Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women...

63
Document of The World Bank FOR OFFICIAL USE ONLY Report No: ICR00004261 IMPLEMENTATION COMPLETION AND RESULTS REPORT ON A CREDIT and GRANT IN THE AMOUNT OF SDR 25.9 MILLION (US$ 40 MILLION EQUIVALENT) TO THE Ministry of Finance FOR THE NEPAL: COMMUNITY ACTION FOR NUTRITION PROJECT (SUNAULA HAZAR DIN) ( P125359 ) March 28, 2018 Health, Nutrition & Population Global Practice South Asia Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Transcript of Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women...

Page 1: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

 

Document of 

The World Bank FOR OFFICIAL USE ONLY 

  

Report No: ICR00004261 

  

 

IMPLEMENTATION COMPLETION AND RESULTS REPORT 

ON A 

CREDIT and GRANT  

IN THE AMOUNT OF SDR 25.9 MILLION 

(US$ 40 MILLION EQUIVALENT) 

TO THE 

  Ministry of Finance  

 FOR THE 

NEPAL: COMMUNITY ACTION FOR NUTRITION PROJECT (SUNAULA HAZAR DIN) ( P125359 )  

March 28, 2018  

Health, Nutrition & Population Global Practice 

South Asia Region 

   

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

 

 CURRENCY EQUIVALENTS  

 

(Exchange Rate Effective {Oct31, 2017}) 

 

Currency Unit  =    NPR 

NPR 103.63 =  US$1 

US$  1.40 =  SDR 1  

 FISCAL YEAR 

July 1 ‐ June 30 

                

 

Regional Vice President: Annette Dixon 

Country Director: Qimiao Fan 

Senior Global Practice Director: Timothy Grant Evans 

Practice Manager: E. Gail Richardson 

Task Team Leader(s): Manav Bhattarai 

ICR Main Contributor: Abeyah A. Al‐Omair  

Page 3: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

 

ABBREVIATIONS AND ACRONYMS 

 

  

AAMA  Action Against Malnutrition through Agriculture 

CDD  Community Driven Development 

CPS  Country Partnership Strategy 

DDC  District Development Committee 

DALY  Disability Adjusted Life Year 

DHS  Demographic and Health Survey 

FA  Financing Agreement 

FM  Financial Management 

GoN  Government of Nepal 

ICR  Implementation Completion and Results 

IDA  International Development Association 

IFA  Iron and Folic Acid 

ISN  Interim Strategy Note 

ISR  Implementation Status Report 

M&E  Monitoring and Evaluation 

MAM  Moderately Acute Malnourished 

MOFALD  Ministry of Federal Affairs and Local Development 

MSNP  Multi Sector Nutrition Plan 

MTR  Mid‐Term Review 

NAGA  Nutrition Assessment and Gap Analysis 

NFSSC  Nutrition and Food Security Steering Committee 

NHSP  Nepal Health Sector Program 

NLSS  Nepal Living Standard Survey 

PAD  Project Appraisal Document 

PDO  Project Development Objective 

PM  Procurement Management 

PMT  Project Management Team 

RRA  Rapid Results Approach 

RRI  Rapid Result Initiative  

RRNI  Rapid Results for Nutrition Initiatives 

SAM  Severely Acute Malnourished 

SHD  Sunaula Hazar Din 

SoE  Statement of Expenditures 

SWAp  Sector Wide Approach 

SUN  Scaling Up Nutrition 

UNICEF  United Nations International Children's Emergency Fund 

VDC  Village Development Committee 

WHO  World Health Organization 

   

Page 4: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had
Page 5: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

 

  

  

TABLE OF CONTENTS  

DATA SHEET ................................................................................................................................................................... 1 

I.  PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES .......................................................................................... 6 

A. CONTEXT AT APPRAISAL ................................................................................................................................... 6 

B. SIGNIFICANT CHANGES DURING IMPLEMENTATION (IF APPLICABLE) ........................................................... 11 

II.  OUTCOME ........................................................................................................................................................... 13 

A. RELEVANCE OF PDOs ...................................................................................................................................... 13 

B. ACHIEVEMENT OF PDOs (EFFICACY) ............................................................................................................... 14 

C. EFFICIENCY ...................................................................................................................................................... 19 

D. JUSTIFICATION OF OVERALL OUTCOME RATING............................................................................................ 21 

E. OTHER OUTCOMES AND IMPACTS (IF ANY) .................................................................................................... 21 

III.  KEY FACTORS THAT AFFECTED IMPLEMENTATION AND OUTCOME .................................................................. 22 

A. KEY FACTORS DURING PREPARATION ............................................................................................................ 22 

B. KEY FACTORS DURING IMPLEMENTATION ..................................................................................................... 24 

IV.  BANK PERFORMANCE, COMPLIANCE ISSUES, AND RISK TO DEVELOPMENT OUTCOME ................................... 25 

A. QUALITY OF MONITORING AND EVALUATION (M&E) .................................................................................... 25 

B. ENVIRONMENTAL, SOCIAL, AND FIDUCIARY COMPLIANCE ............................................................................ 27 

C. BANK PERFORMANCE ..................................................................................................................................... 28 

D. RISK TO DEVELOPMENT OUTCOME ............................................................................................................... 30 

V.  LESSONS AND RECOMMENDATIONS .................................................................................................................. 30 

ANNEX 1. RESULTS FRAMEWORK AND KEY OUTPUTS ................................................................................................. 32 

ANNEX 2. BANK LENDING AND IMPLEMENTATION SUPPORT/SUPERVISION ............................................................. 43 

ANNEX 3. PROJECT COST BY CATEGORIES ................................................................................................................... 46 

ANNEX 4. EFFICIENCY ANALYSIS .................................................................................................................................. 47 

ANNEX 5. BORROWER, CO‐FINANCIER AND OTHER PARTNER/STAKEHOLDER COMMENTS ...................................... 49 

ANNEX 6. SUPPORTING DOCUMENTS ......................................................................................................................... 51 

   

Page 6: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had
Page 7: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 1 of 57  

      

       

DATA SHEET 

  

BASIC INFORMATION  Product Information 

Project ID  Project Name 

P125359 Nepal: Community Action for Nutrition Project (Sunaula 

Hazar Din) 

Country  Financing Instrument 

Nepal  Specific Investment Loan 

Original EA Category  Revised EA Category 

Partial Assessment (B)  Partial Assessment (B) 

Organizations 

Borrower  Implementing Agency 

Ministry of Finance  Ministry of Federal Affairs and Local Development 

Project Development Objective (PDO)  Original PDO 

The Development Objective for the Project is to improve attitudes and practices known to improve nutritional outcomes of women of reproductive age and children under the age of 2.  Changes in attitudes and practices would address the key risk factors for child malnutrition and create demand for nutrition related services and products.  The supply of these services and products will be provided through existing public sector and donor‐funded programs, the private sector and, to a limited extent, financed through the Project.  Revised PDO 

The proposed revised PDO is "to improve practices that contribute to reduced under‐nutrition of women of reproductive age andchildren under the age of two and to provide emergency nutrition and sanitation response to vulnerable populations in Earthquakeaffectedareas.”   

Page 8: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 2 of 57  

      

FINANCING 

 

  Original Amount (US$)   Revised Amount (US$)  Actual Disbursed (US$) 

World Bank Financing        IDA‐H7860 

18,000,000  18,000,000  15,803,579 

 IDA‐51370 

22,000,000  17,900,446  15,779,816 

Total    40,000,000  35,900,446  31,583,395 

Non‐World Bank Financing       

Borrower     0     0     0 

Total     0     0     0 

Total Project Cost  40,000,000  35,900,446  31,583,394  

  KEY DATES 

   

Approval  Effectiveness  MTR Review  Original Closing  Actual Closing 

26‐Jun‐2012  24‐Aug‐2012  15‐Feb‐2015  30‐Jun‐2017  30‐Jun‐2017 

   RESTRUCTURING AND/OR ADDITIONAL FINANCING 

 

 

Date(s)  Amount Disbursed (US$M)  Key Revisions 

30‐Jun‐2015  4.86  Change in Project Development Objectives Change in Results Framework Change in Components and Cost Reallocation between Disbursement Categories Change in Disbursements Arrangements Change in Legal Covenants Change in Institutional Arrangements Change in Financial Management Change in Procurement 

  

KEY RATINGS  

 

Outcome  Bank Performance  M&E Quality 

Satisfactory  Satisfactory  Substantial 

 

Page 9: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 3 of 57  

      

RATINGS OF PROJECT PERFORMANCE IN ISRs  

 

No.  Date ISR Archived  DO Rating  IP Rating Actual 

Disbursements (US$M) 

01  14‐Nov‐2012  Satisfactory  Satisfactory  0 

02  19‐Jun‐2013  Moderately Satisfactory  Moderately Satisfactory  2.00 

03  16‐Oct‐2013  Moderately Satisfactory  Moderately Satisfactory  2.00 

04  27‐Mar‐2014 Moderately 

Unsatisfactory Moderately Unsatisfactory  2.04 

05  06‐Aug‐2014 Moderately 

Unsatisfactory Moderately Satisfactory  2.04 

06  27‐Jan‐2015 Moderately 

Unsatisfactory Moderately Unsatisfactory  2.04 

07  15‐Apr‐2015 Moderately 

Unsatisfactory Moderately Unsatisfactory  4.86 

08  09‐Oct‐2015 Moderately 

Unsatisfactory Moderately Unsatisfactory  4.86 

09  24‐Jan‐2016 Moderately 

Unsatisfactory Moderately Satisfactory  12.06 

10  30‐Mar‐2016  Moderately Satisfactory  Moderately Satisfactory  16.65 

11  25‐Sep‐2016  Moderately Satisfactory  Moderately Satisfactory  16.65 

12  23‐Mar‐2017  Moderately Satisfactory  Moderately Satisfactory  27.65 

13  23‐Jun‐2017  Moderately Satisfactory  Moderately Satisfactory  27.65 

 

SECTORS AND THEMES  

 Sectors 

Major Sector/Sector  (%) 

 

Health    36 

Public Administration ‐ Health  7 

Health  29 

 

Page 10: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 4 of 57  

      

 

Social Protection    35 

Social Protection  29 

Public Administration ‐ Social Protection  6 

  

Water, Sanitation and Waste Management    29 

Sanitation  29 

  Themes   

Major Theme/ Theme (Level 2)/ Theme (Level 3)  (%)  Human Development and Gender  76  

Health Systems and Policies  50  

Reproductive and Maternal Health  25   

Child Health  25    

Nutrition and Food Security  26  

Nutrition  13   

Food Security  13  

   Urban and Rural Development  25  

Rural Development  25  

Rural Infrastructure and service delivery  25  

   

ADM STAFF  

Role  At Approval  At ICR 

Regional Vice President:  Isabel M. Guerrero  Annette Dixon 

Country Director:  Ellen A. Goldstein  Qimiao Fan 

Senior Global Practice Director:  Amit Dar  Timothy Grant Evans 

Practice Manager:  Julie McLaughlin  E. Gail Richardson 

Task Team Leader(s):  Albertus Voetberg  Manav Bhattarai 

ICR Contributing Author:    Abeyah A. Al‐Omair 

     

Page 11: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 5 of 57  

      

    

Page 12: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 6 of 57  

      

 

I. PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES 

 

A. CONTEXT AT APPRAISAL  

Context 1. Despite the long period of political instability and transition towards peace, Nepal made significant progress 

on  reducing poverty and hunger. Nepal had gone  through a  long period of political unrest,  insurgency, and violence which lasted more than a decade and resulted in a significant number of deaths and internally displaced persons. The country achieved remarkable progress by halving the percentage of people living on less than $1.25 a day in only seven years, from 53 percent in 2003/2004 to 25 percent in 2010/20111. Nepal Living Standards Surveys  (NLSSs)  II and  III  found  the  incidence of poverty  to have declined by one percentage point per year between 2005 and 20102.   

2. At  the  time  of  project  appraisal  in  2011,  Nepal was  achieving  steady  improvements  in  health  outcomes. Between the period of 1990 and 2011, significant progress had been made to reduce under‐five mortality by 62%, from 142 per thousand live births in 1990 to 54 in 2011, and infant mortality by 54%, from 99 per thousand live births to 46. Similarly, the maternal mortality ratio had decreased by 76%, from 790 per 100,000 live births in 1996 to an estimated 190 in 2011. In 2009, Nepal received a “Child Survival Award” from GAVI Alliance (GAVI) for its outstanding performance in improving child health and immunization (progress in MDG43). Similarly, in 2010, Nepal  received a UN MDG 5 award  for  its outstanding national  leadership,  commitment and progress toward achievement of improved maternity health goal under the MDG‐54,5.  

 

3. Despite remarkable successes in achieving most of the MDGs targets, malnutrition had remained a serious problem for Nepal with deleterious consequences for the human development and overall economy. Nepal ranked in the top 10 countries with the highest prevalence of stunting and was one of the top 20 countries with the highest number of stunted children6. While the stunting rate of under‐five children had dropped from 57% in 2001 to 41% in 2011, Nepal needed to bring down the stunting rate to 30% to meet the MDG target on malnutrition by 20157. Similarly, over the same period, slow progress was made to reduce the ratio of underweight children under‐five (from 43% to 29%), and there was only a slow decline in reducing the proportion of wasted children (from 13% in 2006 to 11% in 2011)8. Nepal Demographic and Health Survey 2011 (DHS) showed that the key nutritional deficiency, anemia, continued to be high; it was recorded as 46% among children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had micronutrient deficiencies.  

                                                                 1 Nepal Country Partnership Strategy FY2014‐2018, World Bank 2014 2 Nepal and the Millennium Development Goals ‐Status Report (2000‐2015). Accessed November 6,2017.   3 http://www.gavi.org/library/news/press‐releases/2009/gavi‐honours‐15‐countries‐for‐excelling‐in‐immunisation‐and‐child‐survival/. Accessed December 14,2017.   4 WHO Country Cooperation Strategy Nepal, 2013‐2017 5 MDG targets are to lower the prevalence of underweight children aged 6‐59 months to 29 and to reduce the proportion of stunted children aged 6‐59 months to 30 by 2015. 6 The State of the World’s Children Report. UNICEF 2009 7 Nepal and the Millennium Development Goals ‐Status Report (2000‐2015). Accessed November 6,2017. 8 Nepal and the Millennium Development Goals ‐Status Report (2000‐2015). Accessed November 6,2017. 9 Nepal Demographic and Health Survey 2011 

Page 13: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 7 of 57  

      

 

4. While the problem of malnutrition was pervasive across the country, there was a wide disparity of nutritional outcomes across economic and geographic strata. Glaring disparities existed between urban and rural dwellers, geographical regions and various social groups. In 2010/2011, the mountains and hills had a higher percentage of poor people than the Terai areas. Similarly, rural10 children were more likely to be underweight (30%) than urban children (17%). Children living in the mountain zone were also more likely to be underweight (36%) than those living in the Terai zone (30%) and the hilly zone (27%)11. Children in food‐secure households had the lowest rates of stunting (33%) while children in food‐insecure households had stunting rates up to 49%12.  

