ENVIRONMENTÁLNY VÝUČBOVÝ POGRAM Lienka skúma vodu Bc. Drahomíra Nererová MŠ Lienka – Želiezovce
DLGP-II End of Pogram Evaluation Report-aspiazu-closing workshop Nov 2014
-
Upload
basharat-ahmadali -
Category
Documents
-
view
142 -
download
1
Transcript of DLGP-II End of Pogram Evaluation Report-aspiazu-closing workshop Nov 2014
1
FINAL EVALUATION REPORT
SURINAME
DECENTRALIZATION AND LOCAL GOVERNMENT
STRENGTHENING PROGRAM II
(LOAN 2087/OC-SU)
Consultant
Hernan Aspiazu, MBA; CPA
November 2014
2
Table of Contents
Glossary........................................................................................................................ 3
Basic Data..................................................................................................................... 4
I. Executive Summary............................................................................................. 5
A. Program description………………………………………………………….. 5
B. Findings……………………………………………………………………...... 5
C. Risks and sustainability………………………………………………………. 8
D. Lessons learned and recommendations………………………………………. 9
II. Introduction......................................................................................................... 11
A. Background and purpose of final evaluation…………………………………. 11
B. Evaluation methodology……………………………………………………… 12
III. Program Description............................................................................................ 12
A. Program’s overview…………………………………………………………... 12
IV. Findings................................................................................................................. 16
A. Effectiveness………………………………………………………………….. 16
1. Results for milestones, outputs and outcomes………………………….. 16
2. Achievements by component for milestones and outputs………………... 18
3. Achievements for outcomes……………………………………………… 28
4. Program budget and projected costs……………………………………… 29
B. Efficiency……………………………………………………………………... 30
1. Organizational structure………………………………………………….. 30
2. Project inputs……………………………………………………………... 34
C. Design and relevance…………………………………………………………. 35
D. Monitoring and evaluation systems…………………………………………… 36
V. Risks and sustainability....................................................................................... 36
VI. Lessons learned and recommendations............................................................. 39
3
Glossary
BFM Budget and Financial Management
CBO Community Based Organization
CIC Citizen Information Center
CLAD Government Accounting Office
CPC Citizen Participation Committee
CPP Citizen Participation Plans
DA District Administrator
DC District Commissioner
DEF District Equalization Fund
DLGPI Decentralization and Local Government Strengthening Program I
DLGPII Decentralization and Local Government Strengthening Program II
DMT District Management Team
DNA Suriname National Assembly
DSP District Strategic Development Plan
FDIL Financial Decentralization Interim Law
GLIS Ground Land Information System
GOS Government of Suriname
IAO Internal Audit Office
ICT Information and Communication Technology
IDB Inter-American Development Bank
MD Managing Director
MOF Ministry of Finance
MRD Ministry of Regional Development
NC Neighborhood Committee
NGO Non Governmental Organization
NIMOS National Institute for Environment and Development
ORG Operating Regulations and Guidelines
OTA Tax Directorate of the Ministry of Finance
PCR Project Completion Report
PET Public Entertainment Tax
PIU Program Implementation Unit
POP Promotion and Outreach Plan
RVT Rental Value Tax
SDP District Strategic Development Plan
TMRD Task Force of the Ministry of Regional Development
TMOF Task Force of the Ministry of Finance
WAN Wide Area Network
4
Basic Data
Country Suriname
Project Name Decentralization and Local Government
Strengthening Program (DLGP II)
Loan No. 2087/OC-SU (SU-L1011)
Date of Board Approval 10 December 2008
Date of Contract 20 March 2009
Eligibility Date 9 June 2009
Date of First Disbursement 17 June 2009
Borrower Republic of Suriname
Executing Agency Ministry of Regional Development
Minister Mr. Stanley Betterson
Permanent Secretary Mrs. Drs. Genia Corinde
Approved Amount US$ 13,500,000
Source OC
Project Team Rafael de la Cruz (ICF/FMM), Project Team Leader;
Karen Astudillo (ICF/FMM); Gilberto Chona
(ICF.FMM); Gasbriel Nagy (FMM/CSU); Carlos
Pineda (ICF/FMM); Eduardo Rodal (FMM/CTT);
Rinia Terborg (CCB/CSU); Diego Buchara
(LEG/SGO); and Cecilia Bernedo (ICF/FMM)
DLGP Project Team:
Basharat Ahmadali Managing Director
Mahender Pershad Task Manage, Administration, Finance and Planning
(Moved)
Martin Blenman Task Manager, Civil Works & Capital Investment
Iris Gilliad Task Manager, Citizen Participation
Riaz Ahmadali Task Manager ICT/WAN
Xaviera Souprayen Assitant Financial Officer
Marlon Wamenie Assistance Procurement Officer
Clareca Sajat Office Manger-(Moved)
5
I. EXECUTIVE SUMMARY
A. Program description
DLGP-II is a five year, US$ 15 million program, whose objective was to continue supporting
Suriname’s local government decentralization e f f o r t s . The Program aimed to
contribute to the attainment of a core legal framework, and to assist the new pilot districts of
Paramaribo, Sipaliwini, Saramacca, Coronie, and Brokopondo to obtain adequate institutional
capacity for fiscal self-management and for managing capital investment. Furthermore, DLGP-
II also a i m ed t o assist t he certified districts of Wanica, Para, Nickerie, Commewijne, and
Marowijne in the implementation of community-based basic infrastructure investment projects
and local services. The Program is financed by an IDB loan of US$13.5 million, and a GOS
counterpart contribution of US$ 1.5 million.
The Program had four components: (i) legal framework; (ii) financial, planning, and
administrative capacity; (iii) citizen participation and program outreach; and (iv) capital
investment capacity building and investment program.
B. Findings
Overall the program was well designed to support decentralization: its first component aimed to
provide the districts with the required laws for their financial support; the second contained the
activities to strengthen the administrative and managerial capacity of the districts; the third was
geared to make citizens active participants in the plans and in the work of their local government,
and the fourth aimed to consolidate the districts managerial capacity in basic infrastructure work.
All components are important, but the legal component is of fundamental importance to the
program because it deals directly with the districts’ financial sustainability. In this respect, three
laws represent the backbone to a future financial support and feasibility of the districts, namely:
(i) The District Tax Law, aimed at strengthening own-source revenues for the Districts; (ii) the
Law on Financial Relations between the Central Government and the Districts, aimed at creating
a reliable and predictable source of revenue sharing between central and local governments,
through a District Equalization Fund (DEF); and (iii) the update of Article IV of the framework
Fiscal Decentralization Interim Law (FDIL), also aimed at strengthening own-source revenue
sources in the Districts. Complements to these laws are the legal agreements between the
districts and the GLIS, aimed at strengthening the cadastral system in each District. The approval
of the first two laws, prepared during DLGPI, has been pending since year 2008. The update of
Article IV of the FDIL has been in Cabinet since 2012. And the approval of the GLIS
agreements has been pending in MRD for several years. The lack of action toward the approval
6
of these laws poses a serious risk to the sustainability of the program - that if not mitigated or
controlled could seriously hamper future progress in the decentralization process.
By contrast, the other 3 components of the program have performed with noteworthy success:
achieving a total of 18 milestones (activities), and 4 output indicators1. Except for 2 milestones,
the achievements in comparison to plans go from good to excellent. Some of those milestones
were remarkably well done and could be used as showcases to replicate in similar programs in
the Region. For instance, the Neighborhood Committees (NC) became an exemplary form of
citizen participation, not only monitoring the quality and timing of the work being carried out in
the neighborhood, but also improving business relations with contractors by collaborating with
them in ensuring the overnight safety of their equipment. The capital investment component was
highly productive in the number of infrastructure projects implemented as a result of involving
the communities in the selection and monitoring of the projects. In contrast, there was also a lack
of accomplishments in a few milestones: the internal audit office for the districts was not
organized. The WAN was not connected to the MOF due to larger connectivity issues that still
need to be dealt with.
Were the program’s outcomes2 achieved? In summary form, the program’s achievement - in
terms of outcome indicators – is as follows:
1. Legislation favoring decentralization passed: Not achieved -- as explained above and in the
body of this report.
2. All Districts certified for autonomous financial capacity and systems: Achieved from the
point of view of being now certified. However, the Districts are not financially autonomous
yet.
3. All Districts certified for enhanced management capacity of capital investment projects:
Achieved.
4. Projects executed by certified districts: Partially Achieved.
From the institutional point of view, the program organized a Program Implementation Unit
(PIU) headed by a Managing Director and comprising professional task managers- for three of
the components, plus an ICT manager. The Managing Director, in addition to his normal duties,
also had an operational role with the activities in the legal component. This structure was
reproduced at the MRD and at the District levels -- as TMRD (DLGP Task Force in MRD) and
DMTs (District Management Team) in each District. This overall structure was to be supported
by a task force in the MOF - the TMOF -, to provide assistance in the quality control of financial
activities for the districts Level 1 certification, and to review the districts fulfillment of financial
1 An output is what is expected to be delivered by the project. The execution unit is responsible for the generation
of the outputs. Output indicators describe the outputs to be generated through the implementation of the project. 2 Outcomes are the immediate effects expected to be achieved as a result of the project. Generally these
immediate effects are achieved in the last stages or immediately after the project implementation.
7
conditions required for Level 2 certification. TMRD, headed by an Assistant PS, was designed to
work actively and jointly with the PIU, so as to develop within the permanent staff of MRD
knowledge and experience in program execution with an IDB program. The details on the
strengths and limitations of this structure are presented in the body of the report, with the main
aspects summarized below.
PIU developed high quality systems and efficient internal operations: PIU’s operations are based
on a well prepared operating manual (ORG) -- supported, in turn, by planning and monitoring
systems, as well as administrative, accounting and contracting systems. A capable director which
has served continuously DLGPI and DLGPII was able to build a professional and cohesive team
highly identified with the program and with its success.
Coordination with TMRD not entirely satisfactory: TMRD has developed into a current structure
with a staff of around 27 persons, the majority of them university trained. The level of
coordination and joint working with PIU has been mixed: It has generally been very effective in
the citizen participation and ICT components; and poor in the legal component and the
financial/administration component. In the civil work area the level of joint work participation
was not consistent, being good to very good in some projects (for instance the current project in
Sipalawini) and absent in others.
