A Parents’ Guide to supporting your child’s learning at Dŵr y Felin.
Dŵr ymru yfyngedig (D) - Planning Inspectorate · Dwr Cymru Cyfyngedig (DCC) Interested Party...
Transcript of Dŵr ymru yfyngedig (D) - Planning Inspectorate · Dwr Cymru Cyfyngedig (DCC) Interested Party...
Dŵr Cymru Cyfyngedig (DCC)
Interested Party Reference: 10027373
Planning Inspectorate Application Ref: EN010059 Hirwaun Power Station
Written Submissions
OG 8/21/2014
Dwr Cymru Cyfyngedig (DCC) Interested Party Reference: 10027373
2
SUBMISSION CONTENTS
1.0 SUMMARY OF REPRESENTATION
2.0 CONTEXT OF REPRESENTATION
3.0 DWR CYMRU CYFYNGEDIG (DCC)
4.0 DCC INVOLVEMENT IN APPLICATION
5.0 LOCAL INFRASTRUCTURE
6.0 DCC CONCERNS
ANNEXES
A) DCC RELEVANT REPRESENTATION
B) DCC SCHEDULE OF LAND & ASSETS
C) COPY OF HIRWAUN POWER LTD EMAIL DATED 15TH AUGUST
Dwr Cymru Cyfyngedig (DCC) Interested Party Reference: 10027373
3
1. SUMMARY OF REPRESENTATION
The Examining Authority (‘The Panel’) has requested a summary of an Interested Party’s
representation where the submission exceeds 1500 words. Accordingly, we trust that the following
summary provides an overview of Dŵr Cymru Cyfyngedig’s (DCC) written representation.
1.1 Sections 2.0 and 3.0 sets out the context of this submission and DCC’s role as a statutory
undertaker. DCC is the sixth largest of the ten regulated water and sewerage companies in
England and Wales. Since 2001, we have been owned, financed and managed by Glas
Cymru. Unique in the water and sewerage sector, Glas Cymru is a company limited by
guarantee and as such has no shareholders.
1.2 Section 4.0 provides an overview of DCC’s involvement in the application process both at
pre-application and examination stage. This section clarifies the extent of liaison with
Hirwaun Power Limited.
1.3 Section 5.0 provides The Panel with an understanding of the location of DCC assets within
the Order Limits.
1.4 Section 6.0 refers to matters raised as part of the Relevant Representation, relating
predominantly to the impact of the proposed development upon water quality and water
resources, given the proximity of the site to Penderyn Reservoir and Hirwaun Water
Treatment Works. Based on the information provided within the application documents and
the further information provided by Hirwaun Power Ltd, DCC is currently satisfied that the
potential impact upon both Penderyn Reservoir and the Water Treatment Works can be
mitigated.
1.5 Section 6.0 also refers to the protection of DCC assets and apparatus and the intention to
provide protective provisions. DCC confirms that discussions on the Provisions with Hirwaun
Power Ltd are in an advanced stage, with an agreed intention to submit such Provisions by
Deadline II of the examination timetable.
Dwr Cymru Cyfyngedig (DCC) Interested Party Reference: 10027373
4
2. CONTEXT OF REPRESENTATION
2.1 This submission by Dŵr Cymru Cyfyngedig (DCC) relates to the proposed Development
Consent Order (DCO) for the construction and operation of Hirwaun Power Station.
2.2 This submission takes into account all documentation made available following submission
of the DCO on 21 March 2014, including:
- Hirwaun Power Limited Application Documents
- Publication of The Panel’s Procedural Decisions
- Publication of The Panel’s first round of written questions
- DCC’s Relevant Representation as attached as Annexe B
- Relevant Representations by other Interested Parties
2.3 This representation is submitted in accordance with Deadline I (21st August) of the
examination timetable as confirmed by The Panel’s Procedural Decision issued on 29th July
2014.
Dwr Cymru Cyfyngedig (DCC) Interested Party Reference: 10027373
5
3.0 DŴR CYMRU CYFYNGEDIG (DCC)
3.1 DCC is the sixth largest of the ten regulated water and sewerage companies in England and
Wales. Since 2001, we have been owned, financed and managed by Glas Cymru. Unique in
the water and sewerage sector, Glas Cymru is a company limited by guarantee and as such
has no shareholders.
Glas Cymru
- Glas Cymru is a single purpose company formed to own, finance and manage DCC.
- The company is ‘limited by guarantee’ and secured ownership of DCC in 2001.
- Glas Cymru, as a ‘not-for-profit’ company, is unique in the UK water industry and the
wider utilities sector.
- With no shareholders, profits are reinvested to improve services and keep customer bills
low.
- Under Glas Cymru’s ownership, DCC cannot diversify into new and riskier business
activities and therefore its only concern is its responsibilities as a water and sewerage
company.
Dŵr Cymru Welsh Water
- 1.4 million household and business customers in Wales and parts of Herefordshire and
Deeside.
- 6th largest of the 23 regulated
water companies in Wales and
England.
- Responsible for operating,
maintaining and upgrading
assets to ensure a safe and
reliable drinking water supply
and to deal effectively with
waste water to protect the
environment.
- We look after 67 reservoirs, and
supplies 828 million litres of
safe, clean drinking water
through 27,000km of pipes to
over three million people every
day.