  

5. The Government of Nepal (GON) had several successful engagements with the World Bank to support the health sector, which also included support for nutrition. The first Nepal Health Sector Program (NHSP I, 2004‐2010) was implemented using a Sector Wide Approach (SWAp) and involved donors across the health sector. The project focused  on  expanding  access  and  increasing  utilization  of  essential  health  care  services.  The  project  made significant  improvements  in  key  health  indicators  however,  several  challenges  remained,  especially  for  the underserved  segments  of  the  society.  Therefore,  the  following  engagement  (NHSP  II,  2010‐2015)  was  a continuation of IDA support and followed the same financing modality to enable the GON to increase access to essential health care services and their utilization by the underserved and the poor. While NHSP I and NHSP II focused on improving coverage and access, the current ongoing operation approved in 2016 (Nepal Health Sector Management Reform Program‐for‐Results) focuses on improving efficiency in public resource management of the health sector by financing against the achievement of a set of mutually agreed targets related to financial management, procurement management, use of information systems and citizen engagement13.  

6. Improving nutritional status of children and women has been a top priority for the GoN.   The GoN had been implementing a wide range of programs to  improve the nutrition outcomes  in the country. This  included:  (i) direct  or  nutrition  ‘specific’  programs  such  as  micronutrient  supplements  to  children  and  women  during pregnancy, salt iodization, and behavioral change communication on young children feeding; and (ii) indirect or nutrition ‘sensitive’ programs such as non‐conditional cash and in‐kind transfers, school feeding programs, etc. To  step up  the efforts  to  improve  the nutrition profile  for  the Nepalese people,  the GoN had undertaken  a comprehensive Nutrition Assessment and Gap Analysis (NAGA) in 2010 to provide the synthesis of information necessary  to  accelerate  the  reduction of maternal  and  child malnutrition  in  the  country. NAGA provided an impetus  to  the  development  of  a  multi‐sector  nutrition  plan  (MNSP)  for  FY2013‐2017‐  which  was  being developed at the time of appraisal and provided a multi‐stakeholder, multi‐sectoral platform under the National Planning Commission, the highest planning level authority in the country.   

7. Nepal launched the Sunaula Hazar Din (SHD) – Community Action for Nutrition Project, approved by the Bank in 2012. SHD was the first Bank‐supported standalone nutrition project  in Nepal that focused on improving the nutritional status of women and young children. The project introduced an innovative community‐driven rapid results approach (RRA) in which communities would choose a focus area from a ‘menu’ of 15 different areas with 29  different  goals  relating  to  improved  nutrition  including,  for  instance,  improved  breastfeeding  practices, improved hygiene practices, and continued schooling for girls (The complete list of focus areas and goals is in 

                                                                 10 Nepal is divided into 75 districts distributed across different ecological zones and development regions. The districts are divided into urban (municipalities) and rural (village development committees), VDCs are further divided into wards.   11WHO Country Cooperation Strategy Nepal, WHO 2012. 12 https://www.usaid.gov/what‐we‐do/global‐health/nutrition/countries/nepal‐nutrition‐profile  Accessed December 13,2017 13 The Project Development Objective of the Program‐for‐Results is to improve efficiency in public resource management systems of the health sector in Nepal. Approved January 13,2017. 

Page 14: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 8 of 57  

      

Annex  6).  The  communities would  then  formulate  a  plan  to  achieve  the  self‐selected  goal,  and were  to  be provided with a grant to implement their plan in 100 days.  The ultimate goal was to work at the community level to change practices known to lead to better nutritional outcomes in the long run.  

8. Rapid Result Initiative (RRI): As discussed above, malnutrition in Nepal had been a persistent problem despite the local and international efforts to tackle it. Hence, the project adopted an innovative design using the RRI which is known to be a useful tool to solve complex problems14 under the pressure of short time frames and ambitious targets. The project design was unique because for the first time, the Rapid Results Approach was being used as the core method of design and delivery for a large scale five‐year project, rather than being brought in to ‘connect the last mile’ in projects that encountered implementation challenges.   

9. The  SHD  project  employed  the  community‐driven  rapid  results  approach  to  help  communities  identify  and change key nutrition‐related behaviors that have a detrimental effect on child growth and development within the nation’s poorest rural communities. Whilst this approach was new to Nepal, there was a strong track record in Nepal of community‐driven development (CDD).  

 

Theory of Change (Results Chain) 10. The project’s theory of change is based on UNICEF’s conceptual framework of malnutrition which the nutrition 

community  has  been  using  for  programming  since  1990  which  emphasizes  that  causes  of malnutrition  are multisectoral.15 The framework classifies the causes of malnutrition as: (i) immediate (such as: inadequate food intake  and  diseases);  (ii)  underlying  (such  as  household  food  security,  adequate  care  and  feeding  practices, access to health services, and residing in a healthy environment, etc.); and (iii) basic (such as: social, economic, environmental, and political issues).   

11. As illustrated in Table 1 below, the causal chain of the proposed activities is as follows:    

Table 1. Causal Chain of the proposed activities 

Activities   Outputs  Outcomes  Long‐term Outcomes 

Training of communities in selection of goals.  Each community to implement a selected nutrition defined goal. 

Rapid Results for Nutrition Initiatives (RRNIs) implemented by communities at ward level, with each RRNI dedicated to achieve one of pre‐defined nutrition related goals  selected by targeted communities.  

Improved attitudes and practices known to improve nutritional outcomes of women of reproductive age and children under the age of two. 

Improved nutritional outcomes.  

 

                                                                 14 Obogn’o Sylvester (2012) “Rapid Results Approach/Initiative. Institutionalization of Results Based Management in Kenya Public Service” Mimeo. Commwealth Association for Public Administration and Management. 15 https://www.unicef.org/nutrition/training/2.5/4.html. Accessed December 5,2017.  

Page 15: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 9 of 57  

      

Project Development Objectives (PDOs) 12. The original PDO16 as stated in both the Project Appraisal Document (PAD) and the Financing Agreement was to 

“improve attitudes and practices known to  improve nutritional outcomes of women of reproductive age and children under the age of two”. The statements in the PAD (2014) and Financing Agreement (FA) are consistent.  

Key Expected Outcomes and Outcome Indicators 13. The original PDO was measured through improvements in: (i) family planning practices of girls and young women 

aged  15‐25  years;  (ii)  practices  of  pregnant  women  regarding  iron  and  folic  acid  supplementation;  (iii) breastfeeding practices of mothers with children 0‐6 months of age; (iv) child feeding practices of households with children 6 to 24 months of age; (v) attitude of community members towards the importance of keeping girls school until age 20;  (vi) attitude of community members towards the importance of reducing  indoor air pollution and (vii) attitudes of pregnant women towards their dietary needs. Annex 1 provides the complete Results Framework, including a description of intermediate indicators and how indicators were measured. 

 

Components 14. The project originally had two main components with total cost of $40 million. A description of components is 

as follows:   

Component 1: Rapid Results for Nutrition Initiatives at the Ward Level (US$34.86 million)  15. This component supported the communities at the ward level to design and implement small projects (called 

RRNIs) based on a predefined “menu” of interventions that address risk factors of malnutrition in Nepal. Each 100‐day “RRNI” cycle follows mainly six key steps as described below17 and as illustrated in Figure 1 below.   

16. Selection of ‘focus area’ and RRNI team members: The first step involved a coach conducting a workshop with the Ward Citizen Forum (WCF). The WCF is a ward‐level body with 20‐25 members representing various socio‐economic, ethnic, religious and age groups of the ward. The WCF would identify needs of the ward in nutrition improvement and select an appropriate “Focus Area” to address that need. There were 15 Focus Areas pre‐identified by the SHD program, and the WCF members selected one focus area for that particular 100‐day cycle. The WCF, with guidance from the coach, also selected 9 people from the ward to form the “RRNI team”. Please refer to Annex 6 for the full list of focus areas.  

17. Selection of RRNI team leader and 100‐day project goal: The second step was a meeting among these RRNI team members to develop a goal (i.e., activity) within the selected Focus Area, to be achieved through the 100‐day RRNI project cycle. For example,  if the WCF had selected a focus area of “improved hand washing”, then the RRNI team would decide what kind of concrete activities were needed to work on in order to achieve better hand‐washing practice in 100 days. They would also select a RRNI team leader to coordinate team members and activities.  

 

                                                                  17   Qualitative Study of Community Action for Nutrition Project Nepal. March 2017 

Page 16: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 10 of 57  

      

18. Preparation and submission of proposal:  Once a  particular  goal/activity  was  chosen,  the  RRNI  team developed a detailed 100‐day work plan to help achieve that goal, as well as the budget required to execute the plan.  

19. Review  and  approval  of  the  proposal:  The submitted work plan and budgets were  reviewed and then approved by the local government (by the Village Development  Committee  (VDC)  for  projects  less  than $1,000; by the District Development Committee (DDC) for  projects  between  $1000  and  $3000),  and  the necessary funds were released to the communities.  

20. 100‐day implementation: Communities started to execute their plan and achieve their goal within 100 days. Implementation was divided into first 50 days and second  50  days,  separated  by  a  mid‐term  review  to assess  the  progress,  celebrate  successes  and  make necessary course‐corrections. 

21. Review of results and sustainability: Finally, after this 100‐day cycle, the community organized a ‘sustainability review’ to assess the achievements, celebrate success and plan for sustainability of the practices. The coach (and sometimes an outside monitor) also assessed whether or not the goal had been achieved. If the community had been  unsuccessful,  it  could  apply  for  another  cycle  to  try  to  achieve  the  same  goal  or  another  one.  If  the community had been successful, it could then apply for two goals at once. 

 Component 2: Project Management, Capacity Building, Monitoring and Evaluation (US$5.14 million) 

22. This component comprised three subcomponents: (i)capacity enhancement of the Project Management Team, including Cluster Units, and Food Security and Nutrition Steering Committees (NFSSCs), as well as of coaches and social mobilizers; (ii) providing necessary inputs (consultants, goods and operating costs) for effective project management  at  national,  DDC  and  VDC  levels;  and  (iii)  ensuring  monitoring  and  evaluation  of  the  Project, including the evaluation of the RRNI process through routine and third‐party monitoring. Please refer to Annex 3 for project cost by categories.  

        

1) Selection of Focus Area & RRNI team members at 

Ward Citizen Forum

2) Selection of RRNI team leader & 100‐day subproject goal

3) Preparation and submission of 

Proposal

4) Review and approval of proposal

5) 100‐day Implementation

6) Review of results and sustainability RRNI 

Project 

Cycle 

Figure 1: Key Steps in the 100‐day Rapid Results Nutrition 

Page 17: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 11 of 57  

      

B. SIGNIFICANT CHANGES DURING IMPLEMENTATION (IF APPLICABLE) 

Revised PDOs and Outcome Targets  

23. Following  the  project’s  mid‐term  review  (MTR),  the  project  underwent  a  Level  1  restructuring  which  was approved on June 17, 2015. The key changes are summarized as follow: 

(i) Revision of the PDO. The modified PDO was "to improve practices that contribute to reduced under‐nutrition 

of women of  reproductive  age and  children under  the  age of  two and  to  provide emergency nutrition  and 

sanitation response to vulnerable populations in earthquake affected areas”. The rationale for revising the PDO 

was to sharpen the focus of the project on improved practices as well as the emerging nutrition and sanitation 

needs.  The focus on attitudes was dropped because it was realized that such changes were likely to take longer 

than the project period thus making this part of the PDO not fully measurable. 

 

(ii) Addition  of  an  Earthquake  Relief  Component.  The  rationale  for  adding  an  earthquake  component  (US$12 

million) was to address the emergency nutrition issues which had arisen from the devastating effect of the April 

25, 2015 earthquake and its aftershocks in critically affected districts18. It was decided that the implementing 

agency (MoFALD) would be supported by UNICEF Nepal in providing emergency response in areas of nutrition 

protection  and water,  sanitation  and  hygiene  as  UNICEF  had  the  required  technical  capacity  and  standard 

protocols to support the delivery of this component. 

 

(iii)  Revision of the Results Framework to reflect the changes to the PDO and ensure better alignment with the 

intended project outcomes. The list of dropped, modified, added indicators is in Table 2 as follows: 

Table 2. Changes to Project Indicators 

Dropped PDO level indicators  

Modified PDO level indicators  Added PDO level indicators 

Percentage of unmet family planning needs among women 15‐25 years of age  

Attitude of community members towards the importance of reducing indoor air pollution.   Changed to: percentage of households reporting no smoke in the room while cooking.  

Percent of households reporting using improved toilet facilities (flush toilet, covered pit within household, community latrine).  

Attitude of community members towards the importance of keeping girls in school until at least 20 years of age 

Attitude of pregnant women towards the importance of eating three time a day including at least one animal‐sourced food per day.   Changed to: percent of pregnant women reporting consuming animal‐sourced protein in the previous day.  

Percent of mothers (of children aged 0‐2) reporting always washing hands at critical times (composite of 4 indicators: washing hands after defecation, washing hands after cleaning child’s bottom, washing hands before eating, washing hands before feeding the children).  

    Number of children 6‐59 months old in the earthquake affected districts with Severe Acute Malnutrition receiving therapeutic care. 

    Number of households in the earthquake affected districts provided with hygiene and sanitation kits (water treatment products and soap.) 

 

                                                                 18  The  critically  affected  12  districts  were:  Dhading,  Gorkha,  Rasuwa,  Sindhupalchowk,  Kavre,  Nuwakot,  Dolakha,  Sindhuli, Makwanpur, Okhaldhunga, Ramechhap and Lalitpur.  

Page 18: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 12 of 57  

      

Other changes included: 

  

(iv) Revision of fiduciary and implementation arrangements. Several corrective steps were introduced to increase 

the overall effectiveness of project management, improve the quality of the sub‐project proposals and enhance 

efficiency of proposal processing  as follows: (i) strengthening the project management team (PMT) by hiring of 

additional staff namely three M&E officers, an administrative officer and finance staff; (ii) adding two staff in 

each of the 15 districts to expedite proposal processing; (iii) allowing each ward to submit two proposals at the 

same time to reduce processing time; (iv) conducting intensive training for FM staff, coaches and supervisors; 

and (v) carrying out re‐orientation sessions on project approach, targets and implementation modalities for DDC 

level staff.   