The Program Advisory Council (PAC) was never implemented: The organizational structure for
execution included an Advisory Council comprised of representatives of MRD, MOF,
Directorate of OTA, Ministry of Home Affairs, and the Ministry of Public Works. This Council
was to provide a consultative and problem solving forum to the PIU. While the decree formally
organizing the PAC was prepared this advisory unit was never implemented.
MOF’s unilateral decision to terminate the TMOF team: In the first quarter 2011, the PS of the
Ministry of Finance decided to stop the activities of the team created in MOF (TMOF) to support
DLGPII - under the logic that the functions assigned to this team were the normal functions of
the Ministry, and that consequently there was no need for a special team. There were two aspects
not considered in this decision: (i) the participation of TMOF is established in the ORG and is
part of the contract with the IDB. Thus, any changes in the ORG must have the prior approval of
the Bank; (ii) eliminating TMOF cut off the direct work link that had existed between technical
staff of the MOF and PIU, forcing the PIU to have to go through the MOF upper management
(the PS) to obtain collaboration from TMOF technical staff. One practical result was that TMOF
never participated again after 2011 in the process of District certification.
Level of autonomy and placement of the executing unit: PIU had some level of operating
autonomy, but very little managerial power to have influence with the parallel teams. It also had
negligible or no political clout to influence in the approval of strategic laws necessary to advance
8
the legislative reform agenda required to advance the decentralization process. Considering the
alternative of TMRD as a potential executing unit in the future, there are already signs that it
could have less operating autonomy than PIU - based, for example, on the way the TMRD
capital investment projects are currently being selected – without any reliance on formula-driven
selection criteria (as is the case in DLGP). Furthermore, it’s not likely that TMRD, as an
executing unit, would have any more success than the PIU in promoting pending legislative
reforms in decentralization - judging from the difficulty MRD itself has had in advancing the
program’s strategic laws in the past 8 years.
When DLGPI was designed there were few proactive stakeholders and a more unified central
government political support to enhance and amend the enabling legislation for decentralization.
The context has changed significantly since then, now facing what appears to be more diffuse
central political support and yet, at the same time, a considerably more proactive set of
stakeholders: (i) the districts are active participants; (ii) the public is more informed on the basics
of decentralization; (iii) the ministries involved remain the same, but they are at present more
informed about the needs and solutions; (iv) there are government agencies more actively
involved, CLAD and NIMOS, for instance; (v) non-profit agencies – NGOs - have been
participating and their role is bound to grow in the future; and (vi) the general assembly has to
some degree been involved with the program in the last ten years.
Given this wealth of official and non- official stakeholders, apart from the necessary technical
qualifications, a careful analysis will have to be made on the leadership and placement required
for the future executing unit. From the point of view of leadership the unit should be able to
amalgamate and negotiate among different participants with their own specific goals. From the
point of view of placement, the unit will have to be located at a place high enough to have the
political muscle to contend with political opponents.
C. Risks and sustainability
The main risks attempting against the financial feasibility of the program are legal and political
in nature.
Legal risk - deriving from the lack of approval of the three previously mentioned financial laws
and the 10 GLIS agreements. This is a serious risk that if not mitigated or controlled could very
well affect the future of the decentralization process.
Political risk: The fact that the laws have not been approved in several years brings an analytical
observer to the conclusion that the delay may not be caused by an opposition to the laws, in and
of themselves, but by an opposition to the broader strategic goal of decentralization. If this is
true, however, this constitutes an opposition to the Constitutional mandate of 1987 which
9
stipulates decentralization – through a “Decentralized Monocratic State”- as the model of
organization for Suriname’s political and governmental system. It follows that there is a need for
a common effort, among all stakeholders, to comply with the Constitution and to push Suriname
into a modern, developed country.
Institutional risks are associated with institutional capacity risks at three levels: (i) the
institutional capacity to execute any new follow-up program contemplated after DLGPII ; (ii) the
central institutional capacity to continue supporting the districts – irrespective of a new program;
and (iii) the institutional capacity of the districts to sustain themselves.
The institutional risk related to execution of a new program is twofold. The first has to do with
the placement of the executing unit, a topic already mentioned. The second is of operational
capacity to carry out execution. There are some key functions and systems necessary for
effective execution, regardless of the type of project, namely: planning; procurement; financial
budgeting, accounting and reporting; monitoring; internal controls; and management. An
unusually well-honed capacity was created in all these functional areas through the current
executing mechanism of DLGPII. The risk is that the capacity and systems for these functions
may be lost and will have to be rebuilt after the termination of the current program.
As regards the question of central capacity to continue supporting the districts, in the short to
middle term the districts will require support to maintain proficiency, especially in the areas of
financial administration, taxes, the WAN, and the implementation of new financial software
mandated by Government. Without a thorough institutional analysis it is not possible to
determine fully whether TMRD has developed the required capacity for continuous support to
the districts, but observations based on short interviews indicate this unit will need strengthening
in the areas of planning and financial systems to take on this function.
Financial risk: The central government covers 100% of the districts’ salaries and around 75% to
80% of actual non-salary current and capital expenditures. Furthermore, actual non-salary
expenditures are only a fraction (around 12%, for example in the case of District of Para for year
2013), of the budgetary needs derived and approved by the district councils. Thus, there is a
significant financial risk of non-sustainability at the District level. There is an urgent need for
own-source revenues by the districts and for a systematic, predictable way of allocating central
government transfers to the district. These actions will go a long way toward mitigating the
existing financial gaps and risks.
D. Lessons learned and recommendations
Political support and mitigating measures: Decentralization programs, like the one under review,
require legal reforms in an environment with a wealth of local and national stakeholders with
10
different perceptions on decentralization and its processes, and with different political views.
This makes the approval of the legal reforms risky. To mitigate this risk, the following measures
should be considered: (i) placing the executing unit at upper levels of political power to permit a
negotiated consensus between political equals; (ii) information campaigns directed to the public,
and to government officials on decentralization - its basis, benefits and needs. (PIU ran a very
limited information campaign in support of legal reforms,, as part of its POP activity; it should
have been more ample.); (iii) consensus/lobbying efforts directed to gain support from ministers
and the General Assembly. (The activity included in the program for this consensus building was
unfortunately eliminated by MRD during the execution of the program.); (iv) milestones and
contractual clauses requiring the approval and implementation of laws - not only the drafting of
such laws; and (v) more support from IDB experts to assess achievements of key milestones or
contractual agreements - and require timely adjustments. Alternatively, the IDB may consider the
granting of different type of credits or programs in which disbursements are conditioned to legal
reforms.
Institutional analysis and organizational development: During project preparation there should
be an institutional analysis of the unit to be organizationally developed, so as to have a base line
and monitor its development progress. The program included the organizational development of
TMRD by way of transfer of capacities from PIU, while also participating as a parallel team in
the execution of the program. Unfortunately, there was no institutional analysis of TMRD during
program preparation, so as to know its institutional capacity, its needs and its potential. As a
result, TMRD has developed into a unit with apparently a double function as parallel execution
unit and central support to the districts. However at the present time it is unknown what has been
the degree of organizational development accomplished and what are TMRD’s true capacities,
needs and potential.
Strong direction and coordination: Clear supervisory directions and objectives should be defined
for independent units sharing execution responsibility, while at the same time performing
dissimilar roles. PIU and MRD had the same supervisor and shared responsibility for some
execution activities, but the latter had a role of beneficiary of the know-how to be transferred
from the former. To promote coordination, and avoid subjective interpretations among members
of the units, clear directions should have emanated from the PS in this regard, from the inception
of the program.
Continuity of executing unit: Units with continuous strong leadership create cohesive teams with
members highly identified with the accomplishment of the program’s goals. In spite of many
problems and delays suffered, PIU was able to maintain a good to excellent level of performance
thanks to continuity of a strong, capable leadership.
11
Institutional strengthening in a future program: The following institutional strengthening should
be included in a future DLGP program:
(a) Implementation of the GOS newly mandated “Free Balance” financial software at the
districts’ level. This task to include the preparation of system documentation, users’
manuals and training.
(b) Training on the new decentralization and financial laws, once they have been approved.
(c) Development and implementation of a tax accounting system for the districts.
(d) The prompt signing of the 10 agreements of the districts with GLIS and the
implementation of a system to transfer data from GLIS to the districts tax accounting
system.
(e) A subcomponent for dissemination of information on decentralization and for the
consensus building with ministers and the general assembly.
(f) A joint effort with OTA to resolve the connectivity issues between this office and the
financial district offices.
(g) Development of an Internal Audit Office (IAO) for the districts. The MRD office of
Internal Control could be the basis for organizing the IAO. However the Internal Control
office very possibly would have to be reorganized and strengthened.
(h) Development of a salary classification system for District personnel.
(i) A subcomponent to finance, as needed, expert support to the legislative reform process –
including technical promotion and negotiation with legislative staff, as well as in
mounting public communication and education campaigns, .
(j) Certification processes must be thoroughly spelled out in terms of procedures and
responsibilities - and must be accompanied by the systems needed to measure
benchmarks required as part of the certification.
II. INTRODUCTION
A. Background and purpose of final evaluation
Section 4.09 of Annex A of the Loan Agreement between IDB and the Government of Suriname
for the DLGPII program requires that a consulting firm or an individual consultant be hired to
prepare and submit a final evaluation report on the execution of the Program. In compliance with
this requirement and the Terms of Reference this report presents an independent final evaluation
of the Program focused on: (i) the level of achievements of results; (ii) the level of compliance
by the program with its performance indicators; (iii) the positive and negative aspects of the
program’s design and execution; and (iv) lessons learned and the recommendations of corrective
or monitoring measures for similar programs.
12
B. Evaluation methodology
To evaluation work was carried out in accordance with the work plan agreed and included: (i) the
review of basic documents-IDB Loan proposal, IDB PMR, Program Financial Statements, Work
Plans, Operating Regulations; (ii) gathering of data and information on actual results vs. planned
for activities (milestones) and outputs and reasons for variances; (iii) review of the work of
consultants; (iv) interviews with IDB personnel at the country office in Paramaribo; (v)
interviews at MRD with the PS, the TMRD, and the internal Control Unit; (vi) at MOF interview
with the Minister and with the Director of the TAO and his executive staff; and (vii) a visit and
interview with the Commissioner of Para and his executive staff. In addition, a stakeholder
questionnaire was prepared, distributed and collected. This work was performed in Paramaribo
during the period 9 to 23 September. The consultant thanks the PIU’s Managing Director and his
staff for their invaluable help.