- Operate around 30,000km of
wastewater pipes – or all the
way to Australia and back - and
deal with over 2,000 blockages a month and manage to stop flooding or pollution in 99%
of cases.
Dwr Cymru Cyfyngedig (DCC) Interested Party Reference: 10027373
6
4.0 DCC INVOLVEMENT IN APPLICATION
4.1 PRE-APPLICATION
DCC were consulted at pre-application stage under section 42 of the Planning Act 2008 as a
Statutory Undertaker for water and sewerage. Accordingly, DCC provided comments in
regard to the impact of the proposed development, specifically drawing the applicant’s
attention to;
- Potential impact of the proposals upon the adjacent Penderyn Reservoir
- Potential impact of the proposals upon Hirwaun Water Treatment Works
- Potential impact upon the structural integrity of DCC assets including sewers and
watermains within the boundary of the development site.
4.2 RELEVANT REPRESENTATION
Following the decision to accept the application for examination, DCC submitted its relevant
representation and registered as an Interested Party. DCC’s relevant representation is
included as Annex B to this submission.
4.3 ENGAGEMENT WITH HIRWAUN POWER LTD (HPL)
During both pre-application and examination stages of the Planning Act 2008 process, DCC
has been actively engaged with HPL in relation to the impact of the development upon our
assets.
We are pleased to confirm that we have recently met with representatives of HPL to discuss
our position and potential impact upon our assets. In addition, we can confirm that
discussions regarding suitable protective provisions have been positive. Further information
is provided in the following sections.
Dwr Cymru Cyfyngedig (DCC) Interested Party Reference: 10027373
7
5. LOCAL INFRASTRUCTURE
It is considered beneficial for The Panel as well as all Interested Parties to be provided with
an overview of DCC assets within the area, and specifically within the Order Limits subject to
this proposed Development Consent Order.
5.1 HIRWAUN WATER TREATMENT WORKS
Hirwaun Water Treatment Works (WTW) is the main potable water treatment facility
supplying water to the immediate area and the Cynon valley as a whole. The communities
supplied include Rhigos, Mountain Ash, Abercwmboi, Penderyn and parts of Aberdare. It can
potentially also feed Ynysybwl, Bryntirion, Glenboi and Darrenlas depending on network
configuration. Hirwaun WTW is fed by Penderyn reservoir, however the reservoir has no
direct catchment and is filled primarily by flows captured in two indirect stream catchments
– the Nant Bodwigiad and Nant Bwllfa. When inflow to the reservoir from these streams
decline they are supplemented by decanting water into Penderyn reservoir from the nearby
Nant Moel impounding reservoir. Should further raw water resource be required, there is a
borehole source available that can pump water into Penderyn reservoir.
Water is extracted from the adjacent Penderyn raw water reservoir and fed directly into the
water treatment works. Following treatment the water enters the onsite Clear Water Tank
(CWT) before being pumped to the Million Gallon/Rhigos Service Reservoir (SRV). From
there the water is pumped further up the valley to the Red Lion SRV as well as gravitating
directly out of the Million Gallon SRV to feed customers within the Cynon Valley.
Although a small quantity of potable water can be transferred into the supply network to
support Hirwaun WTW from the adjacent Taff Valley Hirwaun WTW remains the key potable
water supply for approximately 15,000 properties. Hirwaun WTW treats an average of 4
million litres of water per day.
A site location plan of Penderyn Reservoir and adjacent Hirwaun Water Treatment Works is
provided on the following page.
Dwr Cymru Cyfyngedig (DCC) Interested Party Reference: 10027373
9
5.2 HIRWAUN WASTE WATER TREATMENT WORKS (WwTW)
Hirwaun Waste Water Treatment Works is located close to the application site, and serves
the Industrial Estate, the village of Rhigos and outlying residential properties. Accordingly,
Any flows intended to discharge from this development site to the public sewerage network
would to Hirwaun Waste water Treatment Works.
The public sewerage system serving the area of the proposed development is predominantly
of a separate type, therefore a mixture of foul only and surface water only networks. It
should be noted that the site is crossed by a number of public foul water and surface water
sewers ranging in size from a 150mm diameter up to 450mm diameter. Information on the
location of such assets is included at Annex B of this submission and have since been shared
with Hirwaun Power Limited.
Dwr Cymru Cyfyngedig (DCC) Interested Party Reference: 10027373
10
6. DCC CONCERNS
DCC’s relevant representation attached at Annex B includes the following statement:
The specific concerns for DCC include, but are not limited to, the potential impact on:
a) Penderyn Reservoir
b) Hirwaun Water Treatment Works
c) Hirwaun Wastewater Treatment Works
d) Water resources
e) Water quality
f) DCC’s public sewers as a result of trade effluent discharges
g) The structural integrity of DCC assets and apparatus
h) DCC’s statutory rights of access to its sewers, watermains and associated
Apparatus
i) DCC’s ability to fulfil its statutory obligations
j) DCC’s land and associated rights
For the benefit of The Panel and all Interested Parties, these concerns are expanded upon below.
