may be
more appropriate to reach the elderly and non-Ethiopian communities. In contrast, methods such as
direct mail may be the best way to get messages across to segments of the business community.
Channel (Media) Selection
An appropriate communication and media channel mix is critical to ensure that everyone in the target
audience receives and understands the campaign messages. Given customer diversity, any awareness-
raising campaign that relies too heavily on just one medium or type of communication is unlikely to
achieve its goals. However, there could be services that might be targeted at only a small segment of the
society that would require targeted campaign through the channels and media of the choice of that
segment. E.g. Pensions is one service that will only be targeted at elderly people, so the campaign will
have to be directed through a medium that is most appealing to the old age segment. Scholarship service
should be directed towards students and the target area should be educational institutions.
Messages
The development of specific messages should be undertaken after the formal adoption of the e-
Government strategy and implementation plan that specifies the order in which services will become
available, the agencies affected, and other essential details. Assuming that the country adopts a ‗phased-
in‘ approach to implementing the e-Government services, the marketing plan will need to reflect the
planned sequence of operations. The marketing team within the Project Management Office should work
with advertising and public relations professionals to craft specific marketing messages, including both
Amharic and non-Amharic speaking customers. The development of messages should proceed in tandem
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 171 Confidential
with refinement of the overall marketing plan. Creative concepts and material should be tested in focus
groups for clarity, impact, ‗memorability‘ and other dimensions.
Specifically, decisions regarding the level of budget available for the marketing campaign will drive the
types of media that can be utilized, which will in turn drive the development of messages appropriate for
each medium. Working with experts to craft messages requires a disciplined time commitment. Work
should begin on the development of marketing messages at least 3 months prior to the desired launch of
the marketing campaign. The Country must also factor in the additional upfront-time required to select
the vendor(s).
Timing
It is crucial that an appropriate communication and media awareness programme is spread across the
various stages of the e-Government program, to achieve its goals; the marketing campaigns must
commence before the launch of the e-Government programme and must be sustained through the launch
and lifetime of the program.
Development / Approval Process
An explicit communications development/approval process will ensure that communications are
appropriate and consistent. To avoid confusion, it is particularly critical that the meaning of messages
delivered in the internal communications programme be congruent with those that are used in the
external marketing campaign. The marketing team (to be created as part of the MOCIT) will be
responsible for reviewing draft materials, contributing editorial suggestions, approving the final version
and ensuring that scheduled release dates are met. The Technical Committee should also review,
comment and approve on critical internal and external communications.
Feedback, measurement of effectiveness and improvement
For the Country‘s marketing and awareness programme, it is critical that feedback be sought and the
effectiveness of communications measured on a regular basis. This will require scheduling and
commitment to respond to constructive feedback and take action to address issues raised. These
assessment efforts will provide valuable insight into whether the generic messages are reaching the
intended audience and provide insights into ad hoc messages required in the near term. The feedback
mechanism envisaged will address two requirements. The first is quantitative, tracking plan against
execution and the delivery of messages to the intended stakeholder/audience. The second will focus on
qualitative data; stakeholder/audience understanding and engagement of issues generated through
communications. Collation of data will occur on an ongoing basis, and periodic, pre-planned reviews with
the marketing team will be scheduled. It is important that the communication plan be adapted and
subsequent behaviours demonstrate actions in response to feedback collected. This data collection
responsibility can be part of the mandate of the Monitoring and Evaluation team of MOCIT.
Internal Communication
The Country‘s internal communication about the e-Government programme represents the best chance to
create a common frame of mind for the diverse group of employees who make up the government family.
Communications to employees will be concentrated during the development/pre-launch phase, but will
continue throughout the implementation of the e-Government programme.
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 172 Confidential
An explicit marketing objective relates to employees:
Obtain 100% awareness and understanding of the e-Government services among Government
employees
To achieve this objective, Ethiopia must utilize formal and informal communications. The management of
the overall e-Government programme must collaborate with other agency officials to build consensus
regarding the need for change and the expected benefits. The e-Government programme management
must also communicate project activities to all stakeholders with an explanation regarding the
organizational and personal benefits to be attained.
There will be 4 primary components of the internal communication programme:
Internal stakeholder/audience identification
Channel selection
Message development
Feedback, measurement of effectiveness and improvement
Marketing and Awareness Brief
Each of the above elements has been summarized through the marketing and communication brief
presented below, which can also be used as a brief for the appointment of the advertising and marketing
agency. A detailed marketing and awareness strategy document is also provided as Annexure IV to the
report.
Table 30: Marketing and Awareness Brief
Project e-Government Strategy for Ethiopia
Agency To Be Decided
Background
Governments around the world are leveraging advances in Information and Communication
Technologies (ICT) to enhance their service delivery mechanism to improve citizen satisfaction
and gain competitive advantage over other nations to attract investments
As a part of this programme, major projects such as the Woreda Network and National Data
Centre have been launched and should be marketed
The impetus of the Country on leveraging ICT has resulted in a high degree of intra-ministerial
computerization and a good ICT infrastructure
The initiative on the ICT Community Centres to educate and create ICT awareness across the
Country should be highlighted
The Country has also set-up a High Committee and Technical Committee to provide direction and
decision to developing and implementing a comprehensive e-Government strategy
The e-Government strategy proposes providing customer value through aligning Government
across the lifecycle events of the citizens, residents and businesses
The strategy proposes to deliver most of the Government services in an integrated manner
through multiple channels
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 173 Confidential
Benefits offered under the e-Government programme for which the marketing and
awareness strategy needs to cater:
Convenience
Efficiency
Reach
Value for money
Value proposition
―It‘s easy, economical, beneficial and smart to use e-Government services‖
―You can save a lot of time and convenience by renewing your driving license on-line, or apply
Passport online or File Taxes‖
Marketing and Awareness objective
The business objectives should aim for the following:
Create awareness
Build credibility for the e-Government strategy
Drive higher participation across the various target segments
Highlight the impact of the e-Government strategy
The communication objective is as follows:
Pull rather than push communications strategy
We have to establish that e-Government strategy can actually make a difference to the customers in
Ethiopia
Drive confidence amongst businesses - Ethiopia is a good place to invest
E-Government is about participatory Government
Target Audience: Who are we talking to? What do these people currently think of our programme?
What is the desired perception?
At a finer level of granularity, within the residential segment, there are several specific segments of the
Country‘s population that are traditionally harder to reach:
Elderly
Uneducated
Socially underprivileged
People with special needs
Within the business community, there may be particular groups that will require special targeting. For
example, if the Country launches a web application that enables applications for company registrations
process to be done online, it may be necessary to market this service to the relevant users. In the case of
both specific residential and business segments, the Country should consider using specially targeted
media. For example, a greater use of personal communications channels, such as outreach through
community organizations, working with opinion leaders, and developing word-of-mouth, may be more
appropriate to reach the elderly communities. In contrast, methods such as direct mail may be the best
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 174 Confidential
way to get messages across to segments of the business community.
Current Thinking:
Diverse views about what is eGovernment and the benefits
Overall OK with the objective of the programme
Certain pessimism/scepticism within the customer segment in the use of electronic service
What we are trying to achieve is far too down-the-line
Desired Thinking:
The programme is useful
Participation is important
The programme would not wait for anyone
There are many who would benefit
Success of the programme is not in its design but in the collective participation in its
implementation
What is the hot button that we can leverage to influence our target audience?
The programme is already underway and people are benefiting
It is only a start, but the best is yet to come
People who participate now will benefit later
What is the key thought that marketing and advertising has to communicate?
Participating is key to success
e-Government is about services and about customers
eGovernment is a key strategic priority
Act now or repent later – as an industry and as a nation
Call to action?
Strong call-to-action on the desired strategy
Large no. of responses
Possible communication vehicles
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 175 Confidential
One marketing medium cannot reach all segments of the diverse community that makes up the
Country. Marketing campaigns do best when they define specific target markets and deliver a tailored
marketing programme for each market. Prior experience with eGovernment awareness campaigns
indicates that billboards and traditional media – such as radio and newspaper would be most cost
effective, but alone will not be sufficient to penetrate the target market with news of the e-Government
services. We also recommend presentations at schools, community organizations and events to
supplement billboards and traditional advertising. Additionally we could also look at Public places for
distribution of flyers and leaflets. These marketing outlets will provide an opportunity for the Country
to tailor specific messages to individual communities.
Execution considerations
Value for advertisement spend
Summary of the Marketing and Awareness Plan
The objective of the marketing and awareness strategy would be met through the following:
Initial burst of advertisement in dailies with the launch of programme stressing upon the delivery
channels
Sustained public relation efforts aimed at covering the benefits and recipients
Branding of eGovernment strategy for the Country
Documenting the benefits and outcomes of selected agency projects through the preparation of
advocacy videos that can be circulated among the various interest groups
Circulation of bi-monthly progress reports among all internal stakeholders
Preparation and publication of a quarterly event planner for wider circulation through national
dailies. This can also be used to call for applications under various strategies
Message
The development of specific messages should be undertaken after the formal adoption of the e-
Government strategy and implementation plan that specifies the order in which services will become
available, the agencies affected, and other essential details. Assuming that the Country adopts a ―phased-
in‖ approach to implementing the e-Government services, the marketing plan will need to reflect the
planned sequence of operations.
The marketing team within the project office should work with advertising and public relations
professionals to craft specific marketing messages, including both Amharic and non- Amharic speaking
customers. The development of messages should proceed in tandem with refinement of the overall
marketing plan. Creative concepts and material should be tested in focus groups for clarity, impact,
―memorability‖ and other dimensions.
Specifically, decisions regarding the level of budget available for the marketing campaign will drive the
types of media that can be utilized, which will in turn drive the development of messages appropriate for
each medium.
Working with experts to craft messages requires a disciplined time commitment. Work should begin on
the development of marketing messages at least three months prior to the desired launch of the marketing
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 176 Confidential
campaign. The Country must also factor in the additional upfront time required to select the vendor(s).
Table 23 summarises the message development component.
Table 31: Message Development
There are a number of generic messages that can be pre-planned, prepared and pre-approved. These will
serve to raise customer‘s awareness, and to answer the basic questions that they are likely to have about
the e-Government Strategy. Suggested subjects for these generic messages are listed below.
Communication of the rationale
What is the vision for e-Government programme
Why do we need an e-Government strategy
What are the major benefits?
Establish Awareness of the Project
What is the e-Government programme about
Sponsorship – who is the champion?
Structure & organization
Implementation approach
Implementation timeline
Integration with other Country initiatives
What will change?
What will stay the same?
What has happened so far?
Periodic update on progress
Challenges • The timeline for key implementation milestones may change so mapping key
messages to it is a challenge
• Working with authors to craft messages; requires disciplined time commitment
• Tracking and monitoring of messages distributed and to whom
• The timeline for key implementation milestones may change so mapping key
messages to it is a challenge
• Working with authors to craft messages; requires disciplined time commitment
• Tracking and monitoring of messages distributed and to whom
Challenges • The timeline for key implementation milestones may change so mapping key
messages to it is a challenge
• Working with authors to craft messages; requires disciplined time commitment
• Tracking and monitoring of messages distributed and to whom
• The timeline for key implementation milestones may change so mapping key
messages to it is a challenge
• Working with authors to craft messages; requires disciplined time commitment
• Tracking and monitoring of messages distributed and to whom
Actions • Proactive planning of generic messages and build „database‟ of items ready
for publication
• Clearly assign “owners” for content development of messages
• Conduct detailed planning on a rolling 3-4 month basis to reflect shifting
events timeline
• Proactive planning of generic messages and build „database‟ of items ready
for publication
• Clearly assign “owners” for content development of messages
• Conduct detailed planning on a rolling 3-4 month basis to reflect shifting
events timeline
Actions • Proactive planning of generic messages and build „database‟ of items ready
for publication
• Clearly assign “owners” for content development of messages
• Conduct detailed planning on a rolling 3-4 month basis to reflect shifting
events timeline
• Proactive planning of generic messages and build „database‟ of items ready
for publication
• Clearly assign “owners” for content development of messages
• Conduct detailed planning on a rolling 3-4 month basis to reflect shifting
events timeline
Message
Development
Message
Development
• Work with the implementation team to track key milestones and likely timing
• Identify generic messages in advance, plan and prepare drafts for publication
• Work continuously with the implementation team to anticipate
communication/message requirements
• Manage detailed communications plan and work with experts to determine
content and format
• Work with the implementation team to track key milestones and likely timing
• Identify generic messages in advance, plan and prepare drafts for publication
• Work continuously with the implementation team to anticipate
communication/message requirements
• Manage detailed communications plan and work with experts to determine
content and format
Message
Development
Message
Development
• Work with the implementation team to track key milestones and likely timing
• Identify generic messages in advance, plan and prepare drafts for publication
• Work continuously with the implementation team to anticipate
communication/message requirements
• Manage detailed communications plan and work with experts to determine
content and format
• Work with the implementation team to track key milestones and likely timing
• Identify generic messages in advance, plan and prepare drafts for publication
• Work continuously with the implementation team to anticipate
communication/message requirements
• Manage detailed communications plan and work with experts to determine
content and format
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 177 Confidential
Achievement of milestones and celebrations of success
Changes in timeline, scope and/or approach
Differentiation of this project from others
Why will this one succeed?
Lessons incorporated from other projects
Impact on the Government’s functioning
How will we operate differently?
How will this be perceived by the ―outside‖ world?
Impact on the Individual Customer
What will change for me?
Generic, pre approved messages will only partially meet the information requirements of the Country‘s
employees. Ad hoc messages may also be needed as the dynamics and events change through the
implementation lifecycle. Ad hoc messages will be needed to address key developments, issues arising and
achievements across all facets of the e-Government programme. To capture these, the project office and
the e-Government implementation teams in various agencies will need to remain in close contact.
General Awareness
Making a noticeable difference in the Country‘s quality of customer service and increasing public access to
Government information and services are intrinsic drivers of the e-Government Strategy. The judicious
use of the modern customer service technology that will be deployed in the common channels being
created will help to enhance the Country‘s image in the public eye. While there may be a strong tendency
to begin publicity early, the best approach will be to delay the campaign until sufficient infrastructure is in
place to handle a sudden influx of telephone calls, emails, and service requests. In this manner, the
Country will avoid the problem of building expectations that are then unrealized.
Table 32: General Awareness Campaign Overview
Implementation Stage Audience Primary Themes
Pre-launch (Build-up) Government Employees Existing services and
eGovernment strategy
& plan
Launch All Target Segments
(Citizens and Residents,
Businesses, Visitors,
Employees)
Services and channels
being launched
First year of full
implementation All Target Segments
(Citizens and Residents,
Businesses, Visitors,
Employees)
Achievements
Additional services and
channel enhancements
made available
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 178 Confidential
Second year of full
implementation All Target Segments
(Citizens and Residents,
Businesses, Visitors,
Employees)
Achievements so far
Additional services and
channel enhancements
made available
Showcasing e-
Government
programme
internationally
Third year of full
implementation All target segments
(Citizens and Residents,
Businesses, Visitors,
Employees)
Achievements so far
Additional services
made available
Showcasing e-
Government
programme
internationally
Government employees will continue to be responsible for delivering services to residents and businesses.
Employees interface with the public on a daily basis and their understanding of the e-Government
services is a critical success factor. Moreover, if employees are appropriately informed, they can serve as
ambassadors, helping to spread the word about the new services. The general rule of ―tell them early, tell
them often‖ should be observed with truthful, straightforward, consistent communications to all
Government employees.
It is critical that Country‘s management is fully educated about and supportive of, the e-Government
programme. Government employees will take their cue from leadership.
Management‘s approach and attitude about the new system will filter to Agency personnel where the new
system actually interfaces with the public. If the management does not show its commitment to the e-
Government programme, employees will be reluctant to support the new system, eventually resulting in a
lower level of customer service and satisfaction with the system.
Development / Approval Process
An explicit communications development/approval process will ensure that communications are
appropriate and consistent. To avoid confusion, it is particularly critical that the meaning of messages
delivered in the internal communications programme be congruent with those that are used in the
external marketing campaign. The marketing team will be responsible for reviewing draft materials;
contributing editorial suggestions, approving the final version and ensuring that scheduled release dates
are met. MOCIT should also review and comment on critical internal communications. Table 25 below
summarizes the development/approval process.
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 179 Confidential
Table 33: Development / Approval Process
Feedback, measurement of effectiveness and improvement
For the Country‘s internal communications programme, it is critical that feedback be sought and the
effectiveness of communications measured on a regular basis.
This will require scheduling and commitment to respond to constructive feedback and take action to
address issues raised. These assessment efforts will provide valuable insight into whether the generic
messages are reaching the intended audience and provide insights into ad hoc messages required in the
near term.
The feedback mechanism envisaged will address two requirements. The first is quantitative, tracking plan
against execution and the delivery of messages to the intended stakeholder/audience. The second will
focus on qualitative data; stakeholder/audience understanding and engagement or issues generated
through communications.
Collation of data will occur on an ongoing basis, and periodic, pre-planned reviews with the marketing
team will be scheduled. It is important that the communication plan be adapted and subsequent
behaviours demonstrate actions in response to feedback collected.
Challenges • Smart selection of message contributors
• Keeping to development and delivery schedule
• Managing a fast path through the process in the case of extraordinary ad hoc
communications
• Smart selection of message contributors
• Keeping to development and delivery schedule
• Managing a fast path through the process in the case of extraordinary ad hoc
communications
Challenges • Smart selection of message contributors
• Keeping to development and delivery schedule
• Managing a fast path through the process in the case of extraordinary ad hoc
communications
• Smart selection of message contributors
• Keeping to development and delivery schedule
• Managing a fast path through the process in the case of extraordinary ad hoc
communications
Actions • Develop proposed process and seek agreement
• Communicate and educate Champion and implementation team
• Marketing Team within the Programme Office will instigate and manage the
process
• Develop proposed process and seek agreement
• Communicate and educate Champion and implementation team
• Marketing Team within the Programme Office will instigate and manage the
process
Actions • Develop proposed process and seek agreement
• Communicate and educate Champion and implementation team
• Marketing Team within the Programme Office will instigate and manage the
process
• Develop proposed process and seek agreement
• Communicate and educate Champion and implementation team
• Marketing Team within the Programme Office will instigate and manage the
process
Development /
Approval
Process
Development /
Approval
Process
• Creation of a robust yet efficient process for reviewing communications
• Managing the development/editorial process to ensure appropriate content
• Monitoring consistency of messages
• Facilitating timely release of messages
• Ensuring appropriate channel selection and delivery
• Creation of a robust yet efficient process for reviewing communications
• Managing the development/editorial process to ensure appropriate content
• Monitoring consistency of messages
• Facilitating timely release of messages
• Ensuring appropriate channel selection and delivery
Development /
Approval
Process
Development /
Approval
Process
• Creation of a robust yet efficient process for reviewing communications
• Managing the development/editorial process to ensure appropriate content
• Monitoring consistency of messages
• Facilitating timely release of messages
• Ensuring appropriate channel selection and delivery
• Creation of a robust yet efficient process for reviewing communications
• Managing the development/editorial process to ensure appropriate content
• Monitoring consistency of messages
• Facilitating timely release of messages
• Ensuring appropriate channel selection and delivery
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 180 Confidential
Table 34: Feedback, measurement of effectiveness and improvement
Figure below illustrates the continuous cycle of data collection, followed by review and analysis,
adjustment to the communications plan, incorporating feedback from stakeholders, and refined execution
of the communications plan.
Figure 28: Continuous Improvement in Communications
Audience skills and education
Raising awareness about an issue or topic does not necessarily lead to lasting changes in attitudes and
behaviour, especially when people also need specific skills they may not already posses. For awareness
campaign to achieve long-term benefits it is also necessary to consider how to provide a specific customer
group with the skills and incentives to change. Thus, changing behaviour may also mean, for some
Challenges • Leveraging the Kingdom‟s communications network to gather and channel
feedback centrally
• Reacting appropriately and speedily to feedback
• Showing that the eGovernment team listens and hears
• Leveraging the Kingdom‟s communications network to gather and channel
feedback centrally
• Reacting appropriately and speedily to feedback
• Showing that the eGovernment team listens and hears
Challenges • Leveraging the Kingdom‟s communications network to gather and channel
feedback centrally
• Reacting appropriately and speedily to feedback
• Showing that the eGovernment team listens and hears
• Leveraging the Kingdom‟s communications network to gather and channel
feedback centrally
• Reacting appropriately and speedily to feedback
• Showing that the eGovernment team listens and hears
Actions • Develop standard approaches for obtaining qualitative data through focus
groups and on site feedback
• Develop standard approaches for assessing quantitative data from plan
execution, distribution, questionnaires, etc.
• Schedule periodic reviews with the eGovernment team
• Develop standard approaches for obtaining qualitative data through focus
groups and on site feedback
• Develop standard approaches for assessing quantitative data from plan
execution, distribution, questionnaires, etc.
• Schedule periodic reviews with the eGovernment team
Actions • Develop standard approaches for obtaining qualitative data through focus
groups and on site feedback
• Develop standard approaches for assessing quantitative data from plan
execution, distribution, questionnaires, etc.
• Schedule periodic reviews with the eGovernment team
• Develop standard approaches for obtaining qualitative data through focus
groups and on site feedback
• Develop standard approaches for assessing quantitative data from plan
execution, distribution, questionnaires, etc.
• Schedule periodic reviews with the eGovernment team
Feedback and
Measurement of
Effectiveness
Feedback and
Measurement of
Effectiveness
• Develop and facilitate feedback mechanisms
• Capture, document and channel feedback and issues raised as appropriate for
resolution, action planning, further communication
• Develop methods of measuring effectiveness of communication activity, both
quantitative and qualitative
• Conduct scheduled reassessments of communication activity and build
amendments to plan
• Develop and facilitate feedback mechanisms
• Capture, document and channel feedback and issues raised as appropriate for
resolution, action planning, further communication
• Develop methods of measuring effectiveness of communication activity, both
quantitative and qualitative
• Conduct scheduled reassessments of communication activity and build
amendments to plan
Feedback and
Measurement of
Effectiveness
Feedback and
Measurement of
Effectiveness
• Develop and facilitate feedback mechanisms
• Capture, document and channel feedback and issues raised as appropriate for
resolution, action planning, further communication
• Develop methods of measuring effectiveness of communication activity, both
quantitative and qualitative
• Conduct scheduled reassessments of communication activity and build
amendments to plan
• Develop and facilitate feedback mechanisms
• Capture, document and channel feedback and issues raised as appropriate for
resolution, action planning, further communication
• Develop methods of measuring effectiveness of communication activity, both
quantitative and qualitative
• Conduct scheduled reassessments of communication activity and build
amendments to plan
Data Collection
Reporting /
Management
Review
Adjustment to
Communication
Plan
Feedback from
stakeholders
Execute
Communication
Plan
Continuous Improvement
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 181 Confidential
potential customers, the need to upgrade skills, so that the awareness campaign should be linked to
educational and training opportunities whoever provides these (e.g. the public sector, the private sector
and possibly also NGOs) and however provided (e.g. traditionally, through intermediary help, or through
eLearning courses). Existing educational offers must therefore be mapped to see whether adequate
training and support is available and if not, new offers may need to be provided or encouraged in order to
fulfil the needs of the campaign. An excellent campaign could fail if it convinces customers of the
desirability of using Government services but leaves them without the necessary skills.
Advertising Revenue
There is also an opportunity for the Country to earn revenues by charging other organizations to advertise
on the e-Government portal and the common services centres and other channels being set-up. This
revenue could then be used to defray the advertising costs to build awareness for the e-Government
Services.
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 182 Confidential
IV. Standards and policies
Introduction
During the implementation of the e-Government strategy, a number of the proposed eGovernment
initiatives will involve development of new systems for provisioning online services.
These new systems, deployed at either a central or a local agency level, are developed with specifications
and solutions that match the goals and tasks relevant to a particular department. However, taking the big
picture into account, it is important for any such initiative to give adequate attention to surrounding
Government institutions and their allied ICT initiatives so as to enhance the compatibility,
interoperability and efficiency while also eliminating redundancy.
It is important for all Government agencies to make a concerted effort to implement eGovernment
initiatives in a collaborative manner which, in addition to meeting the specific needs of the owner
agencies, are also in line with the overall Management practices
ICT usage
Technical and security issues
Web services provisioning
Data and information exchange
Scalability and Interoperability
Summary of the Current Scenario
Based on Stakeholder Assessment the various standards and policies that are already implemented or
under progress include
Table 35: Regulations, Policies, Guidelines and Standards
Regulations/Laws
S.No Name Status
1. National Electronic Transaction Law
Draft document has been
prepared
2. National Data Protection Law
completed(draft) document has
been prepared
3. e-Commerce Law.
completed(draft) document has
been prepared
4. e-Signature Law.
Ongoing
5. Computer Misuse and Cyber Crime Law.
completed(draft) document has
been prepared
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 183 Confidential
Policies/Framework
S.No Name Status
1. National Public Key Infrastructure (PKI) Framework.
Ongoing
2. National Enterprise Architecture Framework for
Ethiopia
Ongoing
3. Government Information Systems Interoperability
Framework /Standard (e-GIF).
On ratification process
Standards
S.No Name Status
1. Keyboard Layout, Typeface and OCR standard Completed, ratified and implemented
2. Critical Localization Standard for Ethiopic languages
such as Amharic, Oromifa, Tigrigna, Afaraf and
Somali.
Completed, ratified and implemented
3. ICT Accessibility Requirement Standard for People
with Disability Information Exchange Standard.
Completed and on the approval
process
4. ICT Transliteration Standard Completed and on the approval
process
5. Ethiopic Soundex (Phonetic Matching) Standard.
Completed and on the approval
process
6. ICT Content Digitization Standard.
On the Approval Process
7. Information exchange standard completed and waiting for approval
8. E-Commerce Standard.
on going
9. Ethiopic Collation standard.
On the Approval Process
10. Contractual Standard Conditions for ICT
Services/Projects.
Completed
11. Business Process Re-engineering Completed
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 184 Confidential
Guidelines
S. No Name Status
1. Standard Evaluation and Selection guideline for ICT
Hardware and Software.
Completed,
2. Certification Guideline for ICT Professionals,
Consultants and Trainers.
Completed
3. ICT Project management Guideline.
Completed
Recommendation:
There are various standards and policies which need to be laid down for the e-Government strategy.
Following are the suggested measures for implementing Standards and guidelines required for effective
implementation of the strategy -
1. Implementation of Standards through a Technical Committee specifically created, comprising
Government, Academic, Industry and Outside experts( Section 4- Governance Structure)
2. Engage an external agency for design and implementation of the Standards/Policies
3. Implementation of the existing Enterprise Architecture Framework, E-Government Interoperability
Framework and Public Key Infrastructure
4. Adoption of Cyber laws for effective implementation of e-Services
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 185 Confidential
The policies/standards/guidelines that help to support the implementation of various e-Government
initiatives are provided in the figure below:
Figure 29: Policy/Standards/Guidelines Framework
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 186 Confidential
The policies/standards/guidelines that MOCIT needs to develop for further implementing e-Government
is provided in the following tables. The year-wise implementation of the Standards and Policies has
been designed keeping the following considerations:
Current e-readiness of the Ministries/Agencies in Ethiopia
Alignment with the Overall e-Government Strategy Dimensions and Components
Initiatives already undertaken in terms of laws, policies and standards
Phasing is also based on priority of the Standards/Policies/Guidelines, so as to facilitate effective e-
Government implementation.
It has been envisaged that the Policies/Standards/Guidelines framework should be completed within
the next 3 Years for timely implementation of e-Government in the Country.
Figure 30: Implementation Plan for Standards and Policies
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 187 Confidential
V. Public Private Partnerships (PPP)
Introduction
A Public Private Partnership, or PPP, involves government and private sectors working together to deliver
infrastructure or services that are traditionally provided by government. It involves private financing,
construction and management of key infrastructure with the primary objective of improving public
services. PPPs focus on service outcome, not assets.
PPP mode of project implementation is a necessity for the following reasons:-
To enhance public services management and expedite the implementation
To accelerate infrastructure provision and bridge the huge infrastructure gap
To provide opportunity to local private sector to gain experience and work with the government
To address national inequalities
To overcome barriers of social, economic and geographical isolation
To increase access to information and education
To enhance the government capacity to manage the relationship with the private partner as well as
manage the changes associated with the shift from traditional to digital paradigm.
