Dm Make Up Six Sigma

download Dm Make Up Six Sigma

of 7

Transcript of Dm Make Up Six Sigma

  • 8/18/2019 Dm Make Up Six Sigma

    1/7

    36 J SCI IND RES VOL 67 JANUARY 2008Journal of Scientific & Industrial ResearchVol. 67, January 2008, pp. 36-42

    *Author for correspondence

    E-mail: [email protected]

    DM make up water reduction in thermal power plants using Six Sigma

    DMAIC methodology

    Prabhakar Kaushik 1* and Dinesh Khanduja2

    1Mechanical Engineering Deptt, N C College of Engineering, Israna, Panipat 132 1072Mechanical Engineering Deptt, National Institute of Technology, Kurukshetra 136 119

     Received 11 May 2007; revised 22 October 2007; accepted 24 October 2007 

    Six Sigma DMAIC (define, measure, analysis, improve, control) methodology has been applied to a process industry

    seeking energy conservation, taking a specific case of a thermal power plant. DM (De-mineralize) water in these plants is an

    expensive input material. It has been found that 0.1% increase in DM make up water consumption increases generation cost by

    Rs 82.82 lakhs per annum. In present study, implementation of Six Sigma project recommendations brought down mean make

    up water from 0.90% to 0.54% of MCR (Maximum Continuous Rating), accruing with it a comprehensive energy savings of 

    nearly Rs 304.77 lakhs per annum.

    Keywords: CTQ, DM, DMAIC, Process industry, Six Sigma

    Introduction

    Six Sigma (SS) methodologies improve quality and

    produce large cost savings1-9. Kumar4 noted that SS has

    found place primarily in manufacturing industries as a

    quality tool. In process industries, no such convenience

    is available. Working fluid in process industries may not

    be visible and its quality is measured by pressure,

    temperature and flow measurement. In manufacturing

    industries, production is already operating at 1-2 sigmalevel and by applying SS methodology, it can be raised

    up to 5-6 sigma levels. In process industries, there are

    many sub- processes that operate even at negative sigma

    level because of being secondary in nature. So in process

    industries, a quantum jump in sigma value by application

    of SS tools cannot be expected and it is found that the

    improvement potential is maximum up to 2-3 sigma

    levels.

    Present work is an initiative to implement SS in a

    thermal power plant (TPP).

    Six Sigma Application in Thermal Power Plants – ACase Study

    In TPP, optimisation of cycle make up water [De-

    mineralize (DM) water] consumption process involves

    substantial cost. Escalating water charges from water

    supply department and cost of production of DM water

    from raw water are substantial. Mostly, all gas based

    TPPs are operating on one module of combined cycle

    power plant, which consists of two gas turbines, two heat

    recovery steam generators and a steam turbine (Fig. 1).

    DM water is used for steam generation through gas based

    combined cycle power plant. With in this closed cycle of 

    DM water, DM water make up cycle is required to

    compensate for the losses incurred in water-steam cycle

    due to evaporation, start up and shut down venting, valvepassing and blow downs. DM make up water enters in a

    condenser at atmospheric temperature that is heated over

    500°C for raising steam. Flow meter is used to measure

    day cycle make up water as percentage of feed water

    flow. Each 0.1% increase in cycle make up water

    increases generation cost by Rs.82.82 lakhs per annum,

    which includes cost of heat loss, extra water and

    consumption of chemicals.

    Hence, the main customer CTQ (Critical to quality)

    selected for SS implementation is to conserve energy by

    reducing DM makeup water requirement at TPP.

    Presently, makeup water consumption at TPP is around0.9-2.0% of MCR (Maximum Continuous Rating). In

    comparison, other combined cycle power plants of the

    same rating have been able to achieve DM water cycle

    consumption of the order of 0.5-0.7%.

