Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD...

122

Transcript of Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD...

Page 1: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete
Page 2: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete
Page 3: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

UNITED STATES GENERAL ACCOUNTING OFFICE

CHARLES A. BOWSHER

Comptroller General of the United States

VACANT

Deputy Comptroller General of the United States

i

HARRY R. VAN CLEVE

General Counsel

E

I

Page 4: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete
Page 5: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

VOLUME I No. 14

November 1985

Contents

Page

Tab1 e of Des i s ions I

Digests : General Government Matters: Appropriations and Miscellaneous A- 1

Personnel Law: Civilian Personnel 8-1

Personnel Law: Military Personnel c- 1

Procurement Law D- 1

Special Studies & Analysis No Cases

Transport at ion Law F- I

Index i

Compiled in the Index-Digest Section

Office of the General Counsel

Telephone research service regarding Comptroller General decisions: (202) 275-5028

For Copies of cases: (202) 275-6241

1

I

I1 1 I 1 I1

1 I 1

Page 6: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete
Page 7: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

TABU OF DECISIONS

November 1985

Nov. Page - - B-20 1 6 6 9 26...A- 1 3-2 0 5 20 8 29.. .D-74 8-208159.3 19. .D-41 B-2 1 6 88 7 21.. .D-52 8-2 16938 12.. .B- 2 B-2 17095 29...B- 6 E-217 514 25...B- 4 B-2 i 7 a io 27. .D-71 8-217~8 14. .D-35 B-2 1 7 9 3 7 26...B- 5 B-218021.3 26. .D-61 B-218102.5 29.. .D-75 B-218427.3 27.. .D-72 B-zia567.2 5.. .D-14 8-218622.4 13 - -11-27 B-2 1 a 6 94 25...F- 1 8-218730.4 20.. .D-45 B-2 1 8 7 6 3 26...B- 5 8-218766.2 21. .D-53 8-218846 4...D- 7 8-2 1 a a4 8 5.. .D-15 ~-2i8a52 1...D- 1 B- 2 188 5 5 5.. .D-15 B-2 1886 1 4...D- 8 B-2 18946 12-*.B- 3 B- 2 18 964 26...B- 6 B-218982 l . . . A - 1 B-2 189 99 22.. .D-56 B- 2 190 2 6 29.e.B- 7 B- 2 190 5 1 27...B- 6 B-219076) B-2 19 123 25...B- 4 B-219107.2 7.. .D-18 B-219114.2 4 . ..D- 8 8-219236.2 26...A- 2 B-2 193 2 7.6 4...D- 8 B-219423.2 25.. .D-59 B-219428.2) B-219440.2) 21...D-53

Nov. Page - - B-219435.2 26.e.D-62

E-219449 8.. .D-20 8-219458 l..,D- 1 B-219469 4...D- 9 8-2 19470 8...8- 1 13-219 50s 29...B- 7 8-219 508 12.. .D-22 B-219 512 l...D- 2 8-219541.2 13.a.D-28

B-219 57 5 20.. .D-46 E-219601 1 3 . . .D-29 B-219609 21.. .D-53 ~ - 2 m i a 8.. .D-21 B-219623.2 27...D-72 B-2 196 3 5 l...D- 3 8-2 1963 6 4 . . .D-10 R-219643 18.. .D-38 B-219648 5.. .D-16 B-2 196 5 1 26.. .D-62 B-219454 12.. .D-22 B-2 19662 20.. .D-46 B-219664.2 19.e.D-41

B-219448.3 13.a.D-28

8-219546 29.. .B- a

B-219683 26. *D-65 B-2 1969 5 19 - .D-42 B-219699 13.. .D-30 B-219733 21.. .D-54 8-219763.2 26.a.D-66 R-219766 5.. .D-16 B-219825 29.. .D-75 B-21987 2,

et al.) 20...D-47

R-2 1991 7 19.. .D-42 B-219923.2 20.. .D-48 B-219926.2 13...D-30 E-21993 1 5...B- 1

B-2 199 15 la.. .~-39

1

I

Y

r

I

Page 8: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

TABLE OF DECISIONS - Con.

Y I

I

Nov. Page -- NO~. Page -- B-219981 27. a .D-73 B-219388.4 4.e.D-12 B-220000.2 21.e.D-54 B- 2200 12 25. .D-59 B-2200 13 12. .D-23 B-220015 l...D- 3 B-220032 21 .D-55 8- 2 2 003 4 13. .D-31 8-2 2 00 3 7 20 . .D-49 B-2 200 70 26 . .D-68 3-220065 -2 15 .D-36

B-220071 8. *D-21 8-220080.2 22.e.D-56 13-220092,

et al.) 25...D-60 B-22 0 13 2 26. .D-68 B-220141 12.. .D-24 B-220142 19. .D-44 8-220144 26.. .D-69 B-220146.2 25. .D-61 B-220152 ) 8-220152.2) 20.e.D-49 B-220162 22. .D-57

B-2 20 1 7 4 12.. .D-24 B- 2 201 80 4.. .D-12 B-220199.2 8...D-21 B- 2202 00 25.. .D-61 B-2202 09 29.. .D-75 8-220253 22.. .D-58 B-220278 13.. .D-32 B-220354 13.. .D-32 8-220374 8.. .D-22 B-220380 1...D- 4 B-220387 14.. .D-35 B-220390 4 . . .D-12 B-220400 1...D- 5 8-220405 13.. .D-32

B-220168.2 29.e.D-75

B- 2 2040 6 3- 2 2 04 10 B-22 042 4 B-220434.2 8-220463 B-220517.2 B-220545 B-220559.2 B-220560 8-220570

B- 2 206 19 B-22066 3 ) B- 2 2 0 664 ) B-220667.2 B-220672.2 8-220680.2 8-22 0683 B-220693 B-220717.2 B-220731.2 E-220792 B-220800.2 B-220819 B-220824 B- 2 2 08 3 6 B- 220839 B- 2 208 5 7 B-220879 B-220891 B-220894 B- 2 20 90 5 8-220918 -2 B- 2 20 93 5 3-220943 8-22 09 6 3

E-221057

B-22061842

E-220968

4 . .D-l3 13 .D-32 21.. .D-55 2 2 . . . D-58 13.. .D-33 26.. .D-69 20.. .D-50 26.. .D-70 1 3 . . .D-33 20.. .D-51 27.. .D-74 14.. .D-36

27. .D-74 20. .D-51 13.. .D-34 12.. .D-25 22.. .D-58

4. . .D-13 12.. .D-26 12.. .D-26 14...C- 1 12.. .D-26 12.. .D-27

5.. .D-17 29...A- 2

1...n- 5 l...D- 6 15.. .D-37 l...D- 6 L...D- 7 12.. .D-27 20.. .D-52

6 . . .D-17 21 . .D-56 15.. .D-31 6.. .D-l$

20.. .D-52

I

I

I

I1

Page 9: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

GENERAZ. GOVERNMENT MATTERS

PROPERTY B-218982 NOV. 1, 1985 Private

Taking for Government Use Liability of United States

On request for reconsideration, we affirm 2-2854316, Jan. 2 9 , 1985, in which we denied a claim for $175,000 since the record still presents a substantial question about whether a taking of real property by the United States has occurred due to road closings resulting from a Federal construction project.

EOUSING AND URBAN DEVELOPMENT B-201669 NOV. 26, 1985 DEPARTMENT

Mortgage Insurance Funds Distributive Shares

Unrefunded distributive share is held by Department of Housing and Urban Development (HUD) in Mutual Mortgage Insurance Fund as trustee on behalf of persons entitled thereto. If HUD cannot locate persons in order to make payment, amounts should be cleared from the Fund's account and transferred t o the credit of the Treasury account entitled "Unclaimed Moneys of Individuals Whose Whereabouts are Unknown'' in accordance with procedures set forth in Treasury Department Fiscal Requirements Manual f o r Guidance of Federal Agencies Vol. I, Part 6 , Chapter 3000. Statutes of Limitations generally do not run against claims by beneficiaries for amounts held by the Government as trustee in the trust account for "Unclaimed Moneys of Individuals Whose Whereabouts Are Unknown." B-103575, August 27, 1951. Failure to transfer unpaid distributive shares in manner specified does not serve to render the trust amounts subject t o statutes of limitations.

A- 1

I

L

i

1

Page 10: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

OFFICERS AND EMPLOYEES Health Insurance Blue Cross-Blue S h i e l d

Funds

B-219236.2 NOV. 26, 1985

GAO and Department of Justice approved Office of Personnel Management's proposal to accept premium refund from Blue Cross/Blue Shield in the Federal Employee Health Benefits Fund's Contingency Reserve. 3-219136, J u l y 31, 1985 and 5 U.S .C . s 8909 (1982). OPM now proposes that, when employee refund checks art? drawn on the Contingency Reserve account, the Govern- ment's share of the returned premiums be deposited in the Treasury's General Fund. This plan would effect a net savings to the Government, but would violate the Contingency Reserve statute, which permits the reserve fund to be used o n l y to defray rate increases, lower premium contributions or increase benefits. Legislative history shows that refunds of this type were planned for in the o r i g i n a l statute, although they were thought to be unlikely to occur. Deposit in the General Fund would also violate 3 1 U.S.C. 5 1532 prohibiting transfers between appropriation accounts.

ACCOUNTABLE OFFICERS B-220836 NOV. 29, 1985 Relief

Debt Collect ion

The General Accounting Office will deny relief under the diligent claims collection standard of 31 U.S.C. 3527(c) in cases involving Treasury debit vouchers dated after January 15, 1985, if Army's designated collection representative does not begin collection action within 3 months from the time notice of a loss is received.

r

I

I

A- 2

Page 11: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

PERSONNEL LAW: CIVILIAN PERSONNEL

RETIReMENT B-219931 NOV. 5 , 1985 Civilian Reemployed Annuitants Annuity Deduction Validity

Administrative Office of the United States Courts questions whether retirement benefits authorized by 28 U.S.C. 5s 611, 627, and 677 f o r certain officials of the judicial branch may be paid t o an eligible official who accepts post-retirement employment in government service. The Administrative Office is advised that full retirement benefits may be paid to such an official because nothing in the applicable legislation requires s u s p e n s i o n or reduction of annuity payments in the event of t he annuitant s reemployment. Furthermore, we have no legal objections i f a reemployed annuitant wishes t o temporarily waive the retirement benefits payable t o him under 28 U.S.C. S S 611, 627 , or 677, during the period of reemployment.

OFFICERS AND EMPTAYRES B-219470 NOV. 8 , 1985 Promotions

Temporary Detailed Employees

Wilson Case Higher Grade Duties Assignment

An employee who claims entitlement to a retroactive temporary promotion and backpay based on our Turner- Caldwell decisions, appeals a disallowance by our Claims Group. That disallowance was based o n our decision Turner-Caldwell 111, 6 1 Comp. Gen. 408 (1982), which followed the Court of Claims decision in Wilson v. United States, 229 Ct. C1. 510 (1981), denying such entitlement, and stated that it would apply to all pending and future claims. The employee argues that, since our decision postdated the events on which his claim is based , it should not govern his entitlement. The disallowance is sustained. Since the employee's claim was n o t settled prior to our Turner-Caldwell I11 decision, that d e c i s i o n governs.

B- 1

I

I

I

I

I

Page 12: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

GENERAL ACCOUNTING OFFICE 8-216938 WOV. 12, 1985 Decisions Reconsideration Error of Law or Fact Basis

N o t Established

In order to obtain a reversal of a prior decision, a material mistake of law o r fact must be proven. The claimant has raised no new arguments in support of his claim for real estate expenses that were no t considered in the prior decision. Mere disagreement with the previous decisfon is not a proper basis for reversal of a decision upon reconsideration.

OFFICERS AND EMPLOYEES Transfers Govemment v. Employee Interest

Relocat iormpense Reimbursement Administrative Determination

F i M l f ty

A former Internal Revenue Service employee seeks reconsideration of his c la im for real estate expenses. Our d e c i s i o n of January 3 , 1985, denied his claim because the employee requested the transfer for personal reasons. Since the agency determination that the transfer w a s not in the interest of the Government i s in accordance with decisions of this Office, and the employee failed to complete 1 year of service following the transfer, the prior decision is reaffirmed.

I

r

I

B- 2

Page 13: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

TRANSPORTATION B-216938 Con't Household Effects Nov. 12, 1985 What Constitutes

An Internal Revenue Service employee was transferred from Indianapolis, Indiana , to Fairbanks, Alaska. After completion of a 2-year service period specified in the service agreement, the employee requested a transfer t o Portland, Maine, €or personal reasons. The service did not authorize relocation expenses and the employee disposed of most of his household effects before departing Fairbanks. He is claiming an amount equal to the cost of t r a n s p o r t i n g his household effects to Alaska. The claim may no t be paid since the law and regulations provide f o r reimbursement on the basis of the weight of the household effects actually transported.

OFFICERS AND EMPLO!fEES B-218946 NOV. 12, 1985 Transfers

R e a l Estate Expenses Loan Discount Fees

A transferred employee who purchased a new residence paid a 1-1/2 percent loan fee and reimbursed the seller f o r an additional fee of 1-1/4 percent. Although the employee claimed both fees as "loan origination fees," the agency allowed only the 1-1/2 percent fee as an origination fee and denied reimbursement f o r the additional 1-1/4 percent. We sustain the agency's determination that the additional 1-1/4 percent fee must be disallowed, because the record shows that the fee constitutes a nonreimbursable loan discount.

E-3

I

I

I

Page 14: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

OFFICERS AND EMPLOYEES B-217514 NOV. 25, 1985 Transfers Real Estate Expenses Broker's Pees Legal Obligation to Pay Requirement

An employee, i n c i d e n t t o a change of o f f i c i a l d u t y s t a t i o n , s o l d h i s r e s i d e n c e i n C a l i f o r n i a t o a purchaser who was a l i c e n s e d real es ta te broker . The b r o k e r ' s commission, as provided i n t h e c o n t r a c t of s a l e , w a s deducted from t h e s e l l i n g price. The p r o v i s i o n i n t h e c o n t r a c t o f sa le f o r payment of a commission f a i l e d t o s a t i s f y t h e requi rements of t h e C a l i f o r n i a s t a t u t e of f r a u d s s i n c e i t d i d n o t show t h e f a c t o f employment of t h e broker by t h e s e l l e r . The payment of t h e commission, t h e r e f o r e , was not a l e g a l l y e n f o r c e a b l e o b l i g a t i o n and t h e employee may n o t be reimbursed f o r t h e commission.

OFFICERS AND EMPLOYEES B-219076; B-219123 Traasf ers Nov. 25, 1985

Real Estate Expenses Loan Origination Fee

Two t r a n s f e r r e d employees who i n c u r r e d l o a n o r i g i n a t i o n f e e s of 1.5 p e r c e n t are not e n t i t l e d t o reimbursement f o r more t h a n 1 p e r c e n t f e e a l lowed by t h e Veterans Adminis t ra t ion . Survey of l e n d i n g i n s t i t u t i o n s i n t h e Lexington, Kentucky area i n d i c a t i n g t h a t 7 3 p e r c e n t charge l o a n o r i g i n a t i o n f e e s equal t o 1 p e r c e n t o f t h e loan amount conf i rms t h e Veterans A d m i n i s t r a t i o n ' s d e t e r m i n a t i o n t h a t 1 p e r c e n t i s t h e customary loan o r i g i n a t i o n f e e .

B-4

I

i

Page 15: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

LEAVES OF ABSENCE B-217937 N ~ v . 26, 1985 Compensatory Time Credit Hours Limitation on Accrual

E f f e c t Overtime Adjustment

An employee who failed to use compensatory time o f f before the time limit fixed by h i s agency claims overtime pay. Compensatory time remaining to the credit of an employee after the time limit may not be converted back t o overtime unless agency determines that failure t o take compensatory time was for reasons beyond employee ' s cant rol due to exigencies of the service.

LEAVES OF ABSENC3 B-218763 NOV. 26, 1985 Civilians on Military Duty Unlimited Military Leave

Purpose of Duty Consideration District of Columbia National Guard Duty

A former employee of the Government Printing Office and member of the District of Columbia National Guard seeks recredit of 2 days annual leave charged when military leave was denied. Military leave was denied because the employee had used his 15-day annual allotment of military leave under 5 U.S.C. S 6323(a) d u r i n g annua l training. The employee, as a member of D.C. National Guard, was also eligible to take military leave for annual training under 5 U.S.C. 5 6 3 2 3 ( c ) , which is not subject to the 15-day ceiling. In view of this, sub- section 6323(c) leave may be substituted for subsection 6323(a) leave €or annual training in order t o provide military leave to cover the time he was charged annual leave. i

B-5

I

Page 16: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

Y

FEES 8-218964 NOV. 26, 1985 License, Pewit, etc. Fees Prohibition

Employees with the National Park Service, who operate heavy duty trucks in the performance of their duties as tree maintenance workers, may not be reimbursed for payment of fees for state licenses required to operate the vehicles. These fees are personal expenses incurred by the employees to qualify for their Government employment.

