DPR on Piccadily Sugar
-
Upload
aditya-maheshwari -
Category
Documents
-
view
227 -
download
2
Transcript of DPR on Piccadily Sugar
INTRODUCTION
Piccadily Agro Industries Limited(PAIL),a public limited
company incorporated on March 25, 1994 is setting up a new plant
for manufacturing of crystal sugar and super refined white sugar
with licenced capacity of 2500 TCD at village-Bhadson, tehsil
Indri in district Karnal(Haryana). Mill will start its trial
operation at fag end of crushing season 1995-96. Expansion of
crushing capacity to 3500 TCD will be effected in next season
1996-97 season. Final expansion to 5000 TCD will be effected in
near future. At 3500 TCD it is proposed to co-generate surplus
power of 4.94 MW. At 5000 TCD surplus co-generated power for
export will be about 11.2 MW. PAIL is in joint sector with
Haryana State Industrial Development Corporation Ltd(HSIDC) as
co-promoter.
Group of companies under Piccadily umbrella are:
Piccadily Sugar & Allied Industries Limited(PSAIL)
Piccadily Hotels Private Limited(PHPL)
Piccadily Holiday Resorts Limited (PHRL)
Soon-N-Sure Holdings Private limited(SNSHPL)
Promoters are also having large number of hotels restaurants
and bars and other business. These hotels are running into
profits for last several years. Promoters are also having
interest in trading activities. Promoters hold about 60 acres of
agricultural land in Punjab, Himachal pradesh and Chandigarh.
1
PAIL management of factory, which lays great emphasis on
all-around performance improvement, has rightly embarked on a
comprehensive programmes for sugar cane development, like
introduction of foundation seeds, fertilizer on subsidized rates,
supply of plant protection equipment, crop insurance, farmers
welfare scheme etc.
It is also proposed that PAIL will assist farmers in
obtaining loans for seed, fertilizer, pesticides, implements from
commercial banks as crop loan and interest component in deserving
cases is proposed to be borne by mill. At this stage a provision
of Rs 25 Lacs is also being made to provide financial aid to
farmers so that adequate cane availability can be ensured for
expansion of crushing capacity to 5000 TCD.
PRODUCTS
PAIL proposes following products
1. White crystal sugar
2. Super refined white sugar
3. Packaged soft sugar
BY PRODUCTS
1. Bagasse
2. Molasses
3. Co-generation of power
The cane for factory has a fiber content of 14.5%. The
bagasse(with 50% moisture) production is taken to be 30% on cane.
An allowance for bagacillo and start up wastes has been made and
2
for the purpose of boiler combustion, the available bagasse is
taken as 28%. The potential of huge quantum of surplus bagasse,
in near future when expansion will be done to 5000 TCD crushing
capacity has given a fillip to the process of investigating the
viability of co-generation in the factory.
Power is the most essential input for industrialization and
in the Indian context, it is indeed the fulcrum on which, the
future pace of growth and development of this country rests.
Since independence we have multiplied electricity generation by
about 48 times, from 1362 MW in 1947 to over 66000 MW in 1991,
and our unrelenting efforts in this direction continue. However
the demand for power continues to grow at a rapid rate
outstripping the availability of the same. Our efforts to keep
pace with the demand put heavy burden on our limited resources,
and relatively cheaper energy sources, for achieving self
sufficiency in electricity sector assume high priority. Even with
the capacity additions planned and including the private sector
power projects likely to be put up, totaling to an installed
capacity of 99620 MW at the end of the eighth plan, the expected
shortfall is around 5000 MW.
Bagasse based co-generation for power export to the
Electricity Grid has been a subject of interest in many countries
and specifically so to the government of India. This interest is
born out of the fact, that the sugar plant co-generation holds
the promise of narrowing the ever widening gap between the power
supply and demand at low incremental cost and with short
gestation.
Looking at the power situation in Haryana state, where PAIL
is situated, it is seen that there is an appreciable shortfall in
3
the installed power generation capacity, even after taking into
account all sanctioned projects, and including the state share
from central sector projects. In Haryana state, peak load demand
is very high in comparison to installed capacity, leaving a large
deficit to be managed from other resources.
It is under this context that sugar plant co-generation,
with its vast potential for the generation of surplus grid
quality power, assumes greater importance. It is estimated that
the sugar plant co-generation, if implemented in right earnest,
can augment the national grid capacity by 3500 MW at the end of
the eighth plan. Estimated deficit will actually be higher
because of delay in the commissioning/implementation of a few of
the projects. State Electricity Boards should only be happy to
take power from the co-generating sugar factories.
The exciting prospects of tapping the vast potential in the
sugar mills, has caught the attention of the power planners in
the country for the economical way of augmenting the grid power
and that of the sugar mill managements, for the newly opened up
business opportunities in the field of private power generation.
The task force for the formulation of National Programme on Bio-
Mass based co-generation in India has estimated the potential of
surplus exportable power from the sugar industries to be around
3500 MW. The task force in its report, has addressed all the
present constraints for commercially exploiting the co-generation
potential in the sugar plants, and has recommended clear policy
interventions/fiscal incentives to over come those constraints.
The Ministry of Non-conventional Energy Sources, Government of
India, seized of this matter, has announced a lot of incentives
for the setting up of the co-generation plants in sugar mills.
4
Realizing the good potential available for co-generation in
their factory, and considering the thrust given by the Government
of India to this national endeavor, of exploiting the renewable
bio-mass sources of energy for the production of grid quality
power, the progressive management of M/S PAIL have decided to
implement co-generation along with the capacity expansion of the
mill.
As the first step towards this goal of implementing the co-
generation project, the mill management has appointed M/S Connect
consultants (India) Pvt. Ltd., New Delhi, as the consultants for
the preparation of the Detailed Project Report for this bagasse
based co-generation project.
The subsequent sections of the report provides the details
of the envisaged scheme, description and the layout of the plant,
manpower requirements, cost estimate and the financial analysis.
This report is prepared on the guidelines provided by the
Ministry of Non-Conventional Energy Sources, of the Government of
India.
PRESENT OPERATION OF THE FACTORY AND EXPANSION PLANNED
The operation of M/S PAIL will be started in the fag end of
crushing season of 1995-96. The PAIL is a subsidy of Piccadily
group. Piccadily has an excellent past track record and is making
profit continuously during the last ten years. It is worth
mentioning here that the market value of the shares of Piccadily
is Rs. 10/- each for cash at par aggregating Rs. 1320.00 Lakhs.
The management of the mill, which lays great emphasis on the
performance improvement all around, has rightly embarked on a
comprehensive programmes for sugar cane development, like
introduction of early varieties, fertilizer application, plant
protection, ratoon management, irrigation, so that adequate cane
availability is ensured with the expansion of the crushing
capacity to 3500 TCD in first phase and 5000 TCD in second phase.
With the above background, of the overall present operating
condition of the plant, the discussion in this section are
confined to the steam and power systems, that are of interest to
co-generation.
M/S PAIL like any other sugar mill is proposing to generate
its own electrical and thermal energy for production of sugar.
Mill has two numbers of 35.0 TPH boilers operating with outlet
steam parameters of 45.0 Kg/Sq.cm & 440 Degree C for meeting
complete motive and process steam requirements at existing
crushing capacity of 2500 TCD.
The captive power will be produced by existing two, 3.0 MW
B.P. Turbo-Generator sets, having inlet parameters as 43.0
kg/Sq.cm & 440 Degree C. These Turbo-Generator sets will generate
power at 1800 V, but the mill requirement is at 415 V, thus a
step down transformer will be used. The captive power requirement
of the sugar mill at the crushing capacity of 2500 TCD is about
4.0 MW which will be generated by existing turbines at the steam
consumption rate of 8.0 kg/KWhr. The captive steam requirement
will be met by the exhaust steam at 1.5 kg/Sq.cm from these
turbines. Separate PRDS is provided to meet the steam requirement
of the centrifugal and sulphur melting etc at 7.0 kg/Sq.cm.
Both the boilers in the existing system are dumping grate
type and are provided with airpreheaters and economizers. The
steam to bagasse ratio of these boilers is 2.25. The
instrumentation provided on boilers, Turbo-Generator sets and
other auxiliaries are adequate for efficient operation of the
sugar mill.
The Proposed Capacity Expansion
The sugar mill is designed in such a way that it could
expand its crushing capacity to 3500 TCD in first stage and 5000
TCD in second stage. This design also keeps the possibility of
exporting surplus cogenerated power at various stages of
expansion in mind.
There are four mills in the existing sugar mill system, each
driven by a separate electric motor. Two of these four motors are
of 250 HP and remaining are of 350 HP. The rating of existing
motors indicate the future plan of expansion to 5000 TCD. These
motors will be under utilized at the existing crushing rate.
It is planned to retain existing milling tandem and by
adding equipment like GRPF etc on the same mills the crushing
will be increased to 5000 TCD in stages. One of the major aim of
modernization is to achieve and maintain the process steam
consumption down to 44 % for boiling house needs and 3 % at 7.0
kg/Sq.cm steam for centrifugals etc. To achieve this, it is
planned, to add more evaporator bodies, continuous pans and to
effectively use vapor bleeding for juice heating and pan boiling.
The first stage of expansion will lead to a crushing
capacity of 3500 TCD. This expansion will increase the mills
process steam and power requirement. To meet the new requirements
and to properly utilize the available bagasse a new high pressure
boiler of capacity 50.0 TPH with outlet parameters as 65.0
kg/Sq.cm & 485 Degree C will be installed. The capacity of this
boiler is decided keeping the future expansion in mind. A B.P.
5.0 MW Turbo-Generator set will also installed to generate power
for captive use and generate excess power for export to the grid.
This turbine will generate 5.0 MW of power at a steam consumption
rate of 7.2 kg/KWHr. This turbine will be back pressure type
keeping the future process steam requirement in mind.
The second stage of expansion will lead to a crushing
capacity of 5000 TCD. This expansion will again increase the
mills captive process steam and power requirement. To meet the
new requirements and to properly utilize the available bagasse a
new high pressure boiler of capacity 50.0 TPH with outlet
parameters as 65.0 kg/Sq.cm & 485 Degree C will be installed. The
capacity of this boiler is decided to completely consume the
available bagasse and is sized at 50.0 TPH remembering the fact
that the identical boilers will simplify the net system operation
and maintenance. A 12.5 MW Condensing Extraction Steam Turbo-
Generator set will also be installed at this stage for generating
excess power for export to the grid. This will be a stand alone
system which will supply power only for export. The steam
consumption rate of this turbine will be 8.77 kg/KWHr at 7.0
kg/Sq.cm extraction, 6.21 kg/KWHr at 1.5 kg/Sq.cm extraction and
4.17 kg/KWHr at condensing pressure.
CO-GENERATION IN EXPANSION
Management of mill have found that it fits well to go in for
co-generation simultaneously with expansion. Typically an ideal
co-generation plant in a sugar factory is one which takes care of
both steam and power requirement of factory. By proceeding with
both expansion and co-generation together, there are definite
advantages like, planning for common infrastructure, planned
addition of boilers and turbo-generator set of suitable
capacities.
At the crushing capacity of 3500 TCD the mill will
cogenerate surplus power of about 4.94 MW for export. The captive
requirement at this stage will be a net of 6.06 MW which
includes 5.44 MW of sugar mill’s requirement and 0.625 MW of co-
generation plant’s requirement. At this stage mill will have two
3.0 MW Turbo-Generator sets and one 5.0 MW B.P. Turbo-Generator
set generating a total of 11.0 MW. The power generated by 5.0 MW
Turbo-Generator set will be at 11 KV. The power from two 3.0 MW
Turbo-Generator sets at 1800 V and a part of the power, about
0.062 MW, from 5.0 MW Turbo-Generator set at 11 KV will be
stepped down to 415 V for meeting the captive power requirements.
At the crushing capacity of 5000 TCD the mill will
cogenerate surplus power of about 11.20 MW for export. The
captive requirement at this stage will be a net of 9.105 MW which
includes 8.215 MW of sugar mill’s requirement and 0.89 MW of co-
generation plant’s requirement. At this stage mill will have two
3.0 MW Turbo-Generator sets, one 5.0 MW B.P. Turbo-Generator set
and one 12.50 MW Condensing Extraction Steam Turbo-Generator set
generating a total of 20.3 MW. The power generated by 5.0 MW and
12.5 MW Turbo-Generator sets will be at 11 KV. The power from two
3.0 MW Turbo-Generator sets at 1800 V and a part of the power,
about 3.105 MW, from 5.0 MW Turbo-Generator set at 11 KV will be
stepped down to 415 V for meeting the captive power requirements.
The foregoing clearly proves decision of the mill
management to go in for co-generation along with expansion will
result in proper planning for equipment capacities and reduction
in over all capital investment.
THE COGENERATION SCHEME
Co-generation is generation of electrical and thermal energy
(through process steam) simultaneously by an industry. The sugar
manufacturing process requires steam at low temperature and
pressure and electricity for various operation in the mill.
Currently low pressure bagasse fired boilers are used in sugar
mills to generate steam at low temperature and pressure. This
steam is first run through various Back Pressure(B.P.) turbines
to generate power, run mill and operate fiberizor. Exhaust steam
at about 1.5 Kg/Sq.cm is available from various turbines for
process use. High pressure process steam at about 7.0 Kg/Sq.cm
can be directly extracted at the inlet or at suitable points from
power turbines. Thus generation of power and process steam makes
sugar mill self sufficient during crushing season and for
achieving this part of generated bagasse is burned.
As is known from Carnot cycle, high temperature cycles are
essential for efficient utilization of input heat. Due to lack of
interest and proper guideline for buying surplus power, sugar
mills were refraining from optimizing their power generation
system. Recently a number of State Electricity Boards have
announced their policy & guideline for buying surplus co-
generated power through different schemes. This has created a
conducive environment for co-generating surplus power. To improve
the cycle efficiency steam generation has to be at high
temperature and corresponding pressure, but available material
technology limits the highest temperature attainable in a cycle.
In the case of sugar mill co-generation, availability of bagasse
for burning, limits the capacity of the high pressure boilers.