III. PROGRAM DESCRIPTION
A. Program’s overview
DLGP-II is a five year, US$ 15 million program, whose objective is to continue supporting
Suriname’s local government decentralization e f f o r t s . The Program aimed to
contribute to the attainment of a core legal framework, and to assist the new pilot districts of
Paramaribo, Sipaliwini, Saramacca, Coronie, and Brokopondo to obtain adequate institutional
capacity for fiscal self-management and for managing capital investment. Furthermore, DLGP-
II also a i m ed t o assist t he certified districts of Wanica, Para, Nickerie, Commewijne, and
Marowijne in the implementation of community-based basic infrastructure investment projects
and local services. The Program is financed by an IDB loan of US$13.5 million, and a GOS
counterpart contribution of US$ 1.5 million.
The Program had four components: (i) legal framework; (ii) financial, planning, and
administrative capacity; (iii) citizen participation and program outreach; and (iv) capital
investment capacity building and investment program.
Component 1-Legal Framework: The purpose of this component was to continue supporting
changes in legislation that are necessary to improve fiscal relations between central and
local governments, including: (i) preparation of draft laws on Traditional Authority; and
District Cadastre; (ii) design of District Ordinances regulating financial accounting standards
and procedures; and (iii) update laws included in Article 4 of the FDIL, dealing with transfer of
13
revenues to the districts. The Program provided consultancy services and training at the local
level on decentralization-related laws.
Component 2-Financial, planning and administrative capacity: The objective of this
component was to develop a core capacity in the new pilot districts to manage their own budget
and financial systems. Specifically, the Program aimed to assist these districts in: (i) creating
a District Administrator position; (ii) installing core financial and tax systems; (iii)
providing human resources training; (iv) providing appropriate software and hardware; and
(v) providing equipment and rehabilitating district offices, which are necessary to install new
financial systems.
The set of core financial systems for the new pilot districts included: (i) administration and
planning; (ii) budget and financial management; and (iii) local revenue generation. For all
districts the Program viewed to assist in: (i) creating an internal auditing capacity; (ii)
installing an information and communication technology network to connect the districts with
both the MOF and MRD, via a wide area network (WAN) to facilitate cost-effective
harmonization of financial systems and data transfer, as well as to facilitate taxpayers to pay in
any location; and (iii) providing training, equipment, furniture, and remodeling of facilities to
manage the WAN, supporting coordination, and technical cooperation activities of districts.
This component also undertook to assist in the implementation of a simplified tax
administration system in certified districts to manage the registration and collection process for
all local taxes and fees. Activities supported by the Program included: (i) training of tax
administration personnel at the local and central level; (ii) revising and developing procedures
for identifying and alerting reluctant tax payers; (iii) improving methods to ensure compliance
of non-tax payers, including administration of fines for reducing evasion; and (iv) converting
manual taxpayer’s registry into an electronic form that will feed into the Financial
Administration System.
Upon approval of the District Tax Law, the Program aimed to support the creation of
methodologies and correspondent training for the districts to: (i) audit taxpayers records; (ii)
adopt warrant measures in order to ensure the collection of tax and non-tax revenues; (iii) keep
updated records; (iv) identify and define taxpayer’s violations (arrears, fraud, evasion); and (v)
apply interests, fines and other penalties. The approval of the District Tax Law was a
condition prior to the disbursement to finance the activities referred to in this paragraph.
Upon approval the State-Districts Financial Coordination Law, the Program also aimed to
support the Government in: (i) collecting information needed to define the distribution
parameters of DEF and ensure sustainability of data collection; (ii) creating a
methodology and corresponding training for calculating the transfers of DEF to each
14
District in the MOF and MRD; (iii) installing hardware and software needed to perform this
task; and (iv) training personnel. The approval of the State-District Financial
Coordination Law was a condition prior to the disbursement to finance the activities
referred to in this paragraph.
The Program also supported the creation of an internal auditing capacity in the districts by: (i)
supporting District Councils to approve appropriate regulations; (ii) training district
personnel and the District Council; (iii) providing consultancies to define appropriate
audit methodologies and procedures in accordance with the existing legal regulations; and (iv)
providing appropriate hardware and software. The program pursued the creation of the
districts’ capacity to have their own internal auditors, or to pull resources so that they can create
an audit office serving all or part of the districts.
The Program supported the implementation of the WAN in all the districts and in the MOF and
MRD by providing: (i) infrastructure; (ii) hardware and software; and (iii) training.
Component III- Citizen participation and program outreach: The p u r p o s e o f t h i s
component was to engage citizens and stakeholders in the decision making process to achieve
greater transparency and accountability in the districts. Therefore, this component supported: (i)
creation of the citizen participation committees (CPC) at the district level in the new pilot
districts and also the strengthening of those existing in the certified districts; (ii) creation
and training of neighborhood committees at the community level to monitor and report
progress of capital investment projects; (iii) creation and operation of the Citizens
Information Centers (CIC) in all the Ressorts; (iv) provision of training to district trainers;
(v) implementation of a promotion and outreach action plan by the CICs; and (vi)
development and implementation of a strategy for consensus building of all central
government stakeholders by the Program Implementation Unit (PIU) regarding the legal
framework.
Under DLGP-I, a CPC committee was created in each of the certified districts to engage
citizens in the selection and monitoring of district projects. The Program aimed to continue this
effort by creating a committee in each of the new pilot districts and by strengthening the
existing committees. As visualized the CPC comprised of representatives of non-governmental
organizations and community based organizations operating on a voluntary basis.
Furthermore, DLGP-I fostered the creation of five CICs at the district level. CIC is a local
government institution that provides information and fosters citizen mobilization through various
communication and dissemination activities. DLGP-II supported the creation of another five CICs
in the remaining districts. The recurrent costs of CICs are financed by the districts with their
15
general budget. After project termination, the districts will assume the recurrent as well as
the future capital costs of CICs.
DLGP-I supported the development of Promotion and Outreach Plans (POP) to: (i) raise
awareness and obtain active citizen participation for identification of project development; and
(ii) identify issues during project execution. DLGP-II supports the implementation of POP in
the new pilot districts and further implementation of POP in certified districts. POP includes
awareness campaigns on the setting of new laws, taxation and auditing functions.
The Program supported the formulation and implementation of a Citizen Participation Plan
(CPP) in the new pilot districts. The CPP describes the measures to be undertaken by the
districts to ensure adequate citizen participation in the administration of the affairs of the
district. The envisioned CPP is subject to the d i s t r i c t a t ta in ing a c e r t i f i c a t i o n Level 2 .
The CPP i n c l u d es a l o g i c a l framework for citizen participation, a detailed description of
specific activities, as well as guidelines and procedures for the CPC.
Finally, the Program supported the development of a strategy for consensus building of all
central government stakeholders to facilitate inter-governmental coordination.
Component IV– Capital investment capacity building and investment program: DLGP-I
focused on: (i) creating the capacity to manage and maintain basic infrastructure in the
certified districts; and (ii) financing trial road projects. DLGP-II: (i) consolidates institutional
capacity in the already certified districts; (ii) creates institutional capacity for managing basic
infrastructure projects and services in the new pilot districts; and (iii) finances basic
infrastructure projects and services in the certified districts and trial projects for the new pilot
districts, once they are certified at Level 2.
The Program used a participatory methodology to identify, prioritize, and select beneficiary
communities. A ranking system used in all 29 Ressorts in the certified districts considers the
following indicators: (i) households size within the community; (ii) access to healthcare,
utilities (electricity, potable water), education, and garbage collection; (iii) condition of the
road network and drainage systems; (iv) agriculture activities; and (v) recreation facilities. The
project selection methodology is included in the Operating Regulation Guidelines (ORG).
In parallel to the ranking exercise, the districts with the support of the PIU conducted hearings
with communities from all the Ressorts. Four priority sectors were identified: (i) secondary and
tertiary road paving; (ii) basic drainage; (iii) solid waste collection; and (iv) public market
upgrades. Ressort and District Councilors, also with support from PIU consultants, identified
project initiatives.
16
Districts selected the priority projects based on: (i) ranked beneficiary communities; (ii) the four
priority sectors; (iii) a cost-effectiveness analysis; and (iv) resources availability. The Program
includes provisions to achieve sustainability within the economic life of the project and define
a plan for their maintenance.
The component supported the districts in formulating and evaluating the selected projects.
It also provided technical assistance for pre-investment activities, and the procurement and
supervision of construction of the specific projects. Finally, the component supported the
districts in formulating the necessary maintenance and operation plans once projects were
finished.
IV. FINDINGS
A. Effectiveness
1. Results for milestones, outputs and outcomes
The tables below are prepared as follows: for components I and II the End of Program planned
indicators stated in the PMR for the second period January-December 2013, are compared with
the actual results found at September 2014.3 For components III and IV, the planned indicators
and the results are extracted from the PMR for the period January-June 20144.Table I shows the
comparison of End of Program (EOP) results for milestone and output indicators. Table II shows
the same results for the outcome indicators. Table I should be read in conjunction with the
narrative or comments for those results expressed in the section “Achievement by component”
and Table II in conjunction with the Comments on section “Outcome achievements”.
Table 1.
EOP Milestone and Output Indicator comparison at September 2014
Milestones and Output Indicators by Component Units Baseline Plan Actual
Component I- Legal Framework-Milestones
1. Traditional Authority Law Drafted Bill None 0 0
2. Agreement between Districts and GLIS Authority (ex
Cadastre Law)
Agree-
ments
None 12 0
3. Laws included in Article 4 of FDIL updated Bills FDIL 1 2
4. Training on decentralization laws Worksh None 0 0
5. State Decree incorporating Districts to DLGP II issued Sta.Dec 5Districts 10 10
6. MRD/MOF Resolution Districts Level I Certificate
issued
Resolu 5Districts 10 10
3 The planned indicator used is the one shown as P(a), indicating that the indicator was reviewed during execution.
4 After the FER was completed, the PIU and the IDB updated the PMR and decided to update the indicators for
components III and IV in the FER.