  

(v) Revision of the disbursement estimates. A total of US$12 million had been moved from component 1 to the 

added third component “Earthquake Relief Component”. As discussed below, given that the project adopted a 

demand‐driven approach and relied on mobilizing communities to collectively commit to address the risk factors 

of malnutrition,  the  initially  estimated budget  for  the RRNIs  could not be precise but  sufficient  funds were 

allocated to allow communities to implement sub‐projects in all selected districts if all such communities would 

apply. At the MTR, it became clear that not all funds would likely be absorbed and hence when the earthquake 

took place  immediately following the MTR, US$12 million was reallocated to that component as part of the 

Bank’s earthquake response relief plan.   

Implications on the original theory of change  

As per the revised PDO, the theory of change is as follows:   

Activities  Outputs  Outcomes  Long Term Outcomes 

1) Training  of  communities  in selection  of  goals.  Each community  to  implement  a selected nutrition defined goal. 

 

2) Provide  emergency  nutrition  and sanitation response to vulnerable populations  in  earthquake affected  areas  (namely:  (i) provision of therapeutic care and supplementary food supplies and protection  of  breast  feeding,  (ii) provision  of  safe  water  and  of appropriate  sanitation  and hygiene kits, and (iii) provision of latrines). 

1) RRNIs  implemented  by communities  at  ward level,  with  each  RRNI dedicated  to  achieve  one of  pre‐defined  nutrition related  goals  selected  by targeted communities. 

2) Provide nutrition care and treatment  to  severely acute malnourished (SAM) and  moderately  acute malnourished  (MAM) children,  and malnourished mothers. 

1) Improve  attitudes  and practices  known  to improve  nutritional outcomes  of  women  of reproductive  age  and children  under  the  age of two  

2) SAM and MAM children and  malnourished mothers are treated and prevented  from deterioration  of  their nutritional status.  

      Improved nutritional outcomes of children and mothers.  

 

 

Page 19: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 13 of 57  

      

II. OUTCOME 

24. The outcome rating for this project is assessed against the original and revised objectives. Given that the original scope of  the project was not narrowed as a result of  restructuring but actually expanded with the Earthquake Component, the assessment of outcomes does not apply a split rating even though the PDO was slightly revised. However, this ICR assesses all parts of the PDO, including the original and revised.  

 

A. RELEVANCE OF PDOs 

Rating: High 

Assessment of Relevance of PDOs and Rating 

25. The  project was  highly  relevant  to  and  consistent with  the  priorities  laid  out  in  the  Bank’s  Nepal  Interim Strategy Note (ISN 2010‐2011). At the time of project preparation, Nepal was going through a transitional period of  its  history,  with  a  new  government  to  be  formed  and  a  new  constitution  to  be  drafted.  The  country’s overarching  goal  –  as  stated  in  ISN  FY2010‐2011‐  was  to  build  peace  and  focus  on  development19.  The  ISN indicated that the high burden of malnutrition in Nepal was a major persisting shortcoming and undermined the human potential needed to achieve sustained and resilient growth. Similarly,  the following ISN (FY2012‐2013) also emphasized food and nutrition security as a main area of  intervention. The focus on nutrition was highly relevant to the third pillar, namely, promoting access to better quality services20.  

26. The  PDOs  and  project  activities  remained  well‐aligned  with  government  priorities.  The  GoN  development strategy outlined in the Three Year Plan Approach Paper for FY2010‐2013 included nutrition as a separate chapter. Nutrition and nutrition related indicators were explicitly included in the Three‐year Interim Plan (2007‐10). The following Three‐Year Plan (2010‐13) included nutrition as a separate chapter under Health and Nutrition for the first time with an emphasis on nutrition under the agriculture, labor, water and sanitation, education, forest, and women and social welfare sectors21.   

27. Globally, Nepal joined the Scaling Up Nutrition (SUN) movement in 2011. At the same time, the government launched a multi sectoral nutrition plan (2013‐2017) under the leadership of the Prime Minister. The plan aimed to  address  both  the  immediate  underlying  causes  of  undernutrition with  a  package  of  nutrition  specific  and nutrition sensitive interventions focusing on the critical 1000‐day window including the mother’s pregnancy and the child’s first two years. The plan engaged the National Planning Commission and with participation of five‐line ministries  covering  health,  education,  water  and  sanitation,  agriculture,  and  local  development  and  social protection.    

28. The project remained highly relevant. On April 25, 2015, a catastrophic magnitude 7.8 earthquake struck the south‐central  Asian  country  of Nepal,  killing more  than  8,600, making  this  the  nation’s  deadliest  disaster  on record. After weeks of aftershocks, another powerful magnitude 7.3 earthquake struck the same region on May 12. Some 8 million people were affected by the quakes. According to UNICEF, 1.7 million children urgently needed 

                                                                 19 The project is particularly relevant to the third pillar of “Enhancing equitable access to services and social inclusion”. 20 The Country Partnership Strategy FY2014‐2018 focused on Improved health and nutrition services, particularly for the poor and disadvantaged under pillar two (Pillar 2: Increasing inclusive growth and opportunities for shared prosperity). 21 https://scalingupnutrition.org/wpcontent/uploads/2013/03/Nepal_MSNP_2013‐2017.pdf  

Page 20: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 14 of 57  

      

aid and more than 750,000 homes were destroyed. The project was restructured to respond to the emergency nutrition  needs  in  critically  affected  areas.  This  included  adding  a  new  component  for  earthquake  relief  and adding more districts to target beneficiaries in the earthquake critically affected areas.  The project restructure was  aligned  to  the  Bank’s  Nepal  Country  Partnership  Strategy22  (CPS  FY14‐18)  to  enhance  disaster  risk management  systems.  The  restructure  was  solidly  anchored  within  the  “Foundations  and  Cross‐Cutting Dimensions” of the Nepal CPS, which states that the “risks from natural disaster will also continue to be addressed in a cross‐cutting manner by the World Bank”. 

 

B. ACHIEVEMENT OF PDOs (EFFICACY) 

Rating: Substantial 

Assessment of Achievement of Each Objective/Outcome 

29. Given  the novelty  of  the  design of  this  project which offered  the  communities  the option  to  choose  from 15 different focus areas based on their needs and aspirations, the assessment of PDO 1 and 2 uses the correlation between the focus areas selected and the achievement of the goal/objective linked to them. The assessment of achievement of project objectives in this ICR reflects the data from the end‐line survey which was completed after project closing in June 30, 2017. Based on the end‐line survey data, it appears that the project met most of  its objectives.   

Assessment of achievement of PDO1:  Improvement  in attitudes of women of  reproductive age and children under the age of two.  Rating: Modest  

30. The original PDO encompassed expected improvements in attitudes and it was realized at the time of restructuring that such changes were actually part of a long‐term process and that it was likely not the appropriate PDO for this project with a four‐year time frame.  It was also felt that measuring improvements in practices was sufficient to understand the impact of RRNIs on nutrition outcomes.   Hence, the PDO was revised and the attitude indicators were dropped. However, it is still possible to assess improvements in attitudes using data from the midline impact evaluation survey.    

31. The  project  managed  to  make  some  modest  positive  changes  in  attitudes  during  the  first  two  years  of  its implementation. The project had four attitude indicators which are discussed below:  

i. Attitude of community members towards the importance of keeping girls in school until at least 20 years of age. Education of girls in Nepal has improved tremendously in the last decade. 8% of wards selected young girls’ education as a focus area. However, the midline data showed a decline on the percentage of households believing girls should be sent to school until at the least 20 years old, compared to the baseline.  This is not surprising as the global evidence shows23 that young girls marriage and drop out school rates increased during the time of emergencies. Globally, adolescent girls from displaced populations are five times more likely to drop out of school. Given that the midline data was collected after the earthquake, the attitude towards girls education was likely impacted. 

ii. Attitude of community members towards the importance of reducing indoor air pollution: Due to women’s 

                                                                 22 Nepal Country Partnership Strategy (CPS FY14‐18, Report No. 83148‐NP) 23 http://unesdoc.unesco.org/images/0024/002448/244847E.pdf . Accessed January 18,2018.  

Page 21: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 15 of 57  

      

customary involvement with cooking in Nepal, their exposure to harmful smoke inside the house is much higher than that of men. 16% of wards selected this focus area at the time of midline. A higher percentage of households (43%) reported a positive attitude towards reducing exposure to indoor smoke for pregnant women and young children compared to the baseline (32%).  So, this was a particularly important finding and achievement. 

iii. Attitude of community towards dietary needs for pregnant women. 16% of wards selected a focus area to maintain adequate weight and regular eating among pregnant women and young children. There was a statistically significant increase of positive attitudes of household heads in the treatment group towards importance of adequate diet of pregnant women compared to those in the control group. This was also an important achievement. 

iv. The fourth PDO indicator was to assess the unmet family planning needs among women 15‐25 years of age. This was one of the least popular focus areas (i.e. at the time of midline only 1% of wards selected this focus area) and there was no data on any improvements in this area.  

Assessment of achievement of PDO 2:  Improvement of practices known to  improve nutritional outcomes of women of reproductive age and children under the age of two.  Rating: Substantial   

32. The  risk  factors  that  the  project was  addressing  arose  from a  combination  of  individual  and  community  level knowledge and practices. They included practices such as exclusive breast feeding, taking iron and folic acid (IFA) supplements,  consuming  animal‐sourced  protein  and  using  improved  toilet  facilities.  The  project  achieved  its targets  on  focus  areas which  provided  the  communities with  tangible  and universal  (community‐wide  supply) outputs such as using improved toilet facilities and consuming animal sourced protein.  

33. Before restructuring, the project assessed improvements on practices through the following three areas: pregnant women taking an IFA supplement, breastfeeding practices, and complementary feeding practices. As mentioned above, the revised PDO re‐emphasized the project’s focus on improving practices. Thus, in addition to the three practice  PDOs  mentioned  above,  seven  indicators  to  assess  improvement  on  practice  were  added  (namely: households  reporting  no  smoke  in  the  room while  cooking, women  consuming  animal‐sourced  protein,  using improved toilet facilities, and washing hands at critical times‐which is a composite of 4 indicators: washing hands after defecation, washing hands after cleaning child’s bottom, washing hands before eating, washing hands before feeding the children). Please refer to Annex 1 for the results framework and key outputs.  

34. Overall, the project showed good improvement in 9 out of the 10 PDO indicators. Figure 2 below presents the project achievement by comparing the baseline and endline values for each of the PDO 2 indicators.    

    

       

Page 22: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 16 of 57  

      

Figure 2: Results of PDO2 Indicators 

 

35. Given  that  SHD  is  a  unique  type  of  a  CDD  project  in  which  focus  area  selection  was  demand‐driven  (i.e. communities choose from a ‘menu’ of 15 different focus areas relating to improved nutrition), the frequency of selection  of  a  focus  area  varies  based  on  the  communities’  selections  of  what  they  were  interested  in implementing. As illustrated in Table 4 below, some focus areas (such as consuming animal sourced food and using improved  toilet  facilities) were more popular  than other  focus areas  (such as  taking  IFA supplementation, and breastfeeding). 

Table 4: Percentage of Wards Selecting Each Focus Area 

Indicators (PDO 2)  

% of Wards selecting each Focus Area 

Indicator level of achievement 

Percentage of pregnant women reporting consuming animal‐sourced protein in the previous day 

43%  Surpassed  

Percentage of households reporting using improved toilet facilities (flush toilet, covered pit within household, community latrine) 

38%  Surpassed  

Percentage of mothers (of children aged 0‐2) reporting always washing hands at critical times 

37%  Surpassed 

Percentage of pregnant women taking IFA supplements for 180 days  4 %  Partially achieved 

Percentage of children 0‐6 months age who are exclusively breastfed  6 %  Not achieved 

Percentage of children 6‐24 months age who consume a minimum acceptable diet 

*(data is not available) 

Not achieved 

Percentage of households reporting no smoke in the room while cooking 

28%  Not achieved 

 

36. It was noted that there is a significant correlation between the level of exposure to a particular focus area and achieving the desired outcome related to it.  The areas selected also happened to be some of the most critical in impacting overall nutritional outcomes. As presented in Table 4, the four most popular focus areas selected by the 

Page 23: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 17 of 57  

      

beneficiary communities and measured were:(i) increase consumption of animal protein among pregnant women and young children,  (ii) practice proper and consistent handwashing,  (iii) end open defecation, and  (iv)  reduce exposure to indoor smoke for pregnant and young children. As Table 4 shows, the project surpassed its targets for all of these 4 measures except for exposure to indoor smoke. The project was close to achieving the target (45%) of reducing exposure to indoor smoke by midline (43%), however it dropped to (39%) by endline. It is expected that this was due to lack of access to fuel and other amenities required to build improved cooking stoves which was likely a result from the trade blockade in the Indian border that followed the earthquake.    

37. Simultaneously,  the  two  least  selected  focus  areas:  breastfeeding  (selected  by  only  6%  of  wards)  and  IFA supplementation (selected by 4% of wards), did not achieve their PDO targets. Contrary to WHO recommendation that children under 6 months should be exclusively breastfed, Nepal’s 2016 DHS shows a country‐wide drop on rates of breastfeeding compared to 2011 (66% and 70% respectively). There is not yet a clear explanation for this trend. It is possible that the massive earthquake experienced by the Nepalese population placed greater pressure on women to work more to repair the damages and this limited their time and commitment to breastfeeding.   

38.  The end‐line survey shows that the project achieved remarkable success in improving sanitation practices. The five PDO indicators that assessed sanitation practices have all surpassed their targets (see Figure 3) and showed a steady improvement over time. The impact evaluation study (IE) revealed that the overall hygiene and cleanliness practices have improved. Even though it is not a PDO indicator it is noteworthy that fewer households reported observing human feces around the house as well (from 30% at baseline to 10% at endline).  

Figure 3: Sanitation PDO Indicators 

 

39. Sanitation  and  hygiene  practices  are  directly  linked  to  children’s  health,  and  inadequate  access  to  water  or sanitation  facilities can cause  illnesses  such as diarrhea, which  increases  risk of malnutrition. The  IE asked  the households if the child had an illness in the past 15 days prior to the interview. Households reported fewer children suffered from illnesses like coughing, diarrhea and vomiting compared to baseline (see Figure 4). 

