Dignity Health

8
Dignity Health Sequoia Hospital 3” & 4” Pipelining Project Nu Flow America November 2016 Dale Houts

Transcript of Dignity Health

Page 1: Dignity Health

Dignity HealthSequoia Hospital 3”

& 4” Pipelining Project

Nu Flow America

November 2016

Dale Houts

Page 2: Dignity Health

Access Points

Helen’s office ceiling Machine Room

Page 3: Dignity Health

Camera and cleaning the pipe

Camera Inspection Cleaning the pipe Sucking out all loose debris after cleaning

Page 4: Dignity Health

Preparing the felt linerLay out liner Combine epoxies Mix epoxies together

Page 5: Dignity Health

Saturating epoxy into linerPour epoxy into felt Saturating felt Score felt to let epoxy ooze

out for 100% adhesion

Page 6: Dignity Health

Preparing the liner cont..We marked the connection point

(Gapping method)

Cutout the felt at connection point Roll and tape felt to fit into pipe

Page 7: Dignity Health

Installing felt into pipePushing the liner to one

access point

Pulling liner for other access point

Inflate air bladder with air pressure

Page 8: Dignity Health

Finished productEquivalent to schedule 40

pipe inside host pipeLife expectancy 75+ years