PPP in Ethiopia
PPP forums have been established by the Ethiopia Chamber of Commerce and the previously combined
Ministry of Trade and Industry for addressing PPP related issues. For the dialogue platforms, the forum
promotes and strengthens the existing public-private platforms (PPP) in the regions and at federal level.
Presently, the Ministry of Trade and Industry organizes regular forums with the Chamber of Commerce
both at national and regional levels. Following are the two forums that have been established to foster
public and private partnerships:-
Public and Business Community Joint Consultation Forum
Objective: To create awareness concerning government development vision; to provide support for
business communities; to discuss and comment on draft business and investment laws and regulations; to
Basic principles for PPP
PPPs are concerned with services, not assets
o The government does not need to own infrastructure to deliver services
PPPs are a procurement option, not a novel method of developing public infrastructure
o PPP policy sits alongside other procurement methods – i.e. conventional, outsourcing,
leasing etc.
o Suitable to some public projects, not all projects
PPPs are not „new money‟
o Service outputs must be paid for, whether directly (e.g. user charges) or by appropriation
o Must therefore be affordable – either to users (user charges) or to the budget
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 188 Confidential
discus on implementation problems of laws and regulations and to create smooth relationship between
government and business community.
Current activities: Creating common understanding concerning government development policies/vision:
giving ideas and opinion before the issuance of business laws; creating an enabling environment for
business communities; provide suggestions/comments by identifying implementation problems and
finding solutions for the same.,
Addis Ababa Investment and Industry Development Consultation forum
Objective: To create enabling environment for investment and industrial development based on
transparent and free market economic policy; to ensure fast and sustainable industrial development by
creating common understanding and coordination between government and the business
communities/partners; to promote development endeavor of those actors which have key roles in urban
development;: to improve quality and price of industrial products by integrating all development
partners.
Current activities: Finding ways and means to promote the investment and industrial development of
Addis Ababa City Government; improving industrial development by providing necessary support;
conducting studies to solve development problems; working together with investors to introduce large
investment opportunities; and providing training to improve efficiency of human resources.
Besides the above two forum established by the government, some of the successful PPP initiatives in
Ethiopia in the ICT sector are discussed below:
ICT Community Centres
92 ICT Community centers are currently operating across Ethiopia. These centers are mainly driven by
the local communities with support from the ICTAD. A laudable feature of this initiative is the self
sustainable nature of the ICT community centers – while the initial funding has been provided by ICTAD
for one year, these centers need to manage their operations after the first year on their own. Most of these
centers are generating enough revenues to meet their operating costs by providing services such as
training facilities, internet access facilities, photocopying and printing etc. A comprehensive Monitoring
and Evaluation Framework and a repository of learning‘s of the various centers needs to be created to
ensure that this initiative can be expanded and improved. The use of these centers for the delivery of e-
Services will further strengthen the business case of these centers by providing an additional revenue
stream.
Unified Billing System (UBS)
The Unified Billing System (UBS) is one of the flagship projects in ICT sector that is being implemented
on the Build Own Operate Transfer (BOOT) model. The Private partner shall Build Own and Operate
Utility Bill collection centers and will eventually transfer the entire system to the Government at the end
of the PPP contract. 40+ UBS centers are planned to be established as part of the project, to act as one
stop shops for payment of bills for power, water and telecom. It is recommended that these centers may
be upgraded to offer all the e-Services as Common Services Centers after the pilot has been successfully
accomplished.
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 189 Confidential
ICT business incubator in Ethiopia
Incubation Centers have been setup by the ICTAD to encourage and support entrepreneurs of Ethiopia in
ICT related ventures. Currently there are 4 Incubation centers which are supporting 47 startup
companies. Following are the main objectives of the incubation centers:-
Provide shared Workspace and Facilities
• Facilities typically include conference rooms, phone system and broadband connectivity,
security, etc.
Provide Business Advisory Services
• Basic assistance provided by incubator staff (business plan)
• Mentoring/coaching by staff and outside entrepreneurs
• Access to external network of service providers (e.g.,accountants, lawyers), plus
universities, tech parks, private enterprises, etc.
Ensure Access to Capital
• in-house seed equity or small loan fund on a case to case basis
• Affiliated angel investors and venture capital funds
• Relationships with banks
The main focus of the Incubation centers is to create strong companies that can sustain themselves after a
period of initial assistance. Government provides policy and financial support, but does not run the
incubator directly. ICTAD Project contributes significant resources to develop the incubator.
PPP opportunities for implementation of the e-Government program and
recommendations for their realization
Table 36: PPP opportunities and Recommendations
S.No. Area Recommendations
1. Program and project
implementation
1. Ethiopian Telecommunication Company could partner the
e-Government program in roll out of various channels for
services delivery. E-Government implementation across the
country will help the company in increasing its revenues
through increased usage of its ICT infrastructure. ETC
could in turn contribute by lowering bandwidth and mobile
tariffs / making SMS and calls to some of the pre-
designated service delivery numbers free etc..
2. Banks such as the Bank of Ethiopia could develop the
payment gateway and charge a nominal fee from the
government for the use of payment gateway. This will
benefit the bank as number of transactions through its
payment gateway would increase. Furthermore, use of debit
cards and credit cards issued by the bank is likely to
increase once payments for government services are
facilitate electronically. Another way the banking sector
could contribute is by the way of facilitating payment of fees
for government services using their ATM machines and
branch outlets for free / nominal fees.
3. Feasibility of all projects for private partnership must be
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 190 Confidential
S.No. Area Recommendations
examined during the design stage and in case the same is
established then that PPP should be preferred mode of
implementation. This should be done in a manner to ensure
that the private sector brings in the initial investment and
runs the project and recoups its investment through levy of
user charges / transaction fees. This will ensure that the
risk of the project is shared with the private sector,
efficiencies of the private sector are leveraged and the
model is sustainable. The provision of viability gap funding,
where-ever possible (to provide subsidies / one time funds
for making PPP feasible) should also be explored where-
ever required.
4. The government could develop course curriculum aimed at
increasing computer literacy and to train people in using e-
Services while the private educational institutes could take
the onus of imparting the courses at a reasonable cost.
2. Generation of funds and
resources for the
implementation of the e-
Government program
1. The government could allow the private sector to utilize its
service delivery channels such as the portal and the Citizen
Service Centers for advertising their products and services.
This could become a steady revenue stream for the e-
Government program while the companies could gain trust
and goodwill due to their association with a program of
national significance.
2. The industry in general could provide funds as well as used
computers as part of their Corporate Social Responsibility
(CSR) initiatives so that the same may be used at CSCs and
training centers.
3. Encouragement to
entrepreneurs for setting
up companies in the ICT
sector
1. The number of ICT community centers needs to be
increased from the present 65 for a better coverage of the
population. Furthermore, once these centers are allowed to
offer Services as Common Service Centers their revenue
stream would also grow. Entrepreneurs, individuals and
companies should be made aware and encouraged to take
up the establishment of new ICT community centers.
2. The infrastructure and funds available at the 4 ICT
incubation centers that are currently operational needs to
be enhanced so that they can offer better services to the
entrepreneurs. This number also needs to be increased to at
least 10 incubation centers spread across the country for
better results.
Strategies to promote ICT development through Public Private Partnerships
Following are a brief of illustrative strategic initiatives to enable the expansion and growth of the ICT
sector and the Private sector companies as a whole using PPP as a tool.
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 191 Confidential
Revise Policies to attract Investments:
Foreign Investments into ICT Sector: Foreign investment is required to supplement local
investment in the local ICT Sector, in order to stimulate the desired growth within the sector. It is
therefore necessary to explore creation of a consortium-driven agency or policies dedicated to
attracting foreign investment in ICT.
Develop and/or revise tax and other incentives for individuals and firms to encourage investment
in ICT. There are incentive schemes in existence and these need to be reviewed in terms of
directing and effectively supporting the ICT Sector.
Promote Private sector Collaborations:
A key aspect of developing a stable and growing trade environment in ICT Sector is the
establishment of linkages between the larger companies and the SMMEs.
Ownership/investment/mentoring linkages between large companies and new entrant SMMEs.
Outsourcing arrangements of non-core functions of larger companies to other companies in the
sector.
Supply/Distribution arrangements between large companies and SMMEs.
Partnerships and alliances, especially between local companies and Multi National Enterprises.
eKiosks installation on PPP model
The Kiosks are another ICT initiatives which help in reengineering several Public and Private sector
processes and making the citizen self sufficient in accessing information and performing certain key day
to day operations.Kiosks need to be set up across the country to enable information dissemination at the
grass root level. Private sector partnerships need to be encouraged to expedite the rollout of kiosks.
Country wide rollout of ICT Community Centers on PPP model
The lack of ICT usage and PC penetration keeps a large section of the population out of ICT reach. In
order to integrate this section into the mainstream of ICT beneficiaries there is a pressing need for ICT
facilitators who will assist the ICT illiterate citizens in not only availing the Government services but also
will guide them through relevant information. Additional ICT centers need to be implemented on
mechanisms such as the Public Private Partnerships engaging the private sector. Currently there are 65
community driven ICT Centers with different levels of ICT infrastructure and services. There needs to be
Government Driven ICT centers with uniformity in infrastructure access and citizen services.
ICT Trade Fair/ Forums:
In order to create an ecosystem for Public and Private collaborations, the Government must establish
and encourage networking events that permit face-to-face discussion and sharing of information and
knowledge. These networking events can take the form of ICT Sector focused exhibitions, conferences
and workshops.
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 192 Confidential
Table 37: ICT Events
Sr# Events Frequency Stakeholders
1 Workshops Every Month ICT Workshop for students in Universities to build
skills in ICT
ICT workshop Ministries, Agencies for e-Governance
ICT workshop for Private sector to enable better
business operations using ICT
2 Exhibitions Half Yearly Trade fair to show case the ICT technologies to build a
stronger domestic demand
Exhibition to attract Foreign investments in Ethiopian
ICT to promote IT and IT enabled industry in Ethiopia.
3 Conference One Every
Month
Private Sector conference to pursue public private
partnerships
ICT Trade conference to address business related issues
and concerns
International ICT Conference to build stronger ICT
trade relations with other countries and address issues
related to International ICT Trade
Establish a stakeholder group or groups to foster
collaborative projects and networking events, e.g.
projects such as building a broadband community
network.
Establish SME Centers
SME Centers need to be established for supporting and nurturing the Ethiopian SMEs. SME Centers
would act as "one-stop-shops" located in various parts of the country that provide information, advisory
and consulting services in the following areas:
productivity, improvement, technology upgrading, market information, product and market
development, trade promotion, credit, financing and entrepreneurship
Development of SME databases providing easy access to buyers and suppliers.
Imports, customs and tariff rates, etc.
All the ICT Agencies across the regions must set up SME Support Centers in their offices to promote SME
development. There must be clear mandate to the ICT Agencies to incorporate and Implement SME
focused initiatives in their Annual Plans. A central ICT SME Cell must be established in the MINISTRY
OF COMMUNICATIONS & IT to coordinate with all the regional SME Centers in working towards a
common goal to support SMEs.
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 193 Confidential
Promote trade through E-Commerce
The growth of the local ICT Sector cannot be promoted through addressing the local market alone. E-
commerce is a solution to tap potential markets across the world in a very cost effective manner.
Ethiopia with its diverse cultural backgrounds of its people and varieties of natural resources has a rich
heritage of crafts skills. Handicraft, Leather and textiles are one of the important and widely spread
occupations of most Ethiopians next to agriculture. Thus it would be important to design appropriate
mechanisms that will help SMEs participate in product modernization and export market development
especially in leather and leather products, textiles, horticulture, etc., in which the country has comparative
advantages.
ICT Information Centers (IICs): Facilitating access to information and skills
Ethiopia suffers from in information asymmetry. Relevant information is difficult to obtain and it is often
outdated, very expensive or only available from isolated institutions. The main objective of the ICT
Information Centres (IICs) programme would be to use ICT and relevant business information for the
development of local skills and public usage of ICT. The IICs can be set-up as a joint venture between
public and private sector institutions and provide a central information access point for citizens.
These Information centers need to be located in every city.
Mobile Phone Solutions on PPP model
Mobile phones have a huge impact in developing countries like Ethiopia, substituting for scarce fixed
connections, reducing transaction costs, increasing mobility, broadening trade networks, and
facilitating searches for employment.
Currently there is a Mobile Governance initiative wherein a Private partner shall provide SMS based
informational services to the citizens. Government should collaborate with private sector to utilize
mobile telephony and take the ICT enabled services out into the remote communities, enabling:
Women entrepreneurs to build a business as ‗village phone operators‘
Farmers to make good choices based on market conditions
Rural poor to receive banking services they otherwise couldn‘t access
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 194 Confidential
PPP Implementation Plan:
Table 38: PPP Implementation Roadmap
Sr
#
Strategy Implementation Plan Timeline
1 Unified Billing System on
PPP Model
RFP Evaluation and Contracting of Unified
billing System (UBS) project in Addis Ababa for
the following Utilities:
The Addis Ababa Water & Sewage Authority
(AAWSA);
The EEPCO (Ethiopia Electric Power Company);
and
The ETC (Ethiopia Telecommunications
Corporation)
1 month
Program Management Unit of UBS to be setup 3 months
Pilot of UBS in 5 centers in Addis Ababa 6 months
Pilot of UBS across 70 centers in Addis Ababa 1 year
Initiation of UBS across multiple cities in
Ethiopia. EOI and RFP process to be initiated
across 4 regions- Diredawa,Mekelle, Awassa and
Bahir Dar
6 months
Initiation of UBS in rural areas 1 year
Expansion of Utilities in UBS –
Government housing Rent – city and federal
government
Housing Loan repayments to Govt
Broadcasting Payment
Transport related payments
School fees
2 years
2 Exploring PPP
Opportunities
Identification of 3 ICT Services project to be
rolled out on PPP Model
3 months
Schedule and Action plan for ICT Interventions
for Private sector
6 months
3 Policies and Guidelines
to enable PPP
PPP Guidelines for National Level 1 year
Establishment of International ICT Trade panel
to revise policies to support Foreign investment
into ICT in Ethiopia.
3 months
Formulation of Preferential Taxation for Rural
ICT Development
6 months
4 Business enablers to
support partnerships
Establishment of Special Economic Zones to
attract both domestic and Foreign ICT
companies with incentives
1 year
Implementation of payment gateway 2 years
Development of National Trade portal 1 year
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 195 Confidential
integrating all the businesses in Ethiopia
Integration of SMEs, Banks and Micro finance
institutions, NGOs and donor organizations
through ICT for effective funding and project
executions
1 year
Integration of the Inventory of all the goods,
Warehouses and building trade channels for
Ethiopia both at domestic and foreign market
1 Year
Establishment of SME Support centers 1 Year
5 Development of Delivery
Channels for both
Citizens and Business on
PPP Model
Informational and transactional Trade Portals December
2011
PPP in implementing Citizen Service Electronic
Kiosks to enable public and private e-services for
citizens at national level
2 Year
Establish ICT Information Centers in all the
Regions with coordination from the regional ICT
Agencies
1 Year
SMS based public services on PPP model 6 months
Establishment of additional ICT Centers to
deliver Citizen Services
1 year
Mobile Solutions on PPP Model 1 year
11 Training and Capacity
Building with
Partnerships from ICT
Companies and
Educational Institutes
Training for professionals/Students in ICT Every 3
Months
ICT business training for SME in order to relate
their business with ICT
Every 3
months
12 Establishment of Centers
of Excellence on PPP
model
ICT Research and Development Center 1 Year
Setup of De-manufacturing centers 1 Year
e-Waste Management Center:
Development of Regulation document and
Implementation plan for e-Waste Management
1 Year
Establishment Incubation centers in all the
remaining regions
1 Year
Refurbishment Centers for more ICT goods to
provide affordable access to ICT
1 Year
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 196 Confidential
Guidelines for leveraging PPP in Ethiopia
1. PPP projects should be initiated only after the same are examined by the technical committee and approved by the high committee. An indicative format in which such requests should be sent to the Technical Committee is placed below.
2. All projects proposed for PPP mode of implementation should undergo a comprehensive feasibility check and the value added by the private partner should be clearly articulated and quantified.
3. The proposed user charges and tariffs should be checked for appropriateness and acceptability of the users.
4. The process for the selection of the private partner should be clearly defined and notified to ensure that there is transparency in the selection process and the e-Government program does not get tarnished by allegations of corruption and partisanship.
5. A comprehensive Master Services Agreement with unambiguous timelines and service levels and penalties in case of non-adherence to the same must be signed with the private partner before initiating the project.
6. An annual review of the performance of the private partner must be conducted at the level of the high committee.
Table 39: Guidelines for leveraging PPP
1. General
1.1 Name of the Project
1.2 Type of PPP (BOT, BOOT, BOLT, OMT etc.)
1.3 Location (State/District/Town)
1.4 Administrative Ministry/Department
1.5 Name of Sponsoring Authority
1.6 Name of the Implementing Agency
2. Project Description
2.1 Brief description of the project
2.2 Justification for the project
2.3 Possible alternatives, if any
2.4 Estimated Capital costs with break-up under
major heads of expenditure. Also indicate the basis
of cost estimation.
2.5 Phasing of investment
2.6 Project Implementation Schedule (PIS)
3. Financing Arrangements
3.1 Sources of financing (equity, debt, mezzanine
capital etc.)
3.2 Indicate the revenue streams of the project
(annual flows over project life). Also indicate the
underlying assumptions.
3.3 Indicate the NPV of revenue streams with
appropriate discounting
3.4 Who will fix the tariff/ user charges? Please specify
in detail.
4. IRR
4.1 Economic IRR (if computed)
4.2 Financial IRR, indicating various assumptions
(attach separate sheet if necessary)
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 197 Confidential
1. General
5. Clearances
5.1 Status of environmental clearances
5.2 Clearance required from the State Government
and other local bodies
5.3 Other support required from the State
Government
6. Government of Ethiopia Support
6.1 Viability Gap Funding, if required
6.2 Guarantees being sought, if any
7. Concession Agreement
7.1 Details of Concession Agreement
7.2 Service levels and penalties
8. Criteria for short-listing
8.1 Indicate the criteria for short-listing (attach
separate sheet if necessary)
9. Others
9.1 Remarks, If any
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 198 Confidential
Section 7 –
IMPLEMENTATION
PLAN & TIMELINES
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 199 Confidential
VII. Over all Implementation Plan and Timelines
I. Overall Implementation Plan
Table 40 – Overall Implementation Plan
S.No. Yr. v/s Project
Implementation plan
Year 1 Year 2 Year 3 Year 4 Year 5
Agency Priority Projects
1 Agriculture Services
All information services
Agricultural Services Management System
Portal for all Agricultural services and information
2 Benefits Management system
Social Benefits Portal with information regarding all welfare schemes
Pension Management system
Social Benefits Management System
3 Education
Education portal
Exam Management system
Student Management System
Education Administration system
4 eHealth
Hospital Management Portal
Hospital Information Management System
Drug Information Management System
Integration of hospitals and pharmacies
5 E-Trade
All information regarding G2B services
Investors Management system
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 200 Confidential
S.No. Yr. v/s Project
Implementation plan
Year 1 Year 2 Year 3 Year 4 Year 5
Trade Management System
Enterprise Management System
Integrated G2B portal
6 Employment
Employment portal with all information services
Employment Management System
7 Transport
Transport ministry portal including all information services and drivers licenses related services
Vehicle Registration Information system
Online ticket booking system
Government Vehicles Insurance Management System
8 Tourism
All information related to travel attraction, hotels etc.
Travel Licenses Management System
Hospitality Management System
Tour Management System
Disaster Management system
GIS enabled Portal for Tourists
9 Tax
Custom and Revenue Authority Portal (CRAP)
Tax Management and Information System
10 e-Courts
eCourt portal to provide informational services
Case Management system
Property and Land Management system
Integration with Regional court and property
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 201 Confidential
S.No. Yr. v/s Project
Implementation plan
Year 1 Year 2 Year 3 Year 4 Year 5 systems
11 e-Municipality
Portal with all information services of the Municipality
Modules for certificate generation, tax collection, accounts and license
GIS application
Project Systems (for Water/Sewerage / Roads /Building etc.)
Fleet Management System
Asset and Material Management system
12 Passport & Visa
Passport & Visa Management System
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 202 Confidential
S.No. Yr. v/s Project
Implementation plan
Year 1 Year 2 Year 3 Year 4 Year 5
Enablers
1 Marketing and Awareness Campaign
Design of annual plan for Marketing and awareness activities
Internal Awareness Campaign, Feelers
Targeted Customer Campaigns
2 Capacity Building
Establishment of the Knowledge Management System
Design of Change Management Plan, Training Curricula
Operationalization of the ITSG
Courses for leadership, customer orientation, IT and project management etc.
3 Monitoring and Evaluation
Setting up the M&E framework
Baseline survey of government organizations and customers
Annual survey of government organizations and customers
4 Standards and Policies
Selection of a consultant for setting up Standards and Policies
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 203 Confidential
S.No. Yr. v/s Project
Implementation plan
Year 1 Year 2 Year 3 Year 4 Year 5
Identification of Standards, policies and guidelines required for implementation of the e-Government strategy
Phase - I of standards and policies implementation
Phase - II of standards and policies implementation
Phase - III of standards and policies implementation
5 Core Projects
National Data Set
National Enterprise Service Bus
National Integrated Authentication Framework
National Payment Gateway
Public Key Infrastructure
National Data Center
Woredanet
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 204 Confidential
II. Sample Detailed Implementation Plan and RACI Chart for Education Priority project
Table 41 – Education Project Implementation Plan
S.No. Activities
Implementation plan - SBMS
Year 1 Year 2 Year 3
0-6 mon 6-12 mon 12-18 mon 18-24 mon 24-30 mon
30-36 mon
1 Formation of the project team and selection of a project manager
2 Meetings between the Project team and PMO to discuss the way forward
3
Preparation of Detailed Project Report including As-Is processes, To-be processes, detailed costing and implementation timelines
4 Review of the DPR and approval
5
Development of Benefits management portal to put all informational services related to benefit schemes online and for the development of Pension Management System
5.1 Preparation of the RFP for the selection of vendor
5.2 Review and finalization of RFP
5.3 Bid process management leading to selection of the vendor
5.4 Project implementation kickoff
5.5 Application Development
5.6 Testing
5.7 Training of the Staff
5.8 Go live
5.9 Sub-project closure and learning report
6 Development of comprehensive Social Benefits Management System
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 205 Confidential
S.No. Activities
Implementation plan - SBMS
Year 1 Year 2 Year 3
0-6 mon 6-12 mon 12-18 mon 18-24 mon 24-30 mon
30-36 mon
6.1 Preparation of the RFP for the selection of vendor
6.2 Reviezxw and finalization of RFP
6.3 Bid process management leading to selection of the vendor
6.4 Project implementation kickoff
6.5 Application Development and integration with Pension Management System
6.6 Testing
6.7 Training of the Staff
6.8 Go live
6.9 Sub-project closure and learning report
7 Project Closure Report
Implementation Plan detail for Education Ministry priority project
Education Ministry priority project has 4 main components or sub-projects – Education Portal, Exam management System, Student management
System and Education Administration System. As per the proposed implementation plan – the portal implementation may be spread out over
years 1 and 2, while the Exam management system may be implemented in 1st Year and the Education Administration System implementation
(automating the entire functioning of the ministry) is proposed over years 2 and 3.
A RACI chart is detailed below clearly showing the implementation plan – for the Exam management system project.
The same chart may be followed for all projects.
The RACI Chart is used to clarify roles and responsibilities in the project implementation. It is a table that provides the list of activities and
information about roles different people have in relation to those activities. For each activity, different people are assigned different roles as per
―RACI‖.
This acronym stands for (i) Responsible, or the person doing the work; (ii) Accountable, or the person responsible for making sure the work is
done adequately; (iii) Consulted, or the person(s) who is asked for their input; and (iv) Informed, or the person(s) who must be told about the
work.
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 206 Confidential
No Activity/Task Responsible Accountable To Consult To Inform Remark/Comment Guidelines
documents/templates
reference(s)
Formation of the
project team and
selection of a project
manager
Education
Ministry
E-Gov.
Strategy PMO
E-Gov.
Strategy
Technical
Committee
E-Gov.
Strategy High
Committee
Meetings between the
Project team and PMO
to discuss the way
forward
Ministry
project team
E-Gov.
Strategy PMO
E-Gov.
Strategy
Technical
Committee
Preparation of Detailed
Project Report
including As-Is
processes, To-be
processes, detailed
costing and
implementation
timelines
Ministry
project team
E-Gov.
Strategy PMO
E-Gov.
Strategy
Technical
Committee
DPR format provided
in the E-Gov. Strategy
Report
Review of the DPR and
approval
E-Gov.
Strategy PMO
E-Gov.
Strategy
Technical
Committee
E-Gov.
Strategy High
Committee
Project
Sponsor /
Council of
Ministers
E-Gov. Strategy
High committee
will approve the
report
Development of
Exam management
System
Preparation of the RFP
for the selection of
vendor
Ministry
project team
E-Gov.
Strategy PMO
E-Gov.
Strategy High
Committee
Depending on the
funding source of
the project, the
RFP may be
prepared in the
applicable format
- RFP Best practices
document provided by
PwC
- World Bank or other
funding Institution
RFP template
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 207 Confidential
No Activity/Task Responsible Accountable To Consult To Inform Remark/Comment Guidelines
documents/templates
reference(s)
– Example – If it is
funded by Govt.
funds, the RFP
best practices
document
template may be
used
or
If project is
funded by World
bank or other such
Institution then
the RFP template
of the funding
institution will
need to be used.
Review and
finalization of RFP
E-Gov.
Strategy PMO
E-Gov.
Strategy
Technical
Committee
E-Gov.
Strategy High
Committee
E-Gov. Strategy
High committee
will approve the
RFP
Bid process
management leading
to selection of the
vendor
Ministry
project team
E-Gov.
Strategy PMO
E-Gov.
Strategy
Technical
Committee
E-Gov.
Strategy High
Committee
The technical
committee may
approve the
vendor selection
The High
committee will be
informed about the
vendor selection
and give final
approval
Selection criteria as
per approved RFP
Model Template (Excel
Sheet) for evaluation
of proposals submitted
by PwC
Project implementation Ministry E-Gov.
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 208 Confidential
No Activity/Task Responsible Accountable To Consult To Inform Remark/Comment Guidelines
documents/templates
reference(s)
kickoff project team Strategy PMO
Application
Development
Selected
vendor
Ministry
Project Team
E-Gov.
Strategy PMO
E-Gov.
Strategy High
Committee
E-Gov.
Strategy High
Committee
Direct supervision
of Application
development will
be done by
Ministry project
team and PMO
Technical
committee will be
closely guiding this
activity and will
resolve any
technical issues in
implementation
and also be
responsible for
approving final
sign –off of all
documentation like
SRS, test plan,
acceptance test
reports, etc.
The High
committee will be
kept informed of
the progress and
resolve any
administration
issues like scope
Software Project
Management
Guidelines provided by
PwC
Project Management
Guidelines templates
provided by PwC
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 209 Confidential
No Activity/Task Responsible Accountable To Consult To Inform Remark/Comment Guidelines
documents/templates
reference(s)
increase, cost
increase etc.
Testing Selected
vendor
Ministry
Project Team
E-Gov.
Strategy PMO
E-Gov.
Strategy
Technical
Committee
E-Gov.
Strategy High
Committee
High-Committee
may be kept
informed about
testing progress
and reports
Testing guidelines
document provided by
PwC
Training of the Staff Selected
vendor
Ministry
Project Team
E-Gov.
Strategy PMO
E-Gov.
Strategy
Technical
Committee
E-Gov.
Strategy High
Committee
High-Committee
may be kept
informed about
training plan &
progress
Training plan and
material prepared by
vendor and as
approved by Technical
Committee
Go live Selected
vendor
Ministry
Project Team
E-Gov.
Strategy PMO
E-Gov.
Strategy
Technical
Committee
E-Gov.
Strategy High
Committee
High-Committee
will be kept
informed about
project go-live date
Project closure and
learning report
Ministry
project team
E-Gov.
Strategy PMO
E-Gov.
Strategy
Technical
Committee
E-Gov.
