Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2...

24
1 passqw Doncaster Council Permit Scheme Evaluation 2015-2018

Transcript of Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2...

Page 1: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

1

passqw

Doncaster Council

Permit Scheme Evaluation 2015-2018

Page 2: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

2

Table of Contents

1 Executive Summary 3

2 Introduction 3

3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC 4

4 Fee Structure 4

5 Cost and Benefits 5

6 Evaluation of Scheme 6

6.1 PIs 6

6.2 HAUC England KPIs 6

6.3 Authority Measures 6

7 Performance Indicators 7

7.1 PI1 The Number of Permit and Permit Variations Applications 7

7.2 PI2 and PI3 The number of permit applications granted and the number of permit applications refused

8

7.3 PI3 The Number of Approved Revised Durations 8

7.4 PI4 The Number of Occurrences of Reducing the Application Period 9

8 HAUC England KPI Measures 10

8.1 TPI1 – Works Phases Started (Base Data) 10

8.2 TPI2 – Works Phases Completed (Base Data) 12

8.3 TPI3 – Days of Occupancy Phases Completed 13

8.4 TPI4 – Average Duration of Works 14

8.5 TPI5 – Works Phases Completed After The Reasonable Period 16

8.6 TP16 – Number of deemed permit applications (not included under Geoplace Figures)

17

8.7 TPI7 – Number of Phase One Permanent Registrations 18

9 Authority Measures 19

9.1 AM 1 – Average duration of works by permit type 19

9.2 AM2 – Inspections 20

9.3 AM 3 – Days of Disruption Saved/Number of collaborative works 20

9.4 AM 4 – Response Code – Broken Down by Promoter 21

9.5 AM 5 – FPNs (Permit Breaches) 21

9.6 AM 6 – Levels of Customer Enquires 23

10 Conclusion 23

10.1 Conclusions 23

10.2 Recommendations 24

Page 3: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

3

1. Executive Summary

The Yorkshire Common Permit Scheme (YCPS) commenced operation on the 12th June 2012 in six

authority areas, Barnsley, Doncaster, Kirklees, Leeds, Rotherham and Sheffield. Three further

authorities, Bradford, Calderdale, and Wakefield (Tranche 2) commenced operation of the scheme

on 31st March 2015.

The scheme focuses attention on the strategically sensitive highway networks with the New Roads &

Street Works Act noticing rules apply on the rest of the highway network.

The report evaluates the progress of the permit scheme in meeting both the stated objectives and

parity of treatment of both works for road purposes and utility street works. In both respects the

scheme is already demonstrating successful outcomes.

The main objectives of the Scheme were to minimise delay and reduce disruption arising from works

on the highway, and to demonstrate parity of treatment amongst all works promoters.

A total of 2269 permit applications have been received for highway authority works and 14254 for

utility promoters. This equates to a split of 13.73% highway authority and 86.27% utility promoters,

with Doncaster Councils refusal rate at 17.19% and Utility refusals rate at 23.37%.

Overall the performance of the Scheme during the review period has demonstrated that it is

meeting the objectives of the scheme. The scheme has allowed the authority the tools and

resources to effectively coordinate the highway network and reduce both the number of days of

highway occupation together with the amount of disruption caused by street works and road works.

2. Introduction

The Traffic management Act 2004 (TMA), Part 3 Sections 32 to 39, and the Traffic Management

Permit Scheme (England) Regulations 2007 make provision for Permit Schemes to be introduced in

England. The Yorkshire Common Permit Scheme came into effect in Doncaster Council on 12th June

2012, and was revised in accordance with the 2015 Amendment Regulations.

This report is the ‘Year 6’ evaluation of the operation of the Permit Scheme in the Doncaster Council

area. The time period covered by this report is 12 June 2015 to 11th June 2018. A number of the

reports included are produced on a monthly or quarterly basis, and so in these instances the

reporting period has been extended to include 2015 Q1 (April to June) to 2018 Q1 (April to June.)

The additional data will have minimal impact on the results.

Under the YCPS, registerable activities on roads that are reinstatement category 0, 1 or 2, or on

category 3 or 4 streets that are traffic-sensitive, require a permit; activities on other streets continue

to follow the NRSWA ‘notification system’ and are outside of the scope of the YCPS.

Page 4: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

4

3. Objectives of the Yorkshire Common Permit Scheme for Doncaster Council

The objectives of the Permit Scheme for Doncaster Council are set out in a ‘Supplementary

Information’ document which can be found on the council’s website.

The objectives in summary are:

Minimizing delay and reducing disruption to road users arising from road and street works

activity.

Ensuring parity between promoters of street works and works for road purposes.

