District of Columbiastip.wemovedc.org/wp-content/uploads/FY2018-2022-STIP-Draft-Proj… · 14th...
Transcript of District of Columbiastip.wemovedc.org/wp-content/uploads/FY2018-2022-STIP-Draft-Proj… · 14th...
District of Columbia Fiscal Year 2018‐2022
Statewide Transportation Improvement Program
Draft Project ListSeptember 2017
Draft FY 2018-2022 Project List Ward 1 Projects
Planning/Study Design Construction Other
22
Florida Ave NW, 9th St to Sherman AveRemoval of deteriorated base and pavement,repairing the sub-base, replacing or reconstructingpavement and base within the roadway area andresetting or reconstructing curbs and sidewalks.Additional work includes the installation ofwheelchair ramps, bicycle facilities, safety featuresand landscaping improvements.
Streetscape &Public Space
FY 19 $ 6,500,000
66
Mount Pleasant Street LightingUpgrade Lighting upgrade with complete systemincluding manhole, conduit LED lights, and HistoricWashington Globe pole/fixture
Stormwater &Other
InfrastructureFY 18 $ 600,000
Project PhaseID
Project Name and DescriptionProject Category
Proposed FY18-22Cost
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
1
Draft FY 2018-2022 Project List Ward 2 Projects
Planning/Study Design Construction Other
13
Reconstruction of Pennsylvania Ave NW from 17thSt NW to Washington CircleDesign for streetscape of Pennsylvania Avenue NW,including multimodal transportation options.
MajorMultimodal
FY 19 $ 1,500,000
16
Theodore Roosevelt Memorial BridgeRehabilitation of the Theodore Roosevelt MemorialBridge Main Spans and Ramps, includingpedestrian/bicyclist safety improvements; sidewalkwidening; connection for downstream sidewalk toVirginia; modifications to zipper lane; and bridgelighting
MajorMultimodal
FY 18-20 $ 4,000,000
17I-395 from I-695/I-295Project description pending
MajorMultimodal
$ 2,800,000
24Reconstruction of Massachusetts Avenue NWRoadway rehabilitation and streetscape in Kalorama
Streetscape &Public Space
FY 19 $ 9,000,000
30Louisiana Avenue Protected Bike Lanes ProjectFinal design of protected bicycle lanes alongLouisiana Avenue
Bicycle &Pedestrian
FY 19 $ 1,000,000
38
14th Street SW Ramp BridgesOn northbound 14th Street Bridge, the approachbridges to be rehabilitated are over Maine Avenue,over the Outlet Channel, and over Haines Point Park
Bridge & Tunnel FY 18 FY 20-22 $ 30,000,000
45Rehabilitation of Whitehurst Freeway BridgeRehabilitation of Whitehurst Freeway Bridge
Bridge & Tunnel FY 19 $ 1,500,000
44
Rehabilitation of I-395 HOV Bridge over PotomacRiverRepair extensive pier cracking, superstructure, andsubstructure rehabilitation
Bridge & Tunnel FY 18 FY 20 $ 54,500,000
ID Project Name and Description Project CategoryProject Phase Proposed FY18-22
Cost
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
2
Draft FY 2018-2022 Project List Ward 3 Projects
Planning/Study Design Construction Other
20
Cleveland Park StudyImplementation of Cleveland Park studyrecommendations including Connecticut Avenueaccess lane and neighborhood parking supply,streetscape improvements and intersectionreconfiguration at Porter/Quebec/Connecticut AveNW
Streetscape &Public Space
FY 19 $ 2,415,000
24Reconstruction of Massachusetts Avenue NW(Kalorama)Roadway rehabilitation and streetscape in Kalorama
Streetscape &Public Space
FY 19 $ 9,000,000
33
Rock Creek Trail RehabilitationSelected widening, resurfacing, new connections, anew bridge south of the Zoo tunnel, and retainingwall repair on Piney Branch
Bicycle &Pedestrian
FY 18 $ 10,050,000
ID Project Name and Description Project CategoryProject Phase Proposed FY18-22
Cost
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
3
Draft FY 2018-2022 Project List Ward 4 Projects
Planning/Study Design Construction Other
9
Oregon Avenue Roadway ImprovementInstallation of new sidewalk on west side, new curband gutter, new bridge over Pinehurst Run, andPepco undergrounding
MajorMultimodal
FY 18-20 $ 21,000,000
18Blair / Cedar / 4th Street NWImprovement at Blair Road NW, Cedar Street NW,and 4th Street NW intersection
Streetscape &Public Space
FY 18 $ 2,700,000
42