The design temperature of high pressure steam is also
dictated by the available turbine designs. Temperature up to 400
Degree C require the normal carbon steel in the turbine design
but alloy steel has to be used for inlet temperatures higher than
400 Degree C. The material requirement becomes still critical for
inlet temperatures above 500 Degree C. Keeping these facts and
thermodynamics of cycle in mind the most economical boiler
pressure & temperature works out to be 65.0 Kg/sq.cm, 485 Degree
C. This pressure and temperature becomes 63.0 Kg/sq.cm, 480
Degree C by reaching the turbine inlet.
High pressure and temperature steam can be optimally
utilized by using in a condensing turbine. Steam for process use
can be extracted from the suitable points at intermediate stage
from condensing turbine in the desired quantity.
FEASIBILITY STUDY
The feasibility study analyzed various cases, like
* The condensing extraction steam turbine(CEST)
* The straight condensing steam turbine(SCST)
* The back pressure steam turbine(BPST)
and schemes with,
* Completely new high pressure boilers
* A combination of existing boilers and turbo generating sets
and new high pressure boilers and corresponding Turbo-
Generator sets
Following facts were carefully scrutinized in relation to
above options-
* Existing mill and equipment are relatively new
* Constraint on capital cost
* Thermodynamics of total cycle
Finally the scheme with a combination of existing system and
new high pressure boilers, a new B.P. Turbo-Generator set and a
new Condensing Extraction Steam Turbo-Generator set was found
most suitable.
CO-GENERATION SCHEME
The proposed co-generation system is split into following
three systems -
The schematic of PAIL’s co-generation configuration is given
in Figure 3.1.
The first system comprises of the two existing 35.0 TPH,
45.0 kg/Sq.cm, 440 Degree C boilers and both of 3.0 MW B.P.
Turbo-Generator sets. This system basically caters to the sugar
plants steam & electricity requirement at the crushing capacity
of 2500 TCD.
The second system comes into picture at the crushing
capacity of 3500 TCD and consists of a new high pressure boiler
of 50.0 TPH capacity at 65.0 kg/Sq.cm, 485 Degree C and one 5.0
MW B.P. Turbo-Generator set. The exhaust from the two 3.0 MW
Turbo-Generating sets and one 5.0 MW Turbo-Generator set meets
the mill's process steam requirement at 3500 TCD. A part of power
generated by the 5.0 MW B.P. Turbo-Generator set is available in
surplus for export to the grid.
The third system that is stand alone, comprises of a 50.0
TPH, 65.0 kg/Sq.cm, 485 Degree C boiler and one 12.5 MW
Condensing Extraction Steam Turbo-Generator set. This system uses
the remaining bagasse for steam production at a crushing capacity
of 5000 TCD.
OPERATING PARAMETERS OF PLANT AND CO-GENERATION SYSTEM
Plant will be operating during the crushing season using
bagasse as fuel.
Crushing capacity of the plant will be 5000 TCD eventually,
but most of the plant design calculations are done on the basis
of 3500 TCD capacity which plant will achieve within few seasons.
Already two boilers of 35.0 TPH, 45.0 Kg/sq.cm, 440 Degree C and
two back pressure Turbo-Generator sets of 3.0 MW capacity each
are bought to meet the captive requirements at 2500 TCD crushing
capacity.
A 5.0 MW B.P. Turbo-Generator set will be added to the plant
keeping the process steam requirement at 5000 TCD capacity in
mind. This Turbo-Generator set will co-generate surplus power at
crushing capacity of 3500 TCD.
The span of crushing season varies from 160 to 180 days.
Crushing season starts in the month of October and ends in the
month of April.
About 30% bagasse is generated on cane. This bagasse has 50%
moisture in it.
The average quantity of fibre on cane crushed is about 14.5%
which varies from 13.5% to 15% during season.
All the drives in the mill are Electric Motors, except
fiberizor. Fiberizor is driven by a 3.0 MW B.P. Turbo-Generator
set.
Total steam consumption of the plant is about 47% on cane,
out of which 44 % is at 1.0 Kg/Sq.cm, 120 Degree C and 3 % at
about 7.0 Kg/Sq.cm. Losses in steam system are included with high
pressure steam.
Both 3.0 MW Turbo-Generator sets are retained in the design
of co-generation system for exporting surplus power.
The existing two boilers of 35.0 TPH, 45.0 kg/Sq.cm, 440
Degree C are also retained in the new design of co-generation
system. These boilers have steam to bagasse ratio of about 2.25
and will continue to give this performance for their entire life,
with the inlet feed water temperature of 105 Degree C at the
entry of economizer.
The proposed new boilers of 50.0 TPH shall be with the steam
parameters of 65.0 kg/Sq.cm, 485 Degree C at the boiler outlet.
With these steam parameters, new boilers will have a steam to
bagasse ratio of 2.20.
The pressure and temperature requirements of process steam
at the consumption points as 1.0 Kg/Sq.cm, 120 Degree C for the
sugar plant, the back pressure or the extraction pressure is
taken as 1.5 Kg/Sq.cm to meet the pressure losses in the pipe.
The superheated steam extracted at 1.5 kg/Sq.cm and temperature
of about 170 Degree C is first brought down to 120 Degree C.
The 3.0 MW Turbo-Generator sets generate power at 1800 V
which is stepped down to 415 V for captive power requirement. The
5.0 MW Turbo-Generator set will generate power at 11 KV, part of
this power will be stepped down to 415 V to meet captive power
requirement at 5000 TCD crushing capacity and remaining power
will be as such exported to the grid. The power generation by the
Condensing Extraction Steam Turbo-Generator set will be at 11 KV.
All the power from this Turbo-Generator set will be stepped up to
33 kV for export and will be synchronized with the grid.
Steam Balance
With the implementation of the co-generation and the
expansion programs the plant’s Steam and Condensate balance at
5000 TCD will be as shown in Figure 3.2. The process steam
requirement with 47% on cane comes out to 74.8 TPH for the cane
crushing rate of 159.1 TPH (3500 TCD in 22 Hours). Out of this
70.0 TPH is required at 1.5 kg/Sq.cm and the balance of 4.8 TPH
is required at 7.0 kg/Sq.cm.
The existing 35.0 TPH boilers, generate 54.0 TPH of steam to
be fed to the three existing 3.0 MW B.P. Turbo-Generator sets.
The 1.5 kg/Sq.cm exhaust steam from these turbines is taken to
the plant's 1.5 kg/Sq.cm process steam header. The two 3.0 MW
Turbo-Generator sets assigned for power will be run at their full
capacity, consuming 48.0 TPH of 43.0 kg/Sq.cm steam. The
fiberizor turbine will consume 6.0 TPH of 43.0 kg/Sq.cm steam to
generate 0.75 MW of power.
The balance of the process and the deaeration steam
requirement of 20.4 TPH (70.0 + 4.4 - 54.0) will be met by the
50.0 TPH boiler. Because of the availability of excess bagasse,
the new boiler will produce 36.0 TPH steam to meet complete
requirement of 5.0 MW B.P. Turbo-Generator set. The process steam
requirement of 4.8 TPH at 7.0 kg/Sq.cm will be taken through
PRDS. The remaining 10.8 TPH (36.0 - 20.4 - 4.8) will go back to
boiler as feed, at a crushing capacity of 3500 TCD. The 50.0 TPH
boiler is selected at this stage keeping the future expansion in
mind.
Similarly at the cane crushing rate of 227.27 TPH (5000 TCD
in 22 Hours) the process steam requirement with 47% on cane comes
out to 106.8 TPH. Out of this 100.0 TPH is the required at 1.5
kg/Sq.cm and the balance of 6.8 TPH is required at 7.0 kg/Sq.cm.
The existing 35.0 TPH boilers, generate 57.0 TPH of steam to
be fed to the three existing 3.0 MW B.P. Turbo-Generator sets.
The 1.5 kg/Sq.cm exhaust steam from these turbines is taken to
the plant's 1.5 kg/Sq.cm process steam header. The two 3.0 MW
Turbo-Generator sets assigned for power will be run at their full
capacity, consuming 48.0 TPH of 43.0 kg/Sq.cm steam. The
fiberizor turbine will consume 9.0 TPH of 43.0 kg/Sq.cm steam to
generate 1.12 MW of power. The 5.0 MW B.P. Turbo - Generator set
will be running at full capacity consuming 36.0 TPH of 63.0
kg/Sq.cm of steam. This will fetch 36.0 TPH of exhaust steam at
1.5 kg/Sq.cm.
The balance of the process steam requirement of 13.9 TPH
(100.0 + 6.9 - 57.0 - 36.0) will be met by the new Condensing
Extraction Steam Turbo-Generator set. The availability of excess
bagasse leads to installation of another 50 TPH boiler and proper
utilization of earlier erected 50.0 TPH boiler. The high pressure
steam from these two boilers is fed to 12.5 MW Condensing
Extraction Steam Turbo-Generator set, the quantity of extraction
being 20.7 TPH. Out of 106.8 TPH total process steam requirement
6.8 TPH is at 7.0 kg/Sq.cm, which will be suitably extracted from
Condensing Extraction Steam Turbo-Generator set. With the above
extractions and exhaust flows this Turbo-Generator set will
generate about 9.3 MW of power.
Condensate and Water Balance
A total steam quantity of 79.2 TPH is required to meet the
process steam requirement of 74.8 TPH and deaerator steam
requirement of 4.4 TPH at the crushing capacity of 3500 TCD. The
process steam supplied to the juice heaters is returned back as
condensate. The process steam supplied to the evaporator bodies
is also taken as condensate return depending upon its
cleanliness. About 10.8 TPH of steam at 1.5 kg/Sq.cm will be
available as a return to boiler from the exhaust of 5.0 MW Turbo-
Generator.
A total steam quantity of 113.7 TPH is required to meet the
process steam requirement of 106.8 TPH and deaerator steam
requirement of 6.9 TPH at a crushing capacity of 5000 TCD. Other
than steam from juice heaters and vapor bodies, about 26.2 TPH of
condensate will be available from 12.5 MW Condensing Extraction
Steam Turbo-Generator set's surface condenser. This condensate is
sent to condensate storage tank.
The difference in the boiler feed water requirement and
condensate return will be filled by the feed from vapor
condensate tanks or the DM water storage tank. The mixed feed is
supplied as boiler feed water in the quantity of 91.0 TPH at the
crushing capacity of 3500 TCD and 141.3 TPH at the crushing
capacity of 5000 TCD.
Bagasse Balance
With the crushing capacity of 159.1 TPH (3500 TCD in 22
Hours), and with the bagasse generation at the rate of 30% on
cane, the bagasse generated will be 47.73 TPH (in 22 Hours).
About 1.72 TPH of fine bagasse dust known as bagacillo, is
separated through a sieve arrangement, for mixing with the
clarifier mud for filteration in the vacuum filters. The balance
of 48.01 TPH of bagasse is taken to the bagasse storage yard,
from where the bagasse will be fed to the boilers through a
reclaimer. About 1.46 TPH (this quantity and bagacillo together
will be 2% of the bagasse produced) is set aside for losses and
to meet the additional fuel requirement for the start up of the
boilers. A net usable amount of about 40.82 TPH will be
continuously fed to the operating three boilers through bagasse
conveyors. About 3.73 TPH bagasse will be left as surplus.
With the crushing capacity of 227.27 TPH (5000 TCD in 22
Hours), and with the bagasse generation at the rate of 30% on
cane, the bagasse generated will be 68.18 TPH (in 22 Hours).
About 2.44 TPH of fine bagasse dust known as bagacillo, is
separated through a sieve arrangement, for mixing with the
clarifier mud for filteration in the vacuum filters. The balance
of 65.74 TPH of bagasse is taken to the bagasse storage yard,
from where the bagasse will be fed to the boilers through a
reclaimer. About 2.1 TPH (this quantity and bagacillo together
will be 2% of the bagasse produced) is set aside for losses and
to meet the additional fuel requirement for the start up of the
boilers. A net usable amount of about 63.64 TPH will be
continuously fed to the operating four boilers through bagasse
conveyors. At the sugar plant crushing capacity of 5000 TCD there
will be no excess bagasse left as surplus during season as, the
co-generation system is configured for optimum power generation
at this stage. Figure 3.3 gives the bagasse balance for the sugar
mill.
Power Balance
The gross power generation in the mill, with the co-
generation system working at the crushing capacity of 3500 TCD
will be 11.0 MW. The power requirement of the sugar manufacturing
process side of the 3500 TCD crushing capacity plant for running
various auxiliaries will be 5.44 MW. The total power requirement
of the first new high pressure boiler for co-generation, the B.P.
Turbo-Generator set and all other auxiliaries of the co-
generation system is estimated to be 0.62 MW. The net exportable
power will be 4.94 MW at the bus.
The estimated power generation in the mill at the crushing
capacity of 5000 TCD will be about 20.3 MW. The estimated power
requirement for the mill at this stage will be 8.21 MW. The
total power requirement of the second new high pressure boiler
for co-generation, the new Condensing Extraction Steam Turbo-
Generator set and all other auxiliaries of the co-generation
system is estimated to be 0.89 MW. The net exportable power will
be about 11.2 MW at the bus. The Figure 3.4 gives the power
balance for the sugar mill with the installation of the co-
generation plant and after the completion of the expansion.
DESCRIPTION OF MECHANICAL SYSTEMS & EQUIPMENT
The proposed co-generation plant for M/S Piccadily Agro
Industries Limited will have, a gross power generation of 11.0 MW
at a crushing capacity of 3500 TCD and 20.30 MW at a crushing
capacity of 5000 TCD. The co-generation scheme will have a
combination of existing boilers & Turbo-Generators and one new
high pressure boiler of 50.0 TPH capacity & one B.P. Turbo-
Generator set of 5.0 MW capacity at a crushing capacity of 3500
TCD and another new boiler of 50.0 TPH capacity & one Condensing
Extraction Steam Turbo-Generator of 12.5 MW at a crushing
capacity of 5000 TCD. Here we will discuss only the new equipment
installed or will be installed for co-generation at various
stages.
First stage of co-generation plant will consist of one
bagasse fired boiler of capacity 50.0 TPH coupled to one B.P.
Turbo-Generator set of 5.0 MW capacity. The steam parameters at
the outlet of the boiler superheater will be 65.0 kg/Sq.cm and
485 Degree C. The turbine throttle valve inlet pressure and
temperature, will be 63.0 kg/Sq.cm & 480 Degree C and difference
in the boiler outlet parameters and turbine inlet parameters
takes care of the losses in the piping.