To protect the structure of the street and the integrity of apparatus in it.

To encourage proactive rather than reactive attitudes to activities by promoters.

To ensure safety for those using, living or working on the street, including those engaged in

activities controlled by the Permit Scheme.

To improve activity planning by all promoters.

To help improve public transport efficiencies.

To reduce the disruption caused by street and road works and to improve journey time

reliability.

To encourage works promoters to develop innovative working practices to reduce the time

and road space their works require so that the disruption the cause is reduced to a

minimum.

4. Fee Structure

The Traffic Management Permit Scheme (England) (Amendment) Regulations 2015 require that the

permit authority shall give consideration to whether the fee structure needs to be changed in light of

any surplus or deficit;

Doncaster Council is committed to undertake an annual review of the permit fees, and make any

necessary adjustments to the subsequent years fees. Since the commencement of the scheme, no

adjustments to the fee levels have been made.

The permit fees for Doncaster Council and Department for Transport (DfT) Maximum fee levels are

set out in Table 1 Below:

Road Category 0 -2 or Traffic-sensitive

Doncaster Borough

Council Permit Fee

Maximum allowable fee

(DfT)

Provisional

Advance

Authorisation

£91 £105

Page 5: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

5

Major works –

over 10 days

and all major

works

requiring a

traffic

regulation

order.

£211 £240

Major works –

4 to 10 days.

£109 £130

Major works –

up to 3 days

£64 £65

Standard

activity permit

£109 £130

Minor activity

permit

£64 £65

Immediate

activity permit

£59 £60

Table 1 - Fee Levels

5. Cost and Benefits

Based upon this evaluation of the sixth full year of operation of the YCPS, Doncaster Council does

not propose to increase or reduce its current level of permit fees.

The last 3 years have seen a relatively stable income over expenditure leaving a rolling excess

balance of £3191.24 over the full 6 year period of scheme operation. This balance will be closely

monitored over the next year to evaluate if the fee levels remain fit for purpose.

The Traffic Management Permit Scheme (England) (Amendment) Regulations 2015 require that the

permit authority also shall give consideration to whether the permit scheme is meeting key

performance indicators where these are set out in the Guidance. This report contains performance

indicators and authority measures to which Doncaster Council has provided data to evidence that

the authority is meeting key performance indicators and the objectives as set out in the YCPS.

Page 6: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

6

6. Evaluation of the Scheme

The Statutory Guidance for Highway Authority Permit Schemes October 2015 states that (Regulation

16A) authorities must evaluate their permit scheme every 12 months of operation for the first 3

years of operation and then every 3 years thereafter.

This report is the fourth evaluation covering years four to six of the scheme and is specific to

Doncaster Borough Council, it evaluates the progress of the permit scheme in meeting the objectives

and parity of treatment for both street works promoters and works for road purposes.

This evaluation report includes details of scheme-specific performance indicators (PI’s), HAUC

England KPIs, and additional authority measures (AMs) that reflect the business case and objectives

put forward in the scheme submission documentation.

6.1 Scheme Specific Performance Indicators

PI1 The number of permit and permit variation applications received, the number of

granted and the number refused; excluding any applications that are subsequently

withdrawn; broken down by promoter.

PI2 The number of permit applications granted as a percentage of the total applications

made.

PI3 The number of permit applications refused as a percentage of the total applications

made.

6.2 HAUC (England) Key Performance Indicators

The HAUC (England) KPIs are set out in Annex A to the Statutory Guidance for Permit Street Schemes

(October 2015), and are based upon the TMA Performance Indicators (TPIs) collated by Geoplace.

The HAUC (England) KPIs included in this evaluation report are:

TPI 1 Works Phases Started

TPI 2 Works Phases Completed

TPI 3 Days of Occupancy Phases Completed

TPI 4 Average Duration of Works

TPI 5 Works Phases Completed after the reasonable period.

TPI 6 Number of Phase One Permanent Registrations.

TPI 7 Number of Phase One Permanent Registrations

6.3 Authority Measures

AM 1 Average Duration of Works by Permit Type

AM 2 Permit Compliance Inspections

AM2 Days of Disruption Saved / Number of Collaborative Works

AM4 Response Code – Broken Down by Promoter

AM5 FPNs (Permit Breaches)

Page 7: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

7

7. Performance Indicators

7.1 PI1 The number of permits and permit variation applications

This performance indicator lists;

The total number of permits and permit variation applications received,

The number of applications granted as a percentage of the total applications made

The number of applications refused as a percentage of the total applications made

The table below shows a breakdown of permit applications received granted and refused for the 4th

to 6th year of operation in Doncaster.