FRAUD B-219051 NOV. 27, 1985 F a l s e C l a i m s Subsistence Expenses

Agency recouped subsistence expenses advanced t o an employee, determining that he had fraudulently claimed payment of tips to hotel maids on each day of a 19-day temporary duty assignment. Based on evidence in the record, we conclude that the agency has sustained its burden of establishing that the employee fraudulently claimed payment of maid tips. Accordingly, the employee may n o t recover any of the subsistence expenses recouped from him.

TRANSPORTATION B-217095 NOV. 29, 1985 Household Effects Weight Limitation Changes Retroactive

An employee is limited to the maximum weight f o r ship- ment of household goods provided in the regulations in effect on the date of his transfer, November 14, 1982, rather than the maximum weight allowed at the time of his household goods shipment, on December 21, 1983. The regulations implementing the increases authorized by section 118 of Public Law 98-151, November 1 4 , 1983, restrict these increases to employees reporting to their new duty station on or after November 14 , 1983. Contrary statements made by congressional sponsors after enactment awe not sufficient to show that the implementing regulations are improper. See Jack G. Petrie, B-216542, June 11, 1985.

B-6

i

Page 17: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

r

OFFICERS AND EMPLOYEES B-219025 NOV- 29, 1985 Transfers

Real Estate Expenses Loan Origination Fee

A transferred employee purchased a new residence and was charged 2.25 percent of her loan as a "loan origination fee." She was reimbursed 1 percent and now claims the remaining 1.25 percent. Under Federal Travel Regulations (FTR) para. 2-6.2d(l)(b), such fees are reimbursable not to exceed amounts customarily charged in the area fo r similar transact€ons. Since HUD advised that the customary range of loan origination fees charged i n the area is 2-3 percent of the loan, the employee may be reimbursed the additional amount claimed.

LEAVES OF ABSENCE B-219505 NOV. 29, 1985 Annual Leave Adjustment Excess Leave Credited Administrative Error

Where an employee's annual leave account was over- credited due to an error in calculating his service computation date, the employee may be granted waiver only to the extent reconstruction of his leave account results in a negative leave balance. The 123 hours deducted in reconstructing his annual leave account may not be waived or otherwise recredited. When an employee has sufficient leave t o his credit t o cover the adjustment there is no overpayment of pay which may be considered for waiver.

B-7

Page 18: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

OFFICERS AWD EMPulYl3BS 8-219546 NOV. 29, 1985 Transfers Nonreimbursable Expenses Operating and Maintenance Expenses Residence

The cost of removing a damaged tree from the site of a transferred employee's former residence is a cost of maintenance that cannot be reimbursed, either as a real estate expense o r as a part of the miscellaneous expenses allowance. For the same reason the cost of replacing a washer in a shut-of€ valve may not be reimbursed even though the need for repair became apparent only after the employee's washing machine had been disconnected from the supply line in his former residence.

The cost of locks, lock cylinders and the services of a locksmith t o upgrade the security of a transferred employee's new residence may not be reimbursed as a part of the miscellaneous expenses allowance. Even though the former owner could not account for all keys t o the existing locks, the changes or additions can only be characterized as repairs or improvements that must be disallowed under FTR para. 2-3 .1~(13) .

TRAVEL EXPENSES Transfers Dependents Unaccompanied Travel

I

I

Employee claims reimbursement f o r round-trip travel of h i s wife to attend settlement on residence a t the new duty station. Claim may not be paid as neither statute nor regulation authorizes this expense and FTR para. 2-3.lc(ll) precludes reimbursement of travel and transportation expenses in excess of those speclfically authorized.

B-8

Page 19: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

PERSONNEL LAW: MILITARY PERSONHEL

DEBT COLLECTIONS B-220792 NOV. 14, 1985 Uaiver Military Personnel

Allowances Basic Allowance for Quarters (BAQ)

A Navy p e t t y officer's r e q u e s t f o r waiver of h i s d e b t t o rhe United S t a t e s arising o u t o f overpayments of a m i l i t a r y b a s i c allowance f o r q u a r t e r s and a v a r i a b l e hous ing a l lowance i s d e n i e d , where i t appeared t h a t he knew o r s t r o n g l y s u s p e c t e d h e was being o v e r p a i d . Under the gove rn ing p r o v i s i o n s of statutory law, waiver of overpayments of m i l i t a r y pay and al lowances i s no t a l lowed i f the s e r v i c e member knew o r should have known he w a s b e i n g o v e r p a i d and c o n s e q u e n t l y , in this case, t h e r e i s no basis f o r waiving c o l l e c t i o n of t h e overpayments.

c

c- 1

Page 20: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete
Page 21: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

PROCUREMENT L A W

BIDDERS B-218852 NOV. 1, 1985 Debarment

Labor Stipulation Violations

Debarment Unwarranted Davis-Bacon Act

The Department of Labor stated that, in view of the circumstances, it was taking no further action (i.e., debarment) against a contractor for violations of the Davis-Bacon Act. Based on our independent review of the record, we conclude that the contractor underpaid the employees, but the record does not contain sufficient evidence of willful vhlations of the labor standards provisions of the Act to warrant debarment. Rather, we find that the underpayments may have resulted from careless recordkeeping and a misunder- standing of the wage decision's requirements concerning fringe benefits and classification of workers. Therefore, the contractor will not be debarred under the Act.

CONTRACTS B-219458 NOV. 1, 1985 Pro tests 85-2 CPD 501 Preparation

c o s t s Noncompensable

Recovery of quotation preparation expenses and t h e cost of filing and pursuing the protest is denied where a protest is found without merit. Recovery of lost profits is not permitted under any circumstances.

PURCHASES Small Awards Propriety Misplacement of Lower Offer

GAO will not disturb a small purchase contract where after award the contracting agency discovers that protester's timely lower quotation had been misplaced since agency's error was not the result of a conscious or deliberate effort to exclude the protester from

!

consideration. D -1

Page 22: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

r

BIDS B-219512 mv. 1, 1985 Opening 85-2 CPD 502 Postponement Denied

Failure to extend bid opening date was not improper where protester was given adequate time to submit competitive b id and where adequate competition and reasonable prices were obtained and protester does not allege that any contracting agency action was deliberately intended to preclude protester from competing on procurement.

CONTRACTS Protests General Accounting Office Procedures Filing Protest With Agency

When protest is initially filed with the contracting agency before bid opening, bid opening in the face of protester’s objections constitutes initial adverse agency action, and protest to GAO must be filed within 10 working days thereafter.

CONTRACTS Protests Procurement Pending Requirement

GAO will consider only protests involving specific procurement action and w i l l dismiss allegations of past improprieties.

0- 2

i

Page 23: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

BIDS B-219635 NOV. 1, 1985 Invitation for Bids 85-2 CPD 503 Specifications

Minimum Needs Requirement Administrative Determination Reasonableness

Protest alleging that agency has no rational basis for changing the weight limitation for high pressure portable compressors from 140 pounds t o 210 pounds is denied since agency determination of i t s needs will not be disturbed absent clear evidence that the agency's decision is arbitrary or unreasonable and agency provides reasonable explanation for its determination.

BIDS Opening Postponement

Denied

Protest against agency's refusal to extend bid opening date is denied where agency obtained adequate competition and reasonable prices and protester does not allege that the agency deliberately attempted t o preclude the protester from submitting a bid.

CONTRACTS 8-220015 NOV. 1, 1985 Negotiation 85-2 CPD 505 Awards

In i t ia l Proposal Basis Propriety

An award based on initial proposals, without holding discussions, is proper where the solicitation advised offerors of the possibility and there was adequate competition to demonstrate that award would result in a fair and reasonable price.

i

I

i

E

t

Page 24: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTS B-220015 Con't Negotiation Nov. 1, 1985 Late Proposals and Quotations Modification of Proposals Price Reduction

Contracting agency's decision not to open negotiations after receiving a late price reduction from one offeror--and to proceed with an award based on initial proposals--is reasonable where the expenses of conducting preaward surveys on the intended awardee and its subcontractor already have been incurred and thus will diminish the potential c o s t saving, and the firm offering the late reduction did so 2 months after the initial closing date, only, it appears, after determining from the preaward survey activity the identity of the intended awardee, so that the firm thus would enjoy a competitive advantage not contemplated by the normal procurement process if negotiations were held.

BIDS B-220380 N ~ v . 1, 1985 Responsiveness 85-2 CPD 506 Determination

On Basis of Bid as Submitted at Bid Opening

Bid on total small business set-aside rejected as nonresponsive because bidder indicated that not a l l supplies to be furnished will be the product of a small business concern may not be cured or defect waived as a minor informality since responsiveness must be determined from material available at bid opening and postopening explanations cannot be considered to correct a nonresponsive b i d .

n-4

!

i

!

i

i

I

Page 25: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

I

I

BIDS 6-220380 Con't Responsiveness Nov. I, 1985 Exception Taken to Invitation Terms

Small Business Requirements

Bid on total small business set-aside which indicates in the appropriate block that not all supplies to be furnished will be rhe product of a small business concern is not responsive and may not be considered for award because bidder would be free to furnish supplies from a large business and thus defeat the purpose of the set-aside.

CONTRACTS B-220400 NOV. 1, 1985 Protests 85-2 CPD 507 Authority to Consider Activities not Involving Federal Procurement

To be subject t o review by GAO under the Competition i n Contracting Act of 1984 , a protest must pertain t o a procurement of property o r services by a federal agency. A protest concerning a lease of government property therefore will not be considered, since a lease is a type of sale, n o t a procurement of property or services. Protests concerning sales will be reviewed by GAO only where the federal agency involved has agreed t o such review.

CONTRACTS B-220839 NOV. 1, 1985 Negotiation 85-2 CPD 508

Not Proper Basis to Prevent Award "Buying In"

Protest alleging that awardee submitted below-cost offer is dismissed. There is no legal basis to object t o a contract award solely because the awardee submitted a below-cost or "buy-in" offer.

i

I

I

D- 5

Page 26: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

!

BIDDEXS B-220857 NOV. 1, 1985 Qualifications 85-2 CPD 509 License Requirement

State, etc. Certifications

Where solicitation does not impose a specific license requirement, agency may make award without regard to whether bidder is licensed under local l a w .

coNpRBcToRs Responsibility Determination Review by GAO

Protest against awardee's ability to comply with solicitation requirements concerns matter of responsibility which GAO does not generally review.

!

i

LABOR DEPARTMENT Jurisdiction Service Contract Act Violations

Responsibility for administration and enforcement of the Service Contract Act is vested in the Department of Labor, not GAO.

CONTRACTS B-220891 NOW. 1, 1985 Protests 85-2 CPD 510

Basis for Protest Requirement

Where protester alleges that it should have been awarded the contract but fails to take any exception with the agency's evaluation of proposals, protest is properly dismissed for failure to state a basis €or protest.

D-6 !

i

!

!

i

r

I

Page 27: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

i

C O r n C T S B-220894 NOV. 1, 1985 Protests 85-2 CPD 511 General Accounting Office Procedures Timeliness of Protest Solicitation ImproprierIes Apparent Prior to Bid Opening/Closing Date for Proposals

Protest filed with GAO within 10 working days of agency's denial of protest i s untimely because it pertains to alleged defect i n invitation for bids and w a s not filed initially with the agency until after bid opening.

BIDDEBS B-218846 NOV. 4, 1985 Debarment Labor Stipulation Violations Davis-Bacon Act Wage Underpayments

Debarment Required

The Department of Labor recommended debarment of a subcontractor under the Davis-Bacon Act because the subcontractor had falsified certified payroll records and induced several of its employees to rebate substantial portions of their back wages. Based on o u r independent review of the record in this matter, we conclude that t h e subcontractor disregarded its obligations to its employees under the Act. There was a substantial violation of the A c t i n that the under- payment of employees and rebate inducement was intentional. Therefore, the subcontractor will be debarred under the A c t .

I

!

!

i

I

!

!

a- 7

I

!

i

Page 28: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

i

I BIDDERS 3-218861 Nova 4, 1985 Debarment

Labor Stipulation Violations Davis-Bacon Act Wage Underpayments Debarment Required

The Departmeat of Labor recommended debarment of a con- t r a c t o r under t h e Davis-Bacon A c t because t h e c o n t r a c - t o r had f a l s i f i e d c e r t i f i e d p a y r o l l r e c o r d s and forged employee r e c e i p t s . Based on o u r independent rev iew of t h e record i n t h i s matter, w e conclude t h a t t h e c o n t r a c t o r d i s r e g a r d e d i t s o b l i g a t i o n s t o i t s employees under t h e Act. There was a s u b s t a n t i a l v i o l a t i o n of t h e A c t i n t h a t t h e underpayment o f employees was i n t e n t i o n a l . T h e r e f o r e , t h e c o n t r a c t o r w i l l be debar red under t h e Act.

CONTRACTS B-219114.2 NOV. 4, 1985 Protests 85-2 CPD 515

General Accounting Office Procedures Timeliness of Coments on Agency's Report

Dismissa l of o r i g i n a l p r o t e s t f o r f a i l u r e t o f i l e w r i t t e n comments on t h e agency r e p o r t w i t h i n 7 working days o f t h e due d a t e f o r d e l i v e r y of t h e r e p o r t t o GAO and t o t h e p r o t e s t e r i s a f f i r m e d . Notwithstanding t h e p r o t e s t e r ' s a s s e r t i o n t h a t it r e c e i v e d t h e r e p o r t l a t e , t h e p r o t e s t e r f a i l e d i n i ts d u t y t o n o t i f y GAO t h a t i t had n o t r e c e i v e d t h e r e p o r t by t h e due d a t e .

CONTRACTS B-219327-6 NOV. 4, 1985 Protests 85-2 CPD 516 Contract Administration Not for Resolution by GAO

Whether t h e awardee a c t u a l l y performs t h e c o n t r a c t i n accordance w i t h t h e terms of t h e s o l i c i t a t i o n i s a matter of c o n t r a c t a d m i n l s t r a t i o n which i s n o t f o r GAO c o n s i d e r a t i o n .

i

I

!

!

i

I

I

!

I

i

D 8

i

i I

!

i

!

I

!

Page 29: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

I

I

CONTRACTS B-219327.6 Coa't Protests Nov. 4, 1985 General Accounting Office Procedures Timeliness of Protest Solicitation Improprieties Apparent Prior to Bid Opening/Closing Date for Proposals

Protest alleging improprieties in an invitation for bids is untimely and will not be considered on the merits where the protest was n o t filed with GAO prior to bid opening.

CONTRACTS S-219469 Nova 4, 1985 Negotiation 85-2 CPD 517 Awards Propriety Technical Superiority-Paramount Consideration

Where the solicitation advises offerors that technical considerations are of paramount importance, acceptance of the highest technically rated proposal that offers 3,000 more hours of effort was reasonable notwithstanding protester's proposed lower cos t .

CONTRACTS Negotiation Offers or Proposals Evaluation Cost Realism Analysis Reasonableness

Cost realism analysis is not subject to objection where the procuring agency's analysis indicates that an offeror's proposed costs compare favorably with the agency's estimate and are based on pay grades that relate most directly t o the work described in the soliciration, and the protester has n o t shown that such an analysis is unreasonable.

I

I

I

I

i

!

!

!

0-9

!

!

I

I

Page 30: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

!

I

CONTRACTS B-219469 COU'~ Negotiation Nov. 4, 1985 Requests for Proposals

Amendment

Where amendment increases level of effort i n solicitation, without correspondingly increasing the estimated number of staff hours, offeror reasonably was on notice t h a t increased number of staff hours would be required. Furthermore, offeror was advised during discussions of concern that its staff hours were low.

CONTRACTS B-219636 NOV. 4, 1985 Negotiation 85-2 CPD 518

Offers or Proposals Evaluation Administrative Discretion Cost/Pricing Evaluation

GAO finds no basis to question the Army's evaluation of awardee's proposal concerning costs associated with awardee's performance schedule where Army adjusted upward awardee's performance costs to cover initial performance period which awardee failed to adequately cost.

CONTRACTS Negotiation

Offers or Proposals Evaluation Personnel

Based QII review of record, GAQ cannot question the Army's position that there is no merit i n the protester's allegations about the awardee's compliance with the RFP's staffing and manning requirements.

I

!

i

I

!

I

I

i

!

!

i

i I

!

!

I I

!

D - 1 0 !

!

!

!

I

!

Page 31: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

!

CONPRACTS B-219636 Con't Protests M v - 4, 1985 Allegations Speculative

GAO rejects as speculative protester's assertion that projected cos t of "portal-to-portal" pay should be added to cost of awardee's proposal where protester is not currently obligated t o pay "portal-to-portal" compensation to contract employees.

CONTRACTS Protests Conflict in Statements of Protester and Contracting Agency

Contrary t o protester's allegation, Army did consider possibility that awardee would be less than successful in recruiting the incumbent contractor's work force as awardee proposed and, consequently, made a cost adjustment t o the protester's proposal.