 

Page 24: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 18 of 57  

      

Figure 4. Child Illness in the Past 15 Days 

                           

40. While  the  PAD  clearly  stated  that  the  targeted  changes  in  practices would  not  necessarily  result  in  improved nutritional outcomes during the project period since improvement on nutritional outcomes takes longer period of time,  in  reality,  the  achievements  did  show  direct  impacts  on  outcomes.  The  IE  included  anthropometric measurements  for  children  under  two  to  assess  changes  in  stunting24,  wasting25  and  underweight26.  The assessment of anthropometric indicators showed a significant improvement over the course of the project. The rate of stunting dropped from 38% at baseline to 33% at endline, wasting dropped from 21% at baseline to 16% at endline, and underweight dropped from 32% at baseline to 15% at endline (see Figure 5).  These improvements are a remarkable testament to the project’s success.  It is also critical to point out that because the project was implemented  in  areas  where  no  other  donor  was  providing  support  (as  this  was  an  intentional  split  of responsibilities  among  the  donor  community),  these  remarkable  achievements  can  only  be  attributed  to  this project. 

Figure 5. Anthropometric Measurement of Children Under Two in Project Areas 

                                  

                                                                 24 Stunting: low height for age, is caused by long‐term insufficient nutrient intake and frequent infections. UNICEF 2010. 25 Wasting: low weight for height, is a strong predictor of mortality among children under five. UNICEF 2010. 26 Underweight: low weight for height, is a physical growth delay and used as a proxy for the deleterious effects undernutrition. UNICEF 2010.

Page 25: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 19 of 57  

      

Assessment of achievement of PDO3: Emergency nutrition and sanitation relief.  Rating: High 

41. The project had two PDO indicators for nutrition and sanitation response to vulnerable populations in earthquake affected areas and both had surpassed their targets. The two PDO 3 indicators were: (i) number of children 6‐59 months in the earthquake affected districts with Sever Acute Malnutrition (SAM); and (ii) number of households in the earthquake affected districts provided with hygiene and sanitation kits. The project sub‐contracted UNICEF to prevent the deterioration of malnutrition in children under five and pregnant and lactating mothers in the 14 districts most critically affected by the 2015 earthquake. Active case finding of the moderately acute malnourished (MAM) children 6‐59 months led to management of about 36,100 cases out of estimated 23,250 cases. Successful management of MAM children naturally led to decrease in the number of SAM children 6‐59 months. Thus, there were only about 4,300 SAM children out of estimated 4,850 children who required attention and were managed effectively in the 14 critically affected districts.  

42. Despite all the serious external challenges faced by the project, including the huge disruption which resulted from the earthquake, the project continued to be implemented in every ward mapped to it. At project closing, 9096 RRNIs had been  implemented. More than 85% were publicly audited. The number of RRNIs per ward per year varied from one district to the other (average was .98/ward/year). Overall, the percentage of RRNIs which achieved 80% of their targets was 92%.  Again, it is hard to overstate what an achievement this was in the context of Nepal over this particular period. Another achievement of the project was ensuring  inclusivity of the RRNI team. The percentage of females participating in all RRNIs was 68%, exceeding the target of 40%. Similarly, the percentage of minority participation in all RRNIs was 63%, exceeding the target of 40%. This had a positive impact on improving community cohesion and integration.   The emergency nutrition and sanitation relief activities reached out to a total  of  169,700  mothers  of  children  6‐24  months  who  received  information  counselling  on  complementary feeding practices and hygiene behaviors, exceeding the target of 86,500. Breastfeeding support for children 0‐24 months was provided to 169,700 mothers, surpassing the target of 115,000. About 80,015 households received hygiene kits and counselling on hygiene and sanitation, exceeding the target of 77,280.  

Justification of Overall Efficacy Rating  

43. The overall Efficacy rating is Substantial because the project achieved the majority of its original and revised PDOs and recorded a remarkable success in the area of sanitation in particular as well as demonstrated significant achievements in the reduction of stunting, wasting and underweight which were beyond what was expected. Please refer to Annex 7 for weighted average of success per each of the PDO indicators.   

 

C. EFFICIENCY 

Rating: Substantial 

Assessment of Efficiency and Rating 

44. It  is  evident  that  the  returns on  investing  in nutrition  are  very high.  According  to  the World Bank  report27, malnutrition slows economic growth and increases poverty through direct costs from increased burden on the health care system, and indirect costs from lost productivity. An analysis of several countries indicates that the overall economic costs of malnutrition  run  to as high as 2‐ 3% of  the growth of GDP of developing countries                                                                  27https://siteresources.worldbank.org/NUTRITION/Resources/2818461131636806329/NutritionStrategyOverview.pdf  accessed December 12, 2017 

Page 26: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 20 of 57  

      

(please refer to Annex 4 for more details). It is estimated that Nepal loses nearly $190 million annually in GDP to vitamin and mineral deficiencies. Childhood anemia alone is associated with a 2.5% drop in adult wages28. (Harton S. and Ross the Economics of Iron deficiencies). A costing exercise conducted by the World Bank to determine the annual  cost  of  scaling‐up  well  proven  nutrition  interventions  in  high  burden  countries  shows  that  such investments give very high economic returns.  Table 7 below illustrates the cost‐benefit ratio of a number of focus areas of the RRNI. Similarly, the Lancet series29 estimated the cost of handwashing counselling that can lead to 30% reduction in the risk of diarrhea, a direct cause of malnutrition (see Table 7). 

Table 7. Estimated Benefits from Scaling‐up Nutrition Interventions 

Intervention  Estimated benefit: cost ratios or cost‐effectiveness  

Behavior change through community nutrition programs 

US$ 53‐153 per DALY 

Hygiene promotion  US$ 3.35 per DALY 

Iron‐folic acid supplements  US$ 66‐115 per DALY (iron) 

Complementary foods  US$ 500‐1000 per DALY 

Latrine construction  US$ 270 per DALY30                          Source: Horton,S., et al. Scaling‐Up nutrition; What Will it Cost?, World Bank,2010 

45. The project was characterized by strong technical efficiency and targeting resources to the neediest populations. The global evidence shows that behavioral change and community based interventions are among the most cost‐effective interventions to improve nutrition outcomes, with some of the highest cost‐benefit ratios in terms of poverty reduction and economic development. The project made substantial contributions to improving equity and targeting resources to the neediest populations. The selection of districts (15 out of 75 districts) under the project was based on population density, stunting levels, poverty levels and absence of overlapping interventions by other partners. Within the selected districts, SHD targeted 25% of the most disadvantaged VDCs. Similarly, the emergency relief component activities targeted the most critically affected districts.     

46. Implementation efficiency: The efficiency of project execution improved with time, after initial delays in starting project activities which was expected given the novelty of  the approach. However,  implementation efficiency improved  in  the second year as  there was a better understanding of  the projection  implementation modality among  stakeholders  as  well  as  community  members.  The  implementation  efficiency  further  improved  after project restructuring as the project modified its fiduciary and implementation arrangements to improve quality and efficiency (see para 16 for more details) and added a third component (emergency relief component).  

Notably, despite the earthquake, the project closed within the originally stipulated time frame and completed most of its envisioned activities. The project disbursed 88% (22.8M out of 25.9M SDR) of its commitment by the closing.   

47. Considering the very high cost‐effectiveness of the interventions, coupled with the successful implementation of a novel approach to improve nutritional outcomes at the community level, and the completion of the project by its original closing date, the overall efficiency is considered as Substantial. 

 

                                                                 28 http://siteresources.worldbank.org/NUTRITION/Resources/281846‐1271963823772/Nepal.pdf accessed Dec 5,2017 29 http://www.thelancet.com/article/S0140‐6736(07)61693‐6. Accessed March 5, 2018 30 https://globalhandwashing.org/about‐handwashing/why‐handwashing/economic‐impact/ Accessed March 5,2018 

Page 27: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 21 of 57  

      

D. JUSTIFICATION OF OVERALL OUTCOME RATING 

48. The  overall  rating  for  Outcome  is  Satisfactory  given  that  the  PDOs  of  the  project  remained  highly  relevant throughout the years of implementation and before and after restructuring. Most of the outcomes’ targets were achieved, and in some cases surpassed its targets, and the project funded highly cost‐effective interventions and was completed on time.  

Table 8. Overall Outcome Ratings  

  Rating 

Relevance  High 

Efficacy:  Substantial 

(1) PDO 1‐attitudes (2) PDO 2‐practices (3) PDO 3‐nutritional and 

sanitation emergency relief  

Modest Substantial High 

Efficiency   Substantial 

Outcome Rating  H/S/S = Satisfactory  

 

E. OTHER OUTCOMES AND IMPACTS (IF ANY) 

 

Gender 

49. The project made a positive impact on gender in many ways. The outcomes of many sub‐projects implemented by communities contributed to better health conditions for women beneficiaries through better indoor air quality, less workload by supplying potable water, and improved sanitation.   

50. The qualitative study associated with the project indicated that although it was difficult to include women in RRNI teams due to social norms in addition to women’s full engagement with household work, women’s participation in RRNI teams was significant. All 18 wards included in the sample of the study had women in their RRNI teams and 12 out of 18 RRNI teams had women as RRNI team leader. 

51. Moreover, 64% of the hired coaches were women belonging to the local residence and they were empowered to voice issues related to malnutrition of children and women. 

 

 

Institutional Strengthening 

52. The  project  contributed  to  improving  the  capacity  of  the  implementing  agency.  At  the  central  level,  project management  team received  training  to strengthen project management skills. Training  to Nutrition and Food Security Steering Committee (NFSSC) at district and VDC level had been carried out in 15 districts and 146 VDCs to enhance participants’  skills  in  steering  the multi‐sectoral  nutrition programs  in  the  country.  In  addition  to capacity building activities of coaches and supervisors, more than 350 personnel were hired and their capacity enhanced in the field of nutrition. 

Page 28: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 22 of 57  

      

Social Capital 

53. Since the project adopted the CDD approach, several social cohesion elements (such as trust and collective action) were measured through the impact evaluation study. Overall, the trust level31 was statistically higher for members of  communities  of  the  treatment  wards  compared  to  the  control  wards.  Higher  percentage  of  treatment households reported to have worked with others in the village for benefits of the community compared to the control wards.  In addition, members of  the  treatment  communities/wards were more  likely  to attend village council meetings, public hearings, or public discussion groups and were more likely to vote in the last election compared to those in the control communities32.   

 

 

III. KEY FACTORS THAT AFFECTED IMPLEMENTATION AND OUTCOME 

 

A. KEY FACTORS DURING PREPARATION 

54. The project was well aligned with the GoNs Multi‐Sectoral Nutrition Plan (NMNP). At the time of project’s preparation33,  Nepal  had  just  joined  the  SUN  movement,  and  the  government  launched  a  multi‐sectoral nutrition plan under the Prime Minister’s leadership. The plan aimed to address the underlying and basic causes of  undernutrition with  a  package  of  nutrition‐specific  and  nutrition‐sensitive  interventions,  both  based  on evidence, focusing on the critical 1,000‐day window including the mother’s pregnancy and the child’s first two years.  

55. Technical design. The focus of the project on stunting on the first 1,000 days (from conception up to the age of 24 months) was technically sound (adopting a life‐cycle approach). Good nutrition during pregnancy and in the first years of a child’s  life has a profound impact on a child’s ability to grow, learn and thrive—and a lasting effect on a country’s health and prosperity. The damage done by malnutrition early in life has lasting effects that can surpass through generations. This is seen throughout the world as malnourished and anemic women giving birth to malnourished daughters who grow up to become malnourished mothers themselves, thereby perpetuating the cycle. 

56. Robust targeting mechanism. The project was implemented in 15 districts out of a total of 75 districts in Nepal. The 15 districts were selected based on (i) stunting levels of children; (ii) population size; (iii) poverty levels; and (iv) the absence of interventions by other partners. There are approximately 1,100 VDCs in these 15 districts. The program targeted 25% of the most disadvantaged VDCs ‐in total approximately 280 VDCs and operated in all wards of the selected VDCs. The baseline data confirmed that the VDCs selected under the project were the most disadvantaged VDCs as most of the baseline indicators of those VDCs were far below the national average of the country. 

57. Implementation  modality.  The  implementation  arrangement  of  this  adopted  a  number  of  “innovative” approaches as described below: 

                                                                 31 Measured via household survey question (most people can be trusted in general). 32 Nepal Sunaula Hazar Din Community Action for Nutrition Project. Impact Evaluation Midline Report, April 2017.  33 The project was prepared in 18 months (from January 2011 to June 2012). 

Page 29: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 23 of 57  

      

i. Community based approach in the implementation of nutrition interventions has been proven to be effective  and  efficient  globally  and  locally,  particularly  when  the  focus  is  to  change  attitude  and behavior. The community approach taken in Action Against Malnutrition through Agriculture (AAMA)34 has shown positive results in terms of knowledge of health and nutrition among mothers and young children. Most of these interventions benefited from community involvement.  

ii. Selection of  the RRNI approach to  improve practices known to  improve nutritional outcomes was a particularly ambitious undertaking. As  the PAD notes,  the project design built upon  lessons  learned from  projects  which  used  RRI  in  both  health  and  non‐health  related  programs  in  other  countries. However,  in most of these cases, the RRI was  implemented at much smaller scale and the targeted changes were much more attainable (mostly in systems and policies). This is clearly different than the case of  the SHD project as changes  in attitudes and behaviors are much more complex and require longer time35.  Nonetheless, the approach was selected because of the strong presence of community based interventions in Nepal, which made the RRNI a potentially successful choice. 

iii. The flexibility built into the design of the project (communities select from a menu of focus areas and decide how they will achieve their goals) was the right approach but it was also risky because it relied on communities to select all 15 interventions whereas there were clear preferences for some specific intervention which was an important lesson in this project.  

58. Risk assessment. The overall risk rating was judged to be substantial at appraisal. The project rightly identified several substantial risks that could affect project implementation. Weak capacity was considered as one of the main substantial risks, which included: (i) capacity of the implementing agency to effectively manage the project given the project’s innovative nature; (ii) capacity of financing management including flow of funds; and (iii) capacity of coaches to guide the RRNI teams and wards in goals selection. Each were planned to be addressed through capacity building and hiring of consultants. In addition, the project planned for capacity enhancement of the project management team including cluster units and NFSSCs at DDC and VDC levels to ensure they were able to review and process work plans and secure necessary supplies at the village level. Another substantial risk was governance and lack of clarity of roles and responsibilities between DDCs and VDCs. To mitigate this risk, detailed description of roles and responsibilities of all project actors was provided in the Operations Manual which helped to lessen the level of confusion.     

59. Early introduction of the RRNI approach. Prior to the start of the project, the plan was to introduce the RRNI approach in two VDCs36 based on a preliminary operations manual to test the approach and incorporate lessons learned into the final operations manual‐ which was one of the legal covenants. Despite the delays in piloting RRNIs, the feedback from communities was very encouraging and the pilot provided the foundation to articulate all dominions of project implementation in the operational manual.  

  

                                                                 34 http://pdf.usaid.gov/pdf_docs/PA00KMDV.pdf. Accessed December 14,2017.     36 Bhimeshwor and Ratamata JhangJholi VDCs of Sindhuli disctrict.  

