Transcript of Division of Scope - EBOP A
-
8/3/2019 Division of Scope - EBOP A
1/2
PT Priamanaya EnergiKEBAN AGUNG
fiw 1 / 201/11/1179755627.doc
no.scope
turn-key based1 EBOP 1 Contractor2 EBOP 2 Contractor
remarks
1 drawings,in addition to the documents as per GeneralTechnical Specification GTS-EBOP-012011 Rev. 0:
1.1 single line diagram, overall for 150 kV, 13,8 kV 1
1.2 single line diagram, overall for 6,6 kV, 400 V and less 2
1.3 equipment foundations including foundation loads 1
2 earthing system2.1 basic grid for the entire project area 1
2.2 connection of the respective equipment with the basicgrid
1 2
3 IPBConnection to the generator terminals, the excitationtransformers, the unit transformers and the generatortransformers
1 supervised by thegenerator respectivelythe generatortransformer supplier
4 cables
4.1 cables,for the inter connection within the respective scope
1 2
4.2 excitation cables
connection to the excitation panels and the generatorslip ring terminals
1 supervised by the
generator respectivelythe generatortransformer supplier
4.3 150 kV cable system 2
4.3.1 cable termination 2
4.3.2 connecting the cable with GIS and the generatortransformer
2 supervised by the GISrespectively thegenerator transformersupplier
4.4 conductor,for the connection of the 150 kV cable system withthe next gantry
2
5 DCS ;
Supply:HMI, Large Screen, Control Station / IO & RIOCubicle, Historian & Performance calculation station,CMMS server and module, Printer, Connectionbetween supplied equipment.
Work :Engineering , installation, commissioning, baby sitting
Out of scope :- DC power and UPS- Grounding for panels- Cable tray / raise floor- Connection to field instrument- CMMS user PC and network
1 DCS vendor must
lead thecoordination duringengineering designphase. HBED willresponsible for finaldesign.
Installation /erection work canbe done by S4EPCor EBOP 1 turnkey.
6 clarification with PLN:
meetings with PLN together with PT PriamanayaEnergi (PE) at the beginning of the design stage tooptimize the implementation of the systems (i.e. SAS,control & protection, metering and communication)into the existing PLN systems.
The Contractor informs the agenda to PE two weeksin advance of such required meeting with PLN
1
7 Site
7.1 Site management 1 2
7.2 Site facilities (i. e. accommodations, office, warehouse, vehicles, crane, tools, electricity, telephone,internet, water, etc.)
1 2
7.3 health safety and environment management 1 2
-
8/3/2019 Division of Scope - EBOP A
2/2
PT Priamanaya EnergiKEBAN AGUNG
DIVISION OF SCOPE EBOP including Lahat SS extension
fiw 2 / 201/11/1179755627.doc