CONTRACTS Protests General Accounting Office Function

Scope of Review of Agency Actions

Protest that contracting agency refused t o provide protester with access to certain' documents for the development of its protest is denied. The contracting agency has the primary responsibility for determinhg which documents are subject to release under the Competition i n Contracting A c t of 1984, Pub. L. 98-369, § 2741(a), 98 Stat. 1175, 1199-1203.

FREEDOM OF INFORMATION ACT Disclosure Requests Records of Agencies, etc., Other Than GAO Authority of GAO to Require Disclosure

GAO has no authority under the Freedom of Information A c t , 5 U . S . C . 5 552 (1982), to determine what information agencies must disclose under the act.

D -11

!

!

i

!

!

!

!

i

!

!

!

!

!

!

I

!

!

!

!

r !

!

I

i

!

!

!

!

i

Page 32: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

I

!

CONTRACTS Negotiation Offers or Proposals Preparation Costs Denied

B-219988.4 NOV- 4, 1985 85-2 CPD 519

Recovery of proposal preparation costs and the costs of pursuing a protest is inappropriate where the remedy afforded the protester is the opportunity to compete in the procurement.

CONTRACTS B-220180 NOV. 4, 1985 Protests 85-2 CPD 520 General Accounting Office Procedures Timeliness of Protest Date Basis of Protest Made Known to Protester

Protest based on agency's failure to provide sufficient information for the submission of a proposal is untimely where the protest is not filed within 10 days after the c l o s i n g date.

Protest concerning the evaluation of the protester's equipment must be filed no later than 10 days after the basis of the protest is known or should have been known, whichever Ls earlier.

CONTRACTS B-220390 NOV. 4, 1985 Protests 85-2 CPD 521 Interested Party Requirement Direct Interest Criterion

Protester who did not bid is not an interested party under GAO's Bid Protest Regulations because protester's interest as a supplier to dealer who bid on IFB is too remote.

i

I

!

I

!

i i

!

!

!

I

!

!

!

I

!

I

I

D-12

!

f !

!

!

!

I

!

!

I

!

!

Page 33: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

coNTRBcmRs B-220406 Mv. 4, 1985 Responsibility 85-2 CPD 522 Determination

R e v i e w by GAO Affirmative Finding A c c e p t e d

GAO will not review a challenge to a contracting agency's affirmative responsibility determination where there is no allegation or showing that the contracting officials acted fraudulently o r in bad faith or that the solicitation contained definitive responsibility criteria that have not been m e t .

CONTRACTS Protests Basis for Protest Requirement

Protester's disagreement with the contracting agency's evaluation of the relative merits of the protester's and the awardee's proposals is not a basis on which to challenge award of the contract where the protester does not: contend that the agency improperly applied the evaluation criteria in the solicitation o r otherwise violated applicable procurement laws o r regulations.

CONTRACTS B-220693 Nov. 4, 1985 Protests 85-2 CPD 523 Moot, A c a d e m i c , etc. Questions Contract Terminated for Convenience

Protest is academic where the protester, the third-low offeror, argues that the awardee's equipment does not comply with Specifications, but the contracting agency has terminated the award on other grounds and proposes to make award to the second-low offeror, whose ability to meet specifications the protester has not challenged.

I

i

!

I

f

I

!

I

I

f

I

i

D-13

I

Page 34: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

i I

CONTRACTS B-218567.2 WOV. 5, 1985 Negotiation 85-2 CPD 524 Offers or Proposals Best and Final Additional Rounds

There is nothing wrong with requesting more than one round of best and f i n a l o f fe rs where a valid reason exists to do so. Where an otherwise strong proposal needs some revision, reopening discussions to permit such revisions does not constitute technical leveling.

CONTRACTS Negotiation Offers or Proposals Evaluation

Technical Acceptability Administrative Determination

Contracting agency reasonably declined to f i n d proposal technically unacceptable where the proposal of fe red personnel already committed to performing other contracts who could be made available with the agency's approval under the other contracts.

CONTRACTS Protests General Accounting Office Procedures Timeliness of Protest Solicitation Improprieties Apparent Prior to Bid Opening/Closing Date for Proposals

Protest that request f o r best and f i n a l offers, after the contracting agency d i sc losed the percentage cost differential between offers, constituted an auction is untimely where filed after the closing date f o r the receipt of b e s t and final offers.

!

!

i

I

I

i

r

j

I

!

f

I

!

!

!

!

I

!

I

Page 35: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

I

!

I

BIDDERS B-218848 NOV. 5 , 1985 Debarment

Labor Stipulation Violations Davis-Bacon A c t Subcontractors Debarment Unwarranted

The Department of Labor stated that, in view of the circumstances, it did not consider further administra- rive action (i.e., debarment) necessary against a sub- contractor for violations of the Davis-Bacon Act. Based on our independent review of the record, we con- clude that the subcontractor underpaid employees, but the record does not contain sufficient evidence of intentional--as opposed t o inadvertent--violation of the labor standards provisions of the Act t o warrant debarment. Therefore, t h e subcontractor will not be debarred under the A c t .

-

BIDDERS B-218855 NOV. 5, 1985 Debarment Labor Stipulation Violations Davis-Bacon A c t

Subcontractors Debarment Unwarranted

The Department of Labor stated that, in view of the circumstances, it was taking no further action (i.e., debarment) against a subcontractor f o r violations of the Davis-Bacon Act. Based on our independent review of the record, w e conclude that t h e subcontractor underpaid the employees, but that the underpayments appear t o be the result of inadvertence caused by ignorance or misunderstanding of the law on the part of the subcontractor and managerial. difficulties of the subcontractor due to i ts President's major surgery and related mental strain. The record does not contain any evidence of willful violation of the Davis-Bacon Act. Therefore, the subcontractor will not be debarred under the Act.

I

I

I

i

!

!

I

I

D-15

!

I

!

I

I

I

!

Page 36: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

I

BIDS B-219648 NOV. 5 , 1985 Responsiveness 85-2 CPD 525 Failure to Furnish Something Required

Informat ion Small Business Concerns End Product Contributor

Telegraphic bid f o r the supply of canned vegetables, submitted in response to total small business set-aside solicitation, which bid stated with reEerence to offered prices and delivery schedule "All above subj.

American processed . . ." f a i l e d to unequivocally represent that bidder would f u r n i s h products produced by small business concern and, therefore, properly w a s rejected as nonresponsive.

to terms and conditions [of solicitation]. 100%

CONTRACTS B-219766 N o v a 5 , 1985 Negotiation 85-2 CPD 526 Requests for Proposals

Minimum Needs Specif icatioas

Not Overstated

Agency's specifications for sweepers with scrubber attachment and electromagnetic interference control are not unduly restrictive of competition where the agency presents a reasonable explanation f o r its minimum needs and t h e protester fails to show that the restrictions are unreasonable.

CONTRACTS Negotiation Requests for Proposals Specifications Restrictive Conformability of Equipment, etc. Offered Administrative Determination

Solicitation requirement chat offered equipment have Underwriters Laboratories Inc. seal of approval attached to each sweeper unit is unduly restrictive of competition and, therefore, improper.

I

I

i

I

I

f

I

I

I

I

I

I

f

I

D-16 !

I

!

Page 37: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

I

I

CONTRACTS B-220824 HQV. 5, 1985 Protests 85-2 CPD 527 Basis for Protest Requirement

I

Protest is dismissed fo r failure to set forth a detailed statement o f the legal and factual grounds of protest where t h e protester merely says that it submitted the best p r o p o s a l and that the agency's evaluation was not fair and equitable, but provides no supporting details.

CONTRACTS Protests General Accouutfng Office Procedures Timeliness of Protest

Debrtef ing Coaf erences Issues Providing Protest Basis

In light of t h e requirement of the Competition in Contracting A c t of 1984 that a n agency suspend performance of a contract i f it receives notice of a protest within 10 days of t h e date of the contract award, GAO recommends that the Federal Acquisition Regulation be revised to require agencies t o schedule post-award debriefings of unsuccessful offerors as soon after award as possible, so that if basis for protest exists, it can be learned in time to permLt protester to have the benefit of suspension of performance requirement.

!

i

I

!

I

I

!

!

!

!

CONTRACTS 8-220935 NQV. 6, 1985 Small Business Concerns Awards Small Business Administration's Authority Size Determination

i

GAO will not consider a protest of a bidder's small business size status because the Small Business Administration has conclusive authority t o determine size status.

I

I

!

I

D-17

I

!

!

!

!

Page 38: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

GENERAL ACCOUNTING OFFICE B-220935 Con't Jurisdiction Nov. 6, 1985

Conflict of Interest Statutes

Protest that award to a firm that employs a former officer of the U n i t e d S ta tes Army will result i n a violation of the Ethics i n Government Act of 1978 (18 U . S . C . 5 207) and is improper provides no basis for objection by GAO in the absence of any evidence suggesting that the former officer exerted any improper influence on the award.

CONTRACTS B-220968 Novo 6, 1985 Small Susiness Concerns 85-2 CPD 528 Avards

Responsibi l i ty Determination Nonresponsibility Finding

Review by GAO

GAO generally will not review a contracting officer's determination of nonresponsibility with respect t o a small business bidder since by law the Small Business Administration is empowered t o determine conclusively whether a small business firm is responsible.

BIDS B-219107.2 NOV. 7, 1985 Preparation 85-2 CPD 529

Costs Noncompensable

Claim for bid preparation costs is denied where the protester was n o t In line f o r contract award because its b i d exceeded the available funds f o r award.

D-18

I

!

I

I

!

I

i

I

!

I

Page 39: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

!

!

BIDS B-219107.2 Con't Preparation Nov. 7, 1985

Costs Noncompensable Protester not in Line for Award

Claim for bid preparation costs filed by the second low bidder, in comments submitted as an interested party, is denied since it was the protester's utilization of the bid protest process that revealed the procurement deficiency in the case, and the second low bidder would not be in line for contract award i n any event.

CONTRACTS Protests Preparation

Costs Noncompensable

Claim for the costs of filing and pursuing the protest, including attorney's fees, is granted where the protester has been prevented from having a fair opportunity to compete. It is apparent that if the agency had acted properly and promptly forwarded the protester's size status protest to the SBA, the solicitation would have been canceled and the requirement resolic i ted . CONTRACTS

Small Business Concerns Size Status Protests Mandatory Referral to Small Business Administration

When a size protest is filed with the contracting officer before award of a contract under a small business set-aside, he must promptly forward that protest t o the Small Business Administration (SEA). The Federal Acquisition Regulation contains no exceptions t o this requirement, and the fact that the contracting officer believes that the protest lacks sufficient evidence to be valid does n o t provide a reasonable basis for his failure to forward the protest promptly to SBA. D-19

!

!

i

!

!

!

!

i

!

f

!

!

!

!

f

!

!

!

!

!

!

!

Page 40: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

!

CONTRACMRS B-219449 NOV. 8 , 1985 Responsibility 85-2 CPD 530 Administrative Determination Nonrespoasibility Finding Supported by Record

Contracting agency reasonably determined that bidder was nonresponsible based on Department of Labor letter advising agency that the offeror underpaid employees under 11 contracts awarded over a recent 1-year period.

CONTRACTS Protests

Burden of Proof On Protester

Evidence does not prove agreement between contracting agency and Small Business Administration (SBA) t o extend the stipulated time period for SBA to issue a certiflcate of competency (COC) where contracting agency merely did not object to SBA's advice that it was holding t h e matter in abeyance while attempting to obtain more information.

CONTRACTS Small Business Concerns Awards Responsibility Determination Nonrespoasibility Finding

R e v i e w by GAO

Where the Small Business Administration does not act on a nonresponsibility referral because it believed it needed additional information from another agency, so that bidder did not obtain a review of the nonresponsibility determination, GAO will review the determination.

D-20

!

!

!

!

!

!

I

!

!

!

!

!

!

!

!

!

!

!

!

r

Page 41: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

I

I

CONTRACTS B-219618 NOV. 8, 1985 Negotiation 85-2 CPD 531 Late Proposals or Quotations

Rejection Propriety

Protest that agency should not have rejected protester's proposal as a late proposal i s denied. Where the protester has only offered the commercial courier's receipts (which are either disclaimed by the agency official who allegedly signed them or which appear to have been altered by someone after the agency official signed them) and where other circumstances i n d i c a t e that the proposal was received late, the protester has failed t o carry the burden of affirmatively proving that the proposal was timely submitted.

CONTRACTORS B-220071 NOV. 8, 1985 Responsibility 85-2 CPD 532 Determination

Review by GAO Nonrespoosibility Finding

An agency may properly determine a bidder to be nonresponsible and reject a bid based on a finding that the bidder's individual sureties on a bid bond are unacceptable because they failed to disclose outstanding bond obligations on their Affidavits of Individual Surety.

BIDS B-220199.2 Nov. 8 , 1985 Invitation for Bids 85-2 CPD 533 Amendment Failure to Acknowledge

Bid Nonresponsive

Where a protester does not allege the existence of limited circumstances under which the protest e r ' s failure to acknowledge a solicitation amendment incorporating minimum wage determinations under the Service Contract Act may be corrected, the protester's bid must be viewed as having been properly rejected since such a failure generally renders the bid nonresponsive.

D-21

I

I ! !

i i c !

i !

r

I

(

I ! ! !

I

I

i

!

!

I

I

I

I

I

I

!

I

I

I

I

Page 42: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

!

I

BIDS 6-220374 NOV. 8, 1985 Responsiveness 85-2 CPD 534 UR What Constitutes

Apparent low bid which took no exception t o specifications is not nonresponsive because of a letter the bidder sent to the agency after bid opening indicating an inability to comply with the solicitation's Underwriters Laboratories listing requirement because bid responslveness is determined as of bid opening and thus letter was relevant only to the issue of bidder responsibility, n o t responsiveness.

EQUIPELENT 8-219508 NOV. 12, 1985 Automated Data Processing 85-2 CPD 535 Systems Acquisition, etc . Competitive Procedures v. Federal Supply Schedule Utilization

3

Protest is sustained where, due t o procuring activity's failure to synopsize a procurement in the Commerce Business Daily in complfance with regulatory requirements for procuring telecommunications equipment from a General Services Administration nonmandatory Federal Supply Schedule contract, protester was unreasonably excluded from an opportunity t o compete.

CONTRACTS B-219654 NOV. 12, 1985 Small Business Concerns 85-2 CPD 536 Awards Responsibility Determination Nonresponsibility Finding Certificate of Competency on Recent Procurement--Resubmission to SBA not Required

Where the Small Business Administration (SBA) declines to issue a certificate of competency (COC) on one procurement, and for similar reasons the contracting officer finds the same company nonresponsible on another procurement shortly before SEA'S action, the nonresponsibility determination on the other second procurement may be considered to have been in essence ratified by SBA even though there was no referral f o r COC consideration.

D-22

I

I

I

i I

I

I

I

!

I

i

Page 43: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

!

CONTRACTS B-219654 Con' t Small Business Concerns Nov. 12, 1985 Awards Responsibility Determination Nonrespoasibility Finding Referral to SBA for COC Mandatory Without Except ion

Since section 401 of the Small Business and Federal Procurement Competition Enhancement Act of 1984 prohibits any exemption from the requirement for referral of small business nonresponsibility determinations t o the Small Business Administration ( S B A ) , exemption is no longer available for small purchase procedure procurements, so that a nonresponsibility determination thereunder must be referred t o SBA for review under the certificate of competency procedures.

CONTRACTS B-220013 NOV. 12, 1985 Negotiation 85-2 CPD 537 Offers or Plroposals Evaluation Administrative Discretion Cost/Pricing Evaluation

Cost evaluation of proposals conducted by an agency under the authority of the Arsenal Statute, 10 U.S.C. s 4532(a) (1982), for the purpose of determining whether supplies can be obtained from government-owned, contractor-operated (GOCO) factories on an economical basis may be made by comparing cost proposals of contractor-owned and -operated plants with out-of- pocket cost proposals of GOCO contractors which exclude those costs that would be incurred by the GOCO contrac- tors whether or not a particular contract i s awarded to a GOCO plant.

D-23

i !

I

!

!

!

!

i I

!

I

I

!

f

I

!

!

Page 44: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

I

CONTRACTS B-220141 NOV- 12, 1985 Protests 8 5 2 CPD 538 Interested Party Requirement Protester not in Line for Award

A protester challenging the government's estimates of the costs to be added t o bids for evaluation purposes, in order to equalize the competition between bids for laundry services to be performed in GOCO or COCO facilities, is not an interested party where the protester would not be in line for award even if the bids had been evaluated using the costs the protester contends reflect the government's true c o s t s .

BIDS B-220174 NOV. 12, 1985 Invitation for Bids 85-2 CPD 539 Specifications Brand Name or Equal Salient Characteristics Conformability Requirement

Salient characteristics listed in brand name or equal description are presumed t o have been regarded as material and essential t o the agency's needs.

I

I

i !