7.1.1 Results

Works Promoter Granted % Granted Refused % Refused Total

Cadent Gas 1692 84.10% 320 15.90% 2012

Highway England 3 100.00% 0 0.00% 3

BT 2015 76.35% 624 23.65% 2639

Doncaster 1879 82.81% 390 17.19% 2269

NPG 1894 88.46% 247 11.54% 2141

Western Power 4 80.00% 1 20.00% 5

National Grid Electric 9 90.00% 1 10.00% 10

Vodafone 6 100.00% 0 0.00% 6

Network Rail 359 95.99% 15 4.01% 374

Virgin Media 1260 80.25% 310 19.75% 1570

O2 38 92.68% 3 7.32% 41

Century Link UK 5 71.43% 2 28.57% 7

Romec 3 100.00% 0 0.00% 3

GTC 29 93.55% 2 6.45% 31

Orange 21 95.45% 1 4.55% 22

Zayo 3 100.00% 0 0.00% 3

T-Mobile 34 87.18% 5 12.82% 39

ES Pipelines 1 100.00% 0 0.00% 1

Northern Gas Networks

168 82.76% 35 17.24% 203

Fulcrum Pipelines 22 61.11% 14 38.89% 36

GEO 5 55.56% 4 44.44% 9

City Fibre 5 100.00% 0 0.00% 5

Harlaxton 42 85.71% 7 14.29% 49

Anglian Water 4 57.14% 3 42.86% 7

Severn Trent Ltd 79 84.04% 15 15.96% 94

Yorkshire Water 3122 64.48% 1720 35.52% 4842

Page 8: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

8

South Yorkshire PTE 100 98.04% 2 1.96% 102

Totals 12802 77.48% 3721 22.52% 16523

Table 2 - Permits Granted / Refused

7.1.2 Analysis

The following consideration must be noted in relation to this data; each application has an

appropriate response period which means that the number of applications received in any one

period does not correspond to the permits granted and refused within that same period. In other

words, a permit application received in one period may be responded to within the next period. This

means that there are a number of permit applications where the status cannot be determined.

Table 2 demonstrates that each works promoter’s permit applications are treated on an individual

basis and assessed on the quality of information provided. Each works promoter approaches the

permitting of works differently which can be demonstrated by the variance in the percentage of

applications that are granted or refused.

7.2 PI2 The number of conditions applied by condition type.

Unfortunately the reporting structure required to produce this data is currently not operational.

Doncaster Council is addressing the issue and is hopeful this report will be available for the next

annual review.

7.3 PI3 The Number of approved revised durations.

This will be measures by promoter and shown as:

The total number of permits granted

The number of requests for revised durations shown as a percentage of permits issued

The number of agreed revised durations as a percentage of revised durations applied for

7.3.1 Results

Organisation Total Total Total %

Sent Rejected Rejected

Cadent Gas 184 7 3.80%

Highways England 0 0 NA

BT 98 1 1.02%

Cable & Wireless 0 0 NA

Doncaster 211 0 0.00%

Northern Powergrid 173 4 2.31%

Western Power Distribution 0 0 NA

National Grid Electric 0 0 NA

Vodafone 0 0 NA

Kingston Communications 0 0 NA

Network Rail 13 0 0.00%

Page 9: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

9

Virgin Media 20 1 5.00%

Telefonica O2 0 0 NA

Century Link 3 0 0.00%

Dept for Transport 0 0 NA

Independent Pipelines 0 0 NA

Romec 0 0 NA

Arqiva 1 0 0.00%

GTC 6 1 16.67%

Orange 0 0 NA

Zayo 0 0 NA

Tycom 0 0 NA

T-Mobile 2 0 0.00%

ES Pipelines 0 0 NA

Energetics Elec 6 0 0.00%

Northern Gas Networks 7 0 0.00%

Fulcrum Pipelines 4 1 25.00%

GEO 0 0 NA

ESP Elec 0 0 NA

Energetics Gas 0 0 NA

H2O Networks 0 0 NA

Thales UK 0 0 NA

City Fibre 0 0 NA

Harlaxton Energy Networks 11 0 0.00%

Arqiva Ltd 0 0 NA

Anglian Water 0 0 NA

Severn Trent Water 5 0 0.00%

Yorkshire Water 162 4 2.47%

South Yorkshire PTE 0 0 NA

Totals 906 19 2.10% Table 3 - The Number of Approved Revised Durations

7.4 P14 The number of occurrences of reducing the application period

The number of permit applications granted and refused as a percentage of the total applications

made is shown in Table 4. The information shows a comparison of the numbers granted and refused

for the Doncaster Councils own works compared to the number granted and refused for other works

promoters. In additions to this data the table also shows the number and percentage of early start

requests along with early start requests that were not agreed, split between Doncaster Councils own

works and other works promoters.

