Development of a Self-Healing Strategy for Future Smart ...
Transcript of Development of a Self-Healing Strategy for Future Smart ...
School of Engineering and Information Technology
Development of a Self-Healing Strategy for
Future Smart Microgrids
Soheil Bourbour
32948493
This thesis is presented for the Degree of
Master of Philosophy
of
Murdoch University
September 2016
ii
Declaration
I declare that this thesis is my own account of my research and contains as its
main content work which has not previously been submitted for a degree at any
tertiary education institution.
Soheil Bourbour
16/09/2016
iii
Abstract
Microgrid is expected to supply its local loads independently. But, due to
intermittency of wind and solar-based energy resources as well as the load
uncertainty, it is probable that a microgrid experiences power deficiency. This
problem can be mitigated by coupling the overloaded microgrid to another
neighbouring microgrid that has surplus power. Considering a distribution network
composed of several islanded microgrids, defining the suitable microgrids to be
coupled to the overloaded microgrid is a challenge. A microgrid overload
management technique is developed in this thesis which first identifies the
overloaded microgrid(s) and then selects the most suitable neighbouring microgrids.
The alternative selection is based on different criteria such as available surplus
power, reliability, supply security, power loss, electricity cost and emissions in the
selected microgrids. Moreover, the frequency and voltage deviation in the system of
coupled microgrids are considered in the selection. In addition, the thesis evaluates
the impact of the weightings of each criterion on the outcome of the alternative
selection strategy and presents the sensitivity of the selection procedure on the
weightings of each criterion since each criterion weighting has the potential to vary
the outcome of the alternative selection therefore the impact of every criteria is found
to be crucial. Therefore, a dynamic multi-criteria decision-making algorithm is
iv
developed for this purpose. To contemplate the uncertainties in the considered
distribution network, a cloud theory-based probabilistic analysis is deployed as the
research framework and the performance of the developed technique is evaluated in
MATLAB. Once a selection is identified, the interconnection should take place, but
before that, a synchronisation between selected microgrids is required for a safe and
appropriate interconnection between them and thereby in this thesis, the transition
stage forming a system of coupled microgrids is also discussed, and a suitable and
practically applicable strategy is developed which facilitates their synchronisation
before interconnection. The performance of the developed strategy is evaluated by
time-domain simulation studies in PSCAD/EMTDC.
v
Table of Contents
Chapter 1 Introduction ............................................................................................ 1
1.1 Introduction ............................................................................................................ 1
1.2 Aims and objectives of the thesis ........................................................................... 5
1.3 Significance of research ......................................................................................... 6
1.4 Structure of the thesis ............................................................................................. 6
Chapter 2 Coupling of Neighbouring Microgrids ................................................. 8
2.1 Necessity and Complexity of Coupling Microgrids............................................... 8
2.2 Proposed Overload Management Technique (OMT) ........................................... 11
2.3 Dynamic Multi-Criteria DMA ............................................................................. 16
2.3.1 Risk Index ......................................................................................................... 19
2.3.2 Dynamic DMA .................................................................................................. 20
2.3.3 Criteria Weightings ........................................................................................... 20
2.3.4 Qualifying Criteria ............................................................................................ 21
2.3.5 Other Criteria .................................................................................................... 22
2.3.6 Power Loss in Interconnecting Lines ................................................................ 23
2.3.7 Electricity Price ................................................................................................. 24
2.3.8 Reliability .......................................................................................................... 25
2.3.9 Supply Security ................................................................................................. 26
2.3.10 CO2 Emissions ................................................................................................ 26
2.4 Power Flow Analysis (PFA) for Microgrids ........................................................ 29
2.5 Cloud Theory-Based Stochastic Analysis ............................................................ 34
vi
2.6 Performance Evaluation ....................................................................................... 37
2.7 Conclusion ............................................................................................................ 48
Chapter 3 Impact of the Criteria Weighting ....................................................... 50
3.1 Performance Evaluation of the Alternative Selection Strategy ............................ 50
3.2 Sensitivity Analysis Results of the Weightings ................................................... 57
3.3 Conclusion ............................................................................................................ 62
Chapter 4 Synchronisation Strategy for Coupling Microgrids .......................... 64
4.1 Considered Structure and Control of ISS ............................................................. 64
4.2 Synchronisation Strategy of Multiple Microgrids ................................................ 72
4.3 Communication System Considerations .............................................................. 82
4.4 Performance Evaluation ....................................................................................... 82
4.4.1 Scenario-A ......................................................................................................... 83
4.4.2 Scenario-B ......................................................................................................... 84
4.4.3 Scenario-C ......................................................................................................... 84
4.5 Conclusion ............................................................................................................ 94
Chapter 5 Conclusions and Recommendations ................................................... 95
5.1 Conclusions .......................................................................................................... 95
5.2 Recommendations for future research .................................................................. 96
5.2.1 Consideration of reactive power capacities and limits of microgrids ............... 96
5.2.2 Possibility of interconnection of a microgrids through multiple links .............. 97
5.2.3 Synchronisation method for microgrids with different topologies ................... 97
5.2.4 Protection Issues of the system of coupled microgrids ..................................... 97
5.2.5 Communication network and data transfer delay effect .................................... 97
References ................................................................................................................ 99
Publications arising from this Thesis ................................................................... 105
vii
List of Figures
Figure 1.1. A distribution network consisting of several isolated microgrids with
normally-open ISSes among them ............................................................................... 2
Figure 1.2. A distribution network consisting of several isolated microgrids with
normally-open ISSes among them. .............................................................................. 4
Figure 2.1. A remote-area distribution network composed of three islanded
microgrids with all three alternative CMGs when MG-1 is overloaded. ..................... 9
Figure 2.2. Schematic diagram of the communication links between the developed
OMT (located within the network tertiary controller) and the central controller of
each microgrid as well as the ISSes. .......................................................................... 11
Figure 2.3. Flowchart of the developed multi-criteria dynamic DMA. ..................... 18
Figure 2.4. Assumed power system topology for the microgrids in the distribution
network under consideration. ..................................................................................... 32
Figure 3.1 Sensitivity analysis plot of the selected alternative versus different
weightings of cost and distance.................................................................................. 60
Figure 4.1. Two sample structures of normally-open ISSes among the microgrids. . 65
Figure 4.2. Developed local controller for the ISSes. ................................................ 66
Figure 4.3. Required communication links and the transferred data. ........................ 66
Figure 4.4. (a) Phase-a voltage at two sides of the ISS when the synchronisation
command is initiated, (b) Phase-a voltage at two sides of the ISS when two MGs are
viii
synchronized, (c) The difference of phase-a voltages at two sides of the ISS at the
synchronisation. .......................................................................................................... 69
Figure 4.5. Required time for interconnection of microgrids for different and f. 70
Figure 4.6. Different interconnections of neighbouring microgrids: (a) Scheme-1, (b)
Scheme-2: radial line, (c) Scheme-2: loop line, (d) Scheme-3, (e) Scheme-4. .......... 73
Figure 4.7. Developed operation sequences of coupling multiple neighbouring
microgrids during the interconnection transition. ...................................................... 77
Figure 4.8. Case-1 simulation results. ........................................................................ 91
Figure 4.9. Case-2 simulation results. ........................................................................ 91
Figure 4.10. Case-3 simulation results. ...................................................................... 92
Figure 4.11. Case-4 simulation results. ...................................................................... 92
Figure 4.12. Case-5 simulation results. ...................................................................... 93
Figure 4.13. Case-6 simulation results. ...................................................................... 93
ix
List of Tables
Table 2.1. Assumed Line Parameters of the Microgrid System of Figure 2.4 at
Fundamental Frequency ............................................................................................. 33
Table 2.2. Assumed Uncertainties in the Generation Capacity and Demand for the
Microgrids. ................................................................................................................. 35
Table 2.3. Assumed Uncertainties in the Parameters of the Criteria in DMA. .......... 35
Table 2.4. Assumed Cloud Theory-Based Probabilistic Power Data and the
Calculated UPC and PDL for the Distribution Network [kW] (Example-1) ............. 38
Table 2.5. Assumed Cloud Theory-Based Probabilistic Data for Each Microgrid of
the Distribution Network Used in DMA (Example-1) ............................................... 39
Table 2.6. Comparison among the Parameters of Available Alternatives to Support
Overloaded MG-1 (Example-1) ................................................................................. 39
Table 2.7. Calculated Decision Making Matrix (Example-1) .................................... 39
Table 2.8. Assumed Weightings for the Criteria in DMA ......................................... 39
Table 2.9. Calculated Weighted Decision Making Matrix (Example-1) ................... 40
Table 2.10. Normalized Weighted Decision Making Matrix (Example-1) ............... 40
Table 2.11. Selected Alternative and Evaluation Results from Different Aggregators
(Example-1)................................................................................................................ 40
Table 2.12. Decision Making Matrix (Example-2) .................................................... 41
Table 2.13. Normalized Weighted Decision Making Matrix (Example-3) ............... 41
x
Table 2.14. Selected Alternative and Evaluation Results from Different Aggregators
and Risk Matrix (Example-3) ..................................................................................... 42
Table 2.15. Risk Matrix (Example-3) ........................................................................ 42
Table 2.16. Assumed Cloud Theory-Based Probabilistic Power Data and the
Calculated UPC and PDL for the Network [kW] (Example-4) ................................. 43
Table 2.17. Assumed Cloud Theory-Based Probabilistic Data for Each Microgrid of
the Distribution Network Used in DMA (Example-4) ............................................... 43
Table 2.18. Comparison among the Parameters of Available Alternatives to Support
Overloaded MG-1 (Example-4) ................................................................................. 44
Table 2.19. Decision Making Matrix (Example-4) .................................................... 45
Table 2.20. Selected Alternative and Evaluation Results from Different Aggregators
(Example-4) ................................................................................................................ 46
Table 2.21. Stochastic Analysis Results Demonstrating the Flags Generated by the
OMT and Decision-making and Load-shedding Functions for a Network Composed
of 3 Microgrids under two Considered Study Cases. ................................................. 48
Table 3.1. Considered Nominal Values for a Network Composed of 6 microgrids. . 51
Table 3.2 Random Values for the Assumed Network at the Time of Study. ............. 51
Table 3.3. Assumed Normalized Weightings for the Criteria. ................................... 52
Table 3.4. Decision Making Matrix for the Network with the Assumptions of the
Data of Table 3.1 and Table 3.2. ................................................................................ 53
Table 3.5 Normalized Weighted Decision Making Matrix Assuming the Weighting
Matrix of Table 3.3. .................................................................................................... 55
Table 3.6. Corresponding Column of the Normalized Weighted Decision Making
Matrix When Only One Criterion is Considered. ...................................................... 58
xi
Table 4.1. The overloaded and selected non-overloaded microgrids of the distribution
network as well as their UPC and PDL in the considered study cases. ..................... 86
Table 4.2. Time-sequence of the events in the considered study cases. .................... 87
xiii
List of Abbreviations
ALS Amount of load to be shed
APC Available power capacity
CMG Coupled microgrids
DER Distributed energy resources
DMA Decision-making algorithm
ISS Interconnecting static switch
MAIFI Momentary average interruption frequency index
MG Microgrid
OMT Overload management technique
PDF Probability density function
PDL Power deficiency level
PFA Power flow analysis
SAIDI System average interruption duration index
SAIFI System average interruption frequency index
SLSA Selective load-shedding algorithm
UPC Unused power capacity
Chapter 1 - Introduction
1
Chapter 1 Introduction
1.1 Introduction
Electrification of remote and rural areas has been always a major challenge due
to a variety of constraints such as the area accessibility and economic factors [1-2].