Rehabilitation of 16th St Bridge over Piney BranchRd NWDeck repair and utility replacement to preserve theintegrity and extend the life of the masonry andreinforced concrete arch superstructure.Completion of the interior safety walkways andrailings
Bridge & Tunnel FY 20 $ 4,800,000
ID Project Name and Description Project CategoryProject Phase Proposed FY18-22
Cost
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
4
Draft FY 2018-2022 Project List Ward 5 Projects
Planning/Study Design Construction Other
28
Arboretum Bridge and TrailPreliminary Design and Environmental Review for aconnection of the Arboretum Bridge to the publicroad network (Maryland Ave)
Bicycle &Pedestrian
FY 19 $ 3,500,000
70
Construction for Upgrade and Repair to Weigh-in-Motion (WIM) SystemsPerform upgrades and repairs to DC's three Weigh-in-Motion (WIM) stations at (1) New York AveEB/WB, (2) I-295 NB, and (3) I-295 SB
AssetManagement
FY 18 $ 2,000,000
84
WIM Maintenance ContractProvide continued operations, maintenance, andrepairs for the Weigh-in-Motion (WIM) systems on I-295 and New York Ave: system calibration, systemvalidation and data collection, preventativemaintenance services, maintenance data andservice reporting, training, and emergency repairs
AssetManagement
FY 18-22 $ 1,050,000
118
Florida Ave StreetscapeStreetscape improvements to include sidewalkwidening, lighting, low-impact developmentfeatures, street trees, bike lanes, and curbextensions between New York Avenue and HStreet/Benning Road
Streetscape &Public Space
FY 20 $ 17,734,876
ID Project Name and Description Project CategoryProject Phase Proposed FY18-22
Cost
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
5
Draft FY 2018-2022 Project List Ward 6 Projects
Planning/Study Design Construction Other
1
Middle Anacostia Crossing - GARVEE BondRepaymentLong-term improvements for 11th Street Bridge.Grant Appreciate Revenue Vehicle (GARVEE) bonddebt service.
MajorMultimodal
FY 18-22 $ 70,500,000
2
New Jersey Ave. Mass. Ave. to N Street SafetyProjectSafety improvement project to facilitate pedestrianand motorists flows. A portion of New JerseyAvenue will be converted into two-way traffic.
MajorMultimodal
FY 18 $ 15,500,000
3
S. Capitol St - New Frederick Douglass MemorialBridgeRedevelopment of the South Capitol Street corridoris a part of the Anacostia Waterfront Initiative.Concept plans for the replacement of the FrederickDouglass Memorial Bridge are under developmentas part of the EIS currently being prepared.
MajorMultimodal
FY 18 $ 12,300,000
4
S. Capitol St - GARVEE Bond RepaymentRedevelopment of the South Capitol Street corridoris a part of the Anacostia Waterfront Initiative.Grant Appreciate Revenue Vehicle (GARVEE) bonddebt service.
MajorMultimodal
FY 18-22 $ 89,200,000
7
I-695 Eastbound D4 Ramp DesignAdministration, design, and construction for closureof several items remaining from the construction ofthe 11th Street Corridor Project
MajorMultimodal
FY 19 $ 2,000,000
ID Project Name and Description Project CategoryProject Phase Proposed FY18-22
Cost
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
6
Draft FY 2018-2022 Project List Ward 6 Projects
Planning/Study Design Construction OtherID Project Name and Description Project Category
Project Phase Proposed FY18-22Cost
12
Pennsylvania Avenue Streetlight UpgradeIncludes but not limited to installation of new lightpoles, light fixtures, wheel chair ramps andunderground infrastructures including conduits,cables, manholes, excavation and backfill,pavement restoration from 2nd Street SE to BarneyCircle SE
MajorMultimodal
FY 18-20 $ 14,229,485
17I-395 from I-695/I-295Project description pending
MajorMultimodal
$ 2,800,000
19C Street NE ImplementationTraffic calming project to slow traffic in the corridorby reducing at least one vehicle lane of traffic
Streetscape &Public Space
FY 18 FY 19 $ 15,000,000
23Maryland Avenue NE Pedestrian Priority CorridorDesign and construction of pedestrian safetyimprovements based on completed study.
Streetscape &Public Space
FY 18 $ 19,300,000
27
Pennsylvania/Potomac CirclePedestrian safety and vehicular movementimprovements to existing traffic circle at theintersection
Streetscape &Public Space
FY 18 $ 1,400,000
30Louisiana Avenue Protected Bike LanesFinal design of protected bicycle lanes alongLouisiana Avenue.