Strategy High
Committee
The high
committee will be
kept informed
about any special
lessons learned
from the project
implementation –
like in case of any
scope increase or
cost increase which
may have been
better controlled
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 210 Confidential
III. Portal Implementation Plan and Timelines
Table 42 – Portal implementation Plan
e-Government Portal for Ethiopia
S.No Key Activities Year I Year II Year III Year IV Year V
1 Design of portal and content management
1.1 Identify a team to upgrade the existing e-Government portal
1.2 Develop portal charter
1.3
RFP for the selection of a vendor for development of a new portal and to develop content for the portal
1.4 Appointment of the vendor for portal design and content
1.5 Requirements gathering by the vendor
1.6 Conference room pilot
1.7 Development of FRS and SRS
1.8 Development of the new portal and content
1.9
Development of Standard operating procedures and content management processes for the portal
1.10 Testing and review of content
1.11 Go-live
2 Development of 46 e-Services for first year
2.1 Requirements gathering by SDA
2.2 Preparation of SRS and FRS by the SDA
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 211 Confidential
e-Government Portal for Ethiopia
S.No Key Activities Year I Year II Year III Year IV Year V
2.3 Development of the e-Services
2.4
Portal Infrastructure augmentation for new e-Services
2.5 Testing of the Services
2.6
Training of the government employees that provide these services
2.7 Go-Live of the portal
2.8 Closure of the sub-project
3 Development of Grievance Redressal System
3.1
Identification of team of officials from various departments for development of the grievance redressal system
3.2
Meeting between PMO and the identified team to understand the requirements for Grievance redressal system
3.3
Identification of officials in every department to whom the grievance redressal requests of their departments would be directed to
3.4
Development of FRS and workflow for the Grievance Redressal system
3.5 Approval of the FRS and workflow
3.6
Development of the Grievance redressal system by the programmers at MoICT
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 212 Confidential
e-Government Portal for Ethiopia
S.No Key Activities Year I Year II Year III Year IV Year V
3.7 Testing
3.8 Go-Live of the Grievance Redressal System
4
Addition of e-Services to the e-Government Portal as per the go-live of e-Services through the Agency Priority Projects
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 213 Confidential
IV. ICT Center Implementation Plan and Timelines
Table 43 – ICT Centre Implementation Plan
e-Government ICT Centres
S.No Key Activities Year I Year II Year III Year IV Year V
1 Identify a team to upgrade the existing ICT Centres for delivering the e-Services
2 Study the existing ICT Community Centre and Unified Billing Centre
3
Study the existing services delivered through the 65 ICT Community Centres and 70 UBS
4 Study the existing infrastructure in the Centres
5
Undertaking a Feasibility Study on the type of services that could be delivered these Channels
6 Identification of the extra number of centres required to cover all the regions
7 Design a Business Model for the Centres for delivering the services
8
Design the Standardization requirements in terms of Services, Infrastructure and Staff cross the Centres
9
Design a RFP for selection of an agency for establishing the extra channels or identify community partners for the same
10 Design the funding requirements of the Centres
11
Establishment of the new ICT Centres and upgradation of the existing for delivering the e-Services
12 Training of the employees of the ICT
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 214 Confidential
e-Government ICT Centres
S.No Key Activities Year I Year II Year III Year IV Year V centres
13 Operationalization of the ICT Centre
14 Delivery of the e-Services - Informational
15 Delivery of the e-Services - Transactional
16 Establishment of a Monitoring and evaluation Framework
17 Monitoring the SLAs of the ICT Centres
18 Monitoring the Channel Uptake
19
Incremental upgradation of the Channel based on the uptake and Feedback received
20 Conduct Customer satisfaction survey for the ICT Centre
21 Revised the Channel Strategy based on survey results
22 Study the Impact of the Channel
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 215 Confidential
V. Contact Center Implementation Plan and Timelines
Table 44 – Contact Center Implementation Plan
e-Government Contact Centre for Ethiopia
S.No Key Activities Year I Year II Year III Year IV Year V
1 Identify a team to upgrade the existing Contact Centre for delivering the e-Services
2 Study the learnings from the existing Contact Centre
3 Design a Business Model for a Private Sector Participation
4 Identify the services that needs to be delivered through the Channel
5 Design the scope of work for a private agency sector for development of the Contact Centre
6 Design the workflow for delivering the e-services through the Contact Centre
7 Conduct a Cost benefit Analysis for creation of the Channel
8 Conduct Customer satisfaction survey for the Contact Centre Channel
9 Bid process Management for selection of the Agency
10 Design the requirements of the Contact Centre Inbound/outbound Software
11 Design the SRS for the Contact Centre Software
12 Develop the Contact Centre Software
13 Installation of the Contact Centre Software
14 Training of all the Contact Centre Employees
15 Operationalization of the Contact Centre
16 Delivery of the e-Services - Informational
17 Delivery of the e-Services - Transactional
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 216 Confidential
18 Establishment of a Monitoring and evaluation Framework
19 Monitoring the SLAs of the agency
20 Monitoring the Channel Uptake
21 Incremental upgradation of the Channel based on the uptake and Feedback received
22 Conduct Customer satisfaction survey for the Contact Centre Channel
23 Revised the Channel Strategy based on survey results
24 Study the Impact of the Channel
25 Design the Sustainability Options after the term of the Agency is completed
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 217 Confidential
VI. Mobile Implementation Plan and Timelines
Table 45 – Mobile Implementation Plan
Mobile Portal for Ethiopia
S.No Key Activities Year I Year II Year III Year
IV Year V
1 Identify a team responsible for the implementation of the mobile gateway
2
Contact ETC to appoint a nodal officer to assist in the implementation of this initiative
3 Identify the services to be delivered through the mobiles
4 Capture the learning from the pilot project
5
Design the scope of work for a private agency sector for development of the Contact Centre
5.1
Develop Terms of Reference and issue an Expression of Interest seeking solution design, architecture, bill of materials and services enablement plan for the mobile gateway
5.2 Shortlist the vendors based on the quality of the EoI response
5.3 Use the EoI responses to draft an RFP with well defined scope of work
5.4 Issue the RFP to the shortlisted bidders
5.5 Bid process Management for selection of the vendor
5.6
Assessment of the services for feasibility and any changes in processes for phase 1
5.7 Development of content for the mobile gateway
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 218 Confidential
Mobile Portal for Ethiopia
S.No Key Activities Year I Year II Year III Year
IV Year V
5.8 Testing
5.9 Go-live
5.10 Capture learning of phase 1
5.11 Closure of phase 1
6 Phase 2 for introduction of additional services
7 Phase 3 for introduction of additional services
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 219 Confidential
VII. Capacity Building Implementation Plan and Timelines
Table 46 – Capacity Building Implementation Plan
Implementation plan - Capacity Building
S.No Key Activities Year I Year II Year III Year IV Year V
1
Identify a team responsible for the implementation of capacity building initiatives within the Government
2 Creation of a IT Services group
2.1 Framing the roles and responsibilities of the ITSG
2.2
Defining the organization structure, no. of resources, qualifications required and job descriptions
2.3 Identification of the staff within government that can fill up these positions
2.4
Permission from relevant authorities to explore the option of forming a joint venture company for ITSG to source resources that are not available within the government
2.5 Development of an EoI to invite private partners for the JV
2.6 Shortlisting of vendors based on their responses
2.7 RFP and bid process management for the selection of private partner
2.8 Formation of the JV and incorporation as a separate company
3 Training Needs Assessment and preparation of training curriculum
3.1
Identification of various categories of officials as per their needs for using IT, project management, customer service skills and providing leadership
3.2
Survey to understand the present level of proficiency of the target groups in the skill areas identified as relevant for performing their jobs
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 220 Confidential
Implementation plan - Capacity Building
S.No Key Activities Year I Year II Year III Year IV Year V
3.3 Design of course curriculum based on survey results
3.4 Development of e-learning modules for delivery to augment instructor led training
3.5 Training based on the training modules
4 Strengthening of IT Training infrastructure
4.1 Identification of training institutes to be leveraged for providing training
4.2
Define minimum infrastructure and other facilities to be available at these training institutes
4.3 Assessment of the present infrastructure of the identified institutes
4.4 Provisioning funds to these institutes for strengthening infrastructure
4.5 Development of the requisite infrastructure
4.6 Augmentation of infrastructure for scaling up the operations and any required improvements
5 Development of Ethiopian Government Knowledge Management Portal
5.1 Development of a DPR for the project by PMO
5.2 Approval of the DPR
5.3
Issue of RFP for the selection of an implementation agency to develop the KM portal
5.4
Bid process management leading to appointment of an agency for implementing KM portal
5.5 Development of the portal
5.6 Procurement of hardware for the portal
5.7 Testing
5.8 Go-Live
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 221 Confidential
Implementation plan - Capacity Building
S.No Key Activities Year I Year II Year III Year IV Year V
5.9
Project closure and learning report along with recommendations and best practices to ensure that the KM portal serves its purpose as one single source of information for government staff
5.10
Awareness campaign within the government departments for contributing towards and using the KM portal
6 Arrangement of Tours, seminars and conferences
6.1
Identification of countries, institutions, conferences and events across the world that can be studied to improve the understanding of e-Government amongst officials
6.2 Identifications of officials for these tours
6.3 Compendium of learning from each of these activities
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 222 Confidential
VIII. Marketing and Awareness Plan and Timelines
Table 47 – Marketing and Awareness Implementation Plan
Implementation plan - Marketing and Awareness
S.No Key Activities Year I Year II Year III Year IV Year V
1
Identify a team responsible for the implementation of Marketing and awareness campaign
2 Development of RFP for the selection of Marketing and PR partner
3
Issue of the RFP after approval from authorities and bid process management leading to the appointment of the marketing and PR partner for e-Government strategy implementation
4 Development of a distinctive theme, branding and symbol for e-Government
5
Workshops with all government organizations to make them aware regarding the branding guidelines for e-Government strategy
6
Discussions with the owner agencies of Agency priority projects whose services will be enabled online during the year
7 Development of annual plan for Marketing and Awareness
8
Development of marketing material for new services including content for bill boards, newspapers, TV and Radio ads etc.
9
Identification of private partners and other innovative means for funding the marketing and awareness program
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 223 Confidential
IX. Public Private Partnership - Plan and Timelines
Table 48 – Public Private Partnership Plan
S.No Activities Year 1 Year 2 Year 3
0-6 mon 6-12 mon 12-18 mon 18-24 mon
24-30 mon
30-36 mon
1 Formation of the project team in charge of PPP Initiatives and selection of a project manager
2
Meetings between the Project team and PMO to discuss the key PPP Initiatives with ETC, Banks, Educational Institutes, Private Sector and Healthcare Institutions
3
Preparation of Detailed Project Report including As-Is processes, To-be processes, detailed costing and implementation timelines.
4
Review of the DPR and approval. Funding road shows and Workshops for generating the required funding.
5
Development of e-Procurement portal to put all informational services related to Public Private Partnerships and Government Tenders
5.1 Preparation of the RFP for the selection of vendor
5.2 Review and finalization of RFP
5.3 Bid process management leading to selection of
the vendor
5.4 Project implementation kickoff
5.5 Application Development
5.6 Testing
5.7 Training of the Staff
5.8 Go live
5.9 Sub-project closure and learning report
6 Development of ICT Centers
6.1 Preparation of the RFP for the selection of
vendor
6.2 Review and finalization of RFP
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 224 Confidential
S.No Activities Year 1 Year 2 Year 3
0-6 mon 6-12 mon 12-18 mon 18-24 mon
24-30 mon
30-36 mon
6.3 Bid process management leading to selection of
the vendor
6.4 Project implementation kickoff
6.5 ICT Center Development and integration with e-
Government Services
6.6 Testing
6.7 Training of the Staff
6.8 Go live
6.9 Sub-project closure and learning report
7 Development of ICT Incubation Centers
7.1 Preparation of the RFP for the selection of
vendor
7.2 Review and finalization of RFP
7.3 Bid process management leading to selection of
the vendor
7.4 Project implementation kickoff
7.5 ICT Incubation Center Development and initial
setup of Entrepreneurial Ventures at the Center
7.6 Testing
7.7 Training of the Staff
7.8 Go live
7.9 Sub-project closure and learning report
8
Implementation of key PPP Projects in collaboration with ETC, Banks, Educational Institutes, Private Sector and Healthcare Institutions. Note: The period of the Partnership and the term of the contract shall depend on the type of PPP Models. Generally the PPP BOOT Model shall be implemented for a period of 3- 5 Years.
8.1 Preparation of the RFP for the selection of
vendor
8.2 Review and finalization of RFP
8.3 Bid process management leading to selection of
the vendor
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 225 Confidential
S.No Activities Year 1 Year 2 Year 3
0-6 mon 6-12 mon 12-18 mon 18-24 mon
24-30 mon
30-36 mon
8.4 Project implementation kickoff
8.5 Project implementation and Tracking
8.6 Testing
8.7 Training of the Staff
8.8 Go live( This period would depend on the
duration and Type of the PPP Contract)
8.9 Sub-project closure and learning report
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 227 Confidential
VII. Cost Estimation & Funding
I. Budgetary Estimates
The proposed e-Government Strategy budget of Birr 3.33 billion for 5 years or Birr 0.67 billion / year
compares with Birr 2.13 billion/ year and Birr 10.13 billion / year for Health and Education sector
respectively. The proposed budget for the e-Government strategy will entail less than 1% of the overall
budget of Government of Ethiopia
Summary of the Cost Estimates of the various initiatives proposed is as below –
Table 49 – e-Government Strategy – Summary of Costs
Ethiopia eGovernment Strategy - Costing Summary
S.No.
Initiatives
Year 1 (In Birr.)
Year 2 (In Birr.)
Year 3 (In Birr.)
Year 4 (In Birr.)
Year 5 (In Birr.)
1 Agriculture Services
15,514,298
4,893,316
4,466,779
4,687,683
4,294,225
2
Benefits Management System
17,442,654
4,269,715
3,954,873
4,124,957
3,833,491
3 Education 23,829,430
7,420,991
6,080,086
6,337,290
5,036,393
4 eHealth 23,529,430
7,090,991
5,717,086
5,937,990
4,597,163
5 G2B Portal 4,759,002
1,197,989
1,223,221
1,303,081
1,343,558
6 Employment
17,287,346
4,946,355
4,335,524
4,527,388
3,944,091
7 Transport 20,203,136
5,553,724
5,166,787
5,431,251
5,085,709
8 Tourism 15,502,509
5,427,716
5,056,619
5,338,507
5,012,131
9 Tax 21,420,680
5,889,513
5,344,682
5,609,146
5,105,709
10 e-Court 14,758,509
4,609,316
4,156,379
4,348,243
3,922,841
11 Municipalities
17,767,346
5,474,355
4,916,324
5,166,268
4,646,859
12 Passport 16,228,048
5,672,355
5,134,124
5,405,848
4,910,397
12 eGovernment Portal
10,097,895
4,197,158
4,537,137
4,910,285
5,319,877
13 Contact Center
29,199,123
29,240,352
32,112,471
35,270,474
38,742,883
14 Mobile Gateway
4,520,000
4,235,509
3,226,291
3,489,082
3,776,991
15
Common Service Center
718,243,842
326,899,053
355,121,309
386,036,106
419,906,215
16 Capacity Building
14,716,421
6,329,996
6,702,958
7,204,999
7,750,824
17
Marketing & Awareness
10,163,170
10,810,802
11,504,763
12,248,764
13,046,842
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 228 Confidential
18 Standards & Policies
5,021,754
5,509,684
6,045,695
6,634,558
7,281,523
19
Enterprise Architecture
5,081,667
435,000
257,000
257,000
257,000
20 NIAF 33,788,816
500,000
500,000
500,000
500,000
21 NSEB 20,595,316
-
-
-
-
22 NDS 36,676,316
-
-
-
-
23 NPG 28,076,316
-
-
-
-
24
PKI( Design and implementation as per the design by external consultant)
124,754,500
25 HRMS 16,243,211
1,473,684
1,473,684
1,473,684
1,473,684
26
e-Procurement System
15,022,158
252,632
252,632
252,632
252,632
27 e-Office System
15,022,158
252,632
252,632
252,632
252,632
28
Financial Manangement Information System
4,319,058
-
-
-
-
29
Email Management System
14,769,526
-
-
-
-
30
ITSG Manpower costs
1,500,000
3,300,000
3,630,000
3,993,000
4,392,300
31
PMO staffing costs
1,860,000
2,706,000
2,976,600
3,274,260
3,601,686
Total 1,317,913,633
458,588,838
484,145,652
524,015,128
558,287,654
Grand Total
3,328,181,379
Grand Total (in USD) 201,463,764
Details of the Costing is provided in Annexure XVII
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 229 Confidential
II. Funding Framework
To enable proper implementation of the Strategy Program, a proper funding and spending system
needs to be developed, approved and implemented to ensure that the funds are sufficiently allocated
for the different development domains. Funding options need to be considered carefully to ensure that
Transparency and accountability is maintained in allocation and utilization of funds
Adequate funds are available for the implementation of the project
utilization of allocated funds is monitored
Strategic control of the government is maintained
E-Government Strategy funding and spending process and the life cycle across the different stages of IT
initiatives are explained in the pages that follow. More specifically the following areas have been
addressed:
Funding options identified during the Assessment Phase and the planning activities.
Funding and Spending Framework including percentages distribution and link to Governance
Structure
Fund allocation and utilization process for core, common, Ministry/Agency specific and
Ministry/Agency owned initiatives.
The annual procedure for short-listing vendors.
The key options available for MOCIT to fund the Strategy are:
Figure 31: Key Options for MOCIT
OPTION 1 (Conventional) - Government Funded: The source of the fund is the Government annual
budget, where the Government of Ethiopia invests the whole project/initiative amount as capital
expenditure
OPTION 2 - International Funding Agencies: Several international donor agencies provide
financial support to development projects in developing countries. Bilateral development agencies
facilitate the provision of grants and loans from one national government to other governments or NGOs
in order to help implement development projects. Multilateral development agencies also provide
resources and carry out development projects with governments and NGOs and include numerous UN
agencies (such as UNDP, UNFPA, UNIFEM), development banks (such as the World Bank, African
Development Bank), and other inter-governmental bodies
OPTION 3(PPP) - Public Private Partnerships: Government and Private sector can collaborate on
different models for the implementation and success of the model
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 230 Confidential
(BOT) – Build Operate and Transfer (BOT): For some of the initiatives the private sector can build the
infrastructure, own the operations for a fixed period of time and transfer it to government once the fixed
period is over.
OPTION 4 (Privatise) – In a longer timeframe when the system is mature and basic infrastructure is in
place, some of the services can be completely privatised where Government funding will not be done and
it will be controlled by parties in private sector
The various funding options mentioned above differ in terms of the ownership by Government and the
risk transferred to the private sector as shown in the diagram below
Figure 32: Government Control/Risk
Some of the key factors to be considered during the design include:
The e-Government Program will be initially funded through Government funds.
Other funding options (mainly BOT and Funding Agencies) can be explored in parallel
PPP can be consider at a later stage once PPP models become more mature in Ethiopia
Privatization is a long term target that can start once services have taken a mature shape or became
well defined.
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 231 Confidential
III. Program funding Options
The E-Government Strategy implementation may be funded by a combination of funding sources –
including Government‘s own budgetary allocations, finance from multilateral institutions like the World
Bank or by partnering with the private sector.
Partnering with the private sector would provide a two-fold benefit – in terms of providing finance as well
as it will help the development of the private sector and develop indigenous capacity and skills.
The above diagram depicts the probable quantum of funding of the E-Government strategy program from
different sources, including Government funds, institutions like the World Bank and through the PPP
(Public-Private Partnership) route. The table below provides the amounts which could be funded by the
different entities.
Table 50 – Funding Options
Funding Options Amount( in Birr) Amount(in USD
Funding Agencies 1,996,908,827 120878258
PPP 665,636,276 40292753
Government 665,636,276 40292753
60%20%
20%
Funding Source
Funding Agency PPP Government
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 232 Confidential
Savings through PPP- Indicative
As mentioned earlier, partnering with the private sector for implementation of the program – will not
only help in funding but will also develop the indigenous private sector. The different projects – including
the identified priority projects and the channels could be implemented in PPP mode.
Assumption: Since the number of transactions for the Ministries/Agencies was not available, it has been
assumed that in projects related to development sectors such as health, education, social and labor etc,
where Government has a larger and more important mandate, and the there will low or no service charges
the PPP participation may be around 10%. However in projects such as E-Trade, Tax, Municipalities,
Tourism – where transactions are more and service charges could be collected the PPP participation may
be around 20%.
Based on above assumptions, following table depicts some of the possibilities of PPP funding of the
program, including savings in investment, which may accrue to the Government.
Table 51 – PPP Options
Sr. No. Project Estimated Cost (Mil.
Birr)
PPP Investment
(i.e. savings in
investment for
Government)
PPP Participation of 10%
1 Agriculture 33.86 3.39
2 Benefits Management 33.63 3.36
3 Education 48.70 4.87
4 Health 46.87 4.69
5 Employment 35.04 3.50
6 E-Court 31.80 3.18
PPP Participation of 20%
7 E-Trade 9.80 1.96
8 Transport 41.44 8.29
9 Tourism 36.34 7.27
10 Tax 43.37 8.67
11 Municipalities 37.97 7.59
12 Passport 37.35 7.47
13 Portal 29.06 14.77
14 Contact Centre 164.57 106.13
15 Mobile Gateway 19.25 14.73
16 Common Service Centres 2206.21 1103.11
Total 2855.26 1302.98
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 233 Confidential
PPP participation in Channels development:
The cost estimates for the development of the different channels have been made, as in other cases, for a
five year period. However, it is expected that private participation would commence from year 3 in case of
Portal and Call centre and from year 2 in case of Mobile gateway. The CSCs are proposed to be
implemented on PPP model itself – though implementation would start from year 2 – after completion of
tendering and selection.
The PPP investment contribution for the channels in above table, has accordingly been estimated for
- Years, 3,4,5 in case of Portal & Call centre
- Years 2,3,4,5 in case of Mobile Gateway
- Years 1,2,3,4,5 in case of CSCs
Thus it can be observed that out of total funding requirement of 3.33 Bil. Birr almost 40% amounting to
1302.98 Mil. Birr, could be funded by partnering with the private sector. It is important that the
Government consider this approach for implementation, because as mentioned earlier, partnering with
private sector is expected to provide multi-fold benefits for the country‘s development.
IV. Fund Management Framework (FMF)
In developing the FMF several variables were discussed and analysed. The major variables are mentioned
below:
1. The size of the fund
2. The distribution of the fund among the different initiatives (central/Ministry/Agency)
3. The approval process
To recommend the target framework, the following factors were taken into consideration:
Governments across the world are spending 3 to 5 per cent of their total annual budget on
modernization efforts; these Governments are of varying levels of maturity and thus require different
budget allocations.
Modernizing Government of Ethiopia requires work on the center level and on the
Ministries/Agencies level as well, the investment for the center will be larger during the Program
initial stages
As the Program develop, tendency will be towards automating work in the Ministries/Agencies, this
will mandate allocating more fund to the center where the center would have reached a good level of
maturity
There will be expenses associated with allocating resources to do designs and evaluations for
implementations to come, studies will have to be conducted to evaluate the need and the shape of
certain projects. These resources can be MOCIT internal resources or external third party resources
In general fund will be utilized for approved projects as detailed in the e-Government Strategy,
however, there will be instances where new requirements might arise and these will need to be tackled
properly.
There should be a system for allocations approval that complies with the Government policies and
procedures.
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 234 Confidential
The diagram below describes the FMF, in which it was assumed that 1% of the annual budget will be
allocated for e-Government Strategy Implementation.
Figure 33: Fund utilization framework
The diagram above describes the framework that is proposed for the fund allocation for the e-Government
Strategy. Important points include:
It has been assumed that the process for approval of budget will follow the normal cycle within
Ethiopian financial year.
There will be a fraction of total budget which will be allocated for the implementation of e-
Government Strategy. As mentioned previously it is assumed this fraction will be 1% of the total
Ethiopia budget.
Once the fund is approved it will be allocated under two separate categories as described below:
1. Central Fund: This fund will be allocated for the implementation of core and common
initiatives which include the shared infrastructure components and the common applications.
These components will be used by the different Government Ministries/Agencies.
2. Ministries/Agencies Fund: This fund will be allocated specifically for the initiatives to be
implemented by Ministries. The fund under this category will be allocated to Ministries for the
implementation of new or approved initiatives. A pre approved list of initiatives will be within the
Entity roadmap and annual IT plan, however, the need for other non-planned deployments might
arise during the year, these new requirements will be assessed and if given high priority will be
allocated a fund from the Entity fund if sufficient amounts are available.
Note: The process of utilization of fund or ‘spending processes will follow the existing
Ministry of Finance and Economic Development procedure. However, the process will be
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 235 Confidential
managed by MOCIT for Core and Common initiatives and by Ministries/Agencies for
specific initiatives.
The Central and Ministry/Agency funds will be divided under the following categories for administrative
and accounting purposes
Table 52: Categories of fund
S.No. Category Details
1. Research and
Development
Ministries/Agencies may need support from experts outside the
Government to analyze ‗new initiatives’ and to prepare DPR for
the fund allocation. This fund can be utilized by
Ministries/Agencies to hire an external agency with support from
PMO
2. Core and Common
Initiatives
This fund will be allocated for the implementation of core and
common initiatives.
3. New Initiatives This fund will be allocated for the implementation of the ‘new
initiatives’ that were not pre-planned.
4. Approved Initiatives This fund will be allocated to Ministries/Agencies for the
implementation of ‘approved initiatives’
Considering the Governance Structure, the approval for allocation of fund and the review of proposal will
be owned by different organizations within the structure for control purposes, these are described in the
table below.
Table 53: Approval for allocation
S.No
.
Initiative
Category
Initiativ
e Value
Implementati
on Owner
Monitoring
role
Supportin
g Role
Approval
for
allocation
of fund
1 Core and
common
value>X MOCIT MOCIT(PMO) Technical
Committee
High
Committee
Value< X Technical
Committee
/MOCIT
2
Ministries/
Agencies
Specific
Value > X Ministry/Agency MOCIT(PMO) Technical
Committee
High
Committee
Value< X Technical
Committee
/MOCIT
3 Ministry/Ag
ency Owned
Value > X Ministry/Agency MOCIT(PMO) Technical
Committee
Technical
Committee/
High
Committee
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 236 Confidential
Value< X MOCIT
V. Fund Allocation Process
Allocation of Funds for implementation of the 31 Projects will be done Centrally
Ministries/Agencies to prepare Detailed Project Report with the assistance from ITSG. The
various details to be covered under DPR are mentioned in the following sections and the Detailed
Project Report – Template has been provided in Annexure V.
Funding Approval will be done by the High Committee
Responsibility for Implementation of the Projects lies with the Implementation Ministry/ Agency
Fund Management and Review will be done by the PMO
The proposal/DPR will be reviewed by PMO and the recommendations/review comments will be
shared with the owner of initiative for further refinement will approve/reject the allocation of
fund.
High Committee will consolidate the list of approved initiatives and will finalize the fund
allocation.
The consolidated report will be shared with High Committee and fund approval process will
follow the existing Budgeting procedures
Guidelines
Project Case Formulation
Compliance with Guidelines and Procedures - The DPR to be submitted by the Implementation Entity
should contain the following details:
Project Description, including clear definition of the citizen/business need that it is fulfilling and
service standards sought to be achieved
How the project is leveraging existing and proposed infrastructure created by other initiatives
Project Funding sought
Breakdown of costs including Hardware, Software, Systems Development, Communications
Connectivity, Personnel, Training, Civil Works, Materials and supplies, Taxes, Contingency Costs and
Other Significant costs.
Projected Cash Flows (if any)
Ability to support PPP and Initiatives taken
Proposed Implementation Plan including Timeline
Key risk factors
Appraisal and Approval of Project Proposals
The Project DPR would be prepared by the implementing Ministry/Agency along the guidelines
established by MOCIT
The PMO would assist the implementing Ministry/Agency in filling the DRP
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 237 Confidential
The PMO would assist the High Committee in reviewing the projects and facilitating approval for both
Central and Ministry/Agency initiatives
The factors that need to be considered while evaluating projects include:
• Purpose and context -reflects e-Government strategy objectives
• Cost-benefit analysis
– Analysis of benefits in terms of envisaged citizen/business services
– The solution is practical and cost effective
– The project envisages infrastructure built by existing/proposed projects
– The project leverages Government funding with private resources
– The project leverages private sector skills
• Proposed implementation plan is realistic and reasonable
• Project management capacity
• Requisite skills to manage the project implementation as well as ongoing operation
• Risks perceived and mitigation measures (E.g. issue of political and Government staff
acceptability, statutory consents- whether risks are justified by the potentially high
outcomes)
• The way forward:
– Whether the decision is adequate to ensure continuation of services including
availability of O&M budgets in case e-service charges are not available or are not
adequate to cover these expenses
– The approval process would be detailed to ensure that this is the only approval
that the implementing Entity requires.
