DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy...

153
DHBVN (Dakshin Haryana Bijli Vitran Nigam) HVPNL (Haryana Vidyut Prasaran Nigam Limited) Revised D.P.R. Smart Grid Project Gurgaon City First Phase DLF Sub-Division Area 05/05/2016

Transcript of DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy...

Page 1: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

DHBVN

(Dakshin Haryana Bijli Vitran Nigam) HVPNL

(Haryana Vidyut Prasaran Nigam Limited)

Revised D.P.R. Smart Grid Project Gurgaon City

First Phase DLF Sub-Division Area

05/05/2016

Page 2: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

2

Table of Contents Table of Contents .......................................................................................................... 21 Executive Summary ............................................................................................... 6

1.1 Need of Smart Grid leading to Smart City .......................................................... 6

1.2 Gurgaon Smart Grid Leading to Smart City ........................................................ 7

1.3 Phase -1 (Part-1) DLF City Subdivision area .................................................... 10

1.4 Demographic Statistics ..................................................................................... 11

1.5 Electricity Profile of DLF City Sub Division in Gurgaon ..................................... 11

1.6 Transmission Infrastructure & Challenges ........................................................ 12

1.7 Challenges in Distribution: ................................................................................ 14

1.8 Objectives of the Project ................................................................................... 15

1.9 Proposed Strengthening of Infrastructure ......................................................... 16

1.10 Estimated Cost of Project (Phase I) .............................................................. 18

1.10.1 Estimated Cost of Substation and lines .................................................. 20

1.11 Financing Strategy ........................................................................................ 21

1.12 Implementation strategy and ownership ........................................................ 22

1.13 Reliability Surcharge ..................................................................................... 22

1.14 Cost Benefit Analysis .................................................................................... 23

2 BACKGROUND ..................................................................................................... 242.1 SMART CITY GURGAON - The Concept ......................................................... 24

2.2 Gurgaon Smart Grid Leading to Smart City ...................................................... 29

2.3 Geographical Map of Gurgaon under Smart Grid ............................................. 32

2.4 Sectors to be covered under Part-1 .................................................................. 33

2.5 Part-1 Phase-1 DLF City Subdivision area ....................................................... 34

2.6 Demographic Statistics ..................................................................................... 35

2.7 Electricity Profile of DLF City Sub Division in Gurgaon ..................................... 35

2.8 Scope ............................................................................................................... 37

3 DISTRIBUTION ...................................................................................................... 383.1 Analysis of existing infrastructure and Identification of Challenges .................. 38

4 TRANSMISSION .................................................................................................... 474.1 Analysis and Challenges in Gurgaon transmission network ............................. 47

4.2 Challenges in Gurgaon Transmission System .................................................. 49

4.3 Transmission System Studies .......................................................................... 49

5 DEVELOPING THE SMART GRID ........................................................................ 50

Page 3: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

3

5.1 What is Smart Grid ........................................................................................... 51

5.2 Advanced Metering Infrastructure (AMI) ........................................................... 54

5.3 Peak Load Management (PLM) ........................................................................ 59

5.3.1 DR and DSM for All Consumers ................................................................ 61

5.3.2 Power Quality Improvement .......................................................................... 62

5.4 Distribution Transformer Monitoring Unit (DTMU) ............................................ 64

5.5 Smart Grid Control Centre ................................................................................ 65

6 BENEFITS OF SMART GRID INITIATIVES .......................................................... 666.1 Benefits of Advanced Metering Infrastructure ................................................... 66

6.1.1 Reduction in Meter Reading Cost .............................................................. 66

6.1.2 Reduction in Field and Meter Services ...................................................... 67

6.1.3 Reduction in Off Cycle Trips ...................................................................... 67

6.1.4 Reduction in Outage Field Trip .................................................................. 68

6.1.5 Reduction in Unaccounted Energy ............................................................. 68

6.1.6 Theft / Tamper Detection & Reduction ....................................................... 68

6.1.7 Faster Identification of Dead Meters .......................................................... 69

6.1.8 Improved Distribution System Savings ...................................................... 69

6.1.9 Improved Distribution System Management .............................................. 70

6.1.10 Operational Efficiency Improvement ....................................................... 70

6.1.11 Reduction in Estimated Bills ................................................................... 70

6.1.12 Reduction in Customer Call Volume ....................................................... 71

6.1.12.1 Reduction in Float between Meter Read and Customer Billing ........... 71

6.2 Benefits of Peak Load Management ................................................................. 71

6.3 Other Benefits ................................................................................................... 72

7 SCADA IMPLEMENTATION ................................................................................. 737.1 Components of Grid Automation ...................................................................... 73

7.2 Illustration of automated fault restoration by SCADA ........................................ 73

7.3 Requirement of Software Applications with SCADA ......................................... 77

7.3.1 Distribution Management System(DMS) .................................................... 77

7.3.2 Outage Management System .................................................................... 81

7.3.3 EMS Applications at Smart Grid Control Centre: ....................................... 82

7.3.4 Switching Procedure Management ............................................................ 83

7.4 Benefits of Implementation of SCADA & Software Applications ....................... 84

7.4.1 Leading functionality .................................................................................. 84

Page 4: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

4

7.4.2 Operation and informative presentation of the network .............................. 84

7.4.3 Dependable Operational Safety ................................................................. 85

7.4.4 Intelligent switch order management ......................................................... 86

7.4.5 Reduction in Outage duration .................................................................... 87

7.4.6 Fast and efficient reporting of operational statistics and outages ............... 88

7.5 Implementation of SCADA in project area: Architecture & BOQ ....................... 89

7.5.1 Activities to be performed in Distribution System: ...................................... 90

7.5.2 Common SCADA Control centre ................................................................ 90

7.5.3 Communication Network ............................................................................ 90

7.5.4 Field Equipments ....................................................................................... 91

7.5.5 Components of SCADA Control room ........................................................ 92

8 LOAD FORECASTING UPTO 2031 ...................................................................... 95

8.1 Calculation of Ultimate load of Project area ie DLF City Subdivision up to 2031 for design of proposed electrical network ................................................................... 95

8.2 Load to be fed at 11 KV(Other than DLF V) ..................................................... 96

8.3 Table 8.3 Load to be fed at 66 KV &11 KV ...................................................... 98

8.4 Table 8.4 Load to be fed at Various Voltage levels ....................................... 100

8.5 Table 8.5:Year Wise Load Projection at Existing 03 No. 66/11 KV S-stns. and 07 no. proposed 66/11 KV S-stns.(Other than DLF V) ............................................ 100

8.6 Table 8.6:Total No. of 11 KV feeder to be laid Sstn. wise(Except DLF V) ...... 101

8.7 Table 8.7 :DT Installation schedule to meet out Urban load(Other GHS and Single point connections)for meeting Ultimate Load Up to 2031 .............................. 102

9 NETWORK UPGRADATION & STRENGTHENING ............................................ 1049.1 Proposed Network Up-gradation / Strengthening Initiatives by DHBVN ......... 104

9.1.1 Layout of Existing 11 KV Radial feeders .................................................. 105

9.1.2 Layout of proposed 11 KV Ring Main System .......................................... 106

9.2 Proposed Network Up-gradation/Strengthening Initiatives by HVPN .............. 109

9.2.1 HVPN Proposal for Phase-1 of Part-1 ie for area under DLF City Subdivision ........................................................................................................... 114

9.2.2 Connectivity of Proposed HVPN Sub-stations ......................................... 119

9.2.3 Connectivity of proposed HVPN Sub-stations along with down the level connected lines .................................................................................................... 120

9.2.4 Proposal for Transmission Infrastructure at Various Sub-stations ........... 123

10 COST ESTIMATES & BENEFITS ..................................................................... 13910.1 Estimated Cost of Project (Phase I) ............................................................ 139

10.2 BENEFITS ................................................................................................... 141

Page 5: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

5

10.3 COST BENFIT ANALYSIS .......................................................................... 141

10.3.1 Benefit of Implementation of AMI .......................................................... 141

10.3.1.1 Reduction of AT&C losses ................................................................. 141

10.3.1.2 Reduction in average cost of billing ................................................... 142

10.3.2 Peak Load Management ....................................................................... 142

10.3.3 Outage Management System ............................................................... 142

10.4 Summary of Benefits ................................................................................... 146

11 FINANCING STRATEGY .................................................................................. 14712 STRATEGY FOR IMPLEMENTATION .............................................................. 14913 RECOVERY THROUGH RELIABILITY SURCHARGE ..................................... 15114 CONCLUSION ................................................................................................... 153

Page 6: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

6

1 Executive Summary

1.1 Need of Smart Grid leading to Smart City Energy needs of the country are growing at a very rapid pace. In order to

meet increasing energy demand, amidst growing environmental concerns

as well as energy security issues, we need to increase efficiency in all value

chain viz. generation, transmission & distribution. More importantly,

efficiency need to be increased to a point where we shall actually be using

less energy to power more establishment / businesses. Further, to be

sustainable, we must be able to produce the amount of energy we need,

without much impact on environment like through renewable and other non-

conventional resources. Consumer aspiration on quality supply, as well as

operation in open electricity market regime, integration of renewable energy

sources which are intermittent and variable in nature, are also posing new

challenges which needs to be addressed. Smart Grid offers a solution

towards above challenges. Smart Grid is a confluence of Information,

Communication, Electrical/Digital technologies, integrating all users to

efficiently balance demand and supply over an increasing complex network.

Cities occupy 4% or less of the world’s terrestrial surface, yet they are

home to almost half the global population, consume close to three-quarters

of the world’s natural resources, and generate three-quarters of its pollution

and wastes. The United Nations estimates that virtually all net global

population and economic growth over the next 30 years will occur in cities,

leading to a doubling of current populations. India is also not untouched

with above phenomenon. Our cities are becoming more populated

continuously as people are migrating from rural areas towards urban areas

for more facilities, better life, education and employment. India is urbanizing

at an unprecedented rate so much that estimates suggest nearly 600

million of Indians will be living in cities by 2030, up from 290 million as

reported in the 2001 census. Increasing urban population and

Page 7: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

7

unprecedented load on aged and insufficient infrastructure in our cities has

forced many challenges for fulfilling basic facilities like home, energy,

employment, health, mobility etc. In addition infrastructure to supply

commodities like electricity, water, gas is becoming insufficient to cater

such an inflow of population. Increased living standard of people is resulting

high consumer aspirations and affordability.

Therefore, there is a need for development of smart grid leading to smart

cities, to provide quality life for its citizens for inclusive growth, generate

employment as well as reduce pressure of infrastructure requirement on

other large cities. Strengths of Smart Grid technologies can transform cities

to Smart cities which shall facilitate in increasing human productivity,

realization of inherent urban potential and lesser use of natural resources

per person, information access & processing to improve citizen services

etc.

1.2 Gurgaon Smart Grid Leading to Smart City Gurgaon is one of Delhi's four major satellite towns and is part of the

National Capital Region of Delhi. It has an area of 1253 km² and its

demography provides a gateway for access to many other important towns

of the Northern Region. Its proximity to the capital and the Indira Gandhi

International Airport has caused its urbanization to take place at a much

faster rate in recent years and has effectuated Gurgaon to become a

leading cosmopolitan city of the world. It has also become an industrial and

financial hub of the country with one of the highest per capita income

having been recorded here. The per capita consumption of electricity in

Gurgaon is around 4000 kWh per annum which is expected to increase to

up to 6400 kWh by 2022. Consumers in Gurgaon get electricity from

Dakshin Haryana Bijli Vitran Nigam Limited (DHBVN), one of the

distribution utilities catering to Southern part of Haryana. It is a State

Page 8: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

8

Government owned company and governed by the Board of Directors of

DHBVN appointed by the state government. Gurgaon operation circle is

one of the four operation circles under Delhi zone and is headed by an

officer of the rank of Superintending Engineer. It has three operation

divisions under its jurisdiction:

i. City Division

ii. Sub-Urban Division

iii. Manesar Division

It is for quite some time now that the concept of developing Gurgaon as a

Smart City has been under discussion at the highest levels in the

government, State as well as the Union. On 29th April 2015, Hon’ble Union

Minister of State (Independent Charge) for Power, Coal and New &

Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister

Haryana at the headquarters of Power Grid Corporation of india Ltd.

(PGCIL) Gurgaon wherein it was decided to take all necessary steps to

improve power situation in Gurgaon primarily with the two objectives in

mind to start with. One, to provide 24x7 uninterrupted electricity to all the

consumers and two, to make Gurgaon Diesel Generator free town in a year

and to scale up the infrastructure further to make it a Smart Grid. Among

the various subjects discussed during the meeting, the following three were

thought of as the priorities:

i) Strengthening / Up-gradation / Modernization of Power Transmission,

Sub-transmission & Distribution infrastructure to assure 24x7

uninterrupted Power Supply to all the categories of consumers and to

make Gurgaon Diesel Generator Set Free within next one year

ii) Map Gurgaon through Geographical Information System (GIS)

technology

iii) Smart Traffic & Surveillance Management.

Page 9: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

9

Out of these three priorities, the first one, which can be named as Smart

Grid Project of Gurgaon, relates to DHBVN and HVPN. In accordance with

the deliberations held during the meeting, a preliminary assessment of the

work involved was made by DHBVN, HVPN and PGCIL together. A

presentation in this regard was also made before the Hon’ble Chief Minister

Haryana on 9th June 2015 at New Delhi. Again on 8th

1. To take up Gurgaon town and Industrial Area of Manesar together in

one go would be extremely difficult not only in terms of execution on

the ground but also in terms of arrangement of funds to finance it.

October 2015, the

discussions on smart grid restarted and a meeting was held at Shram

Shakti Bhawan, New Delhi. It was co-chaired by Hon’ble Chief Minister

Haryana and the Hon’ble MoS (IC) Power, Coal and Renewable Energy

Departments, Government of India wherein issue of setting up smart grid in

Gurgaon was discussed at length and to make it an iconic city for rest of the

country to follow. Presentations by PGCIL and Power Department Haryana

were made during the meeting.

Following conclusions were arrived at so far as Smart Grid Project of

Gurgaon is concerned:

2. For the ease of execution, proposal of power Department Haryana to

break up the project in smaller parts was considered an appropriate

approach, which was as under:

a) Part I: Sectors 1 – 57, which is almost fully occupied and we know it

as present day Gurgaon. This part will be taken up first.

b) Part II: Sectors 58 to 115,major portion of which is still vacant, land

with some small constructions coming up here and there. This part

can wait and the work here will be taken up subsequently in next few

years.

c) Part III: IMT Manesar area which does not experience much of the

electricity problems as on date and will be taken up at a later date.

Page 10: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

10

3. The load projections on which the work will be planned will be up to

2030-31

4. The total cost estimations of the project, though assessed at around

Rs. 12000 crores for all the three parts, would be around Rs. 7000

crores for Part I.

5. Part I would further be divided in to 4 phases, as explained under:

a) Phase I: Jurisdictional area of DLF Operation Subdivision of DHBVN,

which lies on left side of Delhi-Jaipur Highway after crossing the toll

plaza and going up to IFFCO chowk

b) Phase II: Jurisdictional areas of South City and Sohna Road

Subdivisions of DHBVN, which lie on the left side of Delhi-Jaipur

highway from IFFCO chowk to almost Kherki Daula toll plaza

c) Phase III: Jurisdictional areas of Maruti and IDC subdivisions of

DHBVN, which lie on the right side of Delhi-Jaipur highway from toll

plaza to Jharsa chowk covering mainly Udyog Vihar and the old city

area including Sadar Baazar etc.

d) Phase IV: Jurisdictional areas of Kadipur, New Colony and New

Palam Vihar S/Ds of DHBVN covering rest of the areas under sectors

1-57.

(Copy of the Minutes of meeting dated 8th

1.3 Phase -1 (Part-1) DLF City Subdivision area

October are annexed at

Annexure A for reference.)

DLF City Sub Division is a medium sized neighbourhood in east Gurgaon

which falls under Gurgaon sub-urban division of Gurgaon Circle. It is an

important residential and commercial hub of Gurgaon and a cosmopolitan

locality with people from all parts of India living in harmony with each other.

The area under DLF subdivision being the most disturbed and most

revenue earning, so far as electricity is concerned, will be taken up in

Page 11: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

11

Phase I to effectuate and adopt advanced smart grid technologies to

improve upon the existing sub-transmission and distribution system. Its cost

has been estimated at around Rs. 1382 crores (Distribution at INR 653

crores + Transmission at INR 702 crores + Consultancy at INR 27 crores)

approximately.

1.4 Demographic Statistics The Demographic profile of the proposed project area “DLF City Sub

Division” in Gurgaon City Division is as under:

Location Area in sq km

Population (Nos.) Average literacy

rate

Population Density

(Nos./km2) Total Urban Rural

DLF Sub

Division

20 Sq.

Km 1.5 lacs 100% 0%

About

90%

7,500 person

/km2

1.5 Electricity Profile of DLF City Sub Division in Gurgaon Profile of DLF City Sub Division in Gurgaon, in the year 2014-15 is as

under:

• 29144 Nos. of consumer with an overall annual consumption of 742

MU

• The peak demand of the area is about 225 MW

• Annual billed Energy is 681 MU and estimated AT&C losses are

11.91%

• 2 Nos. major and 65 Nos. minor transformer failures take place

annually, which are typically attended & restored within 3 hours

• Approx. 1205 Nos. of line outages take place annually, which are

typically attended in 160 minutes.

Page 12: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

12

• The area comprises only of LT and HT consumers. There are 29144

Nos. of consumers. LT Consumers-28926, HT Consumers-218.

• Total Sanctioned load of DLF Sub-Division - 542 MW.

• Total DTs installed under DLF Sub-Division - 732 nos.(Maintained by

DHBVN = 462; Maintained by Single point Consumers = 270)

• Total installed Capacity of DTs of DLF Sub-Division – 464 MVA.

• Total Nos. of existing 11KV Feeders – 88 nos.

• Total Load of existing 11KV Feeders – 225 MW.

• HT line length: 234 km

• LT line length: 444 km

• Load Projection up to FY 2031 for first phase (DLF Sub-Division) for

Smart City Project of Gurgaon City – 784 MW

• Profile of Consumers based on sanctioned load basis

Sr.

No.

Description of load No.s Sanctioned

Load(In MW)

1 Single phase,Load up to 5 KW 9380 28.526

2 Three phase,Load >5 KW and <=20 KW

18602 207.685

3 Three phase,LT CT operated meter, >20 KW and <=69 KW

944 36.361

4 HT 11 KV CT operated meter, > 50 KW

217 269.4

5 HT 66 KV CT operated meter 1*

Total 29144 542

• M/s Rapid Metro has an alternate source of supply at 66 KV Voltage

level in addition to connection at 11 KV voltage level

1.6 Transmission Infrastructure & Challenges Gurgaon has witnessed exponential power demand growth in proportion to

the city's population growth rate. Peak Demand requirement has risen to

1670 MW in 2014-15, which is almost double of last 5-6 years. In order to

Page 13: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

13

meet rising demand, HVPN & DHVBN have taken up a number of steps to

strengthen its Transmission and Distribution network. Presently, Gurgaon

District receives power from two (2) Nos. 400/220 kV Substations namely

Daultabad (945 MVA) & Secor-72 (630 MVA) with cumulative

transformation capacity of 1575 MVA. 400/220kV Panchgaon (1000 MVA)

substation (PGCIL) is commissioned and is being interconnected with 220

kV Panchgaon (HVPN) for dispersal of power. Part of the demand is also

served through 220kV Samaypur, 220kV Pali and 66kV BBMB, Delhi

Substations.

Seven (7) Nos. 220 kV substation [220/66 kV & 220/33 kV] viz. at

Badshahpur, Sector 52A, IMT Manesar, Daultabad, Sector-56, Sector-72 &

BBMB Delhi, with 1860 MVA [220/66 kV-1760 MVA & 220/33 kV-100 MVA]

transformation capacity is utilized to feed DHVBN downstream network in

Gurgaon. Existing Power map of Gurgaon is shown at Fig I-B below

Challenges in Transmission: Presently Gurgaon Transmission network faces challenges like inadequate

redundancy of 220 kV lines as well as transformers (both Power

transformers as well as Distribution transformer). These 220 kV

transmission lines and power transformers get critically loaded especially

during contingency conditions and peak summer.

As per the information available, Gurgaon City witnessed about 1100 MW

peak demand in 2012-13, whereas it increased to 1250 MW & 1400 MW in

2013-14 & 2014-15 respectively, which is about 12-13% annualized growth

rate. Substantial demand growth has already taken place. Therefore,

demand growth at such a rapid pace may not sustain in future and may get

moderated to around 10% per annum in coming years. However, while

carrying out demand growth analysis, demand met through DG (10%) as

well as DLF Gas plant (104 MW), for year 2014-15 has been considered.

Analysis reveals that, peak demand requirement shall increase to about

Page 14: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

14

4800 MW by 2022. To assure 24x7 quality power supply to the model

Gurgaon Smart Grid leading to Smart City, Transmission and Distribution

needs to be strengthened to meet such massive demand requirements.

Based on inputs like demand data (node wise), information about existing

and planned transmission system, network topology etc., studies have been

carried out jointly by HVPN/DHVBN. Transmission system of various

regions including STU networks (220kV and above) available in the study

time frame has been simulated based on the data available with

POWERGRID. Based on studies, Transmission system strengthening

(Zones wise) was evolved which broadly includes following:

• Establishment of new 220kV substation (GIS) to cater to demand

growth as well as to meet requirement of new demand centers

• 220kV Multi circuit Transmission line (High capacity conductor)

(Overhead/Cables)

• Formation of 220kV Transmission ring underlying planned 400kV ring

• Augmentation of Transformation capacity on existing / under

construction / HVPN planned Substations at 220/66 kV & 220/33 kV

level

1.7 Challenges in Distribution: Based on the existing infrastructure constraints, following issues and

challenges have been identified in distribution system of Gurgaon::

• Radial distribution feeders

• Infrastructure Capacity inadequacy

• No redundancy at any level

• Overloading of transformers (around 88% transformer are

overloaded)

• Inadequate reactive compensation (about 20% of the total installed

capacity)

Page 15: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

15

• Absence of SCADA & Automation

• Poor voltage regulation in distribution feeders

• High feeder losses

• Poor power quality situation

• High outage rate at 11kV feeder level, SAIFI (System Average

Interruption Frequency Index) is 84 nos. and SAIDI (System Average

Interruption Duration Index) is 451 Minutes

• Capex approved for 2015-16 by HERC (Rs 373 Cr., considering 33%

of total capex approved for DHBVN, apportioned by revenue

percentage) is not sufficient to create infrastructure for ensuring 24x7

supply.