Bicycle &Pedestrian
FY 19 $ 1,000,000
47Southwest Freeway Bridge over S. Capitol StreetConstruction of Southwest Freeway Bridge overSouth Capitol Street
Bridge & Tunnel FY 18 $ 2,500,000
118
Florida Ave StreetscapeStreetscape improvements to include sidewalkwidening, lighting, low-impact developmentfeatures, street trees, bike lanes, and curbextensions between New York Avenue and HStreet/Benning Road
Streetscape &Public Space
FY 20 $ 17,734,876
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
7
Draft FY 2018-2022 Project List Ward 7 Projects
Planning/Study Design Construction Other
6
Benning Road Reconstruction and StreetcarExtension1.95-mile surface fixed guideway transit line thatincludes electrically powered streetcar vehiclesoperating along tracks located within the existingstreet and travel lanes. The National EnvironmentalPolicy Act (NEPA) study will address potentialimpacts of the project, as well as preliminaryengineering (conceptual) for the line.
MajorMultimodal
FY 18-19 $ 7,000,000
11
Pennsylvania Ave SE Phase 2: PA Ave SE fromSousa Bridge to 209' west of 27th St. SEPrepare an Environmental Assessment for FHWA &NPS for the Pennsylvania Ave SE and Minnesota AveSE intersection and the portion on Penn Avenuebetween 27th Street and the Sousa Bridge.
MajorMultimodal
FY 19 $ 9,500,000
21E. Capitol Street Corridor Mobility & Safety PlanDesign and construction of pedestrian safety andtraffic operations improvements
Streetscape &Public Space
FY 18-19 $ 1,900,000
25
Southbound Kenilworth Ave NEReconstruction of southbound Kenilworth Avenuefrom the East Capitol Street Ramp to the CSxRailroad Bridge Overpass. The reconstruction willinclude removal of deteriorated base andpavement, repairing the sub-base, replacing orreconstructing pavement and base within theroadway area and resetting or reconstructing curbsand sidewalks. Additional work includes theinstallation of wheelchair ramps, bicycle facilities,safety features and landscaping improvements.
Streetscape &Public Space
FY 18 $ 8,000,000
ID Project Name and Description Project CategoryProject Phase Proposed FY18-22
Cost
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
8
Draft FY 2018-2022 Project List Ward 7 Projects
Planning/Study Design Construction OtherID Project Name and Description Project Category
Project Phase Proposed FY18-22Cost
32
Pedestrian Bridges over Kenilworth AvenueReplacement of three pedestrian bridges overKenilworth Ave at Lane Pl, Nash St, and Douglas Stto enhance pedestrian mobility and safety byimproving the bridge structure condition and ADAramps to the current standards and requirements
Bicycle &Pedestrian
FY 18-19 $ 14,000,000
39
Rehabilitation of Benning Road Bridge overKenilworth AvenueWidening and safety improvements of existingeastbound and westbound Benning Road Bridgesover Kenilworth Avenue NE. New bridge structureswill have safer pedestrian access and bike path,including streetcar tracks.
Bridge & Tunnel FY 21-22 $ 70,000,000
58
Safety and Geometric Improvements of I-295/DC295Safety improvements and upgrades to SB entranceand NB left exit ramps at Benning Road; shoulderwidening on DC 295 southbound between BenningRoad and East Capitol Street; safety improvementsand upgrades to meet current design standards atsouthbound exit ramps to River Terrace and E.Capitol Street and at the westbound PennsylvaniaAve entrance and exit ramps; improvements tosignage, pavement markings, and roadway lighting(LED lighting) between Pennsylvania Ave andBenning Road; and improvements to guardrail andmedian barriers to meet current design standards
Safety FY 18 $ 9,500,000
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
9
Draft FY 2018-2022 Project List Ward 7 Projects
Planning/Study Design Construction OtherID Project Name and Description Project Category
Project Phase Proposed FY18-22Cost
64
East Capitol Streetlight UpgradeUpgrade the outdated streetlight system in thiscorridor to provide better illumination on sidewalksand streets
Stormwater &Other
InfrastructureFY 18-20 7,389,713$
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
10
Draft FY 2018-2022 Project List Ward 8 Projects
Planning/Study Design Construction Other
1
Middle Anacostia Crossing - GARVEE BondRepaymentLong-term improvements for 11th Street Bridge.Grant Appreciate Revenue Vehicle (GARVEE) bonddebt service.
MajorMultimodal
FY 18-22 $ 70,500,000
3
South Capitol St. - NEW Frederick DouglassMemorial BridgeRedevelopment of the South Capitol Street corridoris a part of the Anacostia Waterfront Initiative.Concept plans for the replacement of the FrederickDiuglass Memorial Bridge are under developmentas part of the EIS currently being prepared for thecorridor.