6.1 PENDERYN RESERVOIR, HIRWAUN WATER TREATMENT WORKS (WTW) & IMPACTS ON
WATER QUALITY & RESOURCES
- WATER RESOURCES
Section 5.1 has provided an overview of Hirwaun Water Treatment Works and its supply
catchment. Although a small quantity of potable water can be transferred into the supply
network to support Hirwaun WTW from the adjacent Taff Valley, Hirwaun WTW remains the
key potable water supply for approximately 15,000 properties.
DCC’s relevant representation identified possible impacts upon this water supply. To provide
further context, DCC’s concern is the vulnerability of supplies in this area since a proportion
of our customers normally fed from Hirwaun WTW are unable to be supplied from other
sources. Therefore, any detrimental harm to the function of Penderyn Reservoir and
subsequently the receiving Water Treatment Works would result in an interruption to supply
for a number of customers.
DCC has reviewed the application documents including the Environmental Statement which
relates to Water Resources. Further, DCC acknowledges information provided by HPL in an
email dated 15th August (attached at Annex C).
Based on this information and in particular details contained in Sections 9.7.17 to 9.7.20 of
the Environmental Statement which states that there will be “no change” to local water
supply resources (potential extra 30m3/d of demand), from a water resources/supply
Dwr Cymru Cyfyngedig (DCC) Interested Party Reference: 10027373
11
perspective DCC is satisfied that the proposed development does not raise any issues in
regard to additional demand placed on the clean water supply network.
Further, it is understood that there is no demand for any process related water supply
generated by this development.
- WATER QUALITY
DCC’s Relevant Representation also referred to the potential impact of the development
upon water quality. In this context, DCC has reviewed the application documents and further
information provided by HPL in its email of 15th August 2014.
DCC has considered the impact on water supply catchments in the vicinity of the site and is
satisfied with the impact of the development upon these areas.
DCC has also reviewed the impact upon the adjacent Penderyn Reservoir and Hirwaun Water
Treatment Works from a water quality perspective. Following a detailed analysis of the
Environmental Statement we concur with HPL’s position that the impact upon Penderyn
Reservoir are deemed to be not significant. DCC draws The Panel’s attention to HPL’s email
of 15th August and Figure’s 6.2 to 6.4 of the Environmental Statement which has been
considered as part of our analysis.
Notwithstanding the above, DCC recommends that provision is made for HPL to notify DCC
of any potential impact upon the reservoir and Water Treatment Works of which it becomes
aware. It is envisaged that such arrangements can be agreed as part of the Protective
Provisions unless The Panel considers that alternative arrangements should be considered.
6.2 HIRWAUN WASTE WATER TREATMENT WORKS (WwTW)
In considering the development proposals, DCC is satisfied that the discharge of domestic
foul flows only from the proposed development site can be accommodated within the public
sewerage system and receiving WwTW. Matters regarding ‘process’ related flows are
covered in section 6.3.
It has been noted that during operation HPL intend to discharge surface water flows to the
public surface water sewer to the south of the site, if determined to be the existing drainage
arrangements for the existing buildings at the site. In the interests of our existing customers
and the environment we encourage the developer to consider methods of Sustainable
Urban Drainage (SUDS). SUDs is an approach to managing surface water runoff which seeks
to imitate natural drainage systems and retain water on or near the site as opposed to
traditional drainage approaches which involve piping water off site as quickly as possible.
SUDs involve a range of techniques including soakaways, infiltration trenches, and
permeable pavements etc. SUDs offer significant advantages over conventional piped
Dwr Cymru Cyfyngedig (DCC) Interested Party Reference: 10027373
12
drainage systems in reducing flood risk by attenuating the rate and quantity of surface water
run-off from a site, promoting groundwater recharge, and improving water quality and
amenity.
In regard to the management of surface water flows deriving from the development site,
DCC encourages HPL to continue to engage with us to discuss and resolve matters.
6.3 DCC’s PUBLIC SEWERS AS A RESULT OF TRADE EFFLUENT DISCHARGES
HPL has advised DCC that any trade effluent waste generated during the power generation
processes will be removed by a licensed contractor and disposed of away from the site. This
is confirmed in HPL’s email of 15th August 2014. DCC therefore concludes that the
development will not dispose of any waste flows via the public sewerage network.
Should circumstances change, DCC invites HPL to discuss any requirements at the earliest
opportunity as an assessment of whether the sewerage network and receiving Waste water
Treatment Works has any capacity to deal with such flows would be required.
For the benefit of The Panel and the developer, DCC advised that should the discharge of
trade effluent, directly or indirectly to the public sewerage system be required, then a
Discharge Consent under Section 118 of the Water Industry Act 1991 should be sought from
DCC.
6.4 THE STRUCTURAL INTEGRITY OF DCC ASSETS AND APPARATUS
DCC owns, operates, maintains, improves and extends the system of public sewers, water
mains and associated apparatus together with treatment works and pumping stations
(‘apparatus/assets’) and has corresponding statutory duties to ensure effectual drainage and
for making available supplies of water.
DCC’s interest is to protect the apparatus/assets.
The spreadsheet and plans attached at Annex B identify all DCC’s apparatus/assets directly
affected by the proposed development.
DCC is negotiating with HPL in relation to the impacts of the proposed development on the
apparatus/assets in order to agree protective provisions to ensure that there is no adverse
impact upon the apparatus/assets and, subsequently, no adverse impact upon DCC’s
statutory duties, rights and powers.