Second stage of co-generation plant will have one more
bagasse fired boiler of 50.0 TPH coupled to one Condensing
Extraction Steam Turbo-Generator of 12.5 MW capacity. The steam
parameters at the outlet of the boiler will be same as stage one
but the turbine in second stage will have steam extraction of
about 6.82 TPH at 7.0 kg/Sq.cm and about 16.0 TPH at 1.5
kg/Sq.cm. The remaining steam, will go to the surface condenser
as exhaust.
In addition to the main power generating equipment, the
plant will be complete with the necessary auxiliary facilities
such as fuel storage and handling system, condensate and feed
water system, cooling water system, electrical system including
power evacuation facilities, ash handling system, compressed air
system and fire protection system.
Steam Generator
The steam generating system for the co-generation plant will
consist of two bagasse fired boiler with all the auxiliaries.
Each boiler shall be of semi-outdoor type, and shall be of bi-
drum, natural circulation, balanced draft, radiant furnace design
with two stage superheaters. The boiler shall be designed with
water cooled membranes/fin welded and the refractory work in the
boiler shall be kept to the barest minimum possible. The rating
of each steam generator shall be 50.0 TPH at the superheater
outlet with the steam pressure and temperature of 65.0 kg/Sq.cm
and 485 Degree C, when supplied with the feed water at a
temperature of 105 Degree C.
The boiler shall be designed for 100% bagasse firing and
there shall be no support fuel. The firing system of the boiler
shall comprise of continuous ash discharge traveling or dumping
grate, variable speed rotary feeder and pneumatic spreaders. The
bagasse feeding system shall include the bagasse storage silo in
front of the boiler with the storage capacity of at least for ten
minutes at MCR requirements. Appropriately designed feeders, with
variable speed drives, suitable for boiler combustion control
operation shall be provided.
The boiler convection shall be of multiple pass, baffled
type construction formed by an array of tubes connecting the
steam and water drum. The entire boiler block shall be GI/Steel
cased and provided with adequate buckstays designed to take over
and under pressure in the furnace.
The superheater provided shall be pendant type vertically
suspended type located in the first convection pass of the
boiler. It shall be designed to achieve rated steam temperature
at maximum continuous rating. The desuperheating system
(attemperator) shall be located in between the two stages of the
superheaters, and shall be either spray type, with the condensate
of steam from the drum used as spray water, or surface water. The
tolerance of the superheater outlet shall be +5 to -5 and
controlled over the operating range of boiler.
The boiler shall be provided with one bare tube in line
construction type economizer to utilize the flue gas heat to
raise the feed water temperature and one tubular flue gas air
preheater to recover heat from the flue gases to heat combustion
air.
The boiler shall be designed to operate under balanced draft
conditions and suitable ID and FD fans driven by electric motors
are to be provided. The fan capacities, capacity margins and the
margin in the head shall be adequate and in line with the
standard practices followed. The fans will be dynamically
balanced and operate without undue vibrations. High pressure
secondary air nozzles are to be provided in number of rows in the
front and rear walls to create adequate air turbulence,
temperature and time for the complete combustion of volatile
matter released from the bagasse.
The boiler design shall have adequate number of soot blowers
for effective cleaning of the superheaters and convection bank
tubes. The Drawing No. 4-785212-1 gives the scheme for steam
generator air and flue gas system.
The boiler shall have a dust collector (Mechanical Multi
cyclone type or Electro-Static Precipitator) to reduce the dust
leaving the boiler to a suitable level. Induced draft fan is
designed and sized to take care of additional draft loss in the
dust collector.
The boiler shall be provided with microprocessor based
instrumentation and control system.
Steam Turbine & Auxiliary System
The Piccadily Agro Industries Limited's co-generation
scheme/project envisages the addition of one 5.0 MW Turbo-
Generator set at the crushing capacity of 3500 TCD and another
one 12.5 MW Condensing Extraction Steam Turbo-Generator set at
the crushing capacity of 5000 TCD. The 5.0 MW turbine will be a
single casing, impulse reaction, back pressure type with back
pressure of 1.5 kg/Sq.cm. The 12.5 MW turbine will be a single
casing, impulse reaction, condensing extraction type with
controlled extraction of 6.8 TPH at 7.0 kg/Sq.cm and uncontrolled
extraction of about 13.9 TPH at 1.5 kg/Sq.cm, rest of the steam
goes to condenser at 0.1 kg/Sq.cm.
The steam inlet into the turbines is through emergency stop
and control valves actuated by hydraulic cylinders and controlled
by the governing system. The extraction points on the turbine are
located such that the pressure of steam after the external
control valve shall be 7.0 kg/Sq.cm and for the pressure after
the internally controlled valve shall be 1.5 kg/Sq.cm. Quick
closing non-return valve shall be provided on the extraction
lines. The exhaust from the CEST-G set goes to a surface
condenser operating at 0.1 kg/Sq.cm. The turbine shaft sealing
system shall consist of labyrinth packing and shall be sealed
with steam. The sealing steam escaping the outer packing boxes
shall be condensed in a gland steam condenser.
For the Turbo-Generator sets the control and lube oil system
shall be separate. The lube oil system for each turbine shall
meet the requirements of the gearbox and turbine. The forced feed
lubrication system shall consist of main oil pump, auxiliary pump
with automatic switching at start-up and when main oil pump is
not supplying oil at desired pressure, two water cooled oil
coolers of sufficient capacity and one set of oil filters. The
auxiliary oil pump shall be D.C. motor driven. A common oil
storage tank of adequate capacity with suction filters, vapor
exhaust fan, etc. shall be provided. Necessary oil pressure
reducing valves for catering to the lube oil requirements,
orifices and sight flow glasses shall form part of the oil
system. One centrifugal oil purifier for each of the Turbo-
Generator set shall be provided. The Drawing No. 4-785212-2 gives
the oil system scheme, applicable for the proposed Turbo-
Generator.
Each of the Turbo-Generator set shall be provided with a
user friendly modern governing system that shall be user
configurable in the field. The safety system of the Turbo-
Generator set shall be designed to protect the Turbo-Generator
set against inadmissible operating conditions such as, rotor over
speed, high shaft axial displacement, low lube oil pressure, low
control oil pressure, high condenser pressure and high
vibrations.
The reduction gear boxes between the turbine and the
generator shall be designed with a minimum service factor of 1.3.
It shall be capable of transmitting the maximum rating of the
turbine and shall withstand 20% over speed over a period of a
minimum of five minutes. The gear box and coupling shall meet the
requirement of AGMA standards.
Condenser and Auxiliary Cooling Water System
The condenser system of the 12.0 MW Turbo-Generator set
consist of a surface condenser with divided water boxes, with
each section amenable for cleaning independently with the turbine
load reduced. One starting ejector capable of pulling 60 % vacuum
in twenty minutes and one main operating ejector of two stag twin
element type with inter and after condenser shall be provided.
The hotwell level control system operating through the two
control valves in the discharge and in the recirculating
condensate lines shall ensure that adequate net positive suction
head is available for the condensate extraction pump. The two
condensate extraction pumps, one for working and another for
standby, shall handle the condensate from the hotwell through the
ejector condensers, gland steam condenser and to the condensate
storage tank. The Drawing No. 4-785212-3 gives the scheme of
steam and condensate system for 12.5 MW condensing Turbo-
Generator.
The general scheme of Cooling water system is given in
Drawing No. 4-785212-4. This cooling water system caters to the
cooling water requirements of the condenser of the Turbo-
Generator set and the auxiliaries of the steam generator. A three
cell , induced draft cooling tower will be in operation to meet
the cooling water requirements. The hot water returning from the
condenser and Turbo-Generator set and boiler auxiliaries are
cooled in cooling tower designed for a cooling range of 10 Degree
C and an approach of 5 Degree C while operating under the
atmospheric wet bulb temperature of about 27 Degree C.
Raw water from the bore well will be drawn, as is being
presently done to meet the requirements of sugar plant and will
be stored in the raw water tank for the purpose of meeting the
makeup required for the cooling tower and that for the DM water
plant. There are two cooling tower makeup water pumps one working
and one remaining as standby, supply the raw water to the cooling
water forebay. From the forbay water flows into the suction of
the cooling water pumps. There will be four cooling water pumps
each with adequate head required to meet the pressure drop in the
entire circuit. Out of the four pumps, three will be in the
operation to meet the complete requirement of the condenser as
well as the auxiliaries of the Turbo-Generator set and steam
generator and one will remain as standby. Necessary stop locks
and springs will be provided in the cooling tower forbay.
The outlet from the cooling water pumps is conveyed to the
surface condenser and to the auxiliaries of the Turbo-Generator
set and the boiler through mild steel buried pipes. Similarly the
hot water from the condenser as well as that from the auxiliaries
will be conveyed to another mild steel pipe and to the cooling
tower and appropriately distributed to the three cells at the
top. The buried steel piping carrying the cooling water will be
internally painted as well as externally protected against
corrosion. It is to be noted that the final optimum size of the
pipes would be arrived at only after the optimization study of
the cooling water system being done at the detailed engineering
stage of the project.
Cast iron gate valves as well as butterfly valves shall be
appropriately placed at the pump inlet and outlet, condenser
inlet and outlet at the cooling tower hot water inlet, etc..
Suitably sized rubber expansion joints will be provided in the
piping network to facilitate dismentaling , installation of
valves and to take care of any misalignment/expansion of the
piping. Automatic air release cum vacuum breaker valves, manual
vents/drain valves will be provided in the condenser cooling
water system.
To prevent/minimize the growth of algae in the cooling water
system chlorine dosing is proposed. Provision will be made for
shock dosing at 3.0 PPM or continuous dosing at 1.0 PPM. Adequate
number of one tonne capacity chlorine cylinders to meet fifteen
days requirements.
It is envisaged that even for the auxiliaries of the Turbo-
Generator set and the boiler the same cooling water will be used.
Since the make up water available is of good quality and with
proper blow down from the cooling tower the hardness in the
cooling water could be easily maintained less than the
precipitation hardness. Hence no close loop system of cooling
using DM water is suggested for the auxiliaries.
Service And potable Water System
The service water system supplies water to toilets, general
washing, gardening, dust suppression system, make up water for
air conditioning plant etc..To meet the service water
requirements of the co-generation plant, the sugar plant`s
facilities could be extended. Similarly, the potable water
requirements of the new plant shall have to be met by extending
the sugar plant potable water system.
Compressed Air System
The requirement of the compressed air for various
instrumentation and control systems of the proposed co-generation
plant will be supplied by compressors with one set operating and
another set remaining as standby. The air compressor shall be of
reciprocating, non-lubricating type and shall be provided with
the accessories like inter-coolers, after-coolers, moisture
separators, driers, air receiver and control panel. The common
air drier unit shall comprise of 2 X 100 % driers, with one of
the driers in operation at any point of time and the other one on
regenaration mode.
Air Conditioning And Ventilation System
The plant control rooms house the controls for the boilers
and Turbo-Generator sets and shall be air conditioned with window
mounted air conditioners. The Turbo-Generator sets and other
buildings shall be provided with suitable exhaust fans or a
combination of supply and exhaust fans.
Fuel Handling System
The co-generation plant proposed for PAIL, depends on the
bagasse generated in the sugar mill for its fuel requirements.
The boilers are designed to burn 100 % bagasse.
The proposed high pressure and temperature boilers are with
membrane wall and minimum refractory are very sensitive to fuel
feed and to ensure steady operation a continuous fuel feed system
should be adopted. The conventional system of feeding the boiler
with the bagasse coming directly from the mill has the drawback
of a complete stoppage of the fuel feed to the boiler, if and
when the mill stops and the occasions are not infrequent. Even
though provision for the back feeding the bagasse on to the
return bagasse conveyors are available, because of human
intervention, there is always time delay and boiler starves for
fuel. To overcome the problem of time delay, attempts have been
made, with good amount of success, to provide a storage silo in
front of the boiler, at least to cater to about ten minutes
requirement, of the fuel at MCR.
The scheme of bagasse handling system for PAIL co-generation
plant is given in Drawing No. 4-785212-6. The scheme is drag type
conveyor system, with a provision of storage capacity to meet the
requirement of boilers for minimum of ten minutes when running at
MCR. The bagasse will be taken to the storage yard through
conveyors and distributed along the length of the yard through
gates and chutes located along the length of the conveyor. A
bagasse reclaimer in the form of a continuous endless conveyor
moving along the length of the storage yard distributes and feeds
the bagasse continuously on to an underground conveyor. This
conveyor rises up and feeds the bagasse on to another conveyor
running in front of the boilers, above the bagasse storage silos
and bagasse is fed to the storage silos from the conveyor. Any
excess bagasse shall be returned to storage yard through the
return bagasse conveyor. The capacity of the bagasse conveyor
shall be 50.0 TPH, adequate to meet the requirement of the
boiler. The operation of the entire conveyor system shall be
controlled from the control room.
Ash Handling System
The ash handling system envisaged now is only for the new
65.0 kg/Sq.cm high pressure boiler. The ash from the existing
boiler will be continued to be handled in the same way as is
being done presently. The system proposed for the new boiler
shall be mainly dry handling, except for the furnace bottom ash.
The drawing No. 4-785212-7 gives the scheme of the ash handling
system for the co-generation project.
The furnace bottom ash from the hoppers shall be handled by
the water impounded submerged scrapper conveyors, and fed on to
the main belt conveyor. Since this ash will be very hot it is
essential that it is cooled before it is fed on to the belt
conveyors. The other ash collection points in the boiler are
airpreheater hopper and dust collector hoppers. The ash collected
in these two places will be dry and powdery. The ash discharged
from these points through rotary pocket feeders will be conveyed
to the main belt conveyor through screw conveyors. At the point
of discharge of the ash from the screw conveyor on to the belt
conveyor, water sprinklers are provided to suppress the dust.
The ash silo storage will be adequate for ash generated
during bagasse firing. The ash from the silo will be disposed off
to the ash disposal area through trucks.
Condensate and DM Water System
For the co-generation project at PAIL there will be two
sources of condensate water. The Drawing No. 4-785212-5 gives the
scheme of the Condensate and DM water system proposed for the co-
generation plant. One is from the surface condenser of Condensing
Extraction Steam Turbo-Generator set and the other one is from
the process side of the sugar plant. The condensate from the
sugar plant itself is categorized into two. One is the condensate
of the exhaust steam used in the juice heaters and evaporators,
which is uncontaminated and can be used as such as boiler feed
water.