MajorMultimodal
FY 18 $ 12,300,000
4
S. Capitol St - GARVEE Debt ServiceRedevelopment of the South Capitol Street corridoris a part of the Anacostia Waterfront Initiative.Grant Appreciate Revenue Vehicle (GARVEE) bonddebt service.
MajorMultimodal
FY 18-22 $ 89,200,000
15
Southern Ave Roadway ImprovementsImprove the livability of the Southern Avenuecorridor from South Capitol Street SE to 23rd StreetSE
MajorMultimodal
FY 19-20 $ 11,500,000
34
S. Capitol Street TrailDesign and construct a paved bicycle andpedestrian trail along South Capitol Street, based onthe 2010 Concept Plan.
Bicycle &Pedestrian
FY 19 $ 11,000,000
ID Project Name and Description Project CategoryProject Phase Proposed FY18-22
Cost
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
11
Draft FY 2018-2022 Project List Ward 8 Projects
Planning/Study Design Construction OtherID Project Name and Description Project Category
Project Phase Proposed FY18-22Cost
58
Safety and Geometric Improvements of I-295/DC295Safety improvements and upgrades to SB entranceand NB left exit ramps at Benning Road; shoulderwidening on DC 295 southbound between BenningRoad and East Capitol Street; safety improvementsand upgrades to meet current design standards atsouthbound exit ramps to River Terrace and E.Capitol Street and at the westbound PennsylvaniaAve entrance and exit ramps; improvements tosignage, pavement markings, and roadway lighting(LED lighting) between Pennsylvania Ave andBenning Road; and improvements to guardrail andmedian barriers to meet current design standards
Safety FY 18 $ 9,500,000
70
Upgrade and Repair to Weigh-in-Motion (WIM)SystemsPerform upgrades and repairs to DC's three Weigh-in-Motion (WIM) stations at (1) New York AveEB/WB, (2) I-295 NB, and (3) I-295 SB
AssetManagement
FY 18 $ 2,000,000
84
WIM Maintenance ContractProvide continued operations, maintenance, andrepairs for the Weigh-in-Motion (WIM) systems on I-295 and New York Ave: system calibration, systemvalidation and data collection, preventativemaintenance services, maintenance data andservice reporting, training, and emergency repairs
AssetManagement
FY 18-22 $ 1,050,000
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
12
Draft FY 2018-2022 Project List Districtwide Projects
Planning/Study Design Construction Other
5
AWI Program ManagementConsultant services to supplement the NEPA processand implement design and construction of theAnacostia Waterfront Initiative (AWI) corridors. Workincludes surveys; geotechnical and environmentalinvestigation and testing preliminary; roadway andbridge design and CE services during construction.
Major Multimodal FY 18-22 $ 17,000,000
26
Urban Forestry ProgramCitywide tree asset management to include treepruning, removal & planting.
Streetscape & PublicSpace
FY 18-22 2,500,000$
29
Capital Bikeshare (CaBi)Citywide Capital Bikeshare system expansion
Bicycle & Pedestrian FY 18-22 4,000,000$
31
National Recreation Trails - MaintenanceRecreational Trails Maintenance grants provideongoing trail maintenance throughout the city
Bicycle & Pedestrian FY 18-22 1,500,000$
ID Project Name and Description Project CategoryProject Phase
Proposed FY18-22Cost
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
13
Draft FY 2018-2022 Project List Districtwide Projects
Planning/Study Design Construction OtherID Project Name and Description Project Category
Project Phase Proposed FY18-22
Cost
35
Asset Preservation of Tunnels in the District ofColumbia - NHPPProvides technical support and supportive servicesthat enables sustained preventive maintenance,rehabilitation and preservation of all tunnel assets inDDOT inventory system
Bridge & Tunnel FY 18-22 46,255,000$
36
Federal Aid Preventive Maintenance and EmergencyRepairs on Highway Structures-NHDesign for Preventive Maintenance and EmergencyRepairs on Bridges and Highway Structures Bridge & Tunnel FY 18-22 25,990,000$
37
Federal Aid Preventive Maintenance and EmergencyRepairs on Highway Structures-STPPerformance of preventive maintenance andemergency repairs on highway structures (bridges,overpasses, underpasses, freeways, ramps, culverts,viaducts, retaining walls, etc.) under the ownership ofthe District of Columbia.