DCC can confirm that discussions around Protective Provisions with HPL are in an advance
stage and it has been agreed between both parties that such provisions will be submitted to
the Examining Authority at Deadline II.
Dwr Cymru Cyfyngedig (DCC) Interested Party Reference: 10027373
13
6.5 DCC’S STATUTORY RIGHTS OF ACCESS TO ITS SEWERS, WATERMAINS AND ASSOCIATED
APPARATUS & DCC’S ABILITY TO FULFIL ITS STATUTORY OBLIGATIONS
DCC’s statutory rights to retain its apparatus in situ, to access, inspect, maintain, renew and
repair apparatus located within or in close proximity to the limits of the proposed
development must not be interfered with. These rights are set out in Sections 158 and 159
of the Water Industry Act 1991 and Part II Schedule 6.
As above, DCC is negotiating with HPL in relation to the potential impacts of the proposed
development on DCC’s statutory rights. Without unfettered access DCC would be unable to
fulfil its statutory obligations to lay, maintain, repair, replace etc. and ultimately provide a
service to its customers; in addition DCC could face a referral to OFWAT, its regulator
followed by enforcement requiring compliance with statutory obligations.
The Draft DCO provides HPL with an element of control over the apparatus. Protective
provisions will ensure that DCC maintains complete control of the apparatus and assets to
enable to fulfil its statutory obligations whilst allowing the HPL development to proceed.
Without these protective provisions, the Draft DCO could result in an interference with
DCC’s statutory duties, rights and powers.
6.6 DCC’S LAND AND ASSOCIATED RIGHTS
DCC must maintain unfettered access to its apparatus and assets at all times for the reasons
set out above.
DCC has reviewed the application documents relating to Compulsory Acquisition
information, specifically the Statement of Reasons, Funding Statement and Book of
Reference (documents 4.1, 4.2 and 4.3 respectively). DCC acknowledges that HPL has
recorded the parcels of land relevant to DCC and DCC’s particular interests within those
parcels. DCC has begun positive discussions with HPL about the protection of apparatus and
assets within those parcels.
1. Dŵr Cymru Cyfyngedig (DCC) is a statutory undertaker responsible for providing over three
million people with a continuous, high-quality supply of drinking water and for taking away,
treating and disposing of wastewater. DCC owns, operates, maintains, improves and extends
the system of public sewers, water mains and associated apparatus together with treatment
works and pumping stations and has corresponding statutory duties to ensure effectual
drainage and for making available supplies of water. DCC’s primary concern within the context
of this application for Development Consent therefore is to ensure that statutory obligations
are met and that our customers and the environment are protected.
2. DCC has actively engaged with Hirwaun Power during the pre-application stage with regard to
the potential impact of the proposed development upon DCC’s assets and apparatus. DCC will
seek to work collaboratively with Hirwaun Power in this context to inform the examination of
the application.
3. The specific concerns for DCC include, but are not limited to, the potential impact on:
a. Penderyn Reservoir b. Hirwaun Water Treatment Works c. Hirwaun Wastewater Treatment Works d. Water resources e. Water quality f. DCC’s public sewers as a result of trade effluent discharges g. The structural integrity of DCC assets and apparatus h. DCC’s statutory rights of access to its sewers, watermains and associated apparatus i. DCC’s ability to fulfil its statutory obligations j. DCC’s land and associated rights
4. The Environmental Statement (‘ES’) refers to the presence of Hirwaun Water Treatment
Works, Penderyn Reservoir and the associated catchment. The ES states that the effect of
emissions from the proposed development upon water quality will be negligible. DCC need to
understand more fully what the effects will be and how the ES arrived at such a conclusion.
DCC also need further details of the water requirements for the proposed development in
order to ensure that an adequate supply can be maintained for all DCC customers.
5. DCC advises that matters relating to emissions and their subsequent effect on water quality
are considered carefully by the Examining Authority (ExA) during the examination of this
application. DCC further advises that the impact from similar developments and the proposed
development should be considered cumulatively by the ExA during the examination of this
application.
6. DCC require details of whether it is the intention of the applicant to apply for discharge
consent for trade effluent to discharge from the proposed development into the public sewer
network.
7. DCC would welcome early engagement with Hirwaun Power in order to determine the
potential impact of the proposed development upon Hirwaun Wastewater Treatment works.
DCC has concerns about the impact of the development upon the capacity of the works and
require further details from Hirwaun Power before submitting more detailed representations.
8. The draft DCO in its current form is inconsistent with DCC’s existing statutory rights and
obligations. In this context DCC will engage with Hirwaun Power with a view to agreeing
protective provisions for inclusion in Schedule 9 of the Draft Development Consent Order
(‘DCO’).
9. In regard to land proposed to be compulsory acquired DCC will provide further information
detailing DCC’s concerns for each affected plot.