The electricity demand in these areas can be supplied by the help of distributed
energy resources (DERs) in an islanded scheme. Thus, the power system of remote
areas can be considered as a microgrid that operates in islanded mode [3]. The
microgrids should be formed such that there is enough generation capacity in their
embedded DERs to meet their local demands [4-6]. It is to be noted that a remote
area/town can be supplied by several independent microgrids, where each may have
a different owner (operator) and each is responsible for supplying the loads of a
specific region. Thus, the distribution network of a remote area can resemble the
system of Figure 1.1. These types of islanded microgrids are conventionally supplied
by diesel generators. The fuel transportation difficulties and the fuel cost adversely
affect the profits for the owners of each microgrid. If these areas are rich in
renewable energies, renewable-energy-based DERs can be utilized for electricity
generation to meet the local electrical demand [7].
Chapter 1 - Introduction
2
MG-2MG-1
MG-k
DERMG-N–1
MG-N
D1
DN–1
DN–2
Load
Figure 1.1. A distribution network consisting of several isolated microgrids with normally-open
ISSes among them
The intermittency of non-dispatchable (e.g. solar and wind- based) DERs in
addition to load uncertainties can lead to imbalance between the instantaneous power
generation and demand in a microgrid. Any generation deficiency (overloading) will
lead to voltage/frequency drop. To address power imbalance problems in microgrids,
several solutions can be considered such as:
under frequency/voltage load-shedding [9]
utilization and control of battery energy storages [10],
optimal capacity design of dispatchable DERs (e.g. diesel generators) [11-
12],
interconnection of the microgrid to utility [13],
coupling of one microgrid to one/more neighbouring microgrid(s) [14].
Microgrids coupling is introduced in [14] as a solution to proliferate the
number of DERs in distribution networks. Each microgrid in Figure 1.1 may be
supported by one/more of its neighbouring microgrid(s) during power deficiency.
Chapter 1 - Introduction
3
This can be achieved by closing the normally-open interconnecting static switch
(ISS) which is located between every two adjunct microgrids.
References [16-17] have proposed a transformative architecture for coupling
the neighbouring microgrids as a technique for improving the self-healing of the
distribution system in case of short-circuit faults in the network. The trade of power
among microgrids in the system of coupled microgrids (CMG) is addressed in [18].
Optimal control of a distribution network composed of utility-connected microgrids
forming a CMG is also studied in [19]. Dynamic operation of DERs within CMGs is
investigated in [20] and the dynamic security of the CMGs is examined in [21]. The
conditions under which two microgrids are interconnected are addressed in [22]. The
stability analysis of a CMG prior to the interconnection of the microgrids is
discussed in [23], as a preliminary step to prevent any interconnection that may lead
to system instability. Selection of the suitable microgrid(s) among the available
neighbouring microgrids when interconnecting them during overloading has not been
addressed in previous literature and is the main focus of this research.
This research proposes an overload management technique (OMT), based on
coupling the neighbouring islanded microgrids, and utilizes a dynamic multi-criteria
decision-making algorithm. The proposed OMT assumes a data communication
system is available to receive the power generation of all DERs and consumption of
essential/non-essential loads in all microgrids. The communication system also
transmits the command (output) of the OMT to the relevant ISS(es) to couple the
microgrids. Under such a case, the power flow control in the considered system is
based on the proper operation of the ISS; i.e. if the OMT decides that some
microgrids should be interconnected, the ISS of each of those microgrids will be
closed and thereby, the power flow will occur between the interconnected microgrids
Chapter 1 - Introduction
4
automatically based on the dynamic operation of the DERs in each microgrid and no
further power control is required.
Load
MG-N
Load
MG-1DER
Load
MG-2DER
Load
MG-N-1DER
DER
Figure 1.2. A distribution network consisting of several isolated microgrids with normally-open
ISSes among them.
Based on the above assumptions, considering the distribution network of
Figure 1.2 with N islanded microgrids among which MG-1 is assumed to be
overloaded. Each of the other existing microgrids may be able to support MG-1
individually or in combination. In general, assuming N overloaded microgrids within
a distribution network composed of N microgrids, 2N–N′
–1 alternatives are available.
Thus, selecting the suitable microgrids to couple with the overloaded microgrid is
challenging due to the high number of alternatives. In addition, different criteria can
be considered for the selection, each with a different weighting which can further
complicate the selection process. Weighting of criteria is another area of research
which is also mentioned in this research. Because a criteria with higher weighting
than others can easily vary the outcome of OMT, different weighting are applied to
the criteria and the result of the outcomes are compared for assessment.
Chapter 1 - Introduction
5
An important stage of forming a CMG is the synchronisation of the
interconnecting microgrids. This transition stage has not been investigated in details
in literature and it is another main research gap that is addressed in this thesis.
Conventionally, synchronisation will take place by using either a forced
technique to achieve quicker synchronisation or a non-forced technique in which
every two microgrids are synchronized over some time. In this research, a suitable
and effective, non-forced technique is considered in which the selected microgrids
are interconnected safely and promptly. To this end, a generalized algorithm is
developed and validated by time-domain simulation studies in PSCAD/EMTDC.
This developed algorithm is able to synchronize any number of microgrids, and
depending on how large the selected group is, this method can manage to
continuously check the voltage and frequency levels of every microgrid and
depending on their voltage and frequency difference, the algorithm decides which
two microgrids can be synchronized first. In large group of microgrids, for example,
when there are ten microgrids to be interconnected, the developed method can
synchronize two, three or even more pairs of microgrids at the same time so then the
final interconnection can be achieved quicker.
1.2 Aims and objectives of the thesis
The main objective of this thesis is to develop an OMT for islanded microgrids
to support a microgrid when a power deficiency occurs in an microgrid. The
proposed technique enables the overloaded microgrid to connect to one or more
neighbouring microgrids depending on some defined criteria. In addition, a
synchronisation strategy is developed for interconnection of the microgrids. To
achieve this goal, the specific objectives of the research are identified as:
Chapter 1 - Introduction
6
to develop a dynamic multi-criteria decision making algorithm (DMA) to
select the suitable microgrids,
to define the different criteria required for DMA,
to qualify the selected microgrid(s) based on the deviations in voltage and
frequency after coupling the microgrids,
to define the portion of the non-essential loads to be shed from each
microgrid based on the proposed DMA such that all essential loads of all
microgrids are always supplied,
to develop a suitable and practically applicable strategy for coupling
neighbouring microgrids,
to develop a suitable local control system for the ISSes.
1.3 Significance of research
It is expected that the future distribution networks will be in the form of
multiple islanded microgrids, distributed over a close proximity. This research will
help to improve the operation, control and management of those microgrids during
power deficiencies. A proper technique is developed which detects the overloading
and aims to interconnect the microgrids to mitigate this problem. Also, proper
synchronisation technique is developed which facilitates the suitable connection of
the microgrids.
1.4 Structure of the thesis
This thesis is organized in five chapters: Chapter 1 outlines the research aims
and objectives along with the need and the justification through a literature review
Chapter 1 - Introduction
7
for the research topic. Chapter 2 discusses the necessity of coupling the microgrids
and the complexity of decision-making in details. The proposed OMT consisting of a
dynamic multi-criteria DMA is introduced in this chapter. The performance of the
developed technique is evaluated within a MATLAB-based stochastic analysis.
Chapter 3 focuses on the impact of the weightings considered for each criterion as it
is expected that these weightings can significantly modify the selected alternative.
Chapter 4 describes the developed synchronisation strategy in details. The required
data communication system for this technique is highlighted in this chapter. The
performance evaluation results of a distribution network with the developed
technique are also presented here. Finally, the conclusions drawn from this research
and the recommendations for future research are highlighted in Chapter 5.
Chapter 2 – Coupling of Neighbouring Microgrids
8
Chapter 2 Coupling of Neighbouring
Microgrids
This chapter discusses the interconnection of microgrids when the generation
in one or more microgrids cannot meet the demand. An algorithm is developed and
presented in this chapter that first detects any overloading in a microgrid and then
aims to interconnect the overloaded microgrid with a suitable neighbouring
microgrid, using the dynamic multi criteria decision making technique. Any decision
is made by considering several criteria in which each criterion has a specific
weighting. The outcome of the decision identifies whether an interconnection will be
able to rectify the overloaded microgrid or not, and if so, identifies the selected
microgrids for interconnection.
2.1 Necessity and Complexity of Coupling Microgrids
This research focuses on remote area networks where a utility connection is not
available. Thus, the loads are supplied by small microgrid networks. Each of these
microgrids may have a different owner, that has invested in the installation of the
DERs in that microgrid and charges the loads based on their electricity consumption.
Thereby, it is assumed that these microgrids operate in islanded mode and
independently from each other.
Chapter 2 – Coupling of Neighbouring Microgrids
9
Due to load and generation uncertainty, it is highly probable to expect power
generation deficiency or overloading at some portions of the operation stage. Under
such conditions, except load-shedding, the other possible option to control a
microgrid is external support in the form of importing power from one or a group of
neighbouring microgrids. Thereby, an OMT is proposed and developed in this
research to overcome the overloading issues of the microgrids that operate in remote
areas.
DER
Load
MG-3
D1
D3
MG-1
MG-2
D2
DER
Load
MG-3
MG-2
CMG
(b)(a)
MG-1
DER
Load
MG-3
MG-1
MG-2
CMG
(d)(c)
DER
Load
MG-3
MG-1
MG-2
CMG
Figure 2.1. A remote-area distribution network composed of three islanded microgrids with all three
alternative CMGs when MG-1 is overloaded.
Consider the distribution network of Figure 1.1 with N islanded microgrids,
among which MG-1 is assumed to be overloaded. Each of the other existing
Chapter 2 – Coupling of Neighbouring Microgrids
10
microgrids may be able to support MG-1 individually or in combination with others.
As an example, for N = 3, the alternative microgrids are [{2}, {3}, {2,3}] (see Figure
2.1) and for N = 4, the alternative microgrids are [{2}, {3}, {4}, {2,3}, {2,4}, {3,4},
{2,3,4}] while for N = 5, the alternative microgrids are [{2}, {3}, {4}, {5}, {2,3},
{2,4}, {2,5}, {3,4}, {3,5}, {4,5}, {2,3,4}, {2,3,5}, {2,4,5}, {3,4,5}, {2,3,4,5}]. In
general, assuming N microgrids are overloaded, the alternatives are combinations of
anysinglemicrogrids,any twomicrogrids, any threemicrogrids…,andanyN– N
microgrids out of the available N– N microgrids. Hence, the total number of
alternatives, denoted by NA, is
NN
NN
NNNNNNNN
i
NN
iA CCCCCN
...3211 (2.1)
where b
aC = b!/[(b–a)!a!] and a! = a (a – 1) …1. Equation (2.1) can be
simplified as
12 NN
AN (2.2)
Thus, selecting the suitable microgrid(s) to couple with the overloaded microgrid
among all alternatives is challenging due to the high number of alternatives. In
addition, different criteria can be considered for the selection, each with a different
weighting, which can further complicate the selection process.
