Q1 2019 SarasotaFL.gov/ Economic Development Office
DEVELOPMENT
PORT
1 of 24
FOR OMISSIONS OR ERRORS,
OR TO SUBMIT PHOTOGRAPHS OR RENDERINGS FOR THIS REPORT:
Please contact Redevelopment Manager Susan Dodd at [email protected] or 941-926-6134
On the Cover:
The ‘Sarasota Times’ Building
Recently renovated and reopened as Sage, a fine dining restaurant with rooftop views, located on 1st St in Downtown Sarasota.
1996: Photograph by Roger W. 2019: Photograph courtesy of Norman Schimmel
www.SarasotaFL.gov/EconomicDevelopmentOffice
• For copies of all published Development Reports
• To subscribe to receive the newest Development Reports in your inbox
• To use the Interactive Development Map
COMPREHENSIVE OVERSIGHT OF DEVELOPMENT IN THE CITY OF SARASOTA IS PROVIDED BY THE PROFESSIONALS WITHIN THE
DEVELOPMENT SERVICES DEPARTMENT WITHOUT WHOM THIS REPORT COULD NOT BE GENERATED:
Tim Litchet, Gretchen Schneider, Dan Greenberg, Lucia Panica, Karen Grasset, Kathleen Kelley
AND THE CITY OF SARASOTA’S IT DEPT ,GIS SERVICES DIVISION.
2 of 24
Q1 2019 Development
Report
48 IN DEVELOPMENT which includes • Projects identified in the media • Projects having submitted applications for development • Projects having received development approval • Projects having submitted applications for building permit • Projects that have been issued a building/foundation permit 29 UNDER CONSTRUCTION includes • Projects actively in construction • Projects that are substantially complete (TCO)
7 COMPLETED which includes • Projects that have received a Certificate of Occupancy and/or Certificate of Completion within one year
3 of 24
10th STREET
FRUITVILLE RD
MAIN ST
WA
SHIN
GTO
N B
LVD
MOUND
US
41
TA
MIA
MI T
RA
IL
PARKWAY
OR
AN
GE
AV
E
RINGLINGBLVD
CO
CO
AN
UT
AV
E
OSP
REY
AV
E
CEN
TRA
L A
VE
BLVD OF THE ARTS
2ND ST
1ST ST
4TH ST
OR
AN
GE
AV
E
DOWNTOWN DEC 1 - APR 1, 2019
LAUREL ST
ALDERMAN ST
LEM
ON
AV
E
IN DEVELOPMENT
UNDER CONSTRUCTION
PROJECT COMPLETED (Last 12 mo)
4 of 24
CITY NORTH
U.S
. 30
1
DR. MLK, JR. WAY
OLD
BR
AD
ENTO
N R
OA
D
UNIVERSITY PARKWAY
17TH ST
IN DEVELOPMENT
UNDER CONSTRUCTION
OR
AN
GE
AV
E
10TH ST
12TH ST
TAM
IAM
I TR
AIL
DEC 1 - APR 1, 2019
30
5 of 24
CITY EAST
DEC 1 - APR 1, 2019
IN DEVELOPMENT
UNDER CONSTRUCTION
PROJECT COMPLETED (Last 12 mo)
CITY SOUTH
FRUITVILLE ROAD
BAHIA VISTA
SCH
OO
L A
VE
SIESTA DRIVE
U.S
. 41
SO
UTH
U
.S. 3
01
17TH ST
RINGLING BLVD TU
TTLE
BEN
EVA
6 of 24
IN DEVELOPMENT
UNDER CONSTRUCTION
PROJECT COMPLETED (Last 12 mo)
BARRIER ISLANDS
DEC 1 - APR 1, 2019
7 of 24
On
MapProject Type Status Location Developer Architect
Cost (Millions)
Comm.
Sq FtApts
Condo/
Townhm
Hotel
RmsFlrs
1 332 CocoanutResidential
Mixed Use
Construct
Permit
Pending
332 Cocoanut Ave (SE corner of
4th and Cocoanut)LC Aldina (Famiglio) DSDG Architects $8.0 9,151 36 5
2 430 Kumquat Ct.Residential
Mixed Use
Dev App
Pending
In between Blue Rooster and
Citrus SquareVictoria King
Halflants + Pichette
Studio for Modern
Architecture
TBD 1,500 22 5
3 Airport Hotel Phase 2 HotelDev App
Pending
995 Airport Circle (Behind the
Hampton Inn north of University)
Sarasota Manatee
Airport Authority
Chancellor Design
Group (Warwick, RI)TBD 171,250 136 5
4 Alvin's IslandCommercial
Renovation
Construct
Permit
Pending
St, Armand's Circle Marco Destin, Inc. Parker Walter Group $1.2 14,506 2
5 Amaryllis Park Place ResidentialDev App
Approved
1912 N Orange Ave (E side of
Orange Ave, just north of
Amaryllis Park)
City of Sarasota
Housing AuthorityHOYT Architects TBD 84 3
6 The AuteurResidential
Mixed Use
Dev App
Pending1000 Blvd of the Arts
Ascentia
Development Group
Curtis Gaines Hall
Jones (Tampa, FL)TBD 9,988 56 18
7 Bath & Racquet & ResidentialResidential
Mixed Use
Dev App
Pending
2170 Robinhood St (Behind
Trader Joes)
Bath & Racquet
Development Inc.
Sweet Sparkman
Architects$33.0 207 7
8 The Bay TBDIn
Develop.
Land bordered by Centennial
park to the North, Tamiami Trail
to the east, and Boulevard of the
Arts to the south.
City of Sarasota
Planning Firm: Sasaki
Associates (Boston,
MA)
TBD
9Bayside Club (Previously
"Cityside, Phase II")
Residential
Mixed Use
Dev App
Approved
850 Cocoanut Ave (north of
Phase I - at NE corner Blvd of
the Arts and Cocoanut Ave)
Jay Harvey Holdings
LLC
Forum Architecture
(Altamonte Springs,
FL)
TBD 9,988 253 5
10 The Beacon ResidentialIn
Develop.1243 2nd Street Noble Equity
5G Studio (Miami,
FL)TBD 6 7
11 Circle K CommercialIn
Develop.5400 Old Bradenton Rd
JBCC Development,
LLC TBD TBD 4,500 1
12The Collection (Previously "1335
2nd St")Residential
Construct
Permit
Pending
1335 2nd Street (Just east of
Library Mews)MK Equity Corp ARS Architecture $12.5 12 10
13 County Chilled Water Plant IndustrialDev App
Pending2150 Ringling Blvd
Sarasota County
GovernmentHall Architects, PA TBD 1
14 The Courtyard at Citrus Phase II Residential
Mixed Use
Foundatio
n Permit
Pending
555 N Orange Ave (East side of
Orange Ave, just north of Citrus
Square)
MBFC LLC HOYT Architects $2.5 6,300 18 4
15 The DeMarcayResidential
Mixed Use
Dev App
Approved33 S Palm Ave XAC Developers Parker Walter Group $23.7 2,400 39 18
16 East and Fruitville Commercial CommercialDev App
Approved
218 N East Ave (SE corner of
East Ave and Fruitville Rd)Oaktree Development C. Alan Anderson TBD 7,000 1
17 Epoch Residential
Construct
Permit
Pending
605 S Gulfstream (East of Palm Avenue, near Oak St)Seaward
Development
Nichols Brosch Wurst
Wolfe & Assoc Inc
(Coral Gables, FL)
$43.5 23 18
18Evolution (Previously "Allure
Townhomes")Residential
Dev App
Approved
Northern portion of the central
section of Golden Gate PtWB Golden Point LLC DSDG Architects TBD 20 9
19 Sarasota Ford Expansion CommercialIn
Develop.