10. DCC intends to make detailed representation on the draft DCO during the examination stage
of this PA2008 process.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
A B C D E F G H
HIRWAUN POWER STATION DCC LAND SCHEDULE 15th JULY 2014
HIRWAUN POWER STATION DRAWING NUMBER DCC ASSET NAME TYPE OF DCC APPARATUS DIAMETER OF DCC APPARATUS DCC ASSET NUMBER RIGHTS TO BE ACQUIRED BY HIRWAUN POWER NATURE OF WORKS BY HIRWAUN POWER DCC LEGAL/STATUTORY RIGHTS
Overall Plan Reg5(2)(o) Drawing Number Figure 4 n/a Distribution Water Main 200mm n/a tbc Gas Connection Route and Electrical Connection Route Statutory Rights as shown on Plan 1 of 3
n/a Surface Water Gravity Sewer 300mm n/a tbc Gas Connection Route Statutory Rights as shown on Plan 1 of 3
n/a Surface Water Gravity Sewer 375mm n/a tbc Gas Connection Route Statutory Rights as shown on Plan 1 of 3
n/a Surface Water Gravity Sewer 450mm n/a tbc Gas Connection Route Statutory Rights as shown on Plan 1 of 3
n/a Foul Gravity Sewer 150mm n/a tbc Gas Connection Route Statutory Rights as shown on Plan 1 of 3
n/a Foul Gravity Sewer 300mm n/a tbc Gas Connection Route Statutory Rights as shown on Plan 1 of 3
n/a Distribution Water Main 6" n/a tbc Gas Connection Route Statutory Rights as shown on Plan 1 of 3
n/a Distribution Water Main 100mm n/a tbc Gas Connection Route Statutory Rights as shown on Plan 1 of 3
n/a Distribution Water Main 180mm n/a tbc Gas Connection Route Statutory Rights as shown on Plan 1 of 3
n/a Raw Water Trunk Main 315mm n/a tbc Gas Connection Route Statutory Rights as shown on Plan 1 of 3
n/a Abandoned Distribution Water Main 17/7/2001 10" n/a tbc Gas Connection Route and Electrical Connection Route Statutory Rights as shown on Abandoned Apparatus Plan 1 of 2
n/a Abandoned Distribution Water Main 12/12/1992 n/a tbc Gas Connection Route Statutory Rights as shown on Abandoned Apparatus Plan 1 of 2
Gas Connection Routes Drawing Number Figure 5 n/a Distribution Water Main 4" n/a tbc Gas Connection Route Statutory Rights as shown on Plan 2 of 3
n/a Distribution Water Main 110mm n/a tbc Gas Connection Route Statutory Rights as shown on Plan 2 of 3
n/a Trunk Water Main 300mm n/a tbc Gas Connection Route Statutory Rights as shown on Plan 2 of 3
n/a Abandoned Distribution Water Main 20/9/2001 3" n/a tbc Gas Connection Route Statutory Rights as shown on Abandoned Apparatus Plan 2 of 2
Hirwaun Power Station 15th July 2014
?
?? ?
?
??
???
?
?
?
?
??
?
?
??
???
??
?
?
?
?
?? ?
?
?
?
?
?
?
??
?
?
? ?
?
?
?
? ???
?
?
?
?
?
?
?
??
?
??
??? ?? ? ?? ? ? ?
?
?
?
?
?
?
??
??
?
?
?
?
?
?
??
?
?
??? ?
?
?
??
?
??
?
?
?
?
??
?
HH
HH
HH
HH
HHHH
Hirwaun Industrial EstateYstad Ddiwydiannol Hirwaun
Hirwaun
Sewage Works
Estate
Nant y Cnapiau
Pont yr Ochain
Nant Llechau
Twyn Bryn-hir
Tip
Tip
Plan 1 of 3
Notes:Dwr Cymru apparatus plan
Dwr Cymru Cyf gives this information as to the position of its underground apparatus by wayof general guidance only on the strict understanding that it is based on the best informationavailable and no warranty as to its correctness is relied upon in the event of excavations orother works made in the vicinity of the Company’s apparatus and any onus of locating theapparatus before carrying out any excavations rests entirely on you. It must be understoodthat the furnishing of the information is entirely without prejudice to the provision of the NewRoads and Streetworks Act 1991 and of the Company’s right to be compensated for anydamage to its apparatus.Service pipes are not generally shown but their presence should be anticipated.
Reproduced by permission of Ordnance Survey on behalf ofHMSO. © Crown copyright and database right 2008.
All rights reserved.Ordnance Survey License number 100019534.
EXACT LOCATIONS OF ALL APPARATUSTO BE DETERMINED ON SITE.
15/07/2014Printed on:sgreyPrinted by:
1:5,000Map scale:Map Ref:
TapPressure ReducingValve
Sluice Valve
MeterBulk MeterFire HydrantCap
Existing DistributionMain
Non Dwr Cymru
Air Valve SINGLE
Gravity SewerRising MainOutfallPumping StationLamphole
Combined Sewer OverflowSpecial Purpose ChamberTreatment Works
NB:Sewer symbol colour indicates the sewer type.RED - CombinedGREEN - Surface WaterBROWN - Foul
LEGEND (Representative of most common features)
Private Sewer Transfer
Inspection ChamberLateral Drain
Whilst every reasonable effort has been taken to correctly record the pipe material of DCWW assets, there is a possibility that in some cases pipe material (other than Asbestos Cement or Pitch Fibre) may be found to be asbestos cement (AC) or Pitch Fibre (PF) . It is therefore advisable that the possible presence of AC or PF pipes be anticipated and considered as part of any risk assessment prior to excavation
293829, 206003
?
