Dynamics 365 for Finance and OperationsGo-live planning
About this Tech Talk
What it doesn’t cover
Go-live planning: agenda1. Glossary and key concepts2. Go-live assessment process3. Go-live checklist4. Important implementation considerations5. Resources
Tech Talk: Go-live planning
Go-live planning: agenda1. Glossary and key concepts2. Go-live assessment process3. Go-live checklist4. Important implementation considerations5. Resources
Tech Talk: Go-live planning
Glossary and key concepts
The time period and activities when the customer transitions from their legacy system to D365FO
Usually performed over a weekend, the ‘cutover weekend’
A trial run of the cutover activities after Production is available but before actual cutover
Confirming that the solution works as expected on Production environment
Executing the solution with the goal to find and fix gaps and issues
This is done on DEV/TEST and UAT environments
Glossary and key concepts, ctd.
The date when the customer will start using Production for live business transactions
Date when deployment of Production has completedDepending on solution complexity, a couple weeks or months before go-live
Go-live planning: agenda1. Glossary and key concepts2. Go-live assessment process3. Go-live checklist4. Important implementation considerations5. Resources
Tech Talk: Go-live planning
Go-live assessment in a nutshell
Why?
Ensure a smooth go-live
Reduce number of escalations later
When?
We send you an email about 8 weeks before your go-live date
You should send the Checklist when you are (almost) done with User Acceptance Test (UAT)
At least 1 to 2 weeks before you plan to request production
How?
Via workshop or email, based on your FastTrack service level
Assessment report with ample guidance specific to your project
Go-live assessment process
*If applicable
Production
Deployment
Request
DB copy
from Sandbox
Request*
Deployable
Package
Installation
Request*
Sizing Deployment Install Copy
Production
ready
Finalize cut over
Update Go-live
date in LCS
FastTrack
architect
review
1
Go-live
Complete and send
Pre-Go-live checklist
Go-live
Assessment/Workshop
Release for
Production
Deployment
2
3
4
5
6
7
8
9
Take action: Please set your estimated Go-live date as soon as possibleYour go-live can be impacted by not updating your go-live date in LCS and by
not following this process
Learn More: Prepare for Go-live and Go-live FAQ
Go-live planning: agenda1. Glossary and key concepts2. Go-live assessment process3. Go-live checklist4. Important implementation considerations5. Resources
Tech Talk: Go-live planning
Go-live checklist
Keep go-live milestone date updated throughout your implementation
Keep LCS users updated –add real email accounts
We send email from Dynamics 365 Pre [email protected] 8 weeks before your go-live date
You can also download the Go-live checklist and send it to [email protected] –always download the latest version
Tech Talk: Go-live planning
• Per email or as part of a workshop (based on FastTrack service level)
• Must be completed before Production can be deployed
• Mitigations might be required and need to be addressed
Go-live planning: agenda1. Glossary and key concepts2. Go-live assessment process3. Go-live checklist4. Important implementation considerations5. Resources
Tech Talk: Go-live planning
Tenant strategy
What is an Azure AD tenant
• How to make sure the licenses end up on the right tenant• Work with your customer to understand which other Microsoft cloud
services they already have and on which tenant they are running
• CSP: make sure you use the correct path in PartnerCenter to either create a new tenant or place subscriptions onto an existing tenant (“Request reseller relationship”)
• VL: make sure your reseller knows which tenant the subscriptions should be placed on
Subscriptions, licenses, accounts, and tenants for Microsoft's cloud offerings
• What to do if the implementation was started on the wrong tenant?Move an LCS Implementation project to another Azure Active Directory tenant
customer.com
License management
• Why is it important to purchase all licenses before the start of implementation?
• FastTrack programService level based on license count (threshold 150 enterprise-equivalent licenses)
Microsoft FastTrack for Finance and Operations
• Production SizingProduction will be sized as per user licenses shown on the active subscription estimate
If you changed the number of licenses after you created the currently active subscription estimate, it is important to create and activate a new estimate prior to requesting Production
If you increase license count after going-live (future roll-outs) it is important to create and activate new subscription estimate.
Solution scope and roll-outs
• FastTrack accompanies you during the first roll-out
• Why do we want to know your scope and rollout plan?
• Plan your incremental rollouts and license needs
• Incremental go-lives and environment management
Need DEV and UAT environments to service Production
Need DEV and UAT environment for new functionality
Watch the Environment PlanningTechTalk
Lifecycle Services (LCS)
Keep your milestones updated
Keep your users updated
Complete the methodology
Stay up to date
Solution acceptance
• Test on the right environment – UAT must be performed on Tier-2 (or higher)
• Test the real thing
• Concurrency
• Data volumes
• Batch jobs
• Printing, emailing, integrations, workflow, etc.
• Don’t implement outside of the subscription
• The topology of the environments that are local or in your private cloud is not like the ones in the subscription and hence may not be similar to production environment as well
• The performance of the system cannot be measured when you do the UAT on local or private hosted VMs
• In case of integrations, it is important to test this on the tier 2 sandbox environment as the environment configurations could be different on your local environment
• It is important that the team experiences the servicing in LCS (like applying updates, creating service requests and others) during the implementation. This makes sure that the customer is familiar with the servicing process upfront.