    Methodology

    To study all possible variations of water consumption,

    6 months data of cycle make up water consumption has

  • 8/18/2019 Dm Make Up Six Sigma

    2/7

    KAUSHIK & KHANDUJA: SIX SIGMA DMAIC METHOD FOR THERMAL POWER PLANT 37

     

    570°C

    Flue gases

    570°C

    G TExhaust

    H.P. Steam

    H.P. Steam

    Gas

    VTB

    VTB

    GT - 2

    GT - 1 HRSG - 1

    HRSG - 2

    L.P. Steam 5kg /cm2 

    200°C

    76 kg / cm2 

    528°C

    Cold Water

    forCondensing

    CONDENSER

    HOT W ELL

    Condensate

    Extraction Pump

    HPST

    LPST   L .   P .   S   t   e   a   m 

    ~

    Deaerator 

    ~

    ~

    GT Gener ator I

    GT Generator II

    Steam Turbine

    Generator

    156 MW

    DM W ater

    Make up

    Boiler Feed Pump

    ABBR. Description

    GT   Gas Turbine

    HRSG  Heat Recovery Steam GeneratorVTB   Vertical Tube Boiler

    H.P. S team  High Pressur e Steam

    L.P. S team  Low Pressure Steam

    HPST  High Pressure Steam Turbine

    LPST  Low Pressure Steam Turbine

    Hot

    Water

    to be collected. Cycle make up water consumption has

    to be converted in terms of percentage of MCR of feed

    water flow so that this methodology can be applied to

    other power plants. As it is not possible to reduce cycle

    make up water consumption to zero and minimum is

    the best, LST (lower specification limit) cannot be fixed

    for water consumption. Hence, only USL (upper

    specification limit) of 0.7% and target value of 0.5%

    are specified and selected based on water consumption

    pattern existing in the best power plants around.

    Implementation of Six Sigma DMAIC Methodology

    A five-step improvement cycle using SS organizations

    (Define, Measure, Analyse, Improve, and Control;

    DMAIC) has been successfully implemented in TPP to

    reduce DM make up water reduction (Fig. 2).

    Fig. 1— Systematic block diagram of combined cycle power plant

    Fig. 2— Flow diagram of methodology adopted

  • 8/18/2019 Dm Make Up Six Sigma

    3/7

    38 J SCI IND RES VOL 67 JANUARY 2008

    Define

    In define phase, High level process map- a SIPOC

    (Supplier, Input, Process, Output, Customer) diagram,

    was drawn for cycle make up water consumption

    (Fig. 3).

    Measure

    In cycle make up water consumption at TPP, makeup water flow is measured by a flow meter. To perform

    Gauge R&R study9 on this process, another flow meter

    of tested accuracy and characteristics needs to put in

    series to the installed flow meter. Two persons (operators

    in shift) were needed to perform this experiment. Sample

    size was 10 and two readings were taken on each sample,

    thereby making a total of 40 readings. From the results

    of Gauge R & R study, repeatability and reproducibility

     

    Suppl ier Input Process O utput Custome r

    DMPlant

    Make Up W aterConsumption

    Data

    Operationand

    Maintenancepractices

    Reduction inMake Up

    WaterConsumption

    ThermalPower

    Management

    CustomerSatisfaction &Relationship

    6 SigmaMethodology

    Thinking

    Flow

                                                         

     

     

     

     

    comes out to be 2.75% and 0.00% and put the percentage

    study variation to be 2.75%, which is less than 10%,

    indicating that flow meter was correct.

    Analyse

    Data is analysed and causes of problem are

    discovered4 using following tools:

     a) Run Chart

    Run chart was drawn from data collected for day cycle

    make up water from TPP measured through flow meter.

    From the results found using Minitab, P-values (Fig. 4)

    for clustering (0.51045), trend (0.36191), oscillation

    (0.63809) and mixtures (0.48955) come out to be more

    than the significance level (0.05), indicating not any

    special cause of variation in data.

    Fig. 3— High-level process map for cycle make up water consumption

    Fig. 4— Run chart of make up water before

       M  a   k  e  u  p  w  a   t  e  r   b  e   f  o  r  e   i  n   %  a  g  e

    Observation

  • 8/18/2019 Dm Make Up Six Sigma

    4/7

    KAUSHIK & KHANDUJA: SIX SIGMA DMAIC METHOD FOR THERMAL POWER PLANT 39

     b) Process Capability analysis

    Process capability analysis was performed using

    Minitab to draw curve for cycle make up water from

    TPP measured through flow meter (Fig. 5). Z- bench

    sigma value of process was found to be -0.75 and existing

    DPMO level of the process comes out to be 774435.70,

    which is remarkably high and shows that there are a lot

    of opportunities for improvement in the process.

