Duncan Glen - Delmarva Power...Mar 30, 2017 · Pre-Construction Meeting Presentation . Presented...
Transcript of Duncan Glen - Delmarva Power...Mar 30, 2017 · Pre-Construction Meeting Presentation . Presented...
![Page 1: Duncan Glen - Delmarva Power...Mar 30, 2017 · Pre-Construction Meeting Presentation . Presented by: Gas Engineering New Business . March 30, 2017 . 2 . Providing Natural Gas To](https://reader034.fdocuments.net/reader034/viewer/2022051910/600077c44715fb72d742dbe8/html5/thumbnails/1.jpg)
1
Duncan Glen
Pre-Construction Meeting Presentation
Presented by: Gas Engineering New Business
March 30, 2017
![Page 2: Duncan Glen - Delmarva Power...Mar 30, 2017 · Pre-Construction Meeting Presentation . Presented by: Gas Engineering New Business . March 30, 2017 . 2 . Providing Natural Gas To](https://reader034.fdocuments.net/reader034/viewer/2022051910/600077c44715fb72d742dbe8/html5/thumbnails/2.jpg)
2
Providing Natural Gas To Duncan Glen
![Page 3: Duncan Glen - Delmarva Power...Mar 30, 2017 · Pre-Construction Meeting Presentation . Presented by: Gas Engineering New Business . March 30, 2017 . 2 . Providing Natural Gas To](https://reader034.fdocuments.net/reader034/viewer/2022051910/600077c44715fb72d742dbe8/html5/thumbnails/3.jpg)
3
Duncan Glen Project Overview
Total Feet of Pipe Installed:
• approx. 1900’ of 2”
• Approx. 1300’ of 4”
Customers in project area:
• 48 directly impacted
Customers signed up for gas service line:
• 29 customers or 60% - Need one more applicant for project to
proceed
Size of PY pipe to be installed:
• 2” & 4”
![Page 4: Duncan Glen - Delmarva Power...Mar 30, 2017 · Pre-Construction Meeting Presentation . Presented by: Gas Engineering New Business . March 30, 2017 . 2 . Providing Natural Gas To](https://reader034.fdocuments.net/reader034/viewer/2022051910/600077c44715fb72d742dbe8/html5/thumbnails/4.jpg)
4
Preliminary Design – Duncan Glen
![Page 5: Duncan Glen - Delmarva Power...Mar 30, 2017 · Pre-Construction Meeting Presentation . Presented by: Gas Engineering New Business . March 30, 2017 . 2 . Providing Natural Gas To](https://reader034.fdocuments.net/reader034/viewer/2022051910/600077c44715fb72d742dbe8/html5/thumbnails/5.jpg)
5
Duncan Glen Construction Timeline
Construction Schedule:
• Begin construction – April 10th
• Complete main installation – May 24th
• Complete final restoration – September 29th
All work is weather dependent
Scope of work may change daily due
to unforeseen conditions
The intent is to complete final
restoration once all main and services
are complete.
Temporary restoration will be done at the end of each task or
week.
![Page 6: Duncan Glen - Delmarva Power...Mar 30, 2017 · Pre-Construction Meeting Presentation . Presented by: Gas Engineering New Business . March 30, 2017 . 2 . Providing Natural Gas To](https://reader034.fdocuments.net/reader034/viewer/2022051910/600077c44715fb72d742dbe8/html5/thumbnails/6.jpg)
6
Natural Gas Expansion Project
Project scope involves:
• Marking of utility lines – 8-1-1
• Choptank will test hole over main
• Set up of the directional drill
• Excavation of the receiving pits, etc.
• Boring of the main
• Gas main will be tied-in (energized)
• Installation of service lines to applicable locations (bore)
• Restoration will occur once all main and services are complete
![Page 7: Duncan Glen - Delmarva Power...Mar 30, 2017 · Pre-Construction Meeting Presentation . Presented by: Gas Engineering New Business . March 30, 2017 . 2 . Providing Natural Gas To](https://reader034.fdocuments.net/reader034/viewer/2022051910/600077c44715fb72d742dbe8/html5/thumbnails/7.jpg)
7
Installation of Natural Gas
Preliminary order of Gas Main installation by street for Duncan
Glen
1. Duncan Rd
2. Faulkland Rd
3. W. Kenmore Dr
4. Hannam Rd
5. Charles Rd
6. N Cora Loop
7. S Cora Loop
![Page 8: Duncan Glen - Delmarva Power...Mar 30, 2017 · Pre-Construction Meeting Presentation . Presented by: Gas Engineering New Business . March 30, 2017 . 2 . Providing Natural Gas To](https://reader034.fdocuments.net/reader034/viewer/2022051910/600077c44715fb72d742dbe8/html5/thumbnails/8.jpg)
8
Service Installations
Services will be installed to each applicant when the customer
is ready to start receiving natural gas
Each applicant will have an on-site meeting with the field
technician and during those on-site meetings it will be
determined if the customer is ready to receive a natural gas
service line during this project.
Applicants are refunded their $200 security deposit when
natural gas is flowing to the residence for a gas-fired appliance.
Customer Converts & Gas meter is installed Security deposit refunded
![Page 9: Duncan Glen - Delmarva Power...Mar 30, 2017 · Pre-Construction Meeting Presentation . Presented by: Gas Engineering New Business . March 30, 2017 . 2 . Providing Natural Gas To](https://reader034.fdocuments.net/reader034/viewer/2022051910/600077c44715fb72d742dbe8/html5/thumbnails/9.jpg)
9
Gas Conversion Projects: Staging of Material
Locations in
neighborhood that
have been identified
as low traveled areas
are used for the
staging of materials.