I

I

i I

I

!

!

BIDS Invitation for Bids Specifications Minimum Needs Requirement Administrative Determination Reasonableness

In the absence of evidence clearly establishing a substantial adverse impact on competition, GAO will not object t o an agency's use of minimum manning or equipment requirements to ensure adequate service.

D-24

I

I

!

I

i

Page 45: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

!

BIDS B-220174 Con't Invitation for Bids Nov. 12, 1985 Specifications Restrictive Burden of Proving Undue Restriction

Protest that requirement for full-time (versus part-time) workers is unduly restrictive is denied where the agency has supported the requirement and the protester has failed to show that the requirement is improper or clearly unreasonable.

CONTRACTS Protests

Moot, Academic, etc. Questions Corrective Action Proposed, Taken, etc. by Agency

Protest allegations are academic and not for consideration by GAO where agency modifies the challenged solicitation provisions as the protester requests.

CONTRACTS B-220680.2 NOV. 12, 1985 Protests

General Accounting Office Procedures Reconsideration Requests Error of Fact or Law Not Established

Original decision dismissing a protest as untimely is affirmed where request for reconsideration confirms the fact that the initial protest t o the agency, based upon an alleged impropriety i n an amendment, was not filed until 11 calendar days after the extended closing date for receipt of proposals.

D- 25

!

i !

i

I

!

i !

!

Y

Page 46: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

!

CONTRACTS B-220717.2 NOV. 12, 1985 Prores ts 85-2 CPD 540 General Accounting Office Procedures Reconsideration Requests

Error of Fact or Law Not Established

Dismissal of protest is affirmed where request for reconsideration does not establish that the decision was based on error of law or fact.

CONTRACTS B-220731.2 NOV. 12, 1985 Protests 85-2 CPD 541 General Accounting Office Procedures

F i l i n g Protest With Agency

Dismissal of original protest for failure to file a copy of the prorest with the contracting officer within 1 day after filing with GAO is affirmed where the agency had not recefved a copy of the protest 2 weeks after the protest was filed with GAO.

Protesters must comply with requirement to furnish a copy of a protest filed with GAO to the contracting agency where a de novo review i s requested of a previous agency protest decision.

- -

GENERAL ACCOUNTING OFFICE 8-220800.2 NOV. 12, 1985 Jurisdiction 85-2 CPD 542 Labor Stipulations Wage Determinations

Prior dismissal of protest concerning wage rates inc luded in solicitation is affirmed since GAO does not review wage determinations issued by the Department of Labor, rather, the challenge should be pursued through Labor's administrative review process.

!

I

!

f

I

!

c

D-26

!

Page 47: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

FEDERAL ACQUISITION REGULATION B-220819 NOV. 12, 1985 Proposed Revision

GAO has no objection to a proposal t o add paragraph (n) to Federal Acquisition Regulation s 31.205-6 stating that rebates and purchase discounts granted by a government contractor to its employees on products or services produced by the contractor are unallowable.

BIDDERS B-220905 NOV. 12, 1985 Invitation Right 85-2 CPD 543 Failure to Sol i c i t Blds Cancellation of Invitation not Required

Failure to provide potential bidder, even incumbent contractor, with copy of solicitation does n o t require resolicitation where protester h a s not shown that procuring agency deliberately or consciously precluded protester f r o m competing, neglected to seek adequate competition, o r failed to o b r a i n reasonable prices.

CONTRACTS B-218622.4 NOV. 13, 1985 Negotiation Offers or Proposals Preparation

Costs Denied

GAO affirms prior decision that protester was not entitled to proposal preparation cos ts since request f o r proposals (RFP) under which offerors competed was defective such that no award could properly be made. In this circumstance, claim musr be denied since legal standard f o r payment of these costs requires that claimant have a substantial chance of receiving a proper award--a standard which the claimant cou ld not meet under this RFP.

I

I

i

I

I

i Y

D-27

Page 48: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

BIDS B-219448.3 NOV. 13, 1985 Invitation for Bids 85-2 CPD 544 Cancellation After Bid Opening Low Bid i n Excess of Government Estimate

Contracting agency1$ rejection o f sole bid on the basis of unreasonable price, resulting in cancellation of the solicitation, was proper when the bid price was significantly higher than the government's estimate and the record discloses no fraud OK bad faith on the part of the contracting agency in making its determination.

CONTRACTS B-219541.2 N~v. 13, 1985 Federal Supply Schedule

Awards P r o p i e t y

Order Limitation Ekceeded

Agency cannot refuse to compete its software requirements on the basis of a determination that its preferred contractor can best meet its needs without f i r s t permitting the protester to submit a formal proposa l in response to a written solicitation setting forth the government's functional needs.

CONTRACTS Protests General Accountlug Office Procedures Reconsideration Requests

Error of Fact or Law N o t Established

Reversal of prior decision is not warranted where request for reconsideration fndicates it is based on misinterpretation of that decision. Contrary to the agency's belief, decision did n o t hold that government may not impose reasonable requirements to assure that offerors propose integrated software design approaches, nor is the agency precluded from acquiring data base management software separately.

D-28

Y

I

I

i

I

I

I

I

i I

I

Y

Page 49: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

I

CONTRACTS 8-219601 NOV. 13, 1985 Negotiation 85-2 CPD 546 Awards

Not Prejudicial to Other Offerars

Although proposal for portable computers having one hard d i s k and one f loppy disk d r i v e deviated from specification requiring that portable units have at least two floppy d i s k drives, acceptance of the proposal did not prejudice competing offeror because hard d i s k drives are generally more expensive to offer and furnish than f l o p p y disk drives and the units proposed did meet agency's actual needs.

CONTRACTS frot es t s Allegations

Unsubstantiated

Protest alleging an o f f e r o r ' s noncompliance with mandatory technical requirements is without merit where the record shows that the successful technical proposal was reasonably evaluated by the agency as meeting the requirements.

CONTRACTS Protests General Accounting O f f i c e Procedures

Piecemeal Development of Issues by Protester

Where a protester raises a broad ground of protest in its initial submission but fails t o provide any detail on this protest ground until it files I t s conference comments subsequent t o its receipt of the agency report, so that a further response from the agency would be needed for a n objective review of the matter, the matter will not be considered because protests may not b e filed in piecemeal fashion.

I

I

D-29 I

I

i

Page 50: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

!

!

C O r n C T S B-219601 COQ't

General Accounting Office Procedures Protests N o v a 13, 1985

Timeliness of Colnments on Agency's Report

Where a p r o t e s t e r f i r s t raises p r o t e s t i s s u e s i n i t s c o n f e r e n c e comments t h a t are based on material f i r s t r e v e a l e d by t h e agency i n i t s r e p o r t on t h e p r o t e s t , GAO w i l l c o n s i d e r these i s s u e s as newly f i l e d p r o t e s t s .

BIDDERS 8-219699 NOV. 13, 1985 Debarment

Labor Stipulation Violations Davis-Bacon Act Wage Underpayments Debarment Required

The Departrnenr of Labor recommended debarment of a prime c o n t r a c t o r and c e r t a i n o f i t s o f f i c e r s and c o n t r o l l i n g employees under t h e Davis-Bacon A c t because of underpayment of wages t o i t s employees and f a l s i f i c a t i o n of c e r t i f i e d p a y r o l l r e c o r d s . Based on o u r independent r e v i e w o f t h e record i n t h i s matter, we f i n d t h a t there was s u b s t a n t i a l v i o l a t i o n of t h e A c t i n t h a t t h e underpayment of wages w a s i n t e n t i o n a l . We conclude t h a t t h e c o n t r a c t o r d i s r e g a r d e d i t s o b l i g a t i o n s t o its employees. Theref o r e , t h e c o n t r a c t o r and t h e named i n d i v i d u a l s w i l l be deba r red under t h e Act.

BIDS 8-219926.2 NOV. 13, 1985 Invitation for Bids 85-2 CPD 547 Cancellation After Bid Opening Defective Solicitation

Agency h a s a compe l l ing r e a s o n t o t e r m i n a t e a p r o t e s t e d c o n t r a c t and t o c a n c e l the u n d e r l y i n g i n v i t a t i o n f o r b i d s f o r r e f r i g e r a t e d produce c a s e s when s p e c i f i c a t i o n s are i n a d e q u a t e i n n o t s t a t i n g t h a t t h e s h e l v e s must be a d j u s t a b l e and removable and when i t does n o t appea r t h a t an award t o t he p r o t e s t e r under t h e o r i g i n a l s o l i c i t a t i o n would meet i t s needs.

D-30

I

!

!

!

i I

I I

!

i

!

!

I

!

!

!

i

Page 51: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTS B-219926.2 Coa't Protests Nav. 13, 1985 Hoot, Academic, etc. Questions

Contract Terminated for Convenience

Protest against rejection of a bid as nonresponsive i s academic where agency terminates a contract f o r the convenience of the government because the underlying invitation f o r b i d s contains inadequate specifications.

BIDS B-220034 NOV. 13, 1985 Competitive System 85-2 CPD 548 Preservation of System's Integrity Pecuniary Disadvantage to Government

A nonresponsive b i d may not be accepted even though it would result in monetary savings to the government since acceptance would be contrary t o the maintenance of the integrity of the competitive b idd ing system.

BIDS Mistakes

Correc t ion Nonresponsive Bids

A nonresponsive b id may not be corrected through mistake-in-bid procedures.

BIDS Responsiveness Exceptions Taken to Invitation Terms

Bid m u s t b e rejected as nonresponsive when cover letter accompanying b i d includes standard commercial term disclaiming liability for consequential damages, since it deviates materially from t h e solicitation.

U-3 1

I

I

I

I

i

I

!

I

I

Page 52: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTS B-220278 NOV. 13, 1985 Protests 85-2 CPD 549 Interested Party Requirement Direct Interest Criterion

Consulting firm which is not a potential bidder is not an interested party under GAO's Bid Protest Procedures.

BIDS B-220354 NOV. 13, 1985 Evaluation 85-2 CPD 550 Discount PrOVfsiOUS Propriety of Evaluation

The Government Printing Oifice, whose procurement regulations permit the evaluation of oEfered prompt payment discounts in evaluating bids, properly reduced a bid offering an eligible prompt payment discount, thereby displacing a lower net bid, where the IFB incorporated by reference a provision that s u c h discounts would be considered.

CONTRACTORS B-220405 NOV. 13, 1985 Responsibility 85-2 CPD 551 Determination

R e v i e w by GAO Affirmative Finding Accepted

GAO does not review affirmative determination of prospective contractor's responsibility absent showing of possible fraud OK bad faith on the part of contracting officials or allegation that definitive responsibility criteria in solicitation were misapplied.

CONTRACTS 3-220410 NOV. 13, 1985 Protests 85-2 CPD 552

Suspended, Debarred, etc. Contractors Interested Party RequLrement

The General Accounting Office will not consider a protest filed by a debarred contractor because it is not an interested party since it i s ineligible to receive an award even if the protest were sustained.

D-32

I

!

!

!

!

I

!

!

!

I

Y

i

!

!

!

!

!

!

Page 53: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTS 8-220463 NOV. 13, 1985 Protests 85-2 CPD 553 Moot, Academic , etc. Questions Corrective Action Proposed, Taken, etc . by Agency

Protest by small business firm o€ agency's failure to submit the matter of protester's responsibility to the Small Business Administration (SBA) for a Certificate of Competency (COC) determination i s dismissed as academic because the agency has since referred the matter t o the SBA whose determination t o issue o r not issue the COC is final.

CONTRACTS B-220560 NOV. 13, 1985 Protests 85-2 CPD 554

General Accounting Office Procedures Filing Protest With Agency

Where agency knew the specific aspect of the procurement to which the protester objected in a protest at that level, subsequent protest t o GAO will not be dismissed on the basis that the actual agency-level filing was not sufficiently detailed.

CONTRACTS Small Business Concerns Awards Set-Asides Withdrawal

Propriety

GAO will n o t object to a contracting officer's pre-bid-opening decision t o withdraw a small business set-aside and issue the solicitation on an unrestricted basis where the record does not show the o f f i c i a l abused h i s discretion i n determining that offers from at least two responsible small businesses could not reasonably be expected.

I

t

t

I

I

I

I

c t

I

I

D-33

I

Page 54: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTS 8-220672-2 NOW. 13, 1985 Protests General Accounting Office Procedures Reconsideration Requests Error of Fact or Law

N o t Established

Information which supplements original grounds of protest, but does not show that decision t o dismiss the p r o t e s t for failure t o file a copy of the protest with the contracting officer within 1 day after the protest was filed with GAO is erroneous, is not germane to request: far reconsideration of the dismissal.

CONTRACTS Protests General Accounting Office Procedures

Significant Issue Exception Timeliness of Protest

Nor for Application

The "good cause" and "significant issue" exceptions in section 21.2(c) o f our Bid Protest Regulations apply o n l y to protests which are untimely filed with GAO and not to protests timely filed, but otherwise deficient.

D-34

I

t

I

I

I

Y

I

I

I

I

I

Page 55: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTS B-217848 NOV. 1 4 , 1985 Labor Stipulations Davis-Bacon Act

Disputes Classification of Workmen

Contractor, on project covered by Davis-Bacon Act, requested creation of new wage classification and rate for use on project. In accordance with then existing regulations, after new classification was approved by contracting officer, notice of this new classification was forwarded f o r informational purposes to Department of Labor (DOL). Classification w a s disapproved by DOL, and contractor appealed unsuccessfully within DOL. Contractor then appealed to Board of Contract Appeals (BCA) which took jurisdiction under "Disputes Concerning Labor Standards" clause of contract. Decision of RCA held that DOL, under then existing regulations, could not overrule contracting officer's decision on new classification. Under S & E Contractors, Inc. v. United States, 406 U.S . 1 (1972), GAO may not rev€ew final BCA decisions rendered under "disputes" clause Therefore, contractor's use of classification was proper, there were no violations of Davis-Bacon Act, and funds withheld should be returned to contracting officer,

SWALL BUSINESS a-220387 NOV. 14, 1985 ADMINISTRATION 85-2 CPD 556

Contracts Contracting With Other Government Agencies Procurement Under 8(a) Program

R e v l e w by GAO

GAO will not review a contracting agency's decision to satisfy its requirement through a section 8(a) subcontract when a protester, arguing that the agency is acting in bad faith, fails t o provide sufficient evidence indicating that agency may be acting in bad faith.

!

i

I

I

f

I

!

I

I

i

I

Y

D-35

i

Page 56: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

!

CONTRACTS 6-220619 NOV. 14, 1985 Negotfation 85-2 CPD 557 Offers or Proposals Evaluation Administrative Discretion

In reviewing protests against allegedly improper evaluations, GAO will not substitute its judgment for that of the agency's evaluators, but rather will examine the record to determine whether the evaluators' judgments were reasonable and in accord with listed criteria, and whether there were any violations of procurement statutes and regulations. In camera review of source selection documents shows tharevaluation was fair and consistent with evaluation scheme in the solicitation.

CONTRACTS Negotiation

Offers or Proposals Evaluation Price Consideration

Price need n o t be considered where a proposal is properly rejected as technically unacceptable.

CONTRACTS 8-220065-2 NOV. 15, 1985 Protests 85-2 CPD 560

Moot, Academic, etc. Questions Solicitation Canceled

A protest of the agency's rejection of a proposal is dismissed as academic where the agency canceled the solicitation under which the proposal was submitted.

!

!

!

i

!

!

I

!

D-3 6

i

Page 57: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

BIDS B-220879 NOV. 15, 1985 Responsiveness 85-2 CPD 561 Failure to Furnish Something Required Affiliates Affidavit Waiver As Minor Informality

A bidder's failure t o furnish with its bid a list of affiliates is a minor informality which may be waived o r cured after bid opening. Regardless of solicitation provision to the contrary, the information does not affect bid responsiveness.

CONTRACTS Awards

Notice To Unsuccessful Bidders

Although the Federal Acquisition Regulation requires the contracting officer to notify unsuccessful bidders "promptly" of award, it does not specify a particular time. When a protest is without merit, the agency's alleged failure to notify the protester in time so that it can take advantage of statutory "stay" provisions does not prejudice the protester.

BIDDERS E-220963 NOV. 15, 1985 Invitation Right 85-2 CPD 562

Bidder Exclusion not Intended

The award of a contract is not improper merely because a contracting agency failed to solicit a potential bidder where there is no evidence that such failure resulted from a deliberate attempt on the part of the agency to exclude the potential bidder from the competition.

D-3 7

i

i

!

!

I

!

!

!

!

!

i

Page 58: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

!

i

i

B-220963 Con' t CONTRACTORS Responsibility Now. 15, 1985 Determination Review by GBO Affirmative Finding Accepted

GAO does not review affirmative determinatioas of responsibility except under limited circumstances not present here.