Between Oak St and Laurel St
east of Washington BlvdSarasota Ford TBD TBD 2
204 Pts by Sheraton (aka Baymont
Conversion)
Hotel
Renovation
Dev App
Approved
1425 S Tamiami Trail (Just
south of Midtown Plaza)
Daus Investments,
LLC
Leese and
Associates (Denver,
CO)
TBD 5
214th And Cocoanut (Previously
"DRAPAC")
Residential
Mixed Use
Construct
Permit
Pending
(NE corner of Cocoanut Ave and
4th Street)
Halflants + Pichette
Studio for Modern
Architecture
$18.4 2,820 61 5
22 Fruitville PlazaResidential
Mixed Use
Dev App
Pending
B/w 4th St and Fruitville Rd, and
b/w 301 and East AveRonald Webber Patrick M. Pillot TBD 36,144 4 3
23 Humane SocietyMedical/
Hospital
Dev App
Pending2331 15th Street
Humane Society of
Sarasota County
Leader Design
Studio, LLCTBD 1
24 Imeca Lumber and Hardware Commercial
Construct
Permit
Pending
3251 N Washington Blvd (W
side of US 301, two blocks south
of Myrtle)
Cocchiola, LLC Schimberg Group $0.8 9,425 1
25 Lofts on Lemon ResidentialDev App
Pending
In between Lemon Ave and
Cohen Way, south of Salvation
Army
Sarasota Housing
Authority, Garner
Capital, and Duvernay
& Brooks
HOYT Architects $32.0 130 5
26 Myrtle Village Student Housing ResidentialIn
Develop.
One block west of Booker HS,
one block south of Myrtle
Student
Accommodation
Services, LLC
TBD TBD 9 3
27 North Trail Apartments ResidentialDev App
Pending
West of Trail between 25th and
24th StreetsTembo Enterprises
Parker Walter Group,
IncTBD 46
IN DEVELOPMENT
8 of 24
On
MapProject Type Status Location Developer Architect
Cost (Millions)
Comm.
Sq FtApts
Condo/
Townhm
Hotel
RmsFlrs
28 Palsar TBDIn
Develop.
Multiple parcels between
Tamiami Trail and Cocoanut
Ave, and between 4th Street and
Fruitville
Palsar Developments,
Inc.N/A TBD
29 Payne Park Village Phase I Residential
Found.
Permit
Issued
301 S School Ave (East of
Payne Park)
David Weekly Homes
(Houston, TX)Weekley Homes TBD 87 1
30Pines Expansion and
Renovation
Medical/
Hospital
In
Develop.
1501 N Orange Ave (West side
of Orange, North of 12th St)
The Pines of
Sarasota, Inc.TBD TBD 2
31Premier on 5th (Previously "1469
5th Street")Residential
In
Develop.
1469 5th Street (W of Lemon
Ave)
Tetra Terra
Development
Kevin Bryon,
Architect (Tetra
Terra)
$3.3 7 5
32 Quarry Direct CommercialIn
Develop.
301 between 29th and 28th
StreetsQuarry Direct, Inc. TBD TBD 10,220
33Quay Sarasota (previously
"Sarasota Bayside")
Residential
Mixed Use
Site Work
In
Progress
333 N. Tamiami Trail (West of
Tamiami Trail at Fruitville Rd)
GreenPoint
Communities LLC
(Jacksonville, FL)
Stantec (Orlando, FL) TBD 218,550 622 175
34 RCAD Dormitory Educational
Construct
Permit
Pending
Ringling College Campus (E
Tamiami Circle and Greensboro
Lane)
Ringling College of Art
and Design, Inc.
Ayers Saint Cross
Architects (Baltimore,
MD)
$10.0 5
35 Residence Inn CommercialDev App
Pending
Block bordered by 3rd St, N East
Ave, 4th St, and Audubon Place
HQ Acquisitions, LLC
(Tampa, FL)TBD TBD 2 121 4
36 Sandcastle Resort at Lido Beach HotelDev App
Approved
1540 Ben Franklin Drive
(between Lido Beach and South
Lido Park)
Lido Sand, LLC
Nichols Brosch Wurst
Wolfe (Coral Gables,
FL)
TBD 304 9
37Selby Botanical Gardens: Phase
IOther
Dev App
Pending926 S. Palm Ave
Marie Selby Botanical
Gardens, Inc.
Overland Partners,
Architects (San
Antonio, TX)
$42.5
38 Six88 Development ResidentialDev App
Pending
680 Golden Gate Pt (north
easternmost parcel on GGP)
Miles Group
Sarasota, LLC
Halflants + Pichette
Studio for Modern
Architecture
TBD 15 9
39 SKEA CommercialDev App
Pending
NE corner of Tamiami Trail and
Hibiscus Street
SKEA Enterprises,
LLC
Lawson Group
Architects, Inc.TBD 7,267 3
40 SMH Surgical Oncology TowerMedical/
Hospital
Dev App
Pending
Southwest corner of US 41 and
Waldamere
Sarasota County
Public Hospital Board
Flad Architects
(Tampa, FL)$139.0 9
41 South Shore Community Church ReligiousDev App
Pending
East of Tuttle, between Arlington
and Hillview Streets
South Shore
Community Church
Lawson Group
Architects, Inc.TBD
42 The Strand on Whitaker Bayou Residential
Construct
Permit
Pending
South of Whitaker Bayou, East
of Tamiami TrailJebco Ventures HOYT Architects $25.0 116 5
43 The Toasted Mango Café CommercialIn
Develop.
NE corner of 10th Street and
Cocoanut AveToasted Mango Café TBD TBD 1
44 Town and Country CommercialDev App
PendingBeneva and Tuttle
Benderson
Development
Cooper Johnson
Smith Architects, Inc
(Tampa, FL)
$0.4 59,000 0 0 0 1
45 WaWa CommercialDev App
PendingNW corner of Fruitville and Lime
JBCC Development,
LLC
Cuhaci and Peterson
(Orlando, FL)TBD 5,636 1
46Westcoast Black Theatre
Expansion
Commercial
Renovation
Construct
Permit
Issued
1015 N Orange Ave (SE corner
of Orange Ave and 10th Way)
Westcoast Black
Theatre Troupe Inc.C. Alan Anderson $4.0
47 Whitaker LoftsResidential
Mixed Use
In
Develop.
1400 N Tamiami Trail (E side of
Trail, between 14th and 15th
Streets)
Halflants + Pichette,
Studio for Modern
Architecture
Halflants + Pichette
Studio for Modern
Architecture
TBD 21
48 Zahrada IIResidential
Mixed Use
Dev App
Pending
S side of 4th Street kitty corner
from Blue Rooster
Dunn Hospitality
Group (Evansville,
Indiana)
Halflants + Pichette
Studio for Modern
Architecture
$7.0 18 5
On
MapProject Type Status Location Developer Architect
Cost
(Millions)
Comm.
