Development Plan Consent Checklist Carports, …...Development Plan Consent Checklist Carports,...

12
Development Plan Consent Checklist Carports, garages, sheds and verandahs As required by Section 39 of the Development Act 1993, three copies of the following information must accompany all planning applications involving a secondary residential structure: A completed Development Application form The prescribed planning lodgement and assessment fee A signed Electricity Act Declaration form A copy of the Certificate of Title (dated no more than 3 months old or original) A scaled site plan of 1:100 (1cm=1m) or 1:200 (1cm=2m) showing: o The boundaries and dimensions of the site(s) o The approximate North point o The location of any easements located on the property (if applicable) o The location of any existing or proposed septic tank/s (if applicable) o The position and dimension of proposed structure relative to the boundaries of the site and any existing buildings o The location of all existing and proposed driveways (if applicable) relative to any street trees and other infrastructure location within Council’s road verge (i.e. stobie poles, light poles, site entry pits etc) o The location and extent of all earth works (cut and fill) and retaining walls proposed (if applicable) o The location of any regulated/significant trees within 15 metres of the proposed development, including any site works (if required) o The method(s) of stormwater disposal and detention for the site Plan view of the structure, to be drawn to a scale of not less than 1:100Elevation drawings for the dwelling/s, to be drawn to a scale of not less than 1:100 Elevation drawings for the structure, to be drawn to a scale of not less than 1:100 Colour and external finish details for the structure Please note, you will require both Planning Consent and Building Rules Consent in order to receive full Development Approval to start building. Building Rules Consent can be granted by Council or a Private Certifier. Should you wish to apply for full development approval through Council, you will be required to submit the following details for Building Rules Consent, in addition to the above list: Scaled frame plan, showing individual elements, span measurements and connection details to be drawn to a scale of not less than 1:100 o If steel framed, manufacturers design computations or specifications and span tables to the correct wind speed o If steel framed and individually designed, design computations from a structural or civil engineer o If timber framed, all timber sizes and structural timber Construction methodology to correct Standards Footing pad dimensions or connection to concrete slab details

Transcript of Development Plan Consent Checklist Carports, …...Development Plan Consent Checklist Carports,...

Page 1: Development Plan Consent Checklist Carports, …...Development Plan Consent Checklist Carports, garages, sheds and verandahs As required by Section 39 of the Development Act 1993,

Development Plan Consent Checklist Carports, garages, sheds and verandahsAs required by Section 39 of the Development Act 1993, three copies of the following information must accompany all planning applications involving a secondary residential structure:

• A completed Development Application form• The prescribed planning lodgement and assessment fee• A signed Electricity Act Declaration form• A copy of the Certificate of Title (dated no more than 3 months old or original) • A scaled site plan of 1:100 (1cm=1m) or 1:200 (1cm=2m) showing:

o The boundaries and dimensions of the site(s)o The approximate North pointo The location of any easements located on the property (if applicable) o The location of any existing or proposed septic tank/s (if applicable) o The position and dimension of proposed structure relative to the boundaries of the site and any

existing buildings o The location of all existing and proposed driveways (if applicable) relative to any street trees and

other infrastructure location within Council’s road verge (i.e. stobie poles, light poles, site entrypits etc)

o The location and extent of all earth works (cut and fill) and retaining walls proposed (if applicable)o The location of any regulated/significant trees within 15 metres of the proposed development,

including any site works (if required)o The method(s) of stormwater disposal and detention for the site

• Plan view of the structure, to be drawn to a scale of not less than 1:100Elevation drawings for thedwelling/s, to be drawn to a scale of not less than 1:100

• Elevation drawings for the structure, to be drawn to a scale of not less than 1:100 • Colour and external finish details for the structure

Please note, you will require both Planning Consent and Building Rules Consent in order to receive full Development Approval to start building. Building Rules Consent can be granted by Council or a Private Certifier.

Should you wish to apply for full development approval through Council, you will be required to submit the following details for Building Rules Consent, in addition to the above list:

• Scaled frame plan, showing individual elements, span measurements and connection details to bedrawn to a scale of not less than 1:100 o If steel framed, manufacturers design computations or specifications and span tables to the

correct wind speedo If steel framed and individually designed, design computations from a structural or civil engineero If timber framed, all timber sizes and structural timber

• Construction methodology to correct Standards • Footing pad dimensions or connection to concrete slab details

Page 2: Development Plan Consent Checklist Carports, …...Development Plan Consent Checklist Carports, garages, sheds and verandahs As required by Section 39 of the Development Act 1993,

• If the structure is to be attached to the roof frame of an existing structure, ie a dwelling, the following

details are required: o Written verification from a suitably qualified person stating that the existing roof structure is

structurally adequate to attach the new structure o Provide clarification of existing roof construction materials and general details (i.e. conventional

construction, timber, rafter size, rafter spacing and connections) o Connection detail between the two structures (i.e. rafter bracket and rafter strengthening detail,

bracket location etc.)