6.4.1 Results

Description Authority Percentage Utilities Percentage

Permits / Variations Granted 1879 82.81% 10923 76.63%

Permits / Variations Refused 390 17.19% 3331 23.37%

Total Variations Summary 2269 13.73% 14254 86.27%

Number of Early Start Requests 445 36.75% 766 63.25%

Page 10: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

10

Number of Early Starts with Agreement

89 37.08% 151 62.92%

Table 4 - Permits Granted & Refused

6.4.2 Analysis

This Measure was considered to be in relation to the number of times promoters were allowed by

Doncaster Council to start their works without having to comply with the minimum permit

application lead-in period, commonly known as an early start agreement.

The YCPS provides a framework for Doncaster Council to treat all activates and activity promoters

covered by the scheme on an equal basis. The above data shows that largely to be the case. Early

start requests are considered individually on their own merits by Doncaster Council and are never

refused without a valid reason.

Table 4 displays that a total of 2269 permit applications have been received for highway authority

works and 14254 for utility promoters. This equates to a split of 13.73% highway authority and

86.27% utility promoters. A higher percentage of utility works applications (23.37%) are refused or

modified in comparison with highway authority works (17.19%).

The percentage refusal rate has decreased significantly since the previous report which showed

Doncaster Councils refusal rate at 17.19% and Utility refusals at 23.37%. This is mainly due to the

increase in discussions prior to the permit being submitted and better co-ordination of works.

Another reason behind the drop in refusals can be attributed to the adoption of the HAUC (England)

advice note on Standard Response Codes which is helping deliver a consistent approach nationally.

8. HAUC England KPI Measures

This section outlines the Permit Indicators (KPI) contained as Annex A within the Statutory Guidance

for Highway Authority Permit Schemes.

These indicators for permit schemes are additional to the general TMA Performance Indicators (TPIs)

which are already being produced.

8.1 TPI1 – Works Phases Started (Base Data)

Quarter Minor Standard Major Immediate Urgent

Immediate Emergency

Total

2015-16 Q1 298 94 68 97 17 574

2015-16 Q2 286 66 68 122 17 559

2015-16 Q3 294 71 34 121 32 552

2015-16 Q4 266 102 64 169 43 644

2016-17 Q1 296 90 63 125 15 589

2016-17 Q2 235 46 45 116 28 470

2016-17 Q3 242 66 25 108 27 468

2016-17 Q4 309 81 45 125 35 595

Page 11: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

11

2017-18 Q1 365 113 67 116 31 692

2017-18 Q2 363 113 59 113 34 682

2017-18 Q3 322 83 37 156 37 635

2017-18 Q4 266 102 64 169 43 644

2018-19 Q1 307 65 76 176 30 654

Total 0 0 0 0 0 0 Table 5 - Works Phases Started

Figure 1 - Phases Started by Works Category

The data demonstrates overall volumes of works across all works categories have remained at a

consistent level throughout the 3 year evaluation period, with the biggest swing evidenced within

the volume of minor works taking place on the network between Q2 2016-17 and Q2 2017-18 of

over 100 additional phases started. Since that peak levels have remained relatively stable.

Page 12: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

12

Figure 2 - Total Number of Works Phases Started

The number of total works phases started on Doncasters Highway Network has seen an increase in

volume since Q3 2016-17 which is due to an increase in major works renew and new build schemes

carried out by Virgin Media and Cadent Gas.

8.2 TPI2 – Works Phases Completed (Base Data)

Quarter Minor Standard Major Immediate Urgent

Immediate Emergency

Total

2015-16 Q1 318 91 51 98 15 573

2015-16 Q2 292 73 79 119 16 579

2015-16 Q3 314 72 51 119 34 590

2015-16 Q4 266 100 60 171 42 639

2016-17 Q1 299 93 59 130 14 595

2016-17 Q2 235 54 43 114 27 473

2016-17 Q3 241 66 30 109 28 474

2016-17 Q4 309 80 40 123 34 586

2017-18 Q1 363 115 66 112 32 688

2017-18 Q2 366 107 58 118 37 686

2017-18 Q3 334 91 46 152 36 659

2017-18 Q4 266 100 60 171 42 639

2018-19 Q1 303 66 63 179 29 640

Total Table 6 - Works Phases Completed

0

100

200

300

400

500

600

700

800N

um

be

r o

f W

ork

s P

has

es

Quarter

Total Number of Works Phases Started

Page 13: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

13

Figure 3- Number of Phases Completed

A slight uptrend in the volume of phases completed has been identified which is predominately

following the same trend as the volume of phases started. The figures for phases completed are

slightly higher than the figures for phases started which may be attributed to the on-going work

Doncaster Councils is carrying out with all works promoters to correctly close down historic works.