Sq FtApts
Condo/
Townhm
Hotel
RmsFlrs
49 Airport Hotel Phase 1 Hotel
Under
Constructi
on
965 University Pkwy (NE corner
of University Pkwy and Royal
Palm Ave)
Sarasota Manatee
Airport Authority
Chancellor Design
Group (Warwick, RI)$6.3 136 5
50 Arbor Village ResidentialUnder
Construct
2901 Fruitville Rd (East of Tuttle,
across from Fairgrounds)
Centennial Bank/Blue
Sky Communities
Forum Architecture
(Altamonte Springs,
FL)
$9.0 10,000 80 4
51Arcos Apartments (previously
"Sarasota Flats")
Residential
Mixed Use
Temp. CO
Issued
1401 Fruitville Rd (N side of
Fruitville, between Central and
Lemon Avenues)
Framework Group,
LLC
Charlan Brock Assoc.
(Maitland, FL)$30.0 3,700 228 5
52Artisan on Main "aka 41 N
School Ave"Residential
Under
Construct
Block bounded by Fruitville Rd to
the north, School Ave to the
east, Main St to the south, and
Audubon Place to the west
ICON Residential,
Tampa, FL
ROJO Architecture
(Tampa, FL)$5.1 37 3
53 BOLD LoftsResidential
Mixed Use
Under
Construct
1659 2nd St (N side of 2nd St
between Orange Ave and
Goodrich)
Biter Idea Vault HOYT Architects $14.5 6,271 97 5
IN CONSTRUCTIONIN CONSTRUCTION
9 of 24
On
MapProject Type Status Location Developer Architect
Cost
(Millions)
Comm.
Sq FtApts
Condo/
Townhm
Hotel
RmsFlrs
54 BLVD SarasotaResidential
Mixed Use
Under
Construct
SE corner of Blvd of the Arts and
Tamiami Trail, AND, NE corner
of 5th St and Tamiami Trail
Core DevelopmentStantec Architecture,
Inc. (Orlando, FL)$69.0 17,625 49 18
55 Church of the Redeemer ReligiousUnder
Construct
222 S Palm Avenue (between
McAnsh and Ringling Blvd)
Church of the
Redeemer, IncAPEX-Studio Suarez $4.3 3
56 The Courtyard at Citrus Phase I ResidentialTemp. CO
Issued
505 N Orange Ave (East side of
Orange Ave, just north of Citrus
Square)
MBFC LLC HOYT Architects $1.9 5,700 10 4
57 Enclave at Laurel Park ResidentialUnder
Construct
500 Laurel Park Drive (West of
Washington Blvd, on South side
of Laurel St)
CND-Laurel Park LLC
(Weekly Homes,
Houston, TX)
C. Alan Anderson $4.3 17 4
58 The Grande (aka Quay Block 6)Residential
Mixed Use
Under
Construct
Within the Quay Site (333 N.
Tamiami Trail), on 'Block 6' (the
SW corner of the site)
Quay Venture, LLCSB Architects (Coral
Gables, FL)$90.0 9,500 72 18
59Laurel Townhomes (previously
"Hudson Commons")Residential
Under
ConstructAlderman St and Rowe Place Gulfside Homes TBD $0.9 7 3
60 The MarkResidential
Mixed Use
Under
Construct
1400 State Street (block
bounded by Pineapple Avenue to
the west and Lemon Avenue to
the east, and located south of
Kolter Group HOYT Architects $70.0 46,000 157 11
61 Miss Susie's Newtown Kitchen CommercialUnder
Construct
1741 Dr. Martin Luther King, Jr.
Way (3 Blocks east of Orange
Ave)
TableSeide
Restaurant GroupHOYT Architects $0.2 2,400 1
62 The Pearl ResidentialUnder
Construct
609 Golden Gate Point (east
side of interior portion of Point)
Golden Gate Point
Ventures, LLCHOYT Architects $6.0 8 5
63 The Pines RenovationResidential
Renovation
Temp. CO
Issued
1501 N Orange Ave (West side
of Orange, North of 12th St)
The Pines of
Sarasota, Inc.
Harvard Jolly
Architects$3.1 1
64RCAD Post Production - Sound
Stage ComplexEducational
Temp. CO
Issued
NE corner of Dr. Martin Luther
King, Jr. Way and Central Ave
Ringling College of Art
and Design, Inc.DSDG Architects $8.2 1
65 RCAD Student Housing EducationalTemp. CO
Issued
2715 S. Riverside Drive (NW
corner of Martin Luther King, Jr.
Way, and Central)
Ringling College of Art
and Design, Inc.
Ayers Saint Cross
Architects (Baltimore,
MD)
$2.0 3
66 RCAD Visual Arts Center EducationalTemp. CO
Issued
2400 N Tamiami Trail (NE
corner of Tamiami Trail and Dr.
Martin Luther King, Jr. Way
Ringling College of Art
and Design, Inc.
Sweet Sparkman
Architects$8.6 3
67 Regions Bank CommercialUnder
Construct
4034 S Tamiami Trail (W side if
Tamiami Trail, 2 blocks south of
Bee Ridge)
Regions BankInterplan, LLC
(Orlando, FL)$1.3 2,645 1
68Renaissance Phases I, II, III
(previously "Valencia at
Rosemary Place")
ResidentialUnder
Construct
West side of Cocoanut Ave,
north of Boulevard of the ArtsIcon Residential BDG Architects $6.0 30 3
69Ringling Blvd Mixed Use
Apartments
Residential
Mixed Use
Under
Construct
2260 Ringling Blvd (the previous
site of the Ringling Shopping
Center)
The Richman Group
of Florida (West Palm
Beach, FL)
Humphreys and
Partners (Maitland,
FL)
$22.4 36,849 222 4
70 Risdon on 5thResidential
Mixed Use
Under
Construct
1350 5th St (5th St west of
Central Ave and east of Florida
Ave)
Steven Bradley,
Risdon Group
Halflants + Pichette
Studio for Modern
Architecture
$6.1 7,000 22 5
71 The Sarasota Modern HotelTemp. CO
Issued
1242 Blvd of the Arts (Southwest
corner of Cocoanut and Blvd of
the Arts)
Cocoanut Arts West,
LLC (Sarasota, FL)HOYT Architects $17.0 3,500 81 5
727 One One Palm (previously
"Azure on Palm")Residential
Under
Construct
711 S Palm Ave (SE corner of
Alderman St and Palm Avenue)
Seaward
DevelopmentDSDG Architects $8.1 16 5
73 SOAR After School EducationalUnder
Construct
2731 N Links Ave (Just north of
Dr. MLK Way)
Greater Hurst Chapel -
AME Church
Sweet Sparkman
Architects$0.5 1
74St. Armand's Circle Public
Parking Garage
Parking
Garage
Temp. CO
Issued73 N Adams Drive City of Sarasota
Jonathon Parks/
Solstice Planning and
Architecture
$12.0 4
75 Starbucks North CommercialUnder
Construct
2455 N Tamiami Trail (One
block south of Indian Beach
Drive on US 41)
Benderson
Development
Design Forum
Architects (Cincinnati,
OH)
$0.7 2,200 1
76 Vanguard Lofts ResidentialUnder
Construct
1343 4th St (4th St just west of
Central)
Tetra Terra
Development
Halflants + Pichette
Studio for Modern
Architecture
$2.4 6 4
77 ZahradaResidential
Mixed Use
Under
Construct
1542 4th St (N side of 4th St
between Lemon and Orange
Avenues)
Dunn Hospitality
Group (Evansville,
Indiana)
Halflants + Pichette
Studio for Modern
Architecture
$4.8 5,562 6 3
On
MapProject Type Status Location Developer Architect
Cost
(Millions)
Comm.