Page 30: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 24 of 57  

      

B. KEY FACTORS DURING IMPLEMENTATION  

Factors outside the control of government/implementing entity:  

60. Project  implementation was adversely  impacted by  the 2015 earthquake  followed by  six months of  trade blockade at the Indian border. The project faced many challenges following the 2015 earthquake: communities and beneficiaries were displaced, some of the tangible and intangible outputs of the project were damaged (such as latrines), and priority was shifted to construction activities particularly in the districts critically affected by the earthquake (4 out of the 15 project districts). The protracted political unrest in the Terai districts (9 out of 15 project districts) and the trade blockade at the Indian border resulted in a fuel crisis which made travel difficult and increased the cost of goods such as food or construction materials needed for communities’ subprojects, which made it difficult for communities to undertake planned work for their subprojects within the approved budget.  

Factors within the control of the government/implementing entity:  

61. Project implementation initially suffered from some setbacks that resulted in implementation delays and low disbursement. After project effectiveness, the project could not secure funds for almost a year due to a country wide delay in approval of a full budget for FY13. This resulted in delays in initiating project activities including the identification of the most disadvantaged VDCs and the poorest wards in the selected VDCs which in turn delayed  the  baseline  study.  Similarly,  the  finalization  of  the  project's  Operations  Manual  took  longer  than expected. 

62. Human  resources  and  implementation  capacity.  The  SHD Project was  the  first  standalone nutrition project implemented by MOFALD and as a result there was a steep learning curve for MOFALD and was supported by frequent trainings given to the stakeholders by the project. Several challenges were faced by the project due to weak capacity and lack of competent human resources, for example (i) the SHD project was implemented by staff  from  the MOFALD who were  involved  in  other  projects  and  other ministerial  jobs  and were  not  fully dedicated to implementing the SHD project. In addition, there was frequent turnover of key project officials (i.e. Project Coordinator and Monitoring and Evaluation Officer) and vacant or part‐time posts (i.e. Accounts Officer, Accountant); (ii) MOFALD staff at VDCs who carried out project management activities at the local level did not have the adequate technical knowledge and experience to manage the project  in addition to that they were already swamped by other ministerial work; (iii) NFSSCs which constitute members of different line agencies did not have sufficient capacity to review and process work plans/proposals particularly at the village level. Approval of proposals typically took longer than planned due to lack of timely meetings. In some cases, proposals were pending  approval  for more  than 6 weeks;  (iv)  coaches needed more  technical  support  to help  communities complete the forms, in many cases proposals were returned to communities for re‐writing and re‐submission due to poor quality (missing information and not completed sections); and (v) low capacity of the FM personnel at the DDCs and VDCs levels resulted in a slow pace of flow of fund to communities. As mentioned in para 16, the  MTR  introduced  several  corrective  steps  to  increase  the  overall  effectiveness  of  project  management, improve the quality of the sub‐project proposals and enhance efficiency of proposal processing. 

    

Factors subject to World Bank control: 

Page 31: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 25 of 57  

      

63. The Bank worked closely with MOFALD to monitor project progress and jointly took several corrective actions during implementation to improve project effectiveness (prior to restructuring). For instance, in order to make up for implementation delays of one year, the project agreed to allow communities which completed their sub‐projects  successfully  to  submit more  than  one  proposal  in  the  following  cycle.  However,  despite MOFALD's agreement  to  allow multiple  initiatives,  the  approval  of  these  second  proposals  submitted  by  communities became a lengthy process due to difficulty in convening the approval committees (NFSSC). Furthermore, fund release was slow to communities whose proposals were approved.  

64. The project had a very successful MTR (February 15‐20,2015) which took place 2 months prior to the earthquake. During the MTR, a decision was made to restructure the project to  introduce several changes  in  institutional arrangement and increase project effectiveness. Directly after the MTR, was as a result of the earthquake, the restructuring was used to make several other changes (along with an added component on provision of nutrition supplements in earthquake affected districts). Some of the key changes that were introduced to improve project efficiency and quality were as follows: 

- Strengthening  the  PMT  capacity  by  hiring  additional  staff  ‐  three monitoring  and  evaluation  officers,  an 

administrative officer and a finance officer. 

- Adding 2 staff in each of the 15 districts to expedite proposals processing 

- Enhancing capacity of FM staff 

- Modifying the approval threshold such that all RRNI proposals for up to US$3,000 could be approved at the 

VDC level (previously the VDC could approve proposals only up to US$ 1,000 and DDC had to approve those 

between US$ 1,000 and 3,000). The VDC was also responsible for ensuring a 60‐day turn‐around between 

proposal submission and disbursement of funds, whereas DDC’s role focused on supervision and monitoring 

of all RRNI projects. 

- Add 2 coaches per VDC and 2 supervisors per district. 

- Enhance training of coaches and supervisors and carry out re‐orientations sessions for DDC level staff on the 

project approach, targets and implementation modalities. 

 

IV. BANK PERFORMANCE, COMPLIANCE ISSUES, AND RISK TO DEVELOPMENT OUTCOME 

 

A. QUALITY OF MONITORING AND EVALUATION (M&E)  

M&E Design 

65. The project had a rigorous M&E design. The PAD defined a clear set of monitoring  indicators. The PDO level indicators were monitored through the impact evaluation surveys. Given the novelty of the project, adequate resources were  dedicated  under  component  2  to  support  regular monitoring  and  evaluation  activities.  This included:  (i)  regular  collection  of  data  on  the  implementation  of  the  RRNIs;  (ii)  independent  third‐party monitoring to verify the results of the RRNI; and (iii) an impact evaluation study (baseline, mid‐term and end‐line surveys were supported by a trust fund37) employing randomized control trials.  

                                                                 37 Conducted by the Development Impact Evaluation (DIME) team of the World Bank, and financed by SUNITA TF (Scaling Up Nutrition Initiative Technical Assistance)‐ window of the South Asia Food and Nutrition Security Initiative (SAFANSI).  

Page 32: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 26 of 57  

      

66. To  complement  the quantitative evaluation,  an  in‐depth qualitative  study was planned  to promote a better understanding of implementation and outcomes of the community‐driven rapid results approach under the SHD project38.  Furthermore,  the  project  planned  semi‐annual  learning  events  for  coaches  as  well  as  an  annual Nutrition Learning Forum where successful RRNI were recognized and lessons learned were shared. 

 

M&E Implementation 

67. Overall, the monitoring requirements of the project were significant due to the large number of sub‐projects that were carried out simultaneously in 15 districts. The PMT with the Bank team regularly conducted supervision visits to districts to monitor the implementation of sub‐projects and provide support to districts stakeholders.  

68. As cited above, due to the delayed start of implementation, the baseline study could not be initiated in a timely manner39. The project ran  in two phases and VDCs were randomized  into two groups ‐early starter for VDCs started in FY14 and late starter for VDCs started in FY16.  

69. Despite the fact that the project planned and supported the installment of digital reporting (via MIS software), it was not utilized and data from the field were collected manually throughout the project life. The hiring of the MIS firm was delayed for more than two years due to administrative reasons, but even after the firm had been hired and the software installed, it was recognized that additional personnel recruitment would be needed for staff with skills in using MIS. 

70. During the MTR, the Bank team noted that the PMT was over‐stretched with other responsibilities and there was a need to increase human resources for effective monitoring both at the PMT level as well as the DDCs level. Three monitoring and evaluation officers were hired in the first quarter of 2016 to strengthen project monitoring. This  enhanced  the  implementation  of  RRNIs  as  M&E  officers  helped  in  providing  technical  support  to  the coaches, facilitated submission of RRNIs proposals and expedited approval of sub‐projects and fund flow.   

71. As planned, the project hired an independent third‐party monitoring during the period of March to August 2014.  529 ‐out of the 843 RRNI projects under implementation at that time‐ were visited. The monitoring visits revealed that although sub‐projects generally followed the guidelines in the Operational Manual, there were some areas where the project needed to strictly comply with monitoring visits by DDC/VDC and public audits (as they were conducted for only 44% and 46% of the projects visited respectively). 

M&E Utilization 

72. The PMT used regular M&E data to keep track of RRNI proposals, status of implementation, focus group selection and budget which was useful on the overall monitoring of implementation and reporting. The impact evaluation surveys provided comprehensive input to track project PDO level indicators. 

 

                                                                 38 By examining the implementation steps and social and political dynamics at the community level in detail, it seeks to provide design  and  implementation  lessons  and  evidence  to  practitioners  and  policy  makers  of  the  SHD  and  similar  development programs 39  Although  the baseline  is  financed  by  a  trust  fund  yet  it  required  identification  of  the  disadvantaged Village Development Committees (VDCs) and few poorest wards in the selected VDCs to come up with the sample of treatment and control groups for the study. 

Page 33: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 27 of 57  

      

Justification of Overall Rating of Quality of M&E Overall rating: Substantial  

73. Justification Despite the shortage of human resources to carry out monitoring activities, the project managed to put in place innovative mechanisms to capture progress and fully capture the impact of the project. 

 

B. ENVIRONMENTAL, SOCIAL, AND FIDUCIARY COMPLIANCE Environmental Compliance  

74. As per the Bank’s standards, the Environmental and Safeguards Management Framework (ESMF) was prepared during project preparation to address possible environmental and social issues.  The ESMF was included in the operation manual  of  the  project.  Key  environmental  and  social  management  guidelines  were  prepared  for various interventions and included in the coaches’ training manuals and during the trainings for DDC/VDC level stakeholders. This enhanced their ability to address safeguard issues on the ground and help communities to implement the activities with full compliance to the environmental and social safeguard guidelines.  

75. Several  environmental  issues  regarding  contamination  of  water  sources  and  water  quality  were  raised  by communities following the earthquake. The Bank worked with the DDCs and UNICEF to support protection of water sources and rehabilitation of water supply.  

76. The Bank team conducted several visits to different project sites to observe sub‐project implementation. In most cases, environmental safety standards were followed. For example, a visit was conducted to the Okhaldhunga district on February 24, 2017 and the team noted that the toilet constructed for open defecation free conformed to  the  environmental  standards.  Likewise,  communities who  selected  the  focus  area of  increasing  intake of animal source protein had constructed chicken coops, and it was observed that improved cooking stoves have been constructed for reducing indoor air pollution. These initiatives have improved the health of women through better  indoor air quality,  significantly  reduced  the drudgery of  local women by supplying potable water and improved the overall sanitation. However, visit to Sindhuli and Ramechhap districts on May 30, 2017, revealed that  few  sub‐projects  were  not  fully  compliant  with  the  environmental  safety  standards  and  have  been encouraged to stick to safeguard compliance when designing the work plan for the sub‐projects. 

Social Compliance  

77. The project triggered the Bank’s Safeguard policy for ‘Indigenous People’ (OP4.10) to ensure that any adverse effects  of  the  activities  on  indigenous  people  are  minimized  or  avoided.    During  implementation,  several measures were followed to ensure minorities inclusion in all project activities including their active participation in the RRNI teams. Both of the project’s intermediate results indicators on minority and women participation on RRNI teams have been met.   

78. To ensure incorporation of the citizens’ voice, the training package for DDC/VDC included a grievance handling mechanisms, coaches and social mobilizers were oriented to handle grievance as the first point of contact for the complainants, and complaints referred to the VDC secretary for decision. However, if the grievance needed to  be  escalated  higher,  then  the  final  decision  rested with  the  Local Development Officer  of  the  respective district.  

 

Page 34: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 28 of 57  

      

Financial Management Compliance  

79. Despite  considerable  efforts made  by MOFALD  in  building  its  financial  management  capacity,  a  number  of challenges were persistent throughout the course of the project. For the first year of project implementation, there was no dedicated full‐time accountant (although this was one of the agreed actions during negotiations). The  assessment  of  the  financial management  capacity  of  the DDCs was only  done  after  the  second  year  of implementation and it highlighted the significant lack of FM capacity at the DDCs level.  

80. The project had a slow pace of flow of funds due to the delays  in establishing  institutional arrangements for rolling‐out  the  sub‐projects.  The  FM performance  (including  flow of  fund)  improved  after  restructuring,  but slowed down again in the last year of implementation due to pending settlements of sub‐projects that had not provided  Statement  of  Expenditures  (SoE).  The  rating  of  FM  performance  was  thus  rated  moderately unsatisfactory in the last two Implementation Status and Result Reports (ISRs). The disbursement from the Bank was thus affected as it was agreed to not claim reimbursement without confirmation of advanced settlement.  

Procurement Compliance  

81. The Project suffered delays in the implementation of procurement activities agreed in the procurement plan at the initial stage of the project, which however, quickly picked up, and by the time of project closing all planned procurement was completed. The initial delays were due to inadequate budget and delays in hiring a dedicated procurement staff throughout the first year of implementation.     

82. In addition to hiring consulting firms for BBC, digital MIS and other goods and services, the project had two high value procurement activities:  (i)  to hire National  Service Providers  (NSP)  for all  the  three clusters who were responsible for hiring the coaches, and (ii) to engage UNICEF for the earthquake relief component. As coaches facilitated  the  implementation  of  the  community  driven  nutrition  initiatives,  the  delays  of  hiring  the  NSPs resulted in delays in rolling out the project activities. The PMT proactively terminated the contracts of NSP in clusters 1 and clusters 2 eight months prior to closing due to their default in fulfilling contractual obligations. UNICEF was  financed  through  a  Technical  Assistance  and  Related  Supplies  contract  with MOFALD  and was responsible for supplying all required inputs for the delivery of the targeted outputs agreed with MOFALD and the Bank.  

 

C. BANK PERFORMANCE  

Quality at Entry 

83. The project was well aligned with the GoN’s response to the persistent problem of malnutrition. As mentioned above, while the team ensured adequate consultations and detailed preparation for the startup period ‐with a planned  pilot  at  smaller  scale  before  rolling  out,  the  implementation modality  that  was  chosen was  highly innovative and may have been overly ambitious for Nepal’s context. However, it was well acknowledged that the informal NGO sector and community outreach was well developed and therefore this approach was selected. 

84. The Bank team recognized the weak capacity of the main counterpart but did not anticipate the delay in the hiring of the coaches and that it would take that much longer to get the process started.  Also, the team could have likely done better to anticipate the lengthy approval process and the associated funds flow mechanism.  

Page 35: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 29 of 57  

      

More analysis should have been done to address potential bottlenecks. 

85. Project preparation benefited from a Quality Enhancement Review on March 27, 2012. Reviewers helped the project team to sharpen the focus of the PDO and enhance the M&E design. While the project took a very specific focus on addressing the root causes of malnutrition at the individual and community level, it was wise that the project  set  realistic  expectations  that  actual  improvement  in  nutrition  outcomes  would  not  necessarily  be captured during the project period.    

