DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries •...

25
Meeting #19 Wednesday 27 November, Seasons Botanic Gardens DOMAIN COMMUNITY REFERENCE GROUP 1

Transcript of DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries •...

Page 1: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

Meeting #19

Wednesday 27 November, Seasons Botanic Gardens

DOMAIN COMMUNITY REFERENCE GROUP

1

Page 2: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

A LOOK BACK AT 2019

2

Page 3: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

3

Page 4: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

ST KILDA ROAD REALIGNMENT

4

Over 13 days:

• 1,390 metres of new tram tracks laid

• 3,400 tonnes of new asphalt laid

• 7,500 cubic metres of ground excavated

• 1,415 cubic metres of concrete poured

• 10,500 tonnes of crushed rock used

• 7,000 cubic metres of concrete and asphalt

demolished

Page 5: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

WORKS UPDATE

5

Page 6: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

ANZAC STATION PROGRAM

6

Look ahead for 2019/20

Page 7: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

CURRENT AND UPCOMING WORKS

• Excavation through the void

• Base slab construction

(Steel fixing and concreting)

• Shed construction

• Diaphragm wall construction

• Tunnel boring machine (TBM)

deliveries

Under the roof slab7

Page 8: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

8

NORTH BOX EXCAVATION

• Excavating through the

void in the station roof

• All material transported

via St Kilda Road

• North box excavation to

be complete in December

Page 9: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

9

NORTH BOX EXCAVATION

Page 10: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

BASE SLAB CONSTRUCTION

10

• Steel fixing currently operating

24/7 under the station roof

• 2 of 6 major concrete pours

completed

• Once complete, tunnelling

team will commence

preparation for the TBM

installation

Page 11: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

BASE SLAB CONSTRUCTION

11

Page 12: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

SHED CONSTRUCTION

12

• Panel installation continuing until

end of the year

• Two gantry cranes now installed

• Internal fit-out works to continue into 2020

Page 13: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

DIAPHRAGM WALL CONSTRUCTION

MIDDLE BOX

13

• First pile completed Friday 22

November

• Piling and D-wall construction to

be completed March 2020

Page 14: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

TBM DELIVERIES

14

• First TBM parts have now been delivered

• Some overnight closures of St Kilda

Road will be required for the remaining

TBM part deliveries. These closures will

all occur between 1am-5am

• Parts will continue to arrive to site until

April 2020

• Preparation work for the TBM assembly

will begin in December

Page 15: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

GROUND CONDITION INVESTIGATIONS

• Boreholes are required at the site of one

of the tunnel cross passages directly

under Toorak Road West

• From 8pm Friday 6 December to 6am

Monday 9 December, Toorak Road West

will be closed to traffic at the corner of

Toorak Road West and Arnold Street

• Works Involve:

• Asphalt cutting

• Non-destructive digging using a vacuum truck

• Drill to bore and take soil samples.

• Backfilling and reinstatement works

• To minimise the duration of the Toorak

Road closure, works will be carried out

24/7

15

Page 16: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

ENVIRONMENT UPDATE

16

Page 17: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

NOISE MONITORING – OOH TBM DELIVERIES

17

• Attended monitoring undertaken for TBM deliveries

• Environmental resource available at night to monitor works post 10pm

Building RIMG Noise Guideline

LAeq – 1 hour

Measured (Night) dB

The Domain

64

58

The Botanica50

Hallmark Apartments52

Domain Hill54

Page 18: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

NOISE MONITORING – OOH TBM DELIVERIES

18

TBM Delivery 25/11 – 2:20am TBM Delivery 25/11– 3:20am

Page 19: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

UPCOMING OOH WORKS

19

• Continuation of TBM deliveries

• Base slab works currently ongoing –

24/7

• TBM assembly works coming up

• Concrete pours associated with middle

box and base slab

Working with tunnels team to review

process and out of hours works required

Page 20: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

ENVIRONMENTAL MONITORING – AIR QUALITY

20

St Kilda Rd Air Quality

(PM10)

St Kilda Rd Air Quality

(PM2.5)

Page 21: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

DOMAIN PRECINCT UPDATE

21

Page 22: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

MAJOR EVENTS

• CYP work with local Council in coordinating

any potential interface between major events

and the Metro Tunnel Project

• In the Domain Precinct this includes events

such as:

o Anzac Day services

o Australian Grand Prix

o Melbourne Marathon

Page 23: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

DOMAIN ROAD POP-UP PARK UPDATE

• Installation of the pop-up park

begins 2 December

• Involves the installation of pre-

fabricated sections

• This is expected to be completed

within two weeks

• Planting will take one week,

following installation

Page 24: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

CHRISTMAS SHUTDOWN

24

• Works finish on 20 December

2019, and return 6 January 2020

• We wish you all a Merry

Christmas, and a happy and

healthy New Year

• See you in 2020!

Page 25: DOMAIN COMMUNITY REFERENCE GROUP · UPCOMING OOH WORKS 19 • Continuation of TBM deliveries • Base slab works currently ongoing – 24/7 • TBM assembly works coming up • Concrete

THANK YOU

25