The other category from the sugar plant is the condensate of
the vapors from the evaporators and the pans. These vapor
condensate are likely to have, at time, traces of sugar and hence
the usage of this condensate as boiler feed water should be done
only after proper monitoring for the quality of condensate.
The condensate from the surface condenser is pumped by the
condensate extraction pumps to the condensate storage tank. The
steam condensate from the process is also led into this
condensate storage tank. The make-up either from the DM water
storage tank or from the vapor condensate tanks, depending upon
the quality of vapor condensate, will also be added to the
condensate storage tank. Boiler feed water from this condensate
storage tank will be pumped to the deaerator through transfer
pumps. The deaerator will be equipped with a deaerator feed water
storage tank. The level inside the deaerated feed water storage
tank shall be maintained at a constant set of valve by
controlling the quantum of feed water pumped by the transfer
pumps. The deaerated feed water from the feed water storage tank
will be supplied to the steam generated by means of boiler feed
water pumps. There will be a number of electrically driven feed
water pumps to cater to the new 65.0 kg/Sq.cm boilers.
To cater to the make-up water requirements of the steam
generator turbine cycle, a demineralized water plant is being
proposed. The DM plant will consist of cation, degasser, anion
and mixed bed ion exchange units along with associated
regeneration system. The DM plant shall have a regeneration time
of 8.0 hours in a day. The source of water for the DM plant will
be from the raw water tanks through raw water pumps. Raw water
from the outlet of these pumps shall be taken directly to the DM
plant. A demineralized water storage tank will be installed in
the DM water area to store the make-up water requirement for the
co-generation plant. Adequate storage of acid and alkali used for
the regeneration of DM plant shall be provided in the DM plant
area. A neutralizing pit for the treatment of the effluents from
the DM plant is envisaged and other neutralization the effluent
will be disposed off into the existing sugar plant’s effluent
disposal system.
Instrumentation And Control System
The plant will be complete with the basic instrumentation
and control system necessary for its safe and efficient
operation.
Comprehensive instrumentation and control equipment will be
provided for each component system of the plant. The control of
each unit will be located in the central control room.
Instrumentation will broadly cover the following functions :
* Locals indications by gauges.
* Remote indications through transmitters with facility for
recording of critical parameters.
* Interlock for safety of personnel/equipment.
* Closed loop control system using single loop controllers.
* Status indications.
* Alarm annunciation.
Controls and interlocking will be of electronic type using
microprocessor based hardware. Actuation will be done generally
with pneumatic actuators. Regulation of the turbine will be
through Electro-Hydraulic system.
The microprocessor based instrumentation and control system
is proposed keeping in view the safety, reliability and
availability for comprehensive presentation of plant operation
status, trends and essential operator interaction facility.
Microprocessor based systems have the following inherent
advantages :
* Increased reliability due to use of Large Scale Integrated
(LSI) components.
* Increased flexibility for modification at any stage due to
software configuration capability.
* Better availability due to provision of circuit redundancy
and manual back-up.
* Expendability for future as both hardware and software are
modular in structure.
* High maintainability due to improved self-diagnostic and
display features.
* Ability to include Data Acquisition System and Improved man-
machine interaction with colour graphic CRT control
stations, at a later date.
Transmitters required for the measurement and control will
be of electronic type using solid state hardware. Field signal
transmission will be 4 - 20 mA, two wire system in view of the
following advantages :
* Suitability for long distance transmission.
* Compatibility with computer interface and
* Ease of conversion into voltage signals using simple
resistors.
Closed loop control system will be provided for steam
generators, Turbo-Generator sets and their auxiliaries with
processor and sensor level redundancy.
The control system will be designed to facilitate manual
operation of the plant from Control Panel. Necessary hardwired
indicators and recorders will be provided on the Control Panel
located in the central control room/rooms.
Both closed and open loop controls for a single equipment
will be integrated in a single microprocessor based system.
Alternatively, closed loop controls will be achieved using
microprocessor based system and open loop controls through
Programmable Logic Controllers (PLC).
All control valves and control damper drives will be of
pneumatic type because of their fast response and ease of
maintenance.
Pneumatic controls will be provided where only local
controls are adequate. Also, turbine local panel, boiler feed
pump panel and circulating water pump panel will be provided near
the respective equipment.
Apart from the basic instrumentation, the turbine will be
provided with the following control system :
* Turbine speed control system.
* Condenser hot well level control system.
* Bently-Nevada based vibration monitoring system.
The following essential control shall be provided for the
steam generators :
* Three element based drum level control.
* Furnace draft control.
* Combustion control.
* Superheater temperature control.
* Deaerator pressure and level controls.
Fire Protection System
The fire protection system for the proposed co-generation
plant will be consisting of :
a. Hydrant system for all the areas of plant.
b. Manual high velocity water spray system for transformers and
turbine lube oil tanks.
c. Deluge system for cable galleries.
d. Portable fire extinguishers in other areas with in the
plant.
The installation and the layout of the system will confirm
to Tariff Advisory Committee (TAC) regulations.
The hydrant, water spray and the deluge system shall be
provided with a motor driven pump and a diesel engine driven
stand by pump. Two Jockey pumps will be provided to keep the
water system under pressure. The water for the fire fighting
system shall be taken from the main raw water tank designed with
the capacity required by the TAC regulations.
High, Medium and Low Pressure Steam Systems
The outlet steam from the high pressure boiler at 65.0
kg/Sq.cm and 485 Degree C will be conveyed through alloy steel
main steam piping to the turbine. Desired number of stop valves,
non return valves and isolating valves shall be suitably placed
in the piping. The piping system shall be complete with necessary
hangers and supports. The steam flow from the boiler shall be
measured by putting steam flowmeter at the individual boiler
outlet.
The medium steam system operates at 7.0 kg/Sq.cm. It starts
from the pressure reducing system(PRDS) at the crushing capacity
of 3500 TCD. The extracted steam from the high/medium pressure
boiler is sent through pressure reducing system to bring the
pressure down to 7.0 kg/Sq.cm, required for sulphur melting etc..
in the sugar manufacturing process. At the crushing capacity of
5000 TCD the medium pressure steam system starts from the
externally controlled extraction from the 12.5 MW turbine. All
the medium pressure piping shall be of carbon steel and shall be
designed with valves, specialities and suitable supports and
hangers.
The low pressure steam system at 1.5 kg/Sq.cm consists of
the exhaust from the existing turbines, exhaust from 5.0 MW
turbine, internally controlled extraction from the 12.5 MW
turbine and a low pressure steam header in the plant area. Steam
shall be tapped of from the header to meet the various
requirements. The major quantum of the steam is taken to the
sugar plant process area to meet the process requirement. All the
piping shall be of carbon steel and designed with valves,
specialities, supports and hangers.
DESCRIPTION OF ELECTRICAL SYSTEMS AND EQUIPMENT
Scheme of electrical generation for proposed co-generation
project shall consist of 1.0 No. 11.0 KV, 50 Hz, 3.0 Phase, 0.8
P.F. alternator of rating 12.5 MW and in addition to, 3.0 Nos,
3.0 MW each alternator and one of 5.0 MW rating. In expansion of
mill 3500 TCD, two alternator of 3.0 MW each, which will continue
to supply sugar plant. After meeting in house requirements due to
expansion and co-generation auxiliary requirements, plant can
export a net power of about 11.20 MW exportable power. The power
shall be stepped up 11/33 KV by a power transformer shall be
paralleled to grid via switch yard of mill. System will be
paralleled with HSEB substation at village Bhadson which is
located at a distance about 1.5 km from the plant. The Drawing
No. 5-785212-1 gives the key single line diagram for the co-
generation project.
Generator
Generator shall have nominal ratings of 12.5 MW with
generation voltage of 11 KV, 50 Hz, three phase and at a rated
power factor of 0.8 and with IP 55 enclosure. The machine shall
run at 1500 rpm and shall operate with the voltage and frequency
variation of + or - 10 % and + or - 5 % respectively. The
generator shall be complete with base frame, closed air circuit
water cooled(CAW) cooling system, brush less exciter, automatic
voltage regulator, neutral grounding cubicle, LASCVT(lighting
arrestor & surge capacitor and voltage transformer) panel, relay,
metering and control panel, instrumentation control and safety
devices and other accessories, spares and special tools that will
be required for satisfactory erection and efficient operation of
the station. The generator coupled to the steam turbine shall be
suitable in all aspects for operating in parallel with grid. The
generator shall match with the respective turbine in respect of
speed, over speed, moment of inertia, overload capacities,
coupling and other relevant requirements.
The stator and the rotor of the generator shall have class
`F`
insulation but the temperature rise shall not exceed the limits
specified for class `B` insulation. The generator shall be fitted
RTDs(min 2 per phase) for thermal protection, space heaters and
temperature indication.
The generator terminals shall be suitable for connecting to
switch gear panel through phase segregated copper/aluminium
busducts. The bus duct will be natural air cooled and air will
be run indoor. The current transformers for metering and
protection shall be provided in the busducts, in 11 KV switch
gear panels and NGR cubicles. The drawing No. 5-785212-2 gives
the protection scheme.
Excitation system & Synchronizing panels
The excitation system shall be of brush less type and shall
be provided with the following features:
* Generator voltage control
* Excitation current control
* Excitation buildup during startup and field suppression on
shutdown
* Limiter for the under excited range and delayed limiter for
overexcited range
The system shall have facility for manual as well as auto
mode operation and shall have diode protection relays to detect
failure of rotating diodes. The following minimum alarms shall be
arranged for:
* AVR fault
* AVR automatic changeover to manual
* Diode failure
Swinging/ trolley type synchronizing bracket complete with
running and incoming voltmeters, running and incoming frequency
meters, synchronoscope, synchronizing check and guard relays,
synchronizing cut off switch, lamps etc. shall be provided.
Provision for automatic synchronizing device with inputs to
governor control shall be made.
Unit control panel
The unit control panel shall comprise of control and
metering
system, synchronizing system, protective relays, start/stop
system alarm, annunciation and temperature measurement system.
The panels may be split up into control panel, metering panel
and relay panel for convenience. All meters shall be of 144 mm
square type 240 Deg scale. Each panel shall have TVM, ammeters,
voltmeters, frequency meter, power factor meter, KW, KVA and KWH
meters. Recorders shall be provided for voltage, pf, frequency
and KW. All relays shall be of static/micro processor based. The
following minimum protection will be provided for the generator:
* Overvoltage, undervoltage relay
* voltage restrained over-current relay
* Field failure relay
* Reverse power(active& reactive) relay
* Differential protective relay
* Stator earth fault relay
* Rotor earth fault relay
* DC failure trip relay
* Under/Over frequency relay
* Over load relay
* Bearing protective relay
LAVT and NGR cubicles
The LAVT cubicle shall house surge capacitor, potential
transformers (class 3P and 0.5), lighting arresters, busduct
chamber etc. The cubicle shall be complete with necessary
tappings for excitation system. The NGR cubicle shall comprise of
current
transformers(class 0.5 and 5P10), neutral isolating switch,
grounding resistor (unbreakable, corrosion proof, joint less
stainless steel grids).
11 KV Switchgear panel
The broad specification for the 11 KV switchgear panel shall
be as follows:
Rated Voltage : 11 KV, 3 Phase, 50 Hz
Maximum Voltage : 12 KV
Power frequency Voltage : 28 KV rms
Impulse frequency Voltage : 75 KV peak
System Fault level : 500 MVA
Enclosure : IP 5X
Maximum bus bar Temperature : 85 Deg. C
Operating Duty : 0-3min-co-3min-co
Control Voltage : 110 V DC
The 11 KV indoor switchgear board shall be metal clad, free
floor standing, totally enclosed, dust and vermin proof with draw
out type vacuum/SF6 circuit breakers. The board shall confirm to
IS:3427 and the breaker shall confirm to IS:13118. Each breaker
shall have distinct positions for service, test and isolation
mode and shall have independent earth switch for earthing the
cable side terminals. All panels shall have earth switch with
interlock as safety measure. The panels shall be suitable for
bottom cable entry. The switchgear shall be connected through
phase segregated busducts from the generator phase side
terminals. The panel shall be provided with one (1) incoming
feeder, Two (2) distribution feeders, one (1) outgoing power
export feeder and one (1) spare feeder.
The switchgear panel shall be complete with necessary CTs
and PTs for metering and protection which shall be of cast resin
type confirming to relevant Indian standards. The busbar in
switchgear panel shall be individually protected by busbar
protective relay. The auxiliary transformers feeders shall be
provided with the necessary relays and meters for protection
purpose.
LT Distribution System
The sugar plant load and co-generation plant load require
power supply at 415 Volt level. In the existing plant this power
is supplied by two 3.0 MW Turbo Generator set and one 5.0 MW
Turbo Generator set. The drawing No. 5-785212-1 gives the LT
distribution schematic for the complete sugar & co-generation
plants.
The system shall be designed to ensure reliable supply for
the plant loads without much disturbing the existing arrangement.
Existing bus shall be connected to a bus coupler at one end which
will couple the existing bus to transformer feeders. All feeders
and bus couplers shall be carefully interlocked to avoid improper
paralleling of different supply sources.
Interlock arrangements shall be given to ensure the
following conditions:
* The 415 Volt generators are not paralleled with transformer
supply.
* Supply from DG/ EB bus is not paralleled with other sources.
It shall be possible to operate all the sugar plant loads
even when the 415 generators are not operating. This shall be
ensured by operating the 415 Volt transformers while the 3.0 MW
sets are not in service.
The loads shall be distributed in such a way that the
transformers are not overloaded in any abnormal condition.
Parallel operation of two transformers will to tend to increase
the fault current in that bus to unmanageable level. This shall
be handled by providing series reactors (coreless type) with
those transformers or by going in for higher impedance (say 9% or
10%) transformers.
Capacitors bank shall be connected in the LT panels to
improve the power factor to about 0.95 lagging . The capacitors
shall be of all polypropylene (APP) dielectric type. The banks
may be controlled manually or by using power factor control
relays.
One feeder from 415 V DG/EB bus shall be connected to the sugar
plant LT bus for operating the colony lighting loads during off
season.
