Transcript of DEWA UserManual
UU ss ee rr MM aa nn uu aa ll
DDEEWWAA eeSSeerrvviicceess
Version: 1.0
DEWA eServices User Manual
Page 2 of 42 Version:1.0
Table of Contents 1. Legend..................................................................................................................... - 3 - 2. Manual Objectives .................................................................................................. - 4 - 3. Description .............................................................................................................. - 4 - 4. System Requirement ............................................................................................... - 4 - 5. How to Navigate? ................................................................................................... - 5 - 6. How to Register?..................................................................................................... - 5 - 7. Forget Password ...................................................................................................... - 8 - 8. How to Login? ...................................................................................................... - 10 - 9. Owner Registration ............................................................................................... - 11 - 10. Building NOC ....................................................................................................... - 13 - 11. LV Design Approval ............................................................................................. - 16 - 12. LV Shop Drawing Approval ................................................................................. - 19 - 13. Fit-out Application ................................................................................................ - 22 - 14. HV Design Approval ............................................................................................ - 25 - 15. HV Inspection ....................................................................................................... - 28 - 16. Application ............................................................................................................ - 31 - 17. LV Inspection........................................................................................................ - 33 - 18. Track your Application ......................................................................................... - 34 - 19. Make your payment (on-line) ............................................................................... - 35 - 20. Update Profile ....................................................................................................... - 35 - 21. Building NOC - Water .......................................................................................... - 37 - 22. Design Approval - Water ......................................................................... - 39 -
DEWA eServices User Manual Page - 3 - of 42 Version:1.0
1. Legend Frequently used symbols / icons and commands in SAP Transactions
Symbols Meaning of symbols and Commands
Increase and decrease font on page
Submit Any application
Cancel application.
Return back to previous Screen
DEWA eServices User Manual
Page - 4 - of 42 Version:1.0
2. Manual Objectives Objective of this manual is to provide the hands on experience of the SAP transactions to the users. Based on the DEWA eService business processes the transaction flow has been structured in this document as per required business.
3. Description
DEWA eService is exclusively design for Consultant, Contractor and Govt Organization to apply and track the application online. DEWA eService will covers the wide range of the Electricity and Water services offered by DEWA. The services are:
Electricity Water Building NOC Building NOC
Demolition NOC Demolition NOC
LV Design Approval Design Approval
LV Shop Drawing Approval Construction Drawing Approval
HV Design Approval Application
Application for Fit-Out Approval Application-Infrastructure (New)
HV Inspection On-line Estimate Payment
LV Inspection Application Application-Infrastructure (New) On-line Estimate Payment
As the owner of our products you can get convenient access to Creation and tracking of application and account information for certain services and performs select self-service transactions online.
4. System Requirement
To access the eService Website, we recommend your computer meets the following requirements:
Computer requirements
Your computer must have at least 1GB RAM, 100MB disk space, 133MHz, and Internet access.
Modem Requirements
The minimum speed requirement for a modem to access eService is 28.8Kbps, although we recommend using 56.6Kbps or higher speeds for optimal performance.
Web Browser Requirements
DEWA eServices User Manual
Page - 5 - of 42 Version:1.0
For the best eService experience we recommend you access the eService site using Microsoft® Internet Explorer - version 6.0 or higher and pop-up should be enable.
The following are known browsers or platforms that are not officially supported by eService:
America Online® Netscape Navigator® Microsoft® Internet Explorer - lower than version 6.0 Certain Sun Microsystems applications, such as, Hot Java Browser and StarOffice Browser Web TV Browsers for the blind (screen readers or braille-writers) Browsers that disable JavaScript Browsers that do not support JavaScript Other browsers, such as, Opera, Mozilla, IE-derivatives MSN Explorer & NeoPlanet, and any other
browser that supports HTML 4.0, CSS 1.0, and JavaScript 1.0 should be able to run eService. However, these browsers are not officially supported platforms and therefore, results vary compared to those of supported browsers and platforms.
5. How to Navigate?
DEWA eService is specially designed for Consultant, Contractor and Government Organization to serve his customer with full satisfaction. Consultant, Contractor and Government Organization needs to be register with DEWA for availing various services offered by DEWA.
To navigate you need to go to https://crm.dewa.gov.ae/
Availing Upon logging into the portal, please go to the eService tab. Select eService and you can directly connected to the application.
