DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

download DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

of 43

Transcript of DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    1/43

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    2/43

    Document released for public co

    July 2002

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    3/43

    RAFT

    This page is intentionally left blank

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    4/43

    Western Australia is experiencing water restrictions due to current dro

    the critically low levels of surface water storage. It is recognised that in

    many householders like to conserve water by reusing their greywa

    these guidelines are to assist in the promotion of acceptable greywand promote conservation of our quality ground and surface water s

    The guidelines were prepared by the Department of Health in consu

    Corporation and Department of Environment, Water and Catchment

    The DRAFT guidelines are being released for a two-month public c

    1 September 2002. At the end of the comment period it will be rev

    submissions received.

    Written comments on these draft guidelines may be sent to either:

    Draft Greywater Reuse Guidelines Comments

    Environmental Health Branch

    Department of Health

    PO Box 8172Perth Business Centre WA 6849

    or

    Fax: (08) 9388 4910

    or

    Email: [email protected]

    Further copies of the draft guidelines are available on the Departme

    at http://www health wa gov au

    FOREWORD

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    5/43RAFT

    TABLE OF CONTENTS

    1. INTRODUCTION

    1.1 CHARACTERISTICS OF HOUSEHOLD GREYWATER

    1.2 HOUSEHOLD WATER USAGE VOLUMES

    1.3 COMPOSITION OF HOUSEHOLD GREYWATER

    2. HEALTH AND SAFETY REQUIREMENTS

    3. ENVIRONMENTAL IMPACT CONSIDERATIONS

    4. DESIGN AND PERFORMANCE REQUIREMENTS

    5. GREYWATER SYSTEM OPTIONS

    5.1 MANUAL BUCKETING OF GREYWATER

    5.2 PRIMARY TREATMENT SYSTEMS

    5.3 SECONDARY TREATMENT SYSTEMS

    5.4 OTHER TREATMENT SYSTEMS

    6. GREYWATER IRRIGATION OPTIONS

    7. DESIGNING A GREYWATER SYSTEM

    7.1 GENERAL

    7.2 CALCULATING GREYWATER QUANTITIES

    7.2.1 For Sizing Greywater Tanks7.2.2 For Sizing Irrigation Areas

    7.3 GREYWATER IRRIGATION SYSTEM SIZING

    7.3.1 Sub Soil Trench Irrigation Systems

    7.3.2 Drip or Spray Irrigation Area Sizing

    7.4 SITING A GREYWATER IRRIGATION SYSTEM

    7.5 MATERIALS

    8. SYSTEM MAINTENANCE9. PROCEDURE FOR OBTAINING A PERMIT TO INSTALL A GREYWAT

    9.1 APPLICATION

    9.2 INSTALLING A SYSTEM

    9.3 GREYWATER SYSTEMS APPROVED FOR USE

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    6/43

    Greywater is the wastewater generated in the bathroom, kitchen and

    is therefore the components of domestic wastewater, which have no

    toilet.

    The opportunity exists for greywater to be reused to irrigate gardens

    demand on quality ground and surface water supplies. Considering

    in many parts of Western Australia and the sometimes limited supply

    is important that water is used efficiently and conserved whereve

    greywater is therefore supported and encouraged by Government to

    However, this has to be accomplished without compromising comm

    unacceptable environmental impact, or downgrading the amenity of

    Greywater must be reused in a beneficial manner for landscapi

    rootzone) rather than simply disposal at a depth, which would not b

    Greywater can contain pathogenic microorganisms including bacter

    and parasites in concentrations high enough to present a health risk

    caution must be exercised with greywater reuse. This can be achi

    unnecessary human contact with greywater, or by treating the gredestroy the microorganisms.

    Greywater also contains oils, fats, detergents, soaps, nutrients, salts

    food and lint, which can impact on operational performance and

    irrigation system. If these contaminants arent managed correctly th

    structure, clog groundwater flow paths or even cause non wettin

    garden soils.

    A clear understanding of the potential health risks, operatio

    environmental impacts that can be caused by improperly designed

    and land application systems, is necessary to ensure only suitably

    treatment and land application systems are permitted There will

    1. INTRODUCTION

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    7/43RAFT

    q setting minimum standards for design, installation and the pro

    approval for greywater reuse system installations;

    q safeguarding the community from possible disease transmission a

    greywater reuse; and

    q ensuring that greywater installations do not harm the environmen

    are appropriately sited and maintained to a satisfactory standard

    This document considers reuse of greywater in residential premis

    principles may be applied and utilised for other types of devel

    greywater.

    1.1 Characteristics of Household GreywaterThe characteristics of greywater produced by a household will va

    number of occupants, the age distribution, lifestyle, health statu

    patterns.