Bridge & Tunnel FY 18-22 6,560,000$
48
Pavement Skid TestingYearly citywide pavement skid testing. Programincludes field testing at locations where pavementsurface may be contributing factor to crash history. Safety FY 18-22 FY 18-22 412,500$
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
14
Draft FY 2018-2022 Project List Districtwide Projects
Planning/Study Design Construction OtherID Project Name and Description Project Category
Project Phase Proposed FY18-22
Cost
49
Traffic Accident Reporting and Analysis System(TARAS)Update and maintenance of existing crash database
Safety FY 18-22 400,000$
50
Traffic Data Collection and Analysis Services (SPR)Yearly citywide traffic data collection. Project includescollection, comprehensive review and QA/QC, andpreparation of technical reports with statisticalsummary of traffic data.
Safety FY 18-22 875,000$
51
Traffic Safety Data Center at Howard UniversityYearly citywide support for Howard University TrafficSafety & Data Center (HUTRC). Program includesevaluation of traffic calming applications and othersafety studies (changes to traffic control, sightdistance, etc.).
Safety FY 18-22 3,750,000$
52
Traffic Safety Design - HSIP ProgramYearly citywide Highway Safety Improvement Program.Program includes study of crash history/patters andpreliminary design for improvements to mitigatesafety concerns.
Safety FY 18-22 FY 18-22 8,250,000$
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
15
Draft FY 2018-2022 Project List Districtwide Projects
Planning/Study Design Construction OtherID Project Name and Description Project Category
Project Phase Proposed FY18-22
Cost
53
Traffic Safety Engineering Support ServicesYearly traffic safety engineering support contract. Thisprogram provides analysis and review support for theDDOT Traffic Operations & Safety Team. Safety FY 18-22 FY 18-22 8,250,000$
54
ADA ComplianceWork consists of citywide rehabilitation of sidewalksincluding construction management consultant,assessment, design, and construction to upgrade curband gutter, wheelchair ramps, sidewalks, drivewaysand alley entrances at various locations in the Districtof Columbia to comply with ADA requirements.
Safety FY 18-21 10,000,000$
55
Citywide IDIQ Traffic Safety ConstructionIncludes small to medium scale traffic engineeringimprovements on roadways/intersections to improvemulti-modal traffic safety. These locations aregenerated from the Highway Safety ImprovementProgram (HSIP), Vision Zero, Livability Studies, andother transportation studies
Safety FY 18-22 17,500,000$
56
Citywide Traffic Engineering DesignTraffic Engineering Analysis and Design of small tomedium scale improvements on roadways andintersections with safety issues. These locations aregenerated from the Highway Safety ImprovementProgram (HSIP), Vision Zero, Livability Studies, andother transportation studies
Safety FY 18-22 8,000,000$
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
16
Draft FY 2018-2022 Project List Districtwide Projects
Planning/Study Design Construction OtherID Project Name and Description Project Category
Project Phase Proposed FY18-22
Cost
57
Citywide Road Safety Audit ProgramYearly citywide roadway safety audit program
Safety FY 18-22 7,500,000$
59
Statewide Transportation Alternatives Program- SafeRoutes to SchoolTo enable and encourage children, including thosewith disabilities, to walk and bicycle to school, to makewalking and bicycling to school safe and moreappealing, and to facilitate the planning, developmentand implementation of projects that will improvesafety, and reduce traffic, fuel consumption, and airpollution in the vicinity of schools
Safety FY 18-22 5,755,000$
60
Traffic Sign Inventory UpgradeTraffic sign inventory upgrades
Safety FY 18 FY 18-22 800,000$
61
Construction of Fiber Communication Networks onCorridorsConstruct fiber communication networks on corridorsand connect to the Traffic Management Center Stormwater & Other
InfrastructureFY 18-20 5,000,000$
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
17
Draft FY 2018-2022 Project List Districtwide Projects
Planning/Study Design Construction OtherID Project Name and Description Project Category
Project Phase Proposed FY18-22
Cost
62
Citywide Streetlight LED ConversionConversion to LED streetlights
Stormwater & OtherInfrastructure
FY 18-19 8,053,807$
63
Culvert Rehabilitation and ReplacementConduct the rehabilitation and repair of culverts in theDistrict based on biannual inspections tomaintain/improve hydraulic capacity and structuralintegrity
Stormwater & OtherInfrastructure
FY 18-22 12,850,000$
65
ITS General SupportConsultant to provide general support for design andimplementation of ITS projects, including deliverablereviews/evaluation, construction managementsupport, system verification and validation, productstudies and research, and inventory
Stormwater & OtherInfrastructure
FY 18-22 1,000,000$
67