8.3 TPI3 – Days of Occupancy Phases Completed

Quarter Minor Standard Major Immediate Urgent

Immediate Emergency

Total

2015-16 Q1 1533 1009 1961 1036 625 6164

2015-16 Q2 1469 1146 2020 511 1246 6392

2015-16 Q3 1303 978 1397 1530 662 5870

2015-16 Q4 1342 1485 1559 1273 567 6226

2016-17 Q1 1366 1079 1350 1572 739 6106

2016-17 Q2 1198 819 43 1579 788 4427

2016-17 Q3 1200 962 1008 879 1640 5689

2016-17 Q4 1549 1007 1254 706 1676 6192

2017-18 Q1 1693 1609 1606 1161 684 6753

2017-18 Q2 1867 1558 1322 1147 481 6375

2017-18 Q3 1635 1288 1336 1023 491 5773

2017-18 Q4 1342 1485 1559 1273 567 6226

2018-19 Q1 1524 1097 1724 1320 561 6226

Total 19021 15522 18139 15010 10727 78419 Table 7 - Days of Occupancy Completed

0

50

100

150

200

250

300

350

4002

01

5-1

6 Q

1

20

15

-16

Q2

20

15

-16

Q3

20

15

-16

Q4

20

16

-17

Q1

20

16

-17

Q2

20

16

-17

Q3

20

16

-17

Q4

20

17

-18

Q1

20

17

-18

Q2

20

17

-18

Q3

20

17

-18

Q4

20

18

-19

Q1

No

. of

Wo

rk P

has

es

Quarter

No. of Phases Completed by Works Category

Minor No.

Standard No.

Major No.

ImmediateUrgent No.

ImmediateEmergencyNo.

Page 14: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

14

Figure 4 - Days of Occupancy Phases Completed

Figure 5 - Total Days of Occupancy

Total days of occupancy have returned to normal levels following an downward swing of 1000 seen

over a full 3 quarter period between 2015 and 2017. The down turn is due to a decrease in works

for road purpose major works scheme within Doncaster.

8.4 TPI4 – Average Duration of Works

0

500

1000

1500

2000

2500

20

15

-16

Q1

20

15

-16

Q2

20

15

-16

Q3

20

15

-16

Q4

20

16

-17

Q1

20

16

-17

Q2

20

16

-17

Q3

20

16

-17

Q4

20

17

-18

Q1

20

17

-18

Q2

20

17

-18

Q3

20

17

-18

Q4

20

18

-19

Q1

No

.of

Day

s

Quarter

Days of Occupancy Phases Completed

Minor Days

Standard Days.

Major Days

Immediate Urgent Days

Immediate Emergency Days.

0

500

1000

1500

2000

2500

3000

3500

4000

4500

5000

Day

s o

f O

ccu

pan

cy

Quarter

Days of Occupancy Total Phases Completed

Page 15: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

15

Quarter Minor Standard Major Immediate Urgent

Immediate Emergency

Total

2015-16 Q1 3.51 7.10 22.71 3.17 4.93 5.77

2015-16 Q2 2.91 12.78 21.61 14.63 3.71 7.19

2015-16 Q3 2.30 7.14 24.14 5.88 3.33 5.19

2015-16 Q4 4.85 8.44 16.80 4.06 4.02 6.27

2016-17 Q1 2.18 7.73 12.17 6.57 3.09 4.34

2016-17 Q2 1.96 9.11 11.56 3.31 22.11 5.12

2016-17 Q3 2.01 7.82 15.47 4.01 5.75 4.35

2016-17 Q4 2.20 6.80 17.63 1.14 20.32 5.34

2017-18 Q1 2.40 9.60 16.88 3.81 12.00 5.67

2017-18 Q2 5.58 11.39 34.76 12.41 3.58 8.29

2017-18 Q3 5.64 8.26 29.31 18.61 3.83 12.27

2017-18 Q4 4.85 8.44 16.80 4.06 4.02 6.27

2018-19 Q1 2.41 10.00 15.44 6.09 3.62 5.56 Table 8- Average Duration of Works

Figure 6 - Average Duration of Works per Category

Page 16: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

16

Figure 7 - Average Duration of Works

The average duration of all works types has remained relatively stable throughout the monitoring

period, with a slight overall rise to the average durations of works since the beginning of the

monitoring period.