6. How to Register?
The Enrollment Process is applicable for following activities
Electrical Installation
Civil construction
Building contracting
General Maintenance and
Demolition
The following categories are available for Consultant and Contractor
Consultant:
Consultant – General ( Electro-Mechanical, Civil, Structural, Architectural etc)
Consultant – Electrical
Consultant – Utility (Govt. organization/Utilities/Companies etc)
Contractor
DEWA eServices User Manual
Page - 6 - of 42 Version:1.0
Contractor – Electrical
Contractor – Civil
Contractor – Fit Out (to be defined clearly to make it easy to the Applicants)
Contractor – Demolition
Prerequisite
Valid Trade License
Simple Steps for Registration
Step 1: Click on New User Enrollment Hyperlink
Step 2: Select Application Category from Drop down list e.g. Consultant-Electrical, General etc.
Step 3: Enter all mandatory fields
Step 4: Enter Valid Trade License or Approved Letter
Step 5: Update the contact person Details
Step 8: Enter User ID and Password
Step 7: Upload required documents
Step 9: Submit application
Step 10: System will automatically send SMS & E-mail
Step 11: Submitted Application will undergo through approval process in DEWA
Step 12: Upon approval, system will automatically send Notification to consultant and contractor.
DEWA eServices User Manual
Page - 7 - of 42 Version:1.0
Note: all * are mandatory fields in the application needs to be fill-up
Enrollment Application From
DEWA eServices User Manual
Page - 8 - of 42 Version:1.0
7. Forget Password Any time if you forget your password, Password can be changed on-line Simple Steps for Reset your password
Step 1: Click on Forget your password Hyperlink
DEWA eServices User Manual
Page - 9 - of 42 Version:1.0
Step 2: Enter your Login Id
Step 3: Enter valid e-mail Id
Step 4: Press Submit
Step 5: System will automatically confirms the password assigned to your user id
DEWA eServices User Manual
Page - 10 - of 42 Version:1.0
8. How to Login? Accessing DEWA eService, you need to user your credentials approved by DEWA e.g. User ID and Password Simple Steps for Login into DEWA eService
Step 1: Enter your User Id
Step 2: Enter your Password
Step 3: Press Log on Button
DEWA eServices User Manual
Page - 11 - of 42 Version:1.0
9. Owner Registration To organize your Owner through Owner registration procedure by using unique identification key e.g. Emirates ID. Single identity for all process in DEWA e.g. Billing, NOC, DA etc.
Navigation Path Customer eService Owner Registration
Prerequisite
Valid User ID and Password
Valid EID Card
Simple Steps for Search existing Owner and relate
Step 1: Enter any of the Search parameter e.g. Driving License No, Passport No, Trade License No, Emirates ID No. to identify an existing Owner.
DEWA eServices User Manual
Page - 12 - of 42 Version:1.0
Step 2: Press Search Owner
Step 3: Select Displayed Owner and
Step 4: Press Relate Owner Button
Create Owner (if Not available in DEWA Repository)
Step 1: Press Create Owner Button
Step 2: Select Owner Type (Individual – For Individual Customer and Organization – Company etc)
Step 3: Enter all Mandatory information e.g. First Name, Last Name etc
Step 4: SAVE Owner Details
Step 5: You will get the System Generated Unique Number, Which can be refer any time in DEWA for reference purpose.
DEWA eServices User Manual
Page - 13 - of 42 Version:1.0
10. Building NOC The purpose of getting Building NOC is to ensure the source of supply as well as safety and protection of existing network, Which is mandatory prior to obtain building permit from DM and to start construction activities at site
Navigation Path Customer eService Building NOC Prerequisite
Valid User ID and Password
Registered Owner Master
Simple Steps for Search existing Owner and relate
Step 1: Enter any of the Search parameter e.g. Driving License No, Passport No, Trade License No, to identify an existing Owner or Press Search Button for Free Search Step 2: Select any of the Owner which you wish to create application.
