Did It Jump or Was It Pushed: Five Lessons from the Prematurely Named Nuclear Renaissance

37
Did It Jump or Was It Pushed: Five Lessons from the Prematurely Named Nuclear Renaissance Peter A. Bradford Adjunct Professor, Vermont Law School Oak Ridge Associated Universities March 6, 2014 1

description

Peter Bradford Presentation at 2014 ORAU Board Meeting

Transcript of Did It Jump or Was It Pushed: Five Lessons from the Prematurely Named Nuclear Renaissance

Page 1: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

1

Did It Jump or Was It Pushed: Five Lessons from the Prematurely Named Nuclear

Renaissance

Peter A. BradfordAdjunct Professor, Vermont Law School

Oak Ridge Associated UniversitiesMarch 6, 2014

Page 2: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

Source : IAEA-PRIS, BP, MSC, 2013

Page 3: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

3

Reactors Under Construction (IAEA, PRIS)

Page 4: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

4

Why the U.S. Stopped Building New NPPs in the 1970s I

• An overreaction to the 1979 accident at Three Mile Island– Excessive regulation caused increased costs– Environmental and antinuclear groups exploited

the accident– The public turned against nuclear and politicians

followed• Can be remedied by political leadership,

streamlined licensing, safer reactors.

Page 5: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

WHERE?

1. In the White House

2. After Three Mile Island

3. At reactor sites

4. In hearing rooms

5. In 10 CFR

WEAPON?

1. Crafty NRC appointments

2. Their tongues

3. Overregulation

4. Cost overruns

5. Cowardice

WHO?

1. Environmentalists

2. The NRC

3. The public

4. Jimmy Carter

5. The industry

Clueless - The Board Game: Who Killed Nuclear Construction

Page 6: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

Why the U.S. Stopped Building New NPPs in the 1970s II

• In 1978 the U.S. Congress passed a law requiring utilities to buy power from anyone who could supply it more cheaply than the utilities could generate it. – This opening of the generation market, not Three Mile Island,

explains the end of new reactor orders in the U.S.• The resulting independent power industry provided far more

generation and innovation than had the utilities, and at lower prices. This had several consequences:– Improved utility operations and therefore lower costs– Electric restructuring and market development in about half of the

U.S.• Shift of economic risk from customers to investors

Page 7: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

7

Page 8: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

8

U.S. Nuclear Output and Nuclear Capacity, 1973-2013: Productivity Improvement in the Face of Competition

1973

1981

1989

1997

2005

2009

2013

0

200000

400000

600000

800000

020406080100120140160180

Capacity

Energy

c

Gi gawatt -hours

Gig

awatt

s

Page 9: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

9

Nuclear Renaissance in Retrospect I

• 2001 – Admnistration embraces new nuclear• 2002 – Bush administration announces

“Nuclear Power 2010”• Two new reactors operational by 2010 to prove the

effectiveness of the new licensing process

• 2003 – The Nuclear Energy Institute sets a target 50,000 new nuclear megawatts from 40-50 new reactors by 2020

Page 10: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

10

Overnight Costs ($2009/kw) of Nuclear Construction (Mark Cooper, 2012)

Page 11: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

11

Nuclear Renaissance in Retrospect II

• 2003 MIT Study “The Future of Nuclear Power” urges federal incentives for “a few first mover plants”

• 2005 “Nuclear Power 2010” target date for two new reactors becomes 2014;

• 2006 – Global Nuclear Energy Partnership proposes U.S. reprocessing

Page 12: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

Nuclear v. Fossil Fuels per MIT 2003 Study

Page 13: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

Energy Policy Act of 2005

• Loan guarantees (capped at $18 billion in 2007)

• Production tax credit (1.8¢/kWh for first 6 GW)

• Price-Anderson renewal• Plus delay insurance, licensing cost sharing

and curtailment of public involvement

Page 14: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

14

Nuclear Renaissance in Retrospect III

• 2006 – Several Southeastern states pass “early cost recovery” laws.– Once utility commission certifies a need, then cost

recovery begins, with no refunds for canceled plants and dwarf prudence reviews.

• 2008 presidential campaign – Obama supportive, McCain promised 50 new reactors by 2030, Republicans later doubled to 100.

Page 15: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

15

Nuclear Renaissance in Retrospect IV

• By the end of 2008, applications for 29 new reactors (of several designs) were on file at the NRC, with four more expected in 2009.

• But only two more arrived;• GNEP essentially dropped in 2009;• Congress did not enact a carbon policy;• The first operating reactors in 15 years closed at

Kewaunee, Crystal River, San Onofre (2) and Vermont Yankee (later in 2014);– Exelon says it may close several more if power markets aren’t

modified

Page 16: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

16

A Nuclear Deal That Might Have Made Sense Circa 2009

• Trade financial support for a few reactors of different types for a sensible carbon policy. Nuclear proponents might have bought it expecting success, opponents expecting failure.– “On time and on budget” won’t help if on budget

is twice the market price.