A Fund Allocation prioritization framework is provided in the figure below
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 238 Confidential
Figure 34: Fund allocation prioritization
D Development of e-Government Strategy and Implementation Plan
PricewaterhouseCoopers Page 239 Confidential
ANNEXURES
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 240 Confidential
Annexures
Annexure I: Concept of Service Life Cycle
The concept of Life Cycle Event, service enablement and agency services, i.e. ‗transaction‘, is explained in
the following table:
Table 54: Lifecycle Event Description
Category Definition Example
Life Cycle Event An event comprises the major categories
through which any customer carries out his
activities and interactions with the
Government. These events are a
combination of Life Cycle functions and
service based
Birth of a child
Starting a business
Service
Enablement
Refers to provisioning of a complete service
offering; it comprises of many transactions. Registering of business
Obtaining driver license
Agency Services
‘transaction’
Refers to individual transactions provided by
multiple agencies/ departments within an
agency for service enablement
Ministry of Trade and Industry– Business License
Ministry of Health – Drug Registration Certificate
The desired end result of enabling services for delivery via alternate channels is to facilitate the customers
to access the services in an easier and faster manner. Life cycle based representation of services is a
powerful tool towards this end. As per this concept, all services for a particular event say ‗starting a
business‘ should be available under a single umbrella and the customer should not be required to have
multiple touch points for the same.
In addition to classifying and prioritizing services, services must be integrated at the back-end based on
customer lifecycle approach. The services can be grouped by their customer base, and these can further be
mapped onto the various customer lifecycle events, where they each respond to a particular need of the
customer at a given time. Hence existing services can be identified based on life-cycle services approach
for the various customer groups— citizens/residents, businesses, visitors and government employees.
The figures below provides an illustration for the life-cycle of events for the citizens/residents, business,
visitors and government employees.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 241 Confidential
Birth
Education
Old Age
Youth and Family
Employment
Death
Housing
Legal Services
Public Utilities
Grievance Redress
Travel
Others
Birth Certif icate; Immunization
certif icate, others
Registration; Scholarship;
Results; Certif icates
Work permit; employment
benef its
Marriage; Divorce; Family
Counseling
Social Assistance; Pension
Death Certif icate; Wealth
Distribution
Building Permit; Sewerage;
Electricity and Water, Permits
Debt Collection; Civil Suits
All Services and Agencies
Electricity; Water; Telephone
Passport; Student; Pilgrim;
Scholarship
Informational Services; Fines;
Registration
Citizen/ Resident
Key servicesLifecycle events
Exploration
Starting Business
Regulatory
Operations
Funding
Closure/ selling of
business
Recruitment
Legal Services
Public Utilities
Expanding
business
Grievance redress
Others
Economic data; business
environment; regulations;
Registration; license; of f ice
setup
options, loans
Approvals; Advertising;
license; etc.
Returns; taxes; laws of land
etc.
cancellation of license; etc.
Work permit; visa; etc.
Debt Collection; Civil Suits
Opening braches; adding
activities
Electricity; Water; Telephone
All Services and Agencies
Real estate; environment;
compliance
Business
Key servicesLifecycle events
Joining
Recurring
Resignation/ retirement
Career Advancement
Employee Welfare
Others
work permit; ID creation; personal details; training
Salary transfer; time and attendance; performance
appraisal
Training/ Promotion/Transfer)
Cancellation of work permit; pension; grant
Loans; further studies
Leave management; employee grievances
Government
Employee
Key servicesLifecycle events
Recruitment Application; interview; offer
Travel within Ethiopia
Travel to Ethiopia
Tourism service providers
Others
Currency exchange; car rentals
Entertainment; food options, emergency contacts, local
customs
Licensing; online services provisioning
Leave management; employee grievances
Visitors
Key servicesLifecycle events
Enquiry Visa rules; travel agencies; destinations; weather; events;
accommodation, flight information
ExplorationInformation on Ethiopia;
brochures
Figure 35: Life-Cycle Services
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 242 Confidential
Annexure II: PMO Staffing Requirements
Considering the roles and responsibilities defined for various teams within PMO the table below proposes
the profiles of various members and the staffing strength for five years. The strength will be reviewed by
the end of every year.
Table 55: PMO staffing Requirements
S.
No
.
Team Title Numbers Key Roles and
Responsibilities
Knowledge
Areas (PMI) Y1 Y2 Y3 Y4 Y5
1. Project Co-
ordination
team
(technology
, process,
application,
Informatio
n Security)
Team Leader 1 1 1 1 1 • Monitoring the progress of various initiatives under e-Government Strategy with the help of team members.
• Managing the co-ordination between various Project Managers
• Project Integration Management
• Project Scope Management
• Project Time Management
Member
(Technology
)
1 1 1 1 1 • Monitoring the initiatives from technology perspectives.
Member
(Process)
1 1 1 1 1 • Monitoring the initiatives from business process perspectives.
Member
(Application
)
1 1 1 1 1 • Monitoring the development of various applications and ensuring the coherence with framework defined under the application architecture
Member
(Information
Security)
1 1 1 1 1 • Monitoring the initiatives for Information Security compliance.
2. Knowledge
Manageme
nt Team
Team Leader 1 1 1 1 1 • Facilitate information exchange and knowledge sharing across
Project
Communications
Management
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 243 Confidential
entities and projects.
Member 1 1 1 1 1 • Manages databases of various initiatives being implemented under Strategy
• Ensure standards are shared with PMs.
• Use best practices in project management to update standards as needed
Member 1 1 1 1 1 • Confirm the compliance of RFPs with the procurement policies.
• Maintain a tracker for procurement activities and share the same with identified stakeholders
3. Appraisal
Team
(technical
and
financial)
Team Leader 1 1 1 1 1 • Review and approve the evaluation done by team for received requests and share the recommendations
• Share Detailed Project Report standard template with Entities and provide necessary awareness and support.
• Project Scope Management
• Project Cost Management
Member
Technical
1 1 1 1 1 • Evaluate the project request to verify applicability
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 244 Confidential
and compliance with technical requirements.
Member
Financial
1 1 1 1 1 • Ensure sufficient financial details and breakdown is included in the request.
• Confirm availability of fund and identify sources and alternatives.
4. ITSG
experts
Team Leader 1 1 1 1 1 • Identify a pool of resources to support with implementations across the Ministries/Agencies.
• Interact with various entities to maintain a demand tracker for various kinds of resources.
• Identify external providers for resources
Project Human
Resource
Management
Member 1 1 1 1 1 • Maintain a database of skilled resources and companies
• Respond to the demand of resources raised by Ministries/Agencies.
5. Marketing
and
Awareness
Team Leader 1 1 1 1 1 • Review the Marketing and Awareness Strategy
• Design and Implement Marketing and Awareness Campaigns
• Marketing and Public Relations
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 245 Confidential
Team
Member
2 2 2 2 2 • Design and Implement Marketing and Awareness Campaigns
• Design and Implement Marketing and Awareness Campaigns
6. Monitoring
and
Evaluation
Team Leader 1 1 1 1 1 • Monitoring the Project Progress
• Review the M&E Framework
• Conduct Evaluations
• M&E of large e-Government Projects
Team
Members
2 2 2 2 2 • Monitoring the Project Progress
• Conduct Evaluations
• M&E of large e-Government Projects
7. Cadre
Control
Team Leader 1 1 1 1 1 • Control Promotion, transfers
• Administrative and HR functions
Team
Member
1 1 1 1 1 • Control Promotion, transfers
• Administrative and HR functions
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 246 Confidential
PMO Staffing Requirements – Background and Qualifications
Table 56: PMO Staffing Requirements
No. Title Background and Qualifications
1. Team Leader (Project
Coordination)
• Post graduate in Management with PMP certification.
• Minimum 8 years of experience in IT industry with 3 years in a Project Manager role
Member (Technology) • Graduate in Computer Science or IT related field with technical certifications in infrastructure and computer hardware
• Minimum 6 years of experience in IT industry
Member (Process) • Post graduate in MIS, Management or related field.
• Minimum 4 years of experience in business processes
Member (Information
Security)
• Graduate in Computer Science or IT related field with security certificates and/or technical infrastructure certifications. These can include CISSP, CISA, CISM, and other vendor specific certificates.
• Minimum 6 years of experience in IT and Information Security.
Member (Application) • Graduate in Computer Science or IT related field with certifications in enterprise architecture and/or software development.
• Minimum 6 years of experience in IT industry
2. Team Leader
(Knowledge
Management)
• Graduate in MIS, Management or related field with certification in Project Management
• Minimum 8 years of experience in industry with 3 years as a KM team leader
Member (Knowledge
Management)
• Graduate in MIS, Management or related field.
• Minimum 2 years of relevant experience
3. Team Leader
(Appraisal)
• Post graduate in Management with certifications. • Minimum 8 years of experience in industry with 3 years in a
Program Management Office of large implementation
Member (Technical) • Post graduate in Management with certifications. • Minimum 4 years of experience in industry with 3 years in a
Program Management Office of large implementation
Member (Financial) • Post graduate in Finance or qualified Chartered Accountant with certifications.
• Minimum 4 years of experience in industry with 2 years in a Financial Analysis role.
4.
Team Leader (ITSG
Experts)
• Post graduate in Human Resources Management with certifications.
• Minimum 8 years of experience in industry with 3 years in leading recruitment division of a big IT organization.
Member • Graduate in Computer Science/IT with certifications. • Minimum 2 years of experience in industry
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 247 Confidential
Team Leader (MIS ) • Post graduate in MIS, Management or related field. • Minimum 8 years of experience in industry with 5 years in a
similar position
5 Team Leader (Cadre
Control)
• Post graduate in Human Resources Management with certifications.
• Minimum 8 years of experience in industry with 3 years in leading HR division of a big IT organization.
Member • Graduate in HR. • Minimum 2 years of experience in industry
6. Team Leader
(Marketing and
Awareness)
• Post graduate in Marketing and Public Relations • Minimum 8 years of experience in industry with 5 years in
leading Marketing division of a big IT organization.
Member • Post Graduate in Marketing • Minimum 2 years of experience in Marketing in industry
Team Leader
(Marketing and
Awareness)
• Post graduate in IT/MIS with relevant certification • Minimum 8 years of experience in industry with 3 years in
handling large e-Governance Project as M&E Expert
Member • Minimum 3 years of experience in e-Governance
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 248 Confidential
Annexure III: Training Courses and Course Levels
Table 57: Training Courses and Course Levels
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 249 Confidential
Training Areas Available course curriculum
Basic Competent Advanced
Technology Management Training
1 Basic Computer Training
2 Network Design and Management √ √
3 Web-Designing and Management √ √
4 Setup and Management √ √
5 Hardware/ Server Sizing and Management √
6 BCP/ DR √
7 Configuration Management √
8 Quality Management √ √
9 SDLC √ √
10 Database and Storage Administration √
11 Information Security √
12 Emerging ICT Technologies √ √ √
13 Open Standards/ Interoperability √ √ √
14 Monitoring √
15 Knowledge Management √ √
16 IT Standards, Guidelines and Procedures √ √ √
17 Application Development (Languages: VB, C, C++,
Java, etc.)
√ √ √
18 Specialized Packages (e.g. AutoCAD, Tally, etc.) √
Project Management Training Basic Competent Advanced
1 IT Project Management √
2 Program Management √
3 Outsourcing Management √ √
4 Vendor Management √
5 General Management √ √ √
6 Strategic Management √ √ √
7 IT Project Evaluation/ Audit √ √
Change Management
1 Managing Change Basics √
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 250 Confidential
2 Human Resource Management √ √
3 Leadership Skills √ √ √
4 Intellectual Property Rights √
5 IT Acts, Policies and Regulations √
6 Application end-user Training √ √ √
7 Government Process Re-engineering √ √
8 Risk Analysis √
9 Champions Training Program √
10 Legal Reforms √ √
11 Business Process designing & detailing; BPM √ √ √
Training Areas Include in which syllabus
Basic Competent Advanced
Financial Management
1 Defining and Understanding Total Cost of
Ownership (TCO)
√
2 Negotiation and Conflict Resolution Skills √
3 Procurement Process (especially licensing cost) √ √
4 Financial Management √ √
5 PPP Modeling √ √
Soft Skills
1 Communication and Presentation Skills √ √
2 Relationship Management √ √ √
3 Team Building √ √ √
4 Technical Report Writing Skills √ √
5 Personal effectiveness Skills √ √
6 Publicity and Awareness/ PR Skills √ √
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 251 Confidential
Annexure IV: Detailed Marketing and Awareness Strategy
Design of the marketing and awareness campaign will include five key components, each of which should
be defined and described in as much detail as possible during the planning and design stage:
Identifying target market segments
Channel (media mix) selection
Timing
Message development
Audience skills and education
Target market segments
One marketing medium cannot reach all segments of the diverse community that makes up the Country of
Ethiopia. Marketing campaigns do best when they define specific target markets and deliver a tailored
marketing programme for each market.
Our prior experience with e-Government awareness campaigns indicates that billboards and traditional
media – such as television and radio – alone will not be sufficient to penetrate the target market with
news of the e-Government services. We also recommend presentations at schools, community
organizations and events to supplement billboards and traditional advertising. Additionally we could also
look at the mosques for distribution of flyers and leaflets. These marketing outlets will provide an
opportunity for the Country to tailor specific messages to individual communities.
One way of segmenting the potential users for e-Government services is into four groups as illustrated in
Table 21 below.
Table 58: Target Market Segments
Audience categories Segmentation basis
Business Size of business
Industry
Citizens and residents Further segmentation based on
Education levels
Age
o Elderly
o Younger generation
Income groups
People with special needs
Socially underprivileged
Visitors Business travellers
Tourists
Government employees For all personnel (awareness of the overall eGovernment strategy)
Agency personnel (agency’s eGovernment programme)
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 252 Confidential
At a finer level of granularity, within the residential segment there are several specific segments of the
Country‘s population that are traditionally harder to reach:
Elderly
Uneducated
Socially underprivileged
People with special needs
Within the business community, there may be particular groups that will require special targeting. For
example, if the Country launches a web application that enables applications for scholarships to be
submitted online, it may be necessary to market this service to the students and their parents.
In the case of both specific residential and business segments, the Country should consider using specially
targeted media. For example, a greater use of personal communications channels, such as outreach
through community organizations, working with opinion leaders, and developing word-of-mouth, may be
more appropriate to reach the elderly and non-Ethiopian communities. In contrast, methods such as
direct mail may be the best way to get messages across to segments of the business community.
Communication and media channel mix
An appropriate communication and media channel mix is critical to ensure that everyone in the target
audience receives and understands the campaign messages. Given customer diversity, any awareness-
raising campaign that relies too heavily on just one medium or type of communication is unlikely to
achieve its goals. However, there could be services which might be targeted at only a small segment of the
society which would require targeted campaign through the channels and media of the choice of that
segment. E.g. Pensions is one service that will only be targeted at the people in the old age, so the
campaign will have to be directed through the medium which is most appealing to the old age segment.
Suggested channels for different segments are illustrated in the table below.
Table 59: Effectiveness of Media Channels by Marketing Segments
Ne
ws
pa
pe
rs
T V
Bil
lbo
ard
s
Dir
ec
t M
ail
er
s
Ag
en
cy
Off
ice
s
Ma
lls
Bu
se
s /
Sh
elt
ers
Te
lep
ho
ne
Bo
ok
s
Bu
sin
ess
Pu
bli
ca
tio
ns
Ch
am
be
rs
of
Co
mm
er
ce
Mo
sq
ue
s
Sc
ho
ols
Lib
ra
rie
s
Ho
sp
ita
ls
Ev
en
ts
Wo
rk
sh
op
s
Cit
izen
s
an
d
Res
iden
ts
Eld
erly
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 253 Confidential
Yo
un
ger
Gen
era
tio
n
Ara
bic
Sp
eak
ing
Un
-
edu
cate
d
Bu
sin
ess
Go
ver
nm
ent
Em
plo
yee
s
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 254 Confidential
Annexure V: Detailed Project Report - Template
Some of the important Areas to be included in Detailed Project Report are as follows
1. Background of initiative and other basic information
2. Initiative overview or summary
Overview
Input and output
costing
source of funding
3. Initiative details including implementation model
Goal and objectives of initiative
Stakeholder analysis
Service and service levels
Implementation strategy
Key activities (‗As Is Study‘, ‗Process Re-engineering‘, ‗Change Management‘ etc.)
Infrastructure requirements including technology
Sustainability Plan
4. Way forward
5. Plan for implementation
A Sample Detailed Template for preparation of a DPR is given below
TABLE OF CONTENTS
1 EXECUTIVE SUMMARY
2 INTRODUCTION
2.1 ABOUT MINISTRY IMPLEMENTING THE PROJECT
2.2 IT INITIATIVES, PLANS OF MINISTRY
2.3 About Project
3 PROJECT OBJECTIVES
3.1 E-GOVERNMENT STRATEGY INITIATIVE OF GOVERNMENT
3.2 PROJECT OBJECTIVES
3.3 SCOPE OF WORK
4 SERVICES ENVISAGED – PRESENT AND FUTURE
5 SERVICES CURRENTLY OFFERED AND AS - IS IT SCENARIO
5.1 PRESENT IT SCENARIO IN MINISTRY
5.2 SERVICES CURRENTLY OFFERED
6 TARGET BENEFICIARIES
7 STAKEHOLDERS - ROLES AND RESPONSIBILITIES
8 STAKEHOLDERS’ EXPECTATION
8.1 CITIZEN
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 255 Confidential
8.2 ADMINISTRATION
8.3 FEDERAL GOVERNMENT
9 BUSINESS MODEL
10 BUSINESS PROCESS RE-ENGINEERING
10.1 REQUIREMENT FOR BPR
10.2 BPR METHODOLOGY
11 SERVICE LEVELS AND MEASUREMENT
12 CAPITAL EXPENDITURE
13 OPERATING EXPENSES
14 CAPACITY BUILDING, TRAINING REQUIREMENTS
15 CONTRACTING ARRANGEMENTS
16 RISK MANAGEMENT
17 KEY SUCCESS FACTORS
18 SERVICE DELIVERY MECHANISM
19 IMPLEMENTATION METHODOLOGY & STRATEGY
20 PROJECT MANAGEMENT AND MONITORING
20.1 PROJECT MANAGEMENT METHODOLOGY
20.2 PROJECT MANAGEMENT AND MONITORING STRUCTURE
21 MILESTONES & ESTIMATED PROJECT TIME SCHEDULE
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 256 Confidential
Annexure VI: Services Prioritization Framework
The implementation of the e-Services has been phased out as part of the phasing out of the sub-projects
under the various Agency Priority Projects. However, during the implementation phase, there may be
unforeseen exigencies that may warrant a further prioritization and phasing of the services planned
during a given year. In order to address the same, a services prioritization framework has been designed
so that the Government of Ethiopia can leverage the same to conduct this prioritization and phasing in a
scientific manner.
The list of services to be electronically enabled should be prioritized using the criticality-feasibility model.
This model facilitates the prioritization and phasing of services and initiatives based on their importance
(criticality) and the ease of implementing them through electronic channels (feasibility).
Criticality should be evaluated though an assessment of:
Strategic Fit – Does this service fit into Ethiopian e-Government strategy?
Visibility – Will creating this service promote a positive image of Government of Ethiopia to
constituents and businesses?
Cost Savings -- Does providing this service over the alternate channels generate cost savings for
Ethiopia?
Revenue generation – Could electronically-enabling this service potentially provide a new
revenue source for the Government?
To determine feasibility, following would be assessed:
Market Readiness – What is the number of customers that use the service? Are customers
demanding this service?
Operational Readiness – Are the ministries and agencies ready from a technology and
capability standpoint, to undertake this project?
Development Cost - Are development costs relatively low or high?
Leveragability – Can the service leverage an existing application? If a new application must be
built, will other applications be able to leverage it?
The criticality and feasibility framework will allow the Government of Ethiopia to determine the phasing
and prioritization of the initiatives in the following manner
Defer – If there is low criticality and low feasibility, the application should not be
undertaken. Low criticality implies little gain and low feasibility implies relatively high risk. So
such services should be taken up in the end.
Permit – If there is low criticality but high feasibility Government of Ethiopia should allow
the development of the application as long as it follows the Standards and Guidelines and uses the
overall infrastructure. Low criticality implies little gain, but high feasibility implies relatively few
risks. This type of project should be allowed.
Pursue – If there is high criticality but low feasibility, Government of Ethiopia should allow
the application to be built. High criticality implies that there is customer demand for such a service or
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 257 Confidential
that significant benefits could be realized from this application, but low feasibility implies that there
may be significant risks.
Target – If there is high criticality and high feasibility, Ethiopia should build this application.
High criticality implies customer demand and benefits to the organization and high feasibility implies
relatively few risks in pursuing this application. Such services should be taken up at the earliest as
they would provide maximum gains with least amount of effort.
Pursue Target
Defer Permit
High Criticality
Low Criticality
Hig
h F
easib
ilit
y
Low
F
easib
ilit
y
Pursue Target
Defer Permit
High Criticality
Low Criticality
Hig
h F
easib
ilit
y
Low
F
easib
ilit
y
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 258 Confidential
Annexure VII: ICT Standing of Ethiopia – Some international Rankings
UN e-Readiness Index
Ethiopia has consistently been ranked around 170 marks on the UN e-Readiness Index in the past few
years as shown in the table below.
Year Ranking
2005 171
2008 172
2010 172
The UN e-readiness Index is evaluated based on the Web maturity, Infrastructure and Human Capital
available in the country. Ethiopia has made significant progress in the web measure index over the years
but the Infrastructure component of the index has been relatively low as seen in the Chart below.
Ethiopia must target to break into the 150 mark on the countries ranking by the next
UN Rankings by targeting a Web Measure Index of 0.3, Infrastructure Index of 0.05
and Human Capital index of 0.39.
0
0.05
0.1
0.15
0.2
0.25
0.3
0.35
0.4
0.45
e-readiness Index Web measure
index
Infratrucure Index Human Capital
Index
2005
2008
2010
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 259 Confidential
The Web Measure Index
The Web Measure Index is based upon a five-stage model, which builds upon the previous levels of
sophistication of a country‘s online presence. As a country migrates upwards through the various stages, it
is ranked higher in the web measure index.
Figure - Stages of UN Web Measurement Index
The Telecommunication Infrastructure Index
The Telecommunication Infrastructure Index is a composite index of five primary indicators relating to a
country‘s infrastructure capacity as they relate to the delivery of eGovernment services. These are:
1. Internet Users /100 persons
2. PCs /100 persons
3. Main Telephones Lines /100 persons
4. Cellular telephones /100 persons
5. Broad banding /100 persons
The Human Capital Index
The Human Capital Index is a composite index of the adult literacy rate and the gross enrolment ratio
(including primary, secondary and tertiary enrollment), with two thirds weight given to the adult literacy
rate and one third to the gross enrolment ratio.
Connected
Transactional
Interactive
Enhanced
Emerging Current State of Ethiopia
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 260 Confidential
ICT DEVELOPMENT INDEXES - 2008 RANKING:
International Telecommunication Union (ITU) places Ethiopia 154th in Global IT Development Index.
The best and the worst performing countries in ICT Development as per ITU are illustrated below
Economy Rank
2008
IDI 2008 Rank
2007
IDI 2007
Sweden 1 7.85 1 7.27
Singapore 14 6.95 15 6.47
United
States
19 6.54 17 6.33
India 117 1.75 116 1.62
Tanzania 149 1.17 151 1.05
Ethiopia 154 1.03 153 0.97
Niger 158 0.9 157 0.86
Chad 159 0.79 159 0.73
The following section illustrates the three major Methodologies to assess the ICT status of Ethiopia.
I. ICT Opportunity Index
II. ICT Development Index
III. ICT Price basket
I. ICT Opportunity Index:
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 261 Confidential
In this method, the evaluation is broadly categorized into Information density and Information Usage.
Information Density comprises of the ICT Networks which is further broken down into sub index of Fixed
Telephone lines, Internet Bandwidth and Mobile subscriptions and ICT Skills which is a basic
requirement for accessing and comprehending the Information. The ICT Skills basically comprises of the
literacy indicators and School enrolment indicators. Information Usage is further broken down into ICT
Usage intensity comprising of Broadband subscription and International outgoing telephone traffic and
the ICT Usage uptake comprising of PC, TV and Internet usage as illustrated in the diagram below.
Ethiopia - ICT Opportunity Index Analysis:
As seen in the above graph, Ethiopia is much below the Low Average in the ICT Skill Levels. The ICT
Uptake which is the usage of PC, TV and Internet is strikingly lower than the Low Average of 63
Countries. The ICT Intensity which is mainly driven by the telephone traffic is relatively better at the same
level as the Low average of countries.
0
50
100
150
200
250
index 104.7 8.7 26.2 103.6 229.6
South
Africa
Ethiopia LOW
AVERAGE
(63
economies)
MEDIUM
AVERAGE
(63
economies)
UPPER
AVERAGE
(28
economies)
SKILLS
UPTAKE
INTENSITY
ICT-OI
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 262 Confidential
II. ICT Development Index
The ICT Development Index method mainly helps to assess the ICT Impact and Outcomes by evaluating
the ICT Access, ICT Usage and ICT Capability of the country. Following is the ICT Index status of Ethiopia
benchmarked against Average values for Indicators.
ICT INDEX 2008 Average Value Ethiopian
Values
Ethiopian Rank
(out of 159
Countries)
ICT Development
Index
3.58 1.03 154
Access 4.07 1.33 148
Usage 1.7 0.01 157
Skills 6.37 2.43 153
Parameters for ICT Development Index:
Following is the description of key parameters used in deducing the ICT Development Index. Ethiopia
which is ranked 154th in this Index needs to focus and improve these parameters in order to go up the
ranking table.
A. Access sub-index:
This index captures ICT readiness and includes five infrastructure and access indicators
fixed telephony,
mobile telephony,
international
Internet bandwidth,
households with computers,
households with Internet
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 263 Confidential
B. Use sub-index:
This index captures ICT intensity and includes three ICT intensity and usage indicators
Internet users,
fixed broadband,
mobile broadband
C. Skills sub-index:
This index captures ICT capability or skills as indispensable input indicators and includes three
proxy indicators
adult literacy,
gross secondary and tertiary enrolment
The skills sub-index therefore has less weight in the computation of the IDI compared to the other two
sub-indices.
ICT Development Index: Benchmarking with Average values
Ethiopian ICT Development has a huge gap to bridge in order to reach the minimum average global
standards of ICT as indicated in the graph below:
III. ICT Price Basket Analysis:
0
1
2
3
4
5
6
7
Average Value
Ethiopian Values
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 264 Confidential
The third approach of ICT Assessment is the ICT Price Basket Analysis where the affordability and pricing
of the ICT services is benchmarked against global standards as indicated in the picture below.
Ethiopia - ICT Price Basket Ranking and key statistics:
Ethiopia is ranked at 140th position out of 161 countries evaluated for ICT Price basket as indicated in the
following table. When compared to a developing country like India, Ethiopia fares similar to India in
Fixed Telephone rates and 6.5 times higher rate than in India for Cellular rates. But the major obstacle to
the Ethiopian ICT Development is the broadband rate which is 360 times higher than that in India and
3600 times higher than that in Singapore.
Details Ethiopia India Singapore
Rank Economy(out of 161
Countries)
140 81 3
ICT Price Basket 37.98 3.64 0.33
Fixed telephone sub-
basket as a % of GNI per
capita(2009)
3.76 3.5 0.27
Mobile cellular sub-basket
as a % of GNI per
capita(2009)
10.19 1.57 0.14
Fixed broadband sub-
basket as a % of GNI per
capita(2009)
2085.05 5.84 0.58
GNI per capita, US$, 2008 280 1'070 34'760
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 265 Confidential
AFRICAN ICT STATISTICS:
Even amongst the African countries, Ethiopian ICT status falls much below the rest of the countries as
illustrated in the following table and graphs.
Country Fixed
telephon
e lines
per 100
inhabita
nts
Mobile
cellular
subscriptions
per 100
inhabitants
International
Internet
bandwidth
per Internet
user(bit/s)
Proportion
of
households
with
computer
Proportion
of
household
s
with
Internet
Ethiopia 1.1 1.5 842 0.2 0.1
Kenya 0.