CONTRACTS B-219643 NOV. 18, 1985 Negotiation 85-2 CPD 563 Offers or Proposals

Best and Final Additional Rounds Denial Propriety

Contracting agency acts reasonably in refusing to reopen discussions with the protester after the receipt of best and final offers, even though the protester's proposal offers an apparent saving of $ 4 million, when the best and final introduces numerous deficiencies into a previously acceptable proposal and raises questions concerning the protester's ability to meet solicitation requirements.

CONTRACTS Negotiation Offers or Proposals

Best and Final Discussions Clarification - v. Reopening Negotiations

Although the deficiencies that the protester's best and final offer introduces into its proposal may be largely "informational" in nature, when their number and variety are great, it is not unreasonable for a contracting agency t o conclude that they cannot be corrected by means of "clarifications," but require the reopening of discussions.

D-38

i

!

!

i

i

!

I

!

!

i

i

i !

i !

!

t

!

I

!

i

!

Page 59: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

!

!

comms 8-219915 Nova 18, 1985 Negotiation 85-2 CPD 564

Offers or Proposals Best and Final Discussions Clarification I V. Reopening Negotiations

Protest that contracting agency held discussions with eventual awardee after best and final offers is denied where discussions which occurred more than 6 months after agency completed evaluation and recommended award were for the purpose of addressing issues raised in an administrative appeal contesting the agency's selection decision. There is no evidence in the record that proposed awardee was afforded any opportunity to revise its offer.

c o m m s Negotiation Offers or Proposals

Reasonable Evaluation

Protest alleging that awardee's offer should not have been found acceptable is dented since record establishes reasonable basis for agency's evaluation.

CONTRACTS Protests Burden of Proof On Protester

The protester has the burden of affirmatively proving bias or favoritism on the part of the procuring agency and where written record fails to demonstrate bias, the protester's allegations are t o be regarded as mere speculation.

D-39

I

i !

I

!

I

!

!

I

!

Page 60: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

i !

CONTRACTS 8-219915 Con't Protests Nov. 18, 1985

General Accounting Office Procedures Filing Protest With Agency

P r o t e s t e r ' s f a i l u r e t o f u r n i s h c o n t r a c t i n g o f f i c e r wi th a copy of i t s p r o t e s t t o GAO wi th in one day of its f i l i n g , as r equ i r ed by Bid P r o t e s t Regulat ions, w i l l not r e s u l t i n t h e d i smis sa l of t he p r o t e s t where t h e purpose of t h i s requirement i s o therwise s a t i s f i e d such as where p r o t e s t e r f i l e d a copy wi th t h e procuring agency 's headquar te rs which n o t i f i e d t h e c o n t r a c t i n g o f f i c e r t e l e p h o n i c a l l y of t h e p r o t e s t . Furthermore, the agency has not been prejudiced by the de l ay I n r ece iv ing a copy of t h e p r o t e s t s i n c e it f i l e d i t s r epor t i n a t imely matter.

CONTRACTS Protests General Accounting Office Procedures Timeliness of Protest Date Basis of Protest Made Known to Protester

Where doubt exists concerning t h e d a t e t h e p r o t e s t e r became aware of t h e b a s i s f o r p r o t e s t , doubt i s reso lved i n f avor of t h e p r o t e s t e r .

CONTRACTS Protests General Accounting Office Procedures Timeliness of Protest Solicitation Improprieties Apparent Prior to Bid Opening/Closing Date for Proposals

P r o t e s t a l l e g i n g t h a t lease s o l i c i t a t i o n was d e f e c t i v e s i n c e i t d i d n o t provide f o r adequate parking i s dismissed as unt imely s i n c e p r o t e s t w a s no t f i l e d u n t i l a f t e r t h e c l o s i n g d a t e f o r r e c e i p t of o f f e r s .

D-40

!

I

!

!

I

i

!

!

Page 61: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

I

CONTRACTS B-208159.3 N o v a 19, 1985 Protests Information Evaluation Sufficiency of Submitted Information

!

In r e sponse t o i n q u i r y conce rn ing GAO p o l i c y r e g a r d i n g supp lemen ta l submiss ions i n b i d p r o t e s t s , l e t t e r e x p l a i n s t h a t g e n e r a l l y , once t h e p r o t e s t e r ' s comments on t h e agency r e p o r t have been f i l e d , GAO ~ € 1 1 n o t c o n s i d e r supp lemen ta l submissions from e i t h e r p a r t y , a l t h o u g h i n a p p r o p r i a t e cases, GAO may r e q u e s t or c o n s i d e r Supplemental comments.

CONTRACTS B-219664.2 NOV. 19, 1985 Negotiation 85-2 CPD 565 Late Proposals and Quotations

C o n t r a c t o r ' s Responsibility for Delivery

Protester's handcarried proposal which was d e l i v e r e d 4 5 minu tes la te because power s u r g e s had i n t e r r u p t e d i t s word p r o c e s s i n g equipment p r o p e r l y w a s r e j e c t e d .

CONTRACTS Negotiation

Late Proposals and Quotations Rejection Propriety

A l a t e p r o p o s a l cannot be c o n s i d e r e d o n the b a s i s t h a t the p r o p o s a l may o f f e r t h e government c e r t a i n advan tages o v e r those proposa ls which have been t i m e l y r e c e i v e d .

I

I

I

!

I

D-41

I

Page 62: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

BIDDERS B-219695 N~v. 19, 1985 Debarment Labor Stipulation Violations Davis-Bacon Act Subcontractors Debarment Required

The Department of Labor recommended debarment of a subcontractor and certain of its officers under the Davis-Bacon Act because of underpayment of wages to its employees and falsification of certified payroll records. Based on our independent review of t h e record in t h i s matter, we find that: there was a substantial violation of the Act in that the underpayment of wages was intentional. We conclude that the subcontractor disregarded its obligations to its employees. Therefore, the subcontractor and the named individuals will be debarred under the Act.

I

CONTRACTS 8-219917 N~v. 19, 1985 Negotiation 85-2 CPD 566 Offers or Proposals

Exceptions Discussion With all Offerors Requirement

Offers not Within Competitive Range

Where protester's initial proposal was properly determined to be outside the competitive range, the agency was not obligated to enter into discussions with the protester regarding technical deficiencies in its proposal

D-42

I

I

I

I

I

Page 63: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTS B-219917 Con't Negotiation Nov. 19, 1985

Offers or Proposals Evaluation Competitive Range Exclusion Reasonableness

An agency's determination of whether a proposal is i n the competitive range i s a matter of agency discretion which will not be disturbed absent a clear showing that the determination lacked a reasonable basis o r was not consistent with the major evaluation criteria set forth i n the request for p r o p o s a l s . Based on the much higher technical evaluation scores of other proposals GAO will not disturb agency's decision to exclude the protester f rom the competitive range on the basis that it d i d n o t have any reasonable chance of belng selected for award.

CONTRACTS Negotiation Offers or Proposals

Evaluation Price Consideration

Once the protester's proposal was determined to be outside of the competitive range as a result o€ the technical evaluation o f its proposal, the potentially lower price which that offer might provide is irrelevant since an o f f e r n o t within the competitive range cannot be considered f o r award.

CONTRACTS Protests

Burden of Proof On Protester

Mere allegations by the protester do not meet its heavy burden of proof that t h e agency's decision to make award to another offeror was the result of bias o r bad faith on the part of t h e agency.

I

i

I

I

D-43

i

Page 64: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

i

CONTRACTS 8-219917 Con't Protests Nov. 19, 1985

Moot, Academic, etc. Questions

Protest on the basis that agency failed to advise protester of its right to file protest w i t h GAO is dismissed as academic where the protester timely f i l e d a protest with GAO.

CONTRACTS 8-220142 NOV. 19, 1985 Negotiation 85-2 CPD 567 Offers or Proposals Evaluation Competitive Range Exclusion Reasonableness

Protest agains t exclusion of proposal from competitive range i s denied where record shows agency's finding that offeror's technical proposal was unacceptable was reasonable.

CONTRACTS Negotiation

Offers or Proposals Evaluation Technical Acceptability Based on Content of Proposal

A technical evaluation must be based on information contained in the proposal and, consequently, information contained i n a preaward survey is n o t a substitute f o r information that should have been included in an offeror's technical proposal.

I

I

I

I

i

D-44

f

I

Page 65: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTS Negotiation Preavard Surveys Preparation

Costs

B-220142 Con' t Nov. 19, 1985

Protester's claim for costs incurred in participating i n preaward survey because protester subsequently was excluded from competitive range is denied where d e c i s i o n to conduct preaward survey has not been shown to be unreasonable. Consistent with customary agency procedure, contracting officer initiated preaward surveys on all offerors before establishing competitive range apparently t o avoid possibility of delay in making award because the preaward survey was noE completed.

CONTRACTS Protests Procedures

Information Disclosure

Protest that contracting agency refused to provide protester with access to certain documents for development of its protest is denied. The contracting agency has t h e primary responsibility €or determining which documents are subject to release under the Competition in Contracting Act of 1984.

CONTRACTS B-218730.4 NOV. 20, 1985 Protests 85-2 CPD 568

General Accounting Office Procedures Reconsideration Requests Error of Pact or Law

N o t Established

To be responsive, b i d submitted under total labor surplus area (LSA) set-aside must contain requisite certification that bidder will perform as an LSA. Arguments which are a reiteration of those previously considered i n deciding initial protest do n o t provide basis f o r reconsideration.

i

I

t

j

D-45

Page 66: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTS B-219575 NOV. 20, 1985 Protests 85-2 CPD 569

General Accounting O f f i c e Procedures Reconsideration Requests

Error of Fact or Law N o t Established

Original decision that protester unreasonably interpreted specification provision and that contracting agency, therefore, properly rejected its bid is affirmed where request for reconsideration does not demonstrate that decision was legally or factually incorrect. Fact that the specification provision was incorrectly punctuated does not mean that the specification was ambiguous.

BIDS B - 2 1 9 6 6 2 NOV. 20, 1985 Invitation for Bids 85-2 CPD 570 Specifications Minimum Needs Requirement Administrative Determination Reasonableness

I

Department of Energy regulations that implement an energy conservation program and establish uniform testing requirements for washers and dryers utilizing formulas that measure tub capacity in terms of cubic Eeet do not preclude manufacturers from rating tub capacity in terms of pounds of d r y weight. Therefore, specifications for washers and dryers having certain capacities expressed i n pounds o f dry weight are proper where protester has not shown them t o be unreasonable.

BIDS Invitation for Bids Specifications Restrictive

Solicitation requirement that washers and dryers for use in Air Force dormitories not be over 2 years o l d is not unduly restrictive where the agency reasonably determines that machines over 2 years old are inoperable more often than newer machines, and that, if machines are inoperable, enlisted personnel may be subject t o disciplinary action for failure to meet dress code.

D-46

Page 67: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTORS B-219872, et al. Hov. 20, 1985 Responsibility 85-2 CPD 571 Determination Review by GAO Nonresponsibility Finding

Nonresponsibility determination may be founded on contracting agency's reasonable perception of inadequate prior performance by a contractor even where the contractor disputes the agency's interpretation of the facts.

A contracting agency, lacking any firsthand experience with an o f f e r o r , may base i t s nonresponsibility determination concerning that offeror on a recent preaward survey conducted by another contracting agency.

CONTRACTS Negotiation Requests for Proposals Construction

Reading all Provisions Together Rule Presumption Against Conflict

Where solicitation defines unit for inspection of custodial services a s a thing to be inspected and also defines unit as an area of square meters, tasks which can be measured, such as f l o o r cleaning, would be hspected by area of square meters. In the case of a latrine, the unit is the thing to be inspected and not an area since latrines are not generally described in square meters.

D-47

Page 68: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTS B-219872, et al. Con't Negotiation Nov. 20, 1985 Requests for Proposals Specifications Adequacy Scope of Work-Sufficiency of Detail

Where contracting agency provides a general estimate of total floor area to be serviced under custodial services contract based on best information available, it is not required to break down the general estimate into specific estimates of different types of flooring.

CONTRACTS Protests

Contract Adminisrra t ion N o t for Resolution by GAO

Implementation of a valid random sampling inspection system is a matter of contract administration which GAO will leave to the reasonable judgment of the contracting agency.

CONTRACTS Protests Interested Party Requirement Noaresponsible Offeror

A nonresponsible offeror remains an interested party for purposes of a bid protest against alleged solicitation deficiences if success on the protest may result in cancellation and resolicitation.

FEDERAL ACQUISITION B-219923.2 NOV. 20, 1985 REGULATION Proposed Revision

GAO has no comments on proposed Federal Acquisition Regularfon (FAR) $ 5 27.409 and 27.410 and a proposed clause at FAR s 52.227-14 which prescribe procedures for reviewing, challenging and resolving disputes over a government contractor's restrictive markings on technical data required by contract to be delivered to the government.

D-48

Page 69: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTO~ B-220037 NOV. 20, 1985 Responsibility 85-2 CPD 572 Determination Reviev by GAO Affirmative Finding Accepted

Allegation that low bidder is affiliated with a debarred corporation constitutes a protest to an affirmative determination of responsihility which our Office ~ € 1 1 not review in the absence of a showing of fraud or bad faith on the pari of contracting officials OK a failure t o apply definitive criteria of responsibility.

CONTRACTING OFFICERS B-220152, 8-220152.2 Determinations Nov. 20, 1985

Administrative v. Judicial Matter Nonresponsibilfty 85-2 CPD 573

Procedural Dug Process Guarantees Bearing not Required

Since responsibility determinations are administrative i n nature, they do n o t require the procedural due process otherwise necessary in judicial proceedings, and a contracting officer may base a determination of nonresponsibility upon the evidence of record without affording bidders an opportunity to exp la in or otherwise defend against the evidence.

CONTRACTOBS Responsibility Administrative Determination

Accepted

Although the protester argues that specific evidence of unsatisfactory performance, financial irresponsibility, and failure to meet solicitation and certification requirements were due t o circumstances beyond its control o r were otherwise explainable, GAO finds that the contracting officer reasonably concluded otherwise in making a negative responsibility determination.

I

A

D-49

I

Page 70: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRArnRS B-220152; B-220152.2 Con't Besponsibilfty Now. 20, 1985

Determination Review by GAO Honresponsibilitp Finding

GAO will not question a contracting officer's nonresponsibility determination unless the protester can demonstrate bad faith, abuse of discretion, o r a l a c k of any reasonable basis for the determination.

C O N T R A r n ~ Responsibility Determination

R e v i e w by GAO Wonresponsibility Finding

Bad Faith Alleged

Where ,bad faith is alleged in connection with a contracting officer's nonresponsibility determination, t h e protester h a s the burden of affirmatively proving its case and unfair or prejudicial motives w i l l not be attributed t o procurement officials on the basis of inference or supposition.

CONTRACTS B-220545 NOV. 20, 1985 Small Business Concerns 85-2 CPD 575 Awards

Small Business Administration's Authority Certificate of Competency Conclusiveness

A s a general rule, GAO will not review a contracting officer's determination of a small business bidder's nonres ponsibil i t y since the Small Business Administration has statutory authority to determine conclusively whether a small business firm is responsible.

!

A

D-50

I !

A !

Page 71: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

BIDS 8-220570 MOV. 20, 1985 Invitation for Bids 85-2 CPD 576 Cancellation

After Bid Opening Insufficient Puading

Agency properly canceled a s o l i c i t a t i o n for sealed bids where i t determined that su f f i c i ent funds were not available to make an award.

CXlNTaAcTS B-220667.2 20, 1985 Protests 85-2 CPD 577

Hoot, Academic, etc. Questions Future Procurements

Protest that agency may not conduct a prospective reso l i c i ta t ion properly i s premature.

CONTRACTS Protests

H o o t , Academic, etc. Questions Solicitation Canceled

Protest against award of delivery order i s rendered academic by agency's cancellation of delivery order.

CONTRACTS Protests Preparation

Costs Noncompensable

Recovery of the costs of pursuing a protest i s inappropriate where t h e remedy afforded the protester i s t h e opportunity t o compete In t h e procurement.

D-5 1

I

1

I

Page 72: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

I

c o m m s 8-220918.2 NOV. 20, 1985 Protests 85-2 CPD 578 General Accounting Office Procedures

Adverse Agency Action Effect Timeliness of Protest

Interim Appeals to Agency-Effect on 10 Working Day GAO Filing Period

I

Adverse agency action on a protest f i l e d with the contracting agency, which begins t h e 10 working day period for filing a subsequent protest with GAO, is any action or inaction that is prejudicial to the protester’s position. The fact that a protester continues to pursue its complaint with the contracting agency after such action does not toll the 10-day period.

CONTRACTS B-221057 NOV. 20, 1985 Small Business Concerns 85-2 CPD 579 Auards

Small Business Administration’s Authority

Inapplicability of COC Procedures Certificate of Competency

Protest that contracting agency determined a small business concern’s proposal technically unacceptable without referring the matter to the Small Business Administration under its certificate of competency (COC) procedures fails t o s t a r e a valid basis for protest, since COC procedures do n o t apply to technical evaluations of proposals.