To overcome the problem of proper alternative selection among a large number
of alternatives, while considering several criteria with different weighting, the
developed OMT utilizes a decision-making algorithm to assess the alternatives and
select the suitable one.
It is worth mentioning that Figure 1.1 depicts only one of the many possible
topologies that the neighbouring microgrids can be connected. The proposed OMT in
this research does not depend on neither the interconnection topologies of the
Chapter 2 – Coupling of Neighbouring Microgrids
11
microgrids, nor the topology of an individual microgrid. Thus, other interconnection
topologies are also acceptable.
2.2 Proposed Overload Management Technique (OMT)
The developed OMT will be located as a module (agent) within the network
tertiary controller and will continuously communicate with the central controller of
each microgrid as well as the ISSes (see Figure 2.2). It is to be noted that the
communication system, data bandwidth and topology is beyond the scope of this
research and is not discussed in this thesis.
MG-2MG-1
MG-k
MG Central
Controller
MG Central
Controller
MG Central
Controller
MG Central
Controller
MG Central
Controller
Network
Tertiary
Controller
Figure 2.2. Schematic diagram of the communication links between the developed OMT (located
within the network tertiary controller) and the central controller of each microgrid as well as the
ISSes.
The proposed OMT is composed of one main function and three sub-functions,
namely decision-making function, load-shedding function, and PFA function. Two
algorithms, namely DMA and selective load-shedding algorithm (SLSA) are used
respectively within the decision-making and load-shedding functions. The proposed
Chapter 2 – Coupling of Neighbouring Microgrids
12
OMT and its sub-functions are described in details below while the algorithms are
described in the next Section. The PFA function is discussed in Section 2.4.
The OMT continuously communicates with the central controller of each
microgrid to receive the information about the total active power generation of the
dispatchable DERs as well as the total active power consumed by all loads. For MG-
i, let us denote these quantities respectively as Pdisp-DER (MG-i) and Pload (MG-i). The
OMT will first identify the overloaded microgrid(s) and then will take action
depending on the network conditions such as the number of overloaded microgrids
and the unused power capacity (UPC) that is available in the other microgrids. The
OMT calculates the UPC for MG-i as
max
)-(MGDER-disp1
ii PUPC (2.3)
It is desired to maintain the UPC of every microgrid higher than a threshold as
}...,,1{ A)-(MGload)-(MGDER-dispNiPPUPC
iii (2.4)
where∑max
)-(MGDER-disp
iP
is the total capacity of dispatchable DERs in MG-i and 0 < 1 < 1
(e.g. 1 = 0.1) imposes a safety margin. In the rest of this thesis, (2.4) is assumed as
the overloading condition of a microgrid.
If condition (2.4) is valid for all microgrids of the distribution network, no
action needs to be taken by the OMT. However, if it is invalid for one or more
microgrids, the OMT evaluates the availability of surplus power in the network as
N
i
i
N
i i PUPC1
max
)-(MGDER-disp11 (2.5)
In the rest of this thesis, (2.5) is considered as the constraint for coupling the
microgrids.
If condition (2.4) flags that one or more microgrids are overloaded and
constraint (2.5) flags the availability of surplus power in the distribution network, the
Chapter 2 – Coupling of Neighbouring Microgrids
13
OMT proceeds to support the overloaded microgrids by coupling one or more of the
non-overloaded microgrids to the overloaded one(s).
If condition (2.4) is invalid for n1 = N – 1 microgrids but constraint (2.5) is
valid, the OMT flags that the only alternative is coupling all microgrids. It then calls
the PFA function to verify that coupling all microgrids will not cause non-standard
voltage and frequency deviation in the CMG system. From the PFA, which is
discussed in Section 2.4, the maximum voltage deviation in the buses of the system
and the maximum frequency deviation in the system, respectively denoted by V and
F, are calculated as
||Δ
|)(|maxΔ
nom
1,...,nom bus
ffF
VVV Nii
(2.6)
where Vi is the per-unit (pu) voltage of bus-i, i 1,2,…,Nbus and f is frequency of
the system and Nbus is the number of buses in the system of CMG while it is assumed
that Vnom = 1 pu and fnom = 50 Hz. These two parameters are then evaluated in
V 0.1 and F 0.5 (2.7)
to verify the possibility of microgrids interconnection, assuming that the maximum
acceptable voltage deviation is 10% and the maximum acceptable frequency
deviation is 0.5 Hz.
If condition (2.4) is invalid for 1 < n1 < N microgrids, the OMT flags that
several alternatives are available and decision-making is required. It then calls the
decision-making function to formulate all alternatives and to define the suitable
alternative using the DMA. The proposed DMA is discussed in details in the next
Section. If an alternative is selected by the DMA, the OMT initiates the proper
command for the relevant ISS(es) to close. However, if no suitable alternative is
Chapter 2 – Coupling of Neighbouring Microgrids
14
chosen, the decision-making function flags that load-shedding is inevitable and
requests the main function of the OMT to call the load-shedding function.
If the OMT calls the load-shedding function, it first seeks the possibility of
shedding a portion of the non-essential loads in one or more microgrids such that the
essential loads of all microgrids are not interrupted. For this, it first identifies the
available power capacity (APC) of each microgrid as
)-(MGDER-nondisp)-(MGDER-disp ii
PPAPC i (2.8)
where ∑Pnondisp-DER (MG-i) denotes the total active power generation by non-
dispatchable DERs in MG-i at that moment. It is to be noted that APC represents the
maximum power that can be supplied in MG-i to its loads plus the power loss in the
lines. Based on (2.8), the load-shedding function defines the amount of loads to be
shed (ALS) from each microgrid as
))(1()-(MGLoad2 ii APCPALS
i (2.9)
where 0 < 2 < 1 (e.g. 2 = 0.1) imposes a safety margin to compensate for line
losses. For successful load-shedding in each microgrid, the ALS should be equal or
smaller than the total of non-essential loads in each microgrid at that moment,
denotedby∑Pnon-ess Load, i.e.
)-(MGLoad ess-non i
PALS i (2.10)
If the load-shedding function defines that condition (2.10) is valid for all
microgrids, it flags that load-shedding is successful and sends the ALS level of each
microgrid to their central controllers. And if condition (2.10) is invalid for all
microgrids, it flags that load-shedding is not viable.
If condition (2.10) is invalid for 1 n2 < N microgrids, the load-shedding
function first sends the ALS level to the microgrid(s) which satisfy (2.10) to shed the
defined portion of their non-essential loads. Then, it evaluates whether the sum of
Chapter 2 – Coupling of Neighbouring Microgrids
15
ALSes in all microgrids of the distribution network is less than the sum of non-
essential loads in all microgrids i.e.
N
i
N
i i iPALS
11 )-(MGLoad ess-non (2.11)
If (2.11) is satisfied, the load-shedding function seeks the possibility of
interconnecting the microgrid(s) which do not satisfy (2.10) with the one(s) that still
have some non-essential loads. For this, it defines a second ALS level to compensate
for the microgrids who did not satisfy (2.10). In the rest of this thesis, (2.11) is
considered as another constraint for coupling microgrids, which is used only when
load-shedding is accompanying coupling. The second ASL level, denoted by ALS 2
,
is defined as
}...,,1{)( 21
2 2
)-(MGLoad ess-nonniPALSALS
n
i i i
(2.12)
The load-shedding function then formulates the alternatives which their total
remaining non-essential loads are higher than ALS 2
, i.e.
}...,,1{)( 2
)-(MGLoad ess-non Ak i NkALSALSPi
(2.13)
where NA is the number of the formulated alternatives. The alternatives qualified in
(2.13) are then assessed by the SLSA to select a suitable alternative. If a suitable
alternative is selected by the SLSA, the load-shedding function flags that a suitable
alternative is selected. It then defines the portion of ALS 2
for each microgrid of the
selected alternative based on the ratios of their non-essential loads and sends the
amount of the second load-shedding level to the central controller of each microgrid
as well as the proper command to the relevant ISS(es) to close. However, if the
SLSA does not select an alternative, the load-shedding function flags that microgrids
coupling with further load-shedding is not viable.
In this research, the microgrids are coupled to prevent overloading of a
microgrid. The proposed method can be further expanded to facilitate coupling of
Chapter 2 – Coupling of Neighbouring Microgrids
16
microgrids so that the surplus power of the DERs of a microgrid can be exported to
other microgrids with a lower electricity price (as an incentive technique) [18] to be
stored in the energy storage [24], or to be consumed by the controllable loads of the
other microgrids under the demand dispatch concept [25].
It is worth mentioning that the proposed OMT solely focuses on the situations
that at least one of the microgrids are overloaded and tries to select a suitable
alternative to which the overloaded microgrid(s) will be interconnected, such that an
acceptable power balance is achieved. The proposed OMT does not lead to an
optimum generation in the DERs but tries to reduce the load-shedding rate and
prevent instability due to power generation-demand imbalance. To achieve optimum
generation in the DERs of a CMG, an economic dispatch-type method can be
utilized.
It is also noteworthy that in this research, overloading is defined based on the
balance of generation and consumption of active power solely. Reactive power was
not considered in this approach assuming that reactive power support (in the form of
fixed or switched capacitors) are available in the network. The proposed OMT can be
further modified to consider the interconnection of microgrids for reactive power
support, after a detailed techno-economic analysis.
2.3 Dynamic Multi-Criteria DMA
The multi-criteria decision-making model prescribes a method for prioritizing
and selecting the most favourable alternative from a set of alternatives, denoted by A
{A1, A2,…, ANA}, based on a set of criteria, denoted by c {c1, c2,…, cNc .}, Nc being
the number of criteria. Each criterion may have a different weighting. The
corresponding normalized weightings for the criteria are denoted by w {w1, w2,…,
Chapter 2 – Coupling of Neighbouring Microgrids
17
cNw .}where∑j wj = 1. These weightings are defined by the help of the experts, as
discussed later in this Section.
The multi-criteria decision-making problem can be modelled in the form of a
matrix as [26]
CAAA
C
C
A
CC
NNNN
N
N
N
NN
xxx
xxx
xxx
A
A
A
wcwcwc
21
22221
11211
2
1
2211 )()()(
(2.14)
where xuv represents the performance of alternative Au from the perspective of
criterion cv. The matrix of (2.14) will then be modified to include the weighting of
each criterion as
ANCNANCNANAN
CNCN
CNCN
AN
CN
X
X
X
xwxwxw
xwxwxw
xwxwxw
A
A
A
ccc
2
1
2211
2222211
1122111
2
1
21
(2.15)
The evaluation results for the alternatives, denoted by X {X 1, X 2,…,ANX }, are
calculated as
)(agg uvvu xwX (2.16)
where agg(.) is an aggregating function such as average, product, max-min and
Hurwitz in the form of [27-29]
Chapter 2 – Coupling of Neighbouring Microgrids
18
Selecting Criteria
{c1, c2,…, c }
Formulating Alternatives
{A1, A2,…, A }
Requesting the
Weightings from ExpertsFirst iteration
k = 1 ?