7
30.2 112 5.5 2.2
Sudan 0.
9
21.3 3800 4.3 1
Egypt 14.
9
39.8 1023 16.1 9.1
Nigeria 1.1 27.3 69 5.1 3.6
South
Africa
9.
6
87.1 852 14.8 4.8
ICT Price Basket
Fixed telephone sub-basket as a % of GNI
per capita(2009)
Mobile cellular sub-basket as a % of GNI
per capita(2009)
Fixed broadband sub-basket as a % of GNI
per capita(2009)
37.98
3.76
10.19
2085.05
3.64
3.5
1.57
5.84
0.33
0.27
0.14
0.58
ICT Price Basket Analysis
Singapore India Ethiopia
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 266 Confidential
0102030405060708090
100
Mobile cellular subscriptions per 100
inhabitants
Mobile cellular subscriptions
per 100 inhabitants
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 267 Confidential
Source: ITU World Telecommunication/ICT Indicators Database
0123456789
10
Proportion of households with Internet
Proportion of households
with Internet
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 268 Confidential
Annexure VIII: Risk in E-Government Strategy Implementation
Implementation of such a large program such as the National E-Government Strategy will naturally
involve many risks and it is important to identify and plan for the management of the different kinds of
risks which will arise in course of the Program Implementation.
The risks may be categorized broadly under two heads i.e. Program Level and Project Level
Program level Risks
These, among others will include
Change in Government priorities or requirements due to unexpected circumstances
Budgetary constraints
Change in Leadership at top levels leading to disruption or modifications
Issues in Governance structure in terms of lack of PMO or inadequate coordination between
stakeholders, etc
Project level Risks
At the project level, the risks would include
Shortage of required human resources
Lack of availability of required skill sets for implementation
Poor project management processes and practices
Inadequate detailed documentation whether DPR or RFP etc, which will lead to delays and
problems in implementation
Inadequate capacity of selected vendors and vendor management issues
The above are a few of the envisaged risks while implementing a large program. It is hence important that
the required Governance structure to oversee and monitor this kind of a program is created and standard
practices and processes are followed.
It is important that a risk identification and management strategy is created at start of adoption of the
strategy and is continuously tracked and updated. Project management, including risk management
templates are provided in the following Annexure. Risk Management will one of the important activities
of PMO
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 269 Confidential
Annexure IX: Sample Project Management templates
1. Minutes of meeting Format
{insert name of meeting} meeting agenda and minutes
Meeting
Date:
Time:
Facilitator: Recorder
:
Location: Number
of Pages:
Distribution and Attendee List: (X indicates that the member was present; T indicates present
via teleconference, A - Absent)
***Visitors-
Agenda:
Item Category: A - action D - decision R - action rolled over C - complete N -
note
Nb
r.
Topic A/C/
D/N/
R
Time
Frame
Start
Time
Responsibl
e
1.
2.
3.
4.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 270 Confidential
Annotated Agenda & Minutes:
Topic 1.
Discussion:
Topic 2.
Discussion:
Topic 3. Team
Discussion:
Future Meeting Schedule
Date Time Location Facilitator/Scrib
e
Future Agenda Item(s)
Agenda Item Planned
Date(s)
Priorit
y
Time Responsib
le
Action Items
Open Action Items
# Create
Date
Action Item Assigned Target
Date
1
2
3
4
6
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 271 Confidential
Closed Action Items
# Create
Date
Action Item Assigned Target
Date
1
Issues Opened
# Open
Date
Issue Description Assigned Target
Date
Category
(1/2/3)
Priority
(H/M/L)
Risks Opened
# Open
Date
Title Assigned
to
Target
Date
Category
(1/2/3)
Impact
(1/2/3/4/5)
Probability
(0-100%)
Cost
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 272 Confidential
2. Project Charter Template
VERSION: [VERSION NUMBER]
Pre-Requisites for this Document None
Review and Approval of the Project Charter indicates an understanding of the purpose and
content described in this document. By signing this deliverable, each individual agrees work
should be initiated on this project and necessary resources should be committed as described
herein.
Title Name Signature Date
Owner Ministry/Agency
PMO Head
PMO Programme Manager
PMO Finance
Revision Any revision of content in this document needs approval as per the below table. Review and Approval of the Project Charter indicates an understanding of the purpose and content described in this document. By signing this deliverable, each individual agrees work should be initiated on this project and necessary resources should be committed as described herein
Revision SNo. 1 Revision Date
Title Name Signature Date
Owner Ministry/Agency
PMO Head
PMO Programme Manager
PMO Finance
Revision SNo. 2 Revision Date
Title Name Signature Date
Owner Ministry/Agency
PMO Head
PMO Programme
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 273 Confidential
Manager
PMO Finance
Contents Section 1. Project Overview 1.1 Problem Statement 1.2 Project Goals and Objectives 1.3 Project Scope 1.4 Assumptions 1.5 Constraints 1.6 Risks Section 2. Project Authority and Milestones 2.1 Funding Authority 2.2 Project Oversight Authority 2.3 Major Project Milestones Section 3. Project Organization 3.1 Project Structure 4 3.2 Roles and Responsibilities Section 4. Points of Contact ……………………………………………………………………………………………………………………… Section 1. Project Overview 1.1 Problem Statement
Describe the business reason(s) for initiating the project, specifically stating the business problem.
Problem Statement
1.2 Project Goals and Objectives
Describe the business goals and objectives of the project.
Sno Problem Goals and Objectives
1.3 Project Scope
Describe the project scope. The scope defines project limits and identifies the products and/or services
delivered by the project. The scope establishes the boundaries of the project and should describe
products and/or services that are outside of the project scope.
Sno Project Includes
Sno Project Excludes
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 274 Confidential
1.4 Assumptions
Describe any project assumptions related to business, technology, resources, scope, expectations, or
schedules.
Sno Assumptions
1.5 Constraints
Describe any project constraints being imposed in areas such as schedule, budget, resources, products to
be reused, technology to be employed, products to be acquired, and interfaces to other products. List the
project constraints based on the current knowledge today.
Sno Constraints
1.6 Risks
Describe any events or conditions that may occur, and whose occurrence, if it does take place, has a
harmful or negative effect in your project
Sno Risks
Section 2. Project Authority and Milestones
2.1 Funding Authority
Funding Authority Estimated Budget –ETB/USD
2.2 Project Oversight Authority
Describe management control over the project. Mention any external oversight bodies, Programme
Management office, etc
Oversight Authority Owner Directorate
2.3 Major Project Milestones
List the expected duration of the project and its major milestones and deliverables and the planned
completion dates for delivery. This list should reflect products and/or services delivered to the end user
as well as the delivery of key project management or other project-related work products.
Expected Total Duration of project
Milestone/Deliverable Planned Completion Date
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 275 Confidential
Section 3. Project Organization 3.1 Project Structure
Assign a Project Manager and describe the initial organizational structure of the project team and
stakeholders, preferably providing a graphical depiction.
Project Manager
Initial Project Organization Structure
3.2 Roles and Responsibilities
Summarize roles and responsibilities for the project team and stakeholders identified in the project structure above.
Role Responsibility
Section 4. Points of Contact
Identify and provide contact information for the primary and secondary contacts for the project.
Primary Contact Name/Title/Organization Phone Email Secondary Contact Name/Title/Organization Phone Email
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 276 Confidential
3. Project Closure Template
PROJECT CLOSURE REPORT
[PROJECT NAME]
VERSION: [VERSION NUMBER] Pre-Requisites for this Document None
Title Name Signature Date
Project Manager
Owner Ministry/Agency
Programme manager
PMO Head
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 277 Confidential
Prepared By
Document Owner(s) Project/Organization Role
Project Closure Report Version Control
Version Date Author Change Description
TABLE OF CONTENTS PROJECT CLOSURE REPORT [PROJECT NAME] 1 PROJECT CLOSURE REPORT PURPOSE 2 PROJECT CLOSURE REPORT GOALS 3 PROJECT CLOSURE REPORT SUMMARY 3.1 Project Background Overview 3.2 Project Highlights and Best Practices 3.3 Project Closure Synopsis 4 PROJECT METRICS PERFORMANCE 4.1 Goals and Objectives Performance 4.2 Success Criteria Performance 4.3 Milestone and Deliverables Performance 4.4 Schedule Performance 4.5 Budget Performance 4.6 Metrics Performance Recommendations 5 PROJECT CLOSURE TASKS 5.1 Knowledge Management 5.2 Issue Management 5.3 Risk Management 5.4 Quality Management 5.5 Communication Management 5.6 Asset Management 5.7 Lessons Learned 5.8 Post project Tasks 5.9 Project Closure Recommendations
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 278 Confidential
PROJECT CLOSURE REPORT PURPOSE
Project Closure Report Purpose
The Project Closure Report is the final document produced for the project and is used
by senior management to assess the success of the project, identify best practices for
future projects, resolve all open issues, and formally close the project.
PROJECT CLOSURE REPORT GOALS
Project Closure Report Goals
[Replace this text with your own statement of goals, or use the following
sample.]
This Project Closure Report is created to accomplish the following goals:
Review and validate the milestones and success of the project.
Confirm outstanding issues, risks, and recommendations.
Outline tasks and activities required to close the project.
Identify project highlights and best practices for future projects.
PROJECT CLOSURE REPORT SUMMARY
Project Background Overview
Project Background Overview
[Replace this text with a brief description of the project background.
What were the original goals, objectives, and success criteria?
Refer to project overview statement and/or project charter for this information.]
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 279 Confidential
Project Highlights and Best Practices
Project Highlights and Best Practices
Project Highlights:
[Highlight]
[Highlight]
Best Practices:
[Best practice]
[Best practice]
Project Closure Synopsis
Project Closure Synopsis
[Replace this text with a brief description of why the project is being
closed.
Is it being closed because all project objectives and deliverables have been met?
Or is it being closed for other reasons (loss of funding, shift in strategy, etc.)?]
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 280 Confidential
PROJECT METRICS PERFORMANCE
Goals and Objectives Performance
Goals and Objectives Performance
[Replace this text with a comparison of actual project performance to
project objectives.]
Success Criteria Performance
Success Criteria Performance
[Replace this text with details of project performance in terms of targeted
success criteria.
Were all criteria achieved? To what level of success?
If some criteria were not achieved, what were the reasons? Is achievement anticipated at a later date?
Who is responsible for measuring continued progress?]
Milestone and Deliverables Performance
Milestones and Deliverables Performance
[Replace this text with an outline of actual performance of project
milestones and corresponding deliverables.
Were all deliverables achieved with high quality and customer acceptance?
If not, what were the reasons?
Is achievement anticipated at a later date?]
Schedule Performance
Schedule Performance
Project Schedule Overview:
[Replace this text with the overview.]
Project Schedule Corrective Actions:
[Replace this text with the corrective actions.]
Budget Performance
Budget Performance
Project Budget Overview:
[Replace this text with the overview.]
Project Budget Corrective Actions:
[Replace this text with the corrective actions.]
Metrics Performance Recommendations
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 281 Confidential
Metrics Performance Recommendations
[Replace this text with an outline of metrics performance
recommendations for the future.]
PROJECT CLOSURE TASKS
Knowledge Management
Knowledge Management
[Replace this text with an explanation of how knowledge can be managed.
Explain how project knowledge (IP) from project team members will be captured and retained for future projects.]
Issue Management
Issue Management
[Replace this text with a list of any issues still outstanding at the end of the
project.
Will each issue be resolved?
Who will continue to report on each issue's progress?]
Risk Management
Risk Management
Project Risks Mitigated:
[Replace this text with the risks mitigated.]
Outstanding Project Risks:
[Replace this text with the outstanding risks.]
Quality Management
Quality Management
[Replace this text with a description of how quality management processes
were used and integrated into the project, and how quality control
measures provided quality assurance.]
Communication Management
Communication Management
[Replace this text with an outline of the project communication process.
How effective was the process?
What changes were made during the project?]
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 282 Confidential
Asset Management
Asset Management
[Replace this text with a list of assets remaining at the end of the project.
How will those assets be dispositioned?
Who will manage the disposition process?]
Lessons Learned
Lessons Learned
[Replace this text with a list of successes and shortcomings to remember
for the future.
Which activities and processes worked well?
Which could have been improved, and how?]
Post project Tasks
Post project Tasks
[Replace this text with a list of outstanding issues for this project.
What actions are not yet completed? Who is responsible for them?
Which success criteria are not yet met? Which deliverables are not yet achieved?
Which training requirements are still outstanding?
This information can be summarized from details in the preceding sections.]
Project Closure Recommendations
Project Closure Recommendations
[Replace this text with a list of recommendations arising from review of
closure tasks.
The main recommendation would usually be to gain project closure approval from the Project Sponsor, including agreement that the project has fulfilled all of the requirements as documented and that the Project Sponsor is satisfied that all outstanding items have been satisfactorily addressed.]
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 283 Confidential
4. Project Status Report Template
Project Name Project Manager
Owner Ministry/Agency
PMO Representative name
Project Start Date Estimated Date of Go-Live Modified?
(Mark ―Modified‖ if there is any change in the date from last week.)
SNo. 1
Estimated Project End Date Modified? SNo. 1 (Indicates the SNos of tasks that resulted in change of dates)
Project Status Meeting details Date & Place of Meeting
MoM
Status of Planned activities
SNo. Activity description Activity type
Status Remarks
Project Task / Action Task
Completed / In Progress / Delayed / Not Started
Targets for next week
SNo. Activity description Activity type
Status Remarks
Project Task / Action Task
Completed / In Progress / Delayed / Not Started
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 284 Confidential
5. Project Snapshot Template
P R O G R A M S N A P S H O T Q U A R T E R L Y O U T C O M E S
PQ TQ Change
eGovernment Program Start Date
Number of services online
PMO Creation Date Number of transactions through alt. channels
Expected Program End Date
Customer Satisfaction Index (CSI)
Government Transformation Index (GTI)
United Nations eGovernment Readiness Ranking
Global
Africa
P R
O J
E C
T
V I
E W
Project Name Stage Status Priority End Date (Expected /
Actual)
Financial Progress
Services online
Support Required
Responsible Directorate
C-D-I H-M-L Allocated Actual Y-N
C H
A N
N E
L
V I
E W
Channel Name Stage Status Date for Pilot (Expected /
Actual)
Date for roll-out
(Expected / Actual)
Financial Progress
Support Required Responsible Directorate
C-D-I Allocated Actual Y-N
eGovernment Portal
National Call Centre
Common Service Centres
Mobile Portal
Kiosk
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 285 Confidential
E N
A B
L E
R
V
I E
W
Enabler Name Status Financial Progress
Deliverables Support Required
Responsible Directorate
Allocated Actual PQ TQ Y-N
Marketing and Awareness
eGovernment Awards
eGovernment Benchmarking
M&E - CSI Evaluation
M&E - GTI Evaluation
Standards and Policies
Customer Charter Framework
Government Process Reforms (GPR)
Capacity Building
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 286 Confidential
6. Risk Management Template
Project Name:
Date: Release: Draft/Final
Author:
Owner:
Client:
Document Number:
Note: This document is only valid on the day it was printed
Revision History
Date of next revision:
Revision
Date
Previous
Revision
Date
Summary of Changes Changes
Marked
Approvals
This document requires the following approvals. A signed copy should be placed in the project files.
Name Signature Title Date of
Issue
Version
Distribution
This document has been distributed to:
Name Title Date of
Issue
Version
Overview
Purpose A Risk Management Strategy describes the specific risk management
techniques and standards to be applied and the responsibilities for achieving an
effective risk management procedure.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 287 Confidential
Contents The Risk Management Strategy should cover the following topics.
Introduction 288
Risk Management Procedure 288
Tools and Techniques 288
Records288
Reporting 288
Timing of Risk Management Activities 288
Roles and Responsibilities 288
Scales 289
Proximity 289
Risk Categories 289
Risk Response Categories 289
Early-warning Indicators 289
Risk Tolerance 289
Risk Budget 289
Advice The Risk Management Strategy is derived from the: Project Brief; Business
Case; The corporate or programme management’s risk management guide,
strategy or policy.
A Risk Management Strategy can take a number of formats, including: Stand-
alone document or a section in the Project Initiation Document; Entry in a
project management tool.
The following quality criteria should be observed:
Responsibilities are clear and understood by all parties
The risk management procedure is clearly documented and can be
understood by all parties
Scales, expected value and proximity definitions are clear and
unambiguous
The chosen scales are appropriate for the level of control required
Risk reporting requirements are fully defined.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 288 Confidential
Introduction
(States the purpose, objectives and scope, and identifies who is responsible for the strategy)
Risk Management Procedure
(A description of (or reference to) the risk management procedure to be used. Any variance from
programme management standards should be highlighted, together with a justification for the variance.)
The procedure should cover activities such as:
Identify
Assess
Plan
Implement
Communicate
Tools and Techniques
(Refers to any risk management systems or tools to be used, and any preference for techniques which may
be used for each step in the risk management procedure)
Records (Definition of the composition and format of the Risk Register and any other risk records to be used by the project) Reporting (Describes any risk management reports that are to be produced, including their purpose, timing and recipients) Timing of Risk Management Activities (States when formal risk management activities are to be undertaken - for example, at end stage assessments) Roles and Responsibilities (Defines the roles and responsibilities for risk management activities)
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 289 Confidential
Scales (Defines the scales for estimating probability and impact for the project to ensure that the scales for cost and time (for instance) are relevant to the cost and timeframe of the project. These may be shown giving the criteria for each level within the scale, e.g. for ‗very high‘, ‗high‘, ‗medium‘, ‗low‘ and ‗very low‘)
Proximity
(Guidance on how proximity for risk events is to be assessed. Proximity reflects the fact that risks will
occur at particular times and the severity of their impact will vary according to when they occur. Typical
proximity categories will be: imminent, within the stage, within the project, beyond the project)
Risk Categories
(Definition of the risk categories to be used (if at all). These may be derived from a risk breakdown
structure or prompt list. If no risks have been recorded against a category, this may suggest that the risk
identification has not been as thorough as it should have been)
Risk Response Categories
(Definition of the risk response categories to be used, which themselves depend on whether a risk is a
perceived threat or an opportunity)
Early-warning Indicators
(Definition of any indicators to be used to track critical aspects of the project so that if certain predefined
levels are reached, corrective action will be triggered. They will be selected for their relevance to the
project objectives)
Risk Tolerance
(Defining the threshold levels of risk exposure, which, when exceeded, require the risk to be escalated to
the next level of management. (For example, a project-level risk tolerance could be set as any risk that,
should it occur, would result in financial loss. Such risks would need to be escalated to corporate or
programme management.) The risk tolerance should define the risk expectations of corporate or
programme management and the Project Board)
Risk Budget
(Describing whether a risk budget is to be established and, if so, how it will be used)
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 290 Confidential
Annexure X: List of Services
Projects Total Services
Informational Services
G2C G2B Total Services
Transactional Services
G2C G2B
e-Agriculture
Provision of data on the Agro-processing Industry.
Yes Yes Agricultural Product Inspection and Certification Services for Investors or any Business man who is engaged in import and/or export of plant and animals products for commercial purpose
Yes
Crop Failure Reports
Yes Yes Application for python sanitary inspection on export and import.
Yes
Provision of information on Enabling Environment, Financing, and Infrastructure in the agro-processing industry.
Yes Application for the import or export pesticide for commercial purpose
Yes
Provision of Information on Market Fragmentation and Investment Potential.
Yes Yes Application for plant import permit,
Yes
Provision of Information on Quality Standard Implementation and Certification.
Yes Application form to obtain the land
Yes
Provision of Information on Competition Indicators in the Agricultural sector.
Yes Provision of Information on the potential Agricultural land
Yes
Provision of Information on Investment Incentives in the Agro-processing Industry.
Yes Technical and Administration support
Yes
Information on prices of Fertilizers, Pesticides, Seeds, and Crops.
Yes Yes Continuous follow-up and support on the land use, Land management
Yes
Technical services and support for farmers.
Yes Yes Custom clearance certificate for agriculture imports
Yes
Information on livestock disease control & surveillance
Yes Yes Certificate of competence on agriculture
Yes
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 291 Confidential
Projects Total Services
Informational Services
G2C G2B Total Services
Transactional Services
G2C G2B
Information on animal infrastructure distribution & personnel
Yes Certificate of import & export of animal & crop products
Yes
Information on quarantine inspection and certification
Yes Irrigation Request by farmers.
Yes
Information on rural land admin. Policies, procedure & guidelines
Yes Yes Loan services for crops Yes
Information on natural resources conservation
Yes Fertilizer Service/ purchase
Yes
Provision of information on import and export statistics by product value, quantities destination
Yes Yes
15 14
Social Benefit
Management
Web-based information publishing
Yes Applications for availing benefits
Yes
Benefits eligibility calculator
Yes Pension Services (Pensioner registration, and pension payment)
Yes
Support Letter (for unemployment; free health treatment, scholarships)
Yes
2 3
e-Education National Exam results
Yes Student registration Yes
Student placement results
Yes Certificate for completion of high school (original & replacement)
Yes
Teacher placement results
Yes Certificate for completion of degree (original & replacement)
Yes
Publish education statistics
Yes Yes National exam candidate registration
Yes
Report student performance results
Yes Teaching permit – for employment
Yes
Education certificate – to be sent abroad
Yes
Re-issuance of national exam certificates upon request
Yes
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 292 Confidential
Projects Total Services
Informational Services
G2C G2B Total Services
Transactional Services
G2C G2B
Scholarships Yes
5 8
e-Health Hospital Information
Yes Yes Issuance of Drug Marketing license
Yes
Drug pricing information
Yes Yes Issuance and renewal of Certificates of competence to drug establishments
Yes
Drug Availability Information
Yes Yes Issuance, Renewal and cancellation of drug registration certificate
Yes
Doctors profile information
Yes Issuance of certificate of competence to health professionals
Yes
Request of Medication/ medical supplies for citizens
Yes Yes
Issuance of licenses to hospitals
Yes
Request for Vaccination
Yes Yes
Issuance, Renewal and cancellation of license to conduct clinical trials
Yes
Booking of Appointments
Yes
4 10 Notification of Test results
Yes
e-Trade Provision of Investor Information
Yes Business Licensing and Registration services(Issuance, Renewal and cancellation) including professional, contractors and construction machines licensing
Yes
Policies on Business Loans
Yes Trade name and trade mark registration and renewal
Yes
Provision of Export/Import Trade Information to the business community
Yes Collection of fines if businesses operate without license or outdated license
Yes
Dissemination of market research to Exporters for investing in existing as well as new markets
Yes Requesting for Business area
Yes
Provision of Information on SMMEs and Large Industries
Yes Application for Subsidies and Duty relaxations
Yes
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 293 Confidential
Projects Total Services
Informational Services
G2C G2B Total Services
Transactional Services
G2C G2B
Encouraging businesses engaged in export trade to utilize he export trade incentive scheme of the country
Yes Issuing commercial representative license
Yes
Giving licenses to forwarders and shipping agents
Yes
Amendment of business license
Yes
Registration of commercial representative
Yes
Issuance of broadcast license
Yes
Issuance of press licenses
Yes
Alteration and modification of principal registration
Yes
6 12
Employment Management
System
Information on employment opportunities within the government
Yes Unemployment Registration/ Unemployment Certificate
Yes
Labour Market Information
Yes Overseas employment registration for Ethiopian Nationals
Yes
Job Matching Yes Employment Agency License Renewal
Yes
Employment Agency Licensing (New)
Yes
Foreign Nationals work permit
Yes
Teacher placement Yes
Registration of labour unions, Employment unions
Registration of work places
Registration of Collective Agreements
Registration of Safety & health Committees
Registration of work place accidents
3 12 Registration of Institution & partner organisations
e-Transport Generic information on the application process, work
Yes Yes Issuance/ Renewal of drivers license (National/ International)
Yes
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 294 Confidential
Projects Total Services
Informational Services
G2C G2B Total Services
Transactional Services
G2C G2B
flow, timelines, documents needed, ministry offices, work timings
Notification of expiry/ renewal of insurance, licenses
Yes Yes Application for change of ownership of vehicles
Yes
Information on Public transport timings, tickets availability, routes, stops etc.
Yes Application and renewal of vehicle Insurance
Yes
Information on the traffic movement, special events, road works, Parking areas, detour information etc.
Yes Application for request of special numbers
Yes
Notification of traffic violations and penalties
Yes Online notification and collection of fines for traffic violation
Yes
Information on regulation, policies, and import duty for vehicles
Yes Online booking of tickets for inter state government transport
Yes
Vehicle Registration Yes
Vehicle Inspection Yes
6 8
e-Tourism Information on Tour Operators, Travel Packages, Itinerary, Fee
Yes Registration of private tour operators
Yes
Information about the Accommodations
Yes Registering for a Tour Yes
Information regarding various resources , Cultural and heritage centers
Yes Registration of Hotels, Resorts, Guest Houses and Local Accommodations
Yes
Information on Various GIS Mapping statistics
Yes Yes Booking a Hotel, Resort etc
Yes
Registering with the DMS for alerts
Yes
Supporting letter for film-makers ,Tourists to go abroad
Yes
Application for Tourist VISA on Arrival
Yes
Driving license Yes
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 295 Confidential
Projects Total Services
Informational Services
G2C G2B Total Services
Transactional Services
G2C G2B
equivalence for foreign citizens
Issuing Birth, Death and Marriage Certificates to foreign nationals
Yes
Permission to visit Heritage sites
Yes
4 10
e-Tax View Pending messages
Yes Yes Online application of Registration as a Taxpayer
Yes Yes
View Registration Data
Yes Yes Online filling of Tax Return (Land tax, Rental Housing tax (paid by owner), Turnover tax, TV tax, VAT, and Excise tax)
Yes Yes
View Field assessments
Yes Yes File a declaration Yes Yes
View list of decelerations not filed
Yes Yes Tax clearance certificate Yes Yes
List previous Tax returns
Yes Yes TIN Number Registration
Yes Yes
Show filed declaration
Yes Yes Application for a tax holiday
Yes Yes
Budgetary information dissemination
Yes
7 6
e-Court Management
System
Buying & Selling Property Agreement
Yes Yes
Construction permit Yes Yes
Land Ownership Yes Yes
Rental Agreement(Transfer)
Yes Yes
Rental agreement (renewal/ownership)
Yes Yes
Land transfer Yes Yes
Property Registration Yes Yes
Application for a Pleading
Yes Yes
Document Transfer Yes Yes
Case Filing Yes Yes
11 Adjourning Cases Yes Yes
e-Municipality Management
Information Provision about A.A. City
Yes Request for Archives of News, Television Programs, Radio
Yes
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 296 Confidential
Projects Total Services
Informational Services
G2C G2B Total Services
Transactional Services
G2C G2B
System Administration Programs
Download of Radio Program
Yes Application for sponsorship of News, Communications
Yes
Download of News
Yes Request to post News Yes
Information on determination of design standards and preparation of design for construction of roads
Yes Request for Advertising different bids and names etc.
Yes
Give information about court case such as adjournment date.
Yes Appeal to damaged roads
Yes
Information on creating awareness for protecting the city from different pollution and natural resource degradation
Yes Requests for the permission of blocking of the road temporarily
Yes
Distributing Organizational Structure for sub cities and center Offices
Yes Application for change of name.
Yes Yes
Distributing directives, guidance, rules and regulation concerning with promotion, allowance, transfer, requirement of employment discipline.
Yes Application for declaration of absence.
Yes Yes
Collect data about employees profile form all offices
Yes Application for succession Certificate.
Yes Yes
Provision of statistical analysis about employees‘ profile.
Yes Application for marriage certificate.
Yes
Distribution of laws
Yes Application for certificate of guardianship.
Yes
Educational management information for researchers
Yes Issuance of Marriage Certificate
Yes
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 297 Confidential
Projects Total Services
Informational Services
G2C G2B Total Services
Transactional Services
G2C G2B
Information on how to get examinee ID
Yes Issuance of Divorce Certificate
Yes
News Release Yes Issuance of Birth Certificate
Yes
Press Release Yes Issuance of Non-Married Certificate
Yes
Documentation and dissemination of information
Yes Issuance of Death Certificate
Yes
Dissemination of declaration ratified by the council
Yes Issuance of license for mining
Yes
Information on safety inspection and certification
Yes Yes Environmental Impact Assessment Permit.