1.8 Objectives of the Project Main objective of this report is to analyze present system and adoption of

Smart Grid technologies and distribution network up-gradation /

strengthening measures that will improve the performance of distribution

system of DLF City Sub Division in Gurgaon and will ensure 24×7 reliable

power supply to the consumers. Efficacy of these advanced

technologies of the modern era will empower consumers to participate in

energy management process and shall make distribution system more

efficient. With these aspects in view, following objectives have

beenoutlined for development of Smart Grid at DLF City

SubDivisionin Gurgaon to:

• Ensure 24x7 power supply to all the consumers

• To make Gurgaon city DG Set free

• Increase in billed energy and reduction in AT & C losses.

• Empowerment of consumers to participate in the energy

management.

• Improvement in reliability by reduction in outage rate and duration

• Improved administration decision making through GIS tools

Page 16: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

16

• Smart Transport and Traffic Management

• Increase in customer satisfaction and consumer awareness

• Propose Smart Grid technologies, which would facilitate efficient,

accurate & effective online recording & monitoring of the energy

exchanges in distribution system to reduce AT&C losses and

operational errors viz. reading error, bias error, typographical errors

etc. caused by involvement of human elemen

• Actuate empowerment of consumers to participate in the energy

management process

• Implement technologies that will enhance quality of power at doorstep

of consumers and will help in proper monitoring of assets for

extended life

• Efficient system operation by better load management

• Enable high level of customer satisfaction and increased awareness

Augmentation of existing distribution system and improvement of

commercial performance is a continuous process, requiring periodic

reviews based on the target achieved. Accordingly, present report covering

complete details of the area in terms of existing assets, present technical

and commercial performance, IT solutions, smart grid technology

deployment; would serve as a base report for implementation of Smart grid

in DLF City Sub Division. The distribution system of project area shall be

shaped like a model Smart Grid by implementation of Smart Grid

Technologies like Advanced Metering Infrastructure (AMI), Peak Load

Management (PLM), Power Quality Management (PQM), and State-of-the-

Art communication system atop existing infrastructure.

1.9 Proposed Strengthening of Infrastructure To mitigate above challenges and to achieve the objectives, following

measures and applications are proposed as under:

Page 17: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

17

• New 220/66/11 kV and 66/11 kV substations (GIS) for transfer of load

from existing overloaded substations with N-1 redundancy

• Augmentation of existing 66/11 kV substation to address ‘N-1’

redundancy

• Conversion of overhead system to underground cable. To start with

11 kV network will be taken up, which will be subsequently scaled

down to LT lines.

• Formation of 11 kV ring main by installing RMU (Ring Main Units)

• SCADA (Supervisory Control and Data Acquisition) and OMS

(Outage Management System).

• Optic Fibre Cable up to Distribution Transformer for bidirectional

communication between Consumer and utility

• Advanced metering system covering 4.4 lacs consumer till 2022.

• Load management at consumer level through Demand response and

Demand side management.

• Payment linked load shedding

• Integration of proposed system with R-APDRP

• Regulatory mechanism for Time of day tariff for all category of

consumers, tariff rationalization and mandatory energy efficiency

measures compliances

• The complete ownership for operation and maintenance will be with

DHBVN and HVPN, as the case may be, even in builder area after

the installation and commissioning of the new system.

• The existing street lights in the city and especially in the bye-lanes

are on DHBVN LT poles which will be removed when system gets

converted to underground and new underground street light system

will be laid alongwith the electrical system for which the concerned

department ie HUDA/MCG will bear the cost and deposit with

DHBVN.

Page 18: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

18

• The operation and maintenance of newly installed system for atleast5

years after commissioning will be in the scope of executor

1.10 Estimated Cost of Project (Phase I) Sr.No.

Description/ Major head of items

Unit Quantity Unit Rate

Total Supply Cost

Total Supply Cost +15%

Erection Total (In Lacs)

In Lacs

DISTRIBUTION DHBVN

1 HT Cables (Various Sizes)

KM 281.42 4642.12 5338.45 232.11 5570.55

2 LT UG Line (Various sizes)

KM 1923.07 5433.16 6248.14 271.69 6519.83

3 LT Feeder Pillar

No.s 7451 11485.49 13208.31 229.70 13438.02

4 RMU(Ring Main Units) with FRTU & FPI

No.s 563 3753.98 4317.08 750.07 4392.16

5 Distribution T/F(11KV/.433KV)

No.s 240 2162.13 2486.44 43.24 2529.69

6 Optical Fiber and PLB-HDPE Pipe

KM 259 280.477 322.54 14.02 336.57

7 Street Light No.s 11000 4395.35

8 Civil work for foundation of DT/RMU/FP etc

No.s 8394 1189.96 1189.96

9 Civil work for underground laying of cable/optical fiber

Mtr. 1043000 3563.50 3563.50

Page 19: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

19

10 Fencing R/ Mtr

9711 322.79 371.21 32.27 403.49

11 RCC slabs and route markers

No.s 905430 1883.00 2165.45 37.66 2203.11

12 PSS No.s 15 409.98 471.47 8.19 479.67

13 Cost of other minor items/works

L/S 991.14 1139.81 128.1 1267.91

14 5 years O & M 4152.73

Sub-Total 50442.32

SCADA & OMS/ADMS

1 SCADA & OMS along with civil work required for the project

lot 1

10055

AMI(including DTMU’s)

1 Field Equipment for AMI & PLM

lot 1

3409

2 IT System and Integration for AMI & PLM

lot 1

672

3 Field equipment for PQM & DTMU

lot 1 756

4 Consumer Education and Awareness

lot 1 10

10

Sub-Total 4847

Total DHBVN -A 65344.32

TRANSMISSION-HVPN

1 Substations & Lines

70182

TOTAL (HVPN) - B 70182

Page 20: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

20

Total Consultancies Charges – C (2% of (A+B)) 2710.52

GRAND TOTAL (A+B+C) 138236.8

1.10.1 Estimated Cost of Substation and lines Sr. No. Description Unit Qty. Unit cost

(In Cr.) Total cost (In Cr.)

1 Establishment Cost of each 220 KV Sub-Station No. 2 10 20

2 Land Cost of each 220 KV Sub-Station No. 2 10 20

3 220/66 kV, 160 MVA transformer No. 6 7 42

4 220 /66 kV, 160 MVA Transformer bay (GIS) No. 6 9 54

5 220 kV Line bays-(GIS) No. 8 9 72

6 220 kV Bus Coupler Bay-(GIS) No. 2 9 18

8 Establishment Cost of each 66 KV Sub-Station No. 6 2 12

9 Land Cost of each 66 KV Sub-Station No. 6 5 30

10 66/11 KV, 25/31.5 MVA T/F No 24 1.5 36

11 66 /11 kV, 25/31.5 MVA Transformer bay (GIS) No. 24 1.5 36

12 66 kV Line bays-(GIS) No. 44 1.5 66.00

13 66 kV Bus Coupler Bay-(GIS) No. 8 1.5 12

14 66 KV I/C Bays (GIS) No 6 1.5 9

15 66 KV Capacitor Bays No. 6 1.5 9

16 Providing additional 25/31.5 MVA T/Fs No. 4 1.5 6

17 11 kV (GIS) panel set comprising of two incomers, two capacitors, two substation & eight VCBs of outgoing feeders.

No. 410 0.08 32.8

18 220 kV M/C line on M/C Towers with HTLS Conductor.

Ckt. Km 8.5 2.6 22.10

19 220 kV D/C line on Underground XLPE Cable 1000 Sq.mm including laying

Ckt. Km 6 20 120

Page 21: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

21

20 66 kV D/C XLPE underground aluminium 1200 sq. mm cable including laying

Ckt. Km 32.51 2 65.02

21 Replacement of Existing Moose ACSR Conductor with HTLS Conductor.

Ckt Km 2 1.25 2.50

22 Dismantlement of Existing AIS 66 KV Sub-Stations at DLF Q- Block and Sec-28, Gurgaon.

No 2 0.5 1

23 Creation of 220 KV D/C line with HTLS Conductor.

Ckt. Km 9 1 9

24. Creation of 220 KV AIS Bays No 2 3.10 06.20

25. Creation of 66 KV Bays ( AIS) No 2 0.60 1.20

Total 701.82 say 702 Cr.

Copy of Detailed estimate is placed as Annexure-B

1.11 Financing Strategy For making an estimated expenditure of Rs. 1382 crores, the funding

mechanism proposed is as under:

1. The Ministry of Power has sanctioned 25% of the project cost as

grant/equity by GOI, which comes to 1382 x 0.25 = Rs. 345.5 Crores.

2. Expenditure is proposed to be made in two (2) years i.e. 2016-17 and

2017-18 expectedly in the ratio of 30:70 percent respectively.

3. The balance Rs. 1036.5 crores is proposed to be arranged as loan

from PFC, a part or total of which will be arranged as equity from the

Haryana Government. It is shown in tabulated form as under:

It is shown in tabulated form as under:

Arrangement of Funds

1st 2 Year (2016-17)

nd Total (in crores)

Year (2017-18)

Grant from MoP (GoI)

103.65 241.85 345.5

Loan from PFC 310.95 725.55 1036.5 TOTAL 414.6 967.4 1382

Page 22: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

22

1.12 Implementation strategy and ownership The work shall be awarded through open tendering on the basis of

per unit cost of each item and shall be awarded to the firm who quotes the

lowest premium. The turnkey contractor will carry out the detailed survey in

the field before execution of work. The work shall be awarded on “Concept

to Commissioning”basis with at least five year’s post commissioning

operations and maintenance. The ownership of the new system after

commissioning will be of DHBVN.

The work shall be executed in phased manner without disturbing the

existing distribution/transmission system. After laying of new system the

connectivity of the newly laid system with old system shall be done in one

go, so that the supply to the consumers is minimally affected.On the DT

side, the 11 kV new line alongwith the DTs shall be installed first and

thereafter the load shall be shifted on the newly laid DTs. Other associated

LT underground works shall be carried out in parallel.

1.13 Reliability Surcharge Considering that this scheme will improve reliability through 24x7

power supply as well as making Gurgaon city DG sets free, it is proposed

that a reliability charge may be levied in the tariff for all the categories of

consumers. The reliability charge would be used to service debt, O&M and

provide return on equity for the investment. Proposed reliability charge will

be uniformly levied @ Rs. 0.50 on domestic category consumers including

Bulk Supply Domestic and @ Rs. 0.60 per unit of consumption on all other

categories of consumers. However, the expected return against levy of this

reliability surcharge has been estimated @ Rs. 0.55 on all categories, as

the consumption of domestic category including Bulk Supply Domestic

consumers and other categories consumers are equal in DLF Sub-Division.

Page 23: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

23

1.14 Cost Benefit Analysis It is anticipated that after arranging the funds through Grant by GoI

and Loan from PFC, recovery through reliability charges would make the

returns better:

Expected benefits per year from above mentioned smart grid initiatives are

and the recovery in shape of Reliability Charge is summarized in table

below:

Benefits during Year 2017

Sr. no.

Initiative Benefits

(in Rs. Cr. Per year)

1 Advanced Metering Infrastructure (AMI) 15.40

2 Peak Load Management(PLM) 4.10

3 Outage Management System (OMS) 2.60

4 Recovery by levying Reliability Charge 60.00

Total 82.10

Benefits during Year 2031

Sr. no.

Initiative Benefits (in Rs. Cr. Per year)

1 Advanced Metering Infrastructure (AMI) 49.14

2 Peak Load Management(PLM) 13.08

3 Outage Management System (OMS) 8.30

4 Recovery by levying Reliability Charge 184.00

Total 254.52

Page 24: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

24

2 BACKGROUND 2.1 SMART CITY GURGAON - The Concept It is for quite some time now that the concept of developing Gurgaon as a

Smart City has been under discussion at the highest levels in the

government, State as well as the Union. On 29th

1. Strengthening / Up-gradation / Modernization of Power Transmission,

Sub-transmission & Distribution infrastructure to assure 24x7 Power

Supply to all categories of consumers

April 2015, Hon’ble Union

Minister of State (Independent Charge) for Power, Coal and New &

Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister

Haryana at Power Grid (PGCIL) Gurgaon wherein it was decided to

improve power situation in Gurgaon primarily with the two objectives to start

with i.e. to provide 24x7 electricity to all categories of consumers and to

make Gurgaon a Generator free city within next one year and subsequently

scaling up the up-gradation to make it a Smart City. The Union Minister

called upon PGCIL to take the lead as Nodal Agency and prepare a road

map in this regard. Among the various subjects discussed during the

meeting, the following three were prioritized as the necessary ones to start

with:

2. Map Gurgaon through Geographical Information System (GIS)

technology

3. Smart Traffic & Surveillance Management.

Gurgaon has earned the distinction of being one of the fastest growing

cities in the country, so far as electricity is concerned. The data shows that

electricity consumption in Gurgaon, especially after 2000-01 has been

increasing at a comparatively higher rate of 12-13% per annum meaning

thereby that the demand has been getting almost doubled every five years.

Even today, the growth does not seem to have slowed down. That is why it

Page 25: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

25

has not been possible to erect the distribution system commensurate with

the demand. Whatever expenditure has been done in the past got

consumed just on the addition of infrastructure, mainly the addition of DTs

and it has not been possible to augment or repair the existing network at all.

As a result, the existing infrastructure gradually became overstretched and

overloaded, demanding an exhaustive overhauling not only in terms of

extension of network but also forcing us to think about creation of more

220/66/11 KV or 66/11 KV S-stns. at load centres.

Before proceeding further, we shall need to understand the physical and

geographical divisions which can be hypothetically chosen for the ease of

carrying out the development work under the smart city project. Broadly

speaking, Gurgaon can be divided in to two major zones. One is Sectors 1

to 57 and the other is from Sectors 58 to 115. Interestingly, Sectors 1 to 57

are almost fully occupied forming the present day Gurgaon whereas

Sectors 58 to 115 are almost unoccupied. Let’s take up these two divisions

one by one:

Sectors 1 to 57

Delhi-Jaipur highway, which is passing through the middle of sectors 1 to

57 provide a natural zoning of the city and is required to be planned

accordingly. Old Gurgaon is comparatively more congested with major

right-of-ways problems would require a detailed engineering at micro level

for laying, augmentation and to provide additional infrastructure to combat

future growth while it is comparatively less cumbersome in new Gurgaon to

carry out the development works and erect new feeders.

Presently, the distribution network in sectors 1 to 57 is 220 / 66 / 11 / 0.435

kV on radial 11 kV distribution feeders having least reliability and the

complete feeder is vulnerable to outages anywhere in the sections The

reliability requirement can only be taken care only if the feeders are in ring-

main mode.

Page 26: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

26

In case of any fault in any one of the feeders, the supply to consumers can

not be restored unless the fault is attended. Most of the feeders are

overloaded and require bifurcation to take up the load growth from time to

time. 66 kV substations are also overloaded and it may not be possible for

further capacity additions at these substations to take up the demand after

2017-18.

Total urban area in Gurgaon is being fed through are 525 nos. out of which

around 250 are urban feeders and 275 are independent feeders of the

group housing societies, commercial establishments, industry and some

government departments. Sectors 58 to 115

This is being called greater Gurgaon spread all across and around sectors

1 to 57. Development in these sectors has just started at some selected

locations but broadly speaking, it is yet to kick off. Almost all the land,

around 27000 acres in area, is owned by different builders / developers and

most of the development in these sectors is likely to come up in the shape

of multi-storey buildings and GHS. Therefore, the electricity load in these

sectors is expected to be much higher as compared to the sectors

developed by HUDA and HSIIDC. Expecting a lot of construction activity

and the demand, 11 kV distribution system was not thought of as the

adequate one to cope with. Therefore, a conscious decision has been

taken to introduce 220 / 33 / 0.435 kV system in these upcoming sectors.

The Union Minister during the meeting in April 2015 called upon the District

Administration and all the departmental heads in Gurgaon to co-ordinate

and associate with PGCIL for implementation and completion of the project

in a period of one year. The PGCIL, in the process, held some preliminary

meetings with the different departmental heads including DHBVN and

HVPN and collected the basic data for the purpose of analysis and

preparation of a Detailed Project Report (DPR).

Page 27: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

27

Following are the few challenges in Gurgaon, the cognizance of

which needs to be taken at the time of conceiving of the project::

1. Old Gurgaon, which is located on the right side of Delhi-Jaipur

highway, has a peak demand of more than 700 MVA (nearly 50% of

total demand) and is highly congested with no right of ways available

for further laying of 11 kV feeders; neither overhead nor underground.

2. To meet the future load growth as well as providing 24x7 power

supply is very difficult to maintain without changing the voltage level

from 11 kV to 33 kV, wherever possible, at most of the congested

places..

3. New 33 or 11 kV systems shall have to be laid in advance before

dismantling/upgrading the present system which would require

sufficient land and right-of-ways for 66/11 or 33/11 kV or 11 KV

switching stations and lines, whether overhead or underground.

4. There are underground pipelines of other utilities also like water,

sewage, telecom, gas etc. which will not allow the underground

electricity cables to be laid so easily.

Primary Bottleneck in establishment of Smart Grid: Inadequate Electrical Infrastructure

It is the up-gradation of distribution system which is the major area of

concern. Not only that the existing system is badly overstretched and

overloaded, there are no right-of-ways available from where the bifurcation

can be planned.There are a number of inadequacies in existing electrical

infrastructure which makes it unsuitable to adopt Smart Grid initiatives like

automated control through SCADA,AMI implementation, roof top SPVs

integration etc.Some of inadequacies which needs to be addressed before

introduction of Smart grid initiatives are as follow:

• Most of the feeders are running Overhead, multiple circuit per

poledue to non-availability of right of way.Conversion of existing

Page 28: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

28

Overhead network to underground network is first requirement of this

project to make feeders fault free,reduce down-time of feeders,

address existing and future problem of right of way in rapidly

urbanising Gurgaon town and to make the electrical network robust

for adoption of smart grid features.

• Air-break switches(GO switches) get damaged frequently due to

weathering,have less useful life, are not reliable and safe for

operation of higher DT capacity.Replacement of Air-break

switches(GO switches) with RMUs is second requirement of electrical

infra. to ensure automatic isolation of faulty sections,safety of network

and quick response to SCADA

• Snapping of 11 kV as well as LT conductor is a normal

feature.Conversion of overhead network to underground network will

avoid such scenario

• Radialfeeders which disallow back feeding of a faulty feeder due to

absence of ring main system of feeders

• Insufficient redundancyat 11 KV and DT level which is required to be

enhanced to 100% to successful operation of 11 KV Ring Main

System

• These all features make the whole distribution system so vulnerable

to breakdowns and tripping that the consumers’ dream of getting

uninterrupted power supply with smart features has remained a

dream. There are cities in India where breakdowns and tripping are

almost nil, transformer damage rate is almost zero and there is

almost a 100% redundancy at distribution level.In most of the best

distribution utilities in India, Underground network in Urban areas has

already been proven a success over overhead network enabling

these utilities to successfully introduce concepts of SCADA and other

features of Smart Grid.

Page 29: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

29

All these features will lead to establishment of Smart Grid and Smart City

so far as electricity is concerned.

Therefore, there is a need for development of smart grid leading to smart

cities, to provide quality life for its citizens for inclusive growth, generate

employment as well as reduce pressure of infrastructure requirement on

other large cities. Strengths of Smart Grid technologies can transform cities

to Smart cities which shall facilitate in increasing human productivity,

realization of inherent urban potential and lesser use of natural resources

per person, information access & processing to improve citizen services

etc.

2.2 Gurgaon Smart Grid Leading to Smart City Gurgaon is one of Delhi's four major satellite towns and is part of the

National Capital Region of Delhi. It has an area of 1253 km² and its

demography provides a gateway for access to many other important towns

of the Northern Region. Its proximity to the capital and the Indira Gandhi

International Airport has caused its urbanization to take place at a much

faster rate in recent years and has effectuated Gurgaon to become a

leading cosmopolitan city of the world. It has also become an industrial and

financial hub of the country with one of the highest per capita income

having been recorded here. The per capita consumption of electricity in

Gurgaon is around 4000 kWh per annum which is expected to increase to

up to 6400 kWh by 2022.

Consumers in Gurgaon get electricity from Dakshin Haryana Bijli Vitran

Nigam Limited (DHBVN), one of the distribution utilities catering to

Southern part of Haryana. It is a State Government owned company and

governed by the Board of Directors of DHBVN appointed by the state

government. Gurgaon operation circle is one of the four operation circles

under Delhi zone and is headed by an officer of the rank of Superintending

Engineer. It has three operation divisions under its jurisdiction:

Page 30: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

30

i. City Division

ii. Sub-Urban Division

iii. Manesar Division

On 8th

1. To take up Gurgaon town and Industrial Area of Manesar together in

one go would be extremely difficult not only in terms of execution on

the ground but also in terms of arrangement of funds to finance it.

October 2015, a meeting was held at Shram Shakti Bhawan, New

Delhi. It was co-chaired by Hon’ble Chief Minister Haryana and the Hon’ble

MoS (IC) Power, Coal and Renewable Energy Departments, Government

of India wherein issue of setting up smart grid in Gurgaon was discussed at

length and to make it an iconic city for rest of the country to follow.

Presentations by PGCIL and Power Department Haryana were made

during the meeting.