Acceptable data
dispersion v e ?
Yes
No
Weighting the Criteria
{w1, w2,…, w }
Yes
},...,,{21
iii
CNwww
No
Start
Evaluating Alternatives
with different aggregators
{X1, X2,…, X }
Defining Dynamic Evaluations
},...,,{21
dN
dd
CXXX
Memory
1-k
uX
Qualifying Alternatives
based on Qualifying Criteria
{xu1, xu2, xu3, xu4}
Calculating Performance of
Alternatives for other Criteria
{xu4, xu5,…, xu }
Retrieving previous iteration
evaluation results
kd
uuXX
Storing new evaluation results
for next iteration
Constitu
ting D
ecis
ion
Ma
kin
g M
atr
ix
Same Alternative Selected
by All Aggregators?
Yes
Selecting the Alternative(s) with
Highest Dynamic Evaluation
from each Aggregator
end
Defining the Risk Index
of Each Alternative
{ru1, ru2,…. ru }
Defining the Risk Index
of Selected Alternative
{R1, R2, R3, R4}
Risk Matrix
No
Choosing the Selected Alternative
with minimum Risk Index {Ru}
Applying the Effect of Different Criteria
Weighting in the Performance Values
{w1xu1, w2xu2,…., w x }
CN
AN
CN
CN
CN CANN
AN
AN
Defining the Criteria Weightings
Figure 2.3. Flowchart of the developed multi-criteria dynamic DMA.
where min(.) and max(.) are respectively the minimum and maximum functions and
3 [0,1] (e.g. 3 = 0.75) is the optimist coefficient used in the Hurwitz method.
Each of these aggregators has advantages and disadvantages as discussed in [27-29].
The alterative with the highest X has the highest priority and is selected by the DMA.
The flowchart of the developed multi-criteria dynamic DMA is shown in
Figure 2.3.
Chapter 2 – Coupling of Neighbouring Microgrids
19
2.3.1 Risk Index
)max().1()min(.)(Hurwitz
)(min
)(product
)(average
33
,...,1
1
1
uvvuvvuvvu
CNvuvvu
CN
u uvvuvvu
C
CN
u uvvuvvu
xwxwxwX
xwX
xwxwX
NxwxwX
(2.17)
All of the aggregators given in (2.17) may not necessarily select the same
alternative. To overcome this problem, the risk index, denoted by R {R1, R2, …,
ANR }, is defined for each alternative in the form of a matrix as [26-27]
ANMNANANAN
MN
MN
AN
MNM
R
R
R
rrr
rrr
rrr
A
A
A
xcxcxc
2
1
21
22221
11211
2
1
maxmax
22
max
11 )()()(
(2.18)
where ruv for criterion cv is the deviation of the performance of each alternative
versus the alternative with the highest performance and is calculated from
max
vuvvuv xxwr (2.19)
where max
vx is the maximum of wvxuv for criterion cv among all alternatives. From
(2.18), the risk index for alternative Au, denoted by Ru, is selected as the maximum of
ruv.
In case of difference among the selections by aggregators of (2.17), the risk
index of the alternatives selected by the aggregators are analyzed only to speed up
the process and the selected alternative with a lower risk index is chosen by the
DMA as the suitable alternative.
Chapter 2 – Coupling of Neighbouring Microgrids
20
2.3.2 Dynamic DMA
DMA carries out dynamically. However, overtime the available alternatives
can be modified e.g. newer alternatives get added or previously existing alternatives
vanish depending on the overloaded microgrids. Furthermore, the criteria and their
weightings can dynamically change due to the preference of the network operator.
Hence, a dynamic DMA is utilized in which the historical decision-making results
are considered in future decision-makings. In dynamic DMA, first the evaluation
result of each alternative is defined from (2.15). Then, a new dynamic evaluation
result, denoted by X d {X
d1, X
d2, …, X
dNA}, is defined at iteration k based on
previous iteration as [28].
11 k
u
k
u
k
u
k
u
d
u XXXXX (2.20)
Note that in case an alternative appears for the first time, its current evaluation
result is used instead of (2.20) In addition, if an alternative vanishes in a new
decision-making iteration but it was available in the previous iteration, its evaluation
result is stored in memory and retrieved in the first decision-making iteration that the
alternative appears again.
2.3.3 Criteria Weightings
The outcome of the DMA highly depends on the assumed weightings for each
criterion. Therefore, these weightings should be selected carefully. In complex
systems such as power systems, there is not a systematic method to define these
weightings. An acceptable method is a census from the experts. For this purpose, a
group of experts are required to be asked to participate in defining the weightings for
these criteria. They will evaluate the weightings for each criterion based on their
experience and outlook in either form of linguistic (extremely big/small, very
Chapter 2 – Coupling of Neighbouring Microgrids
21
big/small, big/small, a little big/small, and neutral) or number (between 0-100%).
After this, the linguistic and numerical values will be first mapped into a number in
[0, 1] range and then normalized. The weighting for each criterion will be defined as
the average of all normalized values as
e
eN
i
i
uu Nww
1 (2.21)
where Ne is the number of the experts. To achieve a high confidence in the
weightings, the variation coefficient for data dispersion (v ) of criterion cv is
calculated as
ue
N
i u
i
v wNwwe
u
1
2)(
(2.22)
If v is smaller than a pre-defined small threshold (e.g. e), it can be concluded that
wv represents the true weighting for criterion cv based on experiences and outlooks
of all participated experts. If v is not smaller than the pre-defined threshold, more
experts should be invited to participate in the census so that the weightings fulfill the
desired dispersion.
2.3.4 Qualifying Criteria
All possible alternatives may not be qualified to couple with the overloaded
microgrid(s) due to reasons such as lack of enough surplus power in microgrids of an
alternative, non-standard voltage and frequency deviation in the system after an
alternative is coupled with the overloaded microgrid(s) or when one microgrid vetoes
supporting another microgrid.
Hence, the DMA first qualifies the alternatives based on these conditions. The
first 4 criteria are defined as:
criterion-1: microgrid consent/veto for coupling,
Chapter 2 – Coupling of Neighbouring Microgrids
22
criterion-2: availability of surplus power in microgrids,
criterion-3: voltage deviation, and
criterion-4: frequency deviation.
The performance of alternative Au versus these criteria is expressed as
0..orΔ0.5if0
0Δ0.5 if1 Δ2
5.0Δ0 if1Δ2
0.orΔ0.1if0
0Δ0.1 if1 Δ10
1.0Δ0 if1Δ10
0or1 if0
31 if)1(5.0
3 if1
coupling consentsMG if1
coupling MG vetoes if0
321
4
21
3
1
2
1
uuuu
uu
uu
u
uuu
uu
uu
u
uu
uu
u
u
u
xxxF
FF
FF
x
xxV
VV
VV
x
x
x
x
(2.23)
where u is the ratio of the UPC in microgrid(s) of alternative Au versus the power
deficiency level (PDL) of overloaded MG-j (i.e. u = UPCu / PDLMG-j).
If any of the above 4 criteria define an alternative unqualified, the performance
of that alternative versus the remaining criteria is neglected i.e.
}...,,5{0...if
0...if0
4321
4321
C
uuuuuv
uuuu
uv Nvxxxx x
xxxx x
(2.24)
2.3.5 Other Criteria
Six other criteria are considered for alternative selection other than the 4
qualifying criteria. These criteria consider the line loss, electricity price, reliability
indices, supply security and CO2 emission when selecting a suitable alternative. It is
to be noted that defining and calculating these indices for each of the microgrids is
beyond the scope of this research. Assuming these parameters are known and
Chapter 2 – Coupling of Neighbouring Microgrids
23
revealed to the OMT, the performance of each alternative for criterion 5-10 will be
calculated, as discussed below:
2.3.6 Power Loss in Interconnecting Lines
One important criterion in the selection of an alternative is the power loss in
the interconnecting lines (tie-lines) which depends on the distance between the
overloaded microgrid and the selected microgrid(s) and the impedance of these lines.
The power loss can be calculated from PFA for each alternative. Then, it is
normalized in the range of [0, 1] where 0 and 1 are respectively for the alternative
with maximum and minimum power loss.
To reduce the required computation time, a second method is utilized in this
research in which the distance and impedance of the line(s) among the overloaded
microgrid and the microgrid(s) of each alternative is considered. These values are
pre-defined for the DMA and the only unknown parameters are the power flow from
each microgrid to the overloaded microgrid. However, based on droop characteristic,
each DER in the microgrid shares the load based on a pre-defined ratio (i.e. droop
curve coefficients). Based on this concept, each microgrid shares a portion of the
power deficiency level of the overloaded microgrid according to the maximum
capacities of its dispatchable DERs. Hence, assuming p microgrids in alternative Au,
coefficient i represents the ratio of power supplied from MG-i to overloaded MG-j
as
}...,,1{1
max
)-(MGDER-disp
max
)-(MGDER-disppiPP
p
i iiui, (2.25)
where∑max
)-(MGDER-disp iP
shows the maximum power capacity of all dispatchable DERs in
MG-i. Coefficient i,u is calculated once only and is not repeated in each iteration.
Chapter 2 – Coupling of Neighbouring Microgrids
24
Thus, the computation time is significantly improved compared to the PFA. After i
is calculated, the total power loss parameter of alternative Au is calculated as
p
i iiui,u DZP1loss, )( (2.26)
Note that (2.26) is not equal to the power loss of each alternative (in kVA) but
represents a relationship among different alternatives from line loss prospective.
From (2.26), the performance of each alternative is calculated for this criterion as
ANuuuu PPx 1,...,loss,loss,5 )max(1 (2.27)
Although the second method is not as accurate as considering PFA but it highly
improves the speed of decision-making and is therefore, preferred and used in this
research.
2.3.7 Electricity Price
Another important criterion in selecting an alternative is the price of electricity
offered by the owner of each microgrid. A microgrid owner may sell electricity to
neighbouring microgrids with a different price with respect to its own costumers. The
price can also dynamically change over time due to different reasons (e.g. the
variations in the price of fuel consumed in diesel generators or the availability of
power from intermittent non-dispatchable DERs). Assuming Ei as the electricity unit
price offered by MG-i (in $/kWh), the total equivalent electricity cost to be paid by
the owner of the overloaded microgrid to the owners of microgrid(s) in alternative Au
is defined as
p
i iui,u EE1cost, (2.28)
From (2.28), the performance of alternative Au is calculated for this criterion as
ANuuuu EEx 1,...,cost,cost,6 )(max1 (2.29)
Chapter 2 – Coupling of Neighbouring Microgrids
25
2.3.8 Reliability
It is highly probable that each microgrid may have a different reliability level.