• Indemnity insurance certificate for domestic building work with a value exceeding $12,000. • Payment of a Construction Industry Training (CITB) levy is required for building work with a value

exceeding $15,000. Please be advised that this checklist contains the minimum information required to lodge your application, in accordance with the Development Act 1993. Should further information be required to assist in the assessment of your application, a request will be made in writing. For more information, please contact us on 08 8397 7444 or visit www.teatreegully.sa.gov.au

Page 3: Development Plan Consent Checklist Carports, …...Development Plan Consent Checklist Carports, garages, sheds and verandahs As required by Section 39 of the Development Act 1993,

Development number

Assessment number

Office use only

DEVELOPMENT APPLICATION

LOCATION OF PROPOSED DEVELOPMENT

House no Lot no Street

Suburb CT: Volume Folio

APPLICANT’S DETAILS

Name (please state name in full, eg Mr John Smith)

Address Postcode

Email Phone

Please note: the stamped plans and approval will only be sent to you as the applicant, by post or the above email. It is your responsibility to forward this information to the property owner.

CONTACT PERSON FOR FURTHER INFORMATION

Name Daytime phone

Mobile phone Email

OWNER’S DETAILS

Name Email

Address Postcode

DESCRIPTION OF PROPOSED DEVELOPMENT

LEVYHas the Construction Industry Training Fund Act 2008 levy been paid?

Yes No

DEVELOPMENT COST

$TICK ONE BOX ONLY

Combined Development (both Planning and Building

Building Rules Consent (Building only)

Development Plan Consent (Planning only)

BUILDING RULES CLASSIFICATION

Classification sought Present classification

If class 5, 6, 7, 8 or 9 classification is sought, state the proposed number of employees – Male ___________ Female ____________ If class 9a classification is sought, state the number of persons for whom accommodation is provided _________________________ If class 9b classification is sought, state the proposed number of occupants of the various spaces at the premises ________________

Council is required by the Development Act 1993 and the Regulations made under it to put on public display all documents and information lodged as part of an application for Category 2 or Category 3 developments and the public have the right (Regulation 34) to obtain copies of that material. You should assume any documents or information you lodge as part of an application which may be categorised in that way, will become public, and these documents may be available for public viewing on Council’s website.

Signature Dated

DECLARATIONI declare that the information I have provided on this application is correct to the best of my knowledge and I have the authority of any copyright holder for the public display and copying of any material I lodge.

571 Montague Road, Modbury 5092 PO Box 571, Modbury 5092 Office Hours - 8.45am to 5.00pm General Enquiries Telephone (08) 8397 7444 Fax (08) 8397 7400 Email [email protected] www.teatreegully.sa.gov.au ABN 69 488 562 969

Name (please state name in full, eg Mr John Smith)

Address Postcode

Email Licence No

BUILDER’S DETAILS

Page 4: Development Plan Consent Checklist Carports, …...Development Plan Consent Checklist Carports, garages, sheds and verandahs As required by Section 39 of the Development Act 1993,

Electricity Act Declaration Schedule 5, clause2A

To: City of Tea Tree Gully From: Location of proposed development House no: ______________ Lot no: ______________ Street: Town/Suburb: Section no (full/part): Hundred: Volume: Folio: Nature of proposed development: I being the applicant/a person acting on behalf of the applicant (delete the inapplicable statement) for the development described above declare that the proposed development will involve the construction of a building which would, if constructed in accordance with the plans submitted, not be contrary to the regulations prescribed for the purposes of section 86 of the Electricity Act 1996. I make this declaration under clause 2A(1) of Schedule 5 of the Development Regulations 2008. Signature: Date: Email address: Telephone number:

Page 5: Development Plan Consent Checklist Carports, …...Development Plan Consent Checklist Carports, garages, sheds and verandahs As required by Section 39 of the Development Act 1993,