8.5 TPI5 – Phases Completed After the Reasonable Period

Quarter Minor Standard Major Immediate Urgent

Immediate Emergency

Average Overall

2015-16 Q1 16 5 4 2 0 27

2015-16 Q2 12 5 4 0 1 22

2015-16 Q3 9 2 2 1 1 15

2015-16 Q4 3 2 1 1 0 7

2016-17 Q1 1 4 0 0 1 6

2016-17 Q2 0 1 0 1 1 3

2016-17 Q3 3 1 1 1 3 9

2016-17 Q4 1 2 3 1 1 8

2017-18 Q1 1 2 3 1 1 8

2017-18 Q2 3 6 1 1 3 14

2017-18 Q3 6 1 1 4 0 12

2017-18 Q4 3 2 1 1 0 7

2018-19 Q1 2 4 0 2 0 8

Total Table 9 - Phases Completed After Reasonable Period

0

2

4

6

8

10

12

14N

o. o

f D

ays

Quarter

Average Duration of Works

Page 17: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

17

Figure 8 - Phases Completed After the Reasonable Period

The total number of phases completed after the reasonable period has significantly reduced over

the monitoring period and maintained a consistent level for the over the last 18 months.

8.6 TPI6 – Number of Deemed Permit Applications

Quarter Minor Standard Major Immediate Urgent

Immediate Emergency

Total

2015-16 Q1 1 0 0 0 0 1

2015-16 Q2 2 0 0 0 0 2

2015-16 Q3 0 0 0 0 0 0

2015-16 Q4 0 0 0 0 0 0

2016-17 Q1 0 0 0 0 0 0

2016-17 Q2 4 0 0 0 1 5

2016-17 Q3 0 2 0 0 0 2

2016-17 Q4 0 0 0 0 0 0

2017-18 Q1 0 0 0 0 0 0

2017-18 Q2 0 2 0 0 0 2

2017-18 Q3 2 2 3 0 2 9

2017-18 Q4 4 0 1 6 0 11

2018-19 Q1 0 3 0 2 0 5

Total 13 9 4 8 3 37 Table 10 - Number of Deemed Permit Applications

The number of deemed permits within the reporting period is very low. Doncaster Council has a

robust procedure for ensuring all permits are processed within prescribed timescales. The primary

reason for deemed permits is unplanned system outages.

0

5

10

15

20

25

30N

o. o

f D

ays

Quarters

Phases Completed After the Reasonable Period

Page 18: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

18

8.7 TPI7 – Number of Phase One Permanent Registrations

Quarter Minor Standard Major Immediate Urgent

Immediate Emergency

Total Overall

2015-16 Q1 171 58 31 85 13 381

2015-16 Q2 185 38 28 93 11 355

2015-16 Q3 144 45 27 101 27 344

2015-16 Q4 134 71 29 136 29 399

2016-17 Q1 171 59 11 121 12 374

2016-17 Q2 126 35 11 20 86 278

2016-17 Q3 107 54 10 91 22 284

2016-17 Q4 158 63 16 107 23 367

2017-18 Q1 243 43 16 91 25 418

2017-18 Q2 224 61 27 98 28 438

2017-18 Q3 191 57 16 113 25 402

2017-18 Q4 134 71 29 136 29 399

2018-19 Q1 174 53 12 140 20 399 Table 11 - Number of Phase One Permanent Registrations

Figure 9- Number of Phase One Permanent Registrations per Category

Page 19: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

19

Figure 10 - Number of Phase One Permanent Registrations

The number of phase one permanent registrations is demonstrating an upward trend with

approximately 58% of all works taking place on Doncaster’s highway network having a phase one

permanent registration within this 3 year monitoring period.

9. Authority Measures

These measures reflect the business case objectives specified in the Permit Scheme submission

documentation.

The following are the complementary measures Doncaster Council has used to reflect the

performance of the scheme.

9.1 AM1 – Average Duration of works by permit type

This measure reports upon the average durations of works by works category.

9.1.1 Results

Quarter Minor Standard Major Immediate Urgent

Immediate Emergency

Total

2015-16 Q1 3.51 7.10 22.71 3.17 4.93 5.77

2015-16 Q2 2.91 12.78 21.61 14.63 3.71 7.19

2015-16 Q3 2.30 7.14 24.14 5.88 3.33 5.19

2015-16 Q4 4.85 8.44 16.80 4.06 4.02 6.27

2016-17 Q1 2.18 7.73 12.17 6.57 3.09 4.34

2016-17 Q2 1.96 9.11 11.56 3.31 22.11 5.12

2016-17 Q3 2.01 7.82 15.47 4.01 5.75 4.35

2016-17 Q4 2.20 6.80 17.63 1.14 20.32 5.34

2017-18 Q1 2.40 9.60 16.88 3.81 12.00 5.67

2017-18 Q2 5.58 11.39 34.76 12.41 3.58 8.29

050

100150200250300350400450500

Nu

mb

er

of

Re

gist

rati

osn

Quarter

Number of Phase One Permanent Registrations

Page 20: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

20

2017-18 Q3 5.64 8.26 29.31 18.61 3.83 12.27

2017-18 Q4 4.85 8.44 16.80 4.06 4.02 6.27

2018-19 Q1 2.41 10.00 15.44 6.09 3.62 5.56

Total 3.29 8.82 17.09 9.29 7.25 Table 12 - Average Duration of Works by Permit Type