FEDERAL ACQUISITION B-216887 NOV. 21, 1985 REGULATION

Proposed Revision

GAO approves of a proposal to add a sentence to section 9.405(a) of the Federal Acquisition Regulation stating that debarred or suspended contractors are excluded from conducting business w i t h the government as agents or representatives of o t h e r contractors.

D-52

I

A

I

Page 73: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

comcTs 8-218766-2 NOV. 21, 1985 Protests 85-2 CPD 581 General Accounting Office Procedures Reconsideration Requests Error of Fact of Law Not Established

Request: for reconsideration of prior decision is denied where the request for reconsideration fails to provide any evidence or legal arguments t o show that the decision was erroneous.

c o m m B-219428.2; 3-219440.2 N~v. 21, 1985 Protests 85-2 CPD 582 General Accounriag Office Procedures Reconsideration Requests

Error of Fact or Law N o t Established

Requests for reconsideration are denied where protesters raise no new facts or legal arguments which were not previously considered while the initial protests were pending.

CONTRACTS B-219609 NOV. 21, 1985 Negotiation 85-2 CPD 583 Requests for Proposals Construction

Reading all Provisions Together Rule Presumption Against Conflict

Protest asserting that the agency misinterpreted the solicitation, and thus evaluated pricing incorrectly, is denied where the solicitation read as a whole and in a manner that gives effect to all its provisions supports the agency's position.

1

I

A

I

1

1

j

D-53

i

Page 74: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

I

BIDS B-219733 Nov. 21, 1985 Acceptance or Rejection 85-2 CPD 584

E f f e c t of Acceptance

When a bidder takes no exception to the requirements of the solicitation in its bid, acceptance of the bid obligates the bidder to perform i n accordance with the terms of the solicitation.

BIDS Responsiveness Test to Determine Unqualified Offer to Meet all Solicitation Terms

Where a bid as submitted does not propose a specific method of performance, the specifications do not require a specific method of performance, and the bid does not otherwise rake exception to solicitation requirements, protest challenging rejection o f bid as nonresponsive is sustained.

c o m c r s B-220000.2 Nov. 21, 1985 Protests 85-2 CPD 585 Basis for Protest Requirement

Protest that consists primarily of a series of questions about the conduct of the procurement which contain no specific allegations of improper conduct by the agency does not state any adequate legal basis f o r protest.

CONTRACTS Protests General Accounting Office Procedupes Timeliness of Protest Date Basis of Protest Hade Known to Protester

To the extent that a protest letter can be read as raising specific bases for protest, t h e issues raised are untimely, as the protest was not filed within 10 working days after the bases for protest were known.

D-5 4

I

I

I

I

Page 75: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

BIDS 8-220032 Nov. 21, 1985 Estimates of Government 85-2 CPD 586 Basis of Estimate

When soliciting for a requirements contract, an agency must base its estimated quantities on the best information available. There is no requirement, however, that these estimates be perfect.

BIDS Invitation for Bids Specif icarioas Adequacy

Allegations of vague or ambiguous solicitation provisions are rejected where requirements are stated clearly and those allegations are based on an unreasonable interpretation of the solicitation.

BIDS Invitation for Bids Specifications Minimum Needs Requirement Aduinistrative Determination Reasonableness

Conrracring agency has the primary responsibility for determining i ts minimum needs and drafting requirements that reElect those needs. We will not question an agency's assessment of its minimum needs where a protester fails to show that the agency's determination is unreasonable.

BIDS 8-220424 NOV. 21, 1985 Responsiveness 85-2 CPD 587

Failure t o Furnish Something Required Standard RepresentatLons and Certifications Waiver

As Minor Informality

Failure t o complete nonmaterial representations and certifications in a bid does not render the bid nonresponsive.

I

D-55

Page 76: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

i FEDERAL ACQUISITION 8-220943 NOV. 21, 1985 REGULATION

Proposed Revision

GAO has no o b j e c t i o n t o t h e proposed a d d i t i o n of F e d e r a l A c q u i s i t i o n Regula t ion (FAR) § 31.205-19(a)(5) t o t h e FAR'S c o n t r a c t c o s t p r i n c i p l e s which would state t h a t premiums € o r r e t r o a c t i v e o r backdated i n s u r a n c e w r i t t e n t o cover occurred and known losses are unal lowable.

BIDDERS E-218999 WOV. 22, 1985 Debarment Labor Stipulation Violations Davis-Bacon Act Wage Underpayments Debarment Required

The Department of Labor recommended debarment of a c o n t r a c t o r under t h e Davis-Bacon A c t because t h e c o n t r a c t o r had f a i l e d t o pay t h e minimum wages r e q u i r e d by t h e A c t and h a s f a l s i f i e d c e r t i f i e d p a y r o l l records . Based on our independent review of t h e record i n t h i s matter, w e conclude t h a t t h e c o n t r a c t o r d i s r e g a r d e d i t s o b l i g a t i o n t o its employees under t h e A c t . There was a s u b s t a n t i a l v i o l a t i o n o f t h e A c t in t h a t t h e underpayment of employees and f a l s i f i c a t i o n o f r e c o r d s was i n t e n t i o n a l . Therefore , t h e c o n t r a c t o r w i l l be debar red under t h e A c t .

CONTRACTS B-220080.2 NOV. 22, 1985 Pro tests 85-2 CPD 589

General Accounting Office Procedures Reconsideration Requests

Error of Fact or Law N o t Established

P r i o r d e c i s i o n is af f i rmed o n r e c o n s i d e r a t i o n s i n c e p r o t e s t e r has n o t shown any e r r o r s of law or f a c t which warran t reversal of t h a t d e c i s i o n .

I

I

D-56

A

A

Page 77: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

BIDS E-220162 NOV. 22, 1985 Competitive System 85-2 CPD 591 Preservation of System's Integrity Pecuniary Disadvantage to Government

A nonresponsive bid may not be accepted, notwithstanding any savings it might represent to the government, since such acceptance would compromise the integrity of the competitive bidding system.

BIDS Responsiveness Exceptions Taken to Invitation Terms

A bid that takes exception t o t h e packaging speciffcations of a solicitation is nonresponsive, since, in order to be considered responsive, a bid must be an unequivocal offer to provide the exact thing described in the invitation for bids, in total conformance with the material terms of the solicitation.

A b i d t h a t includes preprinted terms and conditlons that vary from t h e terms and conditions in the solicitation is nonresponsive.

CONTRACTS Protests General Accounting O f f i c e Procedures Timeliness of Protest Solicitation Improprieties Apparent Prior to Bid Opening/Closing Date for Proposals

Under GAO Bid Protest Regulations, a protest based upon improprieties in the terms of an invitation €or bids apparent on t h e face of t h e invitation must be filed prior t o bid opening.

I

I

I

D-5 7

i

I

Page 78: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

I

CONTRACTS B-220253 NOV. 22, 1985 Federal Supply Schedule 85-2 CPD 592 To Other Than Low Bidder or Offeror Justification

Protest against the issuance of a delivery order t o higher priced Federal Supply Schedule (FSS) contractor by protester with similar FSS contract is denied where the agency reasonably determined that awardee met agency’s needs and protester did not.

CONTRACTS Protests

Abandoned

Where agency rebuts an issue raised in the initial protest and the protester f a i l s to respond t o the agency’s rebuttal in its comments to the agency report, the issue is deemed abandoned.

BIDS E-220434.2 NOV, 22, 1985 Responsiveness 85-2 CPD 593

Brand Name or Equal Procurement

When the solicitation i n a ”brand name or equal” procurement requires that the bid specify the model number of the item t o be supplied, the bidder may not be permitted to supply the model number after bid opening since that would give the bidder the opportunity to make a nonresponsive bid responsive.

CONTRACTORS B-220683 Novo 22, 1985 Responsibility Determination Definitive Responsibility Criteria Compliance

As a matter of information to a member of Congress whose constituent’s protest would be untimely under the Bid Protest Regulations, GAO concludes that the Air Force acted properly in making award to a firm whose product has not received FDA approval, since this is a matter of responsibility and therefore the required authorlzation need only be obtained prior t o the scheduled start of performance.

D-58

I

I I

! !

A

A !

i I !

A I

R

I

f

Page 79: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTS 8-219423-2 NOV. 25, 1985 Negotiation 85-2 CPD 594 Determinations and Findings Basis for Negotiation

Although the Commandant of the Coast Guard was not statutorily empowered at the time to execute the Determination and Findings (D&F) authorizing the negotiation of a vessel modernization procurement, GAO finds no legal error in its conclusion that the D&F may properly be reexecuted now by the Secretary of Transportation if she agrees that the procurement should have been negotiated orlgtnally.

CONTRACTS F'rot es t s General Accounting Office Procedures Reconsideration Requests Error of Fact or Lav

Not Established

In order to prevail in a request f o r reconsideration of a prior decision, the requesting party must convincingly show either errors of fact or of law in the prior decision which warrant its reversal o r modification.

CONTRACTS B-220012 Nov- 25, 1985 Data, Rights, etc. 85-2 CPD 595 Disclosure

Prior t o Award No Evidence to Support Allegation

GAO will not recommend award to the protester rather than the low responsive bidder where the protester does not present clear and convincing evidence that the solicitation's specifications and drawings package is derived from proprietary technical data and drawings.

D-59

A I

I

r

Page 80: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTS B-220092, e t al. Nov. 25, 1985 Negotiation 85-2 CPD 596 Requests for Proposals

Minimum Needs Specifications

N o t Overstated

Allegation that solicitation does not represent agency's minimum needs is denied where protester fails t o establish that agency determination of its needs was unreasonable.

CONTRACTS Negotiation Requests for Proposals Specifications Restrictive Undue Restriction not Established

Protest that specifications for vibration analysis equipment are unduly restrictive is d e n i e d where restrictions imposed are reasonably related to the agency's actual needs.

c o m m s Negotiation Sole-Source Basis Administrative Determination Reasonable Basis

Sole-source awards based on safety considerations and urgency to satisfy agency's interim requirement pending the completion of competitive acquisition are not unreasonable where awardees are the o n l y firms capable of supplying the equipment within the required timeframe.

I

I

D-6 0

Page 81: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTS E-220146.2 NOV. 25 , 1985 85-2 CPD 597 Protests

General. Accounting Office Procedures T i m e l i n e s s of Protest Date Basis of Protest Hade Known to Protester

Under Bid P r o t e s t R e g u l a t i o n s , p r o t e s t based on i n f o r m a t i o n provided t o p r o t e s t e r a t d e b r i e f i n g must be f i l e d w i t h i n 10 working days of t h e d e b r i e f i n g . P r o t e s t e r ' s apparent b e l i e f t h a t agency had agreed a f t e r d e b r i e f i n g t o permit p r o t e s t e r t o f i l e a d e t a i l e d p r o t e s t w i t h i n 30 days a f t e r r e c e i v i n g i n f o r m a t i o n r e q u e s t e d under t h e Freedom of Informat ion A c t does n o t excuse t h e p r o t e s t e r from compliance w i t h GAD bid p r o t e s t t i m e l i n e s s requi rements . Bid P r o t e s t R e g u l a t i o n s provide o b j e c t i v e c r i t e r i a t o b e a p p l i e d t o a l l p r o t e s t s f i l e d w i t h GAO and may n o t b e waived by a c t i o n s o r r e p r e s e n t a t i o n s of a c o n t r a c t i n g o f f i c e r .

BIDS 8-220200 Nov. 25, 1985 Inwitation for Bids 85-2 CPD 598 Amendments Failure to Acknowledge Bid Nonresponsive

A b i d t h a t f a i l s t o acknowledge an amendment which reduced t h e c o n t r a c t d e l i v e r y p e r i o d i s nonresponsive, and t h e d e f i c i e n c y may n o t be waived on t h e b a s i s t h a t t h e b i d d e r d i d n o t r e c e i v e t h e amendment where t h e b i d d e r f a i l s t o show t h a t , as i t contends , t h e agency d e l i b e r a t e l y f a i l e d t o provide a copy o f t h e amendment and o t h e r w i s e c o n s c i o u s l y a c t e d t o exclude t h e b i d d e r from competing.

CONTRACTS B-218021.3 Nov. 26, 1985 Protests 85-2 CPD 599

General Accounting Office Procedures Reconsideration Requests Error of Fact or Law

N o t Established

P r i o r d e c i s i o n i s a f f i r m e d where no new f a c t s o r l e g a l arguments a r e r a i s e d which show t h a t p r i o r d e c i s i o n w a s erroneous.

D-6 1

I

P

P

I

Page 82: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTS 8-219435.2 NOV. 26, 1985 Negotiatlon 85-2 CPD 600 Requests for Proposals Construction

Reasonable Interpretation

Where a company protesting award to another of fe ro r has a fundamental disagreement with the contracting agency about the meaning of certain specifications, and the agency's interpretation is not unreasonable, protest that the agency incorrectly found that the awardee's proposal met those specifications is denied.

CONTRACTS Protests Allegations Unsubstantiated

P r o t e s t that awardee's offered equipment failed to comply with mandatory solicitation specifications is denied where the awardee's proposal indicated that the offered equipment complied with the requirements and there was nothing in the p r o p o s a l , or in the protest record, to establish otherwise.

BIDS 8-219651 NOV. 26, 1985 Mistakes 85-2 CPD 601

Contracting Officer's Error Detection Duty

Although applicable regulations require a contracting of f i cer t o examine a l l bids for error and t o ob ta in verification where a mistake is suspected, there is no reason to do so when a bid i s only 2 percent more that the next-low b i d and 12 percent less than the government estimate.

D-6 2

A

P

Page 83: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

BIDS 8-219651 Con't Mistakes Nov. 26, 1985 Contracting Mficer's Error Dectection Duty

Notice of Error

Discrepancy between the stated t o t a l of a number of items and the correct mathematical total of those items does not constitute constructive notice of a mistake requiring the contracting officer to obtain verification of a bid. Unless there was a duty to verify, a post-award mistake claimed by other than an awardee may not be corrected, since the sole responsibility €or the preparation of a bid rests with the bidder, who must bear the consequences of its mistake unless the contracting officer has actual or constructive notice of a n error before award.

CONTRACTS Offer and Acceptance Oral Written Confirmation

When Department of Energy h a s approved a managing contractor's procurement procedures, and these specifically state that notice of award may be made by telephone, oral award is valid. In these circumstances, the parties intend to make a binding agreement at the time the oral notice is given, and written notice merely confirms the award.

CONTRACTS Protests Basis for Protest Requirement

When protest is otherwise without l e g a l merit, GAO does not reach the question of whether a subcontract awarded by a Department of Energy construction management contractor is subject to the Competition in Contracting Act of 1984, so that, as protester alleges, continued performance violates the stay provisions of the Act.

D-63

I

I

I

I

Page 84: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTS B-219651 C0il.t Small Business Concerns Nov. 26, 1985 Awards Prior to Resolution of Size Protest

Although in a small business set-aside the contracting officer generally is required to notify unsuccessful offerors, befo re award, of the name and location of the successful offeror, providing an opportunity t o file a timely, i.e. pre-award, size status challenge, notice is not required when the contracting officer determines that award must be made without delay. I n such a case, the size status determination w i l l apply only prospectively.

CONTRACTS Small Business Concerns Awards

Small Business Administration's Authority Size Determination

Only the S m a l l Business Administration ( S B A ) has authority to determine whether a firm is "small." Further, size status concerns the b i d d e r ' s eligibility for SBA programs and f o r federal procurement purposes; it does not affect the hidder's responsibility or the responsiveness of its bid.

COrnCTS Subcontracts Competition Applicability of Federal Norm Procurements "for" Government

Federal procurement statutes and regulations do n o t apply per se to a construction management contractor operating by and for the Department of Energy; rather, such a prime contractor must conduct procurements according to the terms of its contract with the agency and its own agency-approved procedures. GAO review is t o determine whether the procurement conforms t o the federal norm, i.e., the policy objectives in the federal statutes and regulations.

--

A

D-64

Page 85: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTS B-219683 NOV. 26, 1985 Negotiation 85-2 CPD 602 Competi tion Equality of Competition

Incumbent Contractor's Advantage

The government is not required to equalize t h e competitive advantage of competing concerns where such advantage is based on incumbency and experience, and no t the result of preference or unfair action by t h e government . CONTRACTS

Nego t fat ion Offers or Proposals Evaluation

Cost Realism Analysis Adequacy

GAO will n o t object to cost realism determination where agency calculated adjusted c o s t estimates by comparing each offeror's proposed c o s t s t o agency cost estimates f o r several sample work items, and relied generally on the quality of each oEferor's support data to substantiate the offeror's c o s t estimate.

CONTRACTS Negotiation

Offers or Proposals Evaluation

Price Consideration

Where solicitation f o r work provided that option work would be evaluated for award, fact that protester, which did not submit low overall c o s t , allegedly submitted lower price for base period work is not significant.

D-65

Page 86: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTS B-219683 Con't

General Accounting Office Procedures Protests Mv. 26, 1985

Timeliness of Protest Date Basis of Protest Made Known to Protester

Protest based on information which protester admits was known from debriefing filed more than 10 working days after debriefing is untimely.