Following conclusions were arrived at so far as Smart Grid Project of

Gurgaon is concerned:

2. For the ease of execution, proposal of power Department Haryana to

break up the project in smaller parts was considered an appropriate

approach, which was as under:

a) Part I: Sectors 1 – 57, which is almost fully occupied and we know it

as present day Gurgaon. This part will be taken up first.

b) Part II: Sectors 58 to 115,major portion of which is still vacant, land

with some small constructions coming up here and there. This part

can wait and the work here will be taken up subsequently in next few

years.

c) Part III: IMT Manesar area which does not experience much of the

electricity problems as on date and will be taken up at a later date.

d) The load projections on which the work will be planned will be up to

2030-31

Page 31: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

31

e) The total cost estimations of the project, though assessed at around

Rs. 12000 crores for all the three parts, would be around Rs. 7000

crores for Part I.

f) Part I would further be divided in to 4 phases, as explained under:

i) Phase I: Jurisdictional area of DLF Operation Subdivision of DHBVN,

which lies on left side of Delhi-Jaipur Highway after crossing the toll

plaza and going up to IFFCO chowk

ii) Phase II: Jurisdictional areas of South City and Sohna Road

Subdivisions of DHBVN, which lie on the left side of Delhi-Jaipur

highway from IFFCO chowk to almost Kherki Daula toll plaza

iii) Phase III: Jurisdictional areas of Maruti and IDC subdivisions of

DHBVN, which lie on the right side of Delhi-Jaipur highway from toll

plaza to Jharsa chowk covering mainly Udyog Vihar and the old city

area including Sadar Baazar etc.

iv) Phase IV: Jurisdictional areas of Kadipur, New Colony and New

Palam Vihar S/Ds of DHBVN covering rest of the areas under

sectors 1-57.

(Copy of the Minutes of meeting dated 8th October are annexed at

Annexure

A for reference.)

Page 32: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

32

2.3 Geographical Map of Gurgaon under Smart Grid

Page 33: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

33

2.4 Sectors to be covered under Part-1

Page 34: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

34

2.5 Part-1 Phase-1 DLF City Subdivision area DLF City Sub Division is a medium sized neighbourhood in east Gurgaon

which falls under Gurgaon sub-urban division of Gurgaon Circle. It is an

important residential and commercial hub of Gurgaon and a cosmopolitan

locality with people from all parts of India living in harmony with each other.

The area under DLF subdivision being the most disturbed and most

revenue earning, so far as electricity is concerned, will be taken up in

Phase I to effectuate and adopt advanced smart grid technologies to

improve upon the existing sub-transmission and distribution system. Its cost

has been estimated at around Rs. 1382 crores (Distribution at INR

653crores + Transmission at INR 702 crores + consultancy charges at INR

27 crores) approximately.

Page 35: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

35

2.6 Demographic Statistics The Demographic profile of the proposed project area “DLF City Sub

Division” in Gurgaon City Division is as under:

Location Area in sq km

Population (Nos.) Average literacy

rate

Population Density

(Nos./km2) Total Urban Rural

DLF Sub

Division

20 Sq.

Km 1.5 lacs 100% 0%

About

90%

7,500 person

/km2

2.7 Electricity Profile of DLF City Sub Division in Gurgaon Profile of DLF City Sub Division in Gurgaon, in the year 2014-15 is as

under:

• 29144 Nos. of consumer with an overall annual consumption of 742

MU

• The peak demand of the area is about 225 MW

• Annual billed Energy is 681 MU and estimated AT&C losses are

11.91%

• 2 Nos. major and 65 Nos. minor transformer failures take place

annually, which are typically attended & restored within 3 hours

• Approx. 1205 Nos. of line outages take place annually, which are

typically attended in 160 minutes.

• The area comprises only of LT and HT consumers. There are 29144

Nos. of consumers. LT Consumers-28926, HT Consumers-218.

• Total Sanctioned load of DLF Sub-Division - 542 MW.

• Total DTs installed under DLF Sub-Division - 732 nos.(Maintained by

DHBVN = 462; Maintained by Single point Consumers = 270)

• Total installed Capacity of DTs of DLF Sub-Division – 464 MVA.

• Total Nos. of existing 11KV Feeders – 88 nos.

Page 36: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

36

• Total Load of existing 11KV Feeders – 225 MW.

• HT line length: 234 km

• LT line length: 444 km

• Load Projection up to FY 2031 (DLF Sub-Division) for Smart City

Project of Gurgaon City – 784 MW

• Line Loss Trend (%)

Page 37: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

37

• Future Load Projection (MW) of DLF City Subdivision

2.8 Scope Broadly, the scope of work under the proposed project covers the

following:

• Analysis of present Transmission and Distribution system

• Identify issues and constraints and propose remedy for the same

• Identify various smart grid technologies to address areas of concern

• Prepare BOQ, cost estimates along with benefits

• Arrangement of Finances

• Bidding Process and Award of Contracts

• Execution & Supervision

315

528585

784

0

100

200

300

400

500

600

700

800

900

2015 2020 2025 2031

Load

in M

W

Year

Peak Load in MW

2015

2020

2025

2031

Page 38: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

38

3 DISTRIBUTION 3.1 Analysis of existing infrastructure and Identification of

Challenges

DHBVN is one of the good distribution utilities in India, who have set the

best standards in operational practices. The distribution business in

Gurgaon is running at comparatively low AT&C losses which reflect the

efforts made in the recent past to bring down the losses and to ensure high

collection efficiency. However, on front of ensuring reliable and quality

power supply to its consumers 24×7, DHBVN is lagging in some areas of

Gurgaon due to various reasons. Factors hampering DHBVN performance

in ensuring reliable and quality power supply in Gurgaon despite the

availability of surplus power in the state are listed below:

1. Radial electrical Network

Electrical network at 11 kV voltage level in Gurgaon is a radial network

which practically means that the 11 kV feeders emanating from a 220/66/11

kV substation feed their respective areas in isolation and in case of any

fault occurring in the line, the whole area gets switched off till such time the

fault is attended. Also, since there is no-ring main system at 11 kV level,

there is hardly any possibility of restoring the supply on any section through

feeding back from another source.

2. Policy of Independent feeder

As per existing policy of DHBVN, a consumer can opt and demand for

single point supply on 66KV/33KV/11KV feeder if the sanctioned load is

250 kVA or more. However, due to the commercial constraint of billing of

consumer from Substation end, it is not possible to back feed the load of

consumer in case of a fault in main feeder of consumer.

Page 39: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

39

3. Non-availability of Right-of-Way

At present, because of a large number of Urban and Independent feeders,

right-of-way for erection of a new feeder is extremely difficult and not at

possible in most of the cases.

. 4. Multiple 11 kV Feeders on a Pole

Because of erection of multiple feeders on single pole because of right-of-

way problems and congestion, permit to work (PTW) has to to be taken on

all the feeders running on a pole with multiple circuits, idf fault occurs in any

of these bunched feeders. It leads to unnecessary loss of sale of power and

reduces reliability of supply.

5. Absence of provision for back-feeding LT network

In case of fault in a distribution transformer, there is no provision for back

feeding the related LT lines emanating from the secondary side of a

distribution transformer.

6. Manual Fault Rectification

Process of identification, isolation and back feeding of faulty portion of a

feeder is manual. It takes long outage durations and reduces reliability of

power supply.

7. Unregulated Constructions

There are certain pockets in Gurgaon City Like DLF Phase-III U Block

where plot owners are building plots up to 7 storeys on plot size measuring

as low as 60 sq. yards or even 40 yards. Because of these types of

unregulated constructions, load is growing in an unpredictable and

exponential manner. DHBVN is not able to keep up pace with load growth

in such pockets due to unavailability of land for creation of new Plinth

Page 40: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

40

mounted / Pole mounted substations. Unless construction in such areas is

regulated by DTCP/Municipal Corporation, load requirement of these areas

will always create pressure on existing electrical infrastructure.

Other Challenges include Capacity Inadequacy, Inadequate reactive

compensation, absence of SCADA & Automation, Poor voltage regulation

in distribution feeder, overloading of transformers and most of all, no

redundancy level at all.

Existing electrical infrastructure and shortcomings are illustrated below:

Fig. A: 7 Storey building under construction on a 60 sq.yd. plot in U Block DLF-III

Page 41: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

41

Fig. B:Other Multi storey buildings under construction on 60 sq.yd. plots in U Block DLF-III

Page 42: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

42

Fig C: Multiple 11 KV Feeders on same poles

Page 43: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

43

Fig. D: Right of way problem due to Multiple 11 KV Feeder Networks

Page 44: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

44

Fig. E: Narrow Lanes leading to issue to safe Horizontal clearance

Page 45: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

45

Fig.F: Open H-Pole substation posing a threat to human and stray animals life

Fig G: Multiple LT Networks passing through LT Poles

Page 46: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

46

Fig. H: Overcrowded LT Poles with meters and Outgoing Service Lines

Page 47: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

47

4 TRANSMISSION

4.1 Analysis and Challenges in Gurgaon transmission network Gurgaon has witnessed power demand growth in proportion to the city's

population growth rate. Peak Demand requirement has risen exponentially

in past one decade. In order to meet the rising demand, a nos. of steps has

been taken up to strengthen its Transmission and Distribution network.

Presently, Gurgaon receives power from two (2) Nos. 400/220 kV

Substations namely Daultabad (945 MVA) & Secor-72 (630 MVA) with

cumulative transformation capacity of 1575 MVA. 400/220 kV Panchgaon

(1000 MVA) substation (PG) is commissioned and is being interconnected

with 220 kV Panchgaon (HVPN) for dispersal of power. Part of the demand

is also served through 220 kV Samaypur, 220 kV Pali and 66 kV BBMB,

Delhi Substations.

Power Supply feeding points for Gurgaon

Page 48: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

48

The Gurgaon city has 3,70,797 consumers having peak

demand of 1400 MW

Power is dispersed through Seven (7) 220 kV substation

(220/66 kV & 220/33 kV) at

Badshahpur,

Sector 52A,

IMT Manesar,

Daultabad,

Sector-56,

Sector-72 &

BBMB Delhi,

1860 MVA [220/66 kV, 1760 MVA & 220/33 kV - 100MVA].

Further in the downstream network, thirty four (34) nos. 66 kV

substations with installed capacity 1991 MVA transformation

capacity feed power to DHVBN in Gurgaon. Existing power

supply arrangement of Gurgaon

Page 49: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

49

4.2 Challenges in Gurgaon Transmission System Presently Gurgaon Transmission network faces challenges like inadequate

redundancy of 220 kV lines as well as power transformers. These 220 kV

transmission lines and power transformer get critically loaded during

contingency conditions and peak summer.

4.3 Transmission System Studies Gurgaon City witnessed about 1100 MW peak demand in 2012-13,

whereas it increased to 1250 MW & 1400 MW in 2013-14 & 2014-15

respectively, which is about 12-15% annualized growth rate. Demand

growth at such a rapid pace may not sustain in future and may get

moderated to about 8-10 % p.a. in coming years. However while doing

demand growth analysis, demand met through DG (10%) as well as DLF

Gas plant (104 MW), for year 2014-15 has been considered. Analysis

reveals that, peak demand requirement shall increase to about 3500 MW

by 2022.

To assure 24x7 quality power supply to the model Gurgaon Smart City,

Transmission and Distribution needs to be strengthened to meet massive

demand requirements rising on day to day basis with the horizontal and

vertical growth of the city. In this regard, based on inputs like demand data

(node wise), information about existing and planned transmission system,

network topology etc., detailed system studies have been carried for

planning of transmission system considering peak demand scenario by

HVPN.

.

Page 50: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

50

5 DEVELOPING THE SMART GRID

In this era of advent of modern technology into the electrical system, it is

possible to make the present system more robust and economically viable

simultaneously using Smart Grid technologies and IT interventions. These

technologies co-ordinate the needs and capabilities of all the stakeholders

of power supply chain viz. generators, grid operators, distributor, end users

and facilitate electricity market in a way to optimize asset utilization,

resource optimization, control and operation with minimum losses and

enhanced quality. This ensures more reliable power along with smart

utilization of available technology to make the today’s cumbersome and

sophisticated activities easier and accurate. Most importantly, consumer

satisfaction becomes the ultimate motto and customers are empowered to

interact with the utility. Therefore smart grid technologies in the field of

Monitoring & Measurements, Communication, Control & Automation, IT

infrastructure, energy efficiency etc. shall be integrated with present system

at DLF City Sub Division in Gurgaon.

Page 51: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

51

5.1 What is Smart Grid Typical structure of the Smart Grid is shown at Figure-1.

Figure-1: Typical smart grid structure

Major intelligent enabling technologies which are building blocks of the

“Smart Grid” are given as under:

• Advanced Metering Infrastructure: It consists of Smart Meters,

Communication Network, Head End equipment, Meter Data

Management System and Analytics. It enables online energy

consumption visualization and helps in controlling leakages of power by

facilitating immediate temper alert and short duration energy audits.

Efficiency of system is also improved through enablement of automated

Page 52: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

52

reading, demand response, remote load dis/re-connection, control of

critical & non-critical loads etc.

• Integrated Communication System: Communication system

comprising of optical fibre network, GPRS, RF Mesh, PLC etc., utilized

by various Smart Grid Technologies for communication of data &

information between control centre and consumers / equipment.

• Peak Load Management: Using advanced metering infrastructure

information, peak load management is done by way of variable intra-day

tariff, load curtailment, device control mechanisms etc.

• Outage Management System: It increases reliability of the power

supply and reduces outage frequency & duration. Faults types &

locations are automatically reported to control centre and maintenance

crew is dispatched in optimized way directly to fault location depending

upon location of team & fault. Also various monitoring devices are

installed which help in checking healthiness of equipment.

• Renewable Energy: It is an essential part of Smart grid to reduce the

dependency on conventional resources and to make cities more

sustainable and clean.

• Distributed Generation: Distributed resources like solar, biomass,

wind etc. reduce transmission and distribution grid requirements and

feed loads directly.

• Energy Storage: Energy Storage helps in balancing intermittency,

uncertainty and variability of renewable resources in any grid and make

them more stable & secure.

• Electric Vehicle: Use of electric vehicles reduces CO2 emission by

transportation sector and make environment healthier. It also helps in

grid balancing as it may be used to absorb excess power in grid, or to

Page 53: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

53

supply power back to grid at peak times through enabling of suitable

market mechanisms.

• Power Quality Management: Sensors & equipment installed at

different nodes of Smart Grid measures power quality and activate

suitable mitigation techniques to make power free with electrical

pollution.

The various attributes of Smart Grid are as shown in the Figure 2 on the

next page

Figure 2: Smart grid attributes

Implementations of various technologies of Smart Grid in DLF City Sub

Division have been discussed with DHBVN. Considering present system

Page 54: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

54

architecture and progression of initiatives like R-APDRP, it is emerged that

following Smart Grid attributes/technologies would be appropriate for

implementation in DLF City Sub Division:

(i) Advanced Metering Infrastructure (AMI)

(ii) Peak Load Management (PLM)

(iii) Power Quality Management (PQM)

In addition to the above, implementation of Real time Distribution

Transformer Monitoring shall also be done.

The details of above implementations are described in following

paragraphs.

5.2 Advanced Metering Infrastructure (AMI) Advanced Metering Infrastructure (AMI) is a system that measures,

collects, transfers and analyzes energy usage and communicates with

metering devices either on request or on a schedule basis. This system

includes Smart meters, communication systems, data concentrator units,

customer associated systems, Meter Data Acquisition System (MDAS),

Meter Data Management (MDM) software, and business analytics. AMI

shall be installed in DLF City Sub Division of Gurgaon to improve

visualization of energy consumption & power quality at consumer level and

facilitate peak load management through demand side management /

demand response. AMI enables two-way communications hence has the

potential to communicate from the utility to the meter and vice-versa. Utility

can have online consumption record of each individual in fifteen (15)

minutes time block which will be helpful in analyzing consumption pattern &

forecasting energy usage. At the same time consumer can access online

data for their consumption, which would help them in controlling monthly

bills. Automatic meter recording would mitigate requirement of manual

Page 55: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

55

process of meter reading, which would make billing system more accurate,

efficient and fast. Using two way communication system pricing signals may

also be sent to consumer participating in demand response mechanism.

With the available data received in advanced metering infrastructure, utility

has following tools to make system smart:

i. Energy audits can be done at distribution transformer level to

check theft

ii. Load pattern of individual consumer can be observed

iii. Withdrawal of power above sanctioned load may be checked

iv. Tampering may be checked in near real time

v. Control actions from control centre for load curtailment may be

taken

vi. Remote connection / disconnection is possible

vii. Sending alert to consumer for higher load withdrawal, bill non-

payment etc. is possible

viii. For variable pricing, signal transmission is possible

DHBVN is implementing various IT related initiatives like GIS mapping,

billing application, consumer indexing etc. in its areas. Since these

applications are also required for Smart Grid project, setting up separate

system would not be prudent and existing set up shall be also utilized for

Smart Grid attributes to economize cost. GIS mapping, Asset Mapping,

Consumer Indexing and billing application etc. covered under the RAPDRP

/ other schemes shall be integrated with Smart Grid system.

Under advanced metering infrastructure, smart meters shall be installed for

all domestic, commercial, industrial, HT, street lights and other consumers

as identified by DHBVN. Meter Data Acquisition System (MDAS), Meter

Data Management System (MDMS) along with necessary hardware /

Page 56: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

56

software shall be installed at control center. Interface of various IT

applications / processes installed in R-APDRP shall be done as below:

1. Billing Application– Billing data of Smart meters installed in Smart

Grid shall be pushed to billing application installed in R-APDRP at the

end of billing cycle.

2. GIS mapping and consumer indexing data shall be integrated with

advanced metering infrastructure applications and periodic

synchronization/ updation shall be carried out.

A proposed layout of Advanced Metering Infrastructure component is

shown in Figure-3.

Figure-3: Proposed architecture of AMI

Communication medium between Smart Meters & Data Concentrator Unit

shall be RF / PLC. Data from DCU to MDAS shall be communicated

through GPRS. In control centre Meter Data Acquisition System & Meter

Page 57: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

57

Data Management Software shall be hoisted, which will collect, store and

analyze data received from DCU / Meters.

Suitable cyber security system shall be installed to protect the system from

viruses and intrusions. Security system shall create different zones,

separated with firewalls. Inner zone will be accessible to operators in

DHBVN, which would consist of workstations, servers for all applications,

data archive server, storage devices and network management system.

The middle zone subsystem will have centralized management console,

web portal / consumer portal servers. Outer zone would be accessible to

the external users and other integrated systems. All the servers/stations will

be equipped with Host based Intrusion Detection & Prevention System

(IDPS). Patch management tools will be provided to update the patches

received by the various OEMs e.g. patches for anti-virus, firewalls,

application software etc.

MDAS shall be the core application for interface to the field devices. It shall

perform following functions:

• Acquisition of meter data, i.e. poll meters for data collection. On

demand read and ping of meters

• Two way communication with the meter, including load control

• Sending remote firmware upgrades/programmable parameters to

meters/ DCU

• Sending load control signals to the meters

• Maintaining time sync with DCU / meters

• Sending Connect/ Disconnect, and pricing signals to the Smart Meter.

Control signals, event messages etc. shall be handled on priority.

• Reporting communication history for meters and DCU

• Supporting encryption of data transmission for secure communication

Page 58: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

58

Meter Data Management system shall take information from MDAS for

further analysis and structured presentation of the same to user. It shall

have following functions:

• Asset Management

• AMI Installation Support

• Meter Data Analysis

• Exception Management

• Service Orders Generation

• Customer Service Support

• Reporting

• Revenue Protection Support

• Demand Control/Demand Response Support

• User Friendly Interface

• Integration with other Systems

Implementation of complete infrastructure as mentioned above shall

provide an excellent tool in the hand of utility for operation of efficient,

accurate, intelligent and customer friendly metering system. Details of

implementation have been discussed below:

5.2.1 Number of Smart Meters Required

DLF City Sub Division has total 29144 Nos. of consumers. Following

considerations have been made to arrive at the actual quantities of smart

meters for the project:

• Energy meters on distribution transformer are being installed under

R-APDRP, therefore these locations have not been considered here

for smart meters under AMI. MDAS/MDM being provided under R-

APDRP would be integrated with MDAS/MDM of AMI to receive DT

meter data for energy audit.

Page 59: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

59

• Quantity of different types of the smart meters is based on master

data of DLF City subdivision as on 30.09.15

Accordingly 29144 consumers shall be covered for smart meter installation

under AMI. Break up of Smart Meter requirement is shown in the following

table:

Table -1: Smart meter requirement

Sl. No.

Type of meter No.

1. Single phase whole current meter 9380

2. Three phase whole current meter 18602

3. LT CT operated meter 944

4. HT 11 KV CT operated meter 218

5. HT 66 KV CT operated meter 1

Total

29145

5.3 Peak Load Management (PLM) During peak load conditions, utilities overdraw power from the grid defying

entitlement schedules, which impacts grid reliability and costly power due to

Unscheduled Interchange (UI) charges. At the same time utility need to

setup infrastructure to meet the peak load whereas at other times such

infrastructure largely remains under-utilized. Therefore for economic

operation of the power network, peak load management is an essential

requirement. The goal of peak load management is to encourage the

consumer to use less energy during peak hours, or to move the time of

energy use to off-peak times such as night-time and weekends. It is the

modification of consumer demand for energy through various methods such

as financial incentives and partial curtailment. Peak demand management

does not necessarily decrease total energy consumption, but could be

Page 60: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

60

expected to reduce the need for investments in networks and/or power

plants. Load shifting involves shifting energy consumption to another time

period, typically when prices/consumption are lower.

The PLM system collects information from various other systems. It takes

data from the Load forecast software, the power scheduler, and the

availability sub systems. Based on these inputs power demand-supply is

determined, deficit/surplus is worked out and demand response signals are

sent out to the consumers. Peak Load Management does not mean load

shedding. Figure - 4 shows the peak load shifting.

Figure - 4: Peak load management

Peak Load Management works in two ways:

a) Demand Response (DR):Demand response refer to mechanisms used

to encourage consumers to voluntarily trim electricity usage at specific

times of the day (such as peak hours) during high electricity prices

(Time of Use tariffs), or during emergencies (such as preventing a

blackout). Depending on the generation capacity, however, demand

response may also be used to shift demand (load) from peak to off-peak

at times of high production and low demand. In demand response the

consumer voluntarily manages his demand in response to some

signals/incentives given by the utility. Dynamic/ ToU pricing of electricity

Page 61: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

61

and other incentives/schemes are communicated to the consumer via

smart meter/ Web and SMS. The consumer responds by reducing

consumption by agreed percentage or limiting consumption to agreed

kW. b) Demand Side Management (DSM):In case of demand management,

the utility in a sense "owns the switch" and sheds loads only when the

stability or reliability of the electrical distribution system is threatened. It

works in three ways: (i) Settable Relay: In this mechanism smartmeters have relay with

switch, which is designed for operation till a threshold load. Any

increase beyond threshold load, operates the relay and switch is

opened to cut-off power supply. Re-connection attempts may be

carried out as per defined number of times. In reconnection attempts

if load is reduced then connection is made otherwise it is locked and

opened with intervention of utility. (ii) Critical & Non-Critical load ckt: Wherever consumer agrees to

segregate load at meter point between critical and non-critical loads

smart meter will feed two separate load circuits. The relay & switch of

non-critical load ckt is opened during peak load times.