Yes
Information on safety consultancy
Yes Request for environmental Lab test
Yes
Information on training and awareness
Yes Yes Request for disposal of solid waste
Yes
Request for park and recreation center/hall
Yes Receiving appeals from employees (Administrative court)
Yes
Information on how to get funeral service
Yes Recruit new employees for all sub cities and center offices
Yes
Information on the provision of ornamental seedlings
Yes Registration of complaints investigation and litigation sub process
Yes
Information on green area adoption and outsource service
Yes Registration of Tax appeal
Yes
Information on public relation mobilization and awareness
Yes Request for new water line
Yes Yes
Request for maintenance of Water/Sewerage lines
Yes
Request for sewerage service
Yes
Bill collection Yes
Registration of Private ECLSE examinees
Yes
Request for summer course registration
Yes
Request for grade 8 report card when they lost it
Yes
Request for buying laws
Yes
Receiving appeal Yes Yes
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 298 Confidential
Projects Total Services
Informational Services
G2C G2B Total Services
Transactional Services
G2C G2B
Preparing Structural Plan
Yes Yes
Preparing Local development Plan
Yes
Collecting land and land related data
Yes
Request for land and land related data (has transaction fee)
Yes
Yes
Yes
25 37 Yes
ePassport Status Check of ID Cards
Yes Application for Resident ID
Yes
Status Check of Passports
Yes Renewal of Resident ID Yes
Replacement of Resident ID
Yes
Application for Passport Yes
Renewal of Passport Yes
Replacement of Passport
Yes
ID card issuance for foreign nationals
Yes
Issuing diplomatic and service visas
Yes
Verification of incoming and outgoing documents
Yes
2 9
Total Informational Services
Informational Total Transactional
Sevices
Transactional Total Services
G2C G2B G2C G2B
79 61 41 140 102 68 219
List of services for Agencies
Sr. No.
Agencies Services Type of Service
1 Ethiopian Investment Agency
Information Services Informational
Licensing and Registration services Transactional
Investment Registration Transactional
Requesting for Business area Transactional
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 299 Confidential
2 General Education Quality Assurance and
Examination Agency(GEQAEA)
Registration of national examinees for examinations Transactional
Examination Result Scoring Informational
Download of Certifications Transactional
Replacement certificates Transactional
Authentications of certificates Informational
3 Transport Authority Annual Vehicles Inspection Transactional
Drivers penalty management Transactional
New Driver license Issuance Transactional
Driver license renewal Transactional
Driving license Transfer to Region Transactional
New vehicles Registration Transactional
Vehicles ownership transfer Transactional
Annual Vehicles Inspection Transactional
Vehicles body change Transactional
Vehicles service change Transactional
Vehicles Transfer to Region Transactional
Garage Licensing and Renewal Transactional
Vehicle Importers and Assemblers Licensing and renewal Transactional
Vehicle Inspection Organizations Licensing and Renewal Transactional
Get Pass of (Drivers and Vehicles for neighboring countries)
Transactional
Membership Registration letters for operators to Associations
Transactional
Issuance for Transport Associations and Companies Competency Certificate
Transactional
Renewal for Transport Associations and Companies Competency Certificate
Transactional
Passenger Transport Dispatching and fleet management Informational
Vehicle Import Permit Transactional
4 Social Security Agency Web-based information publishing Informational
Pension services (Pensioner registration, and pension payment)
Transactional
Services to business(regarding to goods and services) Transactional
5 Revenue and Customs Online application of Registration as a Taxpayer Transactional
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 300 Confidential
Authority Online filling of Tax Return (Land tax, Rental Housing tax (paid by owner), Turnover tax, TV tax, VAT, and Excise tax)
Transactional
File a declaration Transactional
View Pending messages Informational
View Registration Data Informational
View Field assessments Informational
View list of decelerations not filed Informational
View list of assessment Informational
View list of transactions Informational
List previous Tax returns Informational
Show filed declaration Informational
Tax clearance certificate Transactional
TIN Number Registration Transactional
6 Federal Supreme Court Application for a Pleading Transactional
Document Transfer Transactional
Case Filing Informational
Adjourning Cases Informational
7 Ethiopia Commodity Exchange
Market Data Dissemination Informational
Payment transfer Transactional
Membership registration Transactional
Commodity deposit Transactional
8 Department of Postal Service
Electronic money transfer Transactional
Domestic mail transfer Informational
Money transfer and payment system Transactional
Box rental Transactional
Pension services (Pensioner registration, and pension payment)
Transactional
9 Micro and Small Enterprise Development
Agency
Registration of SMEs; Transactional
10 ETC New Service (VPN, Internet) Transactional
Upgrade Transactional
Downgrade Transactional
Cancellation Transactional
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 301 Confidential
CPE Change Transactional
Bill settlement Transactional
Online data service management Transactional
11 Addis Ababa City Administration
Download of Radio Program Transactional
Download of News Transactional
Vacancy Application Transactional
Application for sponsorship Transactional
News Transactional
Communications Transactional
Determine design standards for roads & prepare design for construction of roads or prepare it through qualified consultants.
Transactional
Plan and study ways and means that have to prevent roads from damage and implement same upon approval. With the cooperation of the city government.
Informational
Give permit to requests to temporally block or to use roads for some purposes.
Transactional
Application for change of name. Transactional
Application for declaration of absence. Transactional
Application for succession Certificate. Transactional
Application for marriage certificate. Transactional
Application for certificate of guardianship. Transactional
Give information about court case such as adjournment date.
Transactional
Resident ID Transactional
Marriage Certificate Transactional
Divorce Certificate Transactional
Birth Certificate Transactional
Non-Married Certificate Transactional
Death Certificate Transactional
Permit mining and related activities to those who are in need of investing on mining development in accordance with sustainable environment.
Transactional
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 302 Confidential
Expand environmental education and awareness creation for different time, places and levels.
Transactional
Exerts to pass development projects through the rules and procedures of environmental impact assessment.
Informational
Receiving appeals from employees (Administrative court) Transactional
Recruit new employees for all sub cities and center offices Transactional
Registration of complaints investigation and litigation sub process
Transactional
Registration of Tax appeal Transactional
Request for new water line Transactional
Request for maintenance Transactional
Request for sewerage service Transactional
Bill collection Transactional
Educational management information for researchers Transactional
Information on how to get examinee ID Informational
Registration of Private ECLSE examinees Informational
Request for summer course Transactional
Request for grade 8 report card when they lost it Transactional
Information on business areas/opportunities Transactional
Business requirement Information Informational
Registration of MSEs Informational
Registration of tax payers Transactional
Prepare Tax Identification number Transactional
Preparation and distribution of VAT Certificate Transactional
Preparation and distribution of assessment notification Transactional
Auditing and preparing assessment paper Transactional
Collection of Tax Transactional
Giving clearance paper Transactional
Collecting local and foreign transaction of taxpayers Transactional
News Release Transactional
Press Release Informational
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 303 Confidential
Documentation and dissemination of information Informational
Dissemination of declaration ratified by the council Informational
Receiving appeal Informational
Four Ministries that have not been included in the e-Government Strategy include Ministry of Defence Ministry of Federal Affairs Ministry of Mines Ministry of Science and Technology
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 304 Confidential
Annexure XI: Overview of Stakeholder Assessment
The following chart gives a snapshot of the key findings of the Stakeholder Assessment across various
dimensions and parameters.
Note: Methodology and analysis of the assessment was designed by PwC. The details of each of the
dimensions/parameters and Ministries/Agencies is provided in Stakeholder holder Assessment Report.
However a summary is provided in the next few pages
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 305 Confidential
Ministries and Agencies
Hardware and Networking
During the interaction with Ministries and Agencies it was found that most of the ministries and
Agencies are well equipped with the Hardware and LAN environment. The availability of the
Hardware and presence of LAN in the ministry/agencies is a good indication for the e-Government
implementation. This also indicated that the resources are at-least familiar with technology and only
strategic planning is required for the effective implementation of the e-Government. However some of
ministries such as the Ministry of Youth and Sports and the Ministry of Urban works seem to be
lagging behind in terms of availability of basic IT infrastructure, nevertheless inventory of such
ministries/ agencies can be easily upgraded.
Software
Analysis of survey responses indicate that most of the ministries have some specialized software
developed for their internal use, which will benefit only the Employees/Staff of that organization.
Ministries pertaining to Agriculture, Finance, Foreign Affairs et is also a necetera have HRMS and
Inventory management system in place, similarly other ministries have different applications
developed for their internal use. While it is good to have such applications, an exercise may be
conducted to identify common applications that can be implemented in all the Ministries and
Agencies which can be developed by a central agency, rather than each Ministry developing them
individually There is also a need to identify the citizen centric applications which could be
implemented across different Ministries/Agencies.
e-Services
Interestingly most of the ministries have recognized the importance of e-Services and delivering some
of the services online to the citizens of Ethiopia. The Ministry of Transport and Communication
provides two online services, similarly the Federal Supreme Court and Ethiopian Commodity
Exchange also provides online services to benefit the citizens. However, most of the ministries and
agencies are still their planning phase of ‗going online‘ with the services. Efforts have been made by
the Ministries and Agencies in this direction and they have identified the services that can be rolled
out in phased manner over a period of 2-3 years.
Capacity building
Most of the ministries and agencies feel the biggest challenge to implement e-Government in Ethiopia
is the availability of the technical manpower and capacity building. Almost all ministries such as The
Ministry of Labour and Social Affairs, The Ministry of Foreign Affairs, The Ministry of Youth and
Sports et cetera, have raised a concern about the lack of technical manpower in their respective
organization.
Policies, Standards and Guidelines
In the feedback given by the ministries / agencies one of the key components – Standards and
Guidelines‘ is completely missing. Only The Ministry of Transport and Communication has shown
some level of maturity in terms of the relevant policies defined for the organization for the effective
implementation of the e-Government. However most of the ministry/agency have one or two policies
defined in place. There is a need to design a policy framework with guidelines across the Ministries for
implementation of e-Government.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 306 Confidential
Security
The Ministry of Justice and The Ministry of Youth and Sports have raised concern on the security of
the data and applications. It is extremely necessary for the e-Government applications to be secure
and ‗hack-proof‘ from any attack. During the discussion with the ministries it is evident that a
framework is required to ensure the security of Government Data and Transactions.
Integration
The survey indicates that Ministries are interacting with each other and sharing information. But
there is no interface for the information interchange. Ministries are not concentrating on the
information sharing with other ministries by means of electronic channel. However some of the
Ministries (Ministry of Education, Ministry of Trade and Industry, Ministry of Finance) have raised
the issue of forming a framework at a ational level for such an integration.
Focus Area
The success of e-Government across the world is increasingly being measured by the benefits it
creates for Customers (constituents, citizens and business communities). However, the survey data
indicated that the focus of the business applications purchased or developed by Ministries/Agencies is
mainly on improving internal efficiency rather than focusing on delivery of Customer services. While
internal operational efficiency is a necessity, this emphasis on internal business applications indicate
an inward-looking emphasis by Ministries/Agencies, rather than a more strategic and integrated
approach to e-Government, where on-line Customer services are identified for implementation and
internal applications support this.
ICT infrastructure Usage
The Ethiopia ICT infrastructure is well equipped with a Data centre which is highlighted with the
presence of ―Woreda Net‖. Also the call centre facility is in operational condition. The survey findings
indicate that the shared ICT infrastructure is under-utilized and there is scope to make these facilities
more popular among the ministers and agencies.
Donors
World Bank
Major initiatives: Poverty Reduction, Infrastructure – Transport and ICT, Water Supply,
Education, Health, Agriculture, Private sector development Anti Malaria Campaign, Rural
water supply, Food Security Initiative, Sustainable Land Management, Basic education, Post
secondary education.
Challenges for Citizen Services: Being a Federal Government, there are challenges in
building capacities and implementing e-Government solutions at isolated regions.
United Nations
Major initiatives: Build Local Capacity, Millennium Development Goals such as Poverty
Reduction, Crisis Prevention, HIV/AIDS treatment, Environment, ICT and
EnergyMillennium Development Goal too reduce poverty, provide primary education,
Empower Women, Reduce child mortality, Anti HIV and malaria initiatives
Challenges for Citizen Services: There is a need to strengthen the local capacity to
implement e-Government in the Country.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 307 Confidential
Spanish Development Corporation
Major initiatives: Sectoral Development, Health, Food Security, Agriculture, ICT
Infrastructure, Gender Issues, Culture Public Basic Services to provide basic health and
education , ADG- Agri Growth Program, ,Infrastructure and Capacity Building
Challenges for Citizen Services: Need for incentive schemes to the citizens, to increase
the usage of IT services
African Development Bank
Major initiatives: Socio Economic development for Africa, Poverty Reduction, Living
Conditions Improvement, ICT, Technical and Financial Assistance to the local Government.
Fertilizer Financing, Water facilities, Women Entrepreneurship, Small scale Industries, Agro
Industries, Sanitation, Ethiopia-Djibouti Linking infrastructure
Challenges for Citizen Services: Mobilization of Resources, Uneven distribution and
access to resources
Business
The survey of private companies reveals that the Access to the ICT infrastructure in terms of
availability of computers and peripherals; network connections both internal and external; and
connectivity are the major ICT challenges that these companies face in their operations. The other
major challenges expressed by the private companies are the high cost of ICT access. An ADSL
connection of 2 Mbps costs more than 45,000 ETB per month in tariffs. But voice data and wireless
telephone tariffs are very cheap (0.20 Birr/6 Min for calls within same city and 0.40 Birr/ Min for
calls within same tariff zones) and are the major means for communication in private companies.
Companies also find the import duties on ICT equipments to be exorbitant. The peripherals and
additional equipments such as printers etc do not fall under ICT goods and hence the companies
spend large sums of money on such equipments.
The private ICT companies also find a lack of domestic demand since the ICT Market in Ethiopia is
yet to mature to a self sustainable state. as almost all the ICT equipments are imported. The
companies in the ICT equipments sector mainly operate as resellers, dealers or maintenance and
services. The duties and the taxation on products are passed on to the customers this reduces the
margins for these companies
The major demand for ICT in Ethiopia comes from the Government but the procurement policies of
Government make it almost impossible for the local companies to compete or participate in the
bidding process. Firstly, the private companies do not have the experience that the procurement
guidelines stipulate due to which the local companies get disqualified. Secondly the local companies
do not have resources in terms of staff or infrastructure to carry out large projects of the Government.
Hence it is essential for a collaboration of the Public and Private sectors of the country to mutually
help each other in building a stronger domestic market.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 308 Confidential
Customers
Based on the Survey responses and interaction with the citizens the overall key observations are as
follows:
a) The table below specifies the most commonly used Services / Service Organization
by the Citizens of the Ethiopia.
1. Census
2. Commercial bank of
Ethiopia
3. Education
4. Electricity / Power
5. ERTA (Radio /
Television)
6. Health services
7. Internet
8. Mobile / SMS
9. Municipality services
10. Passport
11. Police
12. Taxpaying
13. Telephone
14. Transportation
15. Water
b) The table below specifies the most commonly used Government Website by the
Citizens of Ethiopia.
Sr. No. Site Address Ministry / Agency / Bureau
1 http://www.erta.gov.et/ Ethiopian Radio and Television Agency
2 http://www.ethionet.et/ Ethiopian Telecommunications Corporation
3 http://www.ena.gov.et/ The Ethiopian News Agency
4 http://www.amhcbb.gov.et/ Amhara National Regional State Capacity
Building Bureau
5 http://www.ethiopianairlines.com/ Ethiopian Airlines
6 http://www.mu.edu.et/ Mekelle University official Website
7 http:// www.bdu.edu.et/ Bahir Dar University website
c) The table below specifies the feedback received and analysed for some of the key
questions that is useful for planning of the future roadmap of the e-Government in
Ethiopia.
Sr. No. Question Analysis
1. Do you know / have you heard about e-
Government initiatives of Government of
Ethiopia?
Only 30%-35% people heard about such
initiatives
2. Have you ever used internet to access the
website of a government agency?
Only 20%-30% people use internet as a
medium to access the Government services
3. What are the key benefits that you expect
from e-Government? Most of the people want ―Faster
Delivery of Services‖
Then people prefer to avail
services through ―One Stop Shop
for Services‖
―Lower cost of obtaining Service‖
4. What could the Government do to encourage
you to use online Government Services?
Citizens of Ethiopia suggested to ―Reduce
cost of internet access, including hardware
/software‖ and the second on priority will
be ―Make services easy to use‖ and then to
―Increased awareness of availability‖
5. For users‘ convenience, the Government People want the government services to be
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 309 Confidential
plans to use alternate channels for providing
Public Services.
delivered through ―Mobile‖ then by
―Internet‖ and then by ―Call Centre‖
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 310 Confidential
Annexure XII: Scope of work for Baseline Survey Agency
The survey will be designed to establish a baseline against which the accrued benefits in terms of
improvements in the government‘s services delivery mechanism and the increase in satisfaction levels of
the customers due to the ongoing e-Government program can be compared. Further, the survey is
envisaged to be a tool to capture some of the key issues, opportunities and challenges for the e-
Government program as it moves into its next phases of development.
The project will consist of four phases as follows:
Survey Design phase
Information Gathering phase
Data Analysis phase
Output and Reporting phase
1. Survey Design phase
Survey objectives
The key objectives of the e-Government Satisfaction Survey are to understand the following:
Awareness regarding e-Government and its activities among major groups of users.
Detailed Usage and Accessibility of all e-Government Services.
Satisfaction with various services among the major stakeholders.
Target Population
The e-Government users are divided into three broad segments: citizens, business and government;
thus three separate modules will be conducted to collect the required information:
The sample size for residents should be such that it is a true representative sample of residents of
Ethiopia in terms of Nationality (Citizens and Residents), Age and Education.
Target respondents for Business and Government
Responsible for e-Government needs in the organization (Decision makers or Influencers)
Following sectors will be included in survey:
o Agriculture
o Education
o Health
o Municipalities
o Labor and Social affairs
o Justice
o Tax
o Trade
o Transport & Communication
The pretest
The pretest is crucial because it allows field-testing the questionnaire on a selected small sample of
the population. The results of the pretest usually suggest that some modifications must be made
before a full-scale sampling is undertaken.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 311 Confidential
2. Information Gathering Phase
Citizens sample design
The Vendor will draw a sample from the citizen's population with the following criteria:
Cluster sampling: Classifying target population into seven regions.
Strata sampling: Stratify each region according to citizens or residents with corresponding
proportion for each type obtained from population census.
The sample will be drawn by simple random sample method.
Business and Government Sample design
The Vendor will draw a sample from the business population with the following criteria:
Cluster sampling: Classifying target population into three groups of establishments
according to the size.
Stratify sampling according to industry type with proportionate representation for each
type obtained.
The sample will be drawn by simple random sampling method.
Sample size for Residents
The sample size for residents should be such that it is a true representative sample of residents of
Ethiopia in terms of Nationality (Citizens and Residents), Age and Education as per census.
Sample size for Business
The indicative sample size for Business is illustrated below in Table
Table: Sample size of Businesses
Industry Sample Size Sample Propositions
Agriculture 29 14%
Financial, Insurance, Real estate &
Business services
42 21%
Health care 6 3%
Hotels + Restaurants 40 20%
Manufacturing industries 26 13%
Transport, IT and Communication 8 4%
Wholesale and Retail trade 31 16%
Business Services (Ad agencies /
Consultants) etc
18 9%
Total 200 100
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 312 Confidential
Methods of measurement
For the citizens' survey,900 face to face interviews and 600 telephonic interviews for residents and
200 face to face interviews for Businesses and the Government respectively will be conducted using a
structured questionnaire. The interviews will be performed in English or Amharic as convenient to the
respondent. Interview length will be determined from pre test procedure.
Selection and training of field workers
The field-workers must carefully be trained in what measurements to be made and how to make them
during the interviews. Training is especially important if interviews because the rate of response and
the accuracy of responses are affected by the interviewer‘s personal style and voice.
Data Validation and Quality Control
Daily checks on the collected questionnaires will be made after collecting them from the field to
ensure that data are correct and clean. Every questionnaire will be reviewed in order to insure the
quality of the collected data.
Data Entry
The vendor shall use SPSS Data Entry software or any appropriate software
3. Data analysis phase
Describing Data
The vendor will describe data through the following techniques:
Count responses
compute descriptive statistics
compare groups
plot data
Index Number
The Vendor will create index number for e-Government Satisfaction with respect to international
definitions and maintain background documentation on sources and methods.
The Satisfaction Index will be composed from the following sub-indices:
Government Satisfaction Index
Citizens Satisfaction Index
Businesses Satisfaction Index
Cluster Analysis
Clustering is the classification of audience and stakeholders into different groups, or more precisely,
the partitioning of respondents into subsets (clusters), so that the data in each respondents subset
(ideally) share some common trait - often proximity according to some defined distance measure.
This will be done in order to explore the heterogeneity of the different stakeholders and audiences.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 313 Confidential
4. Outputs Phase
The Report
The report should cover the following elements:
The beneficiary and the applied methodology.
The poll objective
Population of the research
Sampling techniques
Pre-test procedure
Evaluation of the poll outcome
Full description of results.
Concluding remarks
Reports will be generated as follows:
A draft report 10 weeks after the signature of the contract.
Final report, in draft form 1 weeks prior to the end of the contract to allow for comments by
the beneficiary and the donor (if any) to be incorporated.
Number of reports copies will be three hard copies & one electronic copy.
The final report will be presented in English and Amharic with translation provided by the
POC.
Presentation
Summary conclusion and summary of e-Government Satisfaction Survey will be presented.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 314 Confidential
Annexure XIII: Scope of work for Marketing and Awareness Agency
The scope of work of the consultant will be:
To review the media plan for the proposed Public awareness campaign.
To recommend a comprehensive communications strategy and creative for all mass media, viz.
television, radio, print etc. This should include a comprehensive media plan, media schedules
based on prioritisation of different mass media taking note of different target groups. A
comprehensive strategy, including a media plan for both the campaigns needs to be evolved.
To suggest concept design for production of TV commercial (60/30/10 seconds)
To suggest concept design for production of radio jingle (60/30/10 seconds),
To suggest concept design for production of print advertisements of different sizes.
To recommend a public relation/ publicity strategy covering the entire gamut of the media.
To recommend the need for and assist in organising Events/ Rallies /Exhibition for effective
outreach.
To suggest the modalities of outdoor publicity.
To suggest the concept and design of Internet Advertising/ campaigns using mobile phones.
To recommend the use of Direct Marketing in this endeavor.
Additionally the consultant would be responsible for the following:
Preparing a comprehensive Media Strategy Plan (MSP) that could help leverage the maximum outcome from the Communications campaigns.
Review and implementation of the Communications plan while also help supplement the efforts to create awareness amongst the larger section of stakeholders. It must prepare a Media Implementation Plan (MIP) for this purpose. The plan must take note of the complementarily of the different target groups and ensure that there is no overlap amongst various different kind of communications.
Prepare, based on the respective requirements of the campaign, separate creatives for print, audio, video, internet and other related Communications. It must prepare a Media Creative Plan (MCrP) for this purpose. The plan must highlight different creatives to address different target groups to effectively communicate the message.
Develop time frame for insertions – time releases / media initiatives for sustained visibility at key
centres and liaise with target media to bring out special reports on activities / events. It must prepare a Media Scheduling Plan (MSP) for this purpose.
Examine the replicability of the media plan to cover all stakeholders and media. It must prepare a
Media Replicability Plan (MRP) for this purpose.
Strategically and proactively develop the theme / concept for advertisements, press meets, news releases, articles and other promotional initiatives targeting local, national & international Communications. It must prepare a Media Thematic Plan (MTP) for this purpose.
Communications Scanning / Feedback from across a minimum of 10 centres: Maintain Communications watch / Communications intelligence for any development that may impact the Government; and provide reports of press clippings, TV, online news items, etc. It must prepare a Media Feedback Plan (MFP) for this purpose.
Undertaking media training at various levels including refresher modules for relevant
spokespersons, basic communication process flows & skills equipping media workshops for all
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 315 Confidential
public access points within the organisation and Crisis Communication i.e. help prevent negative news and counter such news if at all it appears and develop a crisis communication module at the outset. It must prepare a Media Training Plan (MTrP) for this purpose.
Create a positive mindset, inculcate a sense of ownership among employees and instill customer orientation by undertaking suitable programmes / interactive sessions. This must also be a part of the MTP.
Undertake Influencer / Opinion Leader Outreach by highlighting the objectives and relevance of
Stakeholders Efficiency with a view to positively influencing opinion leaders through initiatives like Seminars, Conferences and Presentations. This must also be a part of the MTP.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 316 Confidential
Annexure XIV: Job Descriptions of the IT Officials at the Ministry
No. Title Background and Qualifications
1. Chief Information
Officer (CIO)
• Master‘s degree in Information Technology, Management Information Systems, Business Administration, or related field
• Minimum of 8 years of senior management experience in managing a large organization‘s information technology strategic plan
2. Project Champion (s)
(Domain)
• Undergraduate/Masters degree in engineering/Computer Science
• Project Management Certification
• 10+ years of relevant work experience
IT Capacity Building
Expert
• MBA with focus on Capacity Building/Change Management
• 8+ years of experience
• Desirable to have additional certification or training in e-Governance, change management, change psychology or mass communication
Government Process
Re-engineering Expert
• Degree in economics, accounting, information technologies, business or public administration or similarly relevant discipline;
• At least 10 years of working experience in business process management and change within Government organizations.
• At least 5 years international experience in undertaking similar assignments within a Government environment where processes are subject to laws, rules, habit, conservatism, patronage and a long history of total reliance on multi-stage, multi-authorization manual, paper-based processes involving people at all levels of Government
Domain Experts • Masters Degree in Business Administration/Engineering
• Over 15 years of experience in the relevant area of expertise
• At least 10 years of hands-on experience in the relevant areas
3. Technical Solution
Architect
• Masters Degree in Computer Science or Engineering • 8+ years of experience with at least three years as a
Technology Architect in multiple full life cycle software development projects
• Certified as an Architect
IT Infrastructure
Expert
• Undergraduate/Masters degree in engineering, preferable Computer Science
• 8+ years of work experience, at least 4 years in technical program management
• Should have certifications such as ITIL certification / BS7799 auditing certification, CCNP/PIX/CCSA etc.
IT Security Expert • Undergraduate/Masters degree in engineering, preferable Computer Science
• 8+ years of work experience, at least 4 years in technical program management
• Should have CISA / CEH / ITIL certification.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 317 Confidential
Application Expert
• Undergraduate/Masters degree in engineering, preferable Computer Science
• 8+ years of work experience, at least 4 years in technical program management and software development
• Should have experience in IT application development/ Software Development/ Enterprise-Wide systems integration.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 318 Confidential
Annexure XV: Job Descriptions of the ITSG to support in the Ministries
No. Title Background and Qualifications
1. Project Coordinator
• Post graduate in Management with PMP certification.
• Minimum 8 years of experience in IT industry with 3 years in a Project Manager role
Project Design Expert
• Master's degree in Business Administration/social science
• Minimum of ten years experience in design, implementation, and evaluation of overseas development projects
• Knowledge and experience of different social science techniques including focus group research, key information interviews and surveys
PPP Expert
• Minimum Masters Degree in Business Administration/Public Administration/ Rural development and Communication or any related field from a reputed institute.
• Minimum ten years of experience in providing technical assistance in developing and implementing PPPs or related activities resulting in for profit infrastructure investment
• Proven track record of successful capacity building and association with PPP transactions that have reached closure.
• Familiarity with PPP best practices.
Standards and Policies
Expert
• Post graduate in Management/Information Technology
• Minimum 8 years of experience in developing standards and policies
Project Management
Expert
• Post graduate in Management with PMP certification.
• Minimum 8 years of experience in IT industry with 3 years in a Project Manager role
Solution Design Expert
• B.E. (Computer/E&C)/MCA from a premier institute with minimum 10 years of experience.
• Ability to define functional / technical architecture with good understanding of non-functional requirements & technology risks
• Hands on experience on various technologies including Open Standard Platforms
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 319 Confidential
Annexure XVI: Key Considerations during Procurement Process
Donor agencies, worldwide, are increasingly demanding transparency in the manner in which their funds
are utilized by the implementing agencies. This is mainly to ensure that the funds are used for the
purposes intended, with due attention to economy and efficiency; mitigating risk of misuse. One of the
key aspects that the donors look at is procurement.
Different donors have their own guidelines which need to be followed while carrying out the activities
under a project, include those related to procurement. Some donors (such as The World Bank) do not
finance expenditures for contracts which have not been procured in accordance with the prescribed
procedures/guidelines and would normally not reimburse such amounts to the implementing agencies.