    There are essentially three different greywater streams, they are:

    q Bathroom greywater (bath, basin, and shower) contributes ab

    greywater volume. Bathroom greywater can be contaminate

    shampoos, hair dyes, toothpaste, lint, body fats, oils and clean

    has some faecal contamination (and the associated bacteria

    body washing.

    q Laundry greywater contributes about 34% of the total Wastewater from the laundry varies in quality from wash wa

    second rinse water. Laundry greywater can have faecal con

    associated bacteria and viruses, lint, oils, greases, chemicals,

    other compounds.

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    8/43

    1.2 Household Water Usage VolumesThe average house (based on 3.3 persons per house) uses 337 kiloli

    or approximately 1000 litres each day. This amount will vary accord

    practises of the household and the various percentages are shown i

    Figure 1.2: Household Water Usage Source: Wate

    1.3 Composition of Household GreywaterTable 1.3(a) documents the microbiological quality (ie the numb

    coliforms) of greywater from various sources in a residential dwelling

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    9/43RAFT

    Table 1.3(a): Faecal Coliform Numbers in Greywater prior to storage

    The chemical and physical quality of greywater compared with raw

    Table 1.3 (b). The high variability of the greywater quality is due to fa

    of water, water use efficiencies of appliances and fixtures, individual h

    (soaps, shampoos, detergents) and other site specific characteristics

    Table 1.3(b): Typical Composition of Greywater compared with Raw Se

    SOURCE

    FAECAL COLIFORMS(cfu)/100ML

    Rose et. al.

    (1991)

    Calif. DHS

    (1990)

    Brandes

    (1978)

    Bathing/Shower

    Laundry Wash

    Water

    Laundry Rinse

    Water

    Kitchen

    CombinedGreywater

    6 x 103 cfu

    126 cfu

    25 cfu

    6 to 80 cfuA

    1.5 x 103 cfuB

    1.8 x 105 to 8 x

    106 cfu

    4 x 105 MPN

    2 x 103-107

    MPN

    < 10 to 2 x 10

    200

    115

    100

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    10/43

    The health of a household is usually reflected in the wastewater pr

    household enjoying good health will still excrete pathogenic micro-or

    normal part of the gut. All forms of greywater are capable of transmi

    Pathogens from greywater may spread by direct contact (i.e, toinhaling infectious water droplets) or indirectly by consumption of c

    water.

    To minimise the risk to public health and prevent a nuisance from

    following requirements apply:

    2.1 Greywater systems (this does not include bucketing) must dbelow the ground surface unless treated and disinfected to an

    (see Section 6, Table 6.1).

    2.2 The system must be designed and operated to exclude human

    with the greywater except as required to maintain the system.

    2.3 No cross connection with the potable water supply is allowed.

    2.4 Greywater must not be allowed to enter any stormwater draina

    2.5 Greywater shall not be used in a manner that will result in

    vegetables or other edible plants. It may be used to irrigate fr

    fruit does not make contact with the greywater.

    2.6 No opportunity for mosquito breeding is to exist in any part of

    i.e. in conveyance, treatment, storage, soil application.

    2.7 If irrigated via sub-strata drippers or above ground sprays each

    have signage effectively cautioning those entering the area tha

    2. HEALTH AND SAFETY REQUIRE

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    11/43RAFT

    Domestic reuse of greywater will help the environment by reducing

    quality bore and scheme waters. However, greywater reuse is only

    we need to adopt to protect our water resources. To conserve groun

    resources, even before considering greywater reuse, it is essential thais practiced. Greywater generation should be minimised for three imq to conserve drinking water as a precious natural resource;q to ensure that greywater does not overload the installed greyw

    system; andq to minimise land requirements for a greywater reuse system.

    Various water saving devices can be used to conserve water, inclu

    cisterns and reduced flow shower heads, dishwashers and washing m

    also be conserved using a range of practices such as shorter shower

    when cleaning teeth, ensuring that taps do not continuously drip, an

    and clothes washers only when the load is full. As 47% of househo

    garden watering, a water wise garden can greatly reduce wate

    information on ways to save water in the home contact the Water Co

    The Government has committed significant funds to provide infilunsewered urban areas in Western Australia. This occurred for a

    including environmental concerns about nutrient impacts from se

    would therefore be irresponsible to divert greywater from the sewe

    locations where phosphates from greywater could negatively

    environmentally sensitive water bodies without suitable protecti

    implemented.

    To minimise negative impacts on the environment from greywater

    requirements apply:

    3.1 Greywater must be contained within the confines of the pre

    generated and not be permitted to runoff onto neighbouring pr

    3. ENVIRON MENTAL IMPACT CONSID

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    12/43

    3.4 Washing powders that contain sodium salts as bulking age

    sparingly. High levels of sodium can produce saline greywater.

    soil structure, reducing the air space, giving it a greasy textur

    capability. Products which use potassium salts or liquid con

    used as they produce better quality, less saline greywater.