In DLF City Sub Division management of peak demand would be done

using smart meters, which have been proposed to be installed in consumer

premises as part of advanced metering infrastructure. Peak load

management application would be installed in conjunction with advanced

metering infrastructure software to manage peak load in following ways:

5.3.1 DR and DSM for All Consumers

Peak load management through demand response & demand side

management through settable relay / switch in smart meters shall be

implemented for all the consumers. Implementation shall be as below:

Page 62: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

62

i. ToU tariff shall be notified for all the consumers with significant

difference between peak duration tariff and off-peak duration tariff so

as to encourage them to participate in demand response. Two way

communication facility available with smart meters shall help in

sending variable price signal / alerts to consumers for reducing load.

ii. In demand side management using settable relay, load curtailment

shall be enacted during peak load hours to reduce the power

consumption by users. Users below the load allowed at that time shall

remain connected and if their consumption exceed the allowed level,

they will be disconnected after due warning. Reconnection attempts

shall be allowed three times in every five minutes. Failing to reduce

the load, disconnection shall be locked for thirty minutes.

Popularization of this technique will help in limiting the loads similar to

inverters and batteries.

5.3.2 Power Quality Improvement

Power quality is a measure of the fitness of electrical power fed into the

consumer devices. Without good quality power, an electrical device (or

load) may malfunction, fail prematurely, become economically unviable due

to losses or not operate at all. There are various parameters like voltage

sag/swell, low power factor, current/voltage harmonics, transients etc.

which are related to quality of power and deviation in their value from

reference results into poor quality of power.

The power system in DLF City Sub Division of Gurgaon is designed for a

balanced three phase operation. However, unbalanced operation, harmonic

currents etc. cause extra losses in the system. Similarly over voltages,

transients etc. cause additional stress to the insulation. Low power factor

and large harmonic content increase the losses and reduce the active

power transmission capability of the system. The list of power quality issues

generally present at the distribution level is quite extensive. However, the

Page 63: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

63

most prominent ones that have direct impact on the system efficiency and

security include harmonics, unbalance, poor power factor and zero

sequence components (resulting in neutral current). These are classical

power quality issues, which are addressed by various passive solutions.

However, advancements in power electronics and control have led to much

efficient active solutions generally referred to as Active Power Filters. A

typical schematic of active power filter is shown in figure below.Active

Power Filters are considered to be a single window solution virtually for all

the current related issues. It may be noticed that active filters are shunt

devices that inject a current comprised of all notorious components required

by load (eg. harmonics, negative and zero sequence, reactive component

etc.) that are unhealthy for the overall system and cause high losses.

Technically, an active filter is based on STATCOM principles, with a DC

bus formed by a large capacitor. Thus, modern active filters provide highly

flexible solutions, simultaneously addressing issues like current harmonics,

load unbalance in phases, reactive power demand, neutral current etc. with

priorities configurable by the user. It may be noted that active filters provide

an indirect solution to voltage harmonics issue by limiting current harmonics

travelling into the distribution system.

Page 64: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

64

Figure -5: Schematic for active power filter

In view of the above, deployment of active power filter at 10 distribution

transformers shall be carried out. This would not only make the system

more efficient and reliable but also would help in enhancing the awareness

and understanding of power quality within the utility. In order to identify the

suitable DTs for installation of active filters, we need to carry out power

quality measurement survey of distribution transformers at different

locations in DLF City Sub Division. After measurement & analysis of

recorded data for the distribution transformer, top 10 most suited one will be

recommended for installation of active power filter equipment because of

large content of harmonic currents, unbalancing etc.

5.4 Distribution Transformer Monitoring Unit (DTMU) Distribution transformers are very important equipment near end

consumers, which are needed to be kept healthy from the point of view of

utility as well consumers as any defect in these would result into outage of

many consumers and considerable revenue loss to utility. Distribution

transformers are generally installed in any locality based on the loads

requisitioned by respective consumers and estimated future requirements.

However due to economic uplift of society and penetration of new

appliances in consumer’s premises continue to grow, which outpace the

estimated rise in load considered by utility earlier. Any carelessness in

monitoring of distribution transformers may soon result into overloading

operations and subsequent failures. Further leakage of oil, heating of

terminal connection etc. are some of the other reasons which cause failure

of distribution transformers. Therefore Distribution Transformer Monitoring

Units (DTMUs) are becoming necessary to be installed for healthy

operation of systems.

Page 65: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

65

DTMU is the equipment through which real time monitoring of oil

temperature, oil level & LT side load current / parameters of distribution

transformer can be done. Any abnormality in these parameters triggers an

exception event and reports to control centre for further actions. Based on

the DTMU data, maintenance teams can also take proactive measures to

repair /replace the distribution transformer.

Distribution Transformer Monitoring Unit are proposed to be installed on all

the transformers owned by DHBVN as a part of Smart Grid initiative in DLF

City Sub Division of Gurgaon. The installation of DTMUs will provide online

information of loading, oil temperature & oil level which may prevent failure

of transformer on account of overloading, low oil level, miniature internal

faults etc. There are total 1200 nos. distribution transformers installed in the

system on which DTMU’s have to be installed.

5.5 Smart Grid Control Centre A Smart Grid Control Centre shall be setup in any existing facility to be

decided by DHBVN, where all the software applications along with required

hardware systems shall be installed. All the field equipment shall send the

data to the control centre, where processing of the same shall be done

using software applications to get useful information. The control centre for

Smart Grid project implementation shall require three discrete areas for

operation control (5m X 5m), server (4m X 4m) and UPS & battery (4m X

4m). Smart Grid control centre will require 10 KVA UPS power for operation

of servers, workstation, operation console etc. Building & other civil works

have not been considered in this report.

Page 66: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

66

6 BENEFITS OF SMART GRID INITIATIVES

Smart Grid project is being done as an initiative to embed new technologies

in distribution system in small scale and successful implementation would

draw the way forward for large scale implementation. Therefore for such a

project finding economic viability and feasibility would be prejudice as

qualitative benefits are of paramount importance. Large scale

implementation in future may only prove economies of operation. Benefits

of proposed initiatives in DLF City Sub Division are mentioned below:

6.1 Benefits of Advanced Metering Infrastructure Benefits from AMI may be categorized as:

System Operation Benefits: These are primarily associated with reduction

in meter reading and associated management and administrative support,

increased meter reading accuracy, and improved utility asset management,

easier energy theft detection and easier outage management.

Customer Service Benefits: These are associated with early detection of

meter failures, billing accuracy improvements, faster service restoration,

flexible billing cycles, providing a variety of Smart Grid features like time-

based tariff options to customers, and creating customer energy profiles for

targeting Energy Efficiency/Demand Response programs.

Financial Benefits: These accrue to the utility from reduced equipment

and equipment maintenance costs, reduced support expenses, faster

restoration and shorter outages.

Details of the benefits due to AMI are described below:

6.1.1 Reduction in Meter Reading Cost

In AMI, meter reading shall be communicated to control room automatically

in every 15 minute time block. This will reduce meter reading cost on

account of reduction in manpower.

Page 67: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

67

Presently all the meters proposed to be replaced with smart meters (29144

Nos.) in Smart Grid project are manually read for which 8 meter readers

have been deployed. Cost savings through the reduction in manual meter

reads will be realized through a reduction in meter readers thus reduction in

both in-house and contractor labor costs. Meter reader workforce

reductions shall occur over the course of the AMI implementation period,

and DHBVN may plan to realize these workforce reductions through natural

attrition and work re-assignment over time. Quantifiable benefits related to

manual meter reading savings are expected over business case time

horizon.

6.1.2 Reduction in Field and Meter Services

Smart metering and communication infrastructure enables utilities to

perform several functions remotely that would otherwise require a field visit

to the customer premise. As a result, significant cost savings through the

reduction in the number of personnel for field and meter services can be

achieved. Benefits in this area can be seen in the reduction in manual

disconnect / reconnect of meters, single consumer outages, need for

manual re-reads, as well as customer equipment problem.

6.1.3 Reduction in Off Cycle Trips

Remote connect / disconnect feature of AMI smart meters enables utilities

to turn on and off services for new and cancelled accounts remotely without

a field trip. This benefit not only applies to the ability to turn on and off

services for regular move-in / move-out of customers, but also provides the

ability to cancel service for non-paying customers. As a result, significant

cost savings can be realized through the reduction in need for personnel

and transportation costs to turn on / off services. As a result of AMI, cost

savings will also be seen through the time saved in off cycle reads / special

reads due to reduction in meter access challenges.Approximate 15000 nos.

trips are carried out in DLF City monthly for manual

Page 68: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

68

disconnection/connection, manual off-cycle reads, special meter reads etc.

in one month, which may be reduced by implementation of AMI.

6.1.4 Reduction in Outage Field Trip

AMI implementation is expected to result in cost savings associated with

reduced outage field trips to customer premises. With the ability to provide

near real-time power and outage status information, AMI systems are able

to test for loss of voltage at the service point and shall be able to detect

outage conditions as well as obtain restoration status indication. As a result,

“OK on Arrival” field trips will be virtually eliminated, in AMI areas, thereby

leading to cost savings.With AMI, DHBVN will be able to determine whether

the cause of an outage is the result of an electrical problem with the

customer’s equipment. This automated determination will help save

dispatch labor for customer incidents that involve equipment failure.

6.1.5 Reduction in Unaccounted Energy

Unaccounted Energy in the areas of meter tampering, energy theft, meter

inaccuracy, and dead / stopped meters results in significant revenue loss

for utilities. Through the use of smart meters and sophisticated MDM

systems, unaccounted energy can be detected early and revenue losses

related to unmetered energy can be reduced.

6.1.6 Theft / Tamper Detection & Reduction

AMI systems significantly aid in the early detection of meter tampering and

energy theft. Smart meters can detect tampers like Meter Cover open

detection, Neutral disturbance, Magnetic Interference etc. and these tamper

alerts are communicated immediately to control centre. Also energy audit

for each integration period is carried out in control centre applications for

predefined set of meters. Any discrepancy in energy reading of main meter

and sum of energies of subordinate meters is found by analytical engines

Page 69: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

69

and same is notified to operators. Also analytics software allows

identification of anomalous patterns of energy consumption by consumers

which are may be due to theft and tampering. As per historical data, 8.24%

is the billing inefficiency losses. This component includes energy loss due

to theft and tampering and with implementation of AMI these losses are

likely to reduce.

6.1.7 Faster Identification of Dead Meters

Smart meters have feature to send power loss signal or last gasp message

to control centre. Thus implementation of AMI systems helps utilities in

quick identification of dead and/or stopped meters that can no longer

measure electricity consumption. Such signals/ messages are correlated

with signals/ messages received from other smart meters in that locality. If

found an isolated case then possibility of being dead is confirmed and

notified to operator. This early identification helps utilities to take steps

quickly towards repairing or replacing the dead meter, thereby reducing

potential revenue losses. Non-technical losses before billing include such

losses, which are likely to be reduced after implementation of AMI.

6.1.8 Improved Distribution System Savings

It is expected that AMI shall help in improvements in the distribution system

planning efforts. AMI will provide detailed information across the distribution

network that can be used to optimize investments in infrastructure

improvements. Data available by AMI like Interval (time-based)

consumption data at the customer level (and ability to aggregate up to

transformer and circuit levels), voltage information collected at each

premise, momentary outage information etc. shall help in better

management of system.

Page 70: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

70

6.1.9 Improved Distribution System Management

Interval consumption data can be aggregated at the transformer level to

help identify under-used and overloaded transformers, as well as to

properly size replacement transformers. Information received through AMI

will provide more granular level system health and performance details.

Using more detailed information from AMI enables DHBVN to more

accurately forecast load growth and evaluate system investments resulting

in improved asset planning and strategies.

Further due to peak load management up-gradation work of distribution

system may be deferred. We consider that approx. 25 MW (10% of peak

load) peak shaving may be done using suitable peak load mechanism. For

this 25 MW power flow, distribution system expansion may be deferred by

at least one year resulting into saving of interest cost on borrowed capital.

6.1.10 Operational Efficiency Improvement

An important benefit of AMI is the cost savings realized through efficiency

improvements in customer call volume and management. Meter reading

errors are expected to be virtually eliminated and the need for calculation of

estimated bills due to access issues will be significantly reduced, in AMI

areas. Efforts to raise awareness regarding AMI through marketing

campaigns and customer education will increase customer adoption of self-

service leading to an overall reduction in call volume. The potential to

reduce float between meter read and customer billing will also drive greater

benefits for DHBVN.

6.1.11 Reduction in Estimated Bills

The ability to remotely read meters on a frequent basis greatly reduces bills

based on estimation that often result from meter access issues that

Page 71: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

71

currently prevent meter readers from obtaining reads in hard to access

areas at the customer premise. Fewer customer service resources are thus

expected to review exception reports, resolve billing errors and process

adjustments.

6.1.12 Reduction in Customer Call Volume

Comprehensive marketing campaigns and customer awareness programs

will educate customers about the self-service options available to them

throughout the AMI roll-out. DLF City Sub Division receives large number of

calls annually related to customer inquiries. DHBVN is currently planning on

further developing its customer self-service capabilities, including web and

IVR enhancements channels. DHBVN plan to increase the self-service

marketing efforts during the AMI roll out, encouraging portal use and

promoting self-service within AMI communications. As a fair estimate we

can expect a 5% reduction in call volume as a result of greater self-service

adoption. This will also be driven by lower bill inquiry call volume due to

reductions in bills based on estimation. The reduction in call volume over

the life span will result in cost savings.

6.1.12.1 Reduction in Float between Meter Read and Customer Billing

AMI is expected to enable all accounts within AMI territories i.e. project

area to be billed on the monthly basis on the billing window. Currently bills

which are produced during different days will now be generated

simultaneously as a result of AMI. This will accelerate DHBVN’s revenue

stream and improve its cash flow.

6.2 Benefits of Peak Load Management

PLM programs like demand response/demand side management will help

DHBVN in pecuniary benefits in following terms:

Page 72: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

72

A) Reduction in Power Purchase Cost: Generally time of the day and

season of the year plays an important role in peak power

requirements. It may be 1-2% of the total time, but infrastructure

creation is required to meet such load only. Therefore peak shaving

benefits utility as capital infusion in infrastructure may be deferred for

some years depending upon peak load reduced. This capital may be

used to service operational requirements making utilities more

competitive.

B) To meet peak load, utilities make arrangement of extra power by short

term purchases through bilateral agreements or energy exchanges.

Any short term power purchase that too in peak hours is always

costly. With PLM, short term purchases may be reduced.

C) Reduction in peak load would reduce maximum current through lines,

thereby reducing I2

As per historical data, peak load in DLF City Sub Division is 225 MW with

daily 3 hours peak load ( timings:- 7 pm to 10 pm ). Objective of PLM at

DLF City Sub Division shall be to reduce peak load by about 10% i.e

.approx 25 MW.

R losses. Thus technical losses would be reduced.

6.3 Other Benefits

Apart from above functionalities, other activities shall have following

benefits:

(i) Power Quality Improvement: Reduction in losses, better

performance of equipment / appliances

(ii) Distribution Transformer Monitoring Units: Better knowledge of asset

(distribution transformer) utilization, reduction in outage, predictive

maintenance

Page 73: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

73

7 SCADA IMPLEMENTATION

Grid automation has helped distribution utilities across the world in

increasing their reliability, improving quality of power and optimum

utilization of their assets, resulting in higher customer satisfaction.

Automation decreases human intervention and helps utilities restore the

faulty equipment in minimum duration.

7.1 Components of Grid Automation Grid Automation has following components:

i. Software Modules installed in the control room

ii. Hardware installed in the control room

iii. Communication system like GPRS, CDMA, RF Mesh, OFC etc.

iv. Communication equipment i.e. RTU & FRTU

v. Motorized Switches for remote operation of grid

vi. Sensors such as MFTs, Weather Transducers etc.

7.2 Illustration of automated fault restoration by SCADA

Electrical system has been designed in a ring and if a fault occurs in any

part, the faulty portion is isolated and power is fed through alternate path.

The below mentioned diagram illustrates how the ring system works.

Page 74: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

74

Page 75: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

75

Page 76: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

76

If the closing and opening of load break switches is done manually, it takes

time and requires man power. But the same can be done remotely sitting in

the control room through grid automation system. In grid automation system

motorized load break switch/circuit breakers are installed which can be

controlled remotely through communication system and communication

equipment. Communication equipment are Remote Terminal Unit which

are microprocessor-controlled electronic device that interfaces objects in

the physical world to SCADA (supervisory control and data acquisition)

system by transmitting telemetry data to a master system, and by using

messages from the master supervisory system to control connected objects

. Communication system being used is optical fibre as it is most reliable and

has the potential to cater to future needs in terms of bandwidth. Moreover

laying optical fibre cable is very convenient, being laid over and above the

power cable, no separate digging or boring is required to lay optical fibre.

Sensors like MFTs, Weather transducers are used to collect information like

voltage, current, temperature, wind direction etc. and feed these to

communication equipment’s as mentioned above so that the

sameinformation can be taken to control room over communication system

like optical fibre cable. This is information is received by the front end

Page 77: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

77

server of SCADA system which in turn shares it with various application

servers like SCADA , DMS , OMS , EMS servers etc. for their processing

and storing relevant information in database .

Supervisory Control and Data Acquisition (SCADA) shall provide a variety

of functions that can be grouped to provide core capabilities such as:

• Telemetry

• Monitoring and Alarming

• Controlling

7.3 Requirement of Software Applications with SCADA For optimum utilization of SCADA following software applications will be required:

7.3.1 Distribution Management System(DMS) Generally Distribution Management Systems include following

Sub_Systems over and above the SCADA application: -

I. Voltage/VAR regulation/control.

II. Load shed application.

III. Trouble call and outage management.

IV. Fault management (location/isolation) and System Restoration.

V. Load flow application.

VI. Network connectivity analysis/ Load calibration.

VII. Loss minimization/Loss calculation/Energy accounting.

VIII. Dynamic Network coloring.

IX. Load forecast.

X. Work order management.

XI. Geographical information system.

Voltage / VAR Control:The VVC function monitors the set of

telemetered voltage measurements associated with each VC-

Page 78: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

78

controllable device. If the VC function detects a limit violation, it

advises the corrective control actions to operator. VVC-controllable

devices are the set of transformers and capacitor banks selected by

the operator for VC control. Corrective controls include

incrementing/decrementing the transformer tap position, and

switching in/out a capacitor in a capacitor bank.

Load Shed Application

: -The load-shed application automates and

optimizes the process of selecting the best combination of switches to

open in order to shed the desired amount of load. The load shed

application recommends different possible combinations of switches

to open, in order to meet the requirement. The operator is presented

with various combinations of switching operations, which will result in

a total amount of load shed, which closely resembles the specified

total. The operator can then chose any of the recommended actions,

and execute them through a single action at the console. The

recommendation is based on an evaluation of load priorities and

current load levels.

Trouble call & Outage Management:-

I. Call handling

A trouble call and outage

management system shall be provided to handle telephone calls from

customers of the utility’s reporting electric service problems. TCOMS

provides interactive voice response and automatic call dispatch

facility to track and report problems, analyze and group problems by

type and dispatch problems individually or by groups to appropriate

work crews for resolution:

II. Call Analysis.

III. Task Assignment.

Page 79: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

79

IV. Outage Management and reporting

V. Fault and outage Management

VI. Based on the data organized by the call analysis function, an

additional consolidation of information shall be provided by the

TCOMS.

VII. A comprehensive view of the situation of the network shall be

presented to the dispatcher, allowing to quickly assessing the

nature and importance of the reported troubles.

VIII. The corresponding network trouble tickets shall be assigned to

repair crews, and the progress of the work properly managed,

including the monitoring of partial restorations.

Fault Management (location/isolation) and system Restoration

The Fault Management & System Restoration function provides

assistance to the DMS dispatcher for detection, localization, isolation

and restoration of the distribution system. In case of permanent fault

in the Distribution network, the function proposes switching plans to

restore the supply in the healthy parts of the faulty feeder. The

function shall also be usable and compute switching plans to assist in

the cases of reconfiguration of the network required by maintenance

operations or partial load transfer of an overloaded feeder to the

neighboring feeders.

: -

Load Flow Application: -A power distribution network normally

consists of a large number of devices; a correspondingly large

number of measurements are thus needed to describe its state. In

most cases, however, relatively small portions of the electrical

quantities at network locations are actually measured. The Load flow

application provides values for those electrical quantities at network

location where measurements are not available.

These values are useful both in terms of providing a more

Page 80: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

80

complete view of the network to the operator in real-time, and as the

basis for the remaining DMS software for which the load flow results

serve as inputs.

Network Connectivity Analysis

The NCA function determines the topology of the

distribution network based on the physical connectivity of devices in

the network and the status of connecting devices such as switches.

The electrical status of each device in the network can be presented

dynamically to the operator on one-line displays. The dynamic display

rendering of electrical status provides an indication of energized/de-

energized state, and whether the device forms part of a loop or a

parallel path.

: - The network connectivity analysis

function forms the basis of the analysis/decision/action tools available

to operators. Aside from providing live/dead status information to the

operator in real-time, the results of the NCA function serve as inputs

to virtually every other application in the DMS software package.

Loss Minimization/Loss calculation/energy accounting

The loss minimization via feeder reconfiguration study application

identifies an alternative network topology, which, while meeting the

same nodal power demands, incurs smaller distribution losses. To

this end, the function recommends a series of switching operations,

each consisting of opening one switch and closing another switch, in

order to transfer load from one feeder to another.

: -The loss

minimization optimization study functions provide recommendations,

which may allow operators to reduce overall system losses, thereby

reducing operating costs. Also, the loss minimization

recommendations would result in improved quality of service and

increased reliability.