17
7. Handbook bundle of legislation and procedure for local
government.
Ordinan
bundle
0 1 1
Component I Legal Framework-Output Indicator
Regulatory framework redesign to favor local government
capacity
Framework 0 2 1
Component II-Financial, Planning and Administrative
Capacity-Milestones
1. BFM Systems installed Systems 5Districts 5 6
2. Local tax administration systems installed Systems 5Districts 7 7
3. Local tax administration method and procedures in
place
Method 5Districts 6 7
4. Internal auditing (IA) capacity in the Districts installed Unit MRD/IA
unit
10 0
5. District administrators (DA) positions created DA 5 15 15
6. WAN installed in Districts Districts 0 15 11
7. WAN installed in MRD MRD 0 1 1
8. WAN installed in MOF MOF 0 1 0
9. Districts Offices fully rehabilitated Districts 5 10 10
10. Training provided Workshops 7 25 25
11. Administration and planning systems installed Systems 3
Component II-Financial, Planning and Administrative
Capacity-Output indicator
Administration and planning system to favor local
government capacity
Systems 2 2
Component III- Citizen Participation and Program
Outreach-Milestones
1. Citizen participation plans (CPP) in place CPP 5 5 5
2. Neighborhood Committees (NC) in place NC 0 38 38
3. Citizen Participation Committees (CPC) in place CPC 5 0 0
4. Citizen Information Center (CIC) in place CIC 5 15 13
5. Training Provided Workshop None 50 50
6. Promotion and Outreach Plan (POP) in place POP 5 10 10
7. Consensus Building with Central Government Ministries 1 0 1
Component III- Citizen Participation and Program
Outreach-Output
Citizen participation approach in place to favor participati,
accountability, and transparency at local level.
Approach 1 1
Component IV-Capital Investment Capacity Building and
Investment Program-Output indicators
1. Roads, drainage, garbage collection and market
facilities works
Investment
Projects
45 45
2. Projects design under capital investment projects Projects 0 8 8
18
Table II
Outcome indicators comparison at September 2014
Outcome: Local government capacity enhanced
Indicators Units Base-
line
Base
Year
Planned Actual
Legislation favoring decentralization passed legislation 1 2008 2 0
Districts certified for autonomous financial capacity
and systems
Districts 5 2009 10 10
Districts certified for enhanced management capacity
of capital investment projects
Districts 5 2009 10 10
Outcome: Fiscal relations between central and local government improved
Indicator Units Base-
Line
Base
Year
Planned Actual
Projects executed by certified districts Projects 0 2008 50 26
2. Achievements by component for milestones and outputs
Component I- Legal Framework-Milestones
1. Draft Law on Traditional Authority: the aim of this subcomponent was to integrate the
traditional laws of aboriginal people into the laws of regional Districts. A technical study
was done in 2010, and a consultant was contracted to draft the law regulating the role of the
Traditional Authorities. This consultancy was cancelled, with IDB approval, by the
Minister of MRD due to political sensitivities. Thus, the original planned milestone was
changed from 1 to 0.
This law would affect mostly the aboriginal people that inhabit the Sipalawini District
which represents around 80% on the Suriname territory and where legal and illegal mining
is taking place. No studies exists at the present time of the possible risks to the culture and
traditions of the aboriginal due to mining exploitation. Furthermore, there appears to be no
consensus among the aboriginal people or among government agencies as to whether
integration of traditional law should proceed and how.
Achievement in comparison to current planned indicator: N/A indicator was eliminated.
2. Agreement between GLIS and the 10 Districts: The original intent of this subcomponent
was to prepare technical and legal studies and to draft legislation in the field of cadastre at
the District level. While the studies were being conducted, National Assembly approved
the Law of Cadastre and on the basis of this law the Program then prepared the technical
and legal studies as well as 10 agreements to be signed between each of the Districts and
19
GLIS5permitting the free use of GLIS Cadastre data by the Districts. The agreements were
forwarded in 2011 to each of the Commissioners in the 10 Districts, to GLIS and to the
Minister of MRD, who stopped the signing of the Agreements. Their signature is still
pending in MRD.
Achievement in comparison to current indicator None (0%)
3. Update the Article 4 laws of the Federal Decentralization Interim Law (FDIL): The
objective of this task was to review the very low level of tariffs for taxes and non taxes, as
well as incorporating these sources of income for the Districts in draft bills regulating
Districts’ revenues. In September 2011, the Program forwarded one draft law and one state
decree to MRD which in 2012, in turn, submitted them to Cabinet. There has been no
progress with their approval since then.6 In other words, while the laws were updated and
thus the indicator was accomplished, the benefits of implementation of the updated laws
are still absent.
Achievement in comparison to current planned indicator: Mixed. Draft legal documents
prepared, but never approved nor implemented.
4. Training on decentralization laws: DLGPI prepared two key laws for the decentralization
of the Districts: the Law of Financial Relations with the Districts; and the District Tax
Law. The former, aimed to create a District Equalization Fund (DEF) to be managed jointly
by MRD and MOF, would transfer funds to the Districts to cover budget shortfalls. The
transfer to be done from the national budget on the basis of economic and social indicators.
On the other hand the District Tax Law aimed to increase tax revenues by allowing the
districts to introduce local taxes and non taxes by District’s Ordinance. These laws were
submitted to cabinet on 2008 and again on 2012. An IDB mission at the beginning of
October 2013, and again in February 2014 expressed to the MRD authorities that the
approval of these laws, is the cornerstone for current and future institutional and fiscal
consolidation of the Districts and concluded that non approval of these laws is the main risk
facing the successful completion of the program. Because these laws have not been
approved the subcomponent on training and its indicator were eliminated.
Achievement in comparison to current planned indicator: N/A. Indicator eliminated
because laws on which training was planned were never passed.
5. State Decree incorporating districts to DLGPII issued: To participate in DLGPII a state
decree is necessary. All districts have been so incorporated. Achievement in comparison to
current planned indicator: Fully achieved
5 GLIS, Geographical Land Information System, is an agency in the Ministry of Ground and Land Use. In operation
since the end of 2010, is charged with the digital plotting of land for registration and titling. 6 After Cabinet receives a law proposal, the procedure calls for presentation of the proposal to the President, who
after consultations with his advisers sends the law to Parliament.
20
6. MRD/MOF District Level 1 Certification: As part of the capacity strengthening of the
Districts, they are certified at two levels: For level 1 the Districts require: (i) to have
installed a core administrative, budgetary and financial management system; (ii) to have
installed a tax administrative system; and (iii) the contracting of a District Administrator.
To qualify for Level 2, in addition to the preceding requirements, the Districts must show:
(i) a strategic development plan; (ii) the capacity for revenue generation; and (iii) the
installation of a civil works management system. At present, all of the Districts are certified
at Level 1 and Level 2. In this accomplishment the PIU was very proactive even advancing
with the fulfillment of level 2 requirements, in the face of MRD/MOF bureaucratic delays
with the approval of Level 1.
Achievement in comparison to current planned indicator: Fully achieved
7. Handbook bundle of legislations and procedures for local government: Through this
component the Program in 2011 prepared for the Districts a compilation of laws, bylaws,
district ordinances, and financial guidelines regulating the financial accounting and
procedures at the level of the Districts. This compilation, organized in the form of a
manual, was sent to the Districts through MRD.
Achievement in comparison to current planned indicator: Fully achieved
Component I-Legal Framework-Output
Regulatory framework redesign to favor local government: The seven original milestones related
to the output indicator can be classified in two different frameworks: The first framework of a
legal nature containing four milestones (traditional authority law, agreement Districts/GLIS,
Article 4 FDIL, training on decentralization laws), and a second framework of an organizational,
administrative nature (incorporation of the districts to the program, level 1 certification, and
handbook of procedures and existing legislation). The second framework was fully implemented.
As to the first, the milestones were: (i) eliminated either because of political sensitivities or in the
case of training because the decentralization laws have not been passed; or (ii) not fully achieved
because the approval process has been withheld (article 4 FDIL, Agreement Districts/GLIS). It
appears that the executing agency MRD has problems advancing the approval of legislation.
Achievement in comparison to current planned indicator: 50% considering the execution
achievements of the organizational/administrative milestones and the lack of execution of the
legal milestones
Component II-Financial, Planning and Administrative Capacity-Milestones
1. BMF installed: The objective was to install in the new pilot districts the financial systems
comprising software, hardware and training for accounting, budgeting and reporting. PIU
has shown a great deal of accomplishment under this activity not only by implementing the
systems in the new districts, including a new one created in Paramaribo, but also by
21
upgrading the software of the systems in the DLGPI districts. When directed by GOS to
change the software in 2010 to avoid license fees, PIU was proactive in researching and
finding the open source software (“Open Resource Planning-Open Erp”) and adjusted the
work of the consultants to implement the systems and manuals using this software.
Notwithstanding these accomplishments, it is possible that there may be the need for major
adjustment to the BFM systems in the future. Early in 2014 GOS decided to use open
source software called Free Balance in the public sector which by necessity will include the
Districts. This is a future activity that will require a considerable effort in changing the
software, preparing new manuals and training the users. It is difficult to assess when this
change may be needed at the level of the Districts, given that the change in the public
sector has not begun as yet.
Achievement in comparison to current planned indicator: More than fully achieved,
however pointing out the possible need for further future revisions and changes in the BFM
subcomponent.
2. Local tax administration systems installed: This activity is geared to implement a
simplified tax administration system in the districts to manage the registration and
collection process for all local taxes and fees and to convert the tax reporting system to
MRD and MOF from manual to electronic. Currently the Districts collect the RVT and the
PET taxes, and report manually to MRD and MOF using a system set up with the help of
TAO which also trained the district on the forms, the procedures to use and the records to
keep. It should be pointed out that the system is simple and at present does not include a tax
accounting system and that consequently the accounting of taxes collected as revenue by
the districts is recorded in the financial accounting system developed in the program by the
BFM activity. The tax accounting system is important because it will permit to have as a
part of the system a data base of taxpayers with their respective collection history.