?
? ???
?
?
?
?
?
?
?
?
??
?? ? ?? ? ? ?
?
?
?
?
?
?
??
??
?
?
?
??
?
?
?
?
?
??
?
?
??
?
??
?
?
?
?
?
?
? ?
?
?
?
?
?? ?
?
?
?
?
?
?
?
?
?
?
?
?
?
?
??
?
?
?
?
?
??
?
?
?
??
?
??
?
?
?
?
?
PPPP
?P
P P
PP P
?T
??
?
??
PP?P P
?P?P ?
P?P ?P?P?T?T
?T ?T
?P
?P
P?P?P
?P
?P
L?T
?T
TT ?T
PTT
?TT?T
?T
T?T TTT?T T
?TT T
?T T
?T?T
T T
?T
T
LTP
P
?T?T
?T
?T ?T
?T
?T
T
?
?
?P
?T
P?T
?
?
Hirwaun
Estate
Industrial
Nant y Cnapiau
Bryn-y-Gaer Cemetery
Afon Cynon
Mineral Railway
Ystad Ddiwydiannol HirwaunHirwaun Ponds
Tip
Hirwaun Ponds
Tip
Tip
Plan 2 of 3
Notes:Dwr Cymru apparatus plan
Dwr Cymru Cyf gives this information as to the position of its underground apparatus by wayof general guidance only on the strict understanding that it is based on the best informationavailable and no warranty as to its correctness is relied upon in the event of excavations orother works made in the vicinity of the Company’s apparatus and any onus of locating theapparatus before carrying out any excavations rests entirely on you. It must be understoodthat the furnishing of the information is entirely without prejudice to the provision of the NewRoads and Streetworks Act 1991 and of the Company’s right to be compensated for anydamage to its apparatus.Service pipes are not generally shown but their presence should be anticipated.
Reproduced by permission of Ordnance Survey on behalf ofHMSO. © Crown copyright and database right 2008.
All rights reserved.Ordnance Survey License number 100019534.
EXACT LOCATIONS OF ALL APPARATUSTO BE DETERMINED ON SITE.
15/07/2014Printed on:sgreyPrinted by:
1:5,000Map scale:Map Ref:
TapPressure ReducingValve
Sluice Valve
MeterBulk MeterFire HydrantCap
Existing DistributionMain
Non Dwr Cymru
Air Valve SINGLE
Gravity SewerRising MainOutfallPumping StationLamphole
Combined Sewer OverflowSpecial Purpose ChamberTreatment Works
NB:Sewer symbol colour indicates the sewer type.RED - CombinedGREEN - Surface WaterBROWN - Foul
LEGEND (Representative of most common features)
Private Sewer Transfer
Inspection ChamberLateral Drain
Whilst every reasonable effort has been taken to correctly record the pipe material of DCWW assets, there is a possibility that in some cases pipe material (other than Asbestos Cement or Pitch Fibre) may be found to be asbestos cement (AC) or Pitch Fibre (PF) . It is therefore advisable that the possible presence of AC or PF pipes be anticipated and considered as part of any risk assessment prior to excavation
294615, 205965
VC 300 mm.
CONC 450 mm.
VC 300 mm.
CONC 375 mm.
CONC 450 mm.VC 300 mm.
VC 1
50 m
m.VC
150
mm.
VC 300 mm. CONC 450 mm.CONC 450 mm.
??
? ? ? ?
??
??
??
?
?
SN93066109
SN93068101SN93068102
SN93067101
SN93066108
SN93067102
SN93066102SN93066103 SN93066105
SN93067103
SN93066107
SN93066101
SN93066104 SN93066106, ,
!
!,
,!!
!
!
,
!
,,,
ð
180mm. MDPE 1992
6IN. CI 1912
6IN. CI 1912
6IN. CI 1912
6IN.
CI
1912
200mm. DIEL 2001 ()
200mm. DIEL 2001 ()
200mm. DIEL 2001 ()
200mm. DIEL 2001 ()!FH/WO
!FH/WO
!FH
!FH ð
ðð
ð
#
AA AAA
A
A
A
Pont yr Ochain
TCB212.4m
ElSub Sta
El Sub Sta
Tanks
Drain
FOURTH AVENUE
MAIN AVENUE
Bryn-Hir
Plan 3 of 3
Notes:Dwr Cymru apparatus plan1:1250 @ initial gas connection from proposed site
Dwr Cymru Cyf gives this information as to the position of its underground apparatus by wayof general guidance only on the strict understanding that it is based on the best informationavailable and no warranty as to its correctness is relied upon in the event of excavations orother works made in the vicinity of the Company’s apparatus and any onus of locating theapparatus before carrying out any excavations rests entirely on you. It must be understoodthat the furnishing of the information is entirely without prejudice to the provision of the NewRoads and Streetworks Act 1991 and of the Company’s right to be compensated for anydamage to its apparatus.Service pipes are not generally shown but their presence should be anticipated.
Reproduced by permission of Ordnance Survey on behalf ofHMSO. © Crown copyright and database right 2008.
All rights reserved.Ordnance Survey License number 100019534.