Dynamic Network coloring: - The Dynamic Network Coloring shall

enable the DMS operator to visualize the operational conditions

Page 81: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

81

present in the distribution network. Different types of coloring shall be

available.

I. Automatic coloring

II. On-demand coloring.

Work orders Management

I. The description of the elementary operations to be performed.

: - Work Orders Management (WOM) shall

provide a flexible way to automate the management of job forms

describing the construction and maintenance works on the electrical

network and support the job sheet description and the full life cycle of

the job form. These job forms shall consists of the following

information:

II. The life cycle of the job forms, from their creation through

approval, execution and eventually archival of the form.

III. The necessary information to the operator pertaining to the job

being done such as electrical section getting affected, time

expected to carry out the job and operations not permitted to

perform during this period.

Geographical Information System

: -Geographical Information includes

the network diagram superimposed on geographically map of the

area. The breakers and switch status (on/off/lock) are indicated.

Feeder condition (Lie/dead/Maintenance) is also displayed on the

screen.

7.3.2 Outage Management System

The Outage Management (OM) shall be a collection of functions, tools, and

procedures, which an operator or dispatcher uses to manage the detection,

location, isolation, correction, and restoration of faults, which occur

unexpectedly on the utility electric network.

Page 82: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

82

1. OM shall also be used to facilitate the preparation and resolution of

outages, which are planned for the network. OM processes shall be

used to expedite the execution of the tasks associated with the

handling of outages that affect the network and provide support to

operators at all stages of the outage life cycle starting from events

such as the reception of a trouble call or a SCADA indication of an

outage, until power is restored to all customers.OMS processes shall

further be used to resolve the outage whether the outage is at the

level of a single distribution transformer providing power to one or few

energy consumers or the level of a primary substation providing

power to many energy consumers.

2. All operations, authorizations, and comments, which occur in these

processes shall be documented and collected in outage records. It

shall be possible that this information is made available to external

sites for further statistical analysis and processing.

3. OM shall provide the automatic processing of an outage record used

to monitor changes in the network and have an internal interface to

Crew Management, Switching Procedure Management, and Trouble

Call Management.

4. Data communication to external applications shall be enabled through

web service adapters in the framework of a Service Oriented

Architecture.

7.3.3 EMS Applications at Smart Grid Control Centre:

The Smart Grid Control Centre will have to be fully equipped to discharge

its responsibility as defined in Smart Grid Code & all applicable codes. The

functional requirements will need following tools for operator to optimally

meet challenges of operating a modern SLDC/SSCC.

Page 83: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

83

(a) Load Forecast (b) Outage Scheduler (c) State Estimation (SE) (d) Contingency Analysis (CA) (e) Optimal Power Flow (OPF) (f) Transmission capacity monitoring (TCM) (g) Operation monitor

7.3.4 Switching Procedure Management

Switching Procedure Management (SPM) of the Network Control Center

System shall allow the operator to create, edit, select, sort, print, execute,

and store switching procedures. It shall be possible to create entries in a

switching procedure manually by recording the operator's actions in a

simulation mode, by modifying an existing procedure, by recording the

operator's actions in real-time mode, or automatically by applications, such

as, Distribution Network Applications.

1. The SPM capabilities shall enable preparing, studying and executing

clearance operations. SPM shall also be used to execute switching

operations to alleviate fault conditions and to restore power following

a fault, as well as for the optimization of the network operation.

Switching Procedure Management shall provide management

capabilities via summary displays and easy-to-use menus.

2. Load shedding shall enable an operator to shed or restore a list of

load control elements, shed or restore to a specified MW load

curtailment, shed or restore a percentage of the total available load in

a list, or rotate shedding through a list of load control elements.

Page 84: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

84

7.4 Benefits of Implementation of SCADA & Software Applications

Combined benefits of implementation of SCADA along with supporting software applications illustrated above can be summarized under following main heads:

7.4.1 Leading functionality

SCADA functionality is based on advanced and proven algorithms, for

instance for fault location, as well as for restoration and network

reconfiguration. The traditional SCADA functionality, such as on-line

network monitoring data, is complemented with an advanced DMS network

database. This enables new real-time applications for improved network

monitoring and outage management. Fault location along the feeder can be

determined instantaneously and exact fault location can be presented on a

geographical map.

7.4.2 Operation and informative presentation of the network

Using SCADA, the operator can monitor the network state and related

measurements, and then perform the control actions needed. Versatile

process displays, lists and application tools for network tracing, locating

components and reporting provide the necessary information for different

users. Dynamic line coloring delivers information about topological

connectivity, powered/un-powered network sections and about overloaded

lines and voltage drops. The entire network can be viewed on detailed

geographical maps in raster and vector formats, as well as in a schematic

diagram. Zooming, panning and de-cluttering enable a clear overview and

allow users to focus on a specific area to obtain detailed information. The

functions are at hand via process displays, maps and schematic network

views. In geographical views, several map layers can be used to provide

the details needed. The system automatically selects the correct map layer

in accordance with the current zoom level. Network effects caused by

Page 85: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

85

distributed generation can be analyzed and corrective actions planned and

simulated.

This can already be done in the network planning phase or alternatively

during the real-time operation. Also short-term forecasts of generation can

be used so that operational changes and controls for load or generation

can be planned and informed in advance.

SCADA extends traditional SCADA functionalities by providing

geographically based network views and advanced distribution

management functions over the entire distribution network.

7.4.3 Dependable Operational Safety

SCADA prevents simultaneous operation of primary equipment. It reserves

the device, and verifies whether the selected object can be operated,

before executing the command. Additionally, interlocking schemes prevent

dangerous operations that might otherwise damage primary equipment.

Only authorized users can override interlocking and other locked

operations. Common safety procedures require that any mechanical or

electrical equipment can be locked out and tagged out before being worked

on. Responsible for meeting safety requirements, rules and regulations,

SCADA includes a lock-out/tag-out function. The lock-out/tag-out function

ensures that control of objects in the application or other operations are

properly secured prior to and during, for example, maintenance or servicing

work. An application object in tag-out state can easily be identified on the

HMI by the intuitive tag-out display symbol. SCADA’s dynamic network

coloring function provides the operator with quick access to information

about the powered, un-powered and earthed parts of the network.Alarming

objects are also visualized. The network coloring, combined with object

control simulation of SCADA, ensure the safe and correct operation of our

electrical network.

Page 86: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

86

7.4.4 Intelligent switch order management

The switch order management function supports planning, simulation,

execution and reporting of scheduled maintenance outage operations. The

intelligent algorithms automatically optimize the switching sequence to

minimize the number of affected customers. Through its operation planning

functionality, SCADA allows both automatic and manual switch orders to

open and close switching devices in the distribution network or performing

other actions during the outage. Switch order documents with user-defined

actions can be created based on company-specific Microsoft Word

templates. The switching planning takes the technical constraints of the

network into account, such as voltage drop and load level for each line

section. Furthermore, it eliminates damage to primary equipment and the

network during maintenance outages by ensuring correct relay protection

operation at all times.With the world map view of SCADA, detailed

consumer information is just a few clicks away.

With help of SCADA , detailed consumer information is available instantaneously

Page 87: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

87

7.4.5 Reduction in Outage duration

The advanced distribution management functionality reduces outage time

from hours to minutes. The system retrieves registered data about fault

currents or impedance from protection and control IEDs. It also utilizes data

provided by Feeder Terminal Units (FTU) and fault indicators. This data

together with the network model is used to calculate the fault location,

which is instantaneously shown in the network view.Then, restoration

support provides the operator with a list of recommended actions, such as

reconfiguration of the entire network to minimize the outage area. This

allows for fault isolation and fast and safe network restoration. Restoration

can also be executed completely automatically. In a fault situation, the

GPS-based field crew management enables the operator to quickly find the

nearest service crew.With the help of the integrated geographical map, the

operator can guide the crew to the fault location, where necessary manual

switching operations can be performed to isolate the fault. Or the crew can

access the system via mobile communications or hand-held computers,

which further simplifies the entire process. With the advanced fault

management functionality, you can provide excellent service to your

customers. SCADA system helps to locate the customer calling in and

allows to immediately inform the customer about the fault and its expected

repair time. Integration of an Automatic Meter Infrastructure (AMI) system

into SCADA offers the possibility to use the communication and smart

meter infrastructure created, mainly for energy metering, to also remotely

monitor the low voltage networks. This function enables spontaneous

alarms to be received regarding network faults and voltage violations. It can

also read measurement values from the energy meters. Alarms from

several customer meters can be combined and faults in the low-voltage

network can be located. SCADA also features a Trouble Call Management

function that stores and presents any type of customer contact. The

function provides also customers with information about network

Page 88: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

88

disturbances and collects information about the faults, such as the nature

and location of the fault.

7.4.6 Fast and efficient reporting of operational statistics and outages

Outage reports covering faults, maintenance outages and also reclosing

trips. Based on the data stored in a relational database, various statistics

and indices, such as SAIDI, SAIFI, CAIDI and CAIFI *) can be created. Both

SCADA and company-specific reporting tools can be used. The detailed

storage of outage information even allows the retrieval of customer-specific

outage histories, which can significantly improve customer service.

Individual customer outage reports can be automatically generated if

requested by the authorities. To achieve a complete view of the network

condition and service quality for action planning, these reports(including, for

example, frequent fault locations and device failures) can be integrated into

the company’s business system (ERP) or utilized in a data warehouse

implementation. Measurement reports that present currents, voltages and

active and reactive power in both numerical and graphical formats. The

reports can contain, for instance, five-minute or hourly average values.

Energy reports in both numerical and graphical formats containing active

and reactive energy data with yearly, monthly, weekly, daily and hourly

statistics based on three-minute average values. Customized reports are

easily produced using the flexible Historian that can store all process data

for long periods and refine the data into meaningful information. This gives

a clear view of the situation in the primary process and allows for optimized

utilization of the power and primary equipment. Reports and statistics are

easily produced. The information is visualized in the form of various graphs,

trends and numerical reports. The numerical reports can utilize embedded

Microsoft Excel which provides commonly known tools for further data

refinement.

Page 89: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

89

7.5 Implementation of SCADA in project area: Architecture & BOQ To achieve the objectives of Smart Grid SCADA control centre, the

requisite SCADA system will be installed in the project area which will

control the transmission/sub transmission network of the voltage level 33

kV & above. The 11 kV distribution network in the project area will also be

supervised and controlled by SCADA system. This SCADA system will

carry out the following functions at Transmission level and Distribution level.

i. Resource management for optimum utilization capable to automate

transmission and distribution system with proven efficiency and

reliability based on the steadfast digital technologies. The centralize

station to facilitate energy auditing , preparation of energy accounts

and losses up to DT level having sync with billing and outage

management & response time.

ii. The system architecture will facilitate crew management system,

maintenance management system, power system network

applications, load balancing & network management, distribution loss

minimization, and power quality monitoring & reliability assessment.

iii. The proposed central station to provide higher level of automation at

substation to elevate reliability of power system network and

unmanned operation of substations with a coordinated control, is

required to be established the state of art available technologies,

features, facilities in hardware and software which could at least

deliver and handle SCADA/EMS/ADMS/OMS/GIS/CIS/Asset

management/weather forecasting/Load forecasting/resource

management/Visual Monitoring System/Fire management

system/Access control system/Building Management system ,

integration of renewable energies and real time two way

communication from source to sink to ensure resilient 24x7 power to

the consumers.

Page 90: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

90

7.5.1 Activities to be performed in Distribution System:

i. Remote operation of all the distribution transformers

ii. Automatic detection and isolation of faulty area using FPI

iii. Automatic restoration of supply by backfeeding of feeder from

alternate source and supply after isolation of faulty portion

iv. Remote monitoring of varies parameters of distribution transformers

v. Due to availability of data in database , the SAIDI , SAIFI and CAIFI

can be created and monitored for improved power quality

vi. Load forecasting of area

vii. Health monitoring of all the breakers/transformers installed on 11 kV

network

viii. To help in Short circuit current calculation of the distribution network

7.5.2 Common SCADA Control centre One common SCADA control room for transmission system and distribution

system has been proposed at 220 kV S/Stn, Sector 52, Gurgaon and back

up control centre is proposed to be built in HIsar town. In the present

scenario, it will handle the 11 No. 66 kV S/Stn(7 No. New Substations and 4

no. existing systems) and 11 kV network of the entire project area (Phase I)

i.e. DLF subdivision of DHBVN. In future this SCADA control room will

control complete Gurgaon from sector 1 to sector 115 having no. of

consumers.

7.5.3 Communication Network For remote operation of distribution transformers and fault identification and

rectification at 11 kV;563 no. RMU of various specifications has been

proposed. The RMU’s are SCADA compatible (i.e. motorized RMU’s with

FRTU’s and FPI). The data will be collected by FRTU’s at each RMU’s and

Page 91: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

91

same will be transmitted to nearby 66 kV feeding S/Stn through optical

fiber. At the substation, the data will be collected and merged at FODP

installed at each substation. From substation to SCADA control room; the

data will be transmitted / transported through optical fiber and will be

collected at SCADA control by Front End Server installed in SCADA control

room. This data will be shared with different application servers like

SCADA,DMS,OMS,and EMS etc.

7.5.4 Field Equipments The following equipment are required in the field for distribution purpose :

RMU ( Ring Main Units)

Indoor type11 KV SF6 type extensible and motorized 5 way smart Ring Main Unit (RMU) complete with two VCB and three LBS with FRTU and FPI as per IS

Nos. 5

Indoor type 11 KV SF6 type extensible and motorized 4 way smart Ring Main Unit (RMU) complete with two VCB and two LBS with FRTU and FPI as per IS

Nos. 5

Indoor type 11 KV SF6 type extensible and motorized 3 way smart Ring Main Unit (RMU) complete with one VCB and two LBS with FRTU and FPI as per IS

Nos. 5

Indoor type 11 KV SF6 type extensible and motorized 3 way smart Ring Main Unit (RMU) complete with all three VCB and with FRTU and FPI as per IS

Nos. 5

Indoor type 11 KV SF6 type extensible and motorized one way smart Ring Main Unit (RMU) complete with LB and with FPI as per IS

Nos. 5

Indoor type 11 KV SF6 type extensible and motorized one way smart Ring Main Unit (RMU) complete with VCB and FPI as per IS

Nos. 5

Outdoor type 11 KV SF6 type non extensible and motorized 5 way smart Ring Main Unit (RMU) complete with two VCB and three LBS with FRTU and FPI as per IS

Nos. 17

Outdoor type11 KV SF6 type extensible and motorized 4 way smart Ring Main Unit (RMU) complete with two VCB and two LBS with FRTU and FPI as per IS

Nos. 83

Page 92: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

92

Outdoor type 11 KV SF6 type extensible and motorized 3 way smart Ring Main Unit (RMU) complete with one VCB and two LBS with FRTU and FPI as per IS

Nos. 418

Outdoor type 11 KV SF6 type extensible and motorized 3 way smart Ring Main Unit (RMU) complete with all three VCB and with FRTU and FPI as per IS

Nos. 5

Outdoor type 11 KV SF6 type extensible and motorized one way smart Ring Main Unit (RMU) complete with LB and with FPI as per IS

Nos. 5

Outdoor type 11 KV SF6 type extensible and motorized one way smart Ring Main Unit (RMU) complete with VCB and FPI as per IS

Nos. 5

Optical Fiber

Un- Armoured Optical Fiber (48 Fibers) along with the all accessories connectors, switches etc.

KM 222

Armoured Optical Fiber (48 Fibers) along with the all accessories connectors, switches etc.

KM 37

PLB-HDPE (Permanently Lubricated High Density Poly Ethylene) pipe 40 mm. dia pipe for laying optical Fiber Cable.

KM 259

7.5.5 Components of SCADA Control room The following equipment are required in the SCADA Control Room :

Server/Workstation Hardware Unit MCC BCC Total Qty

Reason for Incorporating

SCADA,ADMS,OMS,EMS Server Nos. 2 2 4.00 Application Server

for SCADA, DMS,OMS,EMS

DMS Simulation Server Nos. 2 0 2.00 Training of operators

DMS Realtime Historian Server Nos. 2 2 4.00 History parameters of all equipment

FEP,Communication,ICCP Integration Server Nos. 2 2 4.00 Communication

server

ISR Server {Data Server} Nos. 2 2 4.00 Data Retrieval/Archival

NMS Server Nos. 2 2 4.00

Network Management for

monitoring health of communication

system

Developmental Server Nos. 3 3 6.00 Coding requirement

Page 93: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

93

Web/Directory Server Nos. 2 2 4.00 Interface with

devices which need data on internet

Asset Management Server Nos. 2 2 4.00 Life Cycle

management of Equipment

Visual Monitoring Server Nos. 4 4 8.00 Physical

Surveillance of Substations

Weather Forecast System Nos. 2 2 2.00 For weather

forecasting for Load forecasting

LV Automation Monitoring (Non-Technical Losses) Server Nos. 4 4 8.00 Calculation of

Losses LED based Video Projection system with 2X3 Module configuration with each module at least 67" diagonal with common projector

Set 1 1 2.00 For having single screen view of whole system

Hardware for BMS Lot 1 1 2.00 Building HVAC ,

Accees control and related hardware

Sensors Nos. 1000.00 MFTs

Cameras for VMS Lot 50.00 Physical Survilance of Substations

SCADA software Lot 1 1 2.00

Software of ADMS ISR Software Lot 1 1 2.00 DMS software Lot 1 1 2.00 OMS Software (HV, MV & LV System) Lot 1 1 2.00

DTS software Lot 1 1 2.00 Software for Training of operators

Developmental software Lot 1 1 2.00 Software for Bug fixing and other

coding requirement

Network Management Software Lot 1 1 2.00

Network Management for

monitoring health of communication

system WEB/Network security software (Included in IT Package) Lot 1 1 2.00 For Cyber security

purposes

RDBMS package (Included in ISR) Lot 1 1 2.00

Database Management

Software GIS Adaptor/Engine for importing data from GIS system under IT system

Lot 1 1 2.00 Importing data from GIS module

Field Client / Web Client Licences for ADMS System Lot 15.00 Software for

Interface with

Page 94: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

94

All the 66 kV breakers and 11 kV VCB’s at existing 66 kV S/Stns in the project area will be replaced/upgraded by the SCADA compatible Breakers/VCB’s .The 66 kV breakers and 11 kV VCB panels at new proposed 7 no. S/Stns will be SCADA compatible. The cost of the same has been considered in the BOQ and estimate of transmission system (Placed at Annexure B)

devices which need data on internet

Inbuilt Web Call Centre for Vip Consumers (Upto 1 Lakh) Lot 1 1 2.00

Call centre module for grievance redressal of consumers

Asset Management Lot 1 1 2.00 Software for Life

Cycle management of Equipments

AVTL (Automatic Vehicle Tracking System) Lot 1 1 2.00 Crew tracking

software Renewable Integration & Weather Forecasting

Lot 1 1 2.00 Software For

weather forecasting for Load forecasting

Building Management system + Access Control + Fire Management System

Lot 1 1 2.00 Software for Life

Cycle management of Equipments

UPS of Control Centre (20 kVA Redundant UPS) Lot 1 1 2.00 Uninterrupted power

supply

Visual Monitoring Software Lot 1 1 1.00 Software for Life

Cycle management of Equipments

Page 95: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

95

8 LOAD FORECASTING UPTO 2031 8.1 Calculation of Ultimate load of Project area ie DLF City

Subdivision up to 2031 for design of proposed electrical network

Based on field survey, load projections have been worked out which are

based on following criteria:

a)Plotted Area-Ultimate load projections upto 2031 for plotted area are

based on DHBVN load norms as per sales circular D-9/2014.

Exception:

For 60 sq. yards plots in DLF-III,load per plot has been assumed as

15KW/Plot(instead of 6 KW) and demand factor has been assumed at

0.7(instead of 0.4).This exception has been made keeping in mind present

construction practice in this area.DLF-III is located behind DLF Cyber city

and is a residential hub for workforce working in DLF Cyber

City.Presently,on a normal 60 Sq. yards plot,5-6 floors,with 02 dwelling

units per floor are being constructed.Entire building is being used for

P.G.accomodation and each room is being fitted with a 0.75 tonnes

A.C.Hence, load norm and demand factor has been modified to arrive at

ultimate load of this area.

b)MCG area-Ultimate load projection has been arrived at by study of

present load of MCG area and possibility of expansion of area by carrying

out physical survey of area and taking inputs of field staff

c)Single Point/HT connections:Sanctioned load of existing connections

has been taken as Ultimate load requirement for these category

connections as most of connections have been running for a long duration

and their load is not expected to go beyond their sanctioned load.

Page 96: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

96

d)Upcoming Load:Upcoming load has been calculated based on possible

load demand of sites which are earmarked in approved layout plans of

DTP/HUDA for commercial/residential projects, but are lying vacant as on

date.