Furthermore, one of the requirements for Level II certification was the measurement of the
collection rate for RVT. But without a tax accounting system with a recording of the
receivables from taxpayers, such measurement is not possible. Further work will be needed
in the future for the eventual development of a tax accounting system in the districts.
While analyzing the activities in this indicator the consultant was made aware of some
apparent problems that under observation were not technical or structural in nature, but that
may be more related to communication shortfalls: There is an impression at a high level of
MOF that there are connectivity problems between the districts and TAO that should have
been resolved by the program. In fact, because of security reasons the connectivity afforded
by the WAN system developed in the program (see below), cannot be used because tax
information must be transmitted in a dedicated, secure line. TAO is proceeding according
to its plans which include developing in the future a dedicated connectivity line between
TAO and the districts. TAO will finance this activity with its own budget. Apart from the
22
connectivity issue, the use of the new software Free Balance to connect the district systems
with TAO systems (mentioned above) will have to be resolved. At this point there are
neither plans nor budget to this effect.
Finally, it should also be pointed out that the planned and actual indicator of 7 districts do
not include the districts of Coronie, Brokopondo, and Sipalawini which have no tax base
for RVT
Achievement in comparison to current planned indicator: Fully achieved, with the caveat
that further work will be needed in the future for this activity.
3. Local tax administration methodology and procedures in place: As pointed out in the
preceding numeral the procedures for local tax administration were set up with the
assistance of TAO. The methodology and procedures were set up at the seven districts
where the local tax administration system was set up.
Achievement in comparison to current planned indicator: Fully achieved, with the caveat
that further work will be needed in the future for this activity.
4. Internal Auditing (IA) capacity in the Districts installed: The objective was the
implementation of internal audit capacity at the district level by either setting up a unit for
each district, or by pooling resources to organize one office for a group of districts or for all
the districts. The request to initiate this activity and the corresponding TORS, were
presented to the IDB only in July 2013. This delay was due in part to several factors: (i) the
lack of qualified auditing personnel to set up an IA unit at the level of individual districts,
or as one office for several or all of the districts; (ii) the reviews required in the financial
BFM system of the districts as a result of the change of financial software to Open Erp.
Because audits are conducted to asses compliance with existing financial procedures and
regulations, the BFM manual which contains district financial procedures needed to be
updated. Another part of the delay appears to be related to the lack of participation of
MRD, particularly the Internal Control Unit, in the process of either supporting the creation
of an independent audit unit for the districts, or – in the case of the Internal Control Unit -
becoming the Internal Audit Office for all the Districts, as a part of the audit functions it
already carries out. In this regard, at present the program has a consultant for supporting the
work and organization of the Internal Control Unit. Some preparatory work has been
planned by this consultant, but this work is dependent on the selection of counterpart
personnel of the Internal Control Unit at MRD. This selection has not occurred and the
consultant’s work has stopped.
Achievement in comparison to current planned indicator: None.
5. Districts Administrators (DA) positions created: This activity is geared toward the
selection, recruitment, and training of district administrators charged with supervision of
23
administrative and financial functions for the new districts in DLGPII. Being a condition
for level I certification, particular attention was given to the selection and training of the
administrators. The potential administrators were selected by a Commission composed of
representatives of PIU, MRD, the District Commissioner’s office and the District Councils.
Consultants were contracted for the preparation of the job description and of the regulations
for recruitment and selection as well as for initial training. During program execution,
training was also provided by PIU and MRD staff. Because Paramaribo split into 2 District
Offices, the final aim of the program was adjusted to establish have administrators in all 11
districts, counting the five from DLGPI. As execution progressed the original district of
Sipalawini was also split - into 5 Districts - resulting finally in an actual implementation of
15 DAs.
Achievement in comparison to current planned indicator: Fully achieved
6. Wide Area Network (WAN) installed in the Districts, in MRD and in MOF: the objective of
this activity was to install an information and communications technology network (ICT)
connecting the districts with both the MRD and the MOF via a WAN to facilitate the
harmonization of financial and data transfer, and to give the individual taxpayer the
facilities to pay in any location. At present the following has been accomplished: (i) the
financial departments of all districts have connected to the WAN. This included the
installation of the Open-erp software and the training on the use of the WAN and of the
software; (ii) MRD has also been connected to the WAN; (iii) document circulation
software has been installed in 4 districts and in the 12 Ressorts of the Paramaribo district;
(iv) Citizen Information Center (CIC) news channels were established in all districts
established through Facebook, where citizens can get information on what is happening in
their districts and input their commentaries. The planned indicator for the districts is 15, as
compared to the actual of 11. The difference is the 4 newer offices in Sipalawini, where the
WAN has not been connected as yet. The planned and the actual indicator deal only with
the WAN connections to the financial departments in the districts, and, as such do not
include the additional achievements associated with the WAN system (document
circulation, Facebook for CICs).
The WAN has not been connected to the MOF/TAO for the reasons expressed before under
the milestone “Local tax administration installed”.
Achievement in comparison to current planned indicator for the districts: Not fully
achieved with the proviso that neither the planned indicator nor the actual include the
additional achievements unrelated to the financial offices. For MRD: Fully Achieved. For
MOF: no achievement.
7. Districts offices fully rehabilitated: included the provision of equipment and the
rehabilitation of offices to accommodate the new financial system, the office of the district
24
administrator and the offices newly created to organize the Commissioner office and
his/her district team. As planned all district offices were rehabilitated.
Achievement in comparison to current planned indicator: Fully achieved
8. Training provided: Under this component training covered the areas of BFM, tax
administration, the use of newly installed software and the WAN. Training at the outset
was provided by a consultant and later given by PIU and MRD staff. The number of actual
workshops agreed with those planned.
Achievement in comparison to current planned indicator: Fully achieved
9. Administration and planning systems installed: This milestone has unit of measure and
indicator number similar to that of the output indicator, and consequently it has not been
analyzed separately.
Component II-Financial, Planning and Administrative Capacity-Ouput
Administration and planning systems to favor local government capacity: This component
worked for the support of the districts in three areas: (i) financial planning/budgeting and
administration (BFM, tax administration and WAN as information channel); (ii) district
administration (posts of DA, organization of offices, WAN as channel of communication); and
internal control (audit). Accomplishments were notable in the first two areas with actual results
equal or very close to plans. For the third area there were not accomplishments. Thus, the
planned indicator should have been 3 systems, for which 2 systems had high achievements. In
consequence the level of achievement in comparison to current planned indicator in terms of
systems could be expressed as 2/3 or 67%.
Regarding Component II it should be mentioned that the actual activities also included the
preparation of 5 District Strategic Development Plans. For these plans, which were prepared with
the support of consultants, there is no current indicator in the PMR.
Component III-Citizen participation and program outreach- Milestones
1. Citizen participation plans (CPP) in place: In DLGPI 5 CPPs were implemented. In this
program this activity is directed to the new pilot districts. Its objective was the formulation
and implementation of plans to guide and ensure adequate citizen participation in the
administration and affairs of the districts. The CPP- prepared by the districts in close
cooperation with PIU and with the help of consultants as required- are one of the conditions
for the districts to attain certification level 2. All new pilot districts in DLGPII prepared the
CPP.
Achievement in comparison to current planned indicator: Fully achieved
25
2. Neighborhood Committees (NC) in place: These committees formed at the community
level with the aim to monitor and report progress of capital investments in neighborhoods.
Integrated by a mix of neighbors (both sexes, old and young), they were instructed on
simple monitoring procedures, on the content of tender documents and on basic patterns of
conduct toward contractors. NC became an exemplary form of citizen participation, not
only monitoring the quality and timing of the work being carried out in the neighborhood,
but also improving business relations with contractors by collaborating with them in
ensuring the overnight safety of their equipment. During program execution the NC were
formed in the number needed.
Achievement in comparison to current planned indicator: Fully achieved
3. Citizen participation committees (CPC) in place: The objective for this activity was to
continue in the DLGPII with the formation of CPCs under the same principles applied for
those started and already implemented during DLGPI. The role of the committees was one
of selection and monitoring of district projects, the principle was the participation on a
voluntary basis of NGO and Community Based Organizations (CBO). However as
execution of the program progressed, NGOs and CBOs, requested compensation and
equipment for their participation on the CPC. Given that these requests could not be
financially satisfied by the program, in 2010 the CPCs were moved to the level of the
Ressorts, where it now functions as needed with local NGOs acting on a voluntary basis.
Because district projects are determined after consultation with the Ressorts, this change
had no effect in the participation of the community in the selection of projects. There is no
information whether the monitoring of district projects intended to be performed by the
CPC has suffered. This may be due to the mitigation resulting from the well organized
supervision being carried out by the engineering group at PIU and at MRD.
Achievement in comparison to current planned indicator: Not achieved due to justified
reasons.
4. Citizen information centers (CIC) in place: Created at the district level, CIC is a local
government institution that provides information and fosters citizen mobilization through
various communication and dissemination activities. DLGPI created 5 CICs. DLGPII was
to continue supporting the creation of CICs in the pilot districts of the program. The main
benefit of this subcomponent has been the centralization and accessibility of information at
the local level, with an information office with its own server and with its own facebook
page to transmit information to its citizens and receive feedback from them electronically.
Due to the split of Sipalawini into 5 District offices, and Paramaribo into 2, a total of 15
CICs were planned during execution of DLGPI and DLGPII, with 13 CICs actually needed
being implemented.
Achievement in comparison to current planned indicator: Fully achieved
26
5. Training provided: Training was ample and conducted in several areas: (i) to
commissioners in public management and public administration; (ii) to CIC personnel on
communication tools and to NC on works’ monitoring; (iii) to resorts and district councils
on citizen participation harmonization mechanisms and on tools to organize hearings; and
(iv) to PIU and MRD personnel as trainers training. The training was conducted first by
consultants and, as experience and knowledge improved, by PIU and MRD personnel. An
estimated number of 50 workshops were conducted.
Achievement in comparison to current planned indicator: Fully achieved
6. Promotion and outreach plans (POP) in place: POPs were established to: (i) raise
awareness and obtain active citizen participation for the identification of project
development; and (ii) identify issues during project execution. Through this
subcomponent, PIU promoted - and citizens expressed their views - on projects in 8
communities of the new pilot districts. PIU also promoted the work of the DLGP in the Fair
of the Chamber of Commerce and is currently developing a book directed to the general
public and to government on the 12th
anniversary of DLGP. Finally, the program assisted
the Districts in the creation and implementation of their own websites and facebook sites,
further contributing to the promotion and awareness of the program. PIU has counted each
of these actions as programs, for a total of 10 promotional activities completed.
