Dip. Fisica Bari Bari INFN toward CMS Upgrade M de Palma INFN-Univ Bari FNAL- Nov. 19, 2008.

26
Dip. Fisica Dip. Fisica Bari Bari INFN toward CMS Upgrade M de Palma INFN-Univ Bari FNAL- Nov. 19, 2008

Transcript of Dip. Fisica Bari Bari INFN toward CMS Upgrade M de Palma INFN-Univ Bari FNAL- Nov. 19, 2008.

Dip. FisicaDip. Fisica

BariBari

INFN toward CMS Upgrade

M de PalmaINFN-Univ Bari

FNAL- Nov. 19, 2008

Dip. FisicaDip. Fisica

BariBari

M. de Palma FNAL Upgrade Workshop 19 Nov 08 2

First step: a Woking Group in INFN Road Map April 2006

http://www.infn.it/csn1/riunioni/agenda/2006/15-05-2006/depalma.ppthttp://www.infn.it/csn1/Roadmap/SLHC.pdf

Final report

Dip. FisicaDip. Fisica

BariBari

M. de Palma FNAL Upgrade Workshop 19 Nov 08 3

History

About CMS, in the report, was underlined for the first time the interest of INFN community to participate in the tracker and muon system upgrade. It was defined two period of activity:

a R&D phase in years 2007-2008 a preproduction phase in years 2009-2010

and for both, a funding profile was present.

… but despite of this, any R&D upgrade program was financed in 2007 and again in 2008 (in both for CMS and ATLAS). Moreover in last June it appears absolutely unclear the situation for the 2009….

We realize that a clear discussion within INFN around the SLHC upgrade was needed and we trigged the Sestri Levante meeting.

Dip. FisicaDip. Fisica

BariBari

M. de Palma FNAL Upgrade Workshop 19 Nov 08 4

The Sestri Levante meeting

• Physic motivations

• Detector performances (???)

• Technologic and financial impact

• Italian contributions and fund

Dip. FisicaDip. Fisica

BariBari

M. de Palma Tracker General Meeting 27/02/08 5

The Sestri Levante meeting – first day

• The CMS upgrade: Field of Interest for INFN Groups

• The CMS upgrade: Field of Interest and committeemen of international community

Dip. FisicaDip. Fisica

BariBariThe Sestri Levante meeting – second day

M. de Palma FNAL Upgrade Workshop 19 Nov 08 6

Summary

13/11/2008 2M. de Palma -CMS upgrade - Sestri Levante

The CMS upgrade plans (omissis here)

Field of Interest for INFN GroupsTracker (Shortly reported here)

Muon system (omissis here)

Cost per R&D phase.

for 1) information's from official CMS talks: J. Nash at LHCC - 23/9/08

From my talk at Sestri meeting

Possible activities for the INFN groups: Could be infer from the R&D proposal submitted to CMS

1) Upgrade of CMS Barrel Muon Detector Contact person: P. Zotto, A.Montanari

Istitution: CIEMAT, Universidad de Cantabria, Torino, Bologna, Padova, Bari, Pavia,

Napoli, RWTH Aachen, Madrid, Legnaro, Frascati, Vienna

Status: Approved

2) R&D for Thin Single-Sided Sensors with HPK Contact Person: M. Mannelli

Istitution: CERN, UCSB, Purdue, FNAL, Perugia, Bari, Pisa, Karlruhe, Vienna, PSI

Status: Approved

3) Development of pixel and micro-strip sensors on radiation tolerant substrates for the tracker upgrade at SLHC Contact Person: M. de Palma

Istutution: Bari,Catania, Firenze,Padova,Perugia,Pisa,Torino, PSI, Fnal, Purdue

Status Approved

4) Proposal for a First Level Trigger based on Tracking Contact Person: F. Palla

Istutution: Lyon, Pisa, Firenze, Bari, Barcellona, Minnesota,,Brown Univ, Boston Univ.

Status Submitted on 30 Oct.

13/11/2008 18M. de Palma -CMS upgrade - Sestri Levante

From my talk at Sestri meeting

CMS Upgrade- Documents

The R&D work should give results already at the end of 2011.

13/11/2008 9M. de Palma -CMS upgrade - Sestri Levante

In the follow, we assume this time schedule.

From my talk at Sestri meeting

Phase I tracker

The actual CMS idea (but it is still evolving) is that the Pixel system will be substituted: BPIX as the third option ( in slide 4), rebuilt it using the actual technology but with improvements on FE, cooling (bi-phase CO2), read-out (-tw pairs)

FPIX still using 3 disk, but maybe with innovative sensors (n-on-p)

In the previous hypothesis of minimal change respect to the actual pixel system, we are not interested in an involvement in the constriction and assembling of new system, but we foresee an our involvement in the phase II.

13/11/2008 20M. de Palma -CMS upgrade - Sestri Levante

From my talk at Sestri meeting

Possible implication for the phase I trackerIt’s reasonable assume that the choice for the tracker phase-II will be made on the basis of the experience at LHC, of the R&D and of solutions taken already for the phase I.

If we want to be relevant on the phase II, we have to be minimally involved in the development phase of the Pixel-phase I. ( MI will want to maintain his involvement with commitment similar to the actual, but there are interest from PI, and maybe BA)

For do what? R&D of pixels n-on-p (with colleagues of FPIX, but already running with SMART(GV), RD50,

CMS proposal), R&D of 3D (with colleagues of FPIX, but already running with TRIDEAS(GV)), Cooling e Mechanics: (at PI with SLIM and SuperB activity, and phase II), Preparation of prototypes module and possible involvement in test beam (in synergy with the

sensors phase II proposal,) Commitment on the test or on the module qualification ( MI?)