Note 1 This declaration is only relevant to those development applications seeking authorisation for a form of development that involves the construction of a building (there is a definition of ‘building’ contained in section 4(1) of the Development Act 1993), other than where the development is limited to: a) an internal alteration of a building; or b) an alteration to the walls of a building but not so as to alter the shape of the building. Note 2 The requirements of section 86 of the Electricity Act 1996 do not apply in relation to: a) an aerial line and a fence, sign or notice that is less than 2.0m in height and is not designed for a person to stand on; or b) a service line installed specifically to supply electricity to the building or structure by the operator of the transmission or distribution network from which the electricity is being supplied. Note 3 Section 86 of the Electricity Act 1996 refers to the erection of buildings in proximity to powerlines. The regulations under this Act prescribe minimum safe clearance distances that must be complied with. Note 4 The majority of applications will not have any powerline issues, as normal residential setbacks often cause the building to comply with the prescribed powerline clearance distances. Buildings/renovations located far away from powerlines, for example towards the back of properties, will usually also comply. Particular care needs to be taken where high voltage powerlines exist; or where the development: • is on a major road; • commercial/industrial in nature; or • built to the property boundary. Note 5 An information brochure ‘Building Safety Near Powerlines’ has been prepared by the Technical Regulator to assist applicants and other interested persons. This brochure is available from council and the Office of the Technical Regulator. The brochure and other relevant information can also be found at sa.gov.au/energy/powerlinesfety Note 6 In cases where applicants have obtained written approval from the Technical Regulator to build the development specified above in its current form within the prescribed clearance distances, the applicant is able to sign the form.

Page 6: Development Plan Consent Checklist Carports, …...Development Plan Consent Checklist Carports, garages, sheds and verandahs As required by Section 39 of the Development Act 1993,

Building safely near powerlines

Office of the Technical Regulator

sa.gov.au/energysafe

Page 7: Development Plan Consent Checklist Carports, …...Development Plan Consent Checklist Carports, garages, sheds and verandahs As required by Section 39 of the Development Act 1993,

2 | Building safely near powerlines

Before you build near powerlinesBefore starting work on a building, you need to consider:

• the type of powerlines near the proposed building or structure e.g. aerial, underground, high or low voltage

• the amount of swing or sag of overhead powerlines

• the location of the building or structure in relation to the powerline – allow enough space for a safe work environment, future structures or scaffolds, and trees.

Scaffolding is considered a structure. When designing a building you should allow for the width of any scaffold you may need to erect. This is to ensure that the scaffold can be positioned in a way that legal clearance distances are met.

Safe clearance distancesMinimum safe clearance distances between buildings or structures and powerlines are set out in the Electricity (General) Regulations 2012. These distances are legal requirements and must be maintained at all times.

If a fence, sign or notice is lower than 2 metres, it may be exempt from minimum clearance distances. It must not restrict safe access to powerlines for repair and maintenance. You may need to install gates to allow trucks to access the powerlines. Always check with ElectraNet when considering fencing near transmission lines.

Locating a swimming pool under any powerline is not recommended.

The clearance distance, and how it is measured, depends on the voltage and type of powerline. Image 1 and 2 provide a general identification guide to determine the voltages of powerlines.

Transmission powerlines – 132kV or higher When building near high voltage transmission powerlines (132 kV or higher), the minimum safety clearance distance is measured horizontally from the centre line of the transmission powerline.

Table 1: Minimum safety clearance distances from the centreline of transmission powerlines

Transmission line voltage Minimum clearance

275 kV 25 metres

132kV (except single pole lines) 20 metres

132kV (single pole lines) 15 metres

Aerial distribution powerlines – 66kV or lowerClearance distances are measured from the point of maximum swing or sag of the powerlines. To determine the safe clearance distance from aerial distribution lines (66 kV or lower), refer to Table 2 and Image 4.

If you need to relocate or insulate the powerlines, the associated costs and work should be negotiated with the electricity network operator, usually SA Power Networks, before starting construction. Construction work must not proceed inside the minimum safety clearance distance until the powerlines are relocated.

Further information on powerlines and their sag and swing is available from SA Power Networks, the Office of the Technical Regulator or by visiting sa.gov.au/energysafe.

Centre-line of transmission powerline

Minimumsafety clearancedistance

Minimumsafety clearancedistance

No building or structure allowed

Image 3: Minimum safety clearance distance for transmission lines

33 kV,66 kV or132 kV

33 kV,66 kV or132 kV

33 kV or11 kV

19 kV(SWER)

Image 2: Common powerlines in South Australia

High voltage 11kV

Service line

Low voltage

Image 1: Typical powerlines in built up areas

Page 8: Development Plan Consent Checklist Carports, …...Development Plan Consent Checklist Carports, garages, sheds and verandahs As required by Section 39 of the Development Act 1993,

For more information visit sa.gov.au/energysafe | 3

The clearance distanceis measured from the point of maximum (worst case) swing or sag.