9.1.2 Analysis

The average duration of all works types has remained relatively stable throughout the monitoring

period, with a slight rise to the average durations of works since the beginning of the monitoring

period.

9.2 AM2 – Inspections

Number of failed permit compliance inspections (where one or more permit conditions have been

breached).

9.2.1 Results

This information has been collated by Doncaster Council and the chart below shows a breakdown of

the all permit conditions inspections with their outcomes that have taken place during the reporting

period.

Quarter Compliant Non-Compliant

Total % Compliant

2015-16 Q1 17 6 23 74%

2015-16 Q2 13 4 17 76%

2015-16 Q3 12 0 12 100%

2015-16 Q4 11 0 12 92%

2016-17 Q1 3 0 3 100%

2016-17 Q2 4 1 5 80%

2016-17 Q3 11 0 11 100%

2016-17 Q4 11 7 19 58%

2017-18 Q1 25 11 36 69%

2017-18 Q2 7 11 18 39%

2017-18 Q3 42 18 60 70%

2017-18 Q4 154 31 185 83%

2018-19 Q1 69 13 82 84% Table 13 - Inspections

9.2.2 Analysis

Unfortunately the quantity of data collected on this measure is affected by the inspection resourcing

problems experienced by Doncaster Council during the monitoring period which has led to an

inconsistent volume of permit compliance inspections.

9.3 AM3 – Days of Disruption Saved / Number of Collaborative Works

This measure is the number of days of disruption saved by an authority through the various co-

ordination methodology available e.g. collaborative works or challenging initial durations etc.

Page 21: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

21

The authority data of the number of collaborative works and the number of days saved as a result of

collaborative works on the authority road network.

9.3.1 Results

Calendar Days Saved

QTR Total

2015/16 – Q1 5

2015/16 – Q2 8

2015/16 – Q3 0

2015/16 – Q4 2

2016/17 – Q1 1

2016/17 – Q2 1

2016/17 – Q3 1

2016/17 – Q4 7

2017/18 – Q1 2

2017/18 – Q2 0

2017/18 – Q3 3

2017/18 – Q4 1

2018/19 – Q1 3

Total 34 Table 14 - Calendar Days Saved

9.3.2 Analysis

The result produced for this measure is disappointing as a much higher number of days saved was

anticipated. Doncaster Council will address the reasons why this figure is low and implement

operational changes to ensure that all options for collaborative working are explored and record.

9.4 AM4 – Response Code – broken down by promoter

This measure is the number of refusals broken down by response code where this has been used by

the authority.

Unfortunately the reporting structure required to produce this data is currently not operational.

Doncaster Council is addressing the issue and is hopeful this report will be available for the next

annual review.

9.5 AM5 – FPNs (Permit Breaches)

This report shows the number of FPN’s given and not withdrawn for FPN codes 5 (an offence under

s70(6), 6 (an offence under s74(7B), 7 (an offence under s74A(11), 8, (working without a permit) and

9 working in breach of permit conditions).

9.5.1 Results

Page 22: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

22

Works Promoter

20

15

/16

– Q

1

20

15

/16

– Q

2

20

15

/16

– Q

3

20

15

/16

– Q

4

20

16

/17

– Q

1

20

16

/17

– Q

2

20

16

/17

– Q

3

20

16

/17

– Q

4

20

17

/18

– Q

1

20

17

/18

– Q

2

20

17

/18

– Q

3

20

17

/18

– Q

4

20

18

/19

– Q

1

Tota

l

Cadent Gas 1 1 2 7 3 1 4 2 2 3 2 6 7 41

Highways England

0 0 0 0 0 0 0 0 0 0 0 0 0 0

BT 5 6 6 5 5 6 3 10 11 15 11 16 7 106

Cable & Wireless

0 0 0 0 0 0 0 0 0 0 0 0 0 0

Doncaster 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Northern Powergrid

