Doug Thiessen, P.E. Managing Director of Engineering
description
Transcript of Doug Thiessen, P.E. Managing Director of Engineering
Doug Thiessen, P.E.Managing Director of Engineering
Update on the Port of Long Beach
ACEC LAJanuary 15, 2014
Port of Long BeachPremier gateway for U.S-Asia
trade, major Southern California economic engine
Who We Are• 3,500 acres of land• 4,600 acres of
water• 6 container
terminals• 66 Ship-to-Shore
cranes• 76-foot-deep main
channel• 2nd busiest U.S.
container cargo seaport
• Part of the world’s 9th busiest port complex
Diverse Cargo3,500-acre Port moves
cars, crude oil, petroleum coke,
lumber and container cargoes.
Big Ship Ready
7,100 TEU1996
1997 8,100 TEU
15,500 TEU2006
18,000 TEU2013
Largest to Call North America
14,000-TEU MSC Corte Real came in October 2013 – too wide to pass
through the expanded Panama Canal.
Investing in the FuturePort has begun a $4 billion upgrade of facilities to stay competitive
Current Major Programs• Pier G Redevelopment• Middle Harbor
Redevelopment• Gerald Desmond Bridge
Replacement• On-and Near-Dock Rail• Shore-to-Ship Power• Fire Protection Program
Middle Harbor$1.2 billion facility will be one of the most technologically advanced terminals in the world.
Middle HarborPhase 1 Currently Underway
Phase 2
Phase 2 Phase 1
Phase 1
Middle Harbor Redevelopment
305-acre facility under construction in two
phases.
Middle Harbor RedevelopmentPhase 1- $779.3 Million• 10 construction projects• Third-party utility
improvements/relocationsPhase 2- $449.7 Million• 9 construction projects• Third-party utility
improvements/relocations
Gerald Desmond Bridge Replacement$1.3 billion cable-stay bridge; $650 million design-build contract awarded to Shimmick, FCC & Impregilo on July 2012.
Pre-ConstructionPreliminary engineering
complete, two-thirds through Right-of-Way
work.
Future Opportunity Demolition of Existing Bridge
On & Near Dock Rail Improvements
Ocean Blvd. Track Realignment
Middle Harbor On-Dock Rail
*Future project
Pier G SouthRail Yard*
Pier B On-Dock Rail
Support Facility*
Shore Power ProjectsPort is reducing air quality impacts through the Clean Air Action Plan. The state has enacted a regulation requiring shore power in 2014.
Major EffortSimultaneous construction at
all container terminals and 12 berths
Project Budget
Actual Cost to Date
Estimated Final Cost
Pier A $19.4 million $16.3 million $18.3 million
Pier G $17.9 million $13.9 million $16.5 million
Pier J $56.1 million $43.2 million $49.9 million
Pier T $33.6 million $24.1 million $31.1 million
Total $127 million $97.5 million $115.8 million
Project Budgets
Fire-Protection Program• New Fireboats for Station 15 & 20• Fireboat Station 15 Replacement
Project• Fireboat Station 20 Replacement
Project (Site Selection Underway)
New FireboatTwo fireboats under construction in Seattle
Upcoming Consultant OpportunitiesConstruction Management Division:• CM Services – Pier G Redevelopment
(under evaluation)• On-Call, Inspection & Material Testing
(under evaluation)• As-Needed Hydrographic Services • (under evaluation)• CM Services – New Fire Stations, 2014• On-Call Construction Mgmt. Services,
2014Other Engineering Divisions:• On-Call Cost Estimating Services,
2014
Upcoming Contractor Opportunities(Next 12 months)• Pier C, Upgrade of Water Facilities, 2013• Berths F209 Chemoil Facility Improvements,
2013• NRG Facilities Relocation/Demolition, 2013• Harbor Scenic Water Valve Replacement,
2013• Pier F, Cut-off Wall & Pavement Rehab., 2013• Edison Avenue Street Improvement, 2014• Pier J, Bike & Pedestrian Path, 2014
The Future is BigWe face big challenges, but we see
big opportunities that will bring a promising future to the Port of Long
Beach