Sq FtApts
Condo/
Townhm
Hotel
RmsFlrs
78Art Ovation Hotel (previously
"Hotel Sarasota")Hotel
Project
Complete
50 Cocoanut Ave (NE corner of
Palm Avenue and Cocoanut
Avenue)
Palm Avenue
Hospitality Holdings
LLC (Hollywood, FL)
Jonathon Parks/
Solstice Planning and
Architecture
$13.0 164 7
79Centerplex (Previously "Sabal
Palm")Commercial
Project
Complete
1950 Ringling Blvd (wedge -
shaped parcel between Ringling
and Golf, north of Osprey Ave)
Mark Kauffman APEX-Studio Suarez $6.5 4
COMPLETED IN LAST FOUR QUARTERSCOMPLETED IN LAST FOUR QUARTERS
10 of 24
Q1 2019 DEVELOPMENT REPORT SUMMARIES
On
MapProject Type Status Location Developer Architect
Cost
(Millions)
Comm.
Sq FtApts
Condo/
Townhm
Hotel
RmsFlrs
80 Elan Rosemary Apartments ResidentialProject
Complete
710 N Lemon Ave (Northeast
corner of Boulevard of the Arts
and Lemon Ave)
Greystar GB II, LLCMeeks & Partners
(Houston, TX)$33.7 286 4
81 Embassy Suites & Spa HotelProject
Complete
204 N Tamiami Trail (NE corner
of 2nd Street and Tamiami Trail)
JEBCO Ventures,
Hotel Paradise
Sarasota LLC
Parker Walter Group $25.0 4,000 180 18
82Plymouth Harbor Northwest
Garden BuildingResidential
Project
Complete
700 John Ringling Blvd (on Coon
Key)Plymouth Harbor Inc.
THW Designs
(Atlanta, GA)$19.7 12 4
83 Sarasota Times BuildingCommercial
Renovation
Project
Complete
1216 1st St (between Tamiami
Trail and Cocoanut Ave)
Ataraxia LLC
(Nokomis, FL)
Design Concepts
(Tampa, FL)$1.2 4
84Sarasota Memorial Parking
Garage
Parking
Garage
Project
Complete
NE corner of Arlington St and
Osprey Ave
Sarasota County
Public Hospital Board
Gresham Smith and
Partners (Tampa, FL)$7.8 5
StatusCommercial
Space (sqft)
Quantity of
Apartments
Quantity of Residential Units
(Condos or Townhomes)
Quantity of
Hotel Rooms
In Development 585,645 583 1,331 736
Under Construction 158,952 547 517 217
Project Completed 4,000 286 12 344
Grand Total 748,597 1,416 1,860 1,297
Increase in Citywide Inventory (By Status)
Citywide Summary of Project Status #
In Development 48
In Development (No application/permit) 11
Dev App Pending 18
Dev App Approved 7
Foundation Permit Pending 1
Construct Permit Pending 8
Found. Permit Issued 1
Construct Permit Issued 1
Site Work In Progress 1
Under Construction 29
Under Construct. 21
Temp. CO Issued 8
Project Completed 7
Project Complete within last 12 months 7
Grand Total 84
Development Type (Citywide) #
Residential 23
Residential Mixed Use 20
Commercial 14
Hotel 6
Educational 5
Commercial Renovation 3
Medical/Hospital 3
Parking Garage 2
Religious 2
TBD 2
Hotel Renovation 1
Industrial 1
Other 1
Residential Renovation 1
Grand Total 84All values reflect data attributable to the period between Dec 1, 2018 and April 1,
2019, as identified by the City of Sarasota Development Services Department, and
the City of Sarasota Office of Economic Development.
11 of 24
332 COCANUT The southeast corner of Cocoanut and 4th Street will be the site of a mixed use residential development that will include a 5-story structure with 36 single family attached dwelling units, and 9,151 sf of commercial space (6 commercial units: 8,326 sf of office space, and an approx. 825 sf coffee shop). The project has received Administrative Site Plan approval from the City of Sarasota, and has submitted an application to begin construction. Demolition of the existing two-story office building took place in early 2019.
430 KUMQUAT CT The southeast corner of Cocoanut and 4th Street will be the site of a mixed use residential development that will include a 5-story structure with 36 single family attached dwelling units, and 9,151 sf of commercial space (6 commercial units: 8,326 sf of office space, and an approx. 825 sf coffee shop). The project has received Administrative Site Plan approval from the City of Sarasota, and has submitted an application to begin construction.
2
AIRPORT HOTEL Phase II An additional hotel is being proposed for construction by the Sarasota Manatee Airport Authority. Located diagonally from 'Airport Hotel Phase I' the proposal would result in a 5 story hotel replacing what is current vacant land, adjacent to the University Blvd entrance into the Sarasota Manatee International Airport. Plans for the hotel (including a request to build 136 guest rooms) will be considered by the City Commission in Spring 2019.
ALVIN’S ISLAND Renovation of the existing Alvin's Island retail store will result in a renovated first-floor retail space, and an expanded and renovated second level that will accommodate a 175-seat indoor/outdoor restaurant.
4
AMARYLLIS PARK PLACE Amaryllis Park Place will transform the western 3.92 acres (between Orange Ave and Gregg St) of the 18.4 acre Housing Authority subdivision by replacing 12 buildings built between 1955 and 1975 (containing 60 living units), with one three story building containing 84 residential units, on-site parking, landscaping, storm water-retention features, and on-site amenities. The Site Plan was approved by the City Commission in August 2018, and a Permit application for demolition of the existing structures has been submitted.
5 6
3
IN DEVELOPMENT
THE AUTEUR The "Auteur" will reinvent the
eastern edge of the Hyatt Hotel and transform an undeveloped 1.23 acre parcel of land into an 18-story mixed use building along Boulevard of the Arts. The structure will include 56 residential units, almost 10,000 s.f. of commercial space, and 284 parking spaces. Included in the development plans will be an alley vacation to allow construction of part of the project above the alley (a public easement will be established for continued alley access).
6
1
12 of 24
THE COLLECTION The 1925 residence at 1335 2nd St is currently in use as a real estate office, but will be redeveloped into 12-unit, 10 story residential condominium called "The Collection". The City is currently reviewing a request for Administrative Site Plan approval as well as application for a Building Permit.