Step 2: Select any of the Owner by pressing Owner Name Step 3: Select Type of NOC as per your wish e.g. New, Revision, Renewal or Additional load/Quantity Step 4: Select Connection Type e.g. Electricity or Water Step 5: Fill-up all mandatory information Step 6: Attached all required document Step 7: Press Submit Button Step 8: System will automatically generate application number, the same can be refer any time Note: all * are mandatory fields in the application needs to be fill-up
DEWA eServices User Manual
Page - 14 - of 42 Version:1.0
Building NOC Application From-Electricity
DEWA eServices User Manual
Page - 15 - of 42 Version:1.0
Building NOC Application From-Water
DEWA eServices User Manual
Page - 16 - of 42 Version:1.0
11. LV Design Approval
Enrolled consultants (consultant – Electrical & Consultant – Gov) and contractors (Contractor- Electrical &
Contractor – Fit outs) are applying on-line for obtaining Drawing Approval through e-Services of DEWA. The
purpose of obtaining Drawing Approval for low voltage wiring installation is to carry out the electrical installation
work complying with DEWA regulation for electrical installation and to apply for connection for the projects.
LV design Approval is issued for consultant who had obtain DEWA Building NOC specifying requirement of
DEWA Substation within the consumer plot, LV Design Approval is also pre-requisite for Applying Shop Drawing
Approval for Such Projects. If requirement of DEWA substation is not specified in DEWA Building NOC, such
cases LV design approval is not mandatory for issuing LV shop drawing approval to the contractors.
Only electrical contractor can apply for LV shop drawing which is mandatory for all the projects.
LV Shop Drawing for Fit-out works is issued to fit-out contractors as well as electrical contractors after the above
LV shop drawing approval for the main project where ever applicable. Such case DEWA NOC is not mandatory
for submission of application.
LV design approval and LV Shop Drawing Approval Process are two independent processes however the
process is identical except for the documents.
Navigation Path Customer eService LV Design Approval Prerequisite
Valid User ID and Password
Registered Owner Master
Approved Building NOC
Simple Steps for LV Design Approval
Step 1: Download attached Sheet 1. Premise Details and 2. Material Request Form
Step 2: Enter any of the Search parameter e.g. Driving License No, Passport No, Trade License No, to identify an existing Owner or Press Search Button for Free Search Step 3: Select any of the Owner which you wish to create application. Step 4: Select any of the Owner by pressing Owner Name Step 5: Search Approved NOC by plot no or Electricity NOC
DEWA eServices User Manual
Page - 17 - of 42 Version:1.0
Step 6: Select Approved NOC by pressing NOC No
Step 7: Select Type of NOC No as per your wish to create LV Design Approval Step 8: Select Type of application e.g. New or Revision Step 7: Fill-up all mandatory information Step 8: Attached all required document and downloaded file (Premise and Material) Step 9: Press Submit Button Step 10: System will automatically generate application number, the same can be refer any time Note: all * are mandatory fields in the application needs to be fill-up
LV Design Application From
DEWA eServices User Manual
Page - 18 - of 42 Version:1.0
DEWA eServices User Manual
Page - 19 - of 42 Version:1.0
12. LV Shop Drawing Approval Enrolled consultants (consultant – Electrical & Consultant – Gov) and contractors (Contractor- Electrical &
Contractor – Fit outs) are applying on-line for obtaining Drawing Approval through e-Services of DEWA. The
purpose of obtaining Drawing Approval for low voltage wiring installation is to carry out the electrical installation
work complying with DEWA regulation for electrical installation and to apply for connection for the projects.
LV design Approval is issued for consultant who had obtain DEWA Building NOC specifying requirement of
DEWA Substation within the consumer plot, LV Design Approval is also pre-requisite for Applying Shop Drawing
Approval for Such Projects. If requirement of DEWA substation is not specified in DEWA Building NOC, such
cases LV design approval is not mandatory for issuing LV shop drawing approval to the contractors.
Only electrical contractor can apply for LV shop drawing which is mandatory for all the projects.
LV Shop Drawing for Fit-out works is issued to fit-out contractors as well as electrical contractors after the above
LV shop drawing approval for the main project where ever applicable. Such case DEWA NOC is not mandatory
for submission of application.
LV design approval and LV Shop Drawing Approval Process are two independent processes however the
process is identical except for the documents.