Citywide Traffic Signal Construction Contract(National Highway System Routes)Project to install citywide new Traffic Signals, HAWKs,RRFBS and modify/rehabilitate existing traffic signalsusing NHPP funds
Asset Management FY 18-22 7,675,000$
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
18
Draft FY 2018-2022 Project List Districtwide Projects
Planning/Study Design Construction OtherID Project Name and Description Project Category
Project Phase Proposed FY18-22
Cost
68
Citywide Traffic Signal Construction Contract (STPRoutes)Construct citywide new traffic signals, HAWKs, RRFBsand modify existing traffic signals with SurfaceTransportation Program (STP) funds
Asset Management FY 18-22 14,000,000$
69
Citywide Thermoplastic Pavements MarkingsInstallation of missing, faded or new thermoplasticmarkings on Federal Highways
Asset Management FY 18-22 9,700,000$
71
Citywide Streetlight ConstructionCitywide streetlight construction to include installationof lights based on request for lighting upgrades
Asset Management FY 18-22 FY 18-22 15,000,000$
72
Emergency Transportation ProjectsResponse to emergencies or other unforeseen eventsthat are not budgeted or planned
Asset Management FY 18-22 125,000$
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
19
Draft FY 2018-2022 Project List Districtwide Projects
Planning/Study Design Construction OtherID Project Name and Description Project Category
Project Phase Proposed FY18-22
Cost
73
Federal Aid Pavement RestorationMilling and resurfacing, curb and gutter and sidewalkrepair, upgrading on wheelchair ramps and pedestrianfacilities to meet ADA Compliance on Federal roads Asset Management FY 18-22 45,432,504$
74
NHS - Federal Aid Pavement Restoration - NHPPStreetsPavement rehabilitation and restoration for NationalHighway Performance Program (NHPP)-designatedstreets
Asset Management FY 19 FY 18-22 47,650,000$
75
On-Call Subsurface Pavement Investigation,Engineering Program SupportSubsurface investigation and engineering, pavementmanagement and design services including analysisand support for Asset Management Program
Asset Management FY 18-22 3,403,225$
76
Replacing and Upgrading Guardrail and ImpactAttenuatorsRepairing, replacing and upgrading safetyappurtenances that have been damaged by errantvehicles. Work also includes constructing guiderailand attenuators at new locations and removing unitsin locations where they are no longer needed
Asset Management FY 18-22 13,061,500$
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
20
Draft FY 2018-2022 Project List Districtwide Projects
Planning/Study Design Construction OtherID Project Name and Description Project Category
Project Phase Proposed FY18-22
Cost
77
Roadway Pavement Condition AssessmentCitywide pavement condition assessment of thestreets within the District
Asset Management FY 18-22 5,000,000$
78
Traffic Signal Consultant DesignDesign of new traffic signals, HAWK, RRFB and othertraffic control devices to improve multimodal trafficoperations in the City Asset Management FY 18-22 2,500,000$
79
Traffic Signal LED Replacement-NHPPReplace traffic and pedestrian signal LED modules atall signalized intersections on the surfacetransportation systems Asset Management FY 19-22 3,060,000$
80
Traffic Signal LED Replacement-STPReplace traffic and pedestrian signal LED modules atall signalized intersections on the surfacetransportation systems Asset Management FY 18-22 5,310,000$
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
21
Draft FY 2018-2022 Project List Districtwide Projects
Planning/Study Design Construction OtherID Project Name and Description Project Category
Project Phase Proposed FY18-22
Cost
81
Traffic Signal Maintenance - NHPPProvide effective and efficient maintenance servicesfor the traffic signal systems throughout the District ofColumbia Asset Management FY 18-22 10,650,000$
82
Traffic Signal Maintenance - STPProvide maintenance services for the traffic signalsystems throughout the District of Columbia
Asset Management FY 18-22 23,100,000$
83
Upgrade and Replacement of Overhead FreewaySignsRepair and replacement of damagedoverhead/oversized signage, primarily located alongInterstate system. This project will facilitatereplacement of damaged signs that are too large tofabricate and install in-house
Asset Management FY 18-22 3,000,000$
85
Traffic Signal OptimizationDevelop optimized traffic signal timing plans for theentire signal system in a five-year cycle to reduceCitywide congestion, and optimize pedestrian andtransit flows
Asset Management FY 18-22 8,000,000$
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
22
Draft FY 2018-2022 Project List Districtwide Projects
Planning/Study Design Construction OtherID Project Name and Description Project Category
Project Phase Proposed FY18-22
Cost
86