86. The  Bank  team  was  likely  overly  ambitious  in  expecting  that  communities  would  select  all  15  types  of interventions; however, it did not mandate any ceilings or limitations on selection.  In this way, the Bank team allowed for a flexible approach to implementation.  As a result, it was also difficult to predict the exact costs of the project and the team decided to allow for more funds to ensure there was no financing gap.  In a sense, this was a pilot project which was to yield lessons for ways to address the malnutrition problem in Nepal. What was certainly not anticipated was the Nepal earthquake and ironically the project funds were able to be used support the aftermath of the crisis.  

87. The overall quality at entry therefore is considered as Moderately Satisfactory. 

 

Quality of Supervision 

88. Regular and sustained engagement with the Project Management Team. The project benefited from a steady and committed Bank team. The project had two task team leaders, the first TTL was in charge of the design and the first two years of implementation. Both initial and subsequent TTLs were based in Nepal and were able to work closely with project counterparts and provide adequate supervision support with at least two supervision missions per year and regular field visits. Please refer to Annex 2 for list of task team members.  

89. The  project  benefited  from  a  successful  MTR  (February  2015).  As  mentioned  above,  the  MTR  identified implementation obstacles and decided on restructuring the project to enhance project performance. This led to efficiency gains and smoother implementation.   

90. The Bank team was responsive to the emergency nutrition issues which arose from the devastating effects of the April 25, 2015 earthquake and its aftershocks in critically affected districts. The team proactively worked with  MOFALD  to  contract  UNICEF  to  take  the  technical  lead  to  support  the  delivery  of  essential  nutrition interventions to women and children in the affected areas.  

91. Monitoring and reporting. ISRs documented regularly (biannually) and included candid and detailed assessment of project progress and implementation challenges.  

92. M&E,  safeguards  and  fiduciary  compliance.  The  Bank  team made  a  significant  effort  to  ensure  close M&E supervision which included qualitative and quantitative data  in addition to third party monitoring.   The Bank team supervised the environmental and social safeguards of the sub‐projects and conducted field visits to ensure compliance. Despite the fact that the Bank provided extra support to address the weaknesses in project FM, the delays in reporting SoE and reimbursement could not be entirely resolved.       

93. The quality of supervision is considered Satisfactory. 

Page 36: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 30 of 57  

      

 

Justification of Overall Rating of Bank Performance 

94. The ICR rates overall Bank performance as Satisfactory in view of the overall outcome rating of Satisfactory.   

 

D. RISK TO DEVELOPMENT OUTCOME 

95. The main risks to sustain project outcomes are as follow: 

‐The project helped in raising awareness and improved understating of nutrition at different levels including communities  and  stakeholders.  However,  sustainable  changes  in  ‘some’  practices  might  require  longer implementation period (more than 100 days) and continuous support. In the focus group discussion conducted by  the  qualitive  study,  participants were  confident  that  some  of  the  changes  are  sustainable  such  as  the construction of toilets which has been accompanied by tailored behavior change messages.  

‐Overall, the project helped in strengthening organizational capacity. Extensive training programs have taken place under the project and several rounds of boosters have been provided to PMT staff at MOFALD, NFSSCs at DDC and VDC levels, coaches, social mobilizers and FM officers. Under federal restructuring, there will be movement  of  officials  across  sectors  and  different  levels  of  government.  However,  these  officials  whose capacity was enhanced through the project are likely to contribute to nutritional outcomes even if they are placed in other sectors as nutrition interventions require a multi sector effort (please refer to Annex 5).   

 

V. LESSONS AND RECOMMENDATIONS 

96. Rapid  Result  Approach  (RRA)  which  uses  a  series  of  mini  projects,  implemented  typically  in  100  days, demonstrated good  results  in  creating  a momentum and  inspiring  communities  to  adapt  behavioral  changes related to nutrition.   

97. While giving the communities the freedom to choose builds ownership, the ability to choose without enough education and advocacy  is a  risky approach which  requires more capacity building at  the outset. The project design followed a demand based approach, and  implemented a number of activities to generate demand for good nutrition outcomes. However, communities tend to ask for tangible outputs like building toilets, piped water supply for safe water, and improved cooking stoves while they focus less on the importance of softer outputs such as awareness and support on exclusive breastfeeding or sexual reproductive health.  

98. Implementing an innovative project in a country with limited human resources has been a steep learning curve. The project had initial delays due to lack of support at district levels. However, the timely restructuring of the project  in  June  2015  brought  greater  implementation  efficiency  and  better  quality when  additional  capacity building activities and  institutional strengthening measures have been added. The results of the restructuring could be seen during the last year of project implementation when a greater number of sub‐projects kicked off and disbursement increased tremendously.   

99. Inclusion of women in the RRNI process was fundamental in addressing women and children nutrition needs. The project made a  conscious effort  to  integrate women and ensure  their  active participation  in  the whole RRNI process. This has helped in empowering women and provided them with an opportunity to voice their health and 

Page 37: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 31 of 57  

      

nutrition needs. 

100. Addressing malnutrition in a sustainable manner needs the entire community – men, women, minority groups, and  local  leaders  and  authorities  –  to  raise  awareness  on  the  importance  and  concrete  ways  of  improving knowledge and behavior. 

101. It seems that the project had been named with an appropriate and catchy title in Nepali. “Sunaula Hazar Din” or “Golden 1000 days”, which was coined at the project formulation, has become a “brand name” now in Nepal. This phrase is now synonymous to the first 1000 days of early childhood nutrition and health and is understood by all people. 

102. Given that the SHD is one of the first initiatives in Nepal and in the world to implement the RRA on the large scale, i.e., across 15 districts of the country, from the onset, the project team have recognized the importance of conducting a rigorous evaluation and relevant studies of SHD’s experiences and achievements which helped in assessing different elements of the project and capture the lessons learned.  

103. The  emergency  relief  component  provided  a  great  learning  experience  in  collaborating  with  development partners. In response to the urgent humanitarian crisis that happened in Nepal after the 2015 earthquake, the project team worked side by side with UNICEF and the ministry team to provide a comprehensive response.  

   

 

 

   . 

Page 38: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 32 of 57  

      

ANNEX 1. RESULTS FRAMEWORK AND KEY OUTPUTS 

      A. RESULTS INDICATORS  A.1 PDO Indicators       

 Objective/Outcome: Improve practices that contribute to reduced under‐nutrition of women of reproductive age and children under the age of two. 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Percentage of pregnant women taking iron and folic acid (IFA) supplements for 180 days 

Percentage  21.00  30.00  30.00  27.00 

  03‐Feb‐2014  03‐Feb‐2014  30‐Jun‐2017  30‐Jun‐2017 

 

Comments (achievements against targets): Target is partially achieved. 

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Percentage of children 0‐6 months age who are exclusively breastfed 

Percentage  69.00  80.00  80.00  58.00 

  03‐Feb‐2014  03‐Feb‐2014  30‐Jun‐2017  30‐Jun‐2017  

Comments (achievements against targets): Target has not been achieved. 

   

Page 39: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 33 of 57  

      

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Percentage of children 6‐24 months age who consume a minimum acceptable diet 

Percentage  9.00  25.00  25.00  15.00 

  03‐Feb‐2014  03‐Feb‐2014  30‐Jun‐2017  30‐Jun‐2017  

Comments (achievements against targets): Target has not been achieved. 

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Percentage of households reporting no smoke in the room while cooking 

Percentage  35.00  0.00  45.00  39.00 

  03‐Feb‐2014  03‐Feb‐2014  30‐Jun‐2017  30‐Jun‐2017  

Comments (achievements against targets): Target has not been achieved. 

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Percentage of pregnant women reporting consuming animal‐sourced protein in the previous day 

Percentage  60.00  0.00  75.00  76.00 

  03‐Feb‐2014  03‐Feb‐2014  30‐Jun‐2017  30‐Jun‐2017 

 

Comments (achievements against targets): Target has been surpassed. 

   

Indicator Name  Unit of Measure  Baseline  Original Target  Formally Revised   Actual Achieved at 

Page 40: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 34 of 57  

      

Target  Completion 

Percentage of households reporting using improved toilet facilities (flush toilet, covered pit within household, community latrine) 

Percentage  25.00  0.00  35.00  80.00 

  03‐Feb‐2014  03‐Feb‐2014  30‐Jun‐2017  30‐Jun‐2017 

 

Comments (achievements against targets): Target has been surpassed. 

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Percentage of mothers (of children aged 0‐2) reporting always washing hands at critical times (after defecation) 

Percentage  71.00  0.00  80.00  98.00 

  03‐Feb‐2014  03‐Feb‐2014  30‐Jun‐2017  30‐Jun‐2017 

 

Comments (achievements against targets): This PDO indicator is composite of 4 indicators: washing hands before defecation (baseline:71%, target 80%, achieved: 98%) , washing hands after cleaning child’s bottom (baseline:53%, target 70%, achieved: 76%), washing hands before eating (baseline:17%, target: 25%, achieved:57%), washing hands before feeding the children (baseline: 10%, target:20%, achieved: 39%). All targets have been surpassed. 

     

 Objective/Outcome: Provide emergency nutrition and sanitation response to vulnerable populations in Earthquake affected areas. 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Number of children 6‐59 months in the earthquake affected districts with Severe 

Number  0.00  0.00  4000.00  4299.00 

  21‐May‐2015  21‐May‐2015  30‐Jun‐2017  30‐Jun‐2017 

Page 41: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 35 of 57  

      

 

Acute Malnutrition receiving therapeutic care  

Comments (achievements against targets): Target has been surpassed. 

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Number of households in the earthquake affected districts provided with hygiene and sanitation kits (water treatment products and so ap) 

Number  0.00  0.00  45000.00  80013.00 

  21‐May‐2015  21‐May‐2015  30‐Jun‐2017  30‐Jun‐2017 

 

Comments (achievements against targets): Target has been surpassed. 

  

 A.2 Intermediate Results Indicators      

 Component: Rapid Results for Nutrition Initiatives at the ward level 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Number of RRNIs completed (disaggregated by 15 focus areas) 

Number  0.00  0.00  10000.00  8950.00 

  16‐Jul‐2012  16‐Jul‐2013  30‐Jun‐2017  30‐Jun‐2017  

Comments (achievements against targets): Disaggregated by focus areas during the project period: Adequate weight and regular eating‐ 12% 

Page 42: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 36 of 57  

      

 Consumption of animal Sourced food‐ 13% Clean water‐ 22% Open Defecation Free‐ 13%  

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Number of RRNIs per ward per year 

Number  0.00  0.00  2.00  1.40 

  16‐Jul‐2012  16‐Jul‐2012  30‐Jun‐2017  30‐Jun‐2017  

Comments (achievements against targets):  

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Characteristics of RRNI teams: % females participating in all RRNIs 

Percentage  0.00  0.00  40.00  68.50 

  16‐Jul‐2012  16‐Jul‐2012  30‐Jun‐2017  09‐Mar‐2017  

Comments (achievements against targets):  

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Characteristics of RRI teams: % minority participation in all RRNIs 

Percentage  0.00  0.00  40.00  63.30 

  16‐Jul‐2012  16‐Jul‐2012  30‐Jun‐2017  09‐Mar‐2017  

Page 43: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 37 of 57  

      

 Comments (achievements against targets):  

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Percentage of RRNIs achieving 80% of their targets 

Percentage  0.00  0.00  75.00  92.00 

  16‐Jul‐2012  16‐Jul‐2012  30‐Jun‐2017  09‐Mar‐2017  

Comments (achievements against targets):  

     

 Component: Project management, capacity building, monitoring and evaluation 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Average time between RRNI proposal submission and fund release to communities (days) 

Days  0.00  0.00  60.00  73.00 

  16‐Jul‐2012  16‐Jul‐2012  30‐Jun‐2017  09‐Mar‐2017 

 

Comments (achievements against targets):  

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Number of coaches trained  Text  0  200  300  311 

  16‐Jul‐2012  16‐Jul‐2012  30‐Jun‐2017  09‐Jun‐2017  

Page 44: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 38 of 57  

      

 Comments (achievements against targets): Male 113 and female 198 

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Percentage of RRNIs publicly audited as part of citizen engagement 

Percentage  0.00  90.00  100.00  85.10 

  16‐Jul‐2012  16‐Jul‐2012  30‐Jun‐2017  09‐Mar‐2017  

Comments (achievements against targets):  

     

 Component: Earthquake relief component. 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

No. of mothers & caregivers of 6‐23 mo. counseled for appropriate complementary feeding, frequency & diversity of foods, and continued breastfeeding for up to 24 mo. in earthquake affected districts 

Number  0.00  50000.00  50000.00  169701.00 

  15‐May‐2015  15‐May‐2015  30‐Jun‐2017  30‐Nov‐2016 

 

Comments (achievements against targets):  

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Page 45: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 39 of 57  

      

 

Number of children 6‐59 months old in the earthquake affected districts with moderate acute malnutrition (MAM) receiving supplementary food 

Number  0.00  18000.00  18000.00  36101.00 

  15‐May‐2015  15‐May‐2015  30‐Jun‐2017  30‐Nov‐2016 

 

Comments (achievements against targets):  

   

         

Page 46: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 40 of 57  

      

B. KEY OUTPUTS BY COMPONENT   

Objective/Outcome 1 

 Outcome Indicators 

1. Attitude of community members towards the importance of keeping girls in school until at least 20 years of age 

2.  Attitude  of  community  members  towards  the  importance  of reducing indoor air pollution 

3.  Attitude of pregnant women towards the importance of eating three time a day including at least one animal‐sourced food per day 

Intermediate Results Indicators 

1. Number of RRNIs completed (disaggregated by 15 focus areas). 

2. Number of RRNIs per ward per year. 

3. Percentage of RRNIs achieving 80% of their targets. 

Key Outputs by Component (linked to the achievement of the Objective/Outcome 1) 

1.Rapid Results for Nutrition Initiatives (RRNIs) implemented by communities at ward level, with each RRNI dedicated to achieve one of pre‐defined nutrition related goals  selected by targeted communities. 

Objective/Outcome 2 

 Outcome Indicators 

1.  Percentage  of  pregnant  women  taking  iron  and  folic  acid  (IFA) supplements for 180 days 

2. Percentage of children 0‐6 months age who are exclusively breastfed 3. Percentage of children 6‐24 months age who consume a minimum 

acceptable diet 4.  Percentage  of  households  reporting  no  smoke  in  the  room while 

cooking 

Page 47: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 41 of 57  

      

5.  Percentage  of  pregnant  women  reporting  consuming  animal‐sourced protein in the previous day 

6. Percentage of households reporting using improved toilet facilities (flush toilet, covered pit within household, community latrine) 

7.  Percentage  of  mothers  (of  children  aged  0‐2)  reporting  always washing hands at critical times (after defecation) 

Intermediate Results Indicators 

1. Number of RRNIs completed (disaggregated by 15 focus areas). 

2. Number of RRNIs per ward per year. 

3. Percentage of RRNIs achieving 80% of their targets. 

Key Outputs by Component (linked to the achievement of the Objective/Outcome 2) 

1. Rapid Results for Nutrition Initiatives (RRNIs) implemented by communities at ward level, with each RRNI dedicated to achieve one of pre‐defined nutrition related goals  selected by targeted communities. 