B

C

No buildings or structures allowed

No buildings or structures allowed

Roofs with a slope ofless than 45 degrees

Balcony

C

Balcony �oor

Top of hand rails

B

A

Image 4: Minimum safety clearance distances for buildings from powerlines

Table 2: Minimum safety clearance distances (in metres) from the nearest conductor at maximum swing and sag for distribution powerlines

Voltage Up to and including 1 kV

Above 1 kV Above 1 kV up to and including 33 kV

66 kV

Conductor type Insulated Bare Insulated with earthed screen

Insulated without earthed screen

Bare or covered

Bare

Dimension A – Vertically above those parts of a building or structure normally accessible to persons.

2.7 m 3.7 m 2.7 m 3.7 m 5.5 m 6.7 m

Dimension B – Vertically above those parts of a building or structure not normally accessible to persons but on which a person can stand.

0.1 m 2.7 m 2.7 m 2.7 m 4.7 m 5.5 m

Dimension C – In horizontal direction from those parts of a building or structure normally accessible to persons or that is not normally accessible to persons but on which a person can stand.

0.1 m 1.5 m 1.5 m 1.5 m 3.1 m 5.5 m

Dimension D – In any direction from those parts of a building or structure not normally accessible to persons.

0.1 m 0.6 m 0.1 m 0.6 m 2.5 m 4.5 m

Notes for Table 2• Vertical dimension A applies, for example, to balconies, terraces,

walkways, bridges and scaffolds.

• Vertical dimension B applies in relation to structures such as roofs with a slope of less than 45°, parapets wider than 0.1 metre, pergolas and carports.

• Horizontal dimension C applies to the same structures as A and B.

• Radial dimension D applies in relation to structures such as roofs with a slope of 45° or more and light poles.

• Your development must achieve either the appropriate horizontal or vertical clearance distance from the worst case position of the powerline to be compliant.

• Powerlines (particularly 19 kV SWER, 33 kV and 66 kV) can sag considerably under high temperatures and loads, and also swing when it is windy. At mid span, a powerline will swing and sag much more than in areas near the pole.

• The clearance distance is measured from the worst case swing and sag point. This may need to be calculated by SA Power Networks. SA Power Networks may charge a fee for this service.

Planning approvals and powerlinesAll development applications submitted to councils must include an Electricity Act Declaration Form, signed by the development applicant, acknowledging the development plans comply with prescribed clearance requirements.

It is the applicant’s responsibility to ensure that the requirements of the Electricity Act 1996 are being met.

The council is not obligated to check the clearance distances to powerlines in your plans. Planning and development approvals issued by a council do not mean that the building plan complies with the minimum clearance requirements prescribed by the regulations.

Page 9: Development Plan Consent Checklist Carports, …...Development Plan Consent Checklist Carports, garages, sheds and verandahs As required by Section 39 of the Development Act 1993,

Underground powerlinesBefore excavating in areas with underground powerlines, you must contact SA Power Networks to find out the exact location and the type of the underground powerline.

Dial Before You Dig (www.1100.com.au) is a referral service that can help with obtaining information on the location of underground powerlines and other services.

Minimum safety clearance distances must be met when building close to underground powerlines, as shown in image 5 and table 3.

Where it is necessary to relocate an underground powerline, the relocation work and costs must be negotiated and finalised with SA Power Networks before starting construction. Construction work must not proceed inside the minimum safety clearance distance until the powerlines are relocated

If a property is supplied from an electrical service pillar or pit, you must not construct or place anything over or too close to it. This includes structures such as garages, retaining walls or moss rocks, as they may restrict safe access to the service pit. Contact SA Power Networks for more information.

Table 3: Minimum safety clearance distances for underground powerlines

Underground powerline voltage Minimum clearance

66, 132 and 275 kV 3 metres

33 kV or less 2 metres

Permission to build inside the safe clearance zoneIn limited circumstances where it is safe to do so, the Technical Regulator has powers to approve buildings and structures within the minimum safety clearance distance.

Contact the Office of the Technical Regulator for further information.

Easements for powerlinesAn easement is a legal right of use over the land of another person. In relation to powerlines, this means that the electricity network provider has legal permission to access and maintain the infrastructure.

There are different kinds of easements on properties containing powerlines. If there is a powerline on your property, the electricity network operator may have a statutory or registered easement to access and maintain the powerline. Even if there is no statutory or registered easement on a property, the electricity network operator has the authority, at any reasonable time, to inspect the powerline and take action to prevent or minimise an electrical hazard.

Building near or on any easement should be discussed with the network operator (usually SA Power Networks).