In addition, the failure rate of CMG is the sum of the failure rates of each
participating individual microgrid. Therefore, as the number of microgrids increases
in an alternative, the failure rate of the alternative increases (i.e. the reliability
decreases). It is highly desirable for the overloaded microgrid to couple with
microgrid(s) in an alternative which have higher reliability to reduce the possibility
of interruption to the essential load of the overloaded microgrid. Different reliability
indices can be considered such as system average interruption frequency index
(SAIFI), momentary average interruption frequency index (MAIFI) and system
average interruption duration index (SAIDI). SAIFI and MAIFI represent the
frequency of supply interruptions whereas SAIDI represents the duration of
interruptions (in minutes). RBfu and RB
du indices are defined for alternative Au
composed of p microgrids as
p
i ui,u
p
i ui,ui,u
SAIDIRB
.MAIFI.SAIFIRB
1
d
1 21
f (2.30)
where {1, 2} [0, 1] and 1 +2 = 1 are the assumed weightings for SAIFI and
MAIFI, respectively. In this research, it is assumed that 1 =2. From (2.30), the
performance of alternative Au is calculated for these criteria as
ANuuuu
ANuuuu
RBRBx
RBRBx
1,...,
dd
8
1,...,
ff
7
)(max1
)(max1
(2.31)
Alternatively, these criteria can be combined together with different weightings to
constitute one criterion only. However, since the performance of each alternative is
easily compared when they are separate (due to dimension difference), reliability is
considered as two criteria but with the same weightings in this research.
Chapter 2 – Coupling of Neighbouring Microgrids
26
2.3.9 Supply Security
If a microgrid has high power generation by its non-dispatchable DERs, it may
have a higher UPC in its dispatchable DERs. Once this microgrid is coupled with an
overloaded microgrid, the overloaded microgrid does not have a high supply security
as any unexpected drop in the power of the non-dispatchable DERs (due to
environmental conditions) may cause overloading of the CMG. Hence, it is important
to consider the security of supply when selecting an alternative. Supply security
index SSu is defined for alternative Au composed of p microgrids as
p
i i
p
i iu PPSS1 )-load(MG1 )-DER(MG-disp (2.32)
where∑Pload(MG-i) shows the average active power consumed by all loads in MG-i.
From (2.32), the performance of alternative Au is calculated for this criterion as
ANuuuu SSSSx 1,...,9 )(max/1 (2.33)
2.3.10 CO2 Emissions
Consider a distribution network in which the distribution network operator
penalizes the microgrid owners based on their level of CO2 emission [30]. Hence,
each microgrid owner may charge CO2 emission penalties from customers in the
form of carbon tax, based on the supplied electricity to each customer. When
selecting an alternative, it is desired to select an alternative with less CO2 emissions
to minimize the penalties imposed to the overloaded microgrid. Therefore, the level
of CO2 emissions by each microgrid can be considered as a criterion. Assuming the
total CO2 emission for MG-i as Emi, CO2 emission index is defined for alternative Au
composed of p microgrids as
p
i iui,uEmCO
12 (2.34)
Chapter 2 – Coupling of Neighbouring Microgrids
27
From (2.34), the performance of alternative Au is calculated for this criterion as
ANuuuu CoCox 1,...,10 )2(max21 (2.35)
The developed OMT with its main, load-shedding and decision-making
functions is shown Algorithm 2.1 and has a time-complexity of O(N).
Chapter 2 – Coupling of Neighbouring Microgrids
28
Algorithm 2.1. Overload Management Technique (OMT)
Pre-defined Inputs: max
)-(MGDER-disp
iP
Dynamic Inputs: ∑Pload (MG-i),∑Pnon-ess load (MG-i),∑Pdisp-DER (MG-i),∑Pnon-disp-DER (MG-i)
Dynamic Outputs: Flag, command to ISSes, ALSi, ALSi2
Main Function:
1 Calculate UPCi from (2.3) for each microgrid;
2 if condition (2.4) is satisfied for all microgrids then
3 | Flag: No interconnection is required;
4 else
5 | Calculate∑UPCi i=1,…,N from (2.3);
6 | if constraint (2.5) is not satisfied then
7 | | Flag: Coupling microgrids is not helpful and load-shedding is
| | inevitable;
8 | | Call Load-shedding Function to evaluate the possibility of load-shedding;
9 | else
10 | | if N – 1 microgrids are overloaded based on condition (2.4) then
11 | | | Flag: The only alternative is coupling all N microgrids;
12 | | | Call PFA Function;
13 | | | if constraint (2.7) is satisfied then
14 | | | | Flag: All N microgrids can be coupled;
15 | | | | Send the command to relevant ISS(es) to close;
16 | | | else
17 | | | | Flag: Coupling all N microgrids is not viable and load-
| | | | shedding is inevitable;
18 | | | | Call Load-shedding Function to evaluate the possibility of
load-shedding;
19 | | | end
20 | | else
21 | | | Flag: Several alternatives are possible; hence, decision-making
| | is required;
22 | | | Call Decision-making Function to assess the alternatives;
23 | | | if an alternative is selected by Decision-making Function then
24 | | | | Flag: A suitable alternative is selected;
25 | | | | Send the command to relevant ISS(es) to close;
26 | | | else
27 | | | | Flag: A suitable alternative is not available and load-
| | | shedding is inevitable;
28 | | | | Call Load-shedding Function to evaluate the possibility of
| | | load-shedding;
29 | | | end
30 | | end
31 | end
32 end
Chapter 2 – Coupling of Neighbouring Microgrids
29
Decision-Making Function:
1 Formulate the alternatives;
2. Call DMA;
3 if an alternative is selected by DMA then
4 | Flag: A suitable alternative is selected for coupling the microgrids;
5 | Send the command to relevant ISS(es) to close;
6 else
7 | Flag: A suitable alternative is not available and load-shedding is inevitable;
|
8 | Call Load-shedding Function to evaluate the possibility of load- shedding;
|
9 end
Load-shedding Function:
1 Calculate ALSi from (2.9);
2 if condition (2.10) is satisfied for all microgrids then
3 | Flag: Load-shedding is successful;
4 | Send ALS to each microgrid to shed its loads accordingly;
5 else
6 | Send the ALS level to those microgrid(s) that satisfy condition (2.10);
7 | if constraint (2.11) is satisfied then
8 | | Calculate ALS 2 from (2.12) & formulate alternatives satisfying (2.13);
9 | | Call SLSA;
10 | | if an alternative is selected by SLSA then
11 | | | Flag: Coupling of microgrids accompanied by further load- shedding is selected;
12 | | | Send ALS 2 to relevant microgrid(s) to shed their loads;
13 | | | Send the command to relevant ISS(es) to close;
14 | | else
15 | | | Flag: Coupling of microgrids accompanied by further load- shedding is not viable;
16 | | end
17 | else
18 | | Flag: Coupling of microgrids accompanied by further load- shedding is not viable;
19 | end
20 end
2.4 Power Flow Analysis (PFA) for Microgrids
Standard PFAs have one slack bus with known voltage magnitude and angle
and regulated buses with known voltage magnitudes and active powers. It also
assumes that frequency is constant. The microgrids operating in islanded mode do
not have slack bus. For a microgrid operating in islanded mode, the DERs modify
their output voltage magnitude and frequency, using the droop control, based on the
Chapter 2 – Coupling of Neighbouring Microgrids
30
network loading conditions, as discussed in [31-32]. Hence, the PFA for an islanded
microgrid needs to consider these characteristics, as highlighted in [33]. It is also to
be noted that as the voltage and frequency are not constant in the microgrid under
different loading conditions, the dependency of the load and line parameters on
voltage and frequency should also be considered in the PFA.
A Gauss-Seidel-based PFA is developed in this research and used within the
OMT to compute the maximum voltage and frequency deviation for the considered
CMG systems. Consider a microgrid with Nbus buses, Ndisp DER dispatchable DERs
and Nnon-disp DER non-dispatchable DERs (which may have a radial or mesh structure)
and an admittance matrix of Ybus
(in pu). Assume that a bus is connected to either a
load or a DER. Bus-i when connected to a load (referred to as load-bus in the rest of
this section) has a power consumption of Siload
= Piload
+ j Qiload
(in pu) whereas when
connected to a non-dispatchable DER (referred to as non-dispatchable DER-bus) has
a power consumption of Sinon-disp DER
= –Pinon-disp DER
(in pu). Assuming a set of initial
values for the voltages of all buses (e.g. 1 0.01 pu), the PFA first calculates the
current drawn by each load in iteration kp as
}...,,1{)(conj load
1NiVSI pk
ii
pk
i
(2.36)
where conj(.) is the conjugate function. In a similar way, the current injected by each
non-dispatchable DER is calculated for i {1,…,Nnon-disp DER}. Then, the voltages of
all load and non-dispatchable DER-buses are calculated similar to classic PFA as
busbus
1
1bus
i
N
k
pk
kki,
pk
i
pk
iYVYIV
(2.37)
Once the voltages for all load-buses and non-dispatchable DER-buses are
updated from (2.37) at each iteration, the voltages of the buses are slightly modified
based on classic Gauss-Seidel method with a correction/acceleration factor of 4 as
Chapter 2 – Coupling of Neighbouring Microgrids
31
)(1
4
1 pk
i
pk
i
pk
i
pk
iVVVV
(2.38)
then, the pu total power loss in the lines of microgrid, denoted by Sloss
, is calculated
as
bus
1
bus 2busloss )()(N
i
N
ik
pk
k
pk
iki,
pkVVYS (2.39)
Hence, the required power to be generated by the dispatchable DERs is
DER disp-nonlossloadDER disp )()( SSSS pkpk (2.40)
The active and reactive power part of∑Sdisp DER
is shared among the dispatchable
DERs of the microgrid based on their pre-defined droop ratios, denoted by mD and
nD, as
)(Im1
1)(
)(Re1
1)(
DER disp
DERdisp
1
D
D
DER disp
DER disp
DERdisp
1
D
D
DER disp
Sn
nQ
Sm
mP
N
i i
ipk
i
N
i i
ipk
i
(2.41)
where i {1,…, Ndisp DER} while Re(.) and Im(.) are respectively the real and
imaginary functions.
Once the active powers generated by the dispatchable DER-buses are defined
from (2.41), the microgrid frequency is calculated from the droop curve of either of
the dispatchable DERs as
pk
ii
pkPmff )( DER disp
max (2.42)
In addition, the voltage magnitude of each dispatchable DER-bus is calculated
from the reactive power-voltage droop coefficient of each DER as
pk
ii
pk
i QnVV| )(| DER disp
max (2.43)
Due to lack of slack bus, the bus connected to one of the dispatchable DERs
(e.g. the first dispatchable DER) needs to be assumed as the reference bus. The angle
Chapter 2 – Coupling of Neighbouring Microgrids
32
of the reference bus is always zero and all other angles in the microgrid are
considered with respect to this bus. Thus, the voltages of the dispatchable DER-buses
are updated at each iteration based on the voltage magnitudes calculated in (A8) and
the angles of the voltages in the previous iteration as
}...,,2{)(angle||
10||
DER disp
1NiVV
iVV
pk
i
pk
i
pk
ipk
i (2.44)
where angle(.) is the function to derive the angle.
The considered loads in this research are assumed to be a voltage and
frequency-dependent constant impedance-type. Thus, all loads are updated in each
iteration of the PFA based on the voltage magnitude and frequency of the buses to
which they are connected at the previous iteration as [34]
)Δ(1)||()(
)Δ(1)||()(
0
1load
0
1load
pk
qvkpk
i
pk
i
pk
pvkpk
i
pk
i
FkVQQ
FkVPP
(2.45)
where P0 and Q0 are respectively the assumed nominal active and reactive power of
the load (in pu) while k′v = 2, k′p = 0.1 and k′q = 0.1.