Achievement in comparison to current planned indicator: Fully achieved
7. Consensus building with central government: Because of the several ministries involved,
the objective of this activity was to support the development of consensus among all central
government stakeholders to facilitate inter-governmental coordination. Only one ministerial
meeting was held, and in 2010 MRD cancelled this activity arguing that ministries have an
obligation to collaborate in government programs, without the need of a special activity to
this end.
Achievement in comparison to current planned indicator: Not achieved due to cancellation
of activity
Component III-Citizen participation and program outreach- Output
Citizen participation approach in place to favor participation, accountability, and transparency
at local level: Measured from the point of a vertical analysis in which the level of achievement of
the milestones determines the level of the achievement of the output, it could be advanced that
the output’s component has been fully or mostly achieved. At the close of the program, there is
much evidence demonstrating the important accomplishments in this regard: Citizens at the level
of the Ressorts participate in open hearings for the multiannual planning of the resorts that, in
turn, evolve into the District plans; communities and neighborhoods now have a voice in the
27
projects affecting them and can monitor their advance or delays; the internet, through the
districts own websites has put the citizens in touch with the business of the district government
and has opened a way for citizens to communicate with their government.
Achievement in comparison to current planned indicator: Fully achieved in terms of the
achievement of the milestones supporting the output approach.
Component IV-Capital investment, capacity building and investment program- Output indicators
1. Roads, drainage, garbage collection and market facilities works
2. Project design under capital investment projects
The narrative that follows was prepared on the basis of the research on site performed by the
consultant in September 2014, complemented by the information in a PIU’s matrix received in
November 2014 showing the breakdown of the actual work done for this component.
In summary Component IV had as objectives: first to create and consolidate capacity in the
districts to manage and maintain basic infrastructure projects; and second to finance basic
infrastructure in the certified districts and trial projects in the new pilot districts. In regard to the
first objective the program set up civil technical and environmental units in all districts, and
provided an extensive training program involving: (i) the methodology to select road and
drainage projects; (ii) the preparation of tender documents for roads; (iii) the process of
contracting, reporting, quality control and supervision in the execution of road projects; (iv)
environmental requirements in road projects; (v) procurement; (vi) preparation and execution of
solid waste projects; and (vii) rehabilitation and maintenance of public markets. In addition,
manuals were prepared for the maintenance of roads and for the maintenance of drainage
systems. Furthermore, for the first time in the country a digital inventory was prepared for
secondary and tertiary roads, and for drainage.
With regards to the above mentioned second objective, 10 training projects were executed in the
pilot districts. While all of them were worthwhile projects, there is one in particular that stands
out, the Sipalawini Communication Path Project, connecting small communities that have been
isolated or badly connected for well over 30 years. The project, which included the construction
of 22 new bridges with a total extension of 1000 meters, benefited 47 small rural communities.
Additionally, in the certified districts a number of small infrastructure projects were designed
and executed, including; 12 road projects, 7 drainage projects, 2 urban markets, and 5 solid waste
projects for a total of 26 projects.
The component suffered some delays: in 2010 due to the electoral process, at the end of 2013
due to the uncertainty as to whether the program was going to continue after the then contract
final project date, and for some time in 2011 for disbursement delays caused by adjustments
28
required by the centralization of the government treasury function. Notwithstanding these delays
the component performance is highly satisfactory in terms of number of projects and execution
time and this is due to a great extent to three factors: (i) the communities participated in the
identification of infrastructure projects; (ii) there was a joint MRD/PIU supervision; (iii) the
packaging of several small projects into one for contracting to avoid the administrative and
contract supervision delays occasioned by many small projects. This showed flexibility and
prompt action on the part of PIU.
The November 2014 PIU matrix shows the following breakdown for actual work accomplished
in the component: (i) create institutional capacity new pilot districts-6 projects; (ii) consolidate
institutional capacity certified districts- 7 projects; (iii) Training projects in new districts- 10
projects; and (iv) small infrastructure projects (roads, drainage, garbage collections and markets)
in certified districts- 26 projects. This categorization and numbers do not correspond to the
indicators categories and numbers stated in the PMR for January-June 2014 and shown on Table
I. Consequently, while from the point of view of results the component was successful, it is not
possible to measure the achievement based solely on the comparison of Planned and Actual
indicators from the January- June 2014 PMR.
Achievement in comparison to current planned indicators: N/A
3. Achievement for Outcomes
Outcome: Local government capacity enhanced
Legislation favoring decentralization passed:
This outcome was not achieved and is a major risk for the sustainability of the program. There
are three pieces of legislation and a set of agreements that favor decentralization and that bear
directly on its success. They are: (i) the Law on Financial Relations with the Districts; (ii) the
District Tax Law; and (iii) the updated article IV laws of the FDIL, as well as (iv) the 10
agreements between the districts and the GLIS authority. The nature of this legislation has been
discussed previously in this report. All are quite important for the organization of a financial
framework for decentralization, especially the first two laws which are specifically geared
towards the generation of district revenues and the participation of the national budget in the
district finances. This approval of this legislation has been in suspense between 4 and 6 years.
MRD has shown limited pro-activity in moving along this legislation, apparently because it
lacks the political power.
Achievement in comparison to current planned indicators: None.
29
Districts certified for autonomous financial capacity
Districts certified for enhanced management capacity for capital investment projects
The first of the above indicators has to do with Level I certification, the second with Level II
certification. At present all districts have been certified at Level I and at Level II
Achievement in comparison to current planned indicators: Fully Achieved from the point of view
of certification. However, the Districts have not reached autonomous financial capacity as yet
Outcome: Fiscal relations between central and local government enhanced
Projects executed by certified districts
The planned indicator number for this outcome is P=50. As reported above under “Component
IV -Capital investment, capacity building and investment program - Output indicators”, the
number of projects executed by certified districts was 26, that actually agrees with the output in
the PIU plans. From the point of view of P=50 projects and A= 26 projects, the outcome has
been partially achieved. However, the indicator and its number raise some questions: the
indicator (projects) does not seem to be related to the nature of the outcome, namely: “Fiscal
relations between central and local government enhanced”. A more appropriate indicator in the
sense of being closer to the nature of the outcome probably could have been for instance “Law
on Financial Relations with the Districts approved”7.
4. Program budget and projected costs
The following table shows by cost categories the original budget and the projected cost to the
end of the program. The table was prepared using unaudited data, which means the amounts
could be somewhat different in the final program’s audited financial statement.
7 In fact the means of verification is: “MOF issues resolution assigning transfers to certified districts”
30
Table III
Budget and projected costs as of September 22, 2014
The columns “Differences in %” measure the relation in percentages between the projected
expenses and the original budget. Overall projected total expenses are very close to the amount
budgeted (96.8%). On a cost category basis the major differences are an expected over budget of
33% in program’s administration due to the increase in the execution period, with most of the
increase of the cost arising from the overhead charged to the program for the assigned rental
value of the PIU premises and for utilities. In the components themselves there is an expected
under budget difference of approximately 36% in Citizen Participation Outreach which is mostly
due to the suspension in the organizing of CPC, lower expenditures on the creation and
organization of CICs, and the budget movement of local resources from this component to the
Capital Investment component. There is also an expected under budget difference of about 25%
in the component Financial Planning and Administration mostly due to expenditures not effected
in the training on the decentralization laws which have not been passed, and of 89% in Audit and
Contingencies due to no expenditures, commitments, or budget reclassifications for
Contingencies.
B. Efficiency
1. Organizational structure
For execution the program organized a Program Implementation Unit (PIU) headed by a
Managing Director and comprising 4 professional task managers-one for the Works and Capital
component, one for the Administration, Finance and Planning component, one for Citizen
Participation and one for the ICT/WAN component. The Managing Director, in addition to his
normal duties, also had an operational role with the activities in the Legal component. This
structure was reproduced at the MRD and at the District levels -- as TMRD (within the MRD)
and DMT (in each of the Districts) . This overall structure was to be supported by a task force in
Cost Category
GOS IDB TOTAL % GOS IDB TOTAL % GOS IDB TOTAL
Legal Framework 0 85 85 0.6 0.0 84.3 84.3 0.6 99.2 99.2
Financial, Plan. & Adm. Capa 450 1450 1900 12.7 158.2 1268.5 1,426.7 9.8 35.2 87.5 75.1
Citizen Partici & Prog. Outreach 300 540 840 5.6 110.0 431 541.0 3.7 36.7 79.8 64.4
Capital Inves, Capac. Buildin and
and Invest. Program 370 9480 9850 65.7 651.9 9443.2 10,095.1 69.5 176.2 99.6 102.5
Program Administration 244 1500 1744 11.6 660.7 1653.1 2,313.8 15.9 270.8 110.2 132.7
Audit and Contingencies 136 445 581 3.9 0.0 62.9 62.9 0.4 0.0 14.1 10.8
TOTAL 1500 13500 15000 100.0 1,580.8 12,943.0 14,523.8 100.0 105.4 95.9 96.8
% 10 90 100 10.9 89.1 100.0
Original Budget (000) Projected Expenses Differences in %
31
the MOF (TMOF), to provide assistance in the quality control of financial activities for the
districts Level 1 certification.
TMRD, headed by an Assistant PS, was designed to work actively and jointly with the PIU, so as
to develop within the permanent staff of MRD knowledge and experience in program execution
with an IDB program. At the district level, the DMTs -- headed by the respective District
Commissioner, directing task managers organized one for each component -- aimed to ensure
functional counterparts to PIU/TMRD.
The findings-strengths and limitations- found in the organizational structure are described in the
following paragraphs.
1. Organizational structure was well conceived: A strong PIU with the required systems and
human resources working actively with a TMRD mirror unit would ensure know-how
transfer and ensure continuity of a capable executing unit. Both units, in turn, working with
counterparts at the district level formed an integrated execution structure, and at the same
time increased the availability of human resources for execution. The support of TMOF
ensured quality control in the key financial area of financial administration.