EXACT LOCATIONS OF ALL APPARATUSTO BE DETERMINED ON SITE.
15/07/2014Printed on:sgreyPrinted by:
1:1,250Map scale:Map Ref:
TapPressure ReducingValve
Sluice Valve
MeterBulk MeterFire HydrantCap
Existing DistributionMain
Non Dwr Cymru
Air Valve SINGLE
Gravity SewerRising MainOutfallPumping StationLamphole
Combined Sewer OverflowSpecial Purpose ChamberTreatment Works
NB:Sewer symbol colour indicates the sewer type.RED - CombinedGREEN - Surface WaterBROWN - Foul
LEGEND (Representative of most common features)
Private Sewer Transfer
Inspection ChamberLateral Drain
Whilst every reasonable effort has been taken to correctly record the pipe material of DCWW assets, there is a possibility that in some cases pipe material (other than Asbestos Cement or Pitch Fibre) may be found to be asbestos cement (AC) or Pitch Fibre (PF) . It is therefore advisable that the possible presence of AC or PF pipes be anticipated and considered as part of any risk assessment prior to excavation
293680, 206150
Hirwaun Industrial EstateYstad Ddiwydiannol Hirwaun
Hirwaun
Sewage Works
Estate
Nant y Cnapiau
Pont yr Ochain
Nant Llechau
Twyn Bryn-hir
Tip
Tip
Abandoned ApparatusPlan 1 of 2
Notes:
Dwr Cymru Abandoned Apparatus Plan
Dwr Cymru Cyf gives this information as to the position of its underground apparatus by wayof general guidance only on the strict understanding that it is based on the best informationavailable and no warranty as to its correctness is relied upon in the event of excavations orother works made in the vicinity of the Company’s apparatus and any onus of locating theapparatus before carrying out any excavations rests entirely on you. It must be understoodthat the furnishing of the information is entirely without prejudice to the provision of the NewRoads and Streetworks Act 1991 and of the Company’s right to be compensated for anydamage to its apparatus.Service pipes are not generally shown but their presence should be anticipated.
Reproduced by permission of Ordnance Survey on behalf ofHMSO. © Crown copyright and database right 2008.
All rights reserved.Ordnance Survey License number 100019534.
EXACT LOCATIONS OF ALL APPARATUSTO BE DETERMINED ON SITE.
15/07/2014Printed on:sgreyPrinted by:
1:5,000Map scale:Map Ref:
TapPressure ReducingValve
Sluice Valve
MeterBulk MeterFire HydrantCap
Existing DistributionMain
Non Dwr Cymru
Air Valve SINGLE
Gravity SewerRising MainOutfallPumping StationLamphole
Combined Sewer OverflowSpecial Purpose ChamberTreatment Works
NB:Sewer symbol colour indicates the sewer type.RED - CombinedGREEN - Surface WaterBROWN - Foul
LEGEND (Representative of most common features)
Private Sewer Transfer
Inspection ChamberLateral Drain
Whilst every reasonable effort has been taken to correctly record the pipe material of DCWW assets, there is a possibility that in some cases pipe material (other than Asbestos Cement or Pitch Fibre) may be found to be asbestos cement (AC) or Pitch Fibre (PF) . It is therefore advisable that the possible presence of AC or PF pipes be anticipated and considered as part of any risk assessment prior to excavation
293841, 205990
Hirwaun
Estate
Industrial
Nant y Cnapiau
Bryn-y-Gaer Cemetery
Afon Cynon
Mineral Railway
Ystad Ddiwydiannol HirwaunHirwaun Ponds
Tip
Hirwaun Ponds
Tip
Tip
Abandoned ApparatusPlan 2 of 2
Notes:
Dwr Cymru Abandoned Apparatus Plan
Dwr Cymru Cyf gives this information as to the position of its underground apparatus by wayof general guidance only on the strict understanding that it is based on the best informationavailable and no warranty as to its correctness is relied upon in the event of excavations orother works made in the vicinity of the Company’s apparatus and any onus of locating theapparatus before carrying out any excavations rests entirely on you. It must be understoodthat the furnishing of the information is entirely without prejudice to the provision of the NewRoads and Streetworks Act 1991 and of the Company’s right to be compensated for anydamage to its apparatus.Service pipes are not generally shown but their presence should be anticipated.
Reproduced by permission of Ordnance Survey on behalf ofHMSO. © Crown copyright and database right 2008.
All rights reserved.Ordnance Survey License number 100019534.
EXACT LOCATIONS OF ALL APPARATUSTO BE DETERMINED ON SITE.