Distribution transformers and LT panels
The distribution transformers confirming to IS:2026 for
supplying the sugar plant, boiler and other loads shall be as per
the following specification.
Transformer Rating : 2 MVA
Cooling : ONAN
Ratio : 11/0.433 KV
Highest system Voltage : 12 KV
Power frequency Voltage : 28 KV rms
Impulse Withstand Voltage : 75 KV peak
Taps and Range : Off circuit tap changer
+5% to -10% insteps of
2.5 %
Voltage Vector : Dyn 11
Impedance : 6.25 % (10 % if transformers
are paralleled and no series
reactors provided)
Neutral Earthing : Solid Earthing
The distribution transformers shall be protected by over
current and earth fault relays at HV side and Restricted Earth
Fault (REF) at neutral end in addition to in built protective
devices like Buchholz relay, Magnetic Oil Level Gauge (MOG), oil
and Winding Temperature Indicators (OTI &WTI)
The LT distribution panels confirming to latest revision of
IS:8623 shall be dust & vermin proof construction sheet steel
clad totally enclosed, floor mounted, self standing type with
both front and rear access. All panels shall be of single bus bar
type with bottom cable entries.
Motors for co-generation auxiliary loads of rating less than
100 HP shall be provided with DOL feeders in MCC. Higher size
motors shall be of wound rotor type with automatic stripping
rotor starter or soft starter/ auto transformer starter depending
on starting torque requirements. DOL: motor feeders shall be
complete contactor, over load relay with single phasing
protection and switch fuse units. Motors of higher ratings shall
be protected by motor protection relays.
Switch Yard and Paralleling with Grid
The Co-generation project envisages a maximum power export
of around 11.2 MW which shall be exported to HSEB grid by
stepping up the power to 33 KV through one no 11/33 KV 20 MVA
power transformer. The 33 KV line shall be connected to HSEB
substation at village Bhadson by extending the bus in 33 KV bay.
Proposed 33 KV switch yard shall have single bus arrangement
with one power transformer with control and protection equipment
(breaker, Cts, Pts, LAs, isolators etc.) CT, PT and TVM for HSEB
measurement shall be arranged in the switch yard. Switch yard
arrangement and other requirements shall be in line with CBIP
specifications. The Drawing No. 5-785212-2 gives the protection
scheme and the Drawing No. 5-785212-3 gives the layout of the
switch yard.
The bus bars shall be formed with 3" IPS Aluminium pipe. The
minimum Phase, Earth, Section and Ground clearances in mm shall
be 915, 610,3000 and 3660 respectively. The switchyard components
will be designed to have a BIL value of 170 KV.
Feeder Protection
The feeders linking the plant substation and the EB
substation shall be protected with directional overcurrent &
earth fault relays. dF/dt relay and low forward power protective
relay shall be provided to protect the system from grid
disturbances and for inter-tripping of EB substation breaker
respectively.
Power Transformer
The transformer, with a rating of 20 MVA, 11/33 KV, Ynd 1
connected shall be complete with the fitting & accessories like
conservator, MOG, breather, Buchholz relay with contacts for
alarm and trip, pressure relief devices, thermometer pockets, OTI
& WTI, Valves, earthing terminals, cooling accessories,
bidirectional flanged rollers with locking and bolting device for
mounting on rails, air release devices, inspection cover, on Load
Tap Changer (OLTC) with remote tap changer control (RTCC) panel,
marshaling box, etc.
The transformer shall have the following minimum protection
to isolate the equipment during fault conditions:
Over current & earth fault relay
Differential relay
Restricted earth fault protection at HV side
Buchholz relay
Winding & oil temperature indicators
Oil level gauge
Over fluxing protective relay
Lightning Arrestor
lightning arresters rated 30 KV, 10 KA shall be provided at
the HV side of the transformer so as to cover the transformer in
the protection region of the lightning arrestor.
The lightning arrestor shall be heavy duty station class
type, discharge class III, confirming to IEC specification IEC-
TC-37
Arresters shall be complete with insulating Base, self
contained discharge counters and suitable milli ammeters.
Insulators and structure
Solid core type post insulators of adequate creepage
distances confirming to IS:2544 shall be provided for insulation
and support in switchyard.
The structure shall be made up of hot- dip
galvanized/reinforced concrete and designed to withstand forces
during normal conditions(wind loads and dead load of switchyard
components) and abnormal conditions( short circuit, earth quake
etc.)
Isolators
Isolators complete with earth switch, galvanized steel base
provided with holes, solid core type post insulators with
adequate creepage distance confirming to IS:2544, blades made up
of non-rusting material, operating mechanism(gang operated,
manual/ motor charging mechanism) shall confirm to IS:1818. They
shall be of center post rotating horizontal double break type and
consist of 3 poles.
The isolators shall have interlocks with circuit breaker and
earth switch.
Instrument transformers
The instrument transformers and accessories shall conform to
standards specified below :
Current Transformers : IS :2704
Potential Transformers : IS :3156
Instrument transformers shall be mounted on 33 KV class,
sealed porcelain bushings suitable for outdoor service and
upright mounting on steel structures.
Instrument transformers shall be hermetically sealed units
with- in-built provision to dissipate any excessive pressure
buildup.
Current Transformers shall be of ring type with suitable
construction at the bottom for bringing out secondary terminals.
Circuit Breaker
The circuit breaker and accessories shall be in general
conforming to IEC-56 and IS:13118. The breakers shall be of
Sulphur Hexafluoride(SF6) gas type.
The circuit breaker shall be totally restrike free under all
duty conditions and shall be capable of performing other duties
without opening resistor. Pole discrepancy shall be within
specified limits.
The SF6 gas shall be comply with IEC-376 and be suitable for
use in the switchgear under the operating conditions. The high
pressure cylinders in which the SF6 gas is shipped and stored
shall comply with requirements of relevant IEC standards.
Closing coil shall be suitable for operation at all values
of voltages between 85% and 110% of the rated voltage. Shunt trip
shall operate correctly under all operating conditions of the
circuit breaker up to the rated breaking capacity of the circuit
breaker and at all values of supply voltage between 70% and 110%
of rated voltage.
Safety Earthing System
A safety earthing system consisting of a buried mild steel
conductor earthing grid would be provided for the power plant
building, switch yard and other outlying areas. The earthing
system shall be formed to limit the grid resistance to below 1
Ohm. In the switch yard area, the touch potential and step
potential shall be limited to the safe values. The earthing
design shall be as per IEEE - 80 recommendations.
The buried earthing grid would be connected to earthing
electrodes, buried underground. Neutral point of transformer,
generator and non current carrying parts of equipment, lightning
arresters, fence etc. shall be earthed rigidly. The following
factors shall be considered for earthing system design :
* Magnitude of fault current
* Duration of fault
* Soil resistivity
* Resistivity of surface material
* Shock duration
* Material of earth conductor
* Earth mat grid geometry
Cables
All cables would be selected to carry the load current under
site conditions, with permissible voltage drop. In addition, high
voltage cables would be sized to withstand the short circuit
current. The following types of cables would be used.
Power cables for 11 KV system shall be with single
core/three core aluminium conductor, XLPE insulated, screened,
armoured and overall PVC sheathed confirming to IS :7098
The power cables of 1.1 KV grade shall be PVC insulated,
aluminium conductor, inner sheath PVC taped strip/wire armoured
with outer sheath of PVC compound conforming to IS :1554
The control cables for control/protection/indication circuit
of the various equipments shall be of 1.1 KV grade, PVC insulated
annealed high conductivity stranded copper conductor, inner
sheath PVC taped, flat/round wire armoured with outer sheath of
PVC compound conforming to IS :1554
Battery and battery charger
Common battery, battery charger and DC board unit shall be
provided for substation and power house.
Lead acid stationary battery(110V) with tubular positive
plate, pasted negative plate in hard rubber containers conforming
to IS :1651, for catering to the various DC loads in power house
and substation, complete with vent plugs, acid level indicating
floats, separators, bolts and nuts, cell insulators, intercell
connectors in dry and uncharged conditions.
The battery sizing shall be based on the basis of the
following type of loads :
Momentary load for 1 min.
Emergency load for 2 Hrs.
Continuous load for 10 Hrs.
The battery charger shall be of SCR controlled float cum
boost charging equipment housed in a free standing, floor
mounting cubicle having a degree of protection of IP 31
Lighting System
Good lighting in the substation and power house shall be
ensured to facilitate normal operation and maintenance activities
and at the same time to ensure safety of the working personnel.
Lux levels and glare index shall be as per recommendations of
IS:3646. The lighting system would comprise of normal and
emergency power supplies as described :
Normal AC lighting system
The lighting DB intended for lighting in power house and
substation area shall be supplied from the most reliable supply
source i.e. AC auxiliary supply panel.
The lighting circuit in the normal 1 phase, 240 Volt AC
lighting system would be fed through 415/ 433 Volt, 3 phase, 4
wire lighting transformers connected to the auxiliary
distribution system.
Emergency DC Lighting System
Direct current emergency lights, which shall be supplied
from battery units shall be provided at strategic points in the
power station, switchyard area and in control rooms.
Lighting Protection System
Building lighting protection system shall be provided as per
IS:2309 and Indian Electricity rules. The protection consisting
of roof conductors, air terminals and down conductors will be
provided for the power house structure. Switchyard equipment
shall be shielded against direct lighting strokes by providing
overhead earth wires. Overhead earthing wires shall be formed to
shield all substation equipments with an angle of shield of about
30 Degree.
AC Auxiliary Supply
AC supplies of single and three phase, are needed in a
substation and plant for internal use for several functions such
as:
* Illumination
* Battery charging
* Transformer tap- changer drives
* Excitation supply
* Power supplies for communication equipment
* Crane
* Breakers/ Disconnect switch, motors
* Fire protection system
* Space heaters in cubicles, generators and marshaling kiosks
* Air conditioning/ ventilation equipment
The design of AC auxiliary supply system must be such that
it ensures continuity of supply under all conditions, as far as
practicable, reliability being the basic requirement. Provision
for supply from minimum three different sources shall be
arranged.
DC Auxiliary Supply
DC auxiliary supply is required for closing and tripping of
circuit breakers, emergency lighting, control board indications,
etc, which shall be supplied by the DC batteries provided in the
substation and in the power house.
PLANT LAYOUT
The proposed co-generation Plant at PAIL’s Indri sugar mill
will be located with in the sugar mill complex. The complete co-
generation plant consisting of the boiler, the main power station
building, the auxiliary installations such as the cooling water
system, DM water system and the switch yard shall be located near
the mill. The space available, in the complex is adequate, for
the complete co-generation plant. The Drawing No. 6-785212-1
gives the locations of the various installations. The co-
generation plant is located such that there shall be no
disturbance to the sugar plant operation during the co-generation
plant construction.
At present 2500 TCD two boilers of 45.0 Kg/Sq.cm pressure,
35.0 TPH are laid out in the plant. In the first phase of
expansion of crushing capacity i.e. 3500 TCD, one more boiler of
50.0 TPH, 65.0 Kg/Sq.cm & 485 Degree C will be easily installed
next to the existing boilers. In second phase of expansion of
crushing capacity i.e. 5000 TCD, one more boiler of 65.0 Kg/Sq.cm
& 485 Degree C and 50.0 TPH capacity will be added. For
installation of this boiler adequate space is available in the
mill. Existing boilers are of semi out-door design, with just a
roof over the furnace area and the bagasse storage silo. The
boiler operating floor level is around 6.0 meters.
The airpreheater and economizer will be arranged in a single
vertical pass behind the boiler. The airheater is laid out such
that the tube replacement is done easily. The fans and cyclone
dust collectors shall be used. Adequate platforms and stair ways
as required for the operation and maintenance of the boiler shall
be provided. The boiler area will be provided with approach roads
and adequate lighting.
The boiler feed water pumps shall be located below the
boiler operating floor on the ground floor and the feed water
control station shall be located on the boiler operating floor.
A stack of 2000 mm inner diameter at the top is located near
the ID fans. Concrete paving will be provided in the boiler area
with necessary drains and trenches for cables and pipes.
The new Turbo-Generator sets of 5.0 MW & 12.5 MW capacity
and their auxiliaries are located next to the existing Turbo-
Generator sets. The Turbo-Generator operating floor shall be at
about 6.0 meter elevation. The building superstructure will be of
structural steel framing with brick clading and R.C.C. floor
slabs. The building roof will be of pre cast concrete panels on
steel trusses. The turbine and generator foundation will be of
reinforced concrete frame isolated from the building foundation
and the super structure. The condenser of the 12.5 MW Turbo-
Generator with its ejector system and the condensate extraction
pump and oil system console for the Turbo-Generator is located on
the ground floor within the building.
One 20.0 tonne capacity electric overhead traveling capable
of serving the entire length of the building is provided in the
Turbo-Generator building. Three cranes with hook capacity of 5.0
tonne each are also provided for cane unloading. An opening is
provided on the operating floor that serves to take out the
Turbo-Generator components for maintenance. The cables and the
bus duct will run
below the switchgear room or control room as the case maybe.
Similarly the inlet, extraction and the exhaust steam piping will
be run below the operating floor.
The raw water storage tank shall be located next to the
existing boilers, close to the existing tanks. The raw water
pumps shall also be located near the tanks. The DM water plant
shall also be located at the same place. Cooling water pumps
shall also be located in the power house.
The bagasse storage yard will remain in its present location
except that the conveyor from the mill house will be further
extended. Another conveyor elevator traveling in the opposite
direction will feed the bagasse reclaimed from the storage yard
on to the conveyor running in front of the boiler.
The ash handling system consisting of water impounded
scraper conveyors, screw conveyors and belt conveyors will
collect the ash from the boiler furnace hoopers, airpreheater
hoopers, cyclone dust collector hoopers and feed the ash into the
concrete silo located near the new stack. The actual location of
the conveyors and the number of conveyors shall have to be
decided during the detailed engineering of the project.
The distribution transformers are located in the plant
depending on the load centers. The 11 KV switch yard is located
near the power house building. The layout of the switch yard is
given in the Drawing No. 5-785212-3.
OPERATION AND MAINTENANCE REQUIREMENTS
OPERATION REQUIREMENTS
The operation of the plant starts with the commissioning. In
broad terms commissioning can be defined as setting the plant to
work safely and on programme. It is necessary to ensure that all
equipment are completely erected before operations begin.