Detail of Ultimate load sector wise Up to 2031

8.2 Load to be fed at 11 KV(Other than DLF V) SECTO

R LOAD IN MVA

24

ULTIMATE LOAD OF DLF-III

NATHUPUR VILL

EXISTING HT CONN LOAD

UPCOMING HT LOAD

TOTAL

PLOTTED AREA

MCG AREA IN PLOTTED DLF-III AREA

ON M.A. ROAD DLF-III

60 15 10 15 100

25

ULTIMATE LOAD OF DLF-II

EXISITNG HT CONN LOAD

HERITAGE SOCIETY

THE VILLAS GHS

UPCOMING HT LOAD

TOTAL

PLOTTED AREA DLF-II

MAJOR HT CONNECTIONS ON MG ROAD & BALANCE IN VARIOUS PHASES OF DLF-II

HERITAGE GROUP HOUSING SOCIETY ON MG ROAD

GROUP HOUSING SOCIETY IN VICINITY OF MG ROAD

PLOTTED AREA DLF-II

34 13 7.5 4.2 10 68.7

26

ULTIMATE LOAD OF GH BLK

SOA GHS, DLF-1

SIKANDERPUR VILL

EXISITNG HT CONN LOAD

UPCOMING LOAD

TOTAL

G AND H BLOCK DLF-1

GROUP HOUSING SOCIETY ON GURGAON FARIDABAD ROAD

MCG AREA HT CONNECTIONS NEAR GURU DRONACAHRYA METRO STATION, MG ROAD

NEAR GURU DRONACAHRYA METRO STATION, MG ROAD

8.4 7.2 6 9 15 45.6

Page 97: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

97

27

ULTIMATE LOAD OF PLOTTED HUDA 27

ULTIMATE LOAD OF S LOK B BLK

ULTIMATE LOAD OF DLF IV

EXISTING HT CONNECTION LOAD

UPCOMING HT LOAD

TOTAL

HUDA PLOTTED AREA SEC-27

PLOTTED AREA B BLOCK SUSHANT LOK-1

PLOTTED AREA DLF-IV

MAJOR HT CONNECTIONS NEAR GALLERIA MARKET AND NEAR HUDA CITY CENTRE, BALANCE IN DLF-IV AND B BLK SUSHANT LOK

5 8.5 7 25 10 55.5

25 A

LOAD OF NMC GHS

LOAD OF BEVELDERE PARK-1&2

OTHER LOAD

TOTAL

GROUP HOUSING SOCIETY ON NH-8 NEAR SHANKAR CHOWK

GROUP HOUSING SOCIETY NEAR RBS BUILDING, DLF CYBER CITY

1 4 2 7

26A

ULTIMATE LOAD OF PLOTTED DLF-1

EXISTING HT CONNECTION LOAD

UPCOMING HT LOAD

TOTAL

26 5 10 41

28

ULTIMATE LOAD OF PLOTTED HUDA 28

ULTIMATE LOAD OF A BLK S LOK

ULTIMATE LOAD OF DLF IV

EXISTING HT CONNECTION LOAD

CHK VILL+S VIHAR + M VIHAR

UPCOMING HT LOAD

TOTAL

Page 98: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

98

PLOTTED AREA OF HUDA SEC-28

PLOTTED A BLOCK SUSHANT LOK-1

PLOTTED AREA DLF-IV

MAJOR HT CONNECTIONS ON MG ROAD,BALANCE LOAD OF GHSs NEAR GALLERIA MARKET

MCG AREA

3 8.1 4.2 61 15 15 106.3

42

ULTIMATE LOAD OF PLOTTED 42

EXISTING HT CONNECTIONS

UPCOMING HT CONNECTION LOAD

TOTAL

PLOTTED AREA OF HUDA SEC-42

HT CONNECTIONS OPP. SEC-43 SSTN.

OPP. SEC-43 SSTN.

5.7 11 5 21.7

43

ULTIMATE LOAD OF PLOTTED 43

ULTIMATE LOAD OF C,D,E BLK S LOK

ULTIMATE LOAD OF DLF IV

EXISTING HT CONNECTION LOAD

UPCOMING HT LOAD

TOTAL

PLOTTED AREA OF HUDA SEC-43

PLOTTED AREA OF SUSHANT LOK-1

PLOTTED AREA OF DLF-IV

HT CONNECTIONS ON HUDA CITY CENTRE TO GOLF COURSE ROAD,HUDA CITY CENTRE TO SEC 52 ROAD AND SEC-52 REDLIGHT TO GOLF COURSE

9.1 24.5 3.4 28 20 85 TOTAL 530.8

8.3 Table 8.3 Load to be fed at 66 KV &11 KV

Page 99: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

99

It is to be noted that load of DLF Phase V is to be fed from 66 KV S-stn.

DLF V, where electrical infrastructure is to be laid by colonizer M/s DLF as

per future load requirement and as per electrification plan)

Detail of Load to be fed at 66 KV & 11 KV(in addition to load tabled at table

8.3)is tabled below:

S.No.

Sector Load in 2015 (in MVA)

Load in 2022 (in MVA)

Load in 2027 (in MVA)

Projected Load in 2031(in MVA) on Basis of Load growth estimation

Feeding Voltage Level of Load (In KV)

Remarks

1 Ambience Island, NH-24

7 21 40 60 66 Load of Ambience island will be shifted to 66 KV Ambience S-Stn.M/s Ambience has already applied for single point connection at 66 KV level

2 Dlf Cyber City

100 110 125 140 66 Load requirement is to be met from 220/66 KV S-Stn to be built for Cyber city

3 Rapid Metro

3 10 15 20 66 Load of Rapid Metro is to be shifted to Proposed 66 KV sec 56 S-Stn to be constructed by Rapid Metro

4 DLF PHASE 5

27 60 90 120 11 Load of DLF Phase V will be fed exclusively from DLF V S-Stn as network of Phase V is sufficient.Augmentation/construction of new 66 KV S-Stn will be carried out by M/s DLF Ltd for DLF V based on load growth

Total of Ultimate Load Up To 2031=A+B=531+340=871 MVA

Page 100: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

100

8.4 Table 8.4 Load to be fed at Various Voltage levels

S.No. Voltage level Load to be fed

1 11 KV 651 MVA

2 66 KV 220 MVA

Total 871 MVA

8.5 Table 8.5:Year Wise Load Projection at Existing 03 No. 66/11 KV S-stns. and 07 no. proposed 66/11 KV S-stns.(Other than DLF V)

SR NO.

NAME OF

S/STN. AREA TO BE FED

ULTIMATE

LOAD (IN MVA)

LOAD BY END

OF 2017

LOAD BY

END OF

2022

LOAD BY

END OF

2027

LOAD BY

END OF

2031

TOTAL LOAD

1 66 KV

S/S MA ROAD

U Block,V Block,W block,T block, M.A. road DLF-III,Nathupur village 23 17 20 22 23 38

MVA Future HT Load 15 0 0 15 15

2 66 KV S/S Q

BLOCK

U Block DLF-III,Nathupur Village,P,Q,M,K block DLF-II, Heritage GHS,MG road HT

Connections,HT connections around DLF Cyber City

63 45.1 50 55 62.9 78 MVA

Future HT Load 15 0 3 8 15

3 66 KV

S/S MG ROAD

Sikanderpur Vill.,Nathuupur Vill. ,S Blk, T Blk , V Blk DLF-III, G Blk DLF-1, Silver Oaks, Garden estate GHS,

HT Connections around Guru Dronacharya Metro station

66 40.3 50 58 65.6 76 MVA

FUTURE LOAD NR D/C METRO STN. 10 0 4 6 10

4 66 KV ARJUN MARG

A,B,C,D,E,F,H,F block Dlf-1 49 34.8 40 44 48.7 49

MVA

5 66 KV

S/S SEC-28

Sector-27,28, DLF-IV 42 26.9 40 41 41.6 50 MVA Future HT Load 8 0 0 4 8

6

66 KV S/S

S/LOK,C-BLOCK

B,C.C1,D Block Sushant Lok-1 and HT Connections from HUDA City

centre to Sec-52 Chowk 55 40 50 52 54.8 65

MVA Future HT Load 10 0 0 5 10

Page 101: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

101

7 66 KV S/S A- BLOCK

A Block S/Lok-1, DLF-IV, HT Connection of MG Road 30 21.1 25 28 30.1 40

MVA Future HT Load 10 2 6 10

8

66 KV S/S, L-

BLK(DLF-II)

DLF Phase-2, HT connections of MG Road

44 31.1 35 38 43.8 54

MVA 10 0 2 6 10

9 66 KV

S/S H.B.CKP.

Sarasvati Vihar, Maruti Vihar, Vill. Chakarpur, HT Connections of MG

road 28 19.5 20 25 27.5

28 MVA

10 66 KV

S/S SEC-43

Plotted area Huda Sector-42,43, GHS Sector-43, HT Connections of Golf course road upto sec-42 and

DLF-1 xrossing 43 30.8 40 42 45.3 53

MVA

Future HT load 10 0 2 10 10

TOTAL 531 306.6 383 465 531.3 531

8.6 Table 8.6:Total No. of 11 KV feeder to be laid Sstn. wise(Except DLF V)

SR NO

. NAME OF S/STN. AREA TO BE FED

LOAD (IN

MVA)

TOTAL LOAD

NOS. OF FEEDERS. TO BE LAID TOTAL

FEEDER PRESENT FUTURE

1 66 KV S/S MA ROAD

U Block,V Block,W block,T block, M.A. road DLF-III,Nathupur village 23 38

MVA 5 0 8

Future HT Load 15 0 3

2 66 KV S/S Q BLOCK

U Block DLF-III,Nathupur Village,P,Q,M,K block DLF-II, Heritage GHS,MG road HT

Connections,HT connections around DLF Cyber City

63 78 MVA

13 0 17

Future HT Load 15 0 4

3 66 KV S/S MG ROAD

Sikanderpur Vill.,Nathuupur Vill. ,S Blk, T Blk , V Blk DLF-III, G Blk DLF-1, Silver Oaks, Garden estate GHS,

HT Connections around Guru Dronacharya Metro station

66 76 MVA

13 0 16

FUTURE LOAD NR D/C METRO STN. 10 0 3

4 66 KV ARJUN MARG

A,B,C,D,E,F,H,F block Dlf-1 49 49

MVA 11 0 11

5 66 KV S/S SEC-28 Sector-27,28, DLF-IV 42 50

MVA 10 0

12 Future HT Load 8 0 2 6 66 KV S/S B,C.C1,D Block Sushant Lok-1 and 55 65 13 0 16

Page 102: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

102

S/LOK,C-BLOCK HT Connections from HUDA City centre to Sec-52 Chowk

MVA

Future HT Load 10 0 3

7 66 KV S/S A- BLOCK

A Block S/Lok-1, DLF-IV, HT Connection of MG Road 30 40

MVA 7 0

10 Future HT Load 10 0 3

8 66 KV S/S, L- BLOCK(DLF-II)

DLF Phase-2, HT connections of MG Road

44 54 MVA

10 0 12

10 0 2

9 66 KV S/S H.B.C. CHAKKARPUR

Sarasvati Vihar, Maruti Vihar, Vill. Chakarpur, HT Connections of MG 28 28

MVA 6 0 6

10 66 KV S/S SEC-43

Plotted area Huda Sector-42,43, GHS Sector-43, HT Connections of Golf course road upto sec-42 and

DLF-1 xrossing 43 53

MVA 10 0

12

Future HT load 10 0 2

TOTAL 531 531 98 22 120

8.7 Table 8.7 :DT Installation schedule to meet out Urban load(Other GHS and Single point connections)for meeting Ultimate Load Up to 2031

Year wise

Requirement

Detail of Utilization of existing

DT / Installation of New DT

Capacity of DT ( In

KVA)

400 500 630 1000

Up to 2022 Existing DT to be Utilized

13 109 21 5

New DT to be Installed Initially ie by end of 2017

19 0 144 65

DT at end of 2022

32 109 165 70

Up to 2027 New DT to be added due to augmentation before end of 2027

0 0 0 109

New DT to be installed before 2027

0 0 0 30

DT at end of 2027

32 0 165 209

Page 103: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

103

Up to 2031 New DT to be added due to augmentation before end of 2031

0 0 0 185

New DT to be installed before 2031

0 0 0 31

DT at end of 2031 12 0 0 425

Remarks:DTs of lower capacity(ie 400/500/630 KVA) will be augmented by

DTs of higher capacity ie 630/1000 KVA as per actual requirement and load

growth post 2022

Page 104: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

104

9 NETWORK UPGRADATION & STRENGTHENING 9.1 Proposed Network Up-gradation / Strengthening Initiatives by

DHBVN Following attributes are proposed in DLF City Sub Division for

electrical distribution infrastructure Up-gradation/Strengthening:

• Identification of load centres and location at these load centres for

creation of 07 no new 66/11 KV S-stns. to address problemsof:

Right of way from existing Substations for laying of new

feeders

Long 11 KV feeders resulting in poor voltage regulation

High down-time of 11 KV feeders due to existence of multiple

feeders on common poles

• Switch over from overhead HT and LT system to underground system

based on feasibility, wherever possible, by laying cables through

trenchless boring or otherwise by simple digging, as the case may be.

Where the laying of underground cables will not be possible, an

overhead system on mono-poles will be erected.

• 100% redundancy level will be created at the distribution level (both

at 11 KV feeder level and Distribution transformer level) whereas N-1

level redundancy will be created at the transmission level and

substations

• Installation of Supervisory Control and Data Acquisition (SCADA)

system with scalability for entire project area of Gurgaon

• Implementation of Advanced Metering Infrastructure (AMI) and set up

of control centre scalable for entire project area of Gurgaon

• Ring Main Units (RMUs) will be installed on different sections to

ensure uninterrupted power supply

• Operation staff will be equipped with latest state-of-art maintenance

equipment to carry out inspections

Page 105: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

105

• After laying of the new up-graded system with 100% redundancy,

complete system will be operated and maintained by DHBVN staff

9.1.1 Layout of Existing 11 KV Radial feeders

Electrical S/STN-1

Electrical S/STN-3

Electrical S/STN-2

Page 106: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

106

9.1.2 Layout of proposed 11 KV Ring Main System

E/SSTN-1

E/SSTN-3

E/SSTN-2

Page 107: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

107

LEGENDS

220/66 KV SUBSTATION

11 KV UNDERGROUND/OH CIRCUIT

PROPOSED 11 KV UG/OH CKT FOR 11 KV RING MAIN

LT FEEDER PILLAR FOR O/G SERVICE CONNECTION

LT CABLE FOR RING MAIN OF FEEDER PILLAR

4 WAY/3 WAY RING MAIN UNIT

11KV/0.433 KV DISTRIBUTION TRANSFORMER

E/SSTN

Page 108: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

108

GIS Based 11 kV Network of existing Sector 27 feeder from Sector 28 S/stn

Page 109: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

109

9.2 Proposed Network Up-gradation/Strengthening Initiatives by HVPN

Based on studies, Transmission system strengthening was evolved which

broadly includes following:

• Establishment of new 220 kV substation (GIS) to cater to requirement

of new demand centers

• 220 kV Multi circuit Transmission line (High capacity conductor)

(Overhead/Cables)

• Formation of 220 kV Transmission ring beneath planned 400 kV ring

• Augmentation of Transformation capacity on existing/under

construction/HVPN planned Substation at 220/66 kV & 220/33 kV

level

Page 110: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

110

1. Existing EHV substations

Sr. No. Location Capacity (MVA)

400/220 kV

1. Daultabad 3x315 = 945

2. Secor-72 (POWERGRID substation)

2x315 =630

3. Panchgaon (POWERGRID substation)

2x500 = 1000

Total 2575

(B) 220/66 kV

1. Badshahpur 4x100 = 400

2. Sector 52A, Gurgaon 3x100= 300

3. IMT Manesar 2x100 = 200

4. Daultabad 4x100 = 400

5. Sector 56, Gurgaon 2x100 = 200

6. Sector 72, Gurgaon 2x100 = 200

7. BBMB, Delhi 60

Sub Total 1760

(C ) 220/33 kV

1. Sector 72, Gurgaon 1x100 = 100

Sub Total 100

Presently Gurgaon Transmission network faces challenges like inadequate

redundancy of 220kV lines as well as transformers (both Power

transformers as well as Distribution transformer). These 220kV

Page 111: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

111

transmission lines and power transformer get critically loaded during

contingency conditions.

Table: Existing 66 KV Substation Network and Capacity

S. No. Location Capacity (MVA)

66/11 kV

1. Badshahpur 2x25/31.5 = 63

2. Sector 52A, Gurgaon 2x16/20 = 40

3. IMT Manesar 1x25/31.5 = 31.5

4. Daultabad 1x25/31.5 + 1x12.5/16 = 47.5

5. Sector 56, Gurgaon 1x12.5/16 + 2x25/31.5 = 79

6. Farukhnagar 2x12.5/16 = 32

7. Gurgaon (Mehrauli Road) 3x12.5/16 + 1x25/31.5 = 79.5

8. Maruti 2x25/31.5 = 63

9. Old Manesar 2x25/31.5 = 63

10. Patuadi 3x12.5/16 + 1x25/31.5 =79.5

11. Sector 9, Gurgaon 2x25/31.5 + 1x12.5/16 = 79

12. Sector 10A, Gurgaon 3x12.5/16 + 1x25/31.5 =79.5

13. Dundahera 3x25/31.5 = 94.5

14. Sector 23, Gurgaon 2x25/31.5 = 63

15. Sector 28, Gurgaon 2x25/31.5 + 1x12.5/16 + 4 MVA Rapid Metro = 79

16. Gurgaon (DLF Enclave Q Block) 3x12.5/16 + 1x25/31.5 =79.5

17. Sector 34, Gurgaon 2x12.5/16 + 2x16/20 = 72

18. IMT Manesar, Sector – 3 2x25/31.5 = 63

19. Bhore Kalan 2x25/31.5 = 63

20. Sector 44, Gurgaon 2x25/31.5 = 63

21. Harsaru, Gurgaon 1x25/31.5 + 1x12.5/16 = 47.5

Page 112: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

112

S. No. Location Capacity (MVA)

22. Sector 38, Gurgaon 2x25/31.5 = 63

23. Sector 2, Gurgaon 3x25/31.5 = 94.5

24. Sector 2, IMT Manesar 2x12.5/16 = 32

25. Sector 4, IMT Manesar 2x25/31.5 = 63

26. Sector 15 II, Gurgaon 2x25/31.5 = 63

27. Sector 43, GGN (GIS) 2x25/31.5 = 63

28. Sector 51, GGN (GIS) 1x25/31.5 + 1x12.5/16 = 47.5

29. IMT Manesar, Sector 8 2x16/40 = 20

30. DLF Phase – V 3x16/20 = 60

31. Rico (Pvt.) 18

32. Sunbeam (Pvt.) 10

33. Munjal Kiriu (Pvt. Consumer) 16

34. Sector 47 (Unitech) 3x16/20 = 60

Total 1991 MVA

Future Transmission System

Considering peak demand requirement of 4800 MW by 2021-22, studies

have been carried out to assess requirement of transmission strengthening,

if any. For this, HVPN transmission future planning has also been taken into

considerations account and any further transmission requirement over

HVPN planned system has been examined. It is to mention that HVPN has

already planned a new 400/220kV substation at Farukh Nagar with LILO of

400 kV Dhanonda-Daulatabad D/c line. Likewise, 220kV Sector-57, Sector-

20, Sector-33 and Panchgaon substations are already under construction

and envisaged to be commissioned in this Financial Year along with their

interconnecting lines.

Page 113: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

113

In the 35th standing committee meeting on power system planning in

Northern region in 03.11.14, establishment of new 400kV substations in

Gurgaon area as Inter State Transmission was agreed. Looking at the load

growth in Gurgaon area, a 400kV ring system connecting existing 400kV

substation with proposed future substations were agreed. Ring System is

proposed with interconnection of 400kV Dhanonda(HVPN) – Farukh

Nagar(HVPN)-Daultabad (HVPN)-Gurgaon(PG)- Sohna Road(ISTS)-

Manesar (PG)-Neemrana(PG) substations. The 400kV Sohna Road as well

as Kadarapur S/s in Gurgaon area are also agreed to be established as

part of Inter State Transmission through Tariff based Competitive Bidding

(TBCB). In above meeting, 400kV Prithla/Palwal S/s was also agreed to be

developed as ISTS with interconnection of Kadarpur and Aligarh

S/s.Proposed 400kV Transmission Ring around Gurgaon is shown at Fig 2-

5 below

Proposed 400 kV Transmission Ring around Gurgaon

Considering establishment of new 400/220kV substations at Farukh Nagar

(HVPN), Sohna Road (ISTS) &Kadarpur (ISTS), it is proposed that future

load may be served

Page 114: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

114

From these load centers based EHV substations so as to relieve

loading of 400kV Daultabad and Gurgaon (PG)/Sec-72 Sub-

stations. Following transmission system is envisaged to come up

in near future at Intra/Inter-state level:

400/220kV substations (3630 MVA)

• Farukh Nagar (2x315 MVA) (HVPN)

• Sohna Road (2x500 MVA) (ISTS)

• Kadarpur (2x500 MVA) (ISTS)

Augmentation of 400/220kV transformation capacity by 2x500 MVA

at Sec-72

9.2.1 HVPN Proposal for Phase-1 of Part-1 ie for area under DLF City Subdivision

1. New plan has been envisaged at 11 KV level and accordingly the

DHBVN has required strengthening of 66 KV and 220 KV

transmission network. As per proposal submitted by SE/Smart City

Project, DHBVN Gurgaon DHBVN envisaged ultimate load of 531

MVA upto year 2031 (excluding load of Ambience Island, DLF Cyber

City, DLF Phase-V and Rapid Metro), 07 no. new 66/11 kV

substations are proposed to be constructed by HVPNL in place of 11

no. 33/11 kV substation proposed earlier. Requirement for creation of

following 66/11 kV HVPNL substations justifying the requirement

herein as under:

Page 115: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

115

Sr. no.

Name of S/Stn. Area to be fed Load (MVA)

Total load

No. of feeders

Total feeders

1 66 kV S./Stn. MA

Road, Land opp.

MA-28A, MA

Road, DLF-III

Nathupur

village

8 49

MVA

2 12

U-Block 18 4

T-Block/V-Block

(DLF-III)

15 4

Up coming load

of DLF-III

8 2

2 66 kV S/S MG

Road MCG Land

Opp. Neelkanth

Hospital

Nathupur

village

7 64

MVA

2 16

Sikkanderpurvill

.

5 2

HT cons. On

MG Road NR

D/C Metro

Station

20 5

Upcoming load

NR D/C Metro

stn.

10 2

Siris Road DLF-

III

10 2

G/H Block +

Silver Oak

12 3

3 66 kV Arjun G/H Block + 12 52 3 13

Page 116: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

116

Marg, Land at C

Block DHBVN

Complaint center

Silver Oak MVA

B, C, D & E

Block DLF-I

24 6

A & A (Extn.)-

Block DLF-I

16 4

4 66 kV S/S S/Lok,

C-Block, Land at

ESS C Block S-

Lok-1

S/Lok-1 C, D &

E Plotted area

28 57

MVA

7 14

HT Conns. On

gold souk road

and HUDA CC

to GC road

25 6

Sushant Lok-1,

B-Block

4 1

5 66 kV S/Stn. A-

Block, Land at

ESS C Block-S-

Lok-1

Sushant Lok-1,

B-Block

5 62 1 14

Sushant Lok-1

A- Block

8 2

DLF Phase IV 4 1

GHS of Sector-

28

17 6

HT conns. Of

MG road.

20 4

6 66 kV S/Stn., L-

Block (DLF-II)

50

MVA

12 12

Page 117: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

117

7 66 kV S/Stn.