13/11/2008 21M. de Palma -CMS upgrade - Sestri Levante

From my talk at Sestri meeting

Possible R&D activity for phase II tracker In the project of the new tracker and its trigger scheme we would like to be active part (and we are already…)

In the short period, we would like to contribute in:

Radiation hardness ( CMS-proposal 2 e 3 ) Sensor design Material/Device study

Trigger L1 architecture ( CMS proposal 4) Algorithm of discrimination and of pre-selection high pT

High rate data transmission Off detector trigger processors

Tracker Layout ( group of simulation)

Subsequently: Module Prototyping/integration, Cooling e Mechanics layer/system

Other useful initiative for the phase I/phase II: GBT, fast optolink TMB (already in GV)

13/11/2008 23M. de Palma -CMS upgrade - Sestri Levante

From my talk at Sestri meeting

R&D Cost Estimation for INFN

13/11/2008 25M. de Palma -CMS upgrade - Sestri Levante

ITEM I° year II° year III° yearSensori pixel/strip CMS proposal n 2,3

200 400 400

LV1 tracker trigger CMS proposal n 4

30 60 60

DT upgrade CMS proposal n 1

100 150 150

RPC upgrade 10 10 50Totali 340 620 660

Cost estimation for the first 3 R&D ears (in K€)

From my talk at Sestri meeting

For phase II tracker – System

13/11/2008 27M. de Palma -CMS upgrade - Sestri Levante

Behind R&D, It is our interest be involved at the definition and at the design of the new system, and also contribute at the realization, of the new tracker.

For this we are collaborating already at the WG of simulation (see talk of A. Tricomi).

The trigger will be the real improvement of the new generation tracker and the layout will be imposed by the chosen trigger scheme.

Once defined the trigger scheme, it will determine heavily the choice of the part of the system that, eventually, we have to build (and pay).

It’s hard to be precise but we would like to follow:

Module Prototyping/integrationMechanics for layers Cooling e Mechanics system

From my talk at Sestri meeting

Conclusions

• The INFN groups are ready for start R&D programs, finalized at the phase II, approved and accepted by CMS.

The timeline for the DTR (2012) and the activity of the others Institutions in CMS urge us in start as soon as possible. There are Institution already financed, so every delay will be negatively reflected, mainly for the tracker, on the relevance of the INFN on the upgrade.

• The commitment for the building part (and the cost) of the phase II in which we are interested can not be defined exactly. They are related to the study on events at LHC, on simulations and on results at R&D. It’s essential to be involved in this study for have at the end a shared project.

Obviously, our capability of action is related to the resources that the INFN will can and will want to invest on this topic and also to the time in which this possible resources will be available.

13/11/2008 29M. de Palma -CMS upgrade - Sestri Levante

From my talk at Sestri meeting

Dip. FisicaDip. Fisica

BariBari

M. de Palma FNAL Upgrade Workshop 19 Nov 08 16

Sestri Meeting discussion

We had a long and useful discussion. It has been driven by the fact that the actual official time schedule for both Phase I and Phase II has been considered unrealistic.The conclusions of our discussion can be synthesized (about CMS tracker) in the following statements:

The R&D on sensors (pixel and strip) must be considered a general and fundamental item and therefore will be smoothly financed, in conjunction with the LV1tracker trigger studies and layout simulation. A clear three years financial plan is request to us, preferably showing also contributions from other institutions.

The INFN-CSN1 had reserved funds already for 2009 financial year. We hope to spend some of them in 2009 by submitting a detailed R&D program to be discussed with INFN referees with a time schedule still to be defined (the amount is <100 K€, maybe before the summer)

The involvement in R&D program does not necessarily mean our automatic commitment in construction of important parts of the Phase II detector. This contribution will be, taking into account the interest of involved people, argument of an agreement between INFN and CMS, to be done in future, at proper time (in 2012?, for TDR?)

Dip. FisicaDip. Fisica

BariBari

M. de Palma FNAL Upgrade Workshop 19 Nov 08 17

Our Conclusions

Since with our CMS R&D proposals, we are almost ready to answer points 1 and 2, we consider the current status promising and positive and……. begin to see sunrise.

Based on those CMS R&D proposals we are preparing a detailed R&D and cost program to discuss with to INFN (we hope at the end of January 2009).

Dip. FisicaDip. Fisica

BariBari

M. de Palma FNAL Upgrade Workshop 19 Nov 08 18

Sensor proposal

If y ou want,

I can recall the main line (in 4 slides) of sensors proposal in which INFN is most

involved, as presented by A. Messineo in the experiment R&D sessions, at Sestri.

Dip. FisicaDip. Fisica

BariBari

M. de Palma FNAL Upgrade Workshop 19 Nov 08 19

Sensor proposal

Dip. FisicaDip. Fisica

BariBari

M. de Palma FNAL Upgrade Workshop 19 Nov 08 20

Sensor proposal

Dip. FisicaDip. Fisica

BariBari

M. de Palma FNAL Upgrade Workshop 19 Nov 08 21

Submission plan (I)

Dip. FisicaDip. Fisica

BariBari

M. de Palma FNAL Upgrade Workshop 19 Nov 08 22

Submission plan (II)

Dip. FisicaDip. Fisica

BariBari

M. de Palma FNAL Upgrade Workshop 19 Nov 08 23

That’s all, thanks

Dip. FisicaDip. Fisica

BariBari

M. de Palma FNAL Upgrade Workshop 19 Nov 08 24

Back-up

Dip. FisicaDip. Fisica

BariBari

M. de Palma FNAL Upgrade Workshop 19 Nov 08 25

Activity matrix

Dip. FisicaDip. Fisica

BariBariTime schedule