Type of procurement activities of the borrowers may include procurement of goods, works and
consultancy & other services.
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 320 Confidential
Basic rules for vendor Short listing Vendors during Procurement of IT Services
Individual companies or consortium of companies operating in different domains identified for short listing process (Application Development, Hardware Procurement, IT Infrastructure Management, Networks, Telecommunication, Training, and Technical Helpdesk Operations) can bid. Consortium with representatives from maximum number of domains will be preferred.
In the event of a consortium, one of the partners shall be designated as a ―Lead Partner‖.
However, every member of the consortium shall be equally responsible and jointly and severally liable for the successful completion of the entire project .The prime bidder is encouraged to form consortium with companies operating in or based in Ethiopia.
The prime bidder and all consortium members should have ISO 9001: 2000 certification or equivalent. Preference shall be given to bidders with business specific latest versions of certifications like CMMi, PCMMi, and ISO and Environmental & Corporate Governance accreditations.
The Prime Bidder has to be an Information Technology Company registered under the existing
rules and regulations in the respective country since last 5 years.
Bidder can also submit if they have any country specific registrations as Technology Company.
The bidder need to have an office in the African Region for past 5 years or at least one of the consortium partners should comply with the condition.
The Prime Bidder should have positive annual turnover of more than <<USD 100 Million>> from all the domains for each of the last three Financial Years ending. If bidding for single track out of three tracks, the bidder should have a positive turnover of more than <<50 Million>> in the particular track. For 2 tracks, the turnover should be <<USD 75 Million>>
An undertaking (self certificate) that the bidder and all consortium partners are not blacklisted by
a Government institution and there has been no litigation with any government department on account of similar services. The prime bidder can submit the same on behalf of other consortium partner also, However, MoC&IT, on its discretion, can ask for individual declarations also.
The bidder is required to provide detailed information on the projects executed by them,
regional/country presence and resources to establish their credentials for evaluation
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 321 Confidential
Annexure XVII: Costing details of Individual Projects
Costing Assumptions
Assumptions and Unit Rates - General
Key Assumptions - General
Rate Hardware Unit Costs (In Birr.)
Salaried / Contract Staff
Unit Costs (In Birr.)
Others Items
Unit Costs (In Birr.)
Salary Growth Rate
0.10 Servers ( with System Software)
200,000.00
Project Manager
180,000.00
User Training per person
10,526.32
IT Equipment
0.10 Personal Computers( with OS, MS office and Antivirus solutions)
17,000.00
Solution / Application Architect
180,000.00
Change Management
3,508.77
Hardware/Software AMC
0.10 Multifunctional Printer/Scanner/Photocopier
45,000.00
Domain Expert
180,000.00
Office Maintenance (Electricity, water, maintenance, diesel cost etc) per office
84,210.53
Maintanence Cost
0.05 Networking and cabling( Router, Switch, Cabling)
140,350.88
Database administrator
180,000.00
Consumables (Paper, stationery, toners etc.) per office
4,210.53
Number of employees to be provided with PCs
0.75 Generator Set (5KVA)
26,315.79
Support Staff
120,000.00
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 322 Confidential
Number of Printers for Total PCs
0.50 Digital Camera
7,017.54
Web administrator
120,000.00
Software
Unit Costs(In Birr.)
Software development cost per man-month
87,719.30
S/w Developer
120,000.00
Data Digitization Software
1754.39
Percentage of total employees to be trained
0.90 Editorial Team - Editor
120,000.00
Percentage of total employees Targetted for change management
0.90 Editorial Team - Asst Editors
168,000.00
Per record digitization cost
3.51 Editorial Team - Support
144,000.00
Ethiopian Birr (In. Rs.)
2.85
Team Leaders - PMO
180,000.00
Team members - PMO
120,000.00
Assumptions and Unit Rates - Priority Project-wise
Agriculture
Number
Benefits Management
Number
Education
Number
eHealth
Number
Total No. of employees
200.00
Total No. of employees
150.00
Total No. of employees
500.00
Total No. of employees
500.00
Number of offices
20.00 Number of offices
20.00 Number of offices
20.00 Number of offices
20.00
Total number of records to be digitized
100,000.00
Total number of records to be digitized
500,000.00
Total number of records to be digitisd
500,000.00
Total number of records to be digitis
500,000.00
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 323 Confidential
d
Software Unit Costs(In Birr.)
Software Unit Costs(In Birr.)
Software
Unit Costs(In Birr.)
Software
Unit Costs(In Birr.)
Agriculture Information Management System
5,263,157.89
Benefits Information and Managements System
7,017,543.86
Education Information and Managements System
7,017,543.86
Health Information and Managements System
7,017,543.86
Number of man-months for development of Software
60.00 Number of man-months for development of Software
80.00 Number of man-months for development of Software
80.00 Number of man-months for development of Software
80.00
G2B Portal
Number
Employment
Number
Transport
Number
Tourism
Number
Total No. of employees
15.00 Total No. of employees
250.00
Total No. of employees
250.00
Total No. of employees
200.00
Number of offices
1.00 Number of offices
20.00 Number of offices
20.00 Number of offices
20.00
Total number of records to be digitized
0.00 Total number of records to be digitized
500000.00
Total number of records to be digitized
500000.00
Total number of records to be digitized
10,000.00
Software Unit Costs(In Birr.)
Software Unit Costs(In Birr.)
Software
Unit Costs(In Birr.)
Software
Unit Costs(In Birr.)
G2B Portal 3,508,771.93
Employment Information and Managements
5,263,157.89
Transport Information and
7,894,736.84
Tourism Informatio
5,263,157.89
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 324 Confidential
System Managements System
n and Managements System
Number of man-months for development of Software
40.00 Number of man-months for development of Software
60.00 Number of man-months for development of Software
90.00 Number of man-months for development of Software
60.00
Tax Number
eCourt Number
Municipalities
Number
Ministry of Foreign Affairs
Number
Total No. of employees
250.00
Total No. of employees
200.00
Total No. of employees
250.00
Total No. of employees
250.00
Number of offices
20.00 Number of offices
20.00 Number of offices
20.00 Number of offices
20.00
Total number of records to be digitized
700,000.00
Total number of records to be digitized
10,000.00
Total number of records to be digitized
500,000.00
Total number of records to be digitized
10,000.00
Software Unit Costs(In Birr.)
Software Unit Costs(In Birr.)
Software
Unit Costs(In Birr.)
Software
Unit Costs(In Birr.)
Tax Information and Managements System
7,894,736.84
eCourts Information and Managements System
5,263,157.89
Municipalities Information and Managements System
5,263,157.89
Passport
5,263,157.89
Number of man-months for developme
90.00 Number of man-months for development
60.00 Number of man-months for
60.00 Number of man-month
60.00
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 325 Confidential
nt of Software
of Software development of Software
s for development of Software
Assumptions and Unit Rates - Other projects
eGovernment Portal
Number
Contact Center
Number
Capacity Building
Number
Common Service Center
Number
Maximim number of calls per day
3000.00
Number of PCs per Training Center
8.00 Total Number of CSC
800.00
Number of Hours in a Shift 8.00
Number of Training Centers
20.00 Number of Operators in each CSC 4.00
Number of calls handled in one 1 hour by an Agent, Assuming 5 minutes per call
12.00
Number of Employees
44.00
Total Number of Operators
3200.00
Hardware
Unit Costs (In Birr.)
Total number of Calls handled by an agent in a day
96.00
High-end Server
2,807,017.54
Total number of Agents required
31.25
Salaried / Contract Staff
Unit Costs (In Birr.)
Salaried / Contract Staff
Unit Costs (In Birr.)
Software Unit Costs (In Birr.)
Supervisors Required 2.00
Business Process Re-engineering Expert
771,929.82
IT Admin
526,315.79
Directory Services
526,31
Number of offices
1.00 PPP Expert
771,92
Site Inspec
385,9
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 326 Confidential
5.79 9.82 tion and Audit Manager
64.91
Integration services
350,877.19
Salaried / Contract Staff
Unit Costs (In Birr.)
Advanced Technologies Expert
771,929.82
CSC Front Staff
42,105.26
Upgradation costs
175,438.60
Call Center Shift Manager
385,964.91
Software Development Expert
771,929.82
HR&Admin Manager
578,947.37
Content Development
175,438.60
Call Center Team Leader
315,789.47
Trainers 350,877.19
Finance Manager
578,947.37
Call Centre Executives
231,578.95
Software
Unit Costs (In Birr.)
Hardware Unit Costs (In Birr.)
CBT - Training content development
1,578,947.3
7
Calling Equipment
8,771.93
Central Knowledge Management Portal
526,31
5.79
IVRS & Call Routing
350,877.19
Other Cost
Unit Costs (In Birr.)
Site Preparation
175,438.60
Leadership Orientation (4 batches of 10 people each)
701,75
4.39
Software Unit Costs
Project Manage
3,000
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 327 Confidential
(In Birr.)
ment (4 batches of 10 people each)
.00
Call Centre Software (eg Clarity)
1,578,947.37
Vendor Management (4 batches of 10 people each)
1,666.
67
Other Cost Unit Costs (In Birr.)
SLA Design and Monitoring (4 batches of 10 people each)
1,666.
67
Lease cost per year
526,315.79
Customer orientation and support (4 batches of 20 people each)
666.6
7
Standards & Policies
Number
Marketing & Awareness
Number
Mobile Gateway
Number
Total No. of employees
20.00 Total No. of employees
WAP Server
3508.77
Number of offices
1.00 Number of offices
Content Converter
3508.77
Total number of records to be digitized
0.00 Total number of records to be digitized
Salaried / Contract Staff
Unit Costs (In Birr.)
Salaried / Contract Staff
Unit Costs (In Birr.)
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 328 Confidential
CIO 877192.98
Marketing Director
771,929.82
Data & Process Expert
771929.82
Manager - PR 473,684.21
Technology Expert
771929.82
Marketing/PR Professional
385,964.91
Service Delivery Expert
771929.82
Cost of Hiring Marketing/PR agency
385,964.91
Security Expert
771929.82
Other Cost Unit Costs (In Birr.)
Legal Expert
771929.82
Direct Mailers
26,67
9.67
Billboards
32,00
0.00
Advertisements in Print Media
33,696.00
Radio Advertisements
56,400.00
Television Advertisements
99,00
0.00
Online Marketing
66,67
9.67
Events
66,67
9.67
Branded Gifts / Paraphanelia
33,33
9.67
Content Development
200,000.00
Priority Project -Agriculture S.no.
Item Unit Cost (Cost in Birr.
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 329 Confidential
)
I Capital Expenditure
(A) Hardware
Servers (Includes AMC for 5 years)
200000 2
400000 40000
40000 40000 40000
Personal Computers (Includes AMC for 5 years) 17000 50
850000 85000 85000 85000 85000
Printers/Scanner/Photocopier
45000 25
1125000 0 0 0 0
Networking and Cabling
140351 20
2807018 0 0 0 0
Generator Set 26316 20 526316 0 0 0 0
Digital Camera 7018 20 140351 0 0 0 0
Sub-Total (A) 58486
84 12500
0 12500
0 12500
0 12500
0
(B) Software
Agriculture Information and Management System (Includes AMC for 5 years)
5263158 1
5263158
526316
526316
526316
526316
Data Digitisation 35087
7 1 35087
7 0 0 0 0
Sub-Total (B) 561403
5 52631
6 52631
6 52631
6 52631
6
II Operational Expenditure
( C ) Salaried / Contract Staff
Project Manager 18000
0 1 18000
0 19800
0 21780
0 23958
0 26353
8
Solution / Application Architect 0 1 0 0 0 0 0
Domain Expert 18000
0 2 36000
0 39600
0 43560
0 47916
0 52707
6
Database administrator 0 1 0 0 0 0 0
Support Staff 12000
0 4 48000
0 52800
0 58080
0 63888
0 70276
8
Sub-Total ( C) 10200
00 11220
00 12342
00 13576
20 14933
82
(D) Others
User Training 10526 180 94736
8 94736
8 47368
4 47368
4 0
Change Management 3509 180 315789 31578
9 15789
5 15789
5 0
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 330 Confidential
Office Maintenance 84211 20 168421
1 17684
21 18568
42 19496
84 20471
68
Consumables 4211 20 84211 88421 92842 97484 10235
8
Sub-Total (D) 303157
9 31200
00 25812
63 26787
47 21495
27
Total (A+B+C+D) 155142
98 48933
16 44667
79 46876
83 42942
25
Priority Project II - Benefits Management S.no.
Item Unit Cost (Cost in Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
I Capital Expenditure (A) Hardware
Servers 200000 2
400000
40000
40000
40000
40000
Personal Computers 1700
0 38 6375
00 6375
0 6375
0 6375
0 6375
0
Printers/Scanner/Photocopier 45000 19
843750 0 0 0 0
Networking and Cabling 1403
51 20 2807
018 0 0 0 0
Generator Set 2631
6 20 5263
16 0 0 0 0
Digital Camera 7018 20 1403
51 0 0 0 0
Sub-Total (A) 5354
934 1037
50 1037
50 1037
50 1037
50 (B) Software
Benefits Managements System (Includes AMC for 5 years)
7017544 1
7017544
701754
701754
701754
701754
Data Digitisation 1754386 1
1754386 0 0 0 0
Sub-Total (B) 87719
30 7017
54 7017
54 7017
54 7017
54
II Operational Expenditure ( C ) Salaried / Contract Staff
Project Manager 1800
00 1 1800
00 1980
00 2178
00 2395
80 2635
38
Solution / Application Architect 0 1 0 0 0 0 0
Domain Experts 1800
00 1 1800
00 1980
00 2178
00 2395
80 2635
38
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 331 Confidential
Database administrator 0 1 0 0 0 0 0
Support Staff 1200
00 2 2400
00 264000
290400
319440
351384
Sub-Total ( C) 6000
00 660000
726000
798600
878460
(D) Others
User Training 1052
6 135 7105
26 7105
26 3552
63 3552
63 0
Change Management 3509 135 2368
42 2368
42 1184
21 1184
21 0
Office Maintenance 8421
1 20 1684
211 1768
421 1856842
1949684
2047168
Consumables 4211 20 84211 884
21 9284
2 9748
4 1023
58
Sub-Total (D) 27157
89 2804211
2423368
2520853
2149527
Total (A+B+C+D) 17442654
4269715
3954873
4124957
3833491
Priority Project III - Education
S.no.
Item Unit Cost (Cost in Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
I Capital Expenditure
(A) Hardware
Servers 2000
00 2 40000
0 4000
0 40000 4000
0 4000
0
Personal Computers 17000 125 212500
0 21250
0 21250
0 21250
0 21250
0
Printers/Scanner/Photocopier
45000 63
2812500 0 0 0 0
Networking and cabling 14035
1 20 280701
8 0 0 0 0
Generator Set 26316 20 526316 0 0 0 0
Digital Camera 7018 20 140351 0 0 0 0
Sub-Total (A) 881118
4 25250
0 25250
0 25250
0 25250
0
(B) Software
Education Management System
7017544 1
7017544
701754 701754
701754
701754
Data Digitisation 17543
86 1 175438
6 0 0 0 0
Sub-Total (B) 877193
0 70175
4 701754 70175
4 70175
4
II Operational
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 332 Confidential
Expenditure
( C ) Salaried / Contract Staff
Project Manager 1800
00 1 18000
0 19800
0 21780
0 23958
0 26353
8
Solution / Application Architect 0 1 0 0 0 0 0
Domain Expert 1800
00 3 54000
0 59400
0 65340
0 71874
0 79061
4
Database administrator 0 1 0 0 0 0 0
Support Staff 1200
00 5 60000
0 6600
00 72600
0 79860
0 87846
0
Sub-Total ( C) 132000
0 14520
00 15972
00 17569
20 19326
12
(D) Others
User Training 10526 450 236842
1 23684
21 118421
1 11842
11 0
Change Management 3509 450 789474 78947
4 39473
7 39473
7 0
Office Maintenance 84211 20 168421
1 17684
21 18568
42 19496
84 20471
68
Consumables 4211 20 84211 88421 92842 97484 10235
8
Sub-Total (D) 492631
6 50147
37 35286
32 36261
16 21495
27
Total (A+B+C+D) 238294
30 74209
91 60800
86 63372
90 50363
93
Priority Project IV - eHealth
S.no.
Item Unit Cost (Cost in Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
I Capital Expenditure
(A) Hardware
Servers 2000
00 2 40000
0 4000
0 4000
0 4000
0 4000
0
Personal Computers 17000 125 212500
0 21250
0 21250
0 21250
0 21250
0
Printers/Scanner/Photocopier
45000 63
2812500 0 0 0 0
Networking and cabling 14035
1 20 280701
8 0 0 0 0
Generator Set 26316 20 526316 0 0 0 0
Digital Camera 7018 20 140351 0 0 0 0
Sub-Total (A) 881118 25250 25250 25250 25250
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 333 Confidential
4 0 0 0 0
(B) Software
Health Management System
7017544 1
7017544
701754
701754
701754
701754
Data Digitisation 17543
86 1 175438
6 0 0 0 0
Sub-Total (B) 877193
0 70175
4 70175
4 70175
4 70175
4
II Operational Expenditure
( C ) Salaried / Contract Staff
Project Manager 1800
00 1 18000
0 19800
0 21780
0 23958
0 26353
8
Solution / Application Architect 0 1 0 0 0 0 0
Domain Expert 1800
00 2 36000
0 39600
0 43560
0 47916
0 52707
6
Database administrator 0 1 0 0 0 0 0
Support Staff 12000
0 4 48000
0 52800
0 58080
0 63888
0 70276
8
Sub-Total ( C) 10200
00 11220
00 12342
00 13576
20 14933
82
(D) Others
User Training 10526 450 236842
1 23684
21 11842
11 11842
11 0
Change Management 3509 450 789474 78947
4 39473
7 39473
7 0
Office Maintenance 84211 20 168421
1 17684
21 18568
42 19496
84 20471
68
Consumables 4211 20 84211 88421 92842 97484 10235
8
Sub-Total (D) 492631
6 50147
37 35286
32 36261
16 21495
27
Total (A+B+C+D) 235294
30 70909
91 57170
86 59379
90 45971
63
Priority Project V- E-Trade
S.no.
Item Unit Cost (Cost in Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
I Capital Expenditure
(A) Hardware
Servers 200000 1
200000
20000
20000
20000
20000
Personal Computers 17000 4 63750 6375 6375 6375 6375
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 334 Confidential
Printers/Scanner/Photocopier
45000 2 84375 0 0 0 0
Networking and cabling
140351 1 140351 0 0 0 0
Digital Camera 7018 1 7018 0 0 0 0 Sub-Total (A)
49549
3 26375 26375 26375 26375 (B) Software
Application Development of G2B Portal
3508772
1 35087
72 35087
7 35087
7 35087
7 35087
7 Sub-Total (B) 35087
72 35087
7 35087
7 35087
7 35087
7 II Operational
Expenditure
( C )
Salaried / Contract Staff
Project Manager 180000 1
180000
198000
217800
239580
263538
Web administrator 120000 1
120000
132000
145200
159720
175692
Solution / Application Architect
0 1 0 0 0 0 0
S/w Developer 120000 1
120000
132000
145200
159720
175692
Support staff 120000 2
240000
264000
290400
319440
351384
Sub-Total ( C)
660000
726000
798600
878460
966306
(D) Others
User Training 10526 14 71053 71053 35526 35526 0 Change Management 3509 14 23684 23684 11842 11842 0 Sub-Total (D) 94737 94737 47368 47368 0 Total (A+B+C+D) 47590
02 11979
89 12232
21 13030
81 13435
58
Priority Project VI - Employment
S.no.
Item Unit Cost (Cost in Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
I Capital Expenditure (A) Hardware
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 335 Confidential
Servers 200000 1
200000
20000
20000
20000
20000
Personal Computers 1700
0 63 1062500
106250
106250
106250
106250
Printers/Scanner/Photocopier 45000 31
1406250 0 0 0 0
Networking and cabling 1403
51 20 2807
018 0 0 0 0
Generator Set 2631
6 20 5263
16 0 0 0 0
Digital Camera 7018 20 1403
51 0 0 0 0
Sub-Total (A) 6142434
126250
126250
126250
126250
(B) Software
Employment Management System (Includes AMC for 5 years)
5263158 1
5263158
526316
526316
526316
526316
Data Digitisation 1754386 1
1754386 0 0 0 0
Sub-Total (B) 7017544
526316
526316
526316
526316
II Operational Expenditure ( C ) Salaried / Contract Staff
Project Manager 180000 1
180000
198000
217800
239580
263538
Solution / Application Architect 0 1 0 0 0 0 0
Domain Expert 180000 2
360000
396000
435600
479160
527076
Database administrator 0 1 0 0 0 0 0
Support Staff 1200
00 2 2400
00 264000
290400
319440
351384
Sub-Total ( C) 7800
00 858000
943800
1038180
1141998
(D) Others
User Training 1052
6 225 1184
211 1184
211 5921
05 5921
05 0
Change Management 350
9 225 3947
37 3947
37 1973
68 1973
68 0
Office Maintenance 8421
1 20 1684
211 1768
421 1856842
1949684
2047168
Consumables 4211 20 8421
1 884
21 928
42 9748
4 1023
58
Sub-Total (D) 3347368
3435789
2739158
2836642
2149527
5 Total (A+B+C+D) 17287346
4946355
4335524
4527388
3944091
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 336 Confidential
Priority Project VII - Transport
S.no.
Item Unit Cost (Cost in Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
I Capital Expenditure
(A) Hardware
Servers 200000 1
200000
20000
20000
20000
20000
Personal Computers 17000 63
1062500
106250
106250
106250
106250
Printers/Scanner/Photocopier 45000 31
1406250 0 0 0 0
Networking and cabling 140351 20
2807018 0 0 0 0
Generator Set 263
16 20 5263
16 0 0 0 0
Digital Camera 701
8 20 1403
51 0 0 0 0
Sub-Total (A) 6142434
126250
126250
126250
126250
(B) Software
Transport Information & Management System (Includes AMC for 5 years)
789473
7 1 7894
737 789474
789474
789474
789474
Data Digitisation (Includes AMC for 5 years)
1754386 1
1754386 0 0 0 0
Sub-Total (B) 9649
123 789474
789474
789474
789474
II Operational Expenditure ( C ) Salaried / Contract Staff
Project Manager 180000 1
180000
198000
217800
239580
263538
Solution / Application Architect 0 1 0 0 0 0 0
Domain Expert 180000 4
720000
792000
871200
958320
1054152
Database administrator 0 1 0 0 0 0 0
Support Staff 120000 4
480000
528000
580800
638880
702768
Sub-Total ( C) 1380000
1518000
1669800
183678
0
202045
8
(D Others
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 337 Confidential
)
User Training 10526 180
947368
947368
473684
473684 0
Change Management 350
9 180 3157
89 3157
89 1578
95 1578
95 0
Office Maintenance 842
11 20 1684
211 1768
421 1856842
194968
4 204
7168
Consumables 4211 20 8421
1 884
21 928
42 97484
102358
Sub-Total (D) 3031
579 3120000
2581263
267874
7 2149
527
Total (A+B+C+D) 20203136
5553724
5166787
5431251
508570
9
Priority Project VIII- Tourism
S.no.
Item Unit Cost (Cost in Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
I Capital Expenditure
(A) Hardware
Servers 200000 1
200000
20000
20000
20000
20000
Personal Computers 1700
0 50 8500
00 8500
0 8500
0 8500
0 850
00
Printers/Scanner/Photocopier 45000 25
1125000 0 0 0 0
Networking and cabling 1403
51 20 2807
018 0 0 0 0
Generator Set 2631
6 20 52631
6 0 0 0 0
Digital Camera 7018 20 1403
51 0 0 0 0
Sub-Total (A) 5648
684 1050
00 1050
00 1050
00 1050
00
(B) Software
Tourism Management System (Includes AMC for 5 years)
5263158 1
5263158
526316
526316
526316
526316
Data Digitisation 3508
8 1 3508
8 0 0 0 0
Sub-Total (B) 5298
246 5263
16 5263
16 5263
16 5263
16
II Operational Expenditure
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 338 Confidential
( C ) Salaried / Contract Staff
Project Manager 1800
00 1 1800
00 1980
00 2178
00 2395
80 2635
38
Solution / Application Architect 0 1 0 0 0 0 0
Domain Expert 1800
00 2 3600
00 3960
00 4356
00 4791
60 5270
76
Database administrator 0 1 0 0 0 0 0
Support Staff 1200
00 2 2400
00 2640
00 2904
00 3194
40 3513
84
Editorial Team - Editor 1200
00 1 1200
00 1320
00 1452
00 1597
20 1756
92
Editorial Team - Asst Editors 1680
00 2 3360
00 3696
00 4065
60 4472
16 4919
38
Editorial Team - Support 1440
00 2 2880
00 3168
00 3484
80 3833
28 4216
61
Sub-Total ( C) 1524000
1676400
1844040
2028444
2231288
(D) Others
User Training 1052
6 180 9473
68 9473
68 4736
84 4736
84 0
Change Management 3509 180 31578
9 3157
89 1578
95 1578
95 0
Office Maintenance 8421
1 20 1684
211 1768
421 1856842
1949684
2047168
Consumables 4211 20 84211 8842
1 9284
2 9748
4 1023
58
Sub-Total (D) 3031
579 3120000
2581263
2678747
2149527
Total (A+B+C+D) 15502
509 5427
716 5056
619 5338
507 5012
131
Priority Project IX - Tax
S.no.
Item Unit Cost (Cost in Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
I Capital Expenditure
(A) Hardware
Servers 2000
00 2 4000
00 4000
0 4000
0 4000
0 4000
0
Personal Computers 1700
0 63 10625
00 1062
50 1062
50 1062
50 1062
50
Printers/Scanner/Photocopier 4500
0 31 14062
50 0 0 0 0
Networking and cabling 1403
51 20 2807
018 0 0 0 0
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 339 Confidential
Generator Set 2631
6 20 52631
6 0 0 0 0
Digital Camera 7018 20 14035
1 0 0 0 0
Sub-Total (A) 63424
34 1462
50 1462
50 1462
50 1462
50
(B) Software
Tax Management System (Includes AMC for 5 years)
7894737 1
7894737
789474
789474
789474
789474
Data Digitisation 2456
140 1 24561
40 0 0 0 0
Sub-Total (B) 10350
877 7894
74 7894
74 7894
74 7894
74
II Operational Expenditure ( C ) Salaried / Contract Staff
Project Manager 1800
00 1 1800
00 1980
00 2178
00 2395
80 2635
38
Solution / Application Architect 0 1 0 0 0 0 0
Domain Expert 1800
00 4 7200
00 7920
00 8712
00 9583
20 1054
152
Database administrator 0 1 0 0 0 0 0
Support Staff 1200
00 4 4800
00 5280
00 5808
00 6388
80 7027
68
Sub-Total ( C) 13800
00 1518000
1669800
1836780
2020458
(D) Others
User Training 1052
6 225 11842
11 1184
211 5921
05 5921
05 0
Change Management 3509 225 39473
7 3947
37 1973
68 1973
68 0
Office Maintenance 8421
1 20 16842
11 1768
421 1856842
1949684
2047168
Consumables 4211 20 84211 8842
1 9284
2 9748
4 1023
58
Sub-Total (D) 33473
68 3435
789 2739
158 2836
642 2149
527
Total (A+B+C+D) 21420
680 5889
513 5344682
5609146
5105709
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 340 Confidential
Priority Project X- eCourt
S.no.