Load
Bus-1Bus-2
Bus-3
Bus-4
Bus-5
Tie-lineISS
Figure 2.4. Assumed power system topology for the microgrids in the distribution network under
consideration.
Chapter 2 – Coupling of Neighbouring Microgrids
33
Table 2.1. Assumed Line Parameters of the Microgrid System of Figure 2.4 at Fundamental
Frequency
From To Line Impedance
Bus-1 Bus-2 0.3 + 3.0i []
Bus-1 Bus-3 0.2 + 2.0i []
Bus-2 Bus-5 0.1 + 1.0i []
Bus-3 Bus-4 0.3 + 3.0i []
Bus-4 Bus-5 0.2 + 2.0i []
Bus-5 External loop* 0.1 + 1.0i [/km]
* The distance between Bus-5 of each microgrid and the external loop is a probabilistic data, as
given in Table 2.2.
The assumed line parameters for the microgrid power system of Figure 2.4 are
provided in Table 2.20 at fundamental frequency (i.e. 50 Hz). It is to be emphasized
that the impedance of the lines and thus the Ybus
of the system is updated in each
iteration to consider the effect of the frequency changes in the microgrid.
At every iteration, the mismatch value is calculated as the maximum of
differences between all bus voltages of the microgrid with their values in the
previous iteration along with the differences between the active/reactive power of all
dispatchable DERs with the values in the previous iteration, as
),,max(Δ || QPV eee (2.46)
where
DER disp1
1DER dispDER disp
DER disp1
1DER dispDER disp
bus1
1
||
)()(max
)()(max
||||max
N,...,i
pk
i
pk
iQ
N,...,i
pk
i
pk
iP
N,...,i
pk
i
pk
iV
PP
VV
e
e
e
Once is smaller than a pre-defined value (e.g. 10–10
), the PFA is deemed to be
Chapter 2 – Coupling of Neighbouring Microgrids
34
converged.
Through the observations in this research, it is revealed that the developed PFA
converges as far as the assumed demand is within the power generation capacity of
the DERs. It is to be noted that since the size of the considered network is small, the
number of iterations are limited and no convergence problems were observed.
However, analysing the convergence property, rate and regions of the developed
PFA is beyond the scope of this research and can be a future research topic.
2.5 Cloud Theory-Based Stochastic Analysis
To consider the uncertainties in the wind and solar generation, load, capacity of
dispatchable DERs, reliability indices, CO2 emissions and electricity price in each
microgrid, a stochastic framework is developed in this research. Monte Carlo is an
approach for modelling uncertainties in power system studies in which the
uncertainties are modelled with an appropriate probability density function (PDF).
Although the mean of the PDF for the above- mentioned uncertainties can be
compromised by the historical statistics, the standard deviation is another uncertain
parameter [35-36]. This issue can be solved by considering a stochastic framework
based on cloud theory in which the standard deviation for each uncertainty is defined
as a hyper entropy index. Hence, the uncertainty of parameter x is defined by a cloud
theory-based model, denoted by CL (Ex, En, He) where Ex is the expected (mean)
value, En is the entropy (variation range) and He is the hyper entropy (divergence of
variation range) [35-36]. He uses a normal distribution to model the entropy of En
and CL uses a normal distribution to model uncertainty x with the assumed mean of
Ex and standard deviation of En. Thus, the cloud theory-based stochastic framework
captures the uncertainty that exists in the determination of standard deviation. The
Chapter 2 – Coupling of Neighbouring Microgrids
35
values for cloud theory-based models of load demand and its essential and non-
essential portion, maximum (capacity) of power generated by wind and solar-based
and dispatchable DERs, electricity price, CO2 emissions, SAIFI, SAIDI and MAIFI
in each microgrid are listed in Table 2.2 and Table 2.3 where floor(.) is the floor
function.
Table 2.2. Assumed Uncertainties in the Generation Capacity and Demand for the Microgrids.
load ess
max
loadload ess-non
max
loadload ess
maxwind
maxsolar
maxload
maxDERdisp
maxload
))01.0,05.0,75.0(normrnd
kW))5.0,315,((floor
kW))5.0,210,((floor
kW}3.0,6.0{
kW))3,15100,((floor
PPP
PP
CP
CP
PP
CP
L
L
L
Table 2.3. Assumed Uncertainties in the Parameters of the Criteria in DMA.
m/s))1,514,((floor
C))1,530,((floor
km))1,2,5((floorDistance
min))5,20,001((floor
))5.0,25,((floor
))5.0,25,((floor
kg/kW)01.0,1,5.3(
/kWh$)02.0,05.0,03.0(
nominalwind L
LA
L
L
L
L
L
L
Cv
CT
C
CSAIDI
CMAIFI
CSAIFI
CEm
CE
The probabilistic load of network is chosen from a uniform distribution over [0,
max
loadP ] range. The random output power of a solar-based DER in each microgrid
depends on the random solar irradiance parameter, denoted by s, and derived from a
Beta PDF as [37-38] where 5 and 5 are the shape parameters of the beta
distribution (e.g. 5 =2 and 5 = 2).
Chapter 2 – Coupling of Neighbouring Microgrids
36
1515
55
55 )1()Γ()Γ(
)Γ()(
sssfbeta
(2.47)
The probabilistic output power of a solar-based DER, denoted by PPV, is then
calculated from [37-38]
))25(()8.0
20(PV
ci
scop
Av
oc TkIsT
sTkVNc.FF.P (2.48)
where Nc is the number of cells; FF = 0.7 is the fill factor; Tc = 25 °C and Top = 25
°C are respectively the assumed cell and normal operational temperatures; TA is
ambient temperature, Voc
= 22 V and Isc
= 3.7 A are the assumed open-circuit voltage
and short-circuit current of the PV cells and kv = –2.3 and ki = 6E-5 are respectively
the assumed voltage and current coefficients.
The random value for the nominal (rated) wind speed of wind-based DERs is
chosen from a normal PDF where the value for the wind speed (vwind) is chosen
randomly from a Rayleigh PDF as [37-38]
2)wind(wind
windrayleigh e2
)( v/cv
vc
vvf
(2.49)
where cv 1.128 vm and vm is the average wind speed. Thus, the probabilistic output
power of a wind-based DER, denoted by Pwind, is [37-38]
co
ci
ci
ci
coci
vvvP
vvvvv
vvP
vvvv
P
wind
nominal
windmax
wind
nominal
windwindnominal
wind
maxwind
windwind
wind
or0
(2.50)
where vci = 3.5 m/s and v
co = 25 m/s are respectively the assumed cut-in and cut-out
speeds for the wind turbine.
Chapter 2 – Coupling of Neighbouring Microgrids
37
2.6 Performance Evaluation
To evaluate the performance of the developed OMT based on the proposed
DMA, first the network of Figure 2.1, composed of 3 isolated microgrids, is
considered. Later, a larger distribution network composed of 6 microgrids is focused.
It is to be noted that although in theory a network with infinite number of microgrids
can be assumed, in reality, the number of microgrids in a remote-area network will
be limited.
In the carried out analysis, all microgrids are assumed to have the power
system topology of Figure 2.4. In this topology, it is assumed that the non-
dispatchable solar and wind- based DERs are connected to bus-1 and 2 respectively
whereas the dispatchable DER (i.e. diesel-generator) is connected to bus-4. The
essential and non-essential loads are assumed to be connected to bus-3 while bus-5 is
the assumed interconnection point of the microgrid to its neighbouring microgrids.
The assumed line parameters are provided in Table 2.1 in Section 2.4.
It is worth mentioning that in reality, the microgrids will have different
topologies; however for simplicity, the same structure is considered for all of the
microgrids in this Section. It is to be highlighted that the developed OMT does not
depend on neither the microgrid topology nor the line parameters.
A cloud theory-based stochastic analysis is carried out in this research which
defines randomly the microgrid essential and non-essential loads, capacity of the
dispatchable and non-dispatchable DERs, nominal and actual wind speed for wind
turbines, sun radiation for solar-based DERs, electricity price, CO2 emission and the
reliability indices for each microgrid. The cloud theory-based stochastic analysis is
discussed in details in Section 2.5 and all uncertainty values are provided in Table
2.5 and Table 2.6.
Chapter 2 – Coupling of Neighbouring Microgrids
38
First, let us consider the network of Figure 2.1 with three microgrids. Examples
1 to 3 demonstrate three examples in which the OMT flags that one microgrid is
overloaded while there is surplus power in the other microgrids of the network (i.e.
condition (2.4) is invalid for one of the microgrids while constraint (2.5) is valid for
the distribution network). Table 2.4 provides the assumed cloud theory-based
probabilistic power data for all 3 microgrids as well as the calculated UPC and PDL
for Example-1. This table illustrates that MG-1 is overloaded while MG-2 and MG-3
have surplus power. Thus, several alternatives (i.e. A1 = {MG-2}, A2 = {MG-3} and
A3 = {MG-2, MG-3}) are available for microgrids interconnection and thereby the
OMT calls the decision-making function. Table 2.5 lists the assumed cloud theory-
based probabilistic data for each microgrid of the alternatives for this example. These
data are utilized in DMA to define the performance of each alternative for each
criterion, as seen from Table 2.6. Table 2.7 demonstrates the calculated decision-
making matrix of (14).
Let the normalized weightings for the considered criteria based on the experts
comments, defined from (2.21), be as listed in Table 2.8. From the data of Table 2.7
and Table 2.8, the weighted decision-making matrix is calculated from (2.15).