Digging or excavating near stobie polesDigging near stobie poles and other electrical infrastructure, such as padmounted transformer boxes, could present risks to your safety and the surrounding property. You may make contact with underground cables or destabilise the pole, causing it to fall over.

If you intend to dig deeper than 30cm within 3 metres of a stobie pole, you are legally required to obtain a written permission from the electricity network operator.

It is also prohibited to alter the ground level directly under powerlines if it reduces the ground clearance to less than prescribed by the regulations.

This information is provided to offer general guidance only on building safely near powerlines, and does not purport to cover all situations, or any particular situation, or to outline a complete list of procedures that must be followed. It is not to be taken as a statement of law or legal advice, and must not be construed to waive or modify any legal obligation. The Government of South Australia will not be liable for any injury, damage or loss of any kind sustained by any person that arises directly or indirectly from reliance upon any information contained herein or source of information referred to.

May 2015

For more informationOnline: sa.gov.au/energysafeEmail: [email protected]: 08 8226 5500

Foundation

Undergroundpowerline

Minimum safety clearance distance

Image 5: Minimum safety clearance distance for electricity supplier’s underground powerlines

Page 10: Development Plan Consent Checklist Carports, …...Development Plan Consent Checklist Carports, garages, sheds and verandahs As required by Section 39 of the Development Act 1993,

CREDIT CARD AUTHORISATION

Details Amount

Lodgement fee

Planning consent fee

Building consent fee

Building staged lodgement fee

Swimming pool inspection fee

Certificate of Title fee

Agency referral fee

Public notification fee

Urban tree fund payment

Total amount

571 Montague Road, Modbury 5092 PO Box 571, Modbury 5092 Office Hours - 8.45am to 5.00pm General Enquiries Telephone (08) 8397 7444 Fax (08) 8397 7400 Email [email protected] www.teatreegully.sa.gov.au ABN 69 488 562 969 Date

PROPOSED DEVELOPMENT

Address of proposed development

Development number (if applicable)

PAYMENT

CREDIT CARD DETAILS

Card type Visa Mastercard

Card number

Cardholder name

Expiry date CCV number

Daytime telephone

Postal address

Signature Post receipt Yes No

Please forward this payment with relevant forms to the address above. For further information please contact us on 8397 7444 or visit cttg.sa.gov.au

Page 11: Development Plan Consent Checklist Carports, …...Development Plan Consent Checklist Carports, garages, sheds and verandahs As required by Section 39 of the Development Act 1993,

Development application fees Effective 1 July 2020

Lodgement fees – Building and Planning

Base lodgement fee $68.50 Staged Consent fee $68.50 Inspection fees Development costing more than $5,000 (Excluding applications solely for swimming pool, spa pool. safety barrier)

$77.00

Swimming Pool Inspection fee (Development which includes a swimming pool, spa pool or a safety barrier)

$204.00

Planning consent fees Merit Development

Development costing less than $10,000 $42.50 Development costing more than $10,000 $116.00 Development costing more than $100,000 X0.125% Referral fee $243.00 per authority Referral fee (Developments over $1,000,000) $406.00 per authority Referral fee (Developments of major environmental significance) $406.00 per authority Category 2 & Category 3 fees $116.00 Advertising Fee (Category 3) $630.00

Non-Complying Development (In addition to fees for merit development)

Lodgement (Non-Complying) $109.00 Concurrence $140.00 Development costing less than $10,000 $58.00 Development costing more than $10,000 $140.00 Development costing more than $100,000 X0.125%

Building Rules fees Class 1, 2 & 4 $3.29 Class 3, 5 & 6 $4.38 Class 7 & 8 $2.91 Class 9a & 9c $4.97 Class 9b $4.36 Class 10 $0.98 Minimum building fee $74.50 Building Rules Only fee (Additional fee for Schedule 1A applications) $56.50

Page 12: Development Plan Consent Checklist Carports, …...Development Plan Consent Checklist Carports, garages, sheds and verandahs As required by Section 39 of the Development Act 1993,

Demolition fees

Lodgement Fee (Development cost less than $5,000) $68.50 Lodgement Fee (Development cost more than $5,000) $145.50 Building Rules Only fee (Additional fee for Schedule 1A applications) $56.50 Building Class fee (Multiply by floor area then by 0.2%)

Other associated fees Certificate of Title search $45.00 Extension of Approval application $109.00 Certificate of Occupancy $49.00 Construction Industry Training Levy required for works greater than $40,000 – Calculated at 0.25% of the proposed Cost of development. Payable to the Construction Industry Training Board