15/07/2014Printed on:sgreyPrinted by:
1:5,000Map scale:Map Ref:
TapPressure ReducingValve
Sluice Valve
MeterBulk MeterFire HydrantCap
Existing DistributionMain
Non Dwr Cymru
Air Valve SINGLE
Gravity SewerRising MainOutfallPumping StationLamphole
Combined Sewer OverflowSpecial Purpose ChamberTreatment Works
NB:Sewer symbol colour indicates the sewer type.RED - CombinedGREEN - Surface WaterBROWN - Foul
LEGEND (Representative of most common features)
Private Sewer Transfer
Inspection ChamberLateral Drain
Whilst every reasonable effort has been taken to correctly record the pipe material of DCWW assets, there is a possibility that in some cases pipe material (other than Asbestos Cement or Pitch Fibre) may be found to be asbestos cement (AC) or Pitch Fibre (PF) . It is therefore advisable that the possible presence of AC or PF pipes be anticipated and considered as part of any risk assessment prior to excavation
294615, 205959
From: Murray Davies [[email protected]] Sent: 15 August 2014 13:14 To: George Owain Cc: HUTCHISON Robin ([email protected]) Subject: RE: Hirwaun Power - application for Development Consent Follow Up Flag: Follow up Flag Status: Completed Owain Apologies for the late reply, I was hoping to be able to send over the marked up Protective Provisions along with this but time has been against us this week. Please see the following clarifications from our Environmental Consultants and Engineers on the points raised during our meeting. Impacts on Penderyn Resevoir and Hirwaun Clean Water Works Ambient air quality in the vicinity of the Project is currently good and will remain so with the operation of the Project. The principal emissions form the combustion of gas are nitrogen oxides and carbon monoxide; emissions of hazardous pollutants such as dioxins and metals are not associated with gas power stations. Predicted concentrations of nitrogen dioxide and carbon monoxide resulting from the Project at Penderyn Reservoir are imperceptible. Impacts from annual and hourly nitrogen dioxide emission at Penderyn Reservoir are deemed not significant based on the Environment Agency H1 Annex F guidance (Figure 6.2 -6.4 in the ES). Impacts on the Hirwaun Clean Water works are also deemed not significant as ground level concentrations of nitrogen dioxide, the main pollutant of concern, over the works are imperceptible. Therefore air quality at both facilities will not be affected by the proposals. Domestic Waste and Water Connection Requirements A small amount of water will be required for drinking and sanitation purposes but this is not expected to exceed 30 m3/day. An existing mains water supply already provides the International Greetings UK site with mains water for toilets, kitchens etc. It is therefore envisaged that this water supply would continue to be used during operation of the Power Generation Plant for the same purposes. A comparable or slightly number of operational workers would be employed at the Power Generation Plant Site to the number employed at the International Greetings UK facility. Therefore the domestic/sanitary water requirements during operation will be broadly similar. During operation, surface water drainage from the Power Generation Plant Site may be discharged to the DCC surface water sewer to the south of the site if this is determined to be the existing drainage regime for the International Greetings UK site. Consent to discharge surface water runoff to the DCC surface water sewer will be discussed with DCC during detailed design of the Power Generation Plant to ensure that all requirements can be met. Where possible, existing discharge connections will be reused to reduce disruption to the public sewer. Site infrastructure will be designed in accordance with EA Pollution Prevention Guidelines and industry best practice. The drainage system that will be installed to serve the new Power Generation Plant Site will incorporate oil separators designed and manufactured in accordance with BS EN 858-1 to remove hydrocarbons and oils prior to discharge. A programme of regular maintenance will be put in place to ensure the installed infrastructure performs in accordance with design and a detailed emergency response plan will be prepared which will be enacted in the event of a spill of hazardous material. No effluent generated by processes on the Power Generation Plant Site will be discharged to sewers. Any water generated during washing will be retained on the
Power Generation Plant Site in a storage tank and subsequently tanked off-site by a licensed contractor for disposal at an appropriately licensed disposal facility. The proposed Power Generation Plant Site will not increase the impermeable area when compared to the existing International Greetings UK site. Therefore, the development of the Power Generation Plant will not increase the rate or volume of surface water runoff from the site when compared to the existing situation. It is proposed that the foul drainage from the Power Generation Plant will continue to discharge to the DCC public foul sewer located to the south of the Power Generation Plant Site. As noted above, a comparable number of operational workers would be employed at the Power Generation Plant Site to the number employed at the International Greetings UK facility and as a result there is no anticipated impact on foul drainage infrastructure or the receiving Hirwaun Waste Water Treatment Works. Consent to discharge foul water to the DCC foul water sewer will be discussed DCC during detailed design of the Power Generation Plant to ensure that all requirements can be met. Where possible, existing discharge connections will be reused to reduce disruption to the public sewers. Potential for heat to be generated by gas connection pipeline We can confirm that during normal operation no significant heat will be generated. During construction there will be welding activities which should be considered Hot works, however the heat is not predicted to be significant enough to reach any WW assets and is unlikely to take in close proximity to WW assets. Proposed method for crossing the identified raw water main to/from Pendyrn Reservoir We are proposing to open cut that road crossing as at this stage the ground conditions look inconvenient for an auger bore (but not ruling it out). We were aware of this asset and it the pipeline has been considerd in the conceptual design of the gas pipeline undertaken by HPL. We would propose that our crossing would not interfere with the asset and would expect that at detailed design stage HPL would discuss construction method statements with DCC prior to construction. The depth of cover information you provided is useful and would likely suggest that we would go deeper to avoid any issues. Hope the above is helpful and provides some clarity. If you would like to discuss further or have any questions, please let me know. We are currently looking at the PP’s and hope to send a marked up version over early next week. Kind Regards Murray
Stag Energy t: +44 (0)131 550 3380 f: +44 (0)131 550 3399 m:+44 (0)7748 394 762 www.stagenergy.com