CIRCLE K The northwest corner of the Sarasota Kennel Club's parking lot may be transformed into a 4,500 sf Circle K with 10 gas pumps. Approx. 138 existing Kennel Club parking spaces will be removed to allow for the proposed redevelopment, and the Gas Station/Convenience Store will establish new parking for customers.
THE BEACON 0.12 acres of vacant land zoned
Downtown Core may be redeveloped as a residential structure containing six dwelling units in seven stories, called "The Beacon". The project site is on the north side of 2nd Street, just east of the newly constructed Embassy Suites hotel. Developers indicate a summer 2019 construction date.
THE BAY Phase 1 of The Bay's three-phases has now been approved by the City of Sarasota as part of a comprehensive community-created master plan for 53 publicly-owned waterfront acres. Phase 1 will include optimizing the 10 southernmost acres of the Bay, including removing the 'G Wiz' building (Spring 2019), creating two public piers, establishing food and beverage services, and adding shade structures and other outdoor amenities to encourage recreational use by the public. The City intends to partner with The Bay Conservancy, who will work to realize the Phase I improvements before the end of 2020, at an estimated cost of $15 Million.
BATH & RACQUET
RESIDENTIAL The Bath and Racquet Fitness Club has proposed a plan to consolidate surface parking and renovate existing buildings and amenities on their site. The proposed Club renovations and property reorganization would create additional space on which would be constructed eight residential buildings, containing a total of 207 dwelling units, (27 units will meet the criteria for 'affordable housing'), and varying in height (3,4,5, and 7 stories). The Club's 13.46 acre parcels will need to be rezoned to allow residential uses, and the rezoning process and associated Site Plan approvals are progressing through the City's review processes.
8
10
BAYSIDE CLUB Phase 2 of Cityside will
redevelop 3.61 acres located north of Cityside Phase I, providing 253 living spaces (a mix of rental units and condominiums) and approximately 9,988 sf of commercial space. The Site Plan received City of Sarasota approval in 2017 and subsequently received additional approvals in late 2018 for adjustments and amendments to modify the building proportions and frontage, the amount of habitable space, and to increase the commercial square footage. Design revisions are still being submitted and administrative review continues as of March 2019.
9
11 12
7
13 of 24
THE DEMARCAY The DeMarcay is planned as an adaptive reuse of the historic DeMarcay Hotel façade, combined with 18 stories of new construction. The DeMarcay will include 39 residential units and 2,400 sq. ft. of retail space. Construction is slated to start in summer of 2019, with a move in date of January 2021.
EVOLUTION The ten northernmost parcels within the central portion of Golden Gate Pt were previously planned (in 2016) to become ten individual townhomes, known collectively as the Allure Townhomes. The parcels have now been re-platted to allow for future development in the form of individual multi-family structures. 'Evolution' is proposed as the first structure to be developed: A 9-story, 20-unit condominium including 46 ground level parking spaces. The Evolution received development approval in November 2018, and will now apply for a construction permit.
EPOCH The Epoch will replace the existing 5-story Versailles Condominium (built 1974) with an 18-story, 23 unit condominium. The proposed Site Plan is currently being reviewed for concurrency with the City's design and administrative codes, and has applied for a building permit. Occupancy of the new residential tower is slated for 2021.
EAST AND FRUITVILLE CMRCL Three parcels have been combined to create a 0.69 acre site for a 7,000 s.f. retail development referred to as East and Fruitville Commercial. The project will be divided into five connected retail spaces and 27 on-site parking spaces. The site plan and associated adjustments were approved in 2017. A permit for construction has not been requested yet.
COURTYWARD AT CITRUS Ph II Phase II of the Courtyard at Citrus Square will extend the Citrus Square and Citrus Courtyard further north, to the edge of Boulevard of the Arts. The project is currently pursuing a foundation permit while Phase I is nearing completion. Phase II will add another 6,300 sf of commercial space, with 18 residential units above.
COUNTY CHILLED WATER PLANT Sarasota County is proposing to construct a new Downtown Cooling Plant, to be located adjacent to the County's Public Parking Garage at the southwest corner of School Avenue and Ringling Blvd. The Chilled Water Plant will contain three chillers, four cooling tower cells, ice storage tanks, and 350 sf of maintenance office and restroom space. The Chiller Plant will be built in place of the surface parking lot currently located to the east of the County's parking garage, and containing 41 parking spaces.
16
17
18
13 14 15
14 of 24
4TH AND COCOANUT Site plan approval was received in February of 2017 to allow for redevelopment of the 1 acre site located at the northeast corner of Cocoanut Ave and 4th St into a single 5-story building with 61 apartments and 2,820 s.f. of retail space. A construction permit was requested in March 2019 and approval is currently pending.
FRUITVILLE PLAZA Fruitville Plaza will transform four vacant parcels on the north side of Fruitville Road, and four adjacent parcels on the south side of 4th Street, into a 1.45 acre mixed-use residential development. The project will begin by demolishing nine existing residential units which will allow for the creation of a three story office building fronting on Fruitville Road, and four residential units fronting on 4th Street. The proposed site plan meets the requirements for a property zoned 'Downtown Edge', and falls within the zoning overlay known as the Fruitville Gateway Corridor Overlay District.
HUMANE SOCIETY The Humane Society of Sarasota
currently operates a not-for-profit animal care and adoption center in the industrial area of 15th Street, near Lime Avenue. The organization will undertake a comprehensive redevelopment of the 2.7 acre property in order to renew outdated facilities, and construct new facilities. Demolishing 10,530 sf of existing buildings and constructing a total of 19,965 sf (including new kennels, welcome center, adoption areas, clinic, multi-purpose areas, and future-feline spaces) may be accomplished in multiple phases depending on continued community-fund raising efforts.
22
IMECA LUMBER & HARDWARE Redevelopment of this Newtown area 1.03 acre vacant parcel was approved in November 2018, including a successful rezone from 'Office Regional' to 'Commercial General' to allow the construction of a 9,425 s.f. hardware and home improvements store. The project is currently progressing through the building permit process.
23 24
SARASOTA FORD EXPANSION A Site Plan is being developed that may transform the City block between Washington Blvd and AB Smith Park. Six parcels currently containing residential and commercial buildings may be demolished to create a two-phased redevelopment project. Phase I is proposed to include the construction of a Sarasota Ford Automobile Sales Display Lot and 'temporary' sales office. Phase II would replace the Phase I components with a new 1-2 story commercial liner building wrapped around the north, west, and south faces of a multi-story garage (to be used for Sarasota Ford vehicle storage and display).
19 FOUR POINTS BY
SHERATON The Baymont Inn (currently 99 hotel rooms) will be renovated to add height to the western building (from 3 stories to 5) and the northern building (from 2 stories to 3). The exterior walkways will be converted to interior hallways, and the buildings will be connected with a central lobby space, however the total number of hotel rooms will decrease by 3, for 96 rooms total. The Inn will be operated as a Four Points by Sheraton. The project received the approval of the City Commission in March 2018. No construction permit has been applied for at this time.