Navigation Path Customer eService LV Shop Drawing Approval Prerequisite
Valid User ID and Password
Registered Owner Master
Approved Building NOC
Approved Design Approval (If Substation Required)
Simple Steps for LV Shop Drawing Approval
Step 1: Download attached Sheet 1. Premise Details and 2. Material Request Form
Step 2: Enter any of the Search parameter e.g. Driving License No, Passport No, Trade License No, to identify an existing Owner or Press Search Button for Free Search Step 3: Select any of the Owner which you wish to create application. Step 4: Select any of the Owner by pressing Owner Name Step 5: Search Approved NOC by plot no or Electricity NOC
DEWA eServices User Manual
Page - 20 - of 42 Version:1.0
Step 6: Select Approved NOC by pressing NOC No
Step 7: Select Type of NOC No as per your wish to create LV Shop Drawing Approval Step 8: Select Type of application e.g. New or Revision Step 7: Fill-up all mandatory information Step 8: Attached all required document and downloaded file (Premise and Material) Step 9: Press Submit Button Step 10: System will automatically generate application number, the same can be refer any time Note: all * are mandatory fields in the application needs to be fill-up
LV Shop Drawing Application From
DEWA eServices User Manual
Page - 21 - of 42 Version:1.0
DEWA eServices User Manual
Page - 22 - of 42 Version:1.0
13. Fit-out Application Enrolled consultants (consultant – Electrical & Consultant – Gov) and contractors (Contractor- Electrical &
Contractor – Fit outs) are applying on-line for obtaining Drawing Approval through e-Services of DEWA. The
purpose of obtaining Drawing Approval for low voltage wiring installation is to carry out the electrical installation
work complying with DEWA regulation for electrical installation and to apply for connection for the projects.
LV design Approval is issued for consultant who had obtain DEWA Building NOC specifying requirement of
DEWA Substation within the consumer plot, LV Design Approval is also pre-requisite for Applying Shop Drawing
Approval for Such Projects. If requirement of DEWA substation is not specified in DEWA Building NOC, such
cases LV design approval is not mandatory for issuing LV shop drawing approval to the contractors.
Only electrical contractor can apply for LV shop drawing which is mandatory for all the projects.
LV Shop Drawing for Fit-out works is issued to fit-out contractors as well as electrical contractors after the above
LV shop drawing approval for the main project where ever applicable. Such case DEWA NOC is not mandatory
for submission of application.
LV design approval and LV Shop Drawing Approval Process are two independent processes however the
process is identical except for the documents.
Navigation Path Customer eService Application for Fit-out Prerequisite
Valid User ID and Password
Registered Owner Master
Approved Shop Drawing Approval
Simple Steps for Fit-Out Application
Step 1: Enter any of the Search parameter e.g. Driving License No, Passport No, Trade License No, to identify an existing Owner or Press Search Button for Free Search Step 2: Select any of the Owner which you wish to create application. Step 3: Select any of the Owner by pressing Owner Name
DEWA eServices User Manual
Page - 23 - of 42 Version:1.0
Step 4: Search Approved LV Shop Drawing based on plot no or Application No Step 5: Select Approved LV Shop Drawing and press view link to ensure the correctness
Step 6: Select LV Shop Drawing No as per your wish to create Fit-Out Application Step 8: Select Type of application e.g. New or Revision Step 7: Fill-up all mandatory information Step 8: Attached all required document and downloaded file (Premise and Material) Step 9: Press Submit Button Step 10: System will automatically generate application number, the same can be refer any time Note: all * are mandatory fields in the application needs to be fill-up
DEWA eServices User Manual
Page - 24 - of 42 Version:1.0
Fit-Out Application From
DEWA eServices User Manual
Page - 25 - of 42 Version:1.0
14. HV Design Approval
Design Approval Consultant needs to be enrolled with DEWA through Enrollment Process. The pre-requisite for
Applying Design Approval is to have valid Building NOC.
Categories of Substation Design Approval submission can be.
