“Delivering Outstanding Services”
Dyer Brio Project Update
Strategic Plan 2015 Goal:
7) Enhance and Sustain El Paso’s Infrastructure Network
Strategy:
7.2 Improve competitiveness through infrastructure improvements impacting the quality of life
“Delivering Outstanding Services” 2
Brio Articulated Vehicles
• 60-foot long articulated vehicle
• 45 seated capacity, 59 standing capacity
• ADA Ramp Deployment • On-board Digital El Paso
Hot Spot • On-board bicycle rack • Next stop request • Fare box
Vehicle Improvements
“Delivering Outstanding Services”
Brio Service Improvements
• Frequent bus service 10 min peak, and 15 min off peak 14 hours M-F: 6am – 8pm 11 hours Sat/Holiday: 9am – 6pm No Sunday/Holiday Service
• Less frequent bus stops (approx 1 mile spacing) • Traffic signal prioritization
3
“Delivering Outstanding Services”
Brio Station Improvements
• Pedestrian lighting/sidewalks • Ticket Vending Machines • Digital El Paso Hot Spot • Near-level boarding • ADA accessibility • Landscaping • Bicycle racks • Station Artwork • Real-time displays • Solar trash compactor • Information display case • Mini-shelter design concept
4
“Delivering Outstanding Services” 6
Dyer Brio Corridor
Corridor Features:
• Length: 11 miles
• From DTC to Northgate TC (proposed)
• Station Platforms: 18
• Vehicles: 10
“Delivering Outstanding Services”
Dyer BRIO
12
Alameda BRIO
Project Overview
Districts 2, 4, and 8
Approved Budget $35.7M
Source(s) of Funding Certificates of Obligation, Category 2, FTA5309
Completion of Design March 2016
Construction Let Date July 2016
Critical Assumptions New TxDOT requirements, if any ROW issues/concerns, if any
Open to the Public November 2017
“Delivering Outstanding Services”
Northgate Transfer Center
13
Alameda BRIO
Project Overview
Districts 2, 4, and 8
Approved Budget $15.5M
Source(s) of Funding Certificates of Obligation, Tiger V
Completion of Design January 2016
Construction Let Date February 2016
Critical Assumptions ROW issues/concerns, if any
Open to the Public Late 2017 / Early 2018