20 21
15 of 24
PINES EXPANSION AND
RENOVATION In 2018 the Pines undertook improvements to their campus that resulted in a new arrival port cochere, as well as interior improvements to the residential facilities. Additional transformations are now planned as a result of a generous contribution from Sarasota's Esther and Harold Mertz Foundation (2019) that will allow for the creation of a two-story building to expand the skilled nursing facility by 90 beds, as well as replace two existing child care facilities with a consolidated Child Care and Learning Center. A new kitchen, laundry room, theatre, campus entrance, and chapel are also planned as part of the campus' transformation. All improvements are estimated for completion by 2022.
PAYNE PARK VILLAGE The Payne Park Village Development will provide 135 attached and detached single-family homes on the currently vacant 8.68 acre site located just east of Payne Park. Phase I of the Village will construct the first 87 homes on the southern portion of the site. The Subdivision Plan has been approved by the City, and a Foundation Permit is currently pending to begin site preparations.
PALSAR While no development has been formally proposed, Palsar's future development location includes what is presently nine parcels, bisected by an alley (six parcels on the north of the alley, and three parcels on the south). The Developer has completed a rezoning process to ensure that all the individual parcels share the same zoning designation, and will be pursuing a partial alley vacation.
NORTH TRAIL APTS Tembo Enterprises proposes to develop 1.4 acres on North Tamiami Trail into an apartment complex. 2413 and 2433 N Tamiami Trail currently contain seven unoccupied structures, four of which will be demolished, and three will be renovated. The future apartment complex is currently expected to include 46 units, and will be located adjacent to the Ringling College of Art and Design, and just south of the new Starbucks Coffee (opening 2019). The apartment complex plan is current progressing through the City's Development Review Committee.
MYRTLE VILLAGE
STUDENT HOUSING
New multi-family housing is being proposed west of Booker High School in the form of "Myrtle Village Student Housing". Two parcels currently containing one single family home and a 9-unit multi-family complex will be combined as one 0.97 acre project site and will be seeking rezoning to 'RMF-4' (Residential Multi Family-4). Pending approvals, the single family residence will be demolished, and a new three-story building with nine apartments will be added, resulting in a total of 16 apartments on site.
LOFTS ON LEMON Three vacant acres of land on Lemon Avenue will be redeveloped into 130 apartments aimed at helping local professionals by providing 80 units of affordable housing and 50 units of workforce housing. The project will be carried out by the Sarasota Housing Authority, and development partners Gardner Capital, and Duvernay and Brooks. Significant contributions from the Sarasota-based Barancik Foundation will allow for designation of a portion of the residential units to provide specific housing accommodations for Sarasota teachers and other providers of critical services, such as nurses and emergency responders. The 5-story building project looks to break ground in mid-2019, and anticipates a future 'Phase II' taking place on the site.
28 29 30
25 26 27
16 of 24
SANDCASTLE RESORT
The 6.1 acre beachfront site on Lido Key has now been re-zoned (from Residential to Waterfront Resort) to allow the continued use of the site as a beachfront hotel, and has received required Site-Plan approvals, and sea-wall restoration approval. Future demolition of the existing 176-room Sandcastle Resort (previously the Helmsley Sandcastle) will allow for creation of a 304-room modern resort hotel (two towers of eight and nine stories) including restaurants, two ballrooms, meeting space, and two garage levels of parking (601 spaces).
RESIDENCE INN Ten parcels just north of Fruitville Road at East Ave may be combined to create a Residence Inn. The Residence Inn will offer 121 hotel rooms, two residential dwelling units, and hotel conference rooms. The 1.98 acre site will have 121 ground level parking spaces, and will meet a requirement for residential frontage on 4th Street.
RCAD DORMITORY The newest student housing constructed on Ringling College's campus will take place at East Tamiami Circle and Greensboro Lane, replacing three existing college buildings with a 74,487 s.f. dormitory facility that will house 269 first-year art and design students in approx. 75 living units. The building, which will be constructed within the Ringling Overlay District, will be 5 stories, with a roof height of approximately 56 feet, and is expected to be open for incoming students in Fall 2020. A building permit is currently pending.
QUARRY DIRECT Two parcels on the east side of US 301 may be redeveloped into a single story structure for the sale and storage of stone products. The new 10,220 sf structure (including approximately 1,000 sf of retail space and 9,220 sf of storage space) would replace the existing 500 sf building and on-site detached carport. Site improvements would include 10 parking spaces, and vehicular entrances off of 28th Street and 29th Street.
PREMIER ON 5TH In early development is a residential building on the north side of 5th Street, one block west of Lemon Ave, known as Premier on 5th. The 5-story residential building will potentially include 7 condominiums with private terraces, and shared common area. A ground floor parking garage will provide each unit with their own parking.
34 35
36
31 32 QUAY SARASOTA The City of Sarasota has approved a Development Agreement for the 14.69 acre "Quay Sarasota" site that allows redevelopment within the parcel boundaries in nine 'sections' - for a total of (up to) 695 residences, 175 hotel rooms, 189,050 s.f. of retail, and nearly 39,000 s.f. of office space, in buildings with a maximum of 18 stories. Additional improvements will include renovation of the historic Belle Haven Hotel, completion of a section of the City's public Multi-Use Recreational Trail (MURT), and improvements to the right-of-way on Blvd of the Arts, and on US 41. A permit for $1.7M of site work has been issued, and will include underground utilities, storm, sanitary, and potable water, pavement, curb, base, and asphalt work. Permits for improvements to Boulevard of the Arts and the future MURT Trail are currently pending.
33
17 of 24
THE STRAND The Strand was originally approved for redevelopment of a 9.5 acre site (the old 'Whitaker Bayou Yacht Club') into three 5-story residential condominium buildings with waterfront access, and subsequently received approval in June 2018 to reduce the number of buildings by one. A permit to begin construction activities is currently pending.
SOUTH SHORE CHURCH South Shore Community Church would like to add 2,905 additional square feet of building area to their 2.9 acre site which fronts the east side of Tuttle Avenue, the south side of Arlington Street, and the north side of Hillview Street. The existing Church structures (built 1956 and 1972) will be expanded to include a new foyer (670 sf), restrooms (1,625 sf), and a multi-purpose room (610 sf).
SMH ONCOLOGY TOWER As part of a series of facility developments to address regional cancer care, a 9-story, 743-bed Surgical Oncology Tower will be built at the southwest corner of US 41 and Waldamere, on the Sarasota Memorial Hospital's main campus. The 170,000 s.f. treatment center is expected to cost approximately $139 Million, with an opening date anticipated for 2021. Development of the project includes a street vacation, utility easement vacations, and the associated Plan Reviews and Community Workshops.
SKEA Enterprises proposes to construct a three-story medical office building on S. Tamiami Trail in place of an aging single story office structure. The future Medical office building is estimated as 7,267 sf, and the 0.35 acre site will also accommodate 32 vehicle parking spaces. The development proposal is progressing through the City's Development Review Committee.
SIX88 The currently vacant 29,139 sf waterfront parcel will be redeveloped with the construction of a 15-unit, 9 story residential condominium (8 stories above one floor of parking for 42 vehicles). Development application is progressing through the City's Development Review Committee, with Planning Board approval pending.