New Approval
Revision Approval
Renewal after expiry
Up-rating
Shifting of Substation with additional load
Temporary Supply
RMU/ Control Room Approval (For 11/22 kV Dedicated Feeder)
Navigation Path Customer eService HV Design Approval Prerequisite
Valid User ID and Password
Registered Owner Master
DEWA eServices User Manual
Page - 26 - of 42 Version:1.0
Approved Building NOC
Simple Steps for HV Design Approval
Step 1: Enter any of the Search parameter e.g. Driving License No, Passport No, Trade License No, to identify an existing Owner or Press Search Button for Free Search
Step 3: Select any of the Owner which you wish to create application. Step 4: Select any of the Owner by pressing Owner Name Step 5: Search Approved NOC by plot no or Electricity NOC Step 6: Select Approved NOC by pressing NOC No
Step 7: Select Type of NOC No as per your wish to create HV Design Approval Step 8: Select Type of application e.g. New, Revision, Renewal, RMU/Control Room, Up-rating, shifting with additional load and Temporary Supply Step 7: Fill-up all mandatory information
DEWA eServices User Manual
Page - 27 - of 42 Version:1.0
Step 8: Attached all required document Step 9: Press Submit Button Step 10: System will automatically generate application number, the same can be refer any time Note: all * are mandatory fields in the application needs to be fill-up
HV Design Application From
DEWA eServices User Manual
Page - 28 - of 42 Version:1.0
15. HV Inspection Releasing of power supply for new connection, substation room has to be approved by the HV Inspection unit
where ever substation is required. All this case related to the consultant of the project. Site Inspection for
substation room to be carried out by the HV inspection engineer once consultant requests for inspection. Once
the substation room is approved then it will go to the Est. & Job Order Section for further action.
Navigation Path Customer eService HV Inspection
Prerequisite
Valid User ID and Password
Registered Owner Master
Approved HV Design
Simple Steps for HV Inspection Approval
Step 1: Enter any of the Search parameter e.g. Driving License No, Passport No, Trade License No, to identify an existing Owner or Press Search Button for Free Search
Step 3: Select any of the Owner which you wish to create application. Step 4: Select any of the Owner by pressing Owner Name Step 5: Search Approved HV Design based on pre defined parameter Step 6: Select Approved HV Design by pressing HV Design No
DEWA eServices User Manual
Page - 29 - of 42 Version:1.0
Step 7: Fill-up all mandatory information Step 8: Attached all required document Step 9: Press Submit Button Step 10: System will automatically generate application number, the same can be refer any time Note: all * are mandatory fields in the application needs to be fill-up
DEWA eServices User Manual
Page - 30 - of 42 Version:1.0
HV Inspection Application From
DEWA eServices User Manual
Page - 31 - of 42 Version:1.0
16. Electricity/Water/Infrastructure Application The Application for Supply of Electricity and Water, eServices will provide an on-line electronic service with an
automated business workflow on DEWA’s website. Contractor, Consultant or Govt Organization needs to enroll
with DEWA using Enrollment Process to have a valid user id and password. Consultant, Contractor and Govt
Org can submit the Application after obtaining the Building NOC and Design Approval from DEWA. Once DEWA
receives the application from the consultant, contractor or Govt Organization the Application team will check the
integrity of the applicant and application. Then they will forward it to estimate department for Estimation.
Navigation Path Customer eService Application
Prerequisite
Valid User ID and Password
Registered Owner Master
Approved LV Design and LV Shop Drawing for Electricity
Approved Design and Construction Supply for Water
Simple Steps for Application Approval
Step 1: Enter any of the Search parameter e.g. Driving License No, Passport No, Trade License No, to identify an existing Owner or Press Search Button for Free Search
Step 2: Select Application Category e.g. Electricity, Water, Both or Infrastructure Services Step 3: Select Connection type from drop down list e.g. Permanent, Additional Meter etc
DEWA eServices User Manual
Page - 32 - of 42 Version:1.0
Step 4: Select Approved LV Design, LV Shop Drawing, Design Approval-Water or Construction Supply-Water Step 5: Select Connection Type e.g. Permanent Connection, Temporary Connection etc Step 6: Press Create Application
Step 7: Press Create Application Step 8: Fill-up all mandatory information Step 9: Attached all required document Step 10: Press Submit Button Step 11: System will automatically generate application number, the same can be refer any time Note: all * are mandatory fields in the application needs to be fill-up
DEWA eServices User Manual
Page - 33 - of 42 Version:1.0
Application From
17. LV Inspection Releasing of power supply for new connection has to be approved by the LV Inspection unit for which the concerned Electrical contractor of the project has to submit an inspection request. The Site inspection for the inspection request is allocated to an inspection engineer. The Site is then inspected by the engineer and on approval. The supply to the premise is released by the metering staff.