H.B.C.Chakkarpu

r Complaint

centre

45

MVA

11 11

The above chart predicts that area under Part –I of

Ist Phase under Smart Grid Project i.e. DLF Sub-

Division Area comprises of DLF Ph-I, II, III, M.G

Road, Partial area of Golf Course Road,

SushantLok-I, Sector-28, Sector-43 etc. The

ultimate demand of this area as of now is 231 MVA

which is being fed from various sub-stations of

HVPNL located inside or boundary of these areas

with most of the Power transformers and 11 KV

feeders fully loaded with no redundancy.

DISCOMs with their load projections have

anticipated that the present load of 231 MVA of DLF

Sub-Division area will increase to 306.6 MVA by the

end of 2017,370 MVA by 2020, & 531.30 MVA by

2031.

Thus, it becomes evident from above projection that

additional load of 75.60 MVA, 139 MVA, & 300.30

MVA is predicted by the end of 2017, 2020 & 2031

respectively.

Apart from above Bulk Consumers such as DLF,

Ambience and Rapid Metro are also anticipating

load of 140 MVA, 60 MVA & 20 MVA respectively

Page 118: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

118

that cumulatively comes to 220 MVA by the end of

2031.

To cater this increased demand no 220 KV Sub-

stations exists in the area in question. Moreover

the Sub-stations from which this area is being

presently fed have become fully loaded.

2. That the requirement of load at different voltage levelestimated for the

year 2022 and 2031 is estimated as under:

3. It is submitted that all the new transmission assets likely to be created

shall have normal life span of about 25 years and would comply with

the relevant tariff orders life cycles stipulated in the depreciation

schedule of the assets. It is submitted that the strengthening of

transmission system would facilitate unregulated quality 24x7 power

free from outages. It is submitted that the creation and upgradation of

transmission assets would ease out extremely stressed and

overloaded transmission system having no redundancy. It is

submitted that the smart city project envisaged with the improved

transmission and distribution infrastructure would facilitate economic

growth. It is submitted that the total cost of the project of about 702

Crores proposed to be spent by HVPN in the high revenue return

areas would be incurred by HVPN at the behest of distribution utility

to facilitate strengthening of distribution system and by providing

reliability with capacity additions at various substations through up

gradation and augmentations of the capacities of the associated

substations and transmission lines. The amount spent by HVPN

would be recovered through ARR and reliability surcharge. It is

submitted that the improvement in the transmission system having

reliability of 24x7 would save massive quantity of fossil fuels thus

Page 119: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

119

saving huge amount of foreign exchange besides converting

expenditure on fossil fuel.

It is submitted that two new 220 kV substations having transformation at

220/66 kV level would be created. It is submitted that a 220 kV substation is

being proposed at DLF Q Block with the proposed capacity of 3x160 MVA,

220/66 kV (GIS). Presently a 66 kV substation is constructed on the land

measuring – 6136 Sq meters (1.51 acres). Additional land of 5427 Sq

meters (1.34 acres) and 1568 Sq meters (0.39 acres) available at site

under the possession of Town & Country Planning was handed over by M/s

DLF.

Further a 220 kV substation is prosed at Sector-28 with a proposed

capacity of 3x160 MVA, 220/66 kV (GIS). At present the land available is

11164 sq meters (2.76 acres). Adjoining additional land measuring 4170 sq

meter (1.03 acres) pertaining to Municipal Corporation Gurgaon is available

in the vicinity of the substation and is currently being used as garbage

dump.

9.2.2 Connectivity of Proposed HVPN Sub-stations

Page 120: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

120

9.2.3 Connectivity of proposed HVPN Sub-stations along with down the level connected lines

220 KV Lines

1. Creation of associated 220 KV transmission lines as under :-

i) Creation of 220 KV D/C line on M/C towers from

400 KV S/stn Kadarpur to proposed 220 KV Sub-

Station DLF Q- Block, Gurgaon with HTLS

conductor/underground cable having capacity

equivalent to twin Moose ACSR conductor i.e.

approximately 500 MVA (at 50 degree ambient

Page 121: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

121

temperature).{ Tentative Length: 14.00 KM }

ii) Creation of 220 KV D/C line on M/C towers from

400 KV S/stn Kadarpur to 220 KV Sub-Station

Sec-52A, Gurgaon with HTLS conductor having

capacity equivalent to twin Moose ACSR

conductor i.e. approximately 500 MVA (at 50

degree ambient temperature).{ Tentative Length: 08.00 KM }

iii) Creation of 220 KV D/C line on M/C towers from

existing 220 KV Sub-Station Sector-52A,

Gurgaon to proposed 220 KV Sub-Station Sector-

28, Gurgaon with HTLS conductor having

capacity equivalent to twin Moose ACSR

conductor i.e. approximately 500 MVA (at 50

degree ambient temperature).{ Tentative Length: 5.00 KM }

Iv) Creation of 220 KV D/C line on M/C towers from proposed 220 KV

S/stn Sec-28 to proposed 220 KV Sub-Station DLF Q- Block, Gurgaon with

HTLS conductor/underground cable having capacity equivalent to twin

Moose ACSR conductor i.e. approximately 500 MVA (at 50 degree ambient

temperature).{ Tentative Length: 03.00 KM }

66 KV Lines

2. Creation of 66 KV D/C line on underground Aluminum cable of size 1200

Sq.mm XLPE from proposed 220 KV Sub-station Sector-28 to 66 KV Sub-

station Sushant Lok C- Block, Gurgaon. ( Tentative Length – 3.80 Km )

3. Creation of 66 KV D/C line on underground Aluminum cable of size 1200

Sq.mm XLPE from proposed 66 KV Sub-station Sushant Lok A- Block,

Gurgaon to proposed 66 KV Sub-station Sushant Lok C- Block, Gurgaon. (

Page 122: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

122

Tentative Length – 2.30 Km )

4 Creation of 66 KV D/C line on underground Aluminum cable of size 1200

Sq.mm XLPE from proposed 220 KV Sub-station Sector-52 to 66 KV Sub-

station Sushant Lok C- Block, Gurgaon. ( Tentative Length – 2.70 Km )

5 Creation of 66 KV D/C line on underground Aluminum cable of size 1200

Sq.mm XLPE from proposed 220KV Sub-station sector 28 to proposed 66

KV Sub-station Arjun Marg, Gurgaon (Tentative Length – 1.60 Km).

6 Creation of 66 KV D/C line on underground Aluminum cable of size 1200

Sq.mm XLPE from proposed 66KV Sub-station MG Road to proposed 66

KV Sub-station Arjun Marg, Gurgaon ( Tentative Length –5.10 Km ).

7 Creation of 66 KV D/C line on underground Aluminum cable of size 1200

Sq.mm XLPE from proposed 220 KV Sub-station DLF Q Block to proposed

66 KV Sub-station M.G Road, Gurgaon. ( Tentative

Length – 0.71 Km )

8 Creation of 66 KV D/C line on underground Aluminum cable of size 1200

Sq.mm XLPE from proposed 220 KV Sub-station DLF Q-Block to proposed

66 KV Sub-station L Block Gurgaon. ( Tentative

Length – 3.0 Km )

9 Creation of 66 KV D/C line on underground Aluminum cable of size 1200

Sq.mm XLPE from Proposed 66 KV Sub-station S.Lok A-Block, Gurgaon to

proposed 66 KV Sub-station L-Block, Gurgaon. ( Tentative Length – 2.1

Km )

10 Creation of 66 KV D/C line on underground Aluminum cable of size 1200

Sq.mm XLPE from 66 KV Sub-station Sector 44 to proposed 66 KV Sub-

station S.Lok A-Block Gurgaon. ( Tentative

Length – 2.50 Km )

12 Creation of 66 KV D/C line on underground Aluminum cable of size 1200

Page 123: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

123

Sq.mm XLPE from proposed 220 KV Sub-station DLF Q Block to proposed

66 KV Sub-station MA Road Gurgaon. (

Tentative Length – 4.2 Km )

13 Creation of 66 KV D/C line on underground Aluminum cable of size 1200

Sq.mm XLPE from 220 KV Sub-station Sector 20 to proposed 66 KV Sub-

station MA Road Gurgaon ( Tentative Length – 4.50 Km )

4. That the Capacity addition will be made at both 220 kV and 66 kV

levels.. Further, need based conversion of 66/11 kV transformers to

66/33kV would be carried out and additional 66/33 kV transformers

would be added, wherever required. The following substations have

feasibility for upgradation to 220 kV level.

I. 66kV S/S Sector-28 - 2x25/31.5MVA.

II. 66 kV S/S DLF Q Block - 1x25/31.5MVA and

3x12.5/16 MVA.

5. It is submitted that 220 kV level new lines, conversion of existing 220

kV lines to High Capacity HTL, providing new underground cables

would be carried out.

9.2.4 Proposal for Transmission Infrastructure at Various Sub-stations

Sr. No

Description

1. Up-gradation of existing 66 kV AIS substation Q Block DLF

Gurgaon to 220/66/11 kV GIS substation Q Block DLF Gurgaon

completely laced with Substation Automation System fully

compliant for unmanned remote operation from remote SCADA

station with the installed capacity of 3x160 MVA, 220/66 KV,

Page 124: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

124

3x25/31.5 MVA, 66/11 kV Power transformers along with two

250 KVA, 11/0.440 KV with Transformers and Capacitor banks

of appropriate rating and Voltage along with requisite bays and

breakers.

The Sub-station to have following Scope of Works:

220 KV Side(GIS):

a. Three Transformer bays for 3x160 MVA, 220/66 KV

transformers.

b. Four Line bays + Scope for extension of two line bays in future.

c. Bus Coupler Bay

66 kV Side(GIS):

a. Three Incomer 66 kV bays of 3x160 MVA, 220/66kV

transformers.

b. Three 25/31.5 MVA, 66/11 kV transformer bays.

c. Nine Line bays including two bays for private developers

seeking load at 66kV level.

d. Requisite Capacitor bays

e. Bus Coupler Bay

11 kV Side (GIS):

a. Two Incomers (GIS) breakers for each 25/31.5 MVA 66/11 kV

transformer.

b. One Bus Coupler (GIS) breaker against each transformer.

c. Eight outgoing feeders (400 amp.) (GIS) breakers against each

transformer.

d. Capacitor banks 11 kV (GIS) breakers required for appropriate

Page 125: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

125

MVAr rating.

e. Required 11kV breakers for station transformers.

• All breakers essentially to have motorised earth

switch.

Note :

I. The existing 66 kV AIS substation Q-Block shall continue to

function till the commissioning of upgraded 220/66 kV GIS

substation.

II. The existing 66 kV AIS substation shall be dismantled only after

the commissioning of new 220/66 kV GIS substation.

III. An authenticated list of inventory of all usable materials require

reallocation after dismantlement would be provided by Smart

Grid team/ Officer Incharge for execution to the office of Chief

Engineer/MM for further allocation on approved augmentation

and additional works at various substations.

IV. All non- usable material will be got surveyed off from competent

authority and shall be returned to stores.

V. The Design wing would explore the possibility to utilize existing

25/31.5 MVA transformers, however if it is not feasible, the

transformers of 25/31.5 MVA rating which are required to be

provided/allocated on the proposed 66 KV new sub-stations

transformers proposed herein after for the approval.

VI. The Sub-station is required to be commissioned by January

2018 and to be listed in the Works list of FY 2016-17.

2. Up-gradation of existing 66 kV AIS substation sector 28

Gurgaon to 220/66/11 kV GIS substation Sector-28, Gurgaon

with the installed capacity of 3x160 MVA, 220/66 KV, 3x25/31.5

Page 126: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

126

MVA, 66/11 kV Power transformers along with two 250 KVA,

11/0.440 KV Station Transformers completely laced with

Substation Automation System fully compliant for unmanned

remote operation from remote SCADA station

The Sub-station to have following Scope of Works:

220 KV Side(GIS):

a. Three Transformer bays for 3x160 MVA, 220/66 KV

transformers.

b. Four Line bays + Scope for extension of two line bays in future.

c. Bus Coupler Bay

66 kV Side(GIS):

a. Three Incomer 66 kV bays of 3x160 MVA, 220/66kV

transformers.

b. Three 25/31.5 MVA, 66/11 kV transformer bays.

c. Five Line bays + Requisite Capacitor bays + Scope for

extension of two line bays for future (having compatible

ampicity to 1200 sq mm, aluminium XLPE 66 kV underground

cable)

d. Bus Coupler Bay

11 kV Side (GIS):

a. Two Incomers (GIS)breakers for each 25/31.5 MVA 66/11 kV

Transformer

b. One Bus Coupler(GIS) breaker against each transformer

c. Eight outgoing feeders (400 amp.) (GIS) breakers against each

transformer

d. Capacitor banks 11 kV (GIS) breakers required for appropriate

Page 127: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

127

MVAR rating.

e. Required 11kV breakers for station transformers.

• All breakers essentially to have motorised earth

switch.

Note :

i. The existing 66 kV AIS substation sector-28 shall continue to

function till the commissioning of upgraded 220/66 kV GIS

substation.

ii. The existing 66 kV AIS substation shall be dismantled with only

after the commissioning of new 220/66 kV GIS substation.

iii. An authenticated list of inventory and materials require

reallocation after dismantlement would be provided by Smart

Grid team to the office of Chief Engineer/MM for further

allocation on approved augmentation and additional works at

various substations.

iv. All non- usable material will be got surveyed off from competent

authority and shall be returned to stores.

v. The Design wing would explore the possibility to utilize existing

25/31.5 MVA transformers, however if it is not feasible, the

transformers of 25/31.5 MVA rating which are required to be

provided/allocated on the proposed 66 KV new sub-stations

transformers proposed herein after for the approval.

The Sub-station is required to be commissioned by January

2018 and to be listed in the Works list of FY 2016-17.

3. Creation of associated 220 KV transmission lines as under :-

i. Creation of 220 KV D/C line on M/C towers from 400 KV S/stn

Kadarpur to proposed 220 KV Sub-Station DLF Q- Block,

Page 128: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

128

Gurgaon with HTLS conductor/underground cable having

capacity equivalent to twin Moose ACSR conductor i.e.

approximately 500 MVA (at 50 degree ambient temperature). {Tentative Length: 14.00 KM }

ii. Creation of 220 KV D/C line on M/C towers from 400 KV S/stn

Kadarpur to 220 KV Sub-Station Sec-52A, Gurgaon with HTLS

conductor having capacity equivalent to twin Moose ACSR

conductor i.e. approximately 500 MVA (at 50 degree ambient

temperature). { Tentative Length: 08.00 KM }

iii. Creation of 220 KV D/C line partially on M/C/D/C/Monopole

towers ( as per ROW & requirement) from existing 220 KV Sub-

Station Sector-52 A, Gurgaon to proposed 220 KV Sub-Station

Sector-28, Gurgaon with HTLS conductor having capacity

equivalent to twin Moose ACSR conductor i.e. approximately

500 MVA (at 50 degree ambient temperature). { Tentative Length: 5.00 KM }

iv. Creation of 220 KV D/C line on M/C towers from proposed 220

KV S/stn Sec-28 to proposed 220 KV Sub-Station DLF Q-

Block, Gurgaon with HTLS conductor/underground cable having

capacity equivalent to twin Moose ACSR conductor i.e.

approximately 500 MVA (at 50 degree ambient temperature).

{Tentative Length: 03.00 KM }

Note :

a. The Right of Way for creation of lines placed at Sr. No. i &

ii) & iii) above shall be facilitated partially by existing 220

KV D/C Sec -56 to Sector-52 line along with existing 66

KV D/C Sector-52 to Sector-28 line & partial up-gradation

of existing 220 KV Sec 72 –Sec 52 line on D/C towers to

Page 129: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

129

M/C towers respectively

b. The Right of Way for line placed at Sr. No-iv ) above shall

also be partially facilitated by existing 66 KV S/C Sector

28 to Q- Block line.

The Transmission line is required to be commissioned by

January 2018 and to be listed in the Works list of FY 2017-18.

5. Allocation of Four 220kV line bay at 400kV S/stn Kadarpur to

feed below mentioned transmission line mentioned at Sr. No 3 i

)& ii) above i.e.

i. Creation of 220 KV D/C line on M/C towers from 400 KV S/stn

Kadarpur to proposed 220 KV Sub-Station DLF Q- Block,

Gurgaon with HTLS conductor/underground cable having

capacity equivalent to twin Moose ACSR conductor i.e.

approximately 500 MVA (at 50 degree ambient temperature). { Tentative Length: 14.00 KM }

ii. Creation of 220 KV D/C line on M/C towers from 400 KV S/stn

Kadarpur to 220 KV Sub-Station Sec-52A, Gurgaon with HTLS

conductor having capacity equivalent to twin Moose ACSR

conductor i.e. approximately 500 MVA (at 50 degree ambient

temperature). { Tentative Length: 08.00 KM }

6. Allocation of two no. 220 KV Line bays at 220 KV Sub-Station

Sector -52 Gurgaon for line placed at Sr. No 3-ii) above after

facilitation of ROW by existing 220 KV D/C Sec-52 to Sec-56

line for line specified above at Sr. No -3 i) & ii) above.

7. Creation of two no 220 KV line bays at existing 220 KV Sub-

Station Sector-52 A, Gurgaon on back to back/Hybrid

arrangement basis for the proposed line placed at Sr. No -3-iii)

above.

Page 130: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

130

8. Creation of 66/11 kV (GIS) substation Sushant Lok, C- Block,

Gurgaon completely laced with Substation Automation System

fully compliant for unmanned remote operation from remote

SCADA station with the installed capacity of 3x25/31.5 MV A,

66/11 KV transformers along with two 250 KVA, 11/0.440

KVStation Transformers and Capacitor bank of appropriate

Voltage and rating.

The Sub-station to have following Scope of Works:

66kV side(GIS)

a) Three transformers bays for 3x25/31.5 MVA 66/11 kV

Transformer. Out of three one transformer spared transformer

from proposed 220 KV Sub-Station DLF Q-Block or Sec-28,

Gurgaon shall be used at this sub-station.

b) Six line bays(having compatible ampicity to 1200 sq mm,

aluminium XLPE 66 kV underground cable) + Scope for

extension of two line bays for future.

c) Bus Coupler bay

11 KV Side (GIS)

a) Two Incomers (GIS)breakers for each 25/31.5 MVA 66/11 kV

Transformer

b) One Bus Coupler(GIS) breaker against each transformer

c) Eight outgoing feeders (400 amp.) (GIS) breakers against each

transformer

d) Capacitor banks 11 kV(GIS) breakers required for appropriate

MVAR rating.

e) Required 11kV breakers for station transformers.

Page 131: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

131

• All breakers to have motorised earth switch

The Sub-station is required to be listed in the Works list of FY

2016-17.

9 Creation of 66/11 kV (GIS) substation Arjun Marg, Gurgaon

completely laced with Substation Automation System fully

compliant for unmanned remote operation from remote SCADA

station with the installed capacity of 3x25/31.5 MVA, 66/11 KV

transformers along with two 250 KVA, 11/0.440 KV Station

Transformers and Capacitor bank of appropriate Voltage and

rating.

The Sub-station to have following Scope of Works

66kV side(GIS)

a) Three transformers bays for 3x25/31.5 MVA 66/11 kV

Transformer. Out of three one transformer spared transformer

from proposed 220 KV Sub-Station DLF Q-Block or Sec-28,

Gurgaon shall be used at this sub-station.

b) Four line bays (having compatible ampicity to 1200 sq mm,

aluminium XLPE 66 kV underground cable)

c) Bus Coupler bay

d) Scope for extension of Two line bays in future.

11 kV Side (GIS)

a) Two Incomers (GIS)breakers for each

b) One Bus Coupler(GIS) breaker against each transformer

c) Eight outgoing feeders (400 amp.) (GIS) breakers against each

transformer

d) Capacitor banks 11 kV(GIS) breakers required for appropriate

Page 132: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

132

MVAR rating.

e) Required 11kV breakers for station transformers.

• All breakers to have motorised earth switch.

The Sub-station is required to be commissioned by October

2017 and to be listed in the Works list of FY 2016-17.

10 Creation of 66/11 kV (GIS) substation L- Block, Gurgaon

completely laced with Substation Automation System fully

compliant for unmanned remote operation from remote SCADA

station with the installed capacity of 3x25/31.5 MVA, 66/11 KV

transformers along with two 250 KVA, 11/0.440 KV Station

Transformers and Capacitor bank of appropriate Voltage and

rating.

The Sub-station to have following Scope of Works

66 kV Side (GIS)

a) Three transformers bays for 3x25/31.5 MVA 66/11 kV

Transformer. Out of three one transformer spared

transformer from proposed 220 KV Sub-Station DLF Q-Block

or Sec-28, Gurgaon shall be used at this sub-station.

b) Four line bays (having compatible ampicity to 1200 sq mm,

aluminium XLPE 66 kV underground cable).

c) Bus Coupler bay

d) Scope for extension of two line bays in future.

11 kV Side (GIS)

a) Two Incomers (GIS)breakers for each

b) One Bus Coupler(GIS) breaker against each transformer

c) Eight outgoing feeders (400 amp.) (GIS) breakers against each

Page 133: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

133

transformer

d) Capacitor banks 11 kV (GIS) breakers required for appropriate

MVAR rating.

e) Required 11kV breakers for station transformers.

• All breakers to have motorised earth switch

The Sub-station is required to be commissioned by October

2017 and to be listed in the Works list of FY 2016-17.

11 Creation of 66/11 kV (GIS) substation M.G Road, Gurgaon

completely laced with Substation Automation System fully

compliant for unmanned remote operation from remote SCADA

station with the installed capacity of 3x25/31.5 MVA, 66/11 KV

transformers along with two 250 KVA, 11/0.440 KV Station

Transformers and Capacitor bank of appropriate Voltage and

rating.

The Sub-station to have following Scope of Works

66kV side(GIS)

a) Three transformers bays for 3x25/31.5 MVA 66/11 kV

Transformer. Out of three one transformer spared transformer

from proposed 220 KV Sub-Station DLF Q-Block or Sec-28,

Gurgaon shall be used at this sub-station.

b) Four line bays (having compatible ampicity to 1200 sq mm,

aluminium XLPE 66 kV underground cable).

c) Bus Coupler bay

d) Scope for extension of two line bays in future.