Objective/Outcome 3 

 Outcome Indicators 

1. Number of children 6‐59 months in the earthquake affected districts with Severe Acute Malnutrition receiving therapeutic care 

2. Number of households in the earthquake affected districts provided with hygiene and sanitation kits (water treatment products and  

soap) 

Intermediate Results Indicators 

1. No. of mothers & caregivers of 6‐23 mo. counseled for appropriate complementary feeding, frequency & diversity of foods, and continued breastfeeding for up to 24 mo. in earthquake affected districts 

Page 48: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 42 of 57  

      

2. Number of children 6‐59 months old in the earthquake affected districts with moderate acute malnutrition (MAM) receiving supplementary food 

Key Outputs by Component (linked to the achievement of the Objective/Outcome 2) 

1. Provide nutrition care and treatment to severely acute malnourished (SAM) and moderately acute malnourished (MAM) children, and malnourished mothers. 

   

  

Page 49: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 43 of 57  

      

 

ANNEX 2. BANK LENDING AND IMPLEMENTATION SUPPORT/SUPERVISION 

 

A. TASK TEAM MEMBERS 

 Preparation 

Name  Role 

Albertus Voetberg  Lead Health Specialist/Task team Leader 

Maria E. Gracheva  Senior Operations Officer 

Mohammad Khalid Khan  Program Assistant 

Bigyan B. Pradhan  Sr Financial Management Specialist 

Roshan Darshan Bajracharya  Senior Economist 

Kiran R. Baral  Senior Procurement Officer 

Gayatri Acharya  Senior Economist 

Venkatesh Sundararaman  Senior Economist 

Afrah Alawi Al‐Ahmadi  Senior Human Development Specialist 

Phoebe M. Folger  Operations Officer 

Tekabe Ayalew Belay  Sr Economist (Health) 

Drona Raj Ghimire  Environmental Specialist 

Hiramani Ghimire  Senior Governance Specialist 

Mohan Prasad Aryal  Operations Officer 

Silva Shrestha  Research Analyst 

Luc Laviolette  Sr Nutrition Spec. 

Jasmine Rajbhandary  Social Protection Specialist 

Jaya Karki  Team Assistant 

Shambhu Prasad Uprety  Procurement Specialist 

Saurav Dev Bhatta  Senior Education Specialist 

Bandita Sijapati  Consultant 

Manav Bhattarai  E T Consultant 

      

Page 50: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 44 of 57  

      

Name  Role 

Supervision/ICR 

Manav Bhattarai  Task Team Leader(s) 

Shambhu Prasad Uprety  Procurement Specialist(s) 

Timila Shrestha  Financial Management Specialist 

Kari L. Hurt  Team Member 

Jaya Sharma  Social Safeguards Specialist 

Phoebe M. Folger  Team Member 

Abeyah A. Al‐Omair  Team Member 

Jaya Karki  Team Member 

Ramesh Raj Bista  Team Member 

Annu Rajbhandari  Environmental Safeguards Specialist 

       

B. STAFF TIME AND COST 

Stage of Project Cycle Staff Time and Cost 

No. of staff weeks  US$ (including travel and consultant costs) 

Preparation 

FY11  0  6,096.45 

FY12  44.964  206,974.98 

FY13  8.312  18,265.73 

FY16  0  3,135.60 

FY17  0  91,445.05 

FY18  0  1,035.60 

Total  53.28  326,953.41  Supervision/ICR 

FY12  1.726  7,495.35 

FY13  44.524  178,696.69 

FY14  61.946  251,523.91 

Page 51: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 45 of 57  

      

FY15  48.815  147,161.79 

FY16  49.059  123,159.12 

FY17  57.195  137,527.93 

FY18  15.675  56,186.85 

Total  278.94  901,751.64     

  

   

Page 52: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 46 of 57  

      

ANNEX 3. PROJECT COST BY CATEGORIES 

  

Components Amount at Approval  

(SDR‐M) 

Amount at Project 

Restructuring (SDR‐M) 

Actual amount at project closing 

(SDR‐M) 

Percentage of Approval (based on 

the amount at restructuring) 

Sub‐grants for ‐Rapid Results for Nutrition Initiatives at the ward level. 

19.6  12.2 

  

12.4 102% 

Consulting Services and training 

2.1  2.1  

 1.2 

57% 

Goods, non‐consulting services and incremental operating costs 

4.2  3.0 

 0.7 

20% 

Eligible expenditures under component 3‐Earthquake Relief Component 

0.00  8.6 

 8.5 

98% 

Total    25.9  25.9  22.8     88% 

  

   

Page 53: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 47 of 57  

      

ANNEX 4. EFFICIENCY ANALYSIS 

Assessment of Efficiency and Rating 

1. It  is  evident  that  the  returns on  investing  in nutrition  are  very high.  According  to  the World Bank  report40, malnutrition slows economic growth and increases poverty through direct costs from increased burden on the health care system, and indirect costs from lost productivity. Not addressing malnutrition has high costs in terms of higher budget outlays as well as lost GDP.  

2. An analysis of several countries indicates that the returns from programs for improving nutrition far outweigh their costs. Overall economic costs of malnutrition run to as high as 2 to 3% of the growth of GDP of developing countries.  According  to  the World  Health  Organization  (WHO),  underweight  is  the  single  largest  risk  factor contributing to the global burden of disease in the developing world. It leads to around 15% of the total DALY (disability‐adjusted life years) losses in countries with high child mortality. 

3. It  is  estimated  that  Nepal  loses  nearly  $190 million  annually  in  GDP  to  vitamin  and  mineral  deficiencies. Childhood anemia alone is associated with a 2.5% drop in adult wages41 (Harton S. and Ross the Economics of Iron deficiencies). Similarly, a 1% loss in adult height as a result of childhood stunting is associated with 1.4% loss in productivity. In addition to its effect on immune function, poor nutrition also increases susceptibility to chronic diseases in adulthood. Low birthweight may reduce a person’s IQ by 5%, stunting ,ay reduce it by 5‐11%, and iodine deficiency by nearly 10‐15%41.  

4. A costing exercise conducted by the World Bank to determine the annual cost of scaling‐up well proven nutrition interventions in high burden countries shows that such investments give very high economic returns.   Table 7 below  illustrates  the  cost‐benefit  ratio  of  a  number of  focus  areas  of  the  RRNI.  Similarly,  the  Lancet  series42 estimated the cost of handwashing counselling that can lead to 30% reduction in the risk of diarrhea, a direct cause of malnutrition (see table 7). 

  

Table 7. Estimated Benefits from Scaling‐up Nutrition Interventions 

Intervention  Estimated benefit: cost rations or cost‐effectiveness  

Behavior  change  through  community nutrition programs 

US$ 53‐153 per DALY 

Hygiene promotion  US$ 3.35 per DALY 

Iron‐folic acid supplements  US$ 66‐115 per DALY (iron) 

Complementary foods  US$ 500‐1000 per DALY 

Latrine construction  US$ 270 per DALY43                          Source: Horton,S., et al. Scaling‐Up nutrition; What Will it Cost?, World Bank,2010 

5. Based on nutrition data from the Institute for Health Metrics and Evaluation (IHME), during the project life (2011‐2016) the number of estimated direct deaths associated with nutritional deficiencies in all ages, was 

                                                                 40https://siteresources.worldbank.org/NUTRITION/Resources/2818461131636806329/NutritionStrategyOverview.pdf  accessed December 12, 2017 41 http://siteresources.worldbank.org/NUTRITION/Resources/281846‐1271963823772/Nepal.pdf accessed Dec 5,2017 42 http://www.thelancet.com/article/S0140‐6736(07)61693‐6. Accessed March 5, 2018 43 https://globalhandwashing.org/about‐handwashing/why‐handwashing/economic‐impact/ Accessed March 5,2018 

Page 54: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 48 of 57  

      

reduced from 0.59% to 0,49%. The estimations of the number of deaths at age 0‐12 months by nutrition deficiencies reduced from 348 to 225, between 2011 to 2016. 

6. The project was characterized by strong technical efficiency and targeting resources to the neediest populations. The global evidence shows that behavioral change and community based interventions are among the most cost‐effective interventions to improve nutrition outcomes, with some of the highest cost‐benefit ratios in terms of poverty reduction and economic development. The project made substantial contributions to improving equity and targeting resources to the neediest populations. The selection of districts (15 out of 75 districts) under the project was based on population density, stunting levels, poverty levels and absence of overlapping interventions by other partners. Within the selected districts, SHD targeted 25% of the most disadvantaged VDCs. Similarly, the emergency relief component activities targeted the most critically affected districts.     

7. Implementation efficiency: The efficiency of project execution, as measured by the speed of disbursement, was not strong in the first year of implementation. There were initial delays in starting project activities which was expected given the novelty of the approach. However, implementation efficiency improved on the second year of  implementation  as  there  was  a  better  understating  of  the  projection  implementation  modality  among stakeholders as well as community members. The implementation efficiency has further improved after project restructuring  as  the  project modified  its  fiduciary  and  implementation  arrangements  to  improve  quality  and efficiency (see para 16 for more details) and added a third component (emergency relief component).  

8. Since the project adopted a demand‐driven approach and relied on mobilizing communities to collectively commit to address one of the risk factors of malnutrition, the initially estimated budget for the RRNIs could not be precise but sufficient funds were allocated to allow communities to implement sub‐projects in all selected districts. At the MTR, it became clear that not all funds would likely be absorbed and hence when the earthquake took place, US$12 million could be reallocated.   Notably, despite the earthquake, the project closed within the stipulated time frame and completed most of its envisioned activities. The project disbursed 87% (31.58M out of 35.9MSDR) of its commitment by closing.   

9. Considering the very high cost‐effectiveness of the interventions, coupled with the novel approach to improve nutritional outcomes at the community level, the completion of the project by its original closing date, the overall efficiency is considered to be Substantial. 

 

         

   

Page 55: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 49 of 57  

      

ANNEX 5. BORROWER, CO‐FINANCIER AND OTHER PARTNER/STAKEHOLDER COMMENTS 

 

1. Community  Actions  for Nutrition  Project:  Sunaula Hazar Din was  successfully  implemented  to  reduce malnutrition mainly focusing to the central  terai and mid hill of  the country. The primary  focus of the project was to reduce malnutrition implementing through local governance structure namely then the VDCs and DDCs. At the time of implementing the project, the NDHS 2011 report came out with the finding of 41% children under 5 years of age were stunting, 11% wasting and 29 underweight. The concentration of malnutrition was obvious in the area of high densely populated, weighted poverty and dalit as well as backward  community.  Considering  the  fact  and  figures,  the  project  was  implemented  in  15  districts namely Khotang, Okhaldhunga, Udayapur, Sunsari, and Saptari in Cluster I, Ramechap, Sindhuli, Siraha, Mahottari and Sarlahi in Cluster II and Makawanpur, Bara, Parsa, Rautahat, and Sarlahi in Cluster III. In total 25% VDCs (approximately 292 VDCs) of the 15 districts were selected based on Disadvantaged Group (DAG) mapping. The project was supposed to start implementation from FY 2012/13 but couldn't come to effect till March 2014 because of procurement delayed in placing National Service Providers (NSPs) in each cluster. Though, the piloting of the project was carried out in Sindhuli district in FY 2031/14 but real field work got started in the last trimester of FY 2013/14. The project got implemented in phase in strategy as early starter and later starter for the sake of impact evaluation.  

2. The project adopted a unique approach of community demand driven known as Rapid Results Approach in which the targeted community frames their need and aspiration outlining as Rapid Results Nutrition Initiatives (RRNI). The RRNI thrives to achieving nutritional outcomes within 100 days selecting from the given focus area and implemented at particular settlement by the community people themselves officially known as RRNI Team. The process of the approach was pre‐launch meeting, launch meeting /workshop, mid‐point review and sustainability review with in a 100 day. The entry point of the each RRNI begins from the lower level of local governance unit known as Ward Citizen Forum (WCF).  

3. As to smooth  implementation of  the project different  implementation arrangement were set up  from central level to grass root level. A Project Coordination Committee (PCC) was formed headed by the head of division of  self‐governance division of  the Ministry and members  representatives  from the sectoral Ministries including National Planning Commission. The role of the committee was to coordinate at central level.  In addition, Project Management Team (PMT) was also formed to functionalize day to day project works in leadership of Joint Secretary comprising the officials of the ministry and technical expert team for  the  project.  Likewise,  a  district  Nutrition  and  Food  Security  Steering  Committee  headed  by  Local Development Officer (LDO) comprised of the members from different sectors at all 15 districts including NGO federation and private sectors. Similarly, same nature of steering committee was formed 292 the VDCs.   

4. As  Rapid  Results  Approach  was  new  for  the  Ministry,  a  pilot  test  was  done  before  the  project implementation  took  off.  It  was  done  in  2  VDCs  of  Sindhuli  district  namely;  Bhimeshwor,  Ratamata JhangaJholi.  Based  on  the  learnings  of  the  pilot  project,  considering  the  financial  agreement  of Government of Nepal and  the World Bank and  referencing other  related  legal documents; a  separate operational  manual  was  developed  as  one  of  the  milestones  which  paved  the  way  of  RRNI selection/development,  implementation  modality,  fund  flow  mechanism  and  financial arrangement/settlement. As to introduce the operational manual separate cluster level orientation was carried out in Biratnagar, Janankpur and Hetauda on 20 January 2014,  22 January 2014 and on 24 January 

Page 56: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 50 of 57  

      

2014  respectively  inviting  all  sectors  (local  governance,  agriculture,  livestock,  education,  water  & sanitation and women & children) representatives at each districts.  Ministry also awarded to 3 NGOs in all the 3 clusters to hire a coach in each VDCs. The coaches and concerned staffs were also oriented as basic  RRNI  implementation  training  followed  by  different  capacity  building  interventions  known  as booster training and review meetings.  