Although this may be considered difficult, the other extreme of
operating a plant with insufficient instrumentation, controls and
alarms is dangerous. Although some compromise can be made with
regard to plant completion, the commissioning procedures should
never compromise personnel and the system safety.
A proper checklist procedure must be draw up, which shall
include all the section of plant and shall take into account, the
contractual responsibilities, the technological relationship
between the various sections, pre-commissioning cleaning
requirements. The checklist procedure helps in the following:
* To ensure that the necessary checks are carried out on each
item of the plant before it is put into commercial service.
* To indicate a contractor's commissioning requirements from
the client or from other contractors.
* To ensure that energy is supplied to an equipment or a plant
when it is safe to do so.
* To facilitate the recording of the progress on the various
commissioning activities.
* To provide a basis for the plant history.
The operation of the cogenerating unit interconnected to the
grid is an activity that must be properly coordinated, with in
the plant as well as with the electricity board's sub-station to
which the plant feeds power. Operation in parallel with the grid
eventually makes the co-generation plant a part of the HSEB's
utility system, and hence the co-generation plant must assume
some of the same responsibilities of HSEB. With this, the HSEB's
local despatch center will need to monitor the incoming power
from the cogenerating plant on a continuous basis.
The operation of a modern high pressure and high temperature
unit demands closely controlled operating conditions. The unit
starts-ups, shut-down and even load variations must strictly
follow the carefully laid down procedures given in the operation
manuals. Generally, the plant shall be sufficiently instrumented
to permit close checks on such operating parameters as boiler
tube and drum metal temperatures, furnace gas temperatures,
turbine expansions, casing metal temperatures, condenser vacuum
etc.
An important feature of the modern power generating plant is
the automatic safety lock-out devices. While sufficient thought
goes into it at the design stage, it remains the responsibility
of the operating staff to ensure that the safety devices are set
correctly and kept in operation.
While safety of the plant and personnel is the foremost
importance in the operation, the efficient operation of the plant
can not be ignored. While operating, it is important to check the
essential parameters of the plant and equipment to ensure that
the plant performance is at the optimum level. Any variations in
the operating parameters or any deviations from normal
performance of the equipment or plant shall have to be analyzed
immediately to diagnose the problem and to take remedial measures
to bring back the plant and equipment to its original parameters.
The detailed treatise on the operation of the power plant is
beyond the scope of this report. However, two important areas are
highlighted below.
Water chemistry
With the rapid increase in the operating levels of the steam
temperatures and pressures of the modern boilers, ensuring good
quality of water has assumed greater importance.
Pressure at/around 60 kg/Sq.cm is almost a threshold limit
for water quality and above this pressure additional precautions
are to be taken to ensure that the quality of the feed water
given to the boiler is maintained at acceptable limits. This
aspect deserves much greater attention specifically in a sugar
plant where the chances of contamination of the condensate by
sugar juice is a likelihood. The system envisaged provides for
the direct induction of the safe steam exhaust condensate into
the feed water system but restricts the vapor condensate
induction depending on its quality. Another area of concern could
be the condenser leakage where the condensate gets contaminated
by the cooling water. A routine check up of the feed water
quality during the startup of the plant and also periodic check-
ups result in the elimination of any serious problem due to water
quality.
Instrumentation
The modern day power generating system like the one
envisaged for the specific co-generation plant can not be
effectively operated without proper instrumentation and control
system. An effectively designed instrumentation and control
system performs following functions :
* Provides operators with the indication or record of the
instantaneous averaged or integrated value or condition of
the various operating parameters such as temperatures,
pressures, flows, levels, position of switches, currents,
voltages, power etc..
* It also provides at convenient locations either local,
remote or automatic control system to control the above
operating parameters and gives alarms and even ensures
automatic trip outs, when operating parameters reach beyond
the normal range into the unsafe or undesirable range.
Instrumentation is increasingly taking over many functions
of the operator. Its response to changing and transient
conditions, its ability to anticipate, detect and discriminate
faulty conditions and act accordingly is quicker and for more
accurate if well designed. With the ability of the
microprocessor based systems to include data acquisition and
processing capabilities, the system's ability, to log and process
periodically the plant data, is also far superior and permits
more timely corrective action. Presently some of the
responsibilities of the operation section are taken over by good
instrumentation. The most difficult thing to be encountered in
the initial stages of plant operation is the necessity to develop
in the operation staff a faith in the instrumentation. Many times
the operators first response to a meter, reading too high or too
low, is to disbelieve it on the ground that it may be reading
incorrectly. If instruments are not checked and calibrated
frequently an operator will delay taking corrective actions. This
problem could be solved by:
* Frequent checking and calibration of instruments
* Developing in the operator a habit of cross checking
instrument indications with each other to determine whether
the instrument is faulty or there is an abnormal operating
condition; and
* Developing in the operator a habit of analyzing indicated
data to determine accurately what could be wrong.
MAINTENANCE REQUIREMENTS
The main objectives of the maintenance section are to keep
the plant running reliably and efficiently as long as possible.
Reliability is impaired when a plant is thrown to forced and
unforeseen outages. This aspect assumes greater significance in a
co-generating plant exporting power to the SEB's grid under
contractual commitments. It is imperative that any planned
maintenance is under taken with closer co- ordination with HSEB.
Efficient operation implies close control not only over the
cost of production but also over the cost of maintenance. There
are two components in maintenance cost, one is the direct cost of
maintenance i.e. the material and labor and the other is the cost
of production loss.
There are two categories of maintenance work. one is the
irksome breakdown maintenance which is expensive. Much as it is
desirable to avoid or minimize this, its existence must be
accepted. Secondly, it is the preventive maintenance with proper
planning and execution of plant and equipment over hauls. This
maintenance activity should be clearly planned with regard to the
availability of material and labor. It is also essential to
develop proper inspection procedures with non-destructive testing
methods. Such inspections by trained personnel reveal defects
not necessarily detected by mere visual inspection.
The following help in reducing the breakdown maintenance and
also help in planning for preventive maintenance.
* Careful logging of operation data and periodically
processing it to determine abnormal or slowly deteriorating
conditions.
* Careful control and supervision of operating conditions.
Wide and rapid variations in load and frequency conditions
do contribute to increased maintenance particularly on the
high temperature and high pressure units. The turbine
throttle steam pressure and temperature conditions must also be
kept steady on the rated value.
* Regulate routine maintenance work such as keeping equipment
clean, cleaning heat exchanger, filters, effectively
executed lubrication programme, effective operating supervision
over bearings, commutator or slip ring brushes, gland and
flange leakages.
* Correct operating procedures.
* Frequent testing of plant equipment to determine internal
condition of equipment such as plant cycle efficiency
tests, enthalpy drop tests, heat exchanger and pump
performance tests, generator and turbine shaft vibration
tests, turbine lube oil testing, etc.
* Close coordination with the manufacturers to effect
improvements in plant layouts and design, use of better
material, introduction of such facilities as cathodic
protection, use of better protective paints etc.
It is extremely important that proper records are maintained
not merely for the maintenance work done but also of the material
used and actual man hours spent. Some sort of a card system
shall have to be introduced to keep records that are most useful
in future planning of outages and providing for effective
control.
Another important requirement of a good maintenance program
is to ensure that spares are ordered in time, and good stocks of
the frequently required spares are maintained.
MANPOWER AND TRAINING
Rapid growth of industrial activity in the country in
general, and in particular in the power generation industry, has
brought about an acute shortage of skilled and trained manpower.
To run the co-generation plant skilled and trained manpower is
essential. A well defined futuristic plan is required to acquire
such qualified & trained work force at the time of commissioning.
The staffing and the organizational requirements can not be
decided on the operating experience with the existing sugar plant
boilers and Turbo-Generator set, but should be done considering
the specific requirements of the proposed co-generation plant at
the crushing capacity of 5000 TCD.
The requirement of the personnel required must be based on
the rational assessment of the following factors :
* The nature of the plant and machinery i.e. boilers like
bagasse fired, dumping/ traveling grate, etc. Turbo-
Generator
sets like condensing, back pressure, fuel and ash handling
plant, cooling water system, DM plant, size of switch yard
etc.
* Socio-economic conditions.
* Availability of personnel with the right back ground and
experience.
* Company's policy regarding, labor and contract labor.
Once the staff is finalized and agreed, a suitable training
scheme shall be programmed and implemented. The objective of the
training programme must be to equip each individual to carry out
his particular function with skill and confidence. The training
programme shall be based on the classification of the main
functions as operation and maintenance and with in this main
classification, designed to cater to engineers, supervisors,
skilled workers etc..
OPERATION AND MAINTENANCE ORGANIZATION
The Drawing No. 8-785212-1 gives the operation and
maintenance organization chart for the PAIL’s co-generation
plant. The organization proposed assumes that the co-generation
plant will be mostly independent from the sugar plant, with the
Chief Engineer Power Plant, holding the full charge of the co-
generation power plant, reporting directly to the Managing
Director. The staffing recommended here takes care of only the
new plant and machinery to be added to the co-generation plant.
There could be some overlapping of functions between the staff of
the existing boilers and the Turbo-Generator sets and the staff
proposed for the new equipment. Such areas should be identified
and the staffing shall be suitably altered.
The organization under the Chief Engineer( Power Plant)
[CE/(PP)], shall be divided into operation and maintenance
sections each headed by a Deputy Chief Engineer, operation
[DCE(O)] and Deputy Chief Engineer maintenance [DCE(M)]. There is
a separate efficiency cell with an engineer directly reporting to
the CE/(PP).
The shift engineers, one in each shift and one reliever and
the chemist working in the general shift report to the DCE(O).
The electrical operators , boiler operators and the Turbo-
Generator set operators coming in shifts, and each one with a
reliever and shift helpers report to the shift engineer. In
addition to the helpers the boiler operators are assisted by the
boiler auxiliary operators.
The maintenance organization of the co-generation plant
works under the DCE(M). The maintenance engineers for the
mechanical, electrical and instrumentation report to the
DCE(M).The supervisor civil maintenance also reports to the
DCE(M) and takes care of all civil maintenance works. Each of the
maintenance engineer is assisted by supervisors and technicians.
The maintenance staff shall be generally rotated in the general
shift, but will be available on call to attend to any breakdown
even in other shifts.
The efficiency cell is an important section which serves
both the operating and maintenance sections by providing useful
feedback to the operating staff and valuable information to the
maintenance staff on the performance and the healthiness of the
various equipment. The major responsibilities of this cell are:
* To establish from the design and plant acceptance test data,
as well as after overhaul test data norms against which day-
to-day performance can be checked.
* To analyze the daily plant performance data to detect
departures from normal expected performance and to keep
track of trends indicating gradual deterioration.
* To carry out frequent tests on the plant and individual
equipment to determine their internal conditions to help
maintenance scheduling.
* To investigate special problems as and when they arise.
The analysis and the data provided by the efficiency cell
enables plant operation and maintenance personnel to take
suitable corrective actions promptly and with proper priorities.
TRAINING
The major objectives of the operational training shall be to
acquaint the operators of the following:
* The nature, purpose and limitations of all the plant and
equipment.
* The detailed operating instructions on each section and
equipment of the plant
* The normal start up and shutdown programme for the unit.
* The emergency procedures.
The basis for the training shall be Plant Particulars Book,
which is compiled from the manufacturers's instructions, the
contract demand and drawings. In addition, the information
gathered from the visits to the other operating plants and to the
manufacturers work shall also be included in the book.
Supervision and coordination of the training programme requires
full times attention of a senior executive of the plant, and also
the consultant's assistance may be taken. The training programme
shall include lectures, expositions by experienced plant
operators and maintenance personnel, informal discussions and
visits to operating plants and manufacturers's works.
The maintenance training programme should be based on the
requirements of the individual maintenance functions, like
mechanical, electrical, instrumentation etc.. The engineers and
technicians should be sent to the manufacturers works to witness
the production and be associated with the erection of plant and
equipment.
ENVIRONMENT PROTECTION AND WASTE MANAGEMENT
The impact of any project, specifically the thermal based
power generating project, on the environment, should be studied
in detail. A thermal power generating facility generates both air
and water pollutants and adequate measures should be built into
the project proposal to contain these pollutants with in
acceptable limits. One major redeeming factor about sugar plant's
bagasse based co-generation, is that the dust or the green house
gases released into the atmosphere are no more than what would
have been produced by alternative methods of bagasse disposal
(burning bagasse inefficiently in the boilers, or letting it
decompose) practiced presently in the sugar plants. Also the co-
generating plant, feeding surplus power to the grid, indirectly
prevents a prorata quantum of pollutants, being let into the
environs from the utility plant, from where otherwise the equal
quantum of power would have been generated. The cogenerating
plants thus being indirectly environment friendly deserve
encouragement.
The effluents generated in the proposed co-generation plant
can be classified as under:
* Particulate matter and gases due to combustion of bagasse in
the steam generator.
* Dry fly ash and furnace bottom ash.
* Pollution in liquid form such as,
- Effluent from water treatment plant
- Chlorine in cooling water
- Boiler blow down
- Sewage from various building in the plant
Particulate Matter And Gases
The air pollution elements from the proposed unit are,
- Dust particulate from fly ash in flue gas
- Nitrogen oxide in flue gas
- Sulphur-di-oxide in flue gas
The pollution control regulations limit the particulate
matter emission from bagasse fired steam generators as 350 mg/N
cum. The height of the stack which disburses the pollutants have
been fixed as 40 meters based on the guidelines given by the
pollution control regulations.
The sulphur is very minimal in the fuel and sulphur-di-oxide
emission will be negligible. The temperatures encountered in the
steam generator while burning, high moisture bagasse are low
enough not to produce nitrogen-oxides. Moreover, the tender
specification for steam generator stipulates over fire air system
with staged combustion which will also ensure reduction in
nitrogen-oxide emission. Hence no separate measures are taken to
contain the sulphur and nitrogen oxide pollutants.
Water Pollution
Hydrochloric acid and caustic soda will be used as
regenerants in the proposed water treatment plant. The acid and
alkali effluent generated during the regeneration process of the
ion -exchanger would be drained into a epoxy lined under ground
neutralizing pit. Generally these effluents are self
neutralizing. However provisions will be made such that the
effluents will be neutralized by addition of either acid or
alkali to achieve the required pH of about 7.0. The effluent will
then be pumped into the effluent treatment ponds which is part
of sugar plant effluent disposal area.