11 kV Side (GIS)

a) Two Incomers (GIS)breakers for each 25/31.5 MVA 66/11 kV

Page 134: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

134

Transformer

b) One Bus Coupler(GIS) breaker against each transformer

c) Eight outgoing feeders (400 amp.) (GIS) breakers against each

transformer

d) Capacitor banks 11 kV (GIS) breakers required for appropriate

MVAR rating.

e) Required 11kV breakers for station transformers.

• All breakers to have motorised earth switch

The Sub-station is required to be commissioned by October

2017 and to be listed in the Works list of FY 2016-17.

12 Creation of 66/11 kV (GIS) substation Sushant Lok, A- Block,

Gurgaon completely laced with Substation Automation System

fully compliant for unmanned remote operation from remote

SCADA station with the installed capacity of 3x25/31.5 MVA,

66/11 KV transformers along with two 250 KVA, 11/0.440 KV

Station Transformers and Capacitor bank of appropriate

Voltage and rating.

The Sub-station to have following Scope of Works:

66kV side(GIS)

a) Three transformers bays for 3x25/31.5 MVA 66/11 kV

Transformer. Out of three one transformer spared transformer

from proposed 220 KV Sub-Station DLF Q-Block or Sec-28,

Gurgaon shall be used at this sub-station.

b) Six line bays(having compatible ampicity to 1200 sq mm,

aluminium XLPE 66 kV underground cable)

c) Bus Coupler bay

Page 135: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

135

11 KV Side (GIS)

a) Two Incomers (GIS)breakers for each 25/31.5 MVA 66/11 kV

Transformer

b) One Bus Coupler(GIS) breaker against each transformer

c) Eight outgoing feeders (400 amp.) (GIS) breakers against each

transformer

d) Capacitor banks 11 kV (GIS) breakers required for appropriate

MVAR rating.

e) Required 11kV breakers for station transformers.

• All breakers to have motorised earth switch

The Sub-station is required to be commissioned by October

2017 and to be listed in the Works list of FY 2016-17.

13 Creation of 66/11 kV (GIS) substation M.A Road, Gurgaon

completely laced with Substation Automation System fully

compliant for unmanned remote operation from remote SCADA

station with the installed capacity of 3x25/31.5 MVA, 66/11 KV

transformers along with two 250 KVA, 11/0.440 Station

Transformers and Capacitor bank of appropriate Voltage and

rating.

The Sub-station to have following Scope of Works

66kV side(GIS)

a) Three transformers bays for 3x25/31.5 MVA 66/11 kV

Transformer

b) Four line bays (having compatible ampicity to 1200 sq mm,

aluminium XLPE 66 kV underground cable).

Page 136: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

136

c) Bus Coupler bay

d) Scope for extension of two line bays in future.

11 KV Side (GIS)

a) Two Incomers (GIS)breakers for each 25/31.5 MVA 66/11 kV

Transformer

b) One Bus Coupler(GIS) breaker against each transformer

c) Eight outgoing feeders (400 amp.) (GIS) breakers against each

transformer

d) Capacitor banks 11 kV (GIS) breakers required for appropriate

MVAR rating.

e) Required 11kV breakers for station transformers.

• All breakers to have motorised earth switch

The Sub-station is required to be commissioned by October

2017 and to be listed in the Works list of FY 2016-17.

14 Creation of 66 KV D/C line on underground Aluminum cable of

size 1200 Sq.mm XLPE from proposed 220 KV Sub-station

Sector-28 to 66 KV Sub-station Sushant Lok C- Block,

Gurgaon. ( Tentative Length – 3.80 Km )

15 Creation of 66 KV D/C line on underground Aluminum cable of

size 1200 Sq.mm XLPE from proposed 66 KV Sub-station

Sushant Lok C- Block, Gurgaon to proposed 66 KV Sub-station

Sushant Lok A- Block, Gurgaon. ( Tentative Length – 2.30 Km )

16 Creation of 66 KV D/C line on underground Aluminum cable of

size 1200 Sq.mm XLPE from proposed 220 KV Sub-station

Sector-52 to 66 KV Sub-station Sushant Lok C- Block,

Gurgaon. ( Tentative Length – 2.70 Km )

Page 137: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

137

17 Creation of 66 KV D/C line on underground Aluminum cable of

size 1200 Sq.mm XLPE from proposed 220KV Sub-station

sector 28 to proposed 66 KV Sub-station Arjun Marg, Gurgaon

(Tentative Length – 1.60 Km).

18 Creation of 66 KV D/C line on underground Aluminum cable of

size 1200 Sq.mm XLPE from proposed 66KV Sub-station Arjun

Marg to proposed 66 KV Sub-station MG Road, Gurgaon (

Tentative Length –5.10 Km ).

19 Creation of 66 KV D/C line on underground Aluminum cable of

size 1200 Sq.mm XLPE from proposed 220 KV Sub-station

DLF Q Block to proposed 66 KV Sub-station M.G Road,

Gurgaon. ( Tentative Length – 0.71 Km )

20 Creation of 66 KV D/C line on underground Aluminum cable of

size 1200 Sq.mm XLPE from proposed 220 KV Sub-station

DLF Q-Block to proposed 66 KV Sub-station L Block Gurgaon.

( Tentative Length – 3.0 Km )

21 Creation of 66 KV D/C line on underground Aluminum cable of

size 1200 Sq.mm XLPE from Proposed 66 KV Sub-station

S.Lok A-Block, Gurgaon to proposed 66 KV Sub-station L-

Block, Gurgaon. ( Tentative Length – 2.1 Km )

22 Creation of 66 KV D/C line on underground Aluminum cable of

size 1200 Sq.mm XLPE from proposed 66 KV Sub-station

Sector 44 to proposed 66 KV Sub-station S.Lok A-Block

Gurgaon. ( Tentative Length – 2.5

Km )

23 Creation of two no. 66 KV line bays at 66 KV Sub-station

Sector-44 to feed the line placed at Sr. No-22 above i.e.

Page 138: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

138

Creation of 66 KV D/C line on underground Aluminum cable of

size 1200 Sq.mm XLPE from proposed 66 KV Sub-station

Sector 44 to proposed 66 KV Sub-station S.Lok A-Block

Gurgaon. ( Tentative Length – 2.5

Km )

24 Creation of 66 KV D/C line on underground Aluminum cable of

size 1200 Sq.mm XLPE from proposed 220 KV Sub-station

DLF Q Block to proposed 66 KV Sub-station MA Road

Gurgaon. ( Tentative Length – 4.5

Km )

25 Creation of 66 KV D/C line on underground Aluminum cable of

size 1200 Sq.mm XLPE from 220 KV Sub-station Sector 20 to

proposed 66 KV Sub-station MA Road Gurgaon ( Tentative

Length – 4.20 Km )

26 Creation of two no of 66kV GIS bays at 220kV S/stn GIS sector

20 to feed the connectivity mentioned at Sr. No 25 above.

27 Allocation of 66 KV line bays of 66 KV D/C Sector-52 to Sector-

28 line after dismantlement of same as per Sr. No -3 above to

feed 66kV D/C line through U/G underground Aluminum cable

of size 1200 Sq.mm XLPE mentioned at Sr. No. 16 above.

28 Replacement of existing11kV AIS VCBs with 11kV GIS Panels

for compatibility in relation to remote SCADA operations each at

66kV S/stn sector 43 and 66kV S/stn DLF Phase V Gurgaon.

29. All the works mentioned above are to be included in the works

list of HVPNL in FY 2016-17 and require approval of HERC.

Page 139: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

139

10 COST ESTIMATES & BENEFITS Estimated cost of implementation of features of Smart Grid project is Rs.

1337 crores including transmission system for Phase 1. Cost of SCADA

implementation has been taken as one time cost and includes fixed cost for

setup of control room and other system applications. The total cost of

implementation of distribution network including features of Smart Grid is

Rs. 671 crores approximately. Detail is given below:

10.1 Estimated Cost of Project (Phase I)

Sr.No.

Description/ Major head of

items Unit Quantity

Unit Rate

Total Supply Cost

Total Supply Cost +15%

Erection Total (In Lacs)

In Lacs

DISTRIBUTION DHBVN

1 HT Cables (Various Sizes) KM 281.42 4642.12 5338.45 232.11 5570.55

2 LT UG Line (Various sizes) KM 1923.07 5433.16 6248.14 271.69 6519.83

3 LT Feeder Pillar No.s 7451 11485.49 13208.31 229.70 13438.02

4

RMU(Ring Main Units)

with FRTU & FPI

No.s 563 3753.98 4317.08 750.07 4392.16

5 Distribution

T/F(11KV/.433KV)

No.s 240 2162.13 2486.44 43.24 2529.69

6 Optical Fiber

and PLB-HDPE Pipe

KM 259 280.477 322.54 14.02 336.57

7 Street Light No.s 11000 4395.35

8 Civil work for foundation of DT/RMU/FP

No.s 8394 1189.96 1189.96

Page 140: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

140

etc

9

Civil work for underground

laying of cable/optical

fiber

Mtr. 1043000 3563.50 3563.50

10 Fencing R/ Mtr 9711 322.79 371.21 32.27 403.49

11 RCC slabs and route markers No.s 905430 1883.00 2165.45 37.66 2203.11

12 PSS No.s 15 409.98 471.47 8.19 479.67

13 Cost of other

minor items/works

L/S 991.14 1139.81 128.1 1267.91

14 5 years O & M 4152.73

Sub-Total 50442.32

SCADA & OMS/ADMS

1

SCADA & OMS along

with civil work required for the

project

lot 1

10055

AMI(including DTMU’s)

1 Field

Equipment for AMI & PLM

lot 1

3409

2 IT System and Integration for AMI & PLM

lot 1

672

3 Field

equipment for PQM & DTMU

lot 1 756

4 Consumer

Education and Awareness

lot 1 10

10

Sub-Total 4847

Total DHBVN -A 65344.32

Page 141: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

141

TRANSMISSION-HVPN

1 Substations & Lines 70182

TOTAL (HVPN) - B 70182

Total Consultancies Charges – C (2% of (A+B)) 2710.52

GRAND TOTAL (A+B+C) 138236.8

10.2 BENEFITS Smart Grid project is being done as an initiative to embed new technologies

in distribution system in small scale and successful implementation would

draw the way forward for large scale implementation. Therefore for such a

project finding economic viability and feasibility would be prejudice as

qualitative benefits are of paramount importance. Large scale

implementation in future may only prove economies of operation. The main

benefits of the project are as under :

• 24x7 power supply to all consumers.

• Make Gurgaon Diesel Generator Free.

• Reduce AT&C Losses.

• Improve reliability of power by reduction of outage rate and duration.

• Ensure quality power supply by reduction of harmonics

10.3 COST BENFIT ANALYSIS

10.3.1 Benefit of Implementation of AMI Gurgaon is expected to achieve following benefit as the outcome of

distribution strengthening and smart grid.

10.3.1.1 Reduction of AT&C losses

• AT&C losses of DLF City is around 11.91 %

• Total Energy input to DLF City is 742 MU in year 2014-15 time

duration.

Page 142: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

142

• Total billed energy is 681 MU in year 2014-15 time duration billing

efficiency (91.76%).

• After smart grid intervention billing efficiency expected to increase up

to 95% and total billed energy will be 705 MU

• Additional energy billed is 24 MU.

• Revenue saving out of above saving of 24 MU shall be Rs 14.784 Cr.

when the average sale of energy is Rs. 6.16 /unit (ROR on

Assessment and Unit Billed)

10.3.1.2 Reduction in average cost of billing

At present Average cost of billing is Rs. 300/per year/consumer by aiming

70% reduction in the billing cost, cost of billing shall be reduced by Rs. 210/

per year/per consumer hence total saving for 29145 Nos. of consumers

(considering growth of 8 %) is Rs. 0.61 Cr.

10.3.2 Peak Load Management Reduction in peak demand

• The peak demand is 250 MVA. Power factor is 0.9. Average Peak

load time is one hour per day on average basis.

• During the peak time consumption is 225,000 Units.

• Reducing the peak demand to 225 MVA, the peak consumption will

reduced to 202,500 Units, saving 22,500 U

• For 22,500 Units, differential UI charges for peak and non-peak is Rs.

5 / unit hence saving in revenue by shifting peak demand is Rs. 4.10

Cr (365 days for one hour).

Benefit from Peak Load Management would require regulatory

provisions such as Time of Day (TOD) tariff.

10.3.3 Outage Management System Reduction in outages:

Page 143: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

143

Above mentioned OMS/SCADA scheme shall be installed in 11kV/33kV

network of Gurgaon. It is estimated that present tripping rate of approx.

1205 tripping per year may be reduced to Nil tripping per year. Table below

shows the benefits due to reduction in lines trippings after implementation

of OMS.

Table : End scenario of line tripping after OMS

Description Present

status

After Smart Grid

and System

strengthening

Total no of line Outages in the year for 88

Nos. of feeders 1205 0

Average time taken for restoration (Hrs) 2.4 0

Average cost of restoration per outage (Rs

lac) 0.1

Total Cost of restoration (Crore) 1.205 0

Benefits due to reduction in restoration

cost (Rs. Cr) 1.205

Average Energy Loss per outage (MU)

(2000 unit/hr) 0.0048 0

Total energy loss ( MU) 5.784 0

Increase in Energy Sales (MU) - 5.784

Benefits due to Higher energy sales

assuming profit of Rs. 1.74 per unit (Rs.Cr) - 1.006

Benefits by reducing number of outages and outage durations would be

following:

Page 144: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

144

• With the proposed reduction in line outages from 1205 to Nil, the total

saving in restoration cost would be Rs.1.205 Cr/year

• Due to higher energy sales because of reduced failures/ increase

availability, the increase in gross profit for the utility would be Rs.

1.006 Cr/ year

DTMUs

For monitoring oil level, temperature & loading of distribution transformers,

monitoring units shall be installed which shall be helpful in reducing number

of outages, outage duration & restoration time. Also system strengthening

shall also reduce overloading and thus failure of equipment, reducing

outage time. By increasing reliability and reducing outage of DTs, there will

be reduction in No. of transformers under repair also, which will increase

the availability of transformer in store as well. Presently, failure rate of

transformers is at 18.61%, which means 86 distribution transformers have

failed against total strength of 462 nos. in FY 2014-15. By virtue of

transformer monitoring units this failure rate may be brought to 1% level.

Table below depicts benefits after reduction of distribution transformer

failures due to OMS implementation.

Table : End scenario of DT Failures after OMS

Description Before System

Strengthening

After OMS

Implementation

Total No. of DTs 462 462

Percentage of DT failure(2014-15) 18.61% 1%

Approx. no. of failures per year 86 5

Total time taken for restoration per 24 8

Page 145: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

145

outage( Hr)

Average cost of restoration per outage

(Rs. In Lac) 0.516 0.516

Cost of Restoration (Rs. Lac) 44.376 2.58

Benefit due to reduction in restoration

cost (Rs. Cr) 0.42

Average Energy loss per outage (MU)

(100unit/hr) 0.0024 0.0008

Total energy loss(MU) 0.2064 0.004

Increase in Energy sales (MU) 0.202

Benefits due to higher energy sales

assuming profit of Rs 1.74 per unit

(Rs. Cr) 0.035

Benefits by reduction in number of outages & outage time of distribution

transformers shall be as under:

• With the proposed reduction in DT outages the total saving in

restoration cost would be Rs. 0.42 cr /year

• Higher energy sold through the reduced failures/ increase availability

the increase in gross profit for the utility would be Rs 0.035 Cr/ year.

Thus the total benefit to the utility due to outage management system

(benefits from improved scenarios of line trippings & DT failures) would be

Rs.2.666 Cr per Year. Outage Management System benefits can be

achieved subject to deployment of mobile and well equipped maintenance

crew. Also by increasing reliability in supply, a lot of value comes to society

by means of uninterrupted facilities in public services & social causes

whose cost cannot be written in black & white.

Page 146: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

146

10.4 Summary of Benefits Expected benefits from above mentioned smart grid initiatives are

summarized in table below:

S.No. Initiative Benefits (in Rs.

Cr. Per year)

1 Advanced Metering Infrastructure (AMI) 15.4

2 Peak Load Management(PLM) 4.1

3 Outage Management System(OMS) 2.6

Total 22.1

Page 147: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

147

11 FINANCING STRATEGY Plan for development of Smart Grid leading to Smart City Gurgaon involves

Strengthening / modernization of Power Transmission & Distribution

infrastructure to enable 24x7 Power supply as well as making the city DG

sets free. Total estimated cost of above schemes is Rs. 1382 crores and it

is to be implemented progressively by 2017. Broad breakup of cost

estimate is as under:

1. Transmission Rs. 702 crores ·

2. Distribution Rs. 653 crores

3. Project Management & Consultancies Rs. 27 crores

Funding Mechanism

For funding of the Distribution & Smart Grid, the year wise funding

requirement of DHBVN and HVPN is as shown in Table below:

Year DHBVN

Investment (Rs.

Crore)

HVPNL

Investment (Rs.

Crore)

Total

1st 200 Year 214 414

2nd 466 Year 502 968

Total 666 716 1382

As far as arrangement of funds is concerned, 25% of the project cost

would be arranged by way of equity / grant from the MoP (GoI). 75 %

Page 148: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

148

of Project cost would be arranged as loan from financial institutions.

Following shall be the modes of arrangement of funds:

Arrangement of Funds

1st 2 Year (2016-17)

nd Total (in crores)

Year (2017-18)

Grant from MoP (GoI)

103.65 241.85 345.5

Loan from PFC 310.95 725.55 1036.5 TOTAL 414.6 967.4 1382

Page 149: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

149

12 STRATEGY FOR IMPLEMENTATION

Considering the prevailing power supply scenario in DLF City Sub Division

in Gurgaon, it is proposed that Smart Grid technologies may be

implemented for garnering benefits not only from financial gains but also for

better consumer relationship, their engagement in energy management

process, green energy benefits and operational excellence through

increased efficiency, better visualization for fast decision making, optimized

work flow, reduced operational cost etc. The Work will be awarded on

“Concept to Commissioning” basis on per unit rate of each activity.

Following activities are supposed to be part of project which would take

about 24 months in implementing the project:

Formation of a specialized key team for execution of project.

Creation of office infrastructure.

Deciding a Special committee with financial powers for the smart city

project only.

Explore who are the other power utilities in India or Abroad who have

the expertise for making the distribution system underground and who

can advise us during initial stages of planning, tendering, evaluation

and award of contracts and then during the execution.

Load requirement and load growth projection upto 2031

Engagement of Consultant/Advisor.

Preparation of brief note for getting all the necessary administrative

approvals including the expenditure require to make to complete the

project and the possible means to fund the project of the estimated in

the shape of equity / grant by the government.

Field Survey.

Page 150: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

150

Planning.

Design.

Preparation of detailed BOQ to execute the project.

Preparation of detailed project report (DPR).

Finalization of unit rates for floating of NIT.

Finalization of technical specification of all the items required for

completion of project.

Floating of NIT.

Tendering/Evaluation.

Work award/allotment. The Work will be awarded on “Concept to

Commissioning” basis on per unit rate of each activity

Execution

Periodical review of Project

After award, it is proposed to complete Smart Grid implementation in 18

months. For implementation of proposed initiatives following steps need

to be taken-

• Timely implementation of the RAPDRP / other schemes already in

progress.

• Development of Smart Grid with all the proposed attributes.

• Establishment of Control Centre for smart grid application integrated

with other IT system.

• Regulatory and policy advocacy for time of use tariff, demand side

management, as part of smart grid development.

• Support/ coordination of district administration as well as other

departments like HUDA, MCG, DMRC, IGL, BSNL, NHAI and Forest

etc. for resolving the ROW issues and for proving the land required in

execution of project.

Page 151: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

151

13 RECOVERY THROUGH RELIABILITY SURCHARGE

Reliability Surcharge

Considering that this scheme will improve reliability through 24x7 power

supply as well as making Gurgaon city DG sets free, it is proposed that a

reliability charge may be levied in the tariff for all the categories of

consumers. The reliability charge would be used to service debt, O&M and

provide return on equity for the investment. Proposed reliability charge will

be uniformly levied @ Rs. 0.50 on domestic category consumers including

Bulk Supply Domestic and @ Rs. 0.60 per unit of consumption on all other

categories of consumers. However, the expected return against levy of this

reliability surcharge has been estimated @ Rs. 0.55 on all categories, as

the consumption of domestic category including Bulk Supply Domestic

consumers and other categories consumers are equal in DLF Sub-Division.

The estimated calculationis placed at Annexure – B.

The net benefits in the year 2018 after levying of Reliability Charge would

thus be:

S.No. Initiative Benefits

(in Rs. Cr)

1 Advanced Metering Infrastructure (AMI) 15.4

2 Peak Load Management(PLM) 4.1

3 Outage Management System(OMS) 2.6

4 Levy of Reliability Charge 60

Total 82.1

Page 152: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

152

The net benefits which will accrue during the year 2031 have been

assessed at 2031:

Sr. no.

Initiative Benefits (in Rs. Cr. Per year)

1 Advanced Metering Infrastructure (AMI) 49.14

2 Peak Load Management(PLM) 13.08

3 Outage Management System (OMS) 8.30

4 Recovery by levying Reliability Charge 184

Total 254.52

Page 153: DHBVN · Minister of State (Independent Charge) for Power, Coal and New & Renewable Energy co-chaired a meeting with the Hon’ble Chief Minister Haryana at the headquarters of Power

153

14 CONCLUSION In the times to come, everything and every action of us have to be

consumers’ oriented and driven by their expectations and aspirations.

Electricity being the most sought after commodity and having become part

of our lives, it puts a lot of pressure on the electricity transmission and

distribution companies to plan the up-gradation and augmentation of the

existing system. Also, we need to think out of box to find solutions to the

electricity problems and to design the network architecture in a manner that

consumers not only get adequate voltage but also an uninterrupted supply.

Apart from the usual problems which the consumers face, another problem

which the consumers and utility people are facing together is the

congestion and problems of right-of-ways. Smart Grid is the solution to all

these problems. Choosing Gurgaon for developing Smart Grid is the most

appropriate approach which would not only prove to be a role model for

others to follow but also will prove to be preferred destination for

international companies and the people from all across the country.

We hope we shall be able to plan better, execute better and in conformity

with the latest in standards internationally taking in to consideration the

latest in technology available as on date.