2. PIU developed high quality systems and efficient internal operations: Operations are based
on a well prepared operating manual (ORG) detailing 10 steps involved in the program and
the procedures and responsibilities necessary to carry them out. The ORG, in turn, is
supported by planning and monitoring systems, as well as administrative, accounting and
contracting systems. Operationally PIU has performed efficiently - even under constraints in
the normal execution process. For instance, in spite of the delays caused by the elections in
2010, the program was able to keep up with the planned goal for that year and for year 2011.
In response to the GOS request for a change in the type of software for the financial
administration, PIU found the necessary new software and adjusted the work of the
consultants. What is more remarkable is that at present, as the program is closing, it is
executing on time an important part (in number and value) of the investment component,
despite a major decrease of staff and with serious constraints in petty cash to cover
operating expenses. Part of the recent success has been due to the support received from the
technical unit at TMRD.
3. Continuity and strong leadership: The PIU has had a capable director which has served
continuously DLGPI and DLGPII. He was able to build around him a professional and
cohesive team, highly identified with the program and with its success.
4. Coordination with TMRD not entirely satisfactory: TMRD has developed into a current
structure with a staff of around 27 persons, the majority of them university trained. The
32
level of coordination and joint working with PIU has been mixed: It has generally been very
good for citizen participation and the ICT components; and poor in the legal component and
the financial/administration component. In the civil work area the level of joint work
participation was not consistent, being good to very good in some projects (for instance the
current project in Sipalawini) and absent in others. This experience can be explained by
several factors:
(a) Lines of reporting and the nature of the program: both the PIU Managing Director and
the Assistant PS (in charge of TMRD ) report to the MRD Permanent Secretary. The
program’s nature involves not only the execution of the four components, but also the
organizational development of the TMRD team for a potential role as executing unit in
the future, when the PIU is no longer considered necessary. In this type of situation in
which one of the partners has a role of learner (TMRD) and the other of teacher (PIU),
while both are to share the operating responsibility as task managers for execution, a
very good understanding of the program and a very strong leadership and direction is
required at the very top, so that this mix of roles are carried out smoothly at the
subordinate level. This leadership and direction should have been present at the
inception of DLGPII - at the level of the PS. But this was not the case. In the absence of
this initial leadership and direction, the coordination between teams was left laregely to
individuals’ likes, dislikes and objectives. This may be the reason for having good
collaboration among PIU and TMRD in some components, but not in others. It should
be pointed out that leadership and knowledge of the program has vastly improved with
the current PS at MRD.
(b) The function of the TMRD: From interviews with its members, it appears that TMRD
regards its main function as one of supporting the districts in the areas of the program’s
components, namely: legal, administration and finance, citizen participation, and capital
investments8. It is not clear how long this perceived function has been in place, or
whether it has been officially assigned. From this perspective, it is justified for TMRD to
see itself not only as the mirror team, but also and mainly as MRDs district support
team, on its own right. The problem with this view, when not properly set up and
communicated, is that staff at the TMRD team may give priority to their own perceived
functions at the cost of activities of program collaboration to meet DLGP targets.
5. MOF unilateral decision to terminate the MOF team: In the first quarter 2011, the PS of the
Ministry of Finance decided to stop the team MOF (TMOF) under the logic that the
functions assigned to the team were the normal functions of the Ministry, and consequently
8 An institutional analysis of capacity of the TMRD team was not in the TORS of the consultant. However, a
superficial analysis shows good capacity in civil engineering for the capital investment component, and in the citizen participation component. The legal area and the administration/finance area would have to be reinforced.
33
there was no need for a special team and that PIU could at any time go to the MOF to
request that support. There were two aspects not considered in that decision: (i) the
participation of TMOF is established in the ORG and it is part of the contract with the IDB.
In accordance with Section 4.05 of the contract especial conditions, any changes in the ORG
must have the prior approval of the Bank. Such approval was neither sought nor obtained;
(ii) eliminating TMOF stopped the direct link between technical staff, and introduced
bureaucratic steps to get TMOF collaboration through the PS. One practical result was that
TMOF never participated again after 2011 in the process of certification. The unforeseen
distancing from PIU may have also provoked the communications shortfalls discussed under
the milestone Local tax administration systems installed.
6. The Program Advisory Council (PAC) was never implemented: The organizational structure
for execution included an Advisory Council comprised of representatives of MRD, MOF,
Directorate of OTA, Ministry of Home Affairs, and the Ministry of Public Works. This
Council was to provide a consultative and problem solving forum to the PIU. While the
decree formally organizing the PAC was prepared this advisory unit was never
implemented.
7. The District management teams(DMT): Organized in a form similar to the PIU and MRD
team structures, the DMT is headed by the District Commissioner, with the following units
reporting to him: (i) the District Administrator; (ii) Financial and Planning; (iii) Civil
Technical; (iv) ICT; (v) Citizen Participation; (vi) Environment. The last five units
correspond to the components included in the program. The DMTs have played an active
role in the program’s execution, not only receiving the training included in the program, but
also applying that training in the execution of work. For instance, the Civil Technical units
were the recipients of training in the preparation of bidding documents and the supervision
of works. After this training they prepared (initially with the help of PIU) bidding
documents for works financed by the program, and later participated together with
PIU/MRD engineers in the supervision of contracted work.
One risk of this structure is the level of salaries in all areas, especially in technical and
administrative personnel. All district staff is paid by the MRD budget. Their level of salary
is determined by the civil service classification, where salaries are higher for university
graduates. The program trained in ICT, and administrative-financial non university
graduates district personnel that are performing well in their new posts, but that have
remained at their old salary classification. This has produced unhappiness and the risk of
losing trained personnel.
8. Level of autonomy and placement of the executing unit: Because of the identification with
an IDB program and the contractual regulations in the program, PIU had some level of
34
operating autonomy, but very little managerial power to have influence with the parallel
teams, and negligible or no political clout to influence in the approval of strategic laws
necessary to advance decentralization. Considering TMRD as a potential executing unit,
there are already signs that it could have less operating autonomy than PIU (based, for
example, on the way the TMRD capital investment projects are currently being selected).
Furthermore, it’s not likely that TMRD, as an executing unit, would have any more success
than the PIU in promoting pending decentralization reforms, judging from the difficulty
MRD has had in advancing the program’s strategic laws in the past 8 years.
When DLGPI was designed there were few proactive stakeholders and a more unified
central government political support to enhance and amend the enabling legislation for
decentralization. Times have changed apparently bringing more diffuse central political
support, but at the same time more proactive stakeholders: (i) the districts are active
participants and will probably evolve into a political force with a strong call for more steps
toward decentralization, and for more public works; (ii) the public is more informed on the
basics of decentralization, and citizens are willing to voice their concerns on local needs;
(iii) the ministries involved remain the same, but they are at present more informed about
the needs and solutions. For instance, there is a general awareness of the benefits of
increasing the generation of revenues at the local level and TAO/MOF is planning to
improve its systems to connect secure lines to the districts for tax reporting; (iv) there are
government agencies more actively involved, CLAD and NIMOS, for instance; (v) non-
profit agencies – NGOs - have been participating and their role is bound to grow in the
future, especially in Sipalawini due to issues related to traditional communities; and (vi) the
general assembly has to some degree been involved with the program in the last ten years.
Given this wealth of official and non- official stakeholders, apart from the necessary
technical qualifications, a careful analysis will have to be made on the leadership and
placement required for the future executing unit. From the point of view of leadership the
unit should be able to amalgamate and negotiate among different participants with their own
specific goals. From the point of view of placement, the unit will have to be located at a
place high enough to have the political muscle to contend with political opponents
2. Project inputs:
There are three types of input for project execution: human resources, equipment and
financial resources. PIU was adequately staffed for most of the project execution period.
An exception is that the task manager in the administration/financial component was let
go too early - in may 2014, given that preparatory work could have been done with his
help on the government-announced adoption of a new software for the financial systems.
35
Sporadically there have been shortages of consultants due to international experts’
reluctance to accept work in Suriname. Interestingly, this problem provided an incentive
for development of local consultants – at least in the financial system area. Human
resources shortages may be experienced in the future at the districts level, however, if
there is no review of salary classifications for personnel that have been trained by the
program. No staffing problems were detected in TMRD.
Office equipment was provided in a timely fashion at all levels. Of lately there has been
some inability to use the PIU transportation equipment for field inspections due to the
lack of petty cash to buy gasoline. This constraint - which is not budgetary, but caused
by bureaucratic delays - has also affected the availability of funds to pay for utilities and
for salaries for office routine maintenance personnel and for the office driver. Except for
these cases, there have not been problems with the contribution of counterpart funds. A
review of past years audited financial statements show that loan finances and counterpart
funds were used for the purposes established in the contract.
C. Design and relevance.
DLGPII is basically a continuation of DLGPI, thus the program design focus was to continue in
the new districts with the development of institutional capacity for fiscal management and for the
management of capital investment, and in the certified districts to implement basic capital
investment projects. The design also included the consolidation of the legal framework for
decentralization prepared in DLGPI. The components and the Results Matrix were jointly
prepared by the IDB team and its national counterpart. The level of achievements of the
milestone indicators, and the level of projected execution of the program budget, shows that the
program was in general well designed in terms of goals and costs needed to accomplish them.
Nonetheless, several factors were probably not foreseen: the most important is the change of
political support for the decentralization laws. The program legal indicators establish as a goal
only the drafting of the laws, probably under the assumption that political support will continue
and that the laws would be passed. But that political support did not continue with the result that
while the indicators (drafting of the laws) have been achieved, the actual benefits of the law were
never obtained in the absence of their approval. Future programs should consider indicators and
conditionalities based on the actual approval of laws.
Another factor not foreseen is the level of effort actually required to execute a larger investment
component. Assessment based on end of program opinions with professionals involved with the
component, show that the program could have benefitted, in terms of increased quality control
and less time in execution, from the addition of a second task manager to supervise 5 of the
districts. A final unforeseen factor was how to deal with remuneration for clerical staff trained in
36
the districts to perform technical or semi technical tasks. Leaving that staff at the old level of
remuneration creates discontent and the risk of losing trained personnel.
The program was and continues being relevant: Its activities and objectives are geared to comply
with a constitutional mandate, and they are in line with the country’s development plan 2012-
2016. From interview with a District Commissioner the program’s objectives are valid and the
program relevant in terms of the districts’ goals to increase self generated revenue and to
implement projects born out of local needs.