Table 2.4. Assumed Cloud Theory-Based Probabilistic Power Data and the Calculated UPC and PDL
for the Distribution Network [kW] (Example-1)
∑Pload ∑ max
DER-dispP ∑Pdisp-DER Pwind Ppv UPC PDL
MG-1 63 58 61.4424 1.3985 0.1591 - 9.2424 -
MG-2 55 63 37.4820 17 0.5180 25.52 - 0.562
MG-3 34 49 16.8372 17 0.1628 32.16 - 0.437
Chapter 2 – Coupling of Neighbouring Microgrids
39
Table 2.5. Assumed Cloud Theory-Based Probabilistic Data for Each Microgrid of the Distribution
Network Used in DMA (Example-1)
Z.D E SAIFI MAIFI SAIDI Em
MG-2 6 0.2748 5.1883 6.2373 56.4762 3.5261
MG-3 5 0.3158 4.1663 11.2216 43.4203 4.4508
Table 2.6. Comparison among the Parameters of Available Alternatives to Support Overloaded MG-1
(Example-1)
Consent u |Vu| |Fu| Ploss,u Ecost,u RBfu RB
du SSu CO2,u
A 1 1 2.76 0.080 0.383 6 0.275 11 56 0.681 3.526
A 2 1 3.48 0.071 0.136 5 0.316 15 43 0.495 4.451
A 3 1 6.24 0.014 0.151 5.562 0.293 27 99 0.610 3.931
Table 2.7. Calculated Decision Making Matrix (Example-1)
c 1 c 2 c 3 c 4 c 5 c 6 c 7 c 8 c 9 c 10
A 1 1 0.880 0.197 0.234 0 0.130 0.706 0.668 0.681 0.208
A 2 1 1 0.294 0.728 0.166 0 0.604 0.744 0.495 0
A 3 1 1 0.858 0.699 0.073 0.073 0.311 0.412 0.610 0.117
Table 2.8. Assumed Weightings for the Criteria in DMA
w 1 w 2 w 3 w 4 w 5 w 6 w 7 w 8 w 9 w 10
0.133 0.120 0.120 0.120 0.093 0.106 0.080 0.080 0.080 0.006
As given in Table 2.9 and then normalized as given in Table 2.10, the
normalized weighted decision-making matrix is then used to define the evaluation
result of each alternative, using the aggregators of (2.17), as given in Table 2.11. For
Example-1, MG-1 is overloaded and alternative A3 is the preferred choice of all
aggregators and is selected to couple to MG-1. To investigate the reasons behind the
selection of A3 and its superiorities over the two other alternatives, the numerical
Chapter 2 – Coupling of Neighbouring Microgrids
40
values of Table 2.6 should be investigated. From this table, it can be seen that A3
presents the best performance from the perspective of criterion 2 and 3 while it has
an average performance from the perspective of criterion 4, 5, 6, 9 and 10. A3 also
illustrates the worst performance from the perspective of criterion 7 and 8. Finally,
the DMA has selected this alternative since criterion 2, 3, 4 and 6 had larger
weightings versus criterion 7 and 8, based on the experts.
Table 2.9. Calculated Weighted Decision Making Matrix (Example-1)
c 1 c 2 c 3 c 4 c 5 c 6 c 7 c 8 c 9 c 10
A 1 0.133 0.106 0.024 0.028 0 0.014 0.056 0.053 0.054 0.014
A 2 0.133 0.120 0.035 0.087 0.015 0 0.049 0.060 0.040 0
A 3 0.133 0.120 0.103 0.084 0.007 0.008 0.025 0.033 0.049 0.008
Table 2.10. Normalized Weighted Decision Making Matrix (Example-1)
c 1 c 2 c 3 c 4 c 5 c 6 c 7 c 8 c 9 c 10
A 1 0.333 0.306 0.146 0.414 0 0.640 0.435 0.366 0.381 0.640
A 2 0.333 0.347 0.218 0.438 0.696 0 0.373 0.408 0.278 0
A 3 0.333 0.347 0.636 0.421 0.304 0.360 0.192 0.226 0.341 0.360
Table 2.11. Selected Alternative and Evaluation Results from Different Aggregators (Example-1)
Alternatives Average Min Product Hurwitz
A 1 3.3890 0 0 0.1600
A 2 3.0903 0 0 0.1739
A 3 3.5207 0.1917 0.0000 0.3027
Selected Alternative A 3 A 3 A 3 A 3
Example-2 demonstrates another scenario in which MG-2 is overloaded and
alternative A1 (i.e. {MG-1}) fails to satisfy one of the qualifying criteria (i.e.
Chapter 2 – Coupling of Neighbouring Microgrids
41
criterion-4) as seen from Table 2.12. Hence, the performances of this alternative for
all other criteria are neglected based on (2.24) and are discarded from the
alternatives.
Example-3 demonstrates another case in which MG-3 is overloaded. The
normalized weighted decision-making matrix is as given in Table 2.13 and the
evaluation results of each alternative, based on the aggregators of (2.17), are given in
Table 2.14. From this Table, it is seen that alternatives A1 and A3 are selected by the
aggregators. Hence, a risk matrix is defined for these alternatives from (2.18)-(2.19),
as given in Table 2.15. From this table, alternative A3 (i.e. {MG-1, MG-2}) is
selected as it demonstrates a lower risk index.
Table 2.12. Decision Making Matrix (Example-2)
c 1 c 2 c 3 c 4 c 5 c 6 c 7 c 8 c 9 c 10
A 1 1 0.402 0.320 0 0 0 0 0 0 0
A 2 1 0.967 0.628 0.222 0.500 0.177 0.602 0.659 0.707 0
A 3 1 1 0.883 0.302 0.641 0.095 0.384 0.360 0.820 0.065
Table 2.13. Normalized Weighted Decision Making Matrix (Example-3)
c 1 c 2 c 3 c 4 c 5 c 6 c 7 c 8 c 9 c 10
A 1 0.333 0.333 0.304 0.343 0 0.381 0.428 0.400 0.571 0.633
A 2 0.333 0.333 0.114 0.348 0.243 0.279 0.419 0.412 0.069 0
A 3 0.333 0.333 0.581 0.308 0.756 0.338 0.151 0.187 0.358 0.366
Chapter 2 – Coupling of Neighbouring Microgrids
42
Table 2.14. Selected Alternative and Evaluation Results from Different Aggregators and Risk
Matrix (Example-3)
Alternatives Average Min Product Hurwitz
A 1 0.373 0 0 0.158
A 2 0.255 0 0 0.104
A 3 0.371 0.151 0.000 0.302
Selected Alternative A 1 A 3 A 3 A 3
Risk Index 0.756 0.277 0.277 0.277
Preferred Alternative A 3
Table 2.15. Risk Matrix (Example-3)
c 1 c 2 c 3 c 4 c 5 c 6 c 7 c 8 c 9 c 10
A 1 0 0 0.277 0.005 0.756 0 0 0.012 0 0
A 3 0 0 0 0.040 0 0.043 0.277 0.225 0.213 0.267
To illustrate the performance of the developed OMT for a distribution network
with larger number of microgrids, and thus a larger number of alternatives, another
study is carried out which assumes the network of Figure 2.1 with 6 microgrids.
Thus, the OMT may evaluate up to 31 alternatives to define the suitable one.
Example-4 illustrates one of such scenarios. Table 2.16 provides the assumed cloud
theory- based probabilistic power data for all 6 microgrids as well as the calculated
UPC and PDL for Example-4. This table illustrates that MG-2 and MG-6 are
overloaded simultaneously. Thus, the OMT calls the decision-making function to
formulate the possible alternatives to select the suitable one. Table 2.17 provides the
assumed cloud theory-based probabilistic data for each of the microgrids of the
distribution network for this example which are utilized to define the performance of
each alternative for each criterion, as seen from Table 2.18. For this example, a total
Chapter 2 – Coupling of Neighbouring Microgrids
43
of 15 alternatives are possible, as listed in Table 2.18. The calculated decision-
making matrix for this example is provided in Table 2.19. Table 2.20 illustrates the
results of different aggregators for each of the alternatives. Two alternatives (i.e. A6
and A7) are selected by the aggregators. Thus, their risk index is calculated by the
DMA. The risk index of both of these alternatives are the same (i.e. 0.47). So, the
DMA selects one of them randomly. In this example, alternative A6 is selected.
Hence, the OMT sends a command to the ISSes of MG-1, 3, 5 and 6 to close and
form a CMG.
Table 2.16. Assumed Cloud Theory-Based Probabilistic Power Data and the Calculated UPC and
PDL for the Network [kW] (Example-4)
∑Pload ∑ max
DER-dispP ∑Pdisp-DER Pwind Ppv UPC PDL
MG-1 12 58 0 14 0.58 58 -
MG-2 72 49 66.87 4.79 0.33 - 24.55
MG-3 35 63 21.98 12.61 0.40 41.02 -
MG-4 25 70 20.35 4.31 0.33 49.65 -
MG-5 20 62 0.63 19 0.37 61.37 -
MG-6 75 64 63.27 10.99 0.73 - 5.67
Table 2.17. Assumed Cloud Theory-Based Probabilistic Data for Each Microgrid of the
Distribution Network Used in DMA (Example-4)
Z.D E SAIFI MAIFI SAIDI Em
MG-1 9 0.2867 5.18 3.237 72.504 2.312
MG-2 4 0.2869 3.60 3.670 86.561 4.307
MG-3 7 0.2608 5.62 4.521 91.440 3.437
MG-4 6 0.3328 4.59 2.036 85.1244 2.697
MG-5 5 0.2752 5.27 2.938 128.403 2.277
MG-6 7 0.2902 5.13 2.849 100.830 3.646
Chapter 2 – Coupling of Neighbouring Microgrids
44
Table 2.18. Comparison among the Parameters of Available Alternatives to Support Overloaded MG-1 (Example-4)
Composed of Consent u |Vu| |Fu| Ploss,u Ecost,u RBfu RB
du SSu CO2,u
A 1 {MG-1} 1 2.0392 0.0108 0.1652 9 0.2867 8.4175 72.5047 0 2.3126
A 2 {MG-3} 1 1.4422 0.0192 0.1052 7 0.2608 10.1435 91.4408 0.6280 3.4377
A 3 {MG-4} 1 1.7455 0.0073 0.1169 6 0.3328 6.6334 85.1244 0.8141 2.6970
A 4 {MG-5} 1 2.1577 0.0147 0.1719 5 0.2752 8.2127 128.4030 0.0315 2.2770
A 5 {MG-4, MG-5} 1 3.9032 0.0006 0.2175 6 0.3328 6.6334 85.1244 0.8141 2.6970
A 6 {MG-3, MG-5} 1 3.5999 0.0088 0.2117 7 0.2608 10.1435 91.4408 0.6280 3.4377
A 7 {MG-3, MG-4} 1 3.1877 0.0031 0.1695 7 0.2608 10.1435 91.4408 0.6280 3.4377
A 8 {MG-1, MG-5} 1 4.1969 0.0014 0.2580 9 0.2867 8.4175 72.5047 0 2.3126
A 9 {MG-1, MG-4} 1 3.7847 0.0040 0.2134 9 0.2867 8.4175 72.5047 0 2.3126
A 10 {MG-1, MG-3} 1 3.4814 0.0048 0.2073 9 0.2867 8.4175 72.5047 0 2.3126
A 11 {MG-1, MG-3, MG-4} 1 5.2269 0.0062 0.2357 9 0.2867 8.4175 72.5047 0 2.3126
A 12 {MG-1, MG-3, MG-5} 1 5.6391 0.0017 0.2715 9 0.2867 8.4175 72.5047 0 2.3126
A 13 {MG-1, MG-4, MG-5} 1 5.9424 0.0082 0.2748 9 0.2867 8.4175 72.5047 0 2.3126
A 14 {MG-3, MG-4, MG-5} 1 5.3454 0.0020 0.2388 7 0.2608 10.1435 91.4408 0.6280 3.4377
A 15 {MG-1, MG-3, MG-4, MG-5} 1 7.3846 0.0095 0.2828 9 0.2867 8.4175 72.5047 0 2.3126
Chapter 2 – Coupling of Neighbouring Microgrids
45
Table 2.19. Decision Making Matrix (Example-4)
c 1 c 2 c 3 c 4 c 5 c 6 c 7 c 8 c 9 c 10
A 1 1 0.5196 0.8920 0.6696 0.7632 0.1385 0.8270 0.8716 0 0.4631
A 2 1 0.2211 0.8075 0.7896 0.8158 0.2163 0.7915 0.8381 0.6280 0.2019
A 3 1 0.3728 0.9268 0.7662 0.8421 0 0.8637 0.8493 0.8141 0.3739
A 4 1 0.5788 0.8527 0.6562 0.8684 0.1731 0.8312 0.7727 0.0315 0.4714
A 5 1 1 0.9938 0.5650 0.8421 0 0.8637 0.8493 0.8141 0.3739
A 6 1 1 0.9117 0.5766 0.8158 0.2163 0.7915 0.8381 0.6280 0.2019
A 7 1 1 0.9687 0.6611 0.7632 0.2163 0.7915 0.8381 0.6280 0.2019
A 8 1 1 0.9859 0.4840 0.7632 0.1385 0.8270 0.8716 0 0.4631
A 9 1 1 0.9595 0.5731 0.7632 0.1385 0.8270 0.8716 0 0.4631
A 10 1 1 0.9521 0.5853 0.7632 0.1385 0.8270 0.8716 0 0.4631
A 11 1 1 0.9380 0.5285 0.7632 0.1385 0.8270 0.8716 0 0.4631
A 12 1 1 0.9828 0.4571 0.7632 0.1385 0.8270 0.8716 0 0.4631
A 13 1 1 0.9175 0.4503 0.7632 0.1385 0.8270 0.8716 0 0.4631