    3.5 Detergents and powder cleansers contain boron and should bboron can be toxic to plants in high concentrations and can also

    The USA Environmental Protection Agency (1992) recomm

    concentration of boron be 0.75g/L for long term use on sensitiv

    3.6 Try to avoid the use of:q bleaches or softenersq detergents that advertise whitening, softening and enzymq detergents with ingredients which include: boron, bora

    sodium perborate and sodium trypochlorite (salts), acids

    3.7 The following materials should not enter a greywater systemq Paints, automotive oils and greases etcq Any matter designated as trade waste or industrial liquid

    3.8 In sandy soils where the phosphorous retention index (PRI) of the greywater systems should be installed more than 100 m

    wetland, streamflow (including stormwater drains) or ot

    ecosystems. Information about local water features can

    Department of Environment, Water and Catchment Protection

    3.9 System flow rates on coarse sandy soil/gravel should be carefu

    greywater leaching into groundwater or surface water bodies.

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    13/43RAFT

    All greywater systems are an Apparatus for the Treatment of Sewag

    section 3 of the Health Act 1911, and as such their design, manufa

    be approved by the Executive Director, Public Health.

    A greywater reuse system is to be designed, constructed, operated

    accordance with the following:

    4.l All primary greywater reuse systems are to incorporate bel

    methods. Secondary treated greywater if disinfected can be

    ground surface (see Table 6.1).

    4.2 All primary treatment greywater systems must incorporate a sremove fats, greases and solids.

    Greywater systems that treat all greywater streams (ie kitc

    laundry) must have a sedimentation tank that has a minimum

    Greywater systems that treat bathroom and/or laundry grey

    designed to provide at least 24 hour combined retention fgreywater (ie: double the daily flow), with 40 litres/person/yea

    for scum and sludge accumulation.

    4.3 Variations to the above design requirements will be consi

    systems proposed by manufacturers. These systems will requir

    effective long term operation of the system can be expected

    nature of the system, demonstration of this may require the sysa performance trial.

    4.4 Manufacturers of mechanical greywater reuse systems

    demonstrate to the satisfaction of the Department of Health tha

    operated effectively in the long term without blockages betw

    4. DESIGN AND PERFORMANCE REQU

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    14/43

    4.7 The design of all sewer diversion or overflow devices must be ap

    Corporation and all devices must be designed and installed in

    the flow of greywater to the irrigation system to cease when

    commences.

    4.8 Greywater connections must be designed and installed to preve

    entering the property. All plumbing works must be carried out b

    in accordance with the Metropolitan Water Supply Sewerage a

    1981.

    4.9 All treatment tanks and pump pits must comply with the st

    requirements of AS 1546.1 Onsite Domestic Wastewater

    Tanks.

    4.10 Systems incorporating a irrigation pump must have a minimuof 250L if they are fitted with an overflow to sewer, or 250L plus

    unsewered properties.

    4.11 Systems incorporating a irrigation pump must be fitted with

    warning device, to warn of pump failure or system blockage.

    overflow to sewer this should trigger prior to overflow to sewe

    systems without sewer overflow at the 250L level.

    4.12 A person with suitable qualifications and experience must d

    pressurised trench irrigation systems. The system must have m

    than 40mm in diameter and laterals of not less than 25mm in d

    than 3mm diameter holes spaced to give uniform distribution.

    4.13 Systems must have sufficient irrigation area to ensure long termsoil types and likely greywater volumes into consideration.

    4.14 Systems must be designed to avoid above ground pooling o

    application to the soil.

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    15/43RAFT

    4.18 Greywater must undergo treatment to remove material that ma

    pipes and drippers, clog soil or place too many pollutant loads

    4.19 Storage other than that required for treatment is to be avoided

    4.20 Reuse of greywater via sub-strata and sub-surface micro-drip ir

    with the requirements of the Department of Health, Western Au

    of Practice for the Design, Manufacture, Installation and O

    Treatment Units (ATUs) Serving Single Dwellings Drippe

    Criteria.

    4.21 Systems that physically capture/filter out solids from specific gre

    to irrigation and require ongoing owner input to clean out filt

    permitted in sewered areas when their design incorporates:

    overflow which occurs when the filter becomes clogged, pumdiversion device is installed prior to the system. Such systems

    unsewered locations unless they are fitted with an overflow or p

    an onsite wastewater system designed to receive all wastewate

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    16/43

    Greywater reuse methods can range from low cost methods such as t

    of greywater from the laundry trough or bathtubs, to primary trea

    coarsely screen oils, greases and solids from the greywater before

    trench systems, to more expensive secondary treatment systems th

    the greywater to a high standard before irrigating it via microdrip or

    choice of system will be dependant on a number of factors inclu

    system is being installed or a disused wastewater system is being co

    property has been connected to sewer.