D. Monitoring and evaluation systems
The program has used two monitoring systems: operationally, the MS project software; and to
comply with IDB requirements, the Bank’s monitoring system. The MS project system divides a
program’s activity into any number of sub-activities required - establishing time, costs and
responsibilities for each. All PIU task manager are experts in the use of this tool and their work
is controlled by the managing director. Furthermore, the tool has been used to monitor the
advance of work at the district level. Results are evaluated periodically and adjustments are taken
as needed. The operational MS project is complemented by the program’s budgetary system
which organizes budget and expenses in accordance to physical components and activities. This
monitoring and evaluation systems has worked well.
The IDB system includes the PMR monitoring system, semi-annual and annual progress reports,
the annual work and procurements plans, the monitoring and evaluation visits for IDB country
and headquarters officials, the authorization and control procedures established for procurement
and disbursements, and finally the end of year audited program financial statements and auditors
review of the program’s system of internal control. The system is detailed and comprehensive - a
reason why it is rather surprising that MOFs unilateral action to dismantle TMOF apparently
slipped past undetected.
In regards to the PMR system it should be pointed out the PIU reports a great deal of time
required to comply with preparation of PMRs and semi-annual reports, especially in 2013 and
2014, as a result of changes in the system. Also, there is a need for borrower’s training on the
logic and concepts of milestones/activities, outputs, and outcomes. This is an area where
conceptual misunderstandings have occurred.
V. RISKS AND SUSTAINABILITY
Briefly stated, for the districts’ decentralization to be sustainable it has to be financially feasible,
because without funds the institutional capacity erodes and services decrease and eventually
disappear. The main risk attempting against the financial feasibility is legal and this legal risk is
37
closely tied to a political one. In addition there are institutional risks and financial risks to be
considered - to a great extent, the financial risks deriving again from the legal risks.
Legal risk: As pointed out before there are three laws that represent the backbone to a future
financial support and feasibility of the districts, namely: (i) The District Tax Law; (ii) the Law on
Financial Relations between the Central Government and the Districts; and (iii) the update of the
of Article IV of the FDIL law. Complements to these laws are the 10 agreements between the
districts and the GLIS. The approval of the first two laws has been pending since year 2008. The
update of the Article IV has been in Cabinet since 2012. The approval of the signing of the 10
agreements has been pending in MRD for several years. The lack of action toward the approval
of these laws is the serious risk that if not mitigated or controlled could very well affect the
decentralization. In this connection, consider as an example the case the district of Para that in
2013 had a planned budget (net of salaries) of SRD$ 17 million. In comparison, the MRD actual
budget allocation to Para for the same year was SRD$1.5 million. This allocation was arrived at
by MRD under the assumption that the budget needs for Para were around SRD 2 million and
that SRD$ 0.5 million of it was going to be financed by Para with its own generated resources.
The extremely large difference between planned and actual budgets in this one district is
presented here to point out that at the district level there is a need to increase the generation of
funds and that there is also a need for a more systematic transfer of national resources. This is
what the above three fundamental laws pursue.
Political risk: The fact that the laws have not been approved in several years brings an analytical
observer to the conclusion that the delay may not caused by an opposition to the laws, in and of
themselves, but by an opposition to the broader strategic goal of decentralization. In this
connection is worth quoting the conclusion reached by the author of the mid-term review of
DLGPII:
“The political risk is always a permanent risk, mostly if we consider (that) this program is very
political and very sensitive in terms of power structure of Suriname. Decentralization is viewed
by most politicians in the Central Government as giving up power and control. However the
Constitution of Suriname of 1987 stipulates decentralization as a model of governing and
organizing its political system defined as “Decentralized Monocratic State” and is recognized
that the Central Government by itself cannot bring development for the people. A common effort
of the Central Government, District authorities, Private Sector, and Civil Society is needed to
push forward Suriname into a modern, developed country.”9 It is hard not to agree with this
conclusion that also implicitly contains the action needed to control this risk, namely: a common
effort of all stakeholders to comply with the Constitution and to push Suriname into a modern,
developed country.
9 Claudio Ansorena PhD, Mid Term Evaluation Suriname DLGPII, July 2012.
38
Institutional risks are associated with institutional capacity risks at three levels: (i) the
institutional capacity to execute any new follow-up program contemplated after DLGPII ; (ii) the
central institutional capacity to continue supporting the districts – irrespective of a new program;
and (iii) the institutional capacity of the districts to sustain themselves.
Decentralization is a medium to long term effort and GOS may wish to continue with a new
program. The institutional risk related to execution of such a program is twofold. The first has to
do with the placement of the executing unit: if the executing unit is not placed at a level with
power enough to deal with political risk, history- as experienced thus far- may repeat itself. The
second is of operational capacity to carry out execution. There are some key functions and
systems necessary for effective execution, regardless of the type of project, namely: planning;
procurement; financial budgeting, accounting and reporting; monitoring; internal controls; and
management. An unusually well-honed capacity was created in all these functional areas through
the current executing mechanism of DLGPII. The risk is that the capacity and systems for these
functions may be lost and will have to be rebuilt after the termination of the current program.
As regards the question of central capacity to continue supporting the districts, in the short to
middle term, the districts will require support to maintain proficiency, especially in the areas of
financial administration, taxes, the WAN, and the implementation of the new financial software
mandated by Government. Without a thorough institutional analysis it is not possible to
determine fully whether TMRD has developed the required capacity for continuous support to
the districts, but observations based on short interviews indicate the need for strengthening on
planning and financial systems and administration and systems.
Finally, in terms of the capacity of the districts to sustain themselves, the program trained district
personnel in a number of important areas with satisfactory results. This personnel is being paid at
old levels because their posts have not reclassified - as they should have. Their salary levels,
especially for clerical personnel trained in the ITC and financial areas, is low. There is the risk
this personnel may leave, accentuating the already existing limitations of trained staff. The
program also trained district councils on citizen participation topics and to conduct hearings.
This training will have to be repeated periodically as the councils change with elections.
Financial risk: The central government covers 100% of the districts’ salaries and around 75% to
80% of actual non-salary current and capital expenditures. Furthermore, as noted above with the
example of the Distric of Pará, actual non-salary expenditures are only a fraction (around 12%
in the case of Para for year 2013), of the budgetary needs derived and approved by the district
councils. Thus, there is a significant financial risk of non-sustainability at the District level. As
mentioned above, there is an urgent need for self generated revenues by the districts and for a
systematic, predictable way of allocating central government transfers to the district. These
actions will go a long way toward mitigating the existing financial gaps and risks
39
VI. LESSONS LEARNED AND RECOMMENDATIONS
Political support and mitigating measures: Decentralization programs, like the one under review,
require legal reforms in an environment with a wealth of local and national stakeholders with
different perceptions on decentralization and its processes, and with different political views.
This makes the approval of the legal reforms risky. To mitigate this risk, the following measures
should be considered: (i) placing the executing unit at upper levels of political power to permit a
negotiated consensus between political equals; (ii) information campaigns directed to the public,
and to government officials on decentralization- its basis, benefits and needs. (PIU ran a very
limited information campaign in support of legal reforms, as part of its POP activity; it should
have been more ample.); (iii) consensus/lobbying efforts directed to gain support from ministers
and the General Assembly. (The activity included in the program for this consensus building was
unfortunately eliminated by MRD during the execution of the program.); (iv) milestones and
contractual clauses requiring the approval and implementation of laws- not only the drafting of
such laws; and (v) more support from IDB experts to assess achievements of key milestones or
contractual agreements- and require timely adjustments. Alternatively, the IDB may consider the
granting of different type of credits or programs in which disbursements are conditioned to legal
reforms.
Institutional analysis and organizational development: During project preparation there should
be an institutional analysis of the unit to be organizationally developed, so as to have a base line
and monitor its development progress. The program included the organizational development of
TMRD by way of transfer of capacities from PIU, while also participating as a parallel team in
the execution of the program. Unfortunately, there was no institutional analysis of TMRD during
program preparation, so as to know its institutional capacity, its needs and its potential. As a
result, TMRD has developed into a unit with apparently a double function as parallel execution
unit and central support to the districts. However at the present time it is unknown what has been
the degree of organizational development accomplished and what are MRD true capacities,
needs and potential.
Strong direction and coordination: Clear supervisory directions and objectives should be defined
for independent units sharing execution responsibility, while at the same time performing
dissimilar roles. PIU and MRD had the same supervisor and shared responsibility for some
execution activities, but the latter had a role of beneficiary of the know-how to be transferred
from the former. To promote coordination, and avoid subjective interpretations among members
of the units, clear directions should have emanated from the PS in this regard from the inception
of the program.
40
Continuity of executing unit: Units with continuous strong leadership create cohesive teams with
members highly identified with the accomplishment of the program’s goals. In spite of many
problems and delays suffered, PIU was able to maintain a good to excellent level of performance
thanks to continuity of a strong, capable leadership.
Institutional strengthening in a future program: The following institutional strengthening should
be included in a future DLGP program:
(k) Implementation of the GOS newly mandated “Free Balance” financial software at the
districts’ level. This task to include the preparation of system documentation, users’
manuals and training.
(l) Training on the new decentralization and financial laws, once they have been approved.
(m) Development and implementation of a tax accounting system for the districts.
(n) The prompt signing of the 10 agreements of the districts with GLIS and the
implementation of a system to transfer data from GLIS to the districts tax accounting
system.
(o) A subcomponent for dissemination of information on decentralization and for the
consensus building with ministers and the general assembly.
(p) A joint effort with OTA to resolve the connectivity issues between this office and the
financial district offices.
(q) Development of an Internal Audit Office (IAO) for the districts. The MRD office of
Internal Control could be the basis for organizing the IAO. However the Internal Control
office very possibly would have to be reorganized and strengthened.
(r) Development of a salary classification system for District personnel.
(s) A subcomponent to finance as needed expert support to the legislative reform process-
including technical promotion and negotiation with legislative staff, as well as mounting
public communication and education campaigns.
(t) Certification processes must be thoroughly spelled out in terms of procedures and
responsibilities- and must be accompanied by the systems needed to measure benchmarks
required as part of the certification.