Difference Between MRP vs MPS
Transcript of Difference Between MRP vs MPS
-
8/9/2019 Difference Between MRP vs MPS
1/2
Difference between MRP vs MPS
Explain the difference between MRP & MPS. Though both components gives
ou the re!uirement list" what we gain out of MPS run rather than running
MRP. #hat is the main idea behind this$
The following might help in explaining the difference between MPS and its
counter part MRP.
Master Production Schedule %MPS '
MPS operates within only one level of the BOM !hile MRP can be utili"ed
throughout all levels of a material#s BOM. $f a MPS is run on a material the
necessary orders are planned at that level. %ependent re&uirements 'if any( are
placed on the next BOM level down and then the process stops.
Main $dea ) Master production scheduling 'MPS( is a form of MRP that
concentrates planning on the parts or products that have the great influence on
company profits or which dominate the entire production process by ta*ing critical
resources. These items are mar*ed as +,# parts 'MPS items( and are planned with
extra attention. These items are selected for a separate MPS run that ta*es place
before the MRP run. The MPS run is conducted without a BOM explosion so that
the MRP controller can ensure that the Master schedule items 'MS$( are correctly
planned before the detailed MRP run ta*es place.
The master production schedule is a line on the master schedule grid that reflectsthe anticipated build schedule for those items assigned to the master scheduler. The
master scheduler maintains this schedule and in turn it becomes a set of planning
numbers that drives material re&uirements planning. $t represents what the
company plans to produce expressed in specific configurations &uantities and
dates. The master production schedule is not a sales item forecast that represents a
statement of demand. The master production schedule must ta*e into account the
forecast the production plan and other important considerations such as bac*log
availability of material availability of capacity and management policies and
goals. Syn) master schedule.
Material Re!uirements Planning %MRP '
, set of techni&ues that uses bill of material data inventory data and the master
production schedule to calculate re&uirements for materials. $t ma*es
recommendations to release replenishment orders for material. -urther because it
is timephased it ma*es recommendations to reschedule open orders when due
-
8/9/2019 Difference Between MRP vs MPS
2/2
dates and need dates are not in phase. Timephased MRP begins with the items
listed on the MPS and determines
'/( the &uantity of all components and materials re&uired to fabricate those items
and
'0( the date that the components and material are re&uired. Timephased MRP is
accomplished by exploding the bill of material ad1usting for inventory &uantities
on hand or on order and offsetting the net re&uirements by the appropriate lead
times.
MRP (nterview )uestions'
#hat is the need of mrp list if stoc* re!uirement list is alread there$
The MRP list displays the result of the last planning run. 2hanges that have
occurred between planning runs are ignored in the MRP list. $n contrast to this
the system displays all changes in stoc* receipts and issues which have currently
occurred in the stoc*3re&uirements list.
#hich tcode are used to run MRP$
M%4/ is generally used to run the MRP for all the materials in a plant normally
1ust before golive.
M%40 is used to run MRP for materials which have a BOM i.e multilevel. M%45 is used to run MRP for materials which do not have a BOM i.e single
level.