Navigation Path Customer eService LV Inspection Prerequisite
Valid User ID and Password
DEWA eServices User Manual
Page - 34 - of 42 Version:1.0
Registered Owner Master
Approved Application
Simple Steps for LV Inspection Approval
Step 1: Enter any of the Search parameter e.g. Driving License No, Passport No, Trade License No, to identify an existing Owner or Press Search Button for Free Search
18. Track your Application Releasing of power supply for new connection has to be approved by the LV Inspection unit for which the concerned Electrical contractor of the project has to submit an inspection request. The Site inspection for the inspection request is allocated to an inspection engineer. The Site is then inspected by the engineer and on approval. The supply to the premise is released by the metering staff.
Navigation Path Customer eService Track your application Prerequisite
Valid User ID and Password
Registered Owner Master
Registered Application in DEWA
By default you will received all application which required Customer Action.
Various Parameters are available to search your application such by default you will receive all application which required Customer Action.
DEWA eServices User Manual
Page - 35 - of 42 Version:1.0
After Label first Blank Row is use to set the custom filter as you wish e.g. appr* on Status Column. System will display those applications who status start from APPR Simple Steps for Track you Application
Step 1: Enter Plot no or Order No (Application No) Step 2: Enter Application Category e.g. Building NOC, Demolition NOC etc
19. Make your payment (on-line) DEWA is facilitating his support not only limited to application creation and tracking. You can also make estimate payment online using Secure Payment Gateway.
20. Update Profile DEWA is facilitating you to update your profile with latest information so that we can serve your better.
Navigation Path Customer eService Update Profile Prerequisite
Valid User ID and Password
Registered Owner Master
Filter Option e.g.Approv*
DEWA eServices User Manual
Page - 36 - of 42 Version:1.0
Simple Steps for Track you Application
Step 1: Enter your input as you wish to change Step 2: Update all required attachment Step 3: Press Update button to update your profile Note: Application Category hyperlink will help you, how to upgrade your existing Services
DEWA eServices User Manual
Page - 37 - of 42 Version:1.0
21. Building NOC - Water The purpose of getting Building NOC is to ensure the source of supply as well as safety and protection of existing network, Which is mandatory prior to obtain building permit from DM and to start construction activities at site
Navigation Path Customer eService Building NOC Prerequisite
Valid User ID and Password
Registered Owner Master
Simple Steps for Search existing Owner and relate
Step 1: Enter any of the Search parameter e.g. Driving License No, Passport No, Trade License No, to identify an existing Owner or Press Search Button for Free Search Step 2: Select any of the Owner which you wish to create application.
DEWA eServices User Manual
Page - 38 - of 42 Version:1.0
Step 2: Select any of the Owner by pressing Owner Name Step 3: Select Type of NOC as per your wish e.g. New, Revision, Renewal or Additional load/Quantity Step 4: Select Connection Type e.g. Electricity or Water Step 5: Fill-up all mandatory information Step 6: Attached all required document Step 7: Press Submit Button Step 8: System will automatically generate application number, the same can be refer any time Note: all * are mandatory fields in the application needs to be fill-up
Building NOC Application From-Water
DEWA eServices User Manual
Page - 39 - of 42 Version:1.0
22. Design Approval - Water
The purpose of getting Building NOC is to ensure the source of supply as well as safety and protection of existing network, Which is mandatory prior to obtain building permit from DM and to start construction activities at site
Navigation Path Customer eService Design Approval Water Prerequisite
Valid User ID and Password
Registered Owner Master
DEWA eServices User Manual
Page - 40 - of 42 Version:1.0
Approved Building NOC
Simple Steps for Search existing Owner and relate
Step 1: Enter any of the Search parameter e.g. Driving License No, Passport No, Trade License No, to identify an existing Owner or Press Search Button for Free Search Step 2: Select any of the Owner which you wish to create application.
Step 3: Select any of the Owner which you wish to create application. Step 4: Select any of the Owner by pressing Owner Name Step 5: Search Approved NOC by plot no etc Step 6: Select Approved NOC by pressing NOC No
Step 7: Select Type of NOC No as per your wish to create Design Application Waterl Step 8: Select Type of application e.g. New, Revision Step 7: Fill-up all mandatory information Step 8: Attached all required document Step 9: Press Submit Button Step 10: System will automatically generate application number, the same can be refer any time Note: all * are mandatory fields in the application needs to be fill-up
DEWA eServices User Manual
Page - 41 - of 42 Version:1.0
Design Application-Water From
DEWA eServices User Manual
Page - 42 - of 42 Version:1.0
The End