    Options for reusing greywater are listed below.

    5.1 Manual bucketing of greywaterIn its simplest form, manually irrigating (eg. bucketing laundry waste

    soils is acceptable provided that relevant health and safety condition

    These are detailed in Appendix 1.

    5.2 Primary Treatment SystemsPrimary treatment methods use a sedimentation tank to coarsely sc

    and solids prior to irrigation via sub-soil trench irrigation systems

    receive the primary treated greywater. These systems are likely to be

    economically attractive for greywater reuse because they req

    maintenance and generally do not rely heavily on electricity or chem

    basic requirements and examples of these systems are given in App

    5.3 Secondary Treatment SystemsSecondary treatment systems further treat the greywater to reoils/greases and solids than in primary treatment. This allows second

    to be irrigated via micro-drip or surface irrigation methods (where dis

    pipes becoming quickly clogged. These systems are generally more e

    initial establishment costs associated with the further treatment ne

    5. GREYWATER SYSTEM OPTIO

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    17/43RAFT

    For examples of other systems see the Model Guidelines for Domes

    for Australia by the Urban Water Research Association of Australia R

    1996.

    Before the use or sale of greywater systems can be permitted in We

    must have the approval of the Executive Director, Public Health. Be

    granted the Executive Director, Public Health will need to be sati

    system and its design are acceptable.

    Proponents, designers and inventors of greywater systems are encou

    make application for approval, but such approval will require that th

    systems be demonstrated. This may necessitate a performance tria

    expense. Likewise, permission to trial systems will require that pr

    Executive Director, Public Health that the basic design concept appe

    Please contact the Wastewater Management Section of Departmen

    Australia for further information about approvals for trialing and syst

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    18/43

    The appropriate greywater irrigation method is dependent on the tre

    Table 6.1: Greywater Irrigation Options according to Treatment

    All disposal methods must be constructed in accordance with the

    Health (Treatment of Sewage and Disposal of Effluent and Liquid Was

    and/or the AS 1547:2000 Onsite Domestic Wastewater Managem

    Irrigation of greywater below ground means water is not wasted throevaporation and run off and it reduces the scope for human contact

    to public health.

    In sandy soils, soil conditioners should be added to improve the so

    hold the greywater close to the root zone.

    Plants that are deep rooted should be selected, as some shallow rootable to reach enough water to sustain growth. Please contact your lo

    advice.

    There are essentially 5 methods of greywater irrigation. These are:

    6. GREYWATER IRRIGATION OPT

    Treatment Greywater Reus

    Untreated greywater

    Primary treated greywater

    (ie through a sedimentation tank)

    Secondary treated to a 20 mg/L BOD5,

    30 mg/L SS and possible disinfection to

    achieve 10 cfu thermotolerantcoliforms/100mL

    Bucke

    Below ground tre

    Micro drip and s

    Below ground tre

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    19/43RAFT

    4. Surface Spray Irrigation means the greywater is applied to the

    above ground level. This is only permitted where greywater has

    disinfected in accordance with table 6.1 prior to irrigation.

    5. Manual Surface Irrigation The only permitted method for this is v

    as detailed in Appendix 1.

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    20/43

    7.1 GeneralTo design a greywater system, use of these guidelines is recom

    appropriate for persons contemplating a greywater reuse system to

    system designer or other suitably qualified person to consider the op

    Greywater systems will not be permitted where Local Governm

    installation of a system is not in accordance with these Guidelines a

    q Insufficient property area is available;

    q Inappropriate soil conditions exist;

    q The system design is not one approved by the Executive Directo

    section 9.3); or

    q The property is in an environmentally sensitive area (see section

    To design a greywater system an estimation of greywater generation

    site then needs to be evaluated for the land irrigation system.

    7.2 Calculating Greywater QuantitiesTo estimate the quantity of greywater generated in a household follow

    First calculate the number of occupants of a home as follows

    2 persons for first bedroom

    1 person per additional bedroom

    Next calculate each persons daily greywater flow allocation as 112 l

    7. DESIGNING A GREYWATER SY

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    21/43RAFT

    7.2.1 For Sizing Greywater TanksGreywater systems that treat all greywater streams (ie kitchen, bat

    must have a sedimentation tank that has a minimum volume of 182

    Greywater systems that only treat bathroom and/or laundry greywate

    to provide at least 24 hour combined retention for the daily flow of g

    the daily flow), with 40 litres/person/year of capacity allowed foaccumulation.