CONTRACTS Protests General Accounting Office Procedures Timeliness of Protest Debriefing Conferences Issues Providing Protest Basis

Protest against cost evaluation of proposals is timely filed approximately 1 month after debriefing where record indicates that basic pricing information giving rise to protest was not given to protester at debriefing and record shows protester pursued diligently information underlying protest and filed protest within 10 working days after receipt of information.

BIDS B-219763.2 NOV. 26, 1985 Invitation for Bids 85-2 CPD 603 Clauses Inspection of Services Price Reduction v. Reperformance Provisions Reconcilability

A provision in a solicitation for custodial services that permits the government to deduct from the contractor's payments for unperformed o r unsatisfactory services does n o t conflict with any reperformance rights of the contractor. Both the standard "inspection of services" clause and the solicitation itself permit, but do not require, the government to allow the contractor to reperform.

D-44

3

A

P

Page 87: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

BIDS Invitation for Bids

Clauses Liquidated Damages

k g a l i t y

B-219763 -2 Con' t Nov. 26, 1985

Protest againsc a provision in a solicitarion for custodial services that permits the government to deduct from the contractor's payments an amount representing the value of unsatifactory service is denied when protester provides no explanation of its objection to the provision and does not demonstrate the unreasonableness of the provision.

CONTRACTS Protests Basis for Protest Requirement

Protest alleging that work tasks and reperformance r i g h t s provisions of solicitation are ambiguous does not s t a t e a basis of protest when the protester provides no examples of the alleged ambiguities and does not demonstrate that any of the provisions are susceptible to mote than one reasonable interpretation.

CONTRACTS Protests

Contract Adminfstration N o t for Resolution by GAO

The actual implementation of a payment deduction system for deficient performance of services is a matter of contract administration, not f o r GAO's review.

I

D-6 7

P

Page 88: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTS B-220070 NOV. 26, 1985 Protests 85-2 CPD 604 General Accounting Office Procedures

Adverse Agency Action Effect Solicitation Improprieties

Timeliness of Protest

Protest of alleged solicitation defects is untimely where the firm initially protested to the contracting agency prior to the closing date f o r receipt of proposals, but did not protest to GAO within 10 working days of closing. Where the agency does not take corrective action requested regarding solicitation defects, closing constitutes the initial adverse action o n an agency-level protest.

CONTRACTS B-220132 HOP. 26, 1985 Federal Supply Schedule 85-2 CT!D 605 Multiple Suppliers

Agency Issuance of a Request for Quotations Evaluation Propriety

Where it is necessary, an agency properly may obtain additional technical information from a Federal Supply Schedule offeror beyond what the offeror furnishes along with its response to the agency's request f o r schedule price quotation.

CONTRACTS Federal Supply Schedule

Purchases for System Hultiple-Award Schedule Contracts

Minimum Needs Requirement Administrative Determination

GAO will not abject t o an agency's determination that an offered product does not meet its minimum needs unless the deterainarion is unreasonable. Where the protester's descriptive literature submitted with its price quotes shows that the product it is offering does not meet the agency's stated salient requirements, the agency properly may reject the protester's quotes. Moreover, the offeror's blanket statement of compliance with all requirements does not make the of fer acceptable.

D-6 8

P

Page 89: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTS 8-220132 Con't Requests for Quotations Nov. 26, 1985

Specifications Brand Name or Equal "Equal" Product Evaluation

When a design feature, such as size or weight, is specified as a salient characteristic, a product offered as being equal to a stated brand name must meet that characteristic precisely.

Protester's offered product should not have been rejected for failing to meet a certain salient feature where the offered product o f the awardee also did not meet this feature. However, rejection f o r this reason d i d n o t prejudice protester, and thus is not cause for disturbing the award, since protester's offered product was rejected for other valid reasons.

CONTRACTS 8-220144 NOV. 26, 1985 Federal Supply Schedule 85-2 CPD 606

Multiple-Award Schedule Contracts Purchases for System

Minimum Needs Requirement Administrative Determination

Protest against the issuance of a delivery order for printing equipment t o multiple-award Federal Supply Schedule contractor by protester with similar schedule contract is denied where the agency reasonably determined t h a t o n l y on-line equipment would meet its requirement, after the protester demonstrated its equipment, which was not on-line.

CONTRACTS B-220517.2 NOV. 26, 1985 Protests 85-2 CPD 607 General Accounting Office Procedures Reconsideration Requests Error of Fact or Law Not Established

Prior dismissal of untimely protest is affirmed where protester fails t o show the dismissal was based on any errors of fact or law.

D-6 9

P

Page 90: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTS B-220559.2 NOV. 26, 1985 Protests 85-2 CPD 608 General Accounting Office Procedures Reconsideration Requests Error of Fact of Law

N o t Established

P r i o r dismissal of a protest as acadernfc due to the agency's cancellation of the challenged solicitation is affirmed since the protester's mere speculation as t o the agency's future course of action in satisfying the requirement is not a valid reason for GAO to consider the merits of the protest.

CONTRACTS Protests

Moot, Academic, etc. Questions Solicitation Canceled

Where GAO's bid protest authority over objections to solicitation provisions is limited to matters that concern a proposed contract f o r the procurement of property o r services, GAO is not the proper forum to consider the agency's alleged misuse of the protester's proprietary information since the challenged solicitation has been canceled and, hence, there is no longer a proposed contract in issue.

D-70

Page 91: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

BIDDERS B-217810 Nov. 27, 1985 Debarment

Labor Stipulation Violations Davis-Bacon Act Wage Underpayments

Debarment Required

The Department of Labor (DOL) recommended debarment of a contractor under the Davis-Bacon Act (Act) because the contractor had falsified certified payroll records, and failed t o pay its employees the appropriate rates of compensation. Based on our independent review of the record in this matter, we conclude that the con- tractor disregarded its obligations to its employees under the Act. There was a substantial violation of the Act in that the underpayment of employees was intentional and the certified payrolls were falsified. Therefore, the contractor will be debarred under the Act.

CONTRACTS Labor Stipulations Davis-Bacon Act

Wage Underpayments

Pursuant to l(a) of the Davis-Bacon Act, 40 U . S . C . s 276a(a) (1982), workers have a statutory entitlement to certain wage rates which are not subject to contractual modifications, and indeed which are not waivable by the workers. Even if the workers here did attempt to waive their statutory entitlements, the contractor is still liable for their full payment. Thus, the contractor's argument that the employees agreed to such contractual modifications of their wage rates constitutes no defense to violating the Davis-Bacon Act.

A R i R i i P

I

! i i P

P

I

D-71

R

R 1 i R i j

1

P

t

Page 92: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

P

CONTRACTS B-218427.3 NOV. 27, 1985 Negotiation 85-2 CPD 609 Requests for Proposals Construe t €on One Reasonable Interpretation

Protest against award t o firm that offered tugboats that were not classed at time of initial proposal submission is denied where the only reasonable reading of the RFP's classification requirement was that classed tugs had to be used t o perform the work and that tugs thus d i d not have to be classed until time of delivery.

CONTRACTS Protests General Accounting Office Procedures Timeliness of Protest

Freedom of Information A c t Request Involvement

Where protester files Freedom of Information Act request promptly after learning of award and there is no showing that agency-level protest then was not filed within 10 days after protester received the information on which its protest was founded, protest was timely filed. Fact that information might have been available from another source more quickly does not render protest untimely.

CONTRACTS B-219623.2 NOV. 27, 1985 Protests 85-2 CPD 610 Preparation

Costs Noncompensable

Claim f o r attorney's fees is denied where agency, in response to protest, refers nonresponsibility determination to Small Business Administration so that protester in fact is not being unreasonably excluded from the competition.

P

D-7 2

Page 93: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

BIDS B-219981 NOV. 27, 1985 His t akes 85-2 CPD 611 Correction Intended Bid Price Establishment Required

Contracting agency improperly permitted awardee to correct mistake in its bid as a clerical mistake since the unit price and extended price were in agreement and intended bid therefore could not be determined from the face of the bid.

BIDS lrLis takes

Intended Bid Price Uncertainty Bid Withdrawal

Withdrawal of bid, not correction of mistake in bid, was the appropriate remedy where the only evidence of the intended bid was the bidderTs price sheet, which lacked any indication of how price was calculated; the amount of the error in price was substantial; and corrected bid was close in amount to the second low bid.

CONTRACTS Protests Interested Party Requirement Direct Interest Criterion

Protester, the second low bidder, has the direct economic interest necessary to be an interested party entitled to challenge the contracting agency's decision to allow t he l o w bidder to correct an apparent mistake in its bid since, if the protest were sustained, the low bidder's bid would have t o be withdrawn and the protester thus would be in line for award.

P

A

D-73

Page 94: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTS B-220618.2 NOV. 27, 1985 Protests 85-2 CPD 612 General Accounting Office Procedures

Additional Evidence Submitted Reconsideration Requests

Available but not Previously Provided to GAO

GAO affirms prior dismissal of protest, which appeared untimely on its face, where protester did not present in its protest the relevant available facts establishing the timeliness of its protest.

BIDS B-220663; E-220664 NOV. 27, 1985 Late 85-2 CPD 613 Eland Carried Delay Conemercial Carrier Failure to Deliver to Designated Office

Rids delivered by commercial carrier are considered to be hand-carried. Protest i s denied where bidder's failure t o address its b i d package to the hand-carried address is the paramount cause of late receipt; therefore, bids were properly rejected as late.

FEDERAL ACQUISITION B-205208 NOV. 29, 1985 RE-TION Proposed Revision

GAO has no objection to proposed changes to Federal Acquisition Regulation (FAR) contract clauses found at FAR $5 52.230-3(a)(5) and 52.230-5(a)(4) implementing section 934 of the Department of Defense Authorization A c t , 1986, Pub. L . 99-145, which states that the interest rate to be charged a government contractor f o r failure to comply with Cost Accounting Standards or t o follow cost accounting practices consistently shall be t h e rate established by the Secretary of the Treasury under Pub. L. 92-41.

D-74

Page 95: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

CONTRACTS B-218102.5 NOV. 29 , 1985 Pr ot e s E s 85-2 CPD 614

Contract Administration Not for Resolution by GAO

GAO will not review whether an awardee is actually complying with specification requirements during the performance of its contract because that is a matter of contract administration. BIDS 8-219825 N~V. 29, 1985 Responsiveness 85-2 CPD 615 Failure to Furnish Something Required Itemized Buy American A c t Information

Bidder's failure to state tariff fo r foreign end product as required by invitation may be waived as a minor informality where the only use of the tariff is to provide an evaluation preference for domestic end products and end products of certain qualifying countries, and all bidders offered end products from the same country.

CONTRACTS B-220168.2 NOV. 29, 1985 Protests 85-2 CPD 620

Interested Party Requirement Suspended, Debarred, etc. Contractors

GAO will not consider protest that agency improperly canceled solicitation, because protester has been suspended from government contracting and is ineligible to receive a government contract and therefore Is not an interested party to protest under Bid Protest Regulations

BIDS B-220209 NOV. 29, 1985 Responsiveness 85-2 CPD 616 Failure to Furnish Something Required Technical Information

A bidder's failure to specify in its bid the type of retaining wall it intended to build for a road construction project may be waived as a minor informality where the requirement to specify the wall type was inadvertently included in the IFB and the bidder gained no competitive advantage over bidders who furnished the information.

D-7 5 P

Page 96: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete
Page 97: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

TRANSPORTATION L A W

TRANSPORTATION B-218694 NOV. 2 5 , 1985 Rates Tariffs Tariff - v. Section 22 Quotations

For the transporrarion of a Government shipment to Tobyhanna A m y Depot, Pennsylvania, a motor common carrier collected charges based on tariff rates. The General Services Administration (GSA) determined that lower tender rates offered solely to the Government under section 22 of the Interstate Commerce Act, 49 U.S.C. s 10721, were applicable, and collected the overcharges by deduction. The GSA action was improper. Although the carrier had nationwide operating authority t o transport Government traffic between all points in the United States, the statutory authority to offer the Government lower rates is voluntary. The carrler's tender refers to a certificate of public convenience and necessity and a points-of-service tariff that exclude Tobyhanna as a direct service point; thus, the rates in the tender are not applicable to traffic transported t o tha t point.

P

F- I

A

P

Page 98: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete
Page 99: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

ACCOUNTABLE OFFICERS Relief

Debt Collection

INDEX

November 1985

B- 2 208 36

BIDDERS Debar men t

Labor Stipulation V i o l a t i o n s

Davis-Bacon A c t

Unwarranted Debarment

B-2 1 88 5 2

Subcontractors Debarment Required B-219695

De bar ment Unwarranted R-218848

8-218855

Wage Underpayments Debarment Required B-217810

B-2 18846 8-218861 B-2 189 9 9 B-219699

Invitation Right Bidder Exclusion n o t Intended B-220963

Failure to Solicit Bids Cancellation of Invitation not Required B-220905

Qualifications License Requirement

State, etc. Certifications B-220857

i

Page - NOV __c

29... A- 2

l... D- 1

19... D-42

5... D-15 5... D-15

27... D-71 4 . . . D- 7 4 . . . D- 8

22.. . D-56 13.4. D-30

15.. . D-3 1

1 2 . . . D-27

I . . . D- 6

P

A

Page 100: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

INDEX - Con- NOV Page

BIDS Acceptance or Rejection

E f f e c t of Acceptance B-219733

Competitive System Preservation of System's In t eg r i t y

Pecuniary Disadvantage to Government E-220034

B-220162

Estimates of Government Basis of Estimate B-220032

Evaluation Discount Provisions

Propriety of Evaluation B-220354

21.. . D-54

1 3 . . . D-31 22... D-57

21... D-55

13.. . D-32

Invitation for Bids Arne ndmen t

Failure to Acknowledge Bid Nonresponsive 8-220199.2 a,.. D-21

8-2 20200 25.. . D-61

Cancellation After Bid Opening

Defective Solicitation B-219926.2 1 3 . . . D-30

Insuf€ic€ent Funding B-220570 20. . D-51

Low Bid i n Excess of Government Estimate B-219448.3 13.. . D-2 8

Clauses Inspection of Services

Price Reduct ion v. Re perf o r manc e Provisions

-

Reconcilability B-219763.2 26.a. D-66

I

ii

Page 101: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

A

INDEX - Con- Page - NOV -

BIDS - Con. Invitation for Bids - Con.

Liquidated Damages Clauses - Con.

Legality B-219763.2 2 6 . . . D-67

Specifications Adequacy B- 22003 2 21.e . D-55

Brand Name or Equal Salient Characteristics

Conformability Requirement B-220174

Minimum Needs Requirement Administrative Determination

Reasonableness B-219635 8-219662 B-220032 B-220174

Restrictive B- 2 1966 2

Burden of Proving Undue Restriction B-220174

1 2 . . . D-24

l... D- 3 20 ... D-46 21.. . D-55 12 . . . D-2 4

20.. . D-46

12... D-25

Late Hand C a r r i e d Delay

Commercial Carrier Failure to Deliver to Designated Office B-220663)

8-220664) 27... D-74

Mistakes Contracting Officer's Error Detention Duty B-219651 2 6 - D-62

Notice of Error 8-2 19651 26. D-63

I

I

iii

Page 102: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

INDKX - Con- Nov . Page -

BIDS - Con. Mistakes - Con.

Correction In tended Bid Price Establishment Req ui r e d B- 2 I 9 9 8 1

Nonresponsive Bids B- 22 003 4

Intended Rid Price Uncertainty

B i d Withdrawal B-2 1998 1

Open 5. ng Postponement

Denied 3-2 1951 2 B-2 1 96 3 5

Preparation costs

Noncompensable B-219107.2

Protester not in Line €or Award B-219107.2

Responsfveness Brand Name or Equal Procurement B-220434.2

D e terminat i o n On Basis of Bid as Submitted at Bid Opening €3-220380

Exceptions Taken to Invitation Terms B-220034

€3-220162

Small Business Requirements B-220380

27.. . D-73

1 3 . . . D-31

27.e. D-73

l... D- 2 1.. . D- 3

7... D-18

7... D-19

22.. . D-58

l... D- 4

1 3 - m . D - 3 1 22... D-57

l... D- 5

iv

P

Page 103: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

INDEX - Con.

NOV . Page

RIDS - Con. Responsiveness - Con. Failure to Furnish Some thing Required Affiliates Affldavit Waiver

A s Minor Informality B- 2 208 79

Information Small Business Concerns End Product Cont r i but0 r B-219648

Itemized Buy American Act In€ormation B-219825

Standard Represent at ions and Certifications Waiver

A s Minor Informality 3-220424

Technical Information 8-220209

Tes t to Determine Unqualified Offer to Meet all Solicitation Terms B-219733

What Constitutes E- 2 20 3 7 4

1 5 . . . D-37

5. . . D-16

29. . . D-75

2 1 . . . D-55

29. . . D-75

21 . . . D-54

8... D-22

CONTRACTING OFFICERS Determinations Nonrespons€bility Administrative v. Judicial Matter- Procedural Due Process Guarantees Hearing not Required B-220152 )

8-220152.2) ZO... D-49

V

i

Page 104: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

INDEX - Con. NOV - Page

A

CONTRACTORS Responsibility

Administrative Determination Accepted B-220152 )

B-220152.2) 20.a.