Chlorine In Cooling Water
In the condenser cooling water, residual chlorine of about
0.2 ppm is maintained at the condenser outlet. This value would
not result in any chemical pollution of water and also meets the
national standards for the liquid effluent.
Steam Generator Blow Down
The salient characteristics of blow down water from the
point of view of pollution are, the pH and temperature of water
since suspended solids are negligible. The pH would be in the
range of 9.5 to 10.3 and the temperature of blow down water will
be 100 Degree C. The quantity of about 2.0 Tonne/ Hr of blow down
is very small and hence, it is proposed to put the blow down into
the trench and leave it in the effluent ponds.
Sewage From Various Buildings In The Plant
Sewage from various building in the power plant area will be
conveyed through separate drains to the septic tank. The effluent
from the septic tank will be disposed in soil by providing
disposing trenches. There will be no ground pollution because of
leaching due to this. Sludge will be removed occasionally and
disposed off as land fill at suitable places.
Thermal Pollution
A close circuit cooling water system with cooling towers has
been proposed. This eliminates the letting out of high
temperature water into the canals and prevents thermal pollution.
Below down from the cooling tower will be trenched out and
ultimately conveyed to the effluent ponds. Hence, there is no
separate pollution on account of blow down from cooling water
system.
Monitoring Of Effluents
The characteristics of the effluents from the proposed plant will
be maintained so as to meet the requirements of State Pollution
Control Board and the minimum national standards for effluent
from Thermal power plants. Air quality monitoring will also be
under taken to ensure that the dust pollution level is within
limits.
Noise Pollution
The rotating equipment in the co-generation plant will be
designed to operate at a total noise level of not exceeding 85 to
90 db(A) as per the requirement of Occupational Safety and Health
Administration (OSHA) Standards. The rotating equipment are
provided with silencers wherever required to meet the noise
pollution. As per OSHA protection from noise is required when
sound levels exceed those given in the table:
Permissible Noise Levels
Exposure Duration/Day Sound level db(A)
8 90
6 92
4 95
3 97
2 100
1 102
PROJECT IMPLEMENTATION AND SCHEDULE
The most essential aspect regarding the implementation of
this Co-generation project is that the project construction,
spanning more than Twelve(12) months, shall affect neither the
sugar plant operation nor curtail the crushing capacity of the
plant. This aspect is very important since, at least one full
crushing season will fall in the Co-generation project
construction period. A good planning, scheduling and monitoring
program is imperative to complete the project on time and without
cost overruns.
The project Zero Date starts once the management gives the
`Go Ahead’ approval after the project is approved by the Ministry
of Non Conventional Energy Sources(MNES) and the Financial
Institution has indicated its willingness to fund the project.
The sugar plant should, as the first step, employ a detailed
engineering consultant, to entrust them with the complete
responsibility, for the Project Engineering and Design of the Co-
generation plant, and to help the factory in the procurement,
project management and the construction and commissioning
supervision of the project.
A multi disciplinary project like the Co-generation project
needs the services of an experienced consultancy organization,
since most of the sugar plants do neither have the manpower nor
the experience to handle the design and the execution of such a
project. The design phase of the project should start much early,
since the system design and the first stage layout should be
completed before the contract design.
The nature of the project calls for the division of the
project into recognizably discrete plant areas with specific
terminal points that can stand alone for engineering and contract
purposes. An appropriate contract strategy involves, the decision
on the number and the type of contracts to be let, vendor
evaluation, formulation of contract agreement defining respective
obligations, the basis for discharging them and remedies for
default.
The specifications for major equipment like boiler, Tubo-
Generator set etc.. The technical information on which is
essential to the development of the plant design and in
particular to the civil design, shall be drawn up at an early
stage of the project. Program of design information submission,
from the mechanical and electrical contractors, that satisfies
the over all project shall be drawn up. The most important among
such information are the location of the individual plants, floor
loadings, support requirements etc.. Which are required for the
civil design.
Since the project execution calls for closer co-ordination
among the contractors, consultants and the sugar plant proper
contract co-ordination and monitoring procedures shall be
formulated. Detailed bar charts or networks shall be made to plan
and monitor the project progress. Contract drawings and documents
requiring approval from statutory authorities like The Chief
Inspector of boilers, Factory Inspector, Chief Electrical
Inspector, Pollution control Board etc. shall be clearly
identified and scheduled so that the procedural formalities do
not affect the project progress.
The successful and timely implementation of the project and
the avoidance of overspending and frustration depends on the
performance of the project team. This project team shall consists
of the representatives from both the consultants and the sugar
plant.
The responsibilities of this project team shall be :
* Plan and program all the work and resources required for the
project completion.
* Design the plant and the plant support systems.
* Place contracts with the manufacturers and contractors to
procure plant and machinery and services at the right time,
of the right quality and at an economical price.
* Organize the construction and commissioning of the plant by
progressively integrating individual systems.
* Monitor and control the project progress with regular
interactions and co-ordination.
* Ensure cost control to contain the project cost within the
planned budget.
Since the co-generation project is coming up within the
sugar plant complex, in the operating area of the sugar plant, it
is important that the area identified for the co-generation plant
is cleared for the early start of the civil work. The soil
investigation and site grading shall be proceed without any
hindrance. The site development shall include the laying of the
approach road, identifying or constructing adequate storage
space, providing lighting in the work area etc.
Since the plant location is susceptible to monsoon rains,
all the major civil work shall have to be planned in the non-
monsoon period between November to May. It is essential that the
before zero date of the project all the clearances from
government bodies like the pollution control board, electricity
board etc. are obtained. Above all the sugar plant management
should make adequate uninterrupted fund flow available for the
execution of the project.
This is the critical phase of the project where work
progresses in almost all the fronts. The erection and
commissioning phase of all the contracts proceed simultaneously
and it is important to ensure that the various contracts have
adequate facilities and are established on the site in time to
meet their programmed commitments. Adequate power and water shall
be made available for the construction.
The construction manager from the sugar plant side takes the
over all responsibility of the site, assisted by the resident
site manager from the consultant side. The construction team`s
work is to continuously monitor the site progress against the
agreed programme, and to initiate whatever corrective action is
necessary to maintain satisfactory site progress. During the
execution stage of the project at site, quite a few of the
various contracts progressing simultaneously are inter-related,
and hence, the delay in the activities of one contractor will
invariably affect the progress of the other contractors and
ultimately the project progress. This aspect emphasizes the
importance of progress review, project monitoring and timely
remedial measures, for the smooth and “with in the budget”
execution of the project.
Certain basic responsibilities of the construction
management are :
* The contractor shall be encouraged to give the earliest
possible warning of actual or potential difficulties.
* Ensured that the senior management in the contractors
organization are made aware of the serious problems at an
early date.
* Provide a focus for early discussion of any potential
problem and possible remedial measures, while clearly
maintaining the contractors responsibility for recovering
delays.
* Help to foster a climate among all concerned that no
extension of site deliveries and erection schedule are
allowable.
A fortnightly progress review meeting is held with each
contractor, while formal reports are tabled, giving an agreed
progress statement. From these agreed progress statement, an
accurate prediction of the state of the project is available
which helps the construction team to adjust, if necessary, the
activities of the particular contractor and also the activities
of any affected contractor.
One of the major activities in the co-generation project
implementation is the work related to the power evacuation system
inter connecting the co-generation plant and Indri’s sub-station.
This activity should be initiated at the very early stage of the
contract so that the transmission lines and the interconnection
at the sub station are made ready well before the commissioning
of the project.
The commissioning phase in a project is the one where the
design, manufacturing, erection and quality assurance expertise
are put to test. The commissioning team for each plant will
consist of representative from the contractor, consultant, and
the sugar plant. It is essential to associate the staff
identified to operate the plant in the commissioning stage
itself.
When construction work is complete, the check list, designed
to ensure that the plant has been properly installed and
appropriate safety measures have been taken, are gone through,
and all the documentation pertaining to the statutory inspection
and approvals are presented, the commissioning team shall take
over. The commissioning team will follow scrupulously the
commissioning and operating instructions laid down by the
plant/equipment, manufacturer/supplier to prove that the
plant/equipment is in every respect fit for service. The plant
shall be subjected to a performance test, after the stipulated
trial operation and the reliability run. After the successful
completion of the performance test the plant will be taken by the
sugar plant.
The over all project schedule envisages the project
commissioning in twenty(20) months from the zero date of the
project. In the schedule the project is divided into three major
categories like civil, mechanical and electrical and these
categories are then sub-divided into major identifiable
contracts.
For each of the contract, the schedule identifies the
following applicable activities :
* Basic study
* Tendering
* Receipt of offers, evaluation, discussion and purchase order
placement.
* Manufacturing and deliveries.
* Erection and other work at site.
* Commissioning, trial run and testing.
Once the project gets started, it is essential that a
detailed bar or net work chart is prepared incorporating all the
contracts and the activities so that the planning and the
monitoring is effectively done.
PROJECT COST ESTIMATE
The cost of co-generation project is estimated, on the basis
of, the prevailing prices and rates as on February 1996, and the
estimation is for, the installation of power generation and
services facilities described in the previous sections. The
estimate is derived by dividing total quantum of work into two
categories. The category I, is that for which the cost is
calculated based on the current information available on the
prices of plant and equipment and the rates of various works. The
category II, that consisting of major equipment, for which
budgetary offer have been made for any escalation in these
estimates, since the project is expected to be implemented
shortly.
The cost of the co-generation plant covers all the cost
associated with the construction of the plant, and includes the
civil construction cost, cost of equipment for power generation,
cost of auxiliaries and utilities. The total project cost is
arrived at by adding to this cost, the pre-operative expenses
inclusive of project design and engineering, start-up and
training expenses, interest during construction and the margin
money to meet the working capital requirements.
Land and Site Development
This co-generation project at PAIL is coming up as a part of
the sugar plant and adequate land is available within the sugar
plant premises for setting up the co-generation project. Hence no
cost towards the acquisition of land is considered in the project
cost estimate.
Civil and Structural
The civil work includes the earth work and concrete work for
the plant building, equipment foundations, tanks, cooling tower
basin, ash silo, etc.. The cost of laying of in plant roads,
fencing drains and sewers, landscaping is also included as part
of civil cost. The structural steel work for the Turbo-Generator
set building is also included under the heading ‘Civil Cost’. No
pilling has been envisaged for the buildings as well as for
equipment foundations and only open foundations are considered.
The following rates covering the material and construction cost
are considered in the estimation civil works cost.
Reinforced Cement Concrete : Rs.2500/Cu.M
Reinforcement bars : Rs.19,000/tonne
Structural steel : Rs.20,000/tonne
The civil work quantities and the cost of civil works given
are only estimates and will have to be suitably modified after
the equipment supply is finalized and adequate data regarding the
loading and dimensions of equipment are available from the
manufacturers and suppliers during the engineering stage, and
also on the actual soil conditions encountered at different
stages of construction.
The total civil cost of civil works including the items
specified above is estimated as Rs.150.00 Lakhs.
Mechanical and Electrical Works
The cost of the steam generator & its auxiliaries and Turbo-
Generator set & their auxiliaries are based on the budgetary
offers received from a few of the Indian suppliers. It may be
found that the prices quoted by the suppliers are widely varying
with some of the prices quoted deviating very much off from
realistic prices. In the estimation for the project, the cost
which is closer to the price of some of the recently finalized
orders have been considered.
The cost of cooling tower, DM water plant, cooling water
pumps, the turbine hall crane, transformers and switch yard
equipment are based on the budgetary offers from Indian
suppliers.
All other mechanical and electrical equipment costs are
based either on the cost particulars available for similar
equipment or have been estimated.
The cost of transmission lines for evacuating the power from
the Co-generation plant to the nearby HSEBs substation i.e. Indri
substation at a distance of 1.5 km from the sugar plant is
estimates to be Rs.43 Lakhs.
Cost towards plant erection, testing and commissioning have
been included in the equipment cost indicated. Also the costs are
estimated to be inclusive of taxes and duties, freight and
insurance.
The cost of two years operation spares is estimated to be
three(3) percent of the equipment cost.
A provision of Rs. 48.0 Lakhs have been made for the pre-
operative expenses covering establishment and administration
during construction, traveling, design and engineering charges,
training of operation and maintenance personnel and start-up
expenses.
A provision of 5% of the costs of civil and structural work,
mechanical and electrical equipment and other costs has been made
towards contingencies. This contingency provision works out to
212.00 Lakhs.
The Table A gives the Project Cost without the Interest
During Construction (IDC) and the Working Capital Margin.
Table-A
Project cost (without IDC & WCM)
S.No Description Cost Rupees in Lakhs
-------------------------------------------------------1. Civil Works 150.00
2. Mechanical Works 1662.00
3. Electrical Works 200.00________
4. Total Works Cost 2012.00
5. Spares@ 3% of 2.& 3. 56.0
6. Preoperative Expenses 48.00________
7. Sub Total 2116.00
8. Contingency 5% of 7.0 212.00--------
9. Project Cost 2328.00(Without IDC and WCM)
-------------------------------------------------------
Subsidy From Government of India
The Ministry of Non-Conventional Energy Sources, in the
Government of India has announced a subsidy scheme for bagasse
based demonstration Co-generation Plants. The Co-generation plant
being proposed for PAIL fulfills all norms set by MNES to become
eligible for the subsidy. The subsidy amount shall be 15% of the
cost of the equipment identified and listed by MNES or Rs.35
Lakhs for every MW of exportable power or 300 Lakhs whichever is
lowest.
The cost of equipment identified and listed MNES for the
computation of subsidy is given in Table B. The cost figures
furnished are inclusive of the cost of supply, erection and
commissioning and the taxes & duties.
The exportable power from the co-generation project, as
indicated in the power balance is 11.20 MW. The eligible subsidy
for the project under this clause is Rs. 392.00 Lakhs.
The eligible subsidy (Rs. In Lakhs) for the PAIL`s co-
generation project shall be as given below.