    For example:

    3 bedroom house reusing laundry water only, the daily greywater is c

    = 4 persons @ 38L/person/day

    = 152 litres daily greywater flow

    Therefore the capacity of tank required is

    152L + 24 hour combined retention (ie: double the da

    = 152L x 2

    = 304L

    plus 40L sludge accumulation x number of persons

    = 40L x 4persons

    =160 litres

    = 464L tank capacity required

    7.2.2 For Sizing Irrigation AreasThe irrigation area is sized using the daily flow only.

    For example:

    3 bedroom house reusing laundry water only

    = 4 persons @ 38 litres/day

    = 152 litres daily greywater flow

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    22/43

    7.3.1 Sub Soil Trench Irrigation SystemsThe size of the greywater irrigation trench is calculated using the fol

    L = V______

    LIR x A

    Where:

    L =length of trench in metres

    V =daily greywater volume in litres/day

    LIR = Loading Infiltration Rate in litres/metre2/day (related to permea

    A = surface area of the trench in m2 (i.e. the sides below the invert of

    and base of the trench per lineal metre)

    Table 7.3 Greywater Infiltration Rates

    ** a procedure which measures soil permeability by recording the time

    300mm x 300mm hole to fall 25mm, see Schedule 8 of the Health (Treatment o

    Effluent and Liquid Waste) Regulations 1974for a full explanation of the method.

    7.3.2 Drip or Spray Irrigation Area SizingThe required irrigation area size should be calculated on the basis o

    sand and gravel/loam or for other soils in accordance with AS 1

    Domestic Wastewater Management.

    TIME FOR WATER TO

    FALL 25 mm**

    (minutes)

    SOIL TEXTURE

    Alternating System

    LOADING INFILTR

    (litres per m

    1 to 5

    More than 5 to 60

    More than 60

    Sand

    Loams or gravels

    Impervious Clays

    30

    20

    As approve

    Executive Director

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    23/43RAFT

    Greywater irrigation systems must also be sufficiently distanced

    features or water supplies. Indicative setback distances are given be

    Table 7.4 Example Minimum Setback Distances

    Note: Drip distance measured from pipework.

    Spray distance measured from edge of spray plume.

    *Only EDPH may vary this setback requirement.

    ** For description of Public Drinking Water Supply Areas (PDWSA) or we

    DEWCP.

    All greywater irrigation systems (ie, the dripper line or base of tren

    minimum of 500 mm clearance above the highest seasonal groundw

    Below ground greywater tanks must be a minimum of 1.2 metres fr

    building/ structure.

    Trenches should be installed in a manner that ensures even distri

    trenches must be laid level and constructed in such a manner that pr

    portion of a trench will not occur.

    1.8

    1.8

    3.0

    30.0

    1.8

    100

    0.5

    0.5

    3.0

    30.0

    0.5

    100

    Boundaries

    Buildings

    Sub-soil Drains

    Bores* - intended for

    human consumption

    Paths, drives, carports etc.

    Wetlands and water

    dependent ecosystems**

    Item

    Drip Irrigation

    area

    (metres)

    Spray Irrigation

    area

    (metres)

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    24/43

    7.5 MaterialsAll drip irrigation pipework and fittings must comply with AS 147

    fittings for pressure applicationsor AS 2698.2 Perforated effluent

    fittings for sewerage applications.

    The distribution pipe used in gravity fed sub-soil trenches should have

    diameter not less than 80mm in accordance with AS 2439 Perforand effluent pipe and fittings. A porous soakage hose or slotted ag

    acceptable for distribution of primary treated greywater in trench

    likelihood of clogging.

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    25/43RAFT

    The success of a greywater reuse system will depend on an in

    maintaining the system. Once a greywater system is install

    householders responsibility to ensure it is managed in ac

    manufacturers instructions. The owner should also ensure that the

    maintained in good working order at all times. Any defect must be rbecomes apparent.

    Some greywater systems require regular maintenance e.g. weekly c

    filters, periodic desludging, manually diverting greywater back to

    flushing of irrigation lines.

    Operation and maintenance of systems will be at a cost to the househthe initial construction costs, power to operate pumps, replacemen

    irrigation lines and desludging of sedimentation tanks.