• Get business sign-off
Configuration data management
• Data packages
• To export and import data into Dynamics 365 for Finance and operations
• Thoroughly test your data packages on UAT
• Golden configuration database
• Tier-1 add-on: cost effective, but more work for you to copy the database to Tier-2
• Tier-2 add-on: higher cost, but supports direct refresh to Production
How to get the configuration data onto Production
• Database Refresh
• Copy your golden configuration data from any Tier-2 environment to Production
• If database is on a Tier-2 environment already: service request
• If database is on a Tier-1 environment: first bacpac to Tier-2, then service request for database refresh
Copy a Finance and Operations database from SQL Server to a production Azure SQL Database environment
• Point in time restore
• Supports rollback of your data on an Azure SQL database to a specific date and time in the past (no more than 35 days back)
Restore a database on a non-production environment
• Do not manually configure Production from scratch
Performance
• Why should I worry about performance? Isn’t that Microsoft’s responsibility?
• Performance is a combined effort since performance can be affected by variables outside of Microsoft’s influence, including but not limited to your customizations, ISV code, system configurations, timing of batch jobs and integrations
• Where and how much performance testing do I need to do?
• Environment can range from Tier-2 to Tier-5 (Premium Performance Test)
• Concurrency
• Test with realistic data volumes
• Test your customizations, take traces
• Test all your integrations on UAT
• Select the right data center
• Validate connection latency from where the user will be connecting to Dynamics using http://www.azurespeed.com/.
• If your latency result is under 300ms you are in the safe range.
• Watch the Performance Testing ApproachTechTalk
Integrations
• Choose the appropriate Integration patterns and practices for your data and scenario
• Make sure that all integrations are using supported endpoints as described in Services Home Page
• Configure and test your integrations in Sandbox: Standard Acceptance Test environment. Validate with real life data volumes and frequencyof recurrence to confirm that integrations will succeed and meet required performance targets.
• Watch the Integration TechTalks:
Integration Frameworks within Dynamics 365 for Finance & Operations (DYN385PAL)
Azure Integration Tools for Dynamics 3654 for Finance & Operations (DYN386PAL)
Code management
• Set up Visual Studio Team Services (VSTS) for source control
• Use a build environment to build your deployable packages
• Minimize the number of deployable code packages – get to 1
Manage third-party models and runtime packages by using source control
Apply a deployable package
• Understand code promotion from BUILD to UAT and Production
• On Production, code deployment is a scheduled service request with a lead time
• DEV, UAT, and Production must be on same platform and application versions
• Finalize your release candidate - code stability pre Go-live
User and security setup
• Test with the right roles
• Know how to move security setup between environments
All your custom roles and roles association to users can be moved between environments using data entities. The data entities to use are:
Security duty metadata customizations entity
Security privilege metadata customizations entity
Security role metadata customizations entity
Security segregation of duties conflict
Security segregation of duties rule
Security user role association
• The importance of the admin user
• First log-on after initial deployment to any environment – in that case the Admin is the only user that can access the environment
• First log-on to a sandbox environment after a database refresh from Production – in that case all user accounts except for the Admin account are disabled
Cutover
• Have a signed-off cutover plan – down to the minute
• The benefit of a mock cutoverHelps establish the timings for cutover
Gives the team confidence
• Validate the solution in ProductionUse database refresh and point-in-time restore to your advantage
c
Golden Configs
Restore complete
DB
restore
Golden Configs
CompleteMaster Data
Import complete
Opening Balances
Import complete
Mock cutover
Complete
Testing /
Validation
Cutover
Complete
LiveGolden
Gold Env
CutoverData
Packages/
Manually
Configured
Data Packages/
IntegrationsData Entities
1st
Milestone
Cycle
2nd
Milestone3rd Milestone 4th Milestone
Golden Configs
Golden Configs
+
Master Data
Golden Configs
+
Master Data +
Beginning
Balances
First go-live
Production Environment
Monitoring and Support
• How you can monitor your environmentMonitoring and Diagnostics
• Understand support plans and teamsMicrosoft Dynamics 365 Support
• Know how to submit support tickets through LCS Find support for Microsoft Dynamics 365 for Finance and Operations, Enterprise edition and Dynamics Lifecycle Services
• What if Production is down?New process to report a production outage through Lifecycle Services
Getting Production
1. Request
Production
2. Set up
Production
3. Validate
Production
• Configure Production
environment – self-service
request
• Use a generic account for the
Environment administrator
• Select the correct data center,
app and platform version,
package to slipstream
• Allow up to 2 business days for
deployment
• You are responsible to get code
and data onto Production through
service requests
• Allow for lead times
• Minimize number of packages
• Have data ready on a Tier-2
environment
• Validate on Production – Test on
Sandbox
• You can request Point-in-time
restore or database refresh during
cutover phase
Go-live planning: agenda1. Glossary and key concepts2. Go-live assessment process3. Go-live checklist4. Important implementation considerations5. Resources
Tech Talk: Go-live planning
Additional resources
Understand the Implementation Lifecycle
Microsoft Finance and Operations TechTalks
FastTrack Finance and Operations
TechTalksDocs
Community
Thank you!We wish you a successful go-live!