Traffic Signal Systems AnalysisOngoing program which performs various traffic signalanalyses including determination of appropriate levelof traffic control (traffic signal, HAWK, RRFB, Flashers),modification to existing signalized intersections, andsmall to medium scale corridor analysis
Asset Management FY 18-22 3,000,000$
87
Upgrade and Replacement of Overhead FreewaySignsPlacing mile markers along interstates (on I-295, I-395,I-695, and I-66) and updating existing exit numbers onground-mounted and overhead signs to comply withmile-marker designations
Asset Management FY 18 1,000,000$
89
Streetlight Asset ManagementStreetlight asset management
Asset Management FY 18-22 53,991,415$
90
AASHTOWARE PaymentProvides funds to support the Bridge ManagementProgram and to pay the annual Points license fee Planning,
Programming, Fiscal,& Administrative
FY 18-22 1,535,600$
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
23
Draft FY 2018-2022 Project List Districtwide Projects
Planning/Study Design Construction OtherID Project Name and Description Project Category
Project Phase Proposed FY18-22
Cost
91
Asset Inventory & ADA ComplianceIncludes inventorying assets in the public right of way,collection of the required data attributes to update theADA database and determine the ADA compliance andAccessibility of Public Facilities
Planning,Programming, Fiscal,
& AdministrativeFY 18-20 2,200,000$
92
Audit and ComplianceTo ensure audit and compliance for Davis Baconstaffing, training and software Planning,
Programming, Fiscal,& Administrative
FY 18-22 5,000,000$
93
Bridge Management ProgramBridge management program
Planning,Programming, Fiscal,
& AdministrativeFY 18-22 1,625,000$
94
Citywide Federal Aid Consultant Bridge InspectionContractWork under this contract consists of performingdetailed condition inspections and evaluations of allhighway and pedestrian bridges, and tunnels andunderpasses, under the ownership of the District ofColumbia and safety inspections of railroad ownedbridges crossing District streets
Planning,Programming, Fiscal,
& AdministrativeFY 20 7,900,000$
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
24
Draft FY 2018-2022 Project List Districtwide Projects
Planning/Study Design Construction OtherID Project Name and Description Project Category
Project Phase Proposed FY18-22
Cost
95
Citywide Open End Bridge DesignProvides engineering design services for the AssetManagement Division to support the preventivemaintenance program. Typical services includeinvestigation of structural deficiencies encounteredduring bridge inspections and observation, definingthe problems and proposing and designing solutionssuch as temporary shoring and supports and repairand retrofit details for deficient structural elements.
Planning,Programming, Fiscal,
& AdministrativeFY 19-22 3,250,000$
96
Civil Rights / EEO compliance Monitoring ProgramCivil Rights and equal employment opportunity (EEO)compliance and monitoring Planning,
Programming, Fiscal,& Administrative
FY 18-22 3,070,000$
97
Culvert InspectionInspection of the District Department ofTransportation’s culvert inventory. Work under thiscontract will consist of performing detailed inspectionsand evaluations of all applicable DDOT culverts,considering both the structural evaluation andhydraulic capacity analysis.
Planning,Programming, Fiscal,
& AdministrativeFY 18-22 2,500,000$
98
DBE Supportive Services/OJT Supportive ServicesGrant funding for Disadvantaged Business Enterprise(DBE) and On-the-Job Training (OJT) efforts Planning,
Programming, Fiscal,& Administrative
FY 18-22 500,000$
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
25
Draft FY 2018-2022 Project List Districtwide Projects
Planning/Study Design Construction OtherID Project Name and Description Project Category
Project Phase Proposed FY18-22
Cost
99
Disadvantaged Business Enterprise OnlineCertification SystemThis system is being developed as an extension of theDistrict Transportation Access Portal (DTAP), similar tothe Small Business Enterprise Application program,and will serve as a document management repositoryfor the Agency, in particular the Office of Civil Rights
Planning,Programming, Fiscal,
& AdministrativeFY 18 150,000$
100
District TDM (goDCgo)The District's transportation demand management(TDM) program promotes sustainable transportationoptions and works with employers, hotels, andresidential properties to decrease single occupancyvehicle (SOV) use
Planning,Programming, Fiscal,
& AdministrativeFY 18-22 15,900,000$
101
Environmental Management System (EMS)The EMS Program ensures DDOT’s compliance withNEPA and Section 106 per regulation and theProgrammatic Agreements overseeing these approvals
Planning,Programming, Fiscal,
& AdministrativeFY 18-22 2,000,000$
102
Infrastructure Information Technology SupportServicesIT infrastructure project for developers, DBA, hardwareand software licenses
Planning,Programming, Fiscal,
& AdministrativeFY 18-22 5,100,000$
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
26