    Applicants may be required to undertake certain commitments a

    including but not limited to the following:

    q

    Proper operation through a maintenance contract between instal

    q Weekly maintenance of systems with filtering devices.

    q Systems with two reuse areas require regular diversion.

    q Sedimentation tanks require desludging every 5 years.

    q Warning signs should be maintained in good order.

    q The irrigation area should be maintained to prevent the entry of r

    q Test the soils for pH and sodicity on a regular basis The additio

    8. SYSTEM MAINTENANCE

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    26/43

    ensure that cuts, sores, open wounds etc are adequately

    protected from any contact with greywater;

    ensure that exposed body areas that come into contac

    immediately washed;

    do not make contact with the mouth or face either direct

    or indirectly (eg smoking) until after washing hands; and

    do not eat food until hands have been washed thoroughl

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    27/43RAFTOnly greywater systems that have been approved by the Executive Diunder Section 4 of these guidelines are approved for use in WesterSection 9.3).Installation of an approved greywater system or conversion of sep

    Aerobic Treatment Units (ATUs) to greywater systems must be ap

    Government and will require a formal application be made and all fe

    All greywater system applications up to (and including) 10 persons a

    approved by the Local Government.

    All greywater systems above 10 persons are to be submitted to the E

    is the procedure for septic tank applications greater than 540L und

    Health (Treatment of Sewage and Disposal of Effluent and Liquid

    1974.

    9.1 ApplicationAn Application to Construct or Install an Apparatus for the Treatment

    be obtained from the local government. The applicant must co

    sections, including:

    q Greywater source and likely volume.

    q Flow storage and the treatment proposed.

    q Details of the proposed system.

    q Soil type and details of the required area for use and the area/so

    9. PROCEDURE FOR OBTAINING A PE

    INSTALL A GREYWATER SYS

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    28/43

    q Details of the treatment and disposal systems including:

    proposed location of greywater system and reuse area inc

    irrigation lines/trench;

    method of construction of surface irrigation disposal are

    materials to be used; and

    where a split irrigation system is used; details of mecha

    even discharge to each area and to prevent overloading o

    q The application, inspection and local government report fees as c

    Failure to supply all requested information will delay consideration o

    As part of the approval procedure the Water Corporation, or other re

    Service Provider, must agree to the diversion of greywater from t

    regard to possible negative impacts on the sewerage system. Local goissue approval for the use of greywater systems in sewered locations

    service provider has indicated no objections.

    All plumbing work must be undertaken by a licensed plumber w

    approval from the Sewerage Service Provider for any required conne

    to the plumbing works connected to the sewer system.

    9.2 Installing a SystemOnly greywater system designs approved by the Executive Directo

    permitted and it is an offence to commence construction of a greyw

    an approval. Once the local government issues an approval t

    constructed, but not used.

    Before a system can be used, the local government must inspect t

    that it is installed correctly before excavations are refilled. If sa

    government will issue an approval for the system to be used. It is an o

    using the system prior to receiving the local governments approval.

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    29/43RAFT

    q Systems which convert Aerobic Treatment Units to greywater sy

    Appendix 4.

    It is anticipated that with the release of these Guidelines new innovat

    designs shall be trialed and approved by the Executive Director, Pub

    For a current list of approved greywater reuse systems please

    Government office or the Wastewater Management Section of the Don (08) 9388 4932.

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    30/43

    Absorption uptake of liquid into the soil.

    BOD5 (biochemical oxygen demand) a measure of the dissolved oxy

    breakdown of organic material in the effluent; usually refers to a

    typically represents 70 80% of the total BOD in a sample; expresslitre (mg/L).

    Disinfection a process which reduces the number of micro-orga

    sterilise or remove all micro-organisms.

    Greywater The untreated household wastewater which has not co

    toilet waste (black water). It comes from the bath, shower, bathroomsink, clothes washing machine and laundry trough.

    Greywater Reuse means the application of greywater for a beneficial

    include disposal at a depth which would not be a beneficial use to p

    Greywater Systems consist of the greywater diversion, treatment, sto

    equipment that reuses greywater for garden irrigation.

    Pathogens disease causing microbes eg viruses, bacteria, helminth

    Phosphorus Retention Index (PRI) The PRI is defined as the ra

    adsorbed to 5 gram soil, expressed as mg P/kg of soil, and conc

    (mgP/L) after addition of 100 mL of a 10 mg/L P solution in 0.02 M

    for 18h. The practical scale of PRI is from 0 to about 1000 (above w

    meaningless). A PRI of 20 indicates that 5 mg P/L remains in soladdition of 10 mg P/L in 100 mL to 5 g of soil.

    Primary Treatment Systems These systems utilise a sedimentat

    screen out oils/greases, lint, hair and particles.

    10. DEF INIT IONS

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    31/43RAFT

    Sub-Strata Drip Irrigation this term is commonly used to denote uti

    by trickle or micro-drip irrigation where the system is placed on th

    surface and covered with a minimum of 100mm of approved

    woodchips) placed over the irrigation pipework.

    Sub-Surface Drip Irrigation this term is commonly used to d

    wastewater by trickle or micro-drip irrigation which is at a minimu

    below ground level.