15% cost of equipment cost as per Table B : 281.32
Eligible subsidy as per power balance : 392.00
The maximum Eligible Subsidy : 300.00
Table BCost Estimate For The Equipment Listed By MNES
S.No. Description of Equipment Estimated Cost(Rs in Lakhs)
1. Bagasse fired boiler with accessories such as feed pumps,deaerator, heat recovery equipment, economiser, airpreheater, chimney,ID&FD 484.00
2. Turbo-Generator with electricalcontrols and related mechanicalequipment 1000.00
3. Condenser & cooling water system 60.00
4. Water treatment/conditioning plant 13.00
5. Steam piping necessary for (1)&(2),up to the exhaust of Turbo-Generator 2.50
6. Bagasse handling equipment for(1) 34.00
7. Grid interconnection schemeincluding equipments 151.00
8. Civil works for above equipment 131.00----------1875.50
Interest During Construction (IDC)
The interest during the construction period is capitalized
to calculate the total project cost. The rate of interest
considered is 17.5 %, and is calculated for the project cost of
Rs.2328.00 Lakhs less the subsidy of 281.32 Lakhs from the
Government of India and the equity of Rs.2046.68 Lakhs from the
sugar mill. While calculating the IDC, it is considered that the
drawl of long term loans from the financial institutions will
commence only after the equity capital is utilized. The Project
Construction Period is 18 Months. Also the IDC is calculated for
the phased capital expenditure given in Table C. The calculated
figures of IDC is given in Table D. The period and the bracketed
figures in Tables C& D indicate the half years in the year.
Table C Phasing of Capital Expenditure And Mode of Financing
(All figures Rupees in Lakhs)
Year/ Expenditure Subsidy Equity Long Term(Period) during period Component Component Loan-------------------------------------------------------1/(1) 332.00 38.32 293.68 0.001/(2) 998.00 121.50 729.66 146.842/(1) 998.00 121.50 0.00 876.50 -------------------------------------------------------Total 2328.00 281.32 1023.34 1023.34-------------------------------------------------------
Working Capital Margin
The working capital for the Co-generation plant shall meet
the requirements of the salaries and wages, procurement of
chemicals and start up fuel, maintenance expenses and overheads
for a period of two months in the season. Since there is no
direct expense for the procurement of bagasse, which is the main
fuel, for the boilers no provision on this account is required.
For the PAIL’s Co-generation project a working capital provision
of 38.60 Lakhs has been made based on the above, and the entire
money is capitalized included in the project cost.
Table D Calculation of Interest During Construction
(All figures Rupees in Lakhs)
Year Long Term IDC Till(Period) Loan From end of
Institutions Period-------------------------------------------------------1/(1) 0.00 0.00 1/(2) 146.84 25.70 2/(1) 876.50 76.70
---------------------------------------- Total 1023.34 102.40
-----------------------------------------------------------------------------------------------
Total project cost
Rs. In Lakhs
_____________
Project Cost Without IDC &WCM 2328.00
(Refer Table A)
Interest During Construction 102.40
Working Capital Margin 38.60
----------
Total Project Cost 2469.00
----------
FINANCIAL ANALYSIS
The financial analysis gives the details of the
operation and profitability, the cost of generation of power,
cash flow, for a period of ten (10) years from the commissioning
of the project. The analysis also gives the internal rate of
return for the project, debt service coverage ratio and the rate
of return on the equity. The sensitivity analysis included in the
financial analysis gives the scenario with the variation in the
electricity unit price and the fuel price.
The financial viability of the project is based out on
certain assumptions. The Table A of this chapter and subsequent
pages of this chapter gives the Basis for the Financial Analysis
and the assumptions.
Mode of Financing
The total project cost without the interest during
construction and working capital margin is estimated to be
Rs.2328.00 Lakhs as given in the Table A of previous chapter.
Since the project fulfills all the norms set by the Ministry of
Non-Conventional Energy Sources of Government of India, it is
expected that the project will get the eligible subsidy of
Rs.281.32 Lakhs.
The difference between the project cost of Rs.2328.00 Lakhs
and subsidy of Rs.281.32 Lakhs, is equal to the Rs.2046.68 Lakhs,
Rs. 1023.34 Lakhs will be brought in as equity for project.
Balance Rs. 1023.34 Lakhs will be mobilized as long term loans
from financial institutions.
Based on the above pattern of investment the interest during
construction is calculated to be Rs.102.40 Lakhs as given in the
Table D of previous chapter. This IDC as well as provision for
working capital margin Rs. 38.60 Lakhs will be taken as long
term loans and capitalized.
The total long term loans including the IDC and the working
capital margin works out to be Rs.1164.34 Lakhs. It is assumed
that this loan amount will be repaid in Six (6) equal
installments and there will be an initial moratorium of Two(2)
years on the loan repayment. An interest rate of 17.5 % is
considered on the term loans, and it is assumed that the interest
payment and the loan repayment will be half yearly, and the Table
B of this chapter gives the details.
The project envisages no foreign exchange out flow from
PAIL, since all the equipment are assumed to be bought from
indigenous suppliers.
Plant Operation
PAIL’s Co-generation plant is planned to be operated during
cane crushing season, (on an average 180 days in a year) with the
bagasse generated in the sugar plant.
Saleable Electricity
The Gross generation of power in the plant will be 20.30 MW.
Out of this 8.21 MW will be consumed by sugar plant and another
0.89 MW will be consumed by the Co-generation plant auxiliaries.
This leaves a surplus power of 11.20 MW for export.
This exportable power, with a plant capacity utilization of
90% and with 2.0 % for wheeling and banking , gives a seasonal
energy sales of 39.92 Million KWh of electricity over the season
period of 180 days
The power generated could be sold to HSEB or to any third
party, and HSEB may permit third party sales through their grid.
In the analysis wheeling and banking charge of 2.0 % of the
power exported, applicable for sales to HSEB, is considered.
Unit Price of Electricity
The Ministry of Non-Conventional Energy Sources, have
recommended a price of Rs. 2.25 per KWh. However many SEB`s have
not yet implemented this recommendation. It is however expected
that HSEB will also follow this recommendation.
Barter Arrangement For Fuel
The co-generation project will run only with the bagasse and
the sugar plant needs of power and steam for its operation. For
the PAIL`s co-generation plant it is assumed that the sugar plant
will supply all the steam and the power require for the sugar
plant. Since the sugar plant generally saves bagasse after
meeting its power and steam requirements, it was decided to
extent the barter arrangement only to extent of power and steam
require by the sugar plant. The surplus bagasse, defined as the
bagasse that could have been saved if the sugar plant had just
produced the power and steam for its requirements, is charged to
the co-generation plant at the market rate of Rs. 250/- per ton.
The surplus bagasse quantum works out to 59400 Tonne per season.
Operation And Maintenance Cost
The operation and maintenance cost for the project includes
the salaries and wages for the operating and maintenance staff,
repairs and maintenance and general plant expenses towards the
operation of the plant. An operation and maintenance expense of
2.5% of the total work cost is considered in the financial
analysis.
Administration & Overheads
The cost included under this head is 0.32 % of the total
works cost. This considers the general administrative expenses,
plant over heads and the expenses towards selling of power.
Selling Expenses
This cost is 0.75 % of the revenue earned by selling energy
to the grid. This cost comes out to about Rs. 6.7 Lakhs.
Utilities Cost
This included the cost of water, chemicals, oil, lubricants
and other consumables used in the plant. This cost is 1.3 % of
the revenue earned by selling energy to the grid. This cost comes
out to about Rs. 11.80 Lakhs.
Taxes On Generation And Sales
No expenses under this head is considered since this is not
applicable.
Escalation Provision For Various Costs And Expenses
The cost of Fuel, Energy, utilities and the expenses towards
Administration, O & M, selling etc. considered in the analysis
are expected to increase over the years, and the escalation
considered for the various items are given in Table A of this
chapter.
Depreciation
The Depreciation applicable for the co-generation plant is
the same as that applicable for other power generation plants.
Based on the latest guidelines and the applicable depreciation
for this category of plant and equipment is 5 % on the straight
line basis. The depreciation applicable to buildings is 3.46 %.
Since the building cost component of the total Co-generation
project cost is very marginal, a uniform depreciation rate of 5 %
is applied to the total installed project cost.
Generation Cost
The Table C gives the cost of generation of electricity at
the grid per KWh, for ten (10) years operation from plant
commissioning , based on a net energy sale of 39.92 Million KWHr.
No derating of the plant capacity is required over the ten years
period. The cost of generation of the saleable electrical energy
at the grid works out to around Rs. 1.16 per KWHr. This figure
varies between Rs. 1.41 and Rs 0.90 during the ten years period.
Sales And Profitability Statement
Table D gives the details of the sales and profitability. No
provision is made for Income Tax in the analysis of the
profitably, since the G.O.I. has given a five years tax holiday
for private sector power generation, and also the Factory is in
the co-operative sector. The operating profit increases
progressively over the succeeding years, as the interest charges
on term loans are progressively declining starting with Rs.
457.84 Lakhs in the first year of commercial operation, the
profit changes to Rs. 414.03 Lakhs at the end of tenth year of
operation.
Cash Flow
The details of the estimated cash flow generated by the
project operation over a period of ten years is given in table E.
After the re-payment of all the term loans, at the end of the
tenth year, there is a net cumulative surplus cash of Rs.2943.65
Lakhs. It may be seen from the statement, that the term loan re-
payment starts in the third year and ends in the eighth year.
IRR, DSCR And Break-even
Table F gives the working of project Internal Rate of Return
(IRR) and The Debet Service Coverage Ratio (DSCR). The project
IRR works out to 21.92 %, and the average DSCR over the ten years
periods works out to 2.504. The DSCR which is around 3.24 in the
initial two years comes down as the loan re-payments starts in
the third year, and again gradually increases as the interest
burden comes down over the years. The project gives a rate of
return of 44.74 % on the equity, based on the operating profit.
Table G gives the break even analysis. The break even capacity
works out to 54.30 % based on the estimated working results of
the second year of operation.
Table ABASIS FOR FINANCIAL ANALYSIS
Page 1 of 3
-------------------------------------------------------S.No. Description Unit Quantity-------------------------------------------------------
1. Installed Project Cost Rs. Lakhs 2469.00
2. Subsidy From G.O.I. Rs. Lakhs 281.32
3. Equity From PAIL Rs. Lakhs 1023.34
4. Term Loan
- Long term loan Rs. Lakhs 1164.34- Loan for working Rs. Lakhs 0.00
capital
5. Number Of Season Days 180
6. Project Schedule Months 18
7. Gross Power Generation KW 20300.00
8. In-house Consumption For KW 8210.00 Sugar Plant
9. In-house Consumption For KW 890.00 Co-generation Plant
10. Net Exportable Power KW 11200.00 To Grid
11. Plant Capacity % 90.0Utilization
12. Wheeling and Banking % 2.0
13. Seasonal Energy Supply MKWHr 39.92To Grid
14. Surplus Bagasse Used Tonne/Yr 59400
Page 2 of 3-------------------------------------------------------S.No. Description Unit Quantity-------------------------------------------------------
15. Sale Price Of Energy Rs./KWHr 2.25#
16. Sale Price Of Bagasse Rs./Tonne 250.00#
17. Opern. & Maint. Cost Rs. Lakhs 61.70#
18. Admin. & Overheads Rs. Lakhs 7.90#
19. Selling Expenses Rs. Lakhs 6.70#
20. Utility Cost Rs. Lakhs 11.80#
21. Taxes On Generation Rs. Lakhs 0.00And Sales
22. Moratorium In Loan Years 2Repayment
23. Term Loan Repayment Years 6Period
24. Interest Rate On Term % 17.50Loan
25. Project Cost Apportionment 0.00To Sugar Plant
Page 3 of 3-------------------------------------------------------S.No. Description Unit Quantity-------------------------------------------------------
26. Annual Cost Escalation On % 0.00Fuel
27. Annual Cost Escalation On % 0.00Opern. & Maint.
28. Annual Cost Escalation On % 0.00Admin. & Selling
29. Annual Cost Escalation On % 0.00Utilities
30. Annual Cost Escalation On % 0.00Energy
-------------------------------------------------------Note :
# Figures thus identified are at the time of start of the project
Table - BWork Sheet for Interest Payment and Loan Repayment
All payments are made half yearly and all rupees are in Lakhs.
Loan Amount : 1164.34Moratorium : 2
Interest(%) : 17.5 % Repayment Period : 6
Yr
1
1
2
2
3
3
4
4
5
5
6
6
7
7
8
8
9
9
Half year
1
2
1
2
1
2
1
2
1
2
1
2
1
2
1
2
1
2
Loan payment
0.00
0.00
0.00
0.00
97.03
97.03
97.03
97.03
97.03
97.03
97.03
97.03
97.03
97.03
97.03
97.03
0.00
0.00
Out StLoan
1164.34
1164.34
1164.34
1164.34
1067.31
970.28
873.25
776.22
679.19
582.16
485.13 388.10
291.07
194.04
97.01
0.02
Interest
101.88
101.88
101.88
101.88
101.88
93.40
84.90
76.41
67.92
59.43
50.94
42.45
33.96
25.47
16.98
8.49
0.00
0.00
Total Half .Repay.
101.88
101.88
101.88
101.88
198.91
190.43
181.93
173.44
164.95
156.46
147.97
139.48
130.99
122.50
114.01
105.52
Yr. Loanrepayment
__
0.00
__
0.00
__
194.06 __
194.06
__
194.06
__
194.06 __
194.06
__
194.06
__
0.00
Yr. Inst.
__
203.76
__
203.76
__
195.28
__
161.31
__
127.35
__
93.39
__
59.43
__
25.97
__ 0.00
Table G
BREAK-EVEN ANALYSIS
Analysis For The Second Year Of Operation-----------------------------------------
1. Sales Realization Rs. Lakhs : 898.20
2. Variable Costs ---------------
a. Fuel Cost Rs. Lakhs : 148.50
b. Utilities Cost Rs. Lakhs : 11.80
c. Selling Expenses Rs. Lakhs : 6.80
d. Total Variable Cost Rs. Lakhs : 167.00
3. Contribution Rs. Lakhs : 731.20
4. Fixed Costs ---------------
a. Opern.& Maint.Cost Rs. Lakhs : 61.70
b. Admin.& Overheads Rs. Lakhs : 7.90
c. Interest On Term Rs. Lakhs : 203.80Loan
d. Depreciation Rs. Lakhs : 123.40
e. Total Fixed Cost Rs. Lakhs : 396.80
5. BREAK-EVEN CAPACITY : 54.30%-------------------------------------------------------