5. The project has defined 15 focus area of  interventions. Based on facilitation of coaches, the picked‐up focus area to be implemented in respect to the needs and aspiration of the community. Selection of focus area was in increasing trend for the last 4 years (070/71 to 73/74). It was counted as 832 in the base year FY 070/71 increasing to 1991 to 3427 in 71/72 and 72/73 respectively. But it was reduced to 2646 in 73/74.  Total was  9096  combining  all  the  15  focus  areas.  Out  of  15  focus  areas ODF was  highest  demanded followed by clean water. Similarly, immunization was in lowest position followed by family planning.  In addition, amidst the project implementation, the country felt some devastated effects of the earthquake of 7.9 magnitudes on April 25, 2015 followed by strong aftershocks which affected some 39 districts of the  country  where  some  14  districts  were  highly  affected  by  the  earthquake.  Realizing  this  alarming situation of the country MoFALD contracted to UNICEF to address the severe condition of malnutrition in emergency and to support and contribute to the government’s early relief and recovery efforts.  

6. As to vibrate and functionalize all actors involved in the project; national, sub‐national, district and village level orientation and review workshops were carried out aiming to inform / sharing status of project to stakeholders. The event addressed by the Honorable Minister and Secretary reflected the national priority in  investing  children  and  women.  As  to  transfer  knowledge,  a  training  package  was  developed  and delivered to Nutrition and Food Security Steering Committee at district and VDC level. The main objective of the assignment was to strengthen capacity of the central project management team, district and village level  stakeholders  including  the  line  ministries/agencies  and  social  mobilizers/coaches.  The  project organized  booster  training/s  primarily  focusing  on  strengthening  skills  and  knowledge  on  proposal preparation and other areas as well.  

7. Having enormous efforts of the Ministry, the numbers of layers from district to VDC to RRNIs, the delivery of the project couldn't be as expected. Functional role of the sectoral agencies like health, agriculture, education, women were relevant at local level but couldn't be respected properly. MoFALD has realized that the project was one which solely respects the demand of the community and brings the community to implement themselves. The number of best practices and positive behavior at the community need to be  sustained.  For  the  same  the newly  formed  federal  government  has  transferred  Sunaula Hazar Din Program  to  local  government;  rural  municipality  and  municipality.  Hence,  the  spirit  of  project  will definitely expand widely at local level. However, the sequel of the project is highly demanded and required since there pessimistic progress of reducing stunting, wasting and underweight.   

   

Page 57: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 51 of 57  

      

 

ANNEX 6. SUPPORTING DOCUMENTS  

Focus areas and examples of Goal Templates

Focus Areas 1  Adequate Weight and Regular Eating 2  Animal Source Food for pregnant mothers and children 3  Breastfeeding 4  Clean Water 5  Delayed Marriage 6  De‐worming and Iron Supplementation  7  Extending Education  8  Hand Washing 8  Family Planning 10  Immunization of children 11  Open defecation Free 12  Prompt Medical Treatment 13  Reduce Workload 14  School Sanitation 15  Smoke Reduction 

  

NEPAL:  Sunaula Hazar Din – Community Action for Nutrition Project  

Girls and young women aged 15 to 25 (Priorities: Anemia, Delayed Pregnancy, School Attendance)  These RRNIs would be implemented primarily by youth aged 15 to 25.  Senior leaders would mostly likely be members of an SMC, Citizen Ward Forum, FSNC. Alternatively the team could be formed from an existing youth‐focused group.  The primary focus of these RRIs would be youths.  However, at the group’s discretion, for some goals there could be overlap into other sub‐populations (e.g. the goal focused on FP could focus on all women who want to delay a first or next pregnancy and not just youths). 

Goal Template  Illustrative Sub‐projects  

At least ___ families with adolescent girls make a public pledge to delay  marriage and first pregnancy  of daughter(s) until at least 20 years of age, in the next ___ days 

Training for health facilities to provide youth‐friendly services, peer program, positive deviance analysis, establishment of youth center, community based services for the youth 

At least ___ girls of school‐going age who do not want to become pregnant are regularly attending school , in the next ___days 

Provision of school supplies, mid‐day meals, take‐home rations, performance based grants 

At least ___ girls receive de‐worming and weekly iron‐folic acid 

supplementation, for the next ____ weeks.  

Peer programs, health worker visits to schools 

At least ___ girls/women who do not want to become pregnant are using a family planning method,  in the next ___ days 

Training for health facilities to provide youth‐friendly services, establishment of youth center and community based services for the youth 

 

Page 58: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 52 of 57  

      

Pregnant women or women who want to become pregnant in the next 6 months. (Priorities:  Protein, Iron, Smoking, Breastfeeding) These RRNIs would mostly like be implemented by mother’s/women’s groups, or an existing health‐focused group.  Senior leaders would be from Ward Citizen Forum or NFSSC 

Goal Template  Illustrative Sub‐projects 

At least ____ women who may want to become pregnant/are pregnant take the appropriate amount of supplements of iron and folic acid in the next ___ days. 

Peer programs with mother groups, group‐wise monitoring of IFA intake 

At least ____ women who may want to become pregnant/are pregnant  complete a treatment of de‐worming in the next ___days 

Peer programs, FCHV and mother‐group advocacy 

At least ___ (families with) women who may want to become pregnant/are pregnant  make a public declaration not to smoke inside the house, in the next ___ days 

Peer programs, advocacy programs 

At least ___ women who may want to become pregnant make a public declaration to stop smoking before pregnancy, in the next ____ days 

Peer programs 

At least ___families with women who are pregnant make a public pledge to lessen their workload. 

Peer and advocacy programs, positive deviance analysis 

At least ____ families with underweight girls or women who are pregnant or may want to become pregnant gain the appropriate amount of weight, in the next ___ days 

Peer programs , goat/chicken rearing, fisheries project 

At least ____ women who are pregnant eat three times a day, including, at least one animal‐sourced food per day for the next ___ days. 

 

Children 0‐6 months and breast feeding mothers (Priorities: Breastfeeding, Hygiene, Immunization, BMI) These RRNIs would mostly like be implemented by mother’s/women’s groups, or an existing health‐focused group.  Senior Leadership could come from Ward Citizen Forum or NFSSC. 

Goal Template  Illustrative Sub‐projects 

At least  ____ children under the age of 1 year receive immunizations to be in compliance with the recommended schedule, in the next ___ days 

Outreach vaccination program for the VDC, “Fully Immunized VDC” campaign 

At least _____families with  make public pledge for exclusive breast feeding of children until  the age of 6 months, in the next ___days 

Mother group peer programs with FCHVs 

At least _____HH with children 0‐24 mo pass hand washing checklist, in the next ___ days 

Advocacy and peer programs, soap distribution, “Community Led Total Behavior Change in Hygiene and Sanitation” campaign 

At least ____ lactating women eat three times a day, including, at least one animal‐sourced food per day for the next ___days. 

Advocacy, peer programs with mother groups, animal husbandry projects 

At least ____ HH with children 0‐24 that have an improved cooking stove, in the next ___days 

Improved stove construction, advocacy. 

At least ____ women with children 0‐24 months make a public pledge to keep the inside of their house  smoke‐free , in the next ___days 

At least  ___children with signs of chest infection, diarrhea and/or a  fever receive proper treatment within 1 day of on‐set of symptoms, in the next ___days 

Mother group/FCHV meetings and education on early signs and symptoms and the benefits of early treatment 

  

Page 59: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 53 of 57  

      

Children 6‐24 Months (Priorities: Comp feeding.  Iron/MNPs, Protein, Diarrhea/ORS) These RRNIs would mostly like be implemented by Mother’s/Women’s groups, or an existing health‐focused group.  Senior Leadership could come from Ward Citizen Forum. 

Goal Template  Illustrative Sub‐projects 

At least ___ underweight children gain an appropriate amount of weight, in the next ___days 

CMAM, goat/chicken rearing, fisheries project, growth monitoring 

At least ____ children age 6‐24 months eat at least one egg/piece of meat/fish or a glass of dairy  each day for  the  next ___days 

Community advocacy, goat/chicken rearing, fisheries projects 

At least ___HH with children 6‐24 months  pass a IYCF checklist, in the next ___days 

Mother group peer programs, community advocacy. 

At least ___ HHs with children 6‐24 months eat a meal with MNPs once a day, each day for the next ____ days. 

Community branding of MNPs, peer programs among mother groups 

At least  ___children with diarrhea immediately receive proper treatment (ORS, Zinc and increased feeding), in the next ___days 

Mother group peer programs, branding and marketing of Zinc 

At least ___ HH with children 0‐24 mo pass hand washing check‐list, in the next ___days 

“Community Led Total Behavior Change in Hygiene and Sanitation” campaign 

 

Community wide (Priorities: Protein, safe water, Hygiene) Teams could come from a variety of different community‐based groups, selected at large by the Ward committee.  Senior Leaders could come from Ward Citizen Forum or NFSSC. 

Goal Template  Illustrative Sub‐projects  

___% of HH make public commitment against open defecation, in the next ___days 

Latrine construction, Community Led Total Behavior Change in Hygiene and Sanitation” campaign 

Community declared ODF within ____ days 

Ensure ____ sources of water in the community pass “clean water check list” at the point of consumption, in the next ___days 

Small construction (spring boxes, pumps, etc), Community Led Total Behavior Change in Hygiene and Sanitation” campaign 

At least ____ HHs with children or women of child baring age have access to a source of eggs, meat/fish or dairy , in the next ___days 

Funds for goat/chicken rearing, fisheries 

School has appropriate number of latrines in ____days.  Advocacy, latrine construction 

  

       

Page 60: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 54 of 57  

      

Annex 7‐ Results Achieved under PDO 2 and PDO 3 

Surpassed‐ > 100%, Achieved‐ 85‐100%, Partially achieved‐ 65‐84%, and Not achieved‐ < 65% 

A= (Ia‐Ib)/(It‐Ib), where A is achievement, Ia is indicator’s actual; Ib is indicator’s baseline, and It is 

indicator’s target.   

PDO 2 indicators 

Indicators (PDO 2) KPI# 

Value and date of the indicator at baseline 

Value of the indicator target 

Actual values of the indicator endline 

Ratio of achievement 

Indicator level of achievement 

Percentage of pregnant women taking IFA supplements for 180 days 

 21   30   27   67%  Partially achieved 

Percentage of children 0‐6 months age who are exclusively breastfed 

 69   80   58   ‐100%  Not achieved 

Percentage of children 6‐24 months age who consume a minimum acceptable diet 

9  25   15   38%  Not achieved 

Percentage of households reporting no smoke in the room while cooking 

35  45   39   40%  Not achieved 

Percentage of pregnant women reporting consuming animal‐sourced protein in the previous day 

60  75   76   107%  Surpassed  

Percentage of households reporting using improved toilet facilities (flush toilet, covered pit within household, community latrine) 

25  35   80   550%  Surpassed  

Percentage of mothers (of children aged 0‐2) reporting always washing hands at critical times 

after defecation 

 71 80  98   300%  Surpassed 

After cleaning child’s bottom 

53 70  76   135%  Surpassed 

Before eating  17 25  57  250%  Surpassed 

Before feeding the children 

10 20  39   290%  Surpassed  

 

 

 

Page 61: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 55 of 57  

      

Indicators (PDO 2) 

IO# 

Value and 

date of the 

indicator at 

baseline 

Value of 

the 

indicator 

target 

Actual 

values of the 

indicator 

endline 

Ratio of 

achievement 

Indicator 

level of 

achievement 

 Number of RRNIs completed 

(disaggregated by 15 focus 

areas) 

0  10000  8950   89.5%  Achieved  

Number of RRNIs per ward 

per year 

o   2   1.4   70%  Partially 

achieved 

Characteristics of RRNI teams: 

% females participating in all 

RRNIs 

0  40  68.5   171%  Surpassed 

Characteristics of RRI teams: 

% minority participation in all 

RRNIs 

0  40   63.3   158%  Surpassed  

Percentage of RRNIs achieving 80% of their targets 

0  75  92  123%  Surpassed 

Average time between RRNI 

proposal submission and fund 

release to communities (days) 

0  60   73   82%  Partially 

achieved  

Number of coaches trained  0  300   311   104%  Surpassed  

Percentage of RRNIs publicly audited as part of citizen engagement 

0  100  85.1  85%  Achieved 

 

 

 

 

 

 

 

 

 

 

Page 62: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 56 of 57  

      

PDO 3 indicators 

Two KPIs and two IOs 

Indicators (PDO 3) KPI # 

Value and date of the indicator at baseline 

Value of the indicator target 

Actual values of the indicator endline 

Ratio of achievement 

Indicator level of achievement 

Number of children 6‐59 months in the earthquake affected districts with Severe Acute Malnutrition receiving therapeutic care  

 

  0  4000   4299   107%  Surpassed  

Number of households in the earthquake affected districts provided with hygiene and sanitation kits (water treatment products and soap) 

  0   45000   80013   178%  Surpassed  

 

Indicators (PDO 3) IO# 

Value and date of the indicator at baseline 

Value of the indicator target 

Actual values of the indicator endline 

Ratio of achievement 

Indicator level of achievement 

Number of mothers and 

caregivers of 6‐23 months 

children who are counseled 

for appropriate 

complementary feeding, 

frequency and diversity of 

foods, and continued 

 0   50000   169701   339%  Surpassed 

Number of children 6‐59 

months old in the earthquake 

affected districts with 

moderate acute malnutrition 

(MAM) receiving 

supplementary food 

 0   18000   36101   201%  Surpassed  

 

      

Page 63: Document of The World Bankdocuments.worldbank.org/curated/en/...children under 5 and 35% among women aged 15‐499 (DHS 2011) and half of pregnant women and children under five had

 

The World Bank   Nepal: Community Action for Nutrition Project (Sunaula Hazar Din) ( P125359 ) 

 

 

     Page 57 of 57  

      

PDO 2 Indicators 

Rating categories and corresponding point of intervals 

KPI#  IOI# 

Surpassed (>100%)  6  4 

Achieved (85%‐100%)    2 

Partially achieved (65%‐84%)  1  2 

Not achieved (<65%)  3   

Total PDO 2 Indicators  10  8 

% Achieved, surpassed and partially achieved  83%  106% 

 

Success rate is the percentage of indicators surpassed, achieved or partially achieved as a 

share of the total project indicators. A weighted average was calculated using the following 

scale: Surpassed=1.25 times; Achieved=1.0 times and Partially achieved=0.75 times.  

 

 

PDO 3 Indicators 

Rating categories and corresponding point of intervals 

KPI#  IOI# 

Surpassed (>100%)  2  2 

Achieved (85%‐100%)     

Partially achieved (65%‐84%)     

Not achieved (<65%)     

Total PDO 3 Indicators  2  2 

% Achieved, surpassed and partially achieved  125%  125% 

 

Success rate is the percentage of indicators surpassed, achieved or partially achieved as 

a share of the total project indicators. A weighted average was calculated using the 

following scale: Surpassed=1.25 times; Achieved=1.0 times and Partially achieved=0.75 

times.