    Surface Spray Irrigation water applied to the ground from above gr

    Thermotolerant Coliforms (also known as faecal coliforms) a subset

    the intestinal tract of humans and other warm blooded animals. Con

    They are used as indicators of faecal pollution and effectiveness of d

    and measured as a colony forming unit or cfu/100ml.

    The following abbreviations are used in the guideline:

    BOD5 Biochemical Oxygen Demand 5 days

    cfu colony forming unit

    DEWCP Department of Environment, Water and Catchment Pr

    DOH Department of Health

    EDPH Executive Director, Public Health

    L Litre

    m metre

    mL millilitre

    mm millimeter

    PRI Phosphorus Retention Index

    SS S d d S lid (i l d NFR N Filt abl R

    ABBREVIATIONS

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    32/43

    Christova-Boal D, Lechte P, Shipton R (1995) Installation and Evalu

    Greywater Reuse Systems Department of Civil and Building Engine

    University of Technology, Victoria, Australia.

    Department of Health, Western Australia Treatment of Sewage andand Liquid Waste Regulations 1974.

    (available from: www.slp.wa.gov.au)

    Department of Health, Western Australia (2001) Code of Prac

    Manufacture, Installation and Operation of Aerobic Treatment Units (A

    Dwellings.

    Standards Australia (2000) AS 1547:2000 Onsite Domestic Waste

    Standards Australia (1998) AS 1546.1:2000 Onsite Domestic Was

    Septic Tanks.

    Jeppersen, B and Solley, D (1996) Model Guidelines for Domestic

    Australia. Research Report No 107. Urban Research Association o

    City Council.

    (available from: www.wsaa.asn.au)

    US Environmental Protection Agency (1992) Guidelines for Water Re

    88.

    12. REFERENCES

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    33/43R

    AFT

    Californian Department of Water Resources (1995) Using Grayw

    landscape - the Graywater Guide State of California.

    (available from: wwwdpla.water.ca.gov/urban/land/graywater_guide_

    Jeppersen, B and Solley, D (1994) Domestic Greywater Reuse: OverApplicability to Australia. Research Report No 73. Urban Rese

    Australia, Brisbane City Council.

    Kourik, R (1993) Gray Water Use in the Landscape: how to help you

    with recycled water Metamorphic Press, California.

    Ludwig A (2000) Create an Oasis with Greywater: Your complete gubuilding and using Greywater systems 4th Edition, Oasis Design, San

    NSW Department of Health (2000) Greywater Reuse in Sewer

    Premises, Sydney.

    (available from: www.health.nsw.gov.au/public-health/ehb/general/wa

    Wendy van Dok (2000) The Water-efficient Garden: includes detgreywater irrigation Water-efficient Gardenscapes, Victoria, Australia

    (available from: home.nemesis.com.au/water)

    13. B IBL IOGRAPHY

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    34/43

    What is greywater?Greywater is household wastewater that has not come into contac

    comes from the bath, shower, bathroom wash basins, clothes wa

    laundry trough. Wastewater from the kitchen sink and dishwasher s

    as these can contain heavy loads of organic material, fats and caust

    Note: Water from domestic air conditioners is not greywater, and the D

    has no objections to its reuse on gardens.

    Why reuse greywater?Western Australia is experiencing water restrictions due to current dro

    the critically low levels of surface water storage. It is recognised that in

    many householders like to conserve water by reusing their greywate

    guidance on how greywater can best be reused for watering gardens

    For long term sustainable greywater reuse, greywater should be dispo

    in a manner approved by the Department of Health, as required

    legislation. This is because greywater can contain disease causing or

    soaps, nutrients, oils, salts and particles of hair, food, lint, etc. Unles

    these characteristics can give rise to health risks and degradation of

    In the current circumstances there is nevertheless considerablgreywater reuse where facilities for below ground application are

    Department has therefore provided this advice for minimising the

    ground application, which should only be by bucket or similar recep

    APPENDIX 1 GUIDEL INES FOR M A

    BUCKETING GREYWATER

    Reuse of Household Greywater in Western

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    35/43R

    AFT

    The dos

    q Select garden friendly detergents. Only biodegradable products a

    phosphorus, sodium, boron, chlorine and borax should be used.

    softeners should be used sparingly.

    q

    Apply greywater in several locations rather than one single poingreywater does not occur.

    q Apply greywater to areas that are not readily accessible to chil

    pets.

    The donts

    q Dont use greywater from the washing of nappies and soiled cloth

    q Dont use greywater when a household resident has an infectio

    diarrhoea, infectious hepatitis, intestinal parasites, etc.

    q Dont discharge greywater on edible plants or where fruit fallen to

    q Dont store greywater. Stored greywater will turn septic giving rise

    and provide conditions for micro-organisms to multiply.

    q Dont let your greywater go beyond your property and cause

    neighbours.

    q Dont over water. Over application of greywater may clog the soil

    of greywater, which can result in the development of unsightly slime. This slime is caused by the presence of soaps, shamp

    grease in greywater. The accumulation of slime can cause odours

    cause environmental damage.