Material is coned off
for safety and kept to
minimum level of
encroachment into
roadway.
![Page 10: Duncan Glen - Delmarva Power...Mar 30, 2017 · Pre-Construction Meeting Presentation . Presented by: Gas Engineering New Business . March 30, 2017 . 2 . Providing Natural Gas To](https://reader034.fdocuments.net/reader034/viewer/2022051910/600077c44715fb72d742dbe8/html5/thumbnails/10.jpg)
10
Gas Expansion Projects: Test Holes
Test holes may be performed prior to main installation by either
hand digging or possibly vacuum excavation
![Page 11: Duncan Glen - Delmarva Power...Mar 30, 2017 · Pre-Construction Meeting Presentation . Presented by: Gas Engineering New Business . March 30, 2017 . 2 . Providing Natural Gas To](https://reader034.fdocuments.net/reader034/viewer/2022051910/600077c44715fb72d742dbe8/html5/thumbnails/11.jpg)
11
Gas Conversion Projects: Test Holes
Left: Test hole areas left safe with proper coverage until
temporary restoration
Right: Completed temporary restoration with backfill
![Page 12: Duncan Glen - Delmarva Power...Mar 30, 2017 · Pre-Construction Meeting Presentation . Presented by: Gas Engineering New Business . March 30, 2017 . 2 . Providing Natural Gas To](https://reader034.fdocuments.net/reader034/viewer/2022051910/600077c44715fb72d742dbe8/html5/thumbnails/12.jpg)
12
Gas Conversion Project: Main Installation
Install new main throughout neighborhood in the state right-of-
way at the curb line utilizing a directional bore technique.
Equipment may need to encroach on private property for
perpendicular main alignments
![Page 13: Duncan Glen - Delmarva Power...Mar 30, 2017 · Pre-Construction Meeting Presentation . Presented by: Gas Engineering New Business . March 30, 2017 . 2 . Providing Natural Gas To](https://reader034.fdocuments.net/reader034/viewer/2022051910/600077c44715fb72d742dbe8/html5/thumbnails/13.jpg)
13
Gas Conversion Project: Main Installation
Right: temporary restoration on a driveway that was open cut
due to unforeseen underground conditions
Left: temporary restoration on large section of receiving pit for
main
![Page 14: Duncan Glen - Delmarva Power...Mar 30, 2017 · Pre-Construction Meeting Presentation . Presented by: Gas Engineering New Business . March 30, 2017 . 2 . Providing Natural Gas To](https://reader034.fdocuments.net/reader034/viewer/2022051910/600077c44715fb72d742dbe8/html5/thumbnails/14.jpg)
14
Gas Conversion Project: Main Installation
Final Restoration On Driveway
![Page 15: Duncan Glen - Delmarva Power...Mar 30, 2017 · Pre-Construction Meeting Presentation . Presented by: Gas Engineering New Business . March 30, 2017 . 2 . Providing Natural Gas To](https://reader034.fdocuments.net/reader034/viewer/2022051910/600077c44715fb72d742dbe8/html5/thumbnails/15.jpg)
15
Gas Conversion Project: Main Installation - Temporary
Restoration
Left: temporary restoration of test hole in roadway
Right: temporary restoration of disturbed area in right-of-way
![Page 16: Duncan Glen - Delmarva Power...Mar 30, 2017 · Pre-Construction Meeting Presentation . Presented by: Gas Engineering New Business . March 30, 2017 . 2 . Providing Natural Gas To](https://reader034.fdocuments.net/reader034/viewer/2022051910/600077c44715fb72d742dbe8/html5/thumbnails/16.jpg)
16
Service line, Riser, & Meter bar
When customer is ready to
convert to a gas-fired
appliance, they must:
• Hire a licensed contractor to
install fuel lines
• Have NCCO inspect & tag
fuel line
• Private contractor ties fuel
line into meter bar
• Call Delmarva Power to
schedule meter install
![Page 17: Duncan Glen - Delmarva Power...Mar 30, 2017 · Pre-Construction Meeting Presentation . Presented by: Gas Engineering New Business . March 30, 2017 . 2 . Providing Natural Gas To](https://reader034.fdocuments.net/reader034/viewer/2022051910/600077c44715fb72d742dbe8/html5/thumbnails/17.jpg)
17
Meter Installation
Example of Inspection Tag
![Page 18: Duncan Glen - Delmarva Power...Mar 30, 2017 · Pre-Construction Meeting Presentation . Presented by: Gas Engineering New Business . March 30, 2017 . 2 . Providing Natural Gas To](https://reader034.fdocuments.net/reader034/viewer/2022051910/600077c44715fb72d742dbe8/html5/thumbnails/18.jpg)
18
Duncan Glen Gas Project Contact Sheet
Gas New Business Coordinator – Mike June
• Email: [email protected]
• Phone: (302) 429-3290
Field Technician – Eric Mease
• Email: [email protected]
• Phone: (302) 275-8975
Project Engineer – Rob Serrano
• Email: [email protected]
• Phone: (302) 429-3051
![Page 19: Duncan Glen - Delmarva Power...Mar 30, 2017 · Pre-Construction Meeting Presentation . Presented by: Gas Engineering New Business . March 30, 2017 . 2 . Providing Natural Gas To](https://reader034.fdocuments.net/reader034/viewer/2022051910/600077c44715fb72d742dbe8/html5/thumbnails/19.jpg)
19
Questions?
Thanks for attending!