Overview
• Welcome New Member• Development Methodology• Deliverables• Communication• Activity Plan• Milestons• Financial Plans• Project Risks
Development Methodology(1)• Agile Scrum• Scrum Artifacts
Product backlog – will be defined and changed according to changes in requirements.
Sprint backlog – will be defined for every sprint and will hold information about planned tasks.
• Why Scrum Unclear requirements in starting, may change later. Small team size and informal communication. Short sprints undermine project risks.
Development Methodology(2)• Scrum adjusted for DSD course:
– Transport4You Scrum Roles:• Scrum Master: Dajan Zvekic• Product owner: Customers Elizabetta Di Nitto and Mateo Rossi and
supervisor Aneta Vulgarakis• Team of 7 members
– Transport4You Scrum meetings• Daily Scrum Meeting
– Twice a week, localy• Sprint Planning Meeting
– Once a week tasks for upcoming sprint will be defined• Sprint Retrospective Meeting:
– Once a week on skype• Sprint Review Meeting
– Presentation on Tuesday
Deliverables
• Project plan document • Requirements Definition document • Design Description document • Summary Week Report • Minutes of Meeting • Technical documents, project policies etc. • Acceptance test plan• Test report• Final Project Report, • Final product (installation, source code, etc.)
Activity PlanWeek 38
Week 39
Week 40
Week 41
Week 42
Week 43
Week 44
Week 45
Week 46
Week 47
Week 48
Week 49
Week 50
Week 51
Week 52
Requirement gathering x x
Requirement Analysis x x
Architecture Design x x xProduct Implementation x x x x x x x
Unit Testing x x x x x x
Prototype x xSystem and Alfa Testing x x x x
Final Product x x
Final Report x x x x
Final Presentation x x
Estimate to complete Buffer
• Calculating 20 Euros/4hrs • Requirement gathering and analysis =20*5*20=2000 Euros• System Design =20*5*20 = 2000 Euros• Implementation =70*7*20 = 9800 Euros• Testing =28*3*20 = 1680 Euros• Documentation =20*5*20 = 2000 Euros• Mobile for testing = 300 Euros • Rent for Bus = 400 Euros• Price of system in Bus = 400 Euros
• Total Estimated Investment : 18580 Euros
Financial Plan(1)
Project Risks• Missing of deadline.
– Regular meetings to discuss progress.– Keep track of progress by weekly reports
• Team member is leaving – Backup for team members.
• Communication Gap – Information is posted on discussion forum.– Meetings are documented in MOM’s.
• Issue with SVN Repository and Local data– Regular Backup