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    36/43

    A house has 5 bedrooms. The soil type is sand. All greywater is to

    the minimum area required to irrigate the greywater via sub-soil tren

    or spray irrigation.

    1. Calculate the daily greywater flowDaily greywater flow for a 5 bedroom house is calculated as follows:

    i) Calculate the number of occupants based on the number of b

    (2 persons for the first bedroom, 1person per each additional b

    2 persons + 1 persons + 1 persons + 1 pe

    = 6 persons

    ii) Calculate the daily flow per person based on figures given in s

    (112L/person based on kitchen, laundry and bathroom flows)

    6 persons @ 112 Litres/day

    = Total Daily Greywater Flow (V) = 672L/da

    2. Calculate the area of land required to reuse greywater via a Sub-S

    The required length of an alternating subsoil trench irrigation system

    250mm (depth) x 300mm (width) to reuse 672L/day is calculated

    formula (see section 7.3.1):

    V

    L = _______

    LIR x A

    i) Calculate the surface area (A) of the 250mm x 300mm trench pe

    A = [0.25m (side) + 0.30m (bottom) + 0.25m (side)] x 1

    ii) Using the Loading Infiltration Rate (LIR) for sand, 30Litres/m2/day

    7.3. Calculate the required trench surface area (L) to reu

    672L/d

    APPENDIX 2 EXAMPLE GREYWATER CAL

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    37/43

    RAFT

    Two options for primary treatment systems are listed below:

    1. Sedimentation tank with sub-soil trench irrigation

    The basic requirements are listed below:

    q The sedimentation tank must comply with the structural and acc

    AS 1546.1 Septic Tanks.

    q Where a pump system is used to distribute greywater afte

    sedimentation tank to the pump tank, the pump tank must:

    comply with AS 1546.1 Septic Tanks;

    have a minimum capacity of 250L where fitted with a sew

    plus a minimum of one days reserve capacity where se

    available;

    be fitted with a high water level warning device prior to o

    before the 250 litre level; and

    have an inspection opening and manhole access opening

    q Sludge build up in the sedimentation tank must be pumped out

    q Sub-soil trench systems must be constructed in accordance w

    Onsite Domestic Wastewater Management or a DOH approve

    maximum permitted trench depth below surface is 100mm an

    exceed 400mm below ground surface.

    q Sub-soil trench lengths must comply with the Health (Treatm

    Disposal of Effluent and Liquid Waste) Regulations 1974based othe irrigation trenches and the receiving soil permeability.

    2. Conversion of disused septic tank systems to a primary greywater s

    The conversion of disused septic systems to sedimentation tank an

    APPENDIX 3 PRIMARY TREATMENT

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    38/43

    One option for a secondary treatment system that collects, treats and

    to a standard of 20 mg/L BOD5, 30 mg/L SS and 10 cfu thermotolera

    prior to irrigation via drip and/or surface irrigation methods is detaile

    Conversion of Aerobic Treatment Units (ATU) systems to greywater sysThe conversion of disused ATUs to greywater systems is permitted s

    following:

    q The ATU is to be installed, operated and maintained in accordan

    Practice for the Design, Manufacture, Installation and Operation

    Units Serving Single DwellingsNovember 2001.

    q The effluent quality prescribed for ATUs must continue to be ma

    q Desludging of ATUs to allow conversion is not necessary.

    APPENDIX 4 SECONDARY TREATMENT

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    39/43

    RAFTThe following of examples are approved sub-soil trench irrigation AS 1547:2000 Onsite Domestic Wastewater Management. All trenches are to be in accordance with the structural and mateAS 1547:2000 Onsite Domestic Wastewater Management.

    Figure 5.1 Self Supported Arch Trench

    APPENDIX 5 SUB- SOIL TRENCH IR

    DESIGNS

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    40/43

    Figure 5.2 Evapo-transpiration-absorption (ETA) trench/Evapo-transpirtrench

    Figure 5.3: ETA/ETS Bed

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    41/43

    RAFT

    Figure 5.4: Conventional Piped Trench

    Figure 5.5: Conventional Bed

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    42/43

    Figure 5.6 Typical layout of sub-surface irrigation

  • 8/3/2019 DGWA - Draft Guidelines for the Reuse of Greywater in Western Australia

    43/43

    Produced by Environmental Health Service with assistance from Marketing and Campaign SupportPopulation Health Division Department of Health 2002

    HP 8122