Nonr es pons ibi It y F indlng Supported by Record B-219449 $...

Determination Definitive Responsibility Criteria

Compliance B-220683 22.. . Review by GAO B-220857 l...

Affirmative Finding Accepted B- 7.2 00 3 7 20..

8-220405 13.. . E- 2 2 040 6 4 . . . 8-220963 15* . .

Nontesponsibility Finding B-2 1 987 2 ,

et a l . ) 20.. B-2 200 7 1 a... B-220152 ) 8-220152.2) 20...

Bad Faith Alleged B-220152 ) B-220152.2) 20...

CONTRACTS Awards

Not ice To TJnsuccessful Bidders B-220879 15.. .

Data, Rights, etc.

Frior t o Award Disclosure

No Evidence to Support Allegation B-220012 25.. .

v i

D-4 9

D-20

D-58

D- 6

D-49 D-32 D-13 D-38

D-47 D-21

D-50

D- 50

D-3 7

D-59

i

I

Page 105: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

INDEX - Con. NOV . Page

CONTRACTS - Con. Federal Supply Schedule Awards Propriety Order Limitation Exceeded B-219541.2 13. D-28

Multiple Suppliers Agency Issuance of a Request f o r Quotations Evaluation Propriety B-220132

Purchases f o r System Multiple-Award Schedule Con t r ac t s Minimum Needs Requirement

Ad min i s t r a t i ve Determination B- 220 132

B- 220 144

To Other Than Low Bidder or Offeror Just€fication 8-220253

Labor Stipulations Davis-Bacon Act Classification of Workmen Disputes B-217848

Wage Underpayments B-217810

Negotiation Awards Initial Proposal Basis Propriety B-2200 15

N o t Prejudicial to Other Offerots B-2 1960 1

Propriety Technical Superiority-- Paramount Consideration 8-2 19469

vii

26... D-68

26... D-68 26. D-69

22.. D-58

14... D-35

2 7 . e . D-71

I... D- 3

13... D-29

4 . . . D- 9

i

B I R I I R i I A

1 i

i

A

Page 106: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

INDEX - Con. NOV PaGe

CONTRACTS - Con. Negotiation - Con.

"Buying In" Not Proper Basis to Prevent Award 8-220839 l... D- 5

Competition Equality of Competition

Incumbent Contractor's Ad vantage 3-219683 26. D-6 5

D-59 Determinations and Findings Basis for Negotiation B-219423.2 25...

Late Proposa ls and Quotations Contractor's Responsibility f o r Delivery 8-219664.2 19.. . D-4 1

Modification of Proposals Price Reduction B-220015 l... D- 4

Rejection Propriety 8-21 961 8 B-219664.2

8 . . . 19.. . D-2 1

D-4 1

Offers or Proposals Best and Final Additional Rounds 13-218567.2 5...

18.. . D-14

D-3 8 Denial Propriety 8-219643

Discussions Clarification v. Reopening Negotiations B-219643

B-219915

I

l a . . . 18.. . D-38

D-39

Discussion With all Offerors Requirement Except ions Offers not Within Competitive Range 8-219917 19. .. D-4 2

v i i i

P

Page 107: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

A

Nav * Page

CONTRACTS - Con. Negotiation - Con.

Evaluation Offers or Proposals - Con.

Administrative Discretion 8-22061 9 14... D-36

Co s t /Pr i c i n g Evaluation B-219636

8-2200 13 4 . . . D-10

12. . . D-23

Competitive Range Exclusion

Reasonableness B-219917 B-220142

19.. D-43 19... D-44 P

C o s t Realism Analysis Adequacy B-2 1 9 6 8 3 26. . . D-65

Reasonableness B-2 1 94 6 9 4 . . . D- 9

Personnel 8-219636 4... D-10

Price Consideration 8-219683 8-2 199 1 7 B-220619

26.. . D-6 5 19... D-43 14... D-36

Reasonable B-219915 18... D-39

Technical Acceptability Admi n i s t 1: at i ve Determination B-218567.2 5... D-14

Based on Content of Proposal B-220142 19... D-44

Preparation c o s t s

Denied B-218622.4 13... D-27 B-219988.4 4 . . . D-12

ix

Page 108: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

INDEX - Con.

CONTRACTS - Con. Negotiation - Con. Preawards Surveys Preparation

C o s t s 8-220142 19... D-45

Requests f o r Proposals Amendment B-2 19469 4 . . . D-10

Construct ion One Reasonable Interpretation 0-218427.3 27... D-7 2

Reading all Provisions Together Rule Presumption Against Conflict B-219609 21... D-53

8-219872, et al.) 20. * D-47

Re a so nab 1 e Interpretation B-219435.2 26.. . D-62

Speci f icat ions Adequacy

Scope of Work-- Sufficiency of Detail B-219872,

et al.)

Minimum Needs Not Overstated B-2 197 66

13-220092, et al.)

Restrictive Conformability of Equipment, etc. Offered Administrative Determination B-2 1 9 7 6 6

Undue Restrict ion not Established B-220092,

et al.) X

20... D-48

S... D-16

25.. . D-BO

5... D-16

25.. . D-60

i

*

A

Page 109: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

A

A

INDEX - Con. E

Page - NOV . CONTRACTS - Con.

Negotiation - Conr Sole-Source Basis

Administrative Determination Reasonable Basis B-220092,

et al.) 25.. . D-60

Offer and Acceptance Oral

Written Confirmation B-219651 2 6 . D-63

Fro t e s ~s Abandoned D-58 B-220253 22...

Allegations Speculative B-219636 4 . . . D-11

Unsubstantiated B-21943 5 2 B-219601

26.. . 1 3 . . . D-62

D-29

Authority to Consider Activities not Involving Federal Procurement B-220400 l... D- 5

Basis for Protest Requirement 8-2 196 51

B-219763.2

B-220406 B-220824 8-220891

B-220000.2

26.. . 26.. . 2 1 . . .

4 . . . 5... l...

D-63 D-67 D-54 D-13 D-17 D- 6

Burden of Proof On Protester B-2 19449

B-2 199 15 B-219917

8 . . . 18.. . 19.. .

D-20 D-39 D-4 3

Conflict in Statements of Protester and Contracting Agency B-2 19636 4 . . . D-11

xi

I

Page 110: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

NOV Page

CONTRACTS - Con. Protests - Con.

Contract Administration Not f o r Resolution by GAO B-218102.5 29.s. D-7 5

B-219327.6 4 . . . D- 8 R-219763.2 26.. . D-67 B-219872,

et al.) 20... D-48

General Accounting Off ice Function

Scope of Review of Agency Actions E-2 I9 63 6

General Accounting Office Procedures

Filing Protest With Agency 8-2 19 5 12

B-219915 B-220560 B-2207 3 1.2

Piecemeal Development of Issues by Protester B-219 601

4... D-11

l... D- 2 18.. . D-40 13.. . D-33 12.. . D-26

I

I

13.. . D-29

Reconsideration Requests Additional Evidence Submitted

Available but not Previously Provided to GAO 8-220618.2 27... D-74

Error of Fact o r Law Not Established B-218021.3 26.. . D-61

B-218730.4 20.. . D-4 5 B-218766.2 21... D-53 B-219423.2 2 5 . e . D-59 8-219428.2) 8-219440.2) 21.6 D-53

Xii

I

Page 111: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

INDEX - Con. Page - NOV . -

I

CONTRACTS - Con. P r o t e s t s - Con.

Genera l Accounting O f f i c e Procedures - Con.

R e c o n s i d e r a t i o n Requests - Con. E r r o r of Fact o r Law - Con.

Not E s t a b l i s h e d - Con. B-219541.2 B-229575 73-220080.2 B-220517.2 B-220559.2 B-220672.2 B-220580.2 8-220717.2

T i m e l i n e s s of Comments on Agencyts Report 5-219 114.2

R- 2 1960 1

Timeliness of P r o t e s t Adverse Agency Action E f f e c t

I n t e r i m Appeals t o Agency--Effect on LO Working Day GAO F i l i n g Per iod B-220918.2

S o l i c i t a t i o n Improprieties B- 2 200 7 o

Date Basis of P r o t e s t Made Known t o P r o t e s t e r E-2 19683

B-219925 B-220000.2 E-220146.2 R-22 0 180

1 3 . . . 20.. . 22... 26.. . 2 6 . . . 1 3 . . . 1 2 . . . 1 2 . .

4... 1 3 . . .

20.. .

26...

26.. . 18.. . 21.. . 25.. .

4.. .

D-2 8 D-46 D-56 D-69 D-70 D-34 D-25 D-26

D- 8 D-30

D-52

D-68

D-66 D-40 D-54 D-6 1 D-12

x i i i

I

Page 112: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

A

INDEX - Con.

Page - NOV - P

CONTRACTS - Con. Protests - Con.

General Accounting Office Procedures - Con.

Timeliness of Protest - Con. Debriefing Conferences

Issues Providing Protest Basis B- 2 19683

E-220824 26... D-66 5.. . D-17

A Freedom of Information Act Request Involvement B-218427.3 27.. .

1 3 . . .

D-72

Significant Issue Except i o n

Not for Application B-220672.2 D-34

Solicitation Improprieties Apparent Prior to Bid Opening/Closing Date f o r Proposals B-218567 .2

B-219327.6 73-2 19915 E- 2 20 1 6 2 B-220894

5... 4... 18... 22... l...

D-14 D- 9 D-40 D-57 D- 7

Information Evaluation Sufficiency of Submitted Information B-208159.3 19. . D - 4 1

Interested P a r r y Requirement Direct Interest Criterion E-219981

B-22027 8 B-220390

27... 13. ..

4...

D-73 D-32 D-12

Nonresponsible Offeror B-219872, et a l a > 20. . D-48

XiV

A

Page 113: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

INDEX - Con.

Page - NOV - - CONTRACTS - Con.

Protests - Con. Interested Party Requirement - Con.

Protester n o t in Line for Award B- 220 14 1 12.. . D-24

Suspended, Debarred, etc. Contractors B-220168.2

B-220410 29.. . 1 3 . . .

D-75 D-32

Moot, Academic, etc. Quest: ions B-219917 19 .a . D-44

Contract Terminated for Convenience 8-219926.2

B-220693 1 3 . . .

4 . . . D-31 D-13

Corrective Action Proposed Taken, etc. by Agency 8-220174

B- 2 2 04 6 3 12. . . 13.. . D-25

D-33 i

Future Procurements B-220667.2 20.. . D-51

Solicitation Canceled B-220065.2

B-220559.2 B-220667.2

15.. . 26.. . 20.. .

D-36 D-70 D-51

Preparation Costs

Noncompensable 8-219107.2 f . . . D-19 B-219458 l... D- 1 B-219623.2 27... D-72 B-220667.2 20... D-51

Procedures Information Disclosure A

Procurement Pending Requirement B-219512 l... D- 2

xv

Page 114: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

I N D E X - Con. Now. Page

CONTRACTS - Con. Requests f o r Quotations

Brand Name or Equal "Equal" Produc t Evaluation B-220132

Specifications

2 6 . . . D-69

Small Business Concerns

Prior to Resolution Awards

of Size Protest B-2 196 5 1 26... D-64

Responsibility Determination Nonresponsibility Finding

Certificate of Competency on Recent Procurement--Resubmission to SBA not Required B-219654 12.. . D-22

Referral to SBA for COC Mandatory Without Exception B-219654 12.. . D-23

D-20 D-18

Review by GAO 8-219449 8-220968

8... 6 . . .

Set-Asides Withdrawal

Propriety 8-220560

!

13. D-33

Small Business Administration's Authority

Certificate of Competency

Conclusiveness R-220545 20.. . D-50

Inapplicability of COC Procedures B- 22 10 57 20.. . D-52

Size Determination €3-219651 8-22 0935

26.. . 6. .. D-64

D-17

xvi

Page 115: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

INDEX - Con.

NOV Page

CONTRACTS - Con. S m a l l Business Concerns - Con.

Size Status Protests

Mandatory Referral to Small Business Admi ni s t rat io n B-219107.2 7. . . D-19

Subcontracts competition

Applicability to Federal Norm

Procurements " f o r " Government B-2 19 6 5 1

DEBT COLLECTIONS Waiver

Military Personnel Allowances

Basic Allowance f o r Quarters (BAQ) B-220792

26... D-64

1 4 . . . c- 1

EQUIPMENT Automated Data Processing Systems

Acquisition, e r e . Competitive Procedures v. Federal Supply Schedule Utilization B-219508 12... D-22 I

FEES License, Permit, etc. Fees

Prohibit i o n 8-218964 26.. . B- 6

I

\

FEDERAL ACQUISITION REGULATION Proposed Revision B-205208 29... D-74

B- z 1 688 7 21... D-52 B-219923.2 20... D-48 B-220819 12.. . D-27 B- 220943 21.. . D-56

xvii

Page 116: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

INDEX - Con.

FRAUD False Claims

Subsistence Expenses

NOV Page -

B-219051 27... B- 6

FREEDOM OF INFORMATION ACT Disclosure Requests

Records of Agencies, etc., Other Than GAO

Authority of GAO to Require Disclosure B- 2 19636

GENERAL ACCOUNTING OFFICE Decisions

Beconsideration Error of Law or Fact Basis

Not Established 3-216938

Jurisdiction Conflict of Interest Statutes E-22093 5

Labor Stipulations Wage Determinations B-220800.2

4 . . . D - 1 1

12.. . B- 2

6 . . . D-15

12.. . D-26

HOUSING AND URBAN DEVELOPMENT DEPARTMENT

Mortgage Insurance Funds Distributive Shares B-20 L 6 6 9 2 6 . . . A- 1

LA30 R DE PARTME NT Jurisdiction

Service Contract Act Violations B-2 208 5 7 l... D- 6

LEAVES OF ABSENCE Annual

Leave Adjustment Excess Leave Credited

Administrative Error €3-219505 29.. . B- 7

xviii

Page 117: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

INDEX - Con. Page - NOV

I_

LEAVES OF ABSENCE - Con- Civilians on Military Duty Unlimited Military Leave

District of Columbia National Guard Duty B-218763

Furpose of Duty Consideration

Compensatory Time Credit Hours Limitarion on Accrual Effect

Overtime Adjustment B-217937

2 6 . . . B- 5

26.. . B- 5

Promot ions Temporary

Detatled Employees Higher Grade Duties Assignment Wilson Case B-219470

Trans E er s Government v. Employee Interest Relocation Expense Reimbursement

Admin i s t rat 1 ve De termination

-

Finality 13-21 6938

Nonreimbursable Expenses Operating and Maintenance Expenses

R e s i d e nc e B-219546

OFFICERS AND EMPLOYEES Health Insurance Blue Cross-Blue S h i e l d Funds B-219236.2 26.. . A- 2

8... B- 1

12.. . B- 2

29... B- 8

xi x i

Page 118: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

INbEX - Con.

Nov I Page

I

OFFICERS AND EMPLOYEES - Con.

Real Estate Expenses Transfers - Con.

Broker ' s Fees Legal Obligation to Pay Requirement B-2 17 5L4

Loan Discount Fees B-218946

Loan Origination Fee B-219026 8-2 190 7 6 ) B-219123)

PROPERTY Private

Taking for Government Use Liability of United States B-218982

I! URCBASE S Small

Awards Propriety

Misplacement of Lower Offer R-219458

RET1 REMENT Civilian

Reemployed Annuitants Annuity Deduction

Validity R-219931

SMALL BUSINESS ADMINISTRATION

Contracting With Other Government Agencies

Con t r ac t s

Procurement Under 8(a) Program

Review by GAO B-220387

xx

25 . . B- 4

12. . B- 3

29.. . B- 7

25. . B- 4

l... A- 1

Y

l... D- 1

5 . . . B- 1

14. . . D-35

Y

i

Page 119: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

i

INDEX - Con.

TRANSPORTATION Household Effects

Weight Limitation Changes

Retroactive

What Constitutes

R-217095

B-216938

Rates Tariffs

Tariff v. Section 22 Quotations B-2 18694

-

TRAVEL EXPENSES Trans fer s

Dependents Unaccompanied Travel B-219546

NOV Page

29.. . B- 6

12... B- 3

2 5 . . . F- L

Y

i

Y

29.. . B- 8

xxi

\

i

i

Y

Y

Page 120: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete
Page 121: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

i

i

Y

Y

Y

i

Page 122: Digests of Unpublished Decisions of the Comptroller ... · Digests : General Government ... If HUD cannot locate persons in order to make payment, ... employee failed to complete

Y

Y

Y

i