     

     

    Passing of Drain & vent valves 

    Leakages from HP/LP pipelines

    flanges & piping s 

    Improper Adjustment ofS WAS Sampling Valves 

    Vaccum pump overflow 

    Passing due to under sizing of actuators 

    Late closing ofDrain & VentValves during Boiler Startup Sampling Valve s remainingopen after collection of samples 

    MAN  EQUIPMENT 

    M ETHOD  MATERIAL 

    MORE DMCYCLE

    MAKE UP Sample drains remained opened Passing of valves due to improper during Shutdown boiler  limit switch setting Frequency of boiler Longer running with boiler tubehydraulic tests  Leakage Higher no. of sample Blow down opening for Silicacollection in SWAS  & conductivity test 

    Tube Leakages 

    Gland Leakages from

    pump s 

     c) Fish-bone Diagram

    Using expert experience and critical analysis of actual

    combined cycle at site, a fish bone diagram drawn

    (Fig. 6) to find causes of more DM water consumption

    during combined cycle.

     d) Bar Chart

    Actual DM water wastage from different points was

    measured or approximated where no measurement was

    Fig. 5— Process capability analysis of make up water before implementing

    DMAIC methodology

    Fig. 6— Fishbone diagram

  • 8/18/2019 Dm Make Up Six Sigma

    5/7

  • 8/18/2019 Dm Make Up Six Sigma

    6/7

    KAUSHIK & KHANDUJA: SIX SIGMA DMAIC METHOD FOR THERMAL POWER PLANT 41

      Table 1—Action Plan (Improve and Control Phase)

    Recommendation proposed Status

    1 All lab analysts to be individually interacted to emphasize theimportance of closure of SWAS valves after sample collection.

    Implemented

    2 Six month periodic training cum awareness program for lab analysts to

    be conducted to make them aware of the importance of DM water loss.

    First program

    already

    conducted

    3 Instructions to be pasted on SWAS panel for closure of sample valve’s

    each time after sample collection.Im lemented

    Instructions

    pasted

    4 Operation staff to be instructed to cross check from time to time the

    position of SWAS sampling valves in their routine rounds

    Implemented

    Instructions

    being followed

    5 As an improvement measure, the frequency of blow down opening to

    be changed from weekly to fortnightly

    Implemented

    6 To avoid the loss of DM water due to vaccum pump overflow,

    solenoid makeup valves of both the seal water tanks to be adjusted

    properly for both low and high level settings.

    Implemented

    7 Q uarterly checking of solenoid valves of both seal water tanks to be

    carried out.

    Implemented

    8 To detect the problem of seal water tank overflow at the earliest, in the

    log sheet of the operator, the daily checking of seal water tanks to be

    included.

    Implemented

    Included in thelog sheet

    9 The leakages identified from HP/LP pipelines, valve passing to be

    attended during next shutdown.

    To be

    implemented

    10 The glands of all the pumps with excessive leakages to be tightened

    optimally.

    Implemente d 

    11 A schedule to be prepared to check/tighten (if required) the glands of

    all the pumps fortnightly.

    Implemented

    12 For on line sealing of HP steam leakages, annual maintenance contract

    to be awarded

    To be

    implemented

    identified problem from analysis phase were tackled and

    shut out in control phase (Table 1).

    Results

    Cycle make up water consumption was 0.9% MCR,

    which is equivalent to Rs 745 lakhs (Rs.82.82×0.9%)

    per annum (Appendix I). Application of project

    recommendation brought up the sigma level to 1.63 with

    DPMO level of 51389.17 (an improvement of 

    723046.53) and mean of the process reduced to

    0.54066% (an improvement of 0.368% mean), which is

    equivalent to monitory saving of Rs 304.77 lakhs per

    annum (Fig. 8). A few more agreed recommendations

    are still to be implemented during plant shutdown.