SELBY BOTANICAL GARDENS Marie Selby Botanical Gardens (Est. 1975) is implementing a three-part, 10-year strategic plan to sustain their historic 14.73 acre campus which currently houses botanical gardens, research facilities, visitor areas, and historic buildings. Phase 1 plans introduce a new welcome center and research building, as well as a structure for on-site parking that will incorporate retail and restaurant space. The new facilities will echo the sustainable mission of the Gardens not only in their construction - but in their operation; the rooftop restaurant will prepare edible plants and foods grown on site, be powered with a net-positive solar array, and be wrapped in 'living walls' of plant material.
40 41 42
37 38
39
18 of 24
WHITAKER LOFTS New development along the North Trail is taking shape in the form of Whitaker Lofts; a development collaboration from the Studio for Modern Architecture. The mixed use residential structure will benefit from the intersection conversion taking place at 14th and US 41 (construction of a modern roundabout including landscaping and public art) as well as proximity to the Sarasota Bay and walking distance to multiple public parks. Early plans suggest the project will include 21 two-story condominium residences over street-level retail.
WAWA Nine parcels located between Fruitville Rd and 2nd St (west of Lime) within the Fruitville Gateway Corridor Overlay District will be combined to locate a WaWa gas and convenience store. The 1.82 acre site will include 5,636 s.f. of convenience area and 6 gas pumps and is currently progressing through the City's development review process, and will be reviewed by the Planning Board in April 2019.
TOWN AND COUNTRY The proposed redevelopment at the northwest corner of Beneva Road and Tuttle will replace an existing structure (previously a grocery store) with a new 54,000 s.f. structure that will use the same footprint as the previous store, and will include three independent tenant spaces, with a drive thru on the southside of the building. An additional 5,000 s.f. retail structure will also be built within the project boundaries, and both structures are proposed to meet existing standards and requirements for architectural design, setbacks, lighting, and other zoning code restrictions specific to the commercial parcel.
TOASTED MANGO CAFE A vacant parcel at the northeast corner of Cocoanut Avenue and 10th Street may soon be the location for a new 3,000 sf Toasted Mango Café. Additionally, two parcels to the west may be redeveloped to allow for a 9-10,000 sf building (future uses to be determined), which would replace a 18,000 sf warehouse built in 1965.
43 44 45
ZAHRADA II Adjacent to the Zahrada (currently under construction at 1542 4th Street) will be the "Zahrada II". Proposed as an 18-unit, 5-story residential condominium with ground floor commercial space, Zahrada II will continue to activate 4th Street by introducing not only retail activity to the pedestrian level but vertical interest, through the use of translucent terraces, and visible staircase landings. The Zahrada (Czech for 'Garden'), and Zahrada II will both provide residential and commercial infill to the Rosemary District, activating 0.24 acres of land that has remained vacant for more than a decade.
IN CONSTRUCTION
WESTCOAST BLACK THEATRE The 1926 Binz building at the corner of Orange Avenue and 10th Street is home to the Westcoast Black Theatre Troupe. The Troupe's continued growth has lead to a major renovation of their facility, and an expansion of their footprint. The historic Binz building will undertake two phases of improvements which will include new administrative areas, education and outreach offices, a weekday box office, a library, several multi-purpose rooms, and a 6,000 sf garden. Renovations began in late 2017 and the first phase was completed in June 2018. A construction permit was issued in January 2019 for the second phase of improvements.
46 47 48
19 of 24
BOLD LOFTS The 5-story BOLD Lofts are being constructed next to the 4-story BOLD Building on 2nd Street between Goodrich and Adelia. The Lofts will offer 97 residential apartments, 6,271 sf of office space, and 247 parking spaces. Construction began in Spring of 2017, and the building looks to open in Spring of 2019.
BLVD SARASOTA The Boulevard Sarasota ("BLVD") is a multi-phased mixed use development that will provide a total of 49 residential units, approx. 10,918 sf of restaurant, and 6,707 sf of retail/office in an 18-story structure. The project includes a Major Encroachment Agreement, allowing the building to built across the 5th Way alley while leaving public alley access. Construction began in September 2018 and completion is estimated for late 2019.
ARTISAN ON MAIN The Artisan on Main will transform 37 individual parcels into a residential subdivision containing seven three-story buildings, for a total of 37 living units (averaging approx. 2,100 s.f. each). The project began construction on three of the seven buildings in March 2017, with one reaching completion in February 2019, and two still under construction.
ARCOS APARTMENTS Arcos Apartments has converted three acres of vacant land bordering Fruitville Rd into a five story development offering 228 apartments including studios, 1, 2, and 3 bedrooms. A 406-car parking garage is hidden in the building's center, and surrounded by balconied apartments. The project will offer 3,700 sf of commercial street front space, and a Temporary Certificate of Occupancy has been issued, with final construction efforts taking place through Spring 2019.
ARBOR VILLAGE Arbor Village will redevelop 3.5 vacant acres into a mixed-use residential development consisting of 80 multi-family apartments within two buildings, and one commercial office space (10,000 sf) with two units. The project is a partnership between the City and County of Sarasota's Office of Housing and Community Development, CASL (Community Assisted and Supported Living), and the Tampa-based affordable housing developer Blue Sky Communities. Construction began in December of 2018.
AIRPORT HOTEL PHASE 1 A 5-story hotel is being constructed on vacant land owned by the Sarasota Manatee Airport Authority, and will contain 136 hotel rooms. The Airport Hotel at 965 University Parkway is "Phase 1" of a two-phase project (the second phase, located at 995 University Parkway, is progressing through the City's Development approval processes). Construction on Phase 1 began in October 2018.
53 54
51 50 49
52
IN CONSTRUCTION
20 of 24
LAUREL TOWNHOMES Laurel Townhomes will combine four parcels along Hudson Bayou to construct seven townhomes with two and three stories, for a total of 7 dwelling units. The first building of two is under construction, and will contain 4 living units. A second building containing three units (along Alderman) will follow in the future.
ENCLAVE AT LAUREL PARK The Enclave at Laurel Park replaces 17 individual parcels and a portion of Cherry Ln (totaling 0.8 acres) with a unified subdivision that will include seven buildings ranging from two to four stories, made up of 17 single-family units (3 detached, 14 attached), each with a two-car garage. Four of the seven buildings are now under construction, and a four-story model home was opened in February 2019.
CHURCH OF THE REDEEMER Palm Avenue's Episcopalian Church of the Redeemer (built 1952) will add a 14,200 sf three-story addition on its 1.26 acre site, to be used for classrooms, administrative offices, and event space. The project includes off-site parking agreements, and agreements to encroach into the right-of-way of Gulfstream Ave and McAnsh Square. Construction began in August 2018.
THE COURTYARD AT CITRUS Citrus Square (completed 2009) is extended to the north with The Courtyard at Citrus. Phase I of the Courtyard received a Temporary Certificate of Occupancy in February 2019, providing 10 residential units and 6,300 sf of commercial space fronting Orange Avenue. The building varies between heights of three, and four stories.
THE GRANDE The first piece in redeveloping the 14.69 acre Quay site will be The Grande; an 18-story mixed use development on 1.9 acres that will include 72 condominiums, two commercial units (approx. 9,500 s.f. of restaurant space), and a 105,520 s.f. parking garage for 159 vehicles. The Grande will be linked to the Ritz-Carlton tower (to the south) by an elevated pedestrian walkway, and is located in the southwest corner of the Quay site - also known as "Block 6 of the Quay", and often as "The Ritz Carlton Residences". Construction began in December 2018.