1 2 5 1 2 2 1 4 4 1 1 9 2 35

Western Power

1 0 0 0 0 0 0 0 0 0 0 0 0 1

National Grid Elec

0 0 0 0 0 0 0 0 0 0 0 0 1 1

Vodafone 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Kingston Comms

0 0 0 0 0 0 0 0 0 0 0 0 0 0

Network Rail 7 6 4 4 4 6 7 4 9 0 1 3 0 55

Virgin Media 1 1 1 1 1 1 1 0 1 1 10 4 1 24

Telefonica 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Century Link 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Dept for Transport

0 0 0 0 0 0 0 0 0 0 0 0 0 0

Independent Pipelines

0 0 0 0 0 0 0 0 0 0 0 0 0 0

Romec 0 0 0 0 0 0 0 0 0 0 0 1 0 1

Arqiva 0 0 0 0 0 0 0 0 0 0 0 0 0 0

GTC 1 0 0 0 0 0 0 0 0 0 0 0 0 1

Orange 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Zayo 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Tycom 0 0 0 0 0 0 0 0 0 0 0 0 0 0

T-Mobile 0 0 2 0 0 0 0 0 0 0 0 0 0 2

ES Pipelines 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Energetics Elec

0 0 0 0 0 0 0 0 0 0 0 0 0 0

Northern Gas Networks

3 1 3 0 0 1 0 2 0 0 1 4 1 16

Fulcrum 0 0 0 0 0 0 0 0 0 3 1 0 0 4

GEO 0 0 0 0 0 0 0 1 0 0 0 0 1 2

ESP 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Energetics 0 0 0 0 0 0 0 0 0 0 0 0 0 0

H2O 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Thales 0 0 0 0 0 0 0 0 0 0 0 0 0 0

City Fibre 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Harlaxtons 1 0 0 1 0 0 0 0 0 0 0 1 0 3

Page 23: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

23

Arqiva 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Anglian Water 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Severn Trent 0 0 0 0 0 0 0 0 0 2 0 4 1 7

Yorkshire Water

4 14 3 7 1 14 10 10 12 9 9 12 6 111

South Yorkshire PTE

0 0 0 1 0 0 0 1 0 0 0 1 0 3

All Organisations

25 30 26 27 16 31 26 34 39 34 36 61 27 413

Table 15 - FPN (Permit Breaches)

9.5.2 Analysis

Table 16 demonstrates that relatively few FPN’s have been served for breach of permit conditions

over the 3 year monitoring period. FPN’s were served for a variety of reasons ranging from working

without a permit to not displaying a permit number. No trends have been identified for why BT or

Yorkshire Water has been served over half of the total number of FPN’s served to all works

promoters.

9.6 AM 6 – Levels of Customer Enquires

The number of customer enquires made regarding permit works split between utility works

promoters and Doncaster Council internal; works promoters.

Unfortunately the reporting structure required to produce this data is currently not operational.

Doncaster Council is addressing the issue and is hopeful this report will be available for the next

annual review.

10. Conclusions & Recommendations

10.1 Conclusions

The Yorkshire Common Permit Scheme (Doncaster) has achieved all the objectives of the scheme

during the reporting period.

There is a general increase in the number of permit applications which can be explained by the

increase in immediate activity by Yorkshire Water and the commencement of the Fibre to the

premises project by Virgin Media across the borough.

It was not possible for Doncaster Council to produce performance information on several measures

due to ICT issues. Doncaster Council will be working on a solution to these issues for the next annual

report.

The increased use of Roadworks.org has assisted us assess the impact of works with significant

traffic management and authority variations are often imposed to improve the smooth running of

the network.

Page 24: Doncaster Council Permit Scheme Evaluation 2015 …...2 Table of Contents 1 Executive Summary 3 2 Introduction 3 3 Objectives of the Yorkshire Common Permit Scheme for Doncaster MBC

24

The number of deemed permits continues to be low and demonstrates that the majority of permit

applications are coordinated and accessed on time. Doncaster is committed to actively coordination

all works on the highway network and will continue to ensure all applications are processed within

the allowed timescales.

Early discussions with all works promoters has shown parity and such meetings have helped permit

applications to be granted first time with careful consideration being given to traffic management,

timing and location of works.

10.2 Recommendations

Doncaster Council will:

Continue to adhere to national guidance and advice regarding the operation of permit

schemes

Continue to work closely with all works promoters to prove parity and co-ordinate medium

and long term activities.

Strive to increase the number of collaborative works in the Doncaster area.

Actively engage with all works promoters to ensure the continued effective operation of the

Yorkshire Common Permit Scheme (Doncaster).

Seek to address the number reporting capabilities of Street Works ICT system.

Engage and support the role of the YJAG representative on the HAUC (England) Permit

Forum.

Continue our vision to move to an all street permitting scheme, thus transferring the

benefits already realised as part of this permit scheme onto the whole of the Doncaster

network.