  • 8/18/2019 Dm Make Up Six Sigma

    7/7

    42 J SCI IND RES VOL 67 JANUARY 2008

    Estimated saving from the project after implementation

    of all recommendations is expected to be Rs 331.2 lakhs

    per annum with mean make up water expected to come

    down (< 0.5%), which is substantial for any organization.

    Conclusions

    Study proves that firms that successfully implementSix Sigma perform better in virtually every business

    category, including return on scales, return on

    investment, employment growth and stock value growth.

    Higher consumption of DM water is found to be a big

    problem in a thermal power plant. The causes for more

    DM water consumption are SWAS, problem of valve

    passing, vacuum pump overflow etc. SWAS makes a

    big impact having 33% contribution for DM water

    consumption. Further, some actions are recommended

    to reduce the consumption of DM water. Application of 

    Six Sigma project recommendations brought up the

    sigma level to 1.63. Estimated saving from the projectafter implementation of all recommendations is expected

    to be around Rs 331.2 lakhs per annum with mean make

    up water is expected to come down below 0.5%, which

    is substantial for any organization.

    References

    1 Coronado R & Antony J, Critical success factors for the

    implementation of six sigma projects in organization, TQM 

     Mag, 14 (2002) 92-99.

    2 Henderson K M & Evans J R, Successful implementation of 

    Six Sigma: benchmarking: general electric company,

     Benchmarking Int J, 7 (2000) 260-282.3 Kapur K C & Feng Q, Integrated optimisation models and

    strategies for the improvement of the Six Sigma process, Int J 

    Six Sigma and Comp adv, 1 (2005) 210-228.

    4 Kumar P, Six Sigma in manufacturing, Prod J , 43 (2002) 196-

    202.

    5 Mahanti R & Antony J, Confluence of Six Sigma simulation

    and software development, Manag Aud J , 20 (2005) 739-762.

    6 Mathew H, Barth B & Sears B, Leveraging Six Sigma discipline

    to drive improvement,  Int J Six Sigma Comp Adv, 1  (2005)

    121-133.

    7 Pandey P S, Neuman R & Cavanagh R R, The Six Sigma Way:

     How GE, Motorola and Other Top Companies are Honing their 

    Performance (McGraw Hill, New York) 2000.

    8 Park S H, Six Sigma for productivity improvement: Korean

    business corporations, Prod J , 43 (2002) 173-183.

    9 Raisinghani M S, Ette H, Pierce R, Cannon G & Dariply P,

    Six Sigma: concepts, tools, and applications, Ind Manag Data

    Sys, 105 (2005) 491-505.

    Appendix-1

    Cost calculations of loss on account of 0.1% make up water 

    Loss due to make up water consumption

    Water is heated in boiler from 27°C at atmosphere pressure to superheated steam at 528°C and 76kg/cm2

    Heat loss

    Enthalpy of water at 27°C (atmosphere pressure) = 113.25 KJ/kg

    Enthalpy of superheated steam at 528°C and 76kg/cm2 = 3472.74 KJ/kg

    Loss in enthalpy = 3472.74 -113.25 = 3459.49 KJ/kg = (3459.49 × 1000) / 4.18 Kcal/m3 = 827629.1866 Kcal/m3

    Equivalent loss in power = 827629.1866 / 1965 = 421.185 KWh/m3

    (Considering Heat Rate as 1965 Kcal/ KWh for combined cycle)

    Equivalent loss in monetary term = Rs 4.00 × 421.185 = Rs 1684.74 per m 3

    (Considering Rs. 4.00 per unit (KWh))

    Cost of DM water = Rs 22.00 per m 3

    Total loss on account of make up water =Heat loss + water loss = Rs 1684.74 per m 3 + Rs 22.00 per m3 = Rs 1706.741 per

    m3

     Losses on account of 0.1% make up water 

    Total flow in boiler per annum = [(231(HP) + 46 (LP)) × 2 (Boiler)] ×24 h ×365 days = 4853040 m3

    Water quantity for 0.1% make up = (0.1 × 4853040)/ 100 = 4853.04 m3 per annum

    Therefore, loss on account of 0.1% make up water = 4853.04 × Rs 1706.74 = Rs 8282882.343 = Rs 82.82 lakhs approx per

    annum