Item Unit Cost (Cost in Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
I Capital Expenditure
(A) Hardware
Servers 2000
00 1 2000
00 2000
0 2000
0 2000
0 2000
0
Personal Computers 1700
0 50 85000
0 8500
0 8500
0 8500
0 8500
0
Printers/Scanner/Photocopier
45000 25
1125000 0 0 0 0
Networking and cabling 1403
51 20 28070
18 0 0 0 0
Generator Set 2631
6 20 52631
6 0 0 0 0
Digital Camera 7018 20 14035
1 0 0 0 0
Sub-Total (A) 56486
84 1050
00 1050
00 1050
00 1050
00
(B) Software
eCourts System (Includes AMC for 5 years)
5263158 1
5263158
526316
526316
526316
526316
Data Digitisation 3508
8 1 35088 0 0 0 0
Sub-Total (B) 52982
46 52631
6 52631
6 52631
6 52631
6
II Operational Expenditure ( C ) Salaried / Contract Staff
Project Manager 1800
00 1 18000
0 1980
00 2178
00 2395
80 2635
38
Solution / Application Architect 0 1 0 0 0 0 0
Domain Expert 1800
00 2 36000
0 3960
00 4356
00 47916
0 5270
76
Database administrator 0 1 0 0 0 0 0
Support Staff 1200
00 2 24000
0 2640
00 2904
00 31944
0 3513
84
Sub-Total ( C) 78000
0 8580
00 9438
00 10381
80 11419
98
(D) Others
User Training 1052
6 180 94736
8 94736
8 4736
84 4736
84 0
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 341 Confidential
Change Management 3509 180 31578
9 31578
9 15789
5 15789
5 0
Office Maintenance 84211 20 16842
11 17684
21 1856842
1949684
2047168
Consumables 4211 20 84211 88421 9284
2 9748
4 1023
58
Sub-Total (D) 30315
79 3120000
2581263
2678747
2149527
Total (A+B+C+D) 14758
509 4609
316 41563
79 4348
243 3922
841
Priority Project XI - Municipalities S.no.
Item Unit Cost (Cost in Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
I Capital Expenditure
(A) Hardware
Servers 200000 1
200000
20000
20000
20000
20000
Personal Computers 1700
0 63 1062500
106250
106250
106250
106250
Printers/Scanner/Photocopier 45000 31
1406250 0 0 0 0
Networking and cabling 1403
51 20 2807
018 0 0 0 0
Generator Set 2631
6 20 5263
16 0 0 0 0
Digital Camera 7018 20 1403
51 0 0 0 0
Sub-Total (A) 6142434
126250
126250
126250
126250
(B) Software
Municipalities Management System (Includes AMC for 5 years)
5263158 1
5263158
526316
526316
526316
526316
Data Digitisation 1754386 1
1754386 0 0 0 0
Sub-Total (B) 7017544
526316
526316
526316
526316
II Operational Expenditure ( C ) Salaried / Contract Staff
Project Manager 180000 1
180000
198000
217800
239580
263538
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 342 Confidential
Solution / Application Architect 0 1 0 0 0 0 0
Domain Expert 180000 2
360000
396000
435600
479160
527076
Database administrator 0 1 0 0 0 0 0
Support Staff 120000 6
720000
792000
871200
958320
1054152
Sub-Total ( C) 1260000
1386000
1524600
1677060
1844766
(D) Others
User Training 1052
6 225 1184
211 1184
211 5921
05 5921
05 0
Change Management 350
9 225 3947
37 3947
37 1973
68 1973
68 0
Office Maintenance 8421
1 20 1684
211 1768
421 1856842
1949684
2047168
Consumables 4211 20 8421
1 8842
1 928
42 9748
4 1023
58
Sub-Total (D) 3347368
3435789
2739158
2836642
2149527
Total (A+B+C+D) 17767346
5474355
4916324
5166268
4646859
Priority Project XII - Passport and Visa S.no.
Item Unit Cost (Cost in Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
I Capital Expenditure
(A) Hardware
Servers 2000
00 1 20000
0 2000
0 2000
0 2000
0 2000
0
Personal Computers 1700
0 63 10625
00 1062
50 1062
50 10625
0 1062
50
Printers/Scanner/Photocopier
45000 31
1406250 0 0 0 0
Networking and cabling 1403
51 20 28070
18 0 0 0 0
Generator Set 2631
6 20 52631
6 0 0 0 0
Digital Camera 7018 20 14035
1 0 0 0 0
Sub-Total (A) 61424
34 12625
0 1262
50 12625
0 12625
0
(B) Software
Passport System (Includes AMC for 5 years)
5263158 1
5263158
526316
526316
526316
526316
Data Digitisation 3508 1 35088 0 0 0 0
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 343 Confidential
8
Sub-Total (B) 52982
46 52631
6 5263
16 52631
6 52631
6
II Operational Expenditure ( C ) Salaried / Contract Staff
Project Manager 1800
00 1 18000
0 1980
00 2178
00 2395
80 2635
38
Solution / Application Architect
180000 1
180000
198000
217800
239580
263538
Domain Expert 1800
00 2 36000
0 3960
00 4356
00 47916
0 5270
76
Database administrator 0 1 0 0 0 0 0
Support Staff 1200
00 6 72000
0 7920
00 8712
00 9583
20 10541
52
Sub-Total ( C) 14400
00 1584000
1742400
1916640
2108304
(D) Others
User Training 1052
6 225 118421
1 11842
11 5921
05 59210
5 0
Change Management 3509 225 39473
7 3947
37 19736
8 19736
8 0
Office Maintenance 8421
1 20 16842
11 17684
21 1856842
1949684
2047168
Consumables 4211 20 84211 8842
1 9284
2 9748
4 1023
58
Sub-Total (D) 33473
68 3435
789 27391
58 2836
642 21495
27
Total (A+B+C+D) 16228
048 5672
355 51341
24 5405848
4910397
Channels I- eGovernment Portal
S.no.
Item Unit Cost (Cost
in Birr.)
Quantity/
Number of units
Year 1 (Cost
in Birr.)
Year 2 (Cost
in Birr.)
Year 3 (Cost
in Birr.)
Year 4 (Cost
in Birr.)
Year 5 (Cost
in Birr.)
I Capital Expenditure
(A) Hardware
Servers 2807018 2 5614035 561404 561404 561404 561404
Sub-Total (A)
5614035 561404 561404 561404 561404
(B) Software
Directory Services
526316 1 526316 17544 17544 17544 17544
Integration 350877 1 350877 17544 17544 17544 17544
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 344 Confidential
services
Upgradation costs
175439 1 175439 17544 17544 17544 17544
Content Development
175439
1 175439 17544 17544 17544 17544 Sub-Total
(B)
1228070 70175 70175 70175 70175 II Operation
al Expenditure
( C ) Salaried / Contract Staff
Project Manager
180000 1 180000 198000 217800 239580 263538
Database administrator
180000
2 360000 396000 435600 479160 527076 S/w
Developer 120000
15 180000
0 198000
0 217800
0 239580
0 263538
0 Support
Staff 120000
5 600000 660000 726000 798600 878460 Sub-Total (
C) 294000
0 323400
0 355740
0 391314
0 430445
4 (D) Others
User Training for Portal Management Team of MoCIT - 20 Persons
10526
30 315789 331579 348158 365566 383844 Sub-Total
(D)
315789 331579 348158 365566 383844 Total
(A+B+C+D)
10097895
4197158 4537137
4910285
5319877
Channels II - Contact Center S.no.
Item Unit Cost (Cost
in Birr.
)
Quantity/
Number of units
Year 1 (Cost
in Birr.)
Year 2 (Cost
in Birr.)
Year 3
(Cost in
Birr.)
Year 4
(Cost in
Birr.)
Year 5 (Cost
in Birr.)
I Capital Expenditure
(A) Hardware
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 345 Confidential
Servers 2000
00 2 40000
0 40000 40000 40000 40000
Personal Computers 1700
0 31 531250 53125 53125 53125 53125
Calling Equipment 1667 31 52083 2604 2604 2604 2604
IVRS & Call Routing 6666
7 1 66667 0 0 0 0
Networking and cabling
140351 1 140351 0 0 0 0
Printers/Scanner/Photocopier
7018 3 21930 0 0 0 0
Site Preparation 3333
3 1 33333 0 0 0 0
Sub Total (A) 124561
4 95729 95729 95729 95729
(B) Software
Call Centre Software (eg Clarity) (Includes AMC for 5 years)
1578947
1 157894
7 157895 157895 157895 157895
SubTotal (B) 157894
7 157895 157895 157895 157895
II Operational Expenditure
( C) Salaried / Contract Staff
Project Manager 1800
00 2
360000
396000
435600 479160 527076
HR&Admin Manager 5789
47 2
1157895
1273684
1401053
1541158
1695274
Call Center Shift Manager
385965
2 771930 849123
934035
1027439
1130182
Call Center Team Leader
315789 10
3157895
3473684
3821053
4203158
4623474
Call Centre Executives 23157
9 80 185263
16 20378
947 22416
842 24658
526 271243
79
Support Staff 4736
84 4 189473
7 20842
11 22926
32 252189
5 27740
84
Sub Total ( C ) 25868
772 28455
649 313012
14 344313
35 378744
69
(D) Other Costs
Lease Cost 8000
0 1 80000 84000 88200 92610 97241
User Training 10526 31 32894
7 345395 36266
4 38079
8 39983
8
Office Maintenance 84211 1 84211 88421 92842 97484 102358
Consumables (for 3 shifts) 4211 3 12632 13263 13926 14623 15354
Sub Total (D) 50578
9 531079 557633 585515 614790
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 346 Confidential
Total (A+B+C+D) 291991
23 29240
352 321124
71 35270
474 38742
883
Channels III- Mobile Gateway S.no.
Item Unit Cost (Cost
in Birr.)
Quantity/
Number of
units
Year 1 (Cost
in Birr.)
Year 2
(Cost in
Birr.)
Year 3
(Cost in
Birr.)
Year 4
(Cost in
Birr.)
Year 5
(Cost in
Birr.)
I Capital Expenditure
(A) Hardware
Servers 28070
18 1 14035
09 15438
60 29473
7 29473
7 29473
7
Sub Total (A) 14035
09 15438
60 29473
7 29473
7 29473
7
(B) Software
WAP Server 3577 100 357719 35772 35772 35772 35772
Content Converter 3577 100 357719 35772 35772 35772 35772
Application Development
SubTotal (B) 715439 71544 71544 71544 71544
II Operational Expenditure
( C ) Salaried / Contract Staff
Project Manager 18000
0 1 18000
0 19800
0 21780
0 23958
0 26353
8
IT Architect 18000
0 1
180000
198000
217800
239580
263538
Support Staff/Content Developer
120000
6 72000
0 79200
0 87120
0 95832
0 10541
52
DB Administrator 18000
0 1
180000
198000
217800
239580
263538
S/w Developer 12000
0 6
720000
792000
871200
958320
1054152
Sub Total ( C ) 19800
00 21780
00 23958
00 26353
80 28989
18
(D) Other Costs
Training and Awareness of the mobile mananmenegt team of MoCIT 10526 30 315789
331579
348158
365566
383844
Change Management of the mobile mananmenegt team of MoCIT 3509 30
105263
110526 116053 121855
127948
Sub-Total (D) 42105
3 44210
5 464211 48742
1 511792
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 347 Confidential
Total (A+B+C+D) 45200
00 42355
09 32262
91 34890
82 37769
91
Channels IV- Common Service Center S.no.
Item Unit Cost (Cost in Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
I Capital Expenditure
(A) Hardware
Personal Computers
17000 6400
108800000
10880000
10880000
10880000
10880000
Printers/Scanner/Photocopier
45000 6400
288000000 0 0 0 0
Biometric Device (per operator) 667 3200
2133333 0 0 0 0
Smart Card Reader (per operator) 1000 3200
3200000 0 0 0 0
Digital Camera (per operator) 7018 3200
22456140 0 0 0 0
Sub Total (A)
424589
474 10880
000 10880
000 10880
000 10880
000
(B) Software
Billing Software
3577 5 17886 224561
4 224561
4 224561
4 224561
4
Desktop Audit Software 3577 5 17886
2245614
2245614
2245614
2245614
Sub Total (B)
35772 449122
8 44912
28 449122
8 449122
8
II Operational Expenditure
( C )
Salaried / Contract Staff
Project Manager 1800
00 1 180000 198000 21780
0 23958
0 26353
8
HR & Admin Manager 5789
47 1 578947 636842 70052
6 770579 847637
Finance Manager 5789
47 1 578947 636842 70052
6 770579 847637
IT Admin 5263
16 1 526316 578947 63684
2 70052
6 770579
Site Inspection and Audit Manager
385965 1 385965 424561
467018 513719 565091
CSC Front Staff
42105 3200
134736842
148210526
163031579
179334737
197268211
Support Staff
120000 800
96000000
105600000
116160000
127776000
140553600
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 348 Confidential
Sub Total ( C) 232987
018 256285
719 281914
291 310105
720 341116
292
(D) Other Costs
Lease Cost - Per CSC office
53333 800
42666667
44800000
47040000
49392000
51861600
User Training - Per CSc operator 3509 3200
11228070
3368421
3368421
3368421
3368421
Office Maintenance - Per CSC office 4211 800
3368421
3536842
3713684
3899368
4094337
Consumables - Per Office 4211 800
3368421
3536842
3713684
3899368
4094337
Sub Total (D) 606315
79 552421
05 578357
89 605591
58 634186
95
Total (A+B+C+D) 718243
842 326899
053 355121
309 38603
6106 419906
215
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 349 Confidential
Enablers- Capacity Building
S.no.
Item Unit Cost (Cost
in Birr.
)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
I Capital Expenditure
(A) Hardware
Servers 2000
00 1 10000
0 11000
0 21000 21000 21000
Personal Computers 17000 160 27200
00 27200
0 27200
0 27200
0 27200
0
Printers/Scanner/Photocopier
45000 20
900000 0 0 0 0
Networking and cabling 14035
1 20 28070
18 0 0 0 0
Generator Set 26316 20 52631
6 0 0 0 0
Digital Camera 7018 20 14035
1 0 0 0 0
Sub-Total (A) 71936
84 38200
0 29300
0 29300
0 29300
0
(B) Software
CBT - Training content development
1578947 1
1578947 52632 52632 52632 52632
Central Knowledge Management Portal
526316 1
526316 52632 52632 52632 52632
SubTotal (B) 21052
63 10526
3 10526
3 10526
3 10526
3
II Operational Expenditure
( C ) Salaried / Contract Staff
Business Process Re-engineering Expert
771930 1
771930
849123
934035
1027439
1130182
PPP Expert 77193
0 1 77193
0 84912
3 93403
5 10274
39 11301
82
Advanced Technologies Expert
771930 1
771930
849123
934035
1027439
1130182
Software Development Expert
771930 1
771930
849123
934035
1027439
1130182
Trainers 35087
7 40
Sub Total ( C ) 30877
19 33964
91 37361
40 41097
54 45207
30
(D) Training and Other Costs
Leadership Orientation 13333 4 53333 56000 58800 61740 64827
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 350 Confidential
Programme 3 3 0 0 0 0
Project Management 3000 4 12000 12600 13230 13892 14586
Vendor Management 1667 4 6667 7000 7350 7718 8103
SLA Design and Monitoring 1667 4 6667 7000 7350 7718 8103
Customer orientation and support 667 4 2667 2800 2940 3087 3241
Office Maintenance - Per Training Insititute 84211 20
1684211
1768421
1856842
1949684
2047168
Consumables - Per Training Insititute 4211 20 84211 88421 92842 97484
102358
Sub Total (D) 23297
54 24462
42 25685
54 26969
82 28318
31
Total (A+B+C+D) 147164
21 63299
96 67029
58 72049
99 77508
24
Enablers - Marketing and Awareness
S.no.
Item Unit Cost (Cost in Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
(A) Salaried / Contract Staff
Marketing Director 77193
0 1
771930 849123
934035
1027439
1130182
Manager - PR 47368
4 1
473684 521053
573158
630474 693521
Marketing/PR Professional
385965
4 15438
60 16982
46 18680
70 20548
77 22603
65
Cost of Hiring of a Marketing and PR Agency
385965
1 385965 424561
467018 513719 565091
Sub Total (A ) 27894
74 30684
21 33752
63 371278
9 40840
68
(B) Other Costs
Direct Mailers 26680 12 32015
6 336164 35297
2 37062
1 389152
Billboards 32000 12 38400
0 40320
0 42336
0 44452
8 46675
4
Advertisements in Print Media 33696 12
404352
424570
445798
468088 491492
Radio Advertisements 56400 12 67680
0 71064
0 74617
2 78348
1 82265
5
Television Advertisements 99000 12
1188000
1247400
1309770
1375259
1444021
Online Marketing 66680 12 80015
6 84016
4 88217
2 92628
1 972595
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 351 Confidential
Events 66680 12 80015
6 84016
4 88217
2 92628
1 972595
Branded Gifts / Paraphanelia 33340 12
400076
420080
441084
463138
486295
Content Development 20000
0 12 24000
00 25200
00 26460
00 27783
00 291721
5
Sub Total (B) 73736
96 774238
1 81295
00 85359
75 89627
74
Total (A+B) 101631
70 10810
802 115047
63 12248
764 13046
842
Standards & Policies
S.no.
Item Unit Cost (Cost in Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
(A) Salaried / Contract Staff
CIO 87719
3 1 877193 964912 106140
4 116754
4 12842
98
Data & Process Expert
771930 1 771930 849123
934035
1027439
1130182
Technology Expert 77193
0 1 771930 849123 93403
5 102743
9 113018
2
Service Delivery Expert
771930 1 771930 849123
934035
1027439
1130182
Security Expert 77193
0 1 771930 849123 93403
5 102743
9 113018
2
Legal Expert 77193
0 1 771930 849123 93403
5 102743
9 113018
2
Sub-Total ( C)
47368
42 521052
6 573157
9 63047
37 693521
1
(B) Others
Training and Awareness of Standard and Poilicies department
10526 20 210526 221053 232105 243711
255896
Change Management of Standard and Poilicies department 3509 20 70175 73684 77368 81237 85299
Consumables 4211 1 4211 4421 4642 4874 5118
Sub-Total (D) 284912 299158 314116 32982
2 346313
5 Total (A+B) 502175
4 55096
84 60456
95 66345
58 728152
3
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 352 Confidential
Ethiopia - Core projects - EA
S.no.
Item Unit Cost (Cost
in Birr.
)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
I Capital Expenditure
(A) Hardware
Servers 2000
00 2 2000
00 2200
00 4200
0 4200
0 4200
0
Sub-Total (A) 2000
00 2200
00 4200
0 4200
0 4200
0
(B) Software
EA Tool 3500
00 1 21500
0 21500
0 2150
00 2150
00 2150
00
Central Knowledge Management Portal
526316 1
526316 0 0 0 0
SubTotal (B) 74131
6 21500
0 215000
215000
215000
II EA development Expenditure
( C ) Consultant cost
EA Architect 77193
0 1 77193
0 0 0 0 0
Team members 77193
0 3 23157
89 0 0 0 0
Trainers 35087
7 3 10526
32
Sub Total ( C ) 41403
51 0 0 0 0
(D) Training and Other Costs
Sub Total (D) 0 0 0 0 0
Total (A+B+C+D) 50816
67 4350
00 2570
00 2570
00 2570
00
Ethiopia - Core projects - NIAF
S.no.
Item Unit Cost (Cost
in Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
I Capital Expenditure
(A) Hardware
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 353 Confidential
Servers + all related H/w 4000
000 1 4000
000 0 0 0 0
Sub-Total (A) 4000
000 0 0 0 0
(B) Software
Software (all softwares) 4200
000 1 4200
000
SubTotal (B) 4200000 0 0 0 0
II Solution development Cost & Maintenance
( C )
Solution development Cost 25262500 1
25262500 0 0 0 0
Maintenance & support 500,000
500,000
500000
500000
Sub Total ( C ) 25262
500 5000
00 5000
00 500000
500000
(D) Training and Other Costs
Training cost 2000
00 1 2000
00 0 0 0 0
Consumables
4211 30 12631
6 0 0 0 0
Sub Total (D) 32631
6 0 0 0 0
Total (A+B+C+D) 33788
816 5000
00 5000
00 500000
500000
Ethiopia - Core projects - NSEB
S.no.
Item Unit Cost (Cost
in Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
I Capital Expenditure
(A) Hardware
Servers + all related H/w 3000
000 1 30000
00 0 0 0 0
Sub-Total (A) 30000
00 0 0 0 0
(B) Software
Software (all softwares) 74500
00 1 74500
00
SubTotal (B) 74500
00 0 0 0 0
II Solution development Cost & Maintenance
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 354 Confidential
( C )
Consultancy & Solution development Cost
9460000 1
9460000 0 0 0 0
Infrastructure set up 55900
0 1 55900
0 0 0 0 0
Sub Total ( C ) 10019000 0 0 0 0
(D) Training and Other Costs
Training cost 1 0 0 0 0 0
Consumables 4211 30 126316 0 0 0 0
Sub Total (D) 126316 0 0 0 0
Total (A+B+C+D) 20595
316 0 0 0 0
Ethiopia - Core projects - NPG
S.no.
Item Unit Cost (Cost
in Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
I Capital Expenditure
(A) Hardware
Servers + all related H/w 10750
000 1 10750
000 0 0 0 0
Sub-Total (A) 10750
000 0 0 0 0
(B) Software
Software (all softwares) 64500
00 1 64500
00
SubTotal (B) 64500
00 0 0 0 0
II Solution development Cost & Maintenance
( C )
Consultancy & Solution development Cost
10750000 1
10750000 0 0 0 0
Maintenance & support 0 0 0 0
Sub Total ( C ) 10750000 0 0 0 0
(D) Training and Other Costs
Training cost 1 0 0 0 0 0
Consumables 4211 30 126316 0 0 0 0
Sub Total (D) 126316 0 0 0 0
Total (A+B+C+D) 28076
316 0 0 0 0
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 355 Confidential
Ethiopia - Core projects - NDS
S.no.
Item Unit Cost (Cost
in Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
I Capital Expenditure
(A) Hardware
Servers + all related H/w 86000
00 1 86000
00 0 0 0 0
Sub-Total (A) 86000
00 0 0 0 0
(B) Software
Software (all softwares) 64500
00 1 64500
00
SubTotal (B) 64500
00 0 0 0 0
II Solution development Cost & Maintenance
( C )
Consultancy & Solution development Cost
21500000 1
21500000 0 0 0 0
Maintenance & support 0 0 0 0
Sub Total ( C ) 21500000 0 0 0 0
Consumables 4211 30 126316 0 0 0 0
Sub Total (D) 126316 0 0 0 0
Total (A+B+C+D) 36676
316 0 0 0 0
Common Applications - HRMS
S.no.
Item Unit Cost (Cost in
Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
I Capital Expenditure
(A) Hardware
Servers + all related H/w 2807
018 1 2807
018 0 0 0 0
Sub-Total (A) 2807
018 0 0 0 0
(B) Software
Software (all softwares) 70175
44 1 70175
44
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 356 Confidential
SubTotal (B) 70175
44 0 0 0 0
II Solution development Cost & Maintenance
( C )
Consultancy & Solution development Cost
4385965 1
4385965 0 0 0 0
Infrastructure set up 5590
00 1 5590
00 0 0 0 0
Sub Total ( C ) 4944965 0 0 0 0
(D) Training and Other Costs
Training cost
100 1052632
1052632
1052632
1052632
1052632
Consumables
4211 100 4210
53 4210
53 4210
53 4210
53 4210
53
Sub Total (D) 14736
84 1473684
1473684
1473684
1473684
Total (A+B+C+D) 16243
211 1473684
1473684
1473684
1473684
Common Applications - e-Office
S.no.
Item Unit Cost (Cost in
Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
I Capital Expenditure
(A) Hardware
Servers + all related H/w 2807
018 1 28070
18 0 0 0 0
Sub-Total (A) 28070
18 0 0 0 0
(B) Software
Software (all softwares) 70175
44 1 70175
44
SubTotal (B) 70175
44 0 0 0 0
II Solution development Cost & Maintenance
( C )
Consultancy & Solution development Cost
4385965 1
4385965 0 0 0 0
Infrastructure set up 5590
00 1 55900
0 0 0 0 0
Sub Total ( C ) 49449
65 0 0 0 0
(D) Training and Other Costs
Training cost 20 21052 2105 2105 2105 2105
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 357 Confidential
6 26 26 26 26
Consumables
4211 10 42105 4210
5 4210
5 4210
5 4210
5
Sub Total (D) 25263
2 2526
32 2526
32 2526
32 2526
32
Total (A+B+C+D) 15022
158 2526
32 2526
32 2526
32 2526
32
Common Applications - e-Procurement
S.no.
Item Unit Cost (Cost in
Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
I Capital Expenditure
(A) Hardware
Servers + all related H/w 2807
018 1 28070
18 0 0 0 0
Sub-Total (A) 28070
18 0 0 0 0
(B) Software
Software (all softwares) 70175
44 1 70175
44
SubTotal (B) 70175
44 0 0 0 0
II Solution development Cost & Maintenance
( C )
Consultancy & Solution development Cost
4385965 1
4385965 0 0 0 0
Infrastructure set up 5590
00 1 55900
0 0 0 0 0
Sub Total ( C ) 49449
65 0 0 0 0
(D) Training and Other Costs
Training cost
20 21052
6 2105
26 2105
26 2105
26 2105
26
Consumables
4211 10 42105 4210
5 4210
5 4210
5 4210
5
Sub Total (D) 25263
2 2526
32 2526
32 2526
32 2526
32
Total (A+B+C+D) 15022
158 2526
32 2526
32 2526
32 2526
32
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 358 Confidential
Common Applications - Financial Management and Information System
S.no.
Item Unit Cost
(Cost in Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
I Capital Expenditure
(A) Hardware
Upgrdation Costs -Servers + all related H/w 842105 1 842105 0 0 0 0
Sub-Total (A) 842105 0 0 0 0
(B) Software
Software (all softwares) 2105263 1 2105263
SubTotal (B) 2105263 0 0 0 0
II Solution development Cost & Maintenance
( C )
Consultancy & Solution development Cost 1315789 1 1315789 0 0 0 0
Infrastructure set up 55900 1 55900 0 0 0 0
Sub Total ( C ) 1371689 0 0 0 0
(D) Training and Other Costs
Training cost 0 0 0 0 0 0
Consumables 4211 0 0 0 0 0 0
Sub Total (D) 0 0 0 0 0
Total (A+B+C+D)
4,319,057.89 0 0 0 0
Ethiopia - Common Applications - Email Management and Information System
S.no.
Item Unit Cost (Cost in
Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
I Capital Expenditure
(A) Hardware
Servers + all related H/w 2807018 1 2807
018 0 0 0 0
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 359 Confidential
Sub-Total (A) 2807
018 0 0 0 0
(B) Software
Software (all softwares) 7017544 1 7017544
SubTotal (B) 7017544 0 0 0 0
II Solution development Cost & Maintenance
( C )
Consultancy & Solution development Cost 4385965 1
4385965 0 0 0 0
Infrastructure set up 559000 1 5590
00 0 0 0 0
Sub Total ( C ) 4944965 0 0 0 0
(D) Training and Other Costs
Training cost 0 0 0 0 0 0
Consumables 4211 0 0 0 0 0 0
Sub Total (D) 0 0 0 0 0
Total (A+B+C+D) 14769526 0 0 0 0
ITSG Salary of manpower
S.no.
Item Unit Cost (Cost
in Birr.
)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
Manpower costs
1
Solution / application architects
180,000.00 4
360,000.00
792,000.00
871,200.00
958,320.00
1,054,152.00
2 Database Administrators
180,000.00 6
540,000.00
1,188,000.00
1,306,800.00
1,437,480.00
1,581,228.00
3
Software Developers
120,000.00 8
480,000.00
1,056,000.00
1,161,600.00
1,277,760.00
1,405,536.00
4
Web Administrator
120,000.00 2
120,000.00
264,000.00
290,400.00
319,440.00
351,384.00
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 360 Confidential
Total
1,500,000.00
3,300,
000.00
3,630,000.00
3,993,000.00
4,392,
300.00 PMO Staff Costs
Item Unit Cost (Cost
in Birr.)
Quantity/ Number of units
Year 1 (Cost in Birr.)
Year 2 (Cost in Birr.)
Year 3 (Cost in Birr.)
Year 4 (Cost in Birr.)
Year 5 (Cost in Birr.)
Manpower costs
Team Leaders
180,00
0.00 7
1,260,000.00
1,386,000.00
1,524,600.00
1,677,060.00
1,844,766.00
Team Members
120,00
0.00 10
600,000.00
1,320,000.00
1,452,000.00
1,597,200.00
1,756,920.00
Total
1,860,000
.00
2,706,000.00
2,976,60
0.00
3,274,26
0.00
3,601,686.00
Development of e-Government Strategy and Implementation Plan Inception Report
PricewaterhouseCoopers Page 361 Confidential
www.pwc.com
© 2010 PricewaterhouseCoopers. All rights reserved. “PricewaterhouseCoopers”, a registered trademark, refers to
PricewaterhouseCoopers Private Limited (a limited company in India) or, as the context requires, other member firms of
PricewaterhouseCoopers International Limited, each of which is a separate and independent legal entity.