Page 17: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

17

The Status of the U.S. Reactor Renaissance in 2013

2009 Propose

d Reacto

rs

Cance

led as of 2

013

Seekin

g Lice

nse O

nly, or U

ncerta

in

Being Built

as of 2

01405

101520253035

Page 18: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

18

What Happened?

• Too much economic risk for power markets or private investors, manifested in a cascade of events, any one of them arguably fatal:– Nuclear construction cost estimates up by 2-300%– Electricity demand declining due to recession and low cost

energy efficiency;– Natural gas prices below MIT 2003 low end estimates;– No carbon pricing;– Discrediting of federal subsidies especially among pro-

nuclear Republicans– Fukushima

Page 19: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

Same Story, Told Elegantly

Page 20: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

Operating Reactors

• Most probably still competitive, but– Some will eventually close early for economic reasons

• None in the U.S. has ever closed because its license expired

– Margins are narrower;– Output may decline with age;– Major capital investments will be harder to justify;– Much depends on who takes the risk under the

regulatory arrangements in different states.• When investors must take risks of poor performance or

cheaper alternatives, nuclear is less attractive to owners (same issues now confront Japan if it restructures)

Page 21: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

Holding the 20% Share of U.S. Electricity? (Paul Joskow, MIT, 2006)

21

Page 22: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

Fukushima and Changed Perceptions of Nuclear Risk

• Permanent destruction of +/-one percent of the world’s nuclear capacity live on worldwide television

• Destruction of TEPCO – World’s 4th largest utility• Evacuation of +/-100,000 people• The accident goes on and on• Liability issues of more than $100 billion unresolved• Failure of a once respected regulatory regime • Major political impact in Japan • Undetermined health effects, mitigated by wind• Land contamination, some probably for many years• Substantial resurgence of nuclear skepticism in many countries, with

slowing and cancellation of construction programs

Page 23: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

Lesson 1: New Nuclear in Competitive Markets Will Take $Billions in Support Per Reactor

• The reality is that none will be built without extensive government support:

• Loan guarantees and customer supplied capital can reduce price but not cost (because they merely transfer risk).

• Current DOE gas forecasts indicate gas-fueled electricity not rising above 8 cents/kwh for more than 20 years.

• And large amounts of efficiency remain available at less than 4 cents/kwh.

• Alternatives getting cheaper, new nuclear apparently not.• North Florida follies are costing customers more than a billion

dollars for nothing;• Hinckley Point

23

Page 24: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

24

Lesson 2

• Don’t buy insurance that costs more than the event you’re insuring against.

Page 25: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

25

Gas Volatility v. New Nuclear Power at 12 Cents/kWh

Page 26: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance
Page 27: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

27

Lesson 3

• It is possible to explain the downfall of the nuclear renaissance without mentioning waste or proliferation,

• Or Jimmy Carter, or– Overregulation, or– Citizen and environmental intervenors, or– Three Mile Island, or even– Harry Reid.

Page 28: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

Lesson 4: Silver Bullsh*t

• Substitute for serious thought: – “There are no silver bullets. We need silver

birdshot. Therefore, we have to do all of the above.”

• What we really need is what we have always needed – market-harmonized ways to a nuclear policy that serves wise public policy, not the other way around.

Page 29: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

Today’s Alternatives, As Seen by the Largest U.S. Nuclear Operator John Rowe, AEL, March 8, 2011

Page 30: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

30

Page 31: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

Nuclear Power and Climate Change

• To accomplish 10% of the needed greenhouse gas reduction by 2050, we’d have to triple the number of reactors worldwide– Plus enrichment and waste repositories

• But nuclear output has declined since 2002

Page 32: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

Do Everything or Prioritize Wisely? The Pacala/Socolow Wedges (Scientific American, 9/06)

Page 33: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

A Wedge

• Prevent 1 billion tons carbon per year by 2054;• Scaling up only of technologies already

deployed on an industrial scale;• Seven needed to stabilize CO2 at 500ppm;– More will be needed to get to 350ppm

Page 34: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

Other Wedges

• Energy efficiency (3)• Alternative transportation approaches (4)• Enhancing natural carbon sinks (2)• Decarbonizing electricity generation (4)– Of which nuclear is one

Page 35: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

The Nuclear Wedge

• Doubling of nuclear power really requires tripling the existing capacity (372GW/438plants) because today’s plants must be replaced.– Probably 700-900 new plants needed to get 1100GW

• Assumes nuclear replaces all coal. In fact, nuclear will replace some gas and large hydro, requiring more new nuclear capacity to make a wedge.

• Prodigiously difficult and expensive, but so are many of the wedges.

• Little impact before 2030.

Page 36: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

How to Choose

• Without a price on carbon we are left with various forms of governmental picking of “winners”

• Carbon markets have not to date produced prices remotely high enough to support new nuclear,– But a price on carbon might save existing reactors.

Page 37: Did It Jump or Was It Pushed:  Five Lessons from the Prematurely Named Nuclear Renaissance

Lesson 5: Don’t Call It a Renaissance Until You’ve Seen a Masterpiece