Difference Between MRP vs MPS

download Difference Between MRP vs MPS

of 2

Transcript of Difference Between MRP vs MPS

  • 8/9/2019 Difference Between MRP vs MPS

    1/2

    Difference between MRP vs MPS 

    Explain the difference between MRP & MPS. Though both components gives

    ou the re!uirement list" what we gain out of MPS run rather than running

    MRP. #hat is the main idea behind this$ 

    The following might help in explaining the difference between MPS and its

    counter part MRP.

    Master Production Schedule %MPS '

    MPS operates within only one level of the BOM !hile MRP can be utili"ed

    throughout all levels of a material#s BOM. $f a MPS is run on a material the

    necessary orders are planned at that level. %ependent re&uirements 'if any( are

     placed on the next BOM level down and then the process stops.

    Main $dea ) Master production scheduling 'MPS( is a form of MRP that

    concentrates planning on the parts or products that have the great influence on

    company profits or which dominate the entire production process by ta*ing critical

    resources. These items are mar*ed as +,# parts 'MPS items( and are planned with

    extra attention. These items are selected for a separate MPS run that ta*es place

     before the MRP run. The MPS run is conducted without a BOM explosion so that

    the MRP controller can ensure that the Master schedule items 'MS$( are correctly

     planned before the detailed MRP run ta*es place.

    The master production schedule is a line on the master schedule grid that reflectsthe anticipated build schedule for those items assigned to the master scheduler. The

    master scheduler maintains this schedule and in turn it becomes a set of planning

    numbers that drives material re&uirements planning. $t represents what the

    company plans to produce expressed in specific configurations &uantities and

    dates. The master production schedule is not a sales item forecast that represents a

    statement of demand. The master production schedule must ta*e into account the

    forecast the production plan and other important considerations such as bac*log

    availability of material availability of capacity and management policies and

    goals. Syn) master schedule.

    Material Re!uirements Planning %MRP '

    , set of techni&ues that uses bill of material data inventory data and the master

     production schedule to calculate re&uirements for materials. $t ma*es

    recommendations to release replenishment orders for material. -urther because it

    is timephased it ma*es recommendations to reschedule open orders when due

  • 8/9/2019 Difference Between MRP vs MPS

    2/2

    dates and need dates are not in phase. Timephased MRP begins with the items

    listed on the MPS and determines

    '/( the &uantity of all components and materials re&uired to fabricate those items

    and

    '0( the date that the components and material are re&uired. Timephased MRP is

    accomplished by exploding the bill of material ad1usting for inventory &uantities

    on hand or on order and offsetting the net re&uirements by the appropriate lead

    times.

    MRP (nterview )uestions' 

    #hat is the need of mrp list if stoc* re!uirement list is alread there$  

    The MRP list displays the result of the last planning run. 2hanges that have

    occurred between planning runs are ignored in the MRP list. $n contrast to this

    the system displays all changes in stoc* receipts and issues which have currently

    occurred in the stoc*3re&uirements list.

    #hich tcode are used to run MRP$ 

    M%4/ is generally used to run the MRP for all the materials in a plant normally

     1ust before golive.

    M%40 is used to run MRP for materials which have a BOM i.e multilevel. M%45 is used to run MRP for materials which do not have a BOM i.e single

    level.