Distribution Recovery Plan Update 09:00 29th July 2007
1
DISTRIBUTION RECOVERY STREAMWater System Schematic
Estimated Volume (Ml)
Trunk Mains 36
Service Reservoir 188
DMAs 38
Total 262
Treatment works
Main (1883km)
Service Reservoir
Trunk Main
Valve
Valve Meter
DMA
DMA DMA
District Metered Area (DMA)
(110)
Approx
1300
Properties
River
(87km)
(15)
• Flow started here between 1700hrs and 2100hrs, 28th July
• Initial flow of 80Ml/d building to 120Ml/d over following 12 hours
Distribution Recovery Plan Update 09:00 29th July 2007
2
Estimated Recharge Timetable
Phase Area Properties Start date Completion Boil Drink
1 Tewkesbury 9000 27th July 28th July
1 - 5 days later depending on
quality sampling results
2
Tewkesbury / Cheltenham ruralDumbleton / Toddington / Gotherington / Broadway / Snowshill 2900 29th July
3 Quedgeley 5200 30th July
4 Bishop’s Cleeve and Prestbury 7303 30th July
5
GloucesterChurchdown, EasternAve, Longlevens,Treadworth,Abbeymead, Abbeydale,Barnwood, Tuffley, Podsmead,Sandhurst 53700 30th July
6 Cheltenham 27300 31st July
7Brockworth / Upton / Matson /Fox Elms 24200 1st August
8 Woodmancote 2500 2nd August
TOTAL 132103 5th August
All timings are estimated. All timings are liable to vary due to the unique nature of a 2,000km pipeline.
Distribution Recovery Plan Update 09:00 29th July 2007
3
Issues influencing timing
• Demand levels – filling loft tanks, taps left running, washing backlog, flood washdown, etc
• Operational issues in recharging – airlocks
• Mechanical failure of distribution assets – valves, pressure control valves, booster pumps
– Not been run for a while, may have flood damage
• Leakage– system has been discharged– floods will have caused ground movement
• Mythe production – mechanical / electrical / process failure