Draft FY 2018-2022 Project List Districtwide Projects
Planning/Study Design Construction OtherID Project Name and Description Project Category
Project Phase Proposed FY18-22
Cost
103
Metropolitan Area Transportation OperationsCoordination (MATOC)Ongoing project obligation to fund the MATOC, aregional program intended to enhance situationalawareness and response to transportation incidentswhose impacts cross jurisdictional boundaries
Planning,Programming, Fiscal,
& AdministrativeFY 18-22 2,826,000$
104
Professional Capacity-Building Strategy TrainingProfessional Capacity-Building Strategy Training
Planning,Programming, Fiscal,
& AdministrativeFY 18-22 5,250,000$
105
Research Development and Technology TransferThe Research and Technology Transfer Programcoordinates the agency’s research activities, helping todeliver life cycle cost savings and innovative solutionsthat improve the quality of life in the District
Planning,Programming, Fiscal,
& AdministrativeFY 18-22 5,000,000$
106
State Planning and ResearchProvide major support for the District’s transportationplanning activities including regional safety, traffic andinfrastructure
Planning,Programming, Fiscal,
& AdministrativeFY 18-22 15,000,000$
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
27
Draft FY 2018-2022 Project List Districtwide Projects
Planning/Study Design Construction OtherID Project Name and Description Project Category
Project Phase Proposed FY18-22
Cost
107
Traffic Management Center OperationsFunds Traffic Management Center (TMC), RoadwayOperations Patrol (ROP), ITS Support & Maintenance,and ITS Systems Development & Integrationsalaries. This staff operates the TMC and ROP 24/7,improves ITS functions, and keeps ITS systems anddevices up and running.
Planning,Programming, Fiscal,
& AdministrativeFY 18-22 30,000,000$
109
Citywide Engineering Services for Structures andBridgesCitywide on-call bridge consultant for engineeringservices for bridge and structures.
Planning,Programming, Fiscal,
& AdministrativeFY 18-22 2,500,000$
110
Commuter ConnectionsProvides support for the Districts transportationplanning activities including regional, safety, trafficand infrastructure
Planning,Programming, Fiscal,
& AdministrativeFY 18-22 4,156,643$
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
28
Draft FY 2018-2022 Project List Districtwide Projects
Planning/Study Design Construction OtherID Project Name and Description Project Category
Project Phase Proposed FY18-22
Cost
111
Constructability and Work Zone Safety ReviewDDOT staff (1) to review MOT/TMP plans and (2) toaudit construction projects in the field generated byIPMD reconstruction and Asset Managementmaintenance programs
Planning,Programming, Fiscal,
& AdministrativeFY 18-22 1,777,633$
112
Cost Estimate ReviewProvide support to department with independent costestimate for construction projects before finalizing thePS and E package for advertisement. Typical servicesinclude reviewing plans, and specifications, checkingquantity take-off and providing independent costestimate for the project. Other services may includecost analysis and related services. Services will be
Planning,Programming, Fiscal,
& AdministrativeFY 18-22 2,000,000$
113
District STIP DevelopmentConsultant assistance to help develop the 2018-2022DC Statewide Transportation Program (STIP) Planning,
Programming, Fiscal,& Administrative
FY 18 100,000$
114
Metropolitan PlanningProvide major support to the District's transportationplanning activities including regional, safety, trafficand infrastructure
Planning,Programming, Fiscal,
& AdministrativeFY 18-22 13,000,000$
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
29
Draft FY 2018-2022 Project List Districtwide Projects
Planning/Study Design Construction OtherID Project Name and Description Project Category
Project Phase Proposed FY18-22
Cost
115
Oversize/Overweight Routing Tool Maintenance andEnhancementTo facilitate safe operation of trucks in a bicyclist andpedestrian heavy environment, the District built aWaze-like truck routing tool. This project will keep thetool up to date as conditions change in the Districtand provide system enhancements.
Planning,Programming, Fiscal,
& AdministrativeFY 18-19 325,000$
116
Traffic Signal On-site Support ServicesOn-site support services assist DDOT signal divisionwith the review of various signal designs from stand-alone projects, IPMD reconstruction/corridor projects,and development projects
Planning,Programming, Fiscal,
& AdministrativeFY 18-22 1,000,000$
117
Transportation Asset Management PlanDevelopment of the Transportation AssetManagement Plan (TAMP) for DDOT, implementationof process established in initial plan
Planning,Programming, Fiscal,
& AdministrativeFY 18-22 8,039,650$
District of Columbia Fiscal Year (FY) 2018 - 2022 STIPAll costs in current year (2017) dollars. Costs for projects in the planning phase may be reevaluated in future phases.
30