59
THE MARK Construction of The Mark will complete redevelopment efforts originally begun in 2007 as 'Pineapple Square'. The Mark's 11 story mixed-use residential building will include 157 condominium units, 35,000 s.f. of retail, 11,000 s.f. of office, and on-site structured parking. The Mark will be partially built over a vacated portion of State Street between Pineapple and Lemon Avenues. Completion is currently estimated for Fall of 2019.
60
57 56 55
58
21 of 24
RCAD POST PRODUCTION Ringling College of Art and Design's newest facility provides students and professionals the ability to produce professional content right on campus. Three structures make up the Post Production /Sound Stage complex - providing five separate sound stages, editing bays, mixing rooms, screening room, and support spaces (dressing rooms, green rooms, and offices). Studio A (1330 MLK) and Studio B (1370 MLK) opened in Fall of 2017, and the main facility (1300 Dr. MLK) received a Temporary Certificate of Occupancy in November 2018.
MISS SUSIE’S NEWTOWN
KITCHEN Dr. Martin Luther King, Jr. Way's newest redevelopment will recreate the iconic Sarasota location known as Miss Susie's into a modern restaurant: Miss Susie's Newtown Kitchen. The location will ultimately train and employ culinary staff from the surrounding neighborhood. Construction of the one-story restaurant, kitchen, and outdoor dining area began in July 2018, and continued progress is dependent upon additional fundraising efforts.
THE PEARL The Pearl on Golden Gate Point will be a five story residential building with 8 units, each offering 2,720 s.f., and ground floor structured parking. Construction began in early 2018 on the art-deco inspired tower, which is located on the interior of the Golden Gate peninsula.
THE PINES RENOVATION The Pines of Sarasota received a building permit in May 2018 and renovations to the Senior Care facilities on Orange Avenue began in June 2018. The improvements include modernization of residents' rooms, a new Porte cochere, refurnished public areas, and a new activities room. A Temporary Certificate of Occupancy was issued for the project in March 2019.
RCAD STUDENT HOUSING Riverside Drive north of Dr. Martin Luther King, Jr. Way, has received significant right-of-way improvements as part of the completion of Ringling College of Art and Designs' new 3-story student housing building. The building will house as many as 185 students, and includes a pedestrian bridge that crosses Hudson Bayou, connecting the housing directly to other parts of the campus. The facility received a Temporary Certificate of Occupancy in November 2018; A final Certificate of Occupancy is still pending.
65
RCAD VISUAL ARTS CENTER The Richard and Barbara Basch Visual Arts Center provides Ringling College of Arts and Design students with a three-story, 38,000 sf facility including classrooms, workshops, and gallery space. The building is formed with two zinc-clad structures connected by an exterior elevated breezeway, and received a Temporary Certificate of Occupancy in November 2018. A final completion certificate is still pending.
66
63 62 61
64
22 of 24
711 PALM 7 One One Palm began construction in November 2017. The 0.64 acre vacant parcel is being redeveloped into a 5-story building containing 16 condominiums and two guest suites.
THE SARASOTA MODERN The Sarasota Modern broke ground in late 2017, and was open for business in December 2018. The 81-room, 5-story, Rosemary District hotel received a Temporary Certificate of Occupancy in November 2018, with final completion still pending.
SOAR AFTER SCHOOL A 2,200 sf Starbucks Coffee is
under construction at 2455 N. Tamiami Trail. The café is replacing dilapidated motel structures, and will provide drive through service and indoor/outdoor seating.
73 STARBUCKS NORTH
A 2,200 sf Starbucks Coffee is under construction at 2455 N. Tamiami Trail. The new café building has replaced a dilapidated motel, and will provide drive through service and indoor/outdoor seating. Construction began in late October 2018.
75
ST ARMAND’S PARKING GARAGE The City and the Circle land-owners have built a 4-level public garage, including bicycle storage and public restrooms, with approx. 500 public parking spaces and 5 EV stations. Construction began in April 2018 and a TCO was issued in March 2019.
RINGLING BLVD APTS Located on the site of the former
Ringling Shopping Center the Ringling Blvd Apartments will include a 4-story multifamily building with 222 residential apartments, a business center, fitness center, and pool, and approx. 36,849 s.f. of commercial space along Ringling Blvd. Demolition of the vacant shopping center was completed in January 2019, and new construction began in March 2019.
REGIONS BANK A new 2,645 s.f. Regions Bank
branch with four drive through lanes will be constructed on the northwest corner of U.S. 41 and Glengary Street (previously the location of a Steak and Ale restaurant). The1 acre parcel has been vacant since 2008, and required vacation of a water line-easement in order to commence construction. Construction of the bank began in November 2018.
RENAISSANCE Phases I, II, III Located between the Renaissance Condominium (US41) and CitySide (Cocoanut Ave) are the two and three-story Renaissance Townhomes. The thirty townhomes were built in three phases: 12 completed in summer of 2017; 6 completed in March 2019; and the remaining 12 townhomes are nearing construction completion.
RISDON ON 5TH The Risdon on 5th is a mixed use project, combining 22 residential units on top of 6 ground-level retail spaces in the heart of the Rosemary District. Construction began on the 5 story project in March of 2018, and completion is slated for mid 2019.
71 72
69 68 67
70
74
23 of 24
ART OVATION
The 164-room hotel received a Final Certificate of Occupancy in August 2018, and includes a restaurant, lounge, rooftop pool, and a 10,000 s.f. ballroom
78
PLYMOUTH HARBOR NW BLDG The Northwest Garden Building added 12 independent living units, 31 assisted care units, and 30 memory care units to the Plymouth Harbor campus (est. 1966). Construction was completed in November 2018.
ELAN ROSEMARY APTS The four-story, 286-unit apartment complex received a final Certificate of Occupancy in January 2019.
CENTERPLEX The 4-story, 32,000 s.f. wedge-shaped building includes a drive-through bank facility, and 24,000 sf of office space. A Final Certificate of Occupancy was issued November 2, 2018.
80 79
82
SMH PARKING GARAGE Construction of the Sarasota Memorial Hospital 5-story, 600-space parking garage began in August 2018 and was fully complete as of March 2019.
SARASOTA TIMES BUILDING DE Murphy Constructors, Inc. has completed renovations to the historic 1926 4-story building known as the Sarasota Times Building. Originally the location of one of Sarasota's earliest newspapers, the building had been unoccupied since 2013. Renovations began in February 2018 and were completed in February 2019.
EMBASSY SUITES AND SPA Construction of the 18-story, 180-suite hotel commenced in early 2016, and received a final Certificate of Occupancy in December 2018.
83
81
84
VANGUARD LOFTS The four story Vanguard Lofts will provide 6 residential townhomes with separate garage and amenities to Downtown's Rosemary District. Construction began in 2015, however, a future completion date for the partially constructed building is not known.
76
ZAHRADA The Zahrada (Czech for 'garden') is a mixed-use addition to the Rosemary district—with six individual three-story condominium residences located over six retail/office suites (approx. 5,562 s.f. of commercial space) that will face onto 4th Street. Construction on the project began in February 2019.
77