A 14 1 1 0.9804 0.5225 0.8158 0.2163 0.7915 0.8381 0.6280 0.2019
A 15 1 1 0.9053 0.4345 0.7632 0.1385 0.8270 0.8716 0 0.4631
Chapter 2 – Coupling of Neighbouring Microgrids
46
Table 2.20. Selected Alternative and Evaluation Results from Different Aggregators (Example-4)
Alternatives Average Min Product Hurwitz
A 1 0.5927 0 0 0.0202
A 2 0.7170 0.0174 0.0000 0.0507
A 3 0.7176 0 0 0.0488
A 4 0.6196 0.0076 0.0000 0.0262
A 5 0.4787 0 0 0.0488
A 6 0.7614 0.0352 0.0000 0.0641
A 7 0.7752 0.0352 0.0000 0.0641
A 8 0.6160 0 0 0.0202
A 9 0.6243 0 0 0.0202
A 10 0.6252 0 0 0.0202
A 11 0.6177 0 0 0.0202
A 12 0.6127 0 0 0.0202
A 13 0.6072 0 0 0.0202
A 14 0.7601 0.0352 0.0000 0.0641
A 15 0.6045 0 0 0.0202
Selected Alternative A 7 A 6 A 7 A 6
Risk Index 0.47 0.47 0.47 0.47
Preferred Alternative A 6
The stochastic analysis results of the network of Figure 2.1 with three
microgrids are summarized in Table 2.21 which demonstrates the flags pointed out
by the OMT and its embedded decision-making and load-shedding functions. The
table shows the results of two sets of stochastic analyses:
case-1 with the assumption that the dispatchable DERs have a capacity of
60% nominal load demand based on [11-12], and
case-2 with the assumption that the dispatchable DERs have a capacity of
Chapter 2 – Coupling of Neighbouring Microgrids
47
30% of the nominal load demand. From this table, it is seen that for the
considered uncertainties of case-1, no coupling of the microgrids is required
for 25.69% of the cases, as interconnection condition (2.4) is satisfied for all
3 microgrids. In 9.29% of the cases, interconnection of all 3 microgrids is
required among which 6.45% satisfy PFA constraint (2.6) and
interconnection is possible whereas in 2.84% PFA constraint (2.6) is not
satisfied. In 41.54% of the cases, several alternatives are possible and the
OMT calls the decision-making function where in all of them, a suitable
alternative is selected. In 4.45% of the selected alternatives, the DMA selects
an alternative which is composed of one microgrid while in 37.09% an
alternative composed of two microgrids is selected. In 23.48% of the cases,
the OMT calls the load-shedding function where load-shedding is found to be
successful in all microgrids.
From Table 2.21, it can also be seen that in 80.66% of the cases, the OMT calls
the load-shedding function where load-shedding is found to be unsuccessful in
0.01% and successful in 65.18% of them. Coupling of microgrids accompanied by
load-shedding counts for 14.59% of the load-shedding section, among which in
7.59% of them the selected alternative is composed of one microgrid and in 7% of
them the selected alternative is composed of two microgrids. In 0.88% of the total
cases, it is found that coupling of microgrids by further load-shedding is not viable.
Note that the utilized stochastic analysis has a minimum of 10,000 trials to
prevent any immature results. The stopping rule is defined to achieve a confidence
level of 95% in the mean and standard deviation of the results.
Chapter 2 – Coupling of Neighbouring Microgrids
48
Table 2.21. Stochastic Analysis Results Demonstrating the Flags Generated by the OMT and
Decision-making and Load-shedding Functions for a Network Composed of 3 Microgrids under two
Considered Study Cases.
Flags Pdisp DER / Pload = 60% 30%
No interconnection is required. 25.69 4.60
The only alternative is coupling all N microgrids. 9.29 1.83
All N microgrids can be coupled 6.45 0.9
Coupling all N microgrids is not viable and load-shedding is inevitable 2.84 0.93
Several alternatives are possible; hence, decision-making is required. 41.54 12.91
A suitable alternative is selected for coupling microgrids. 41.54 12.91
Selected alternative is composed of one microgrid. 4.45 1
Selected alternative is composed of two microgrids. 37.09 11.91
A suitable alternative is not available and load-shedding is inevitable. 0 0
A suitable alternative is not available and load-shedding is inevitable. 23.48 80.66
Load-shedding is not successful. 0 0.01
Load-shedding is successful. 23.48 65.18
Coupling of microgrids accompanied by load-shedding is selected. 0 14.59
Selected alternative is composed of one microgrid. 0 7.59
Selected alternative is composed of two microgrids. 0 7.00
Coupling of microgrids accompanied by further load-shedding is not
viable.
0 0.88
2.7 Conclusion
An overload management technique is developed in this chapter to reduce the
load-shedding rate of a remote-area microgrid, during overloading conditions, by
interconnecting it with suitable neighbouring microgrid(s). A dynamic multi-criteria
DMA is presented to formulate the possible alternatives, qualify them based on 4
proposed criteria and then assess and select the most suitable one to achieve the
Chapter 2 – Coupling of Neighbouring Microgrids
49
highest satisfaction and minimum risk considering another 6 criteria. All criteria
have different weightings. In case, surplus power is not available in the other
microgrids, the developed OMT proceeds to define the required amount of load to be
shed from each microgrid. If this level is less than the non-essential part of the loads
of a microgrid, the developed technique defines which neighbouring microgrid(s)
have extra non-essential loads. It then proceeds to identify those microgrids, defines
the portion of non-essential load to be disconnected from them and then
interconnects those microgrids. The successful performance of the developed
algorithms is validated in a stochastic frame in MATLAB for a small network
composed of 3 microgrids as well as a large network, composed of 6 microgrids.
Chapter 3 - Impact of the Criteria Weighting
50
Chapter 3 Impact of the Criteria Weighting
As it was mentioned in previous chapter, ten criteria are considered for the
decision-making. Each criterion has a contribution to the final decision. However,
depending on weighting of each criterion, the final decision can lean towards the
criterion that has a higher weighting. Thus, the weightings of criteria have a crucial
influence on the decision-making outcome. In this chapter, the effect of changes in
the weighting of any criterion is investigated and its results are presented.
3.1 Performance Evaluation of the Alternative Selection Strategy
To evaluate the performance of the developed alternative selection strategy, let
us consider the network of Figure 2.2, composed of 6 isolated microgrids. Let us
presume the aggregated generation capacity for the diesel generators (DG), wind
turbines and solar cells, and the nominal demand of each microgrid as listed in Table
3.1This table also lists the assumed electricity price offered by each microgrid, the
distance of each microgrid to the central node of all microgrids, the SAIFI and
SAIDI indices for each microgrid as well as the corresponding CO2 emissions of the
DGs of each microgrid. Now, let us assume that at a specific time of a day, the
aggregated actual electricity generation from the DGs, wind turbines and solar cells
of each microgrid are as listed in Table 3.2.This table also lists the aggregated
amount of the (essential and non-essential) demand of each microgrid and the
Chapter 3 - Impact of the Criteria Weighting
51
expected generation level from the DGs to satisfy the power balance in every
microgrid.
Table 3.1. Considered Nominal Values for a Network Composed of 6 microgrids.
MG No. 1 2 3 4 5 6
Generation
Capacity of
Diesel Generators 46 48 62 63 67 55
Wind Turbines 15 16 17 17 10 12
Solar Cells 10 9 12 11 8 10
Nominal Demand 77 80 104 105 112 105
Electricity Cost 29.95 27.52 33.01 24.76 32.98 31.73
Distance 5 6 1 5 6 2
SAIFI 10.06 7.27 8.37 9.07 13.16 7.70
SAIDI 100.9 100.7 53.5 124.9 103.7 89.3
CO2 Emissions 4.61 4.25 4.21 4.78 5.79 3.64
Table 3.2 Random Values for the Assumed Network at the Time of Study.
MG No. 1 2 3 4 5 6
Actual Solar Generation 0.40 0.49 0.71 0.85 0.40 0.28
Actual Wind Generation 1.74 16 9.13 0 2.43 0
Actual Essential Demand 7.33 18.14 8.74 2.88 12.89 19.57
Actual Non-essential Demand 22.66 34.85 36.25 10.11 36.10 37.42
Actual Aggregated Demand 30 53 45 13 49 57
Expected DG Generation 27.85 36.50 35.15 12.14 46.16 56.70
From Table 3.2, it can be seen that the expected power generation from the
DGs in all microgrids, except MG-6, is well below their respective capacities.
Thereby, condition (2.3) is only valid for MG-6 and thereby, it will be flagged as
overloaded. On the other hand, constraint (2.4) is valid which illustrates that there is
Chapter 3 - Impact of the Criteria Weighting
52
enough extra generation capacity in the neighbouring microgrids to support the
overloaded one. Thereby, in total there will be 31 alternatives available from which
the alternative selection strategy needs to choose the most suitable one.
The decision-making matrix of (2.14) is then formed based on the formulas
provided in chapter 2 for the CMG system, composed of MG-6 and each of the 31
alternatives. This matrix is provided in Table 3.3.
Now, let us assume the weighting for each criterion as listed in Table 3.4.
Based on these weightings, it is assumed that criterion-1 to 4 are the utmost
important criteria and criterion-6 is the second utmost one. Other criteria have lower
importance. With this assumption, the weighted decision-making, after being
normalized will be as given in Table 3.5. From this table and using the aggregators of
(2.17), the alternative selection strategy selects alternative A4 as the most suitable
one.
Table 3.3. Assumed Normalized Weightings for the Criteria.
w 1 w 2 w 3 w 4 w 5 w 6 w 7 w 8 w 9 w 10
0.133 0.120 0.120 0.120 0.093 0.106 0.080 0.080 0.080 0.066
Chapter 3 - Impact of the Criteria Weighting
53
Table 3.4. Decision Making Matrix for the Network with the Assumptions of the Data of Table 3.1 and Table 3.2.
Alternative Participating microgrids c 1 c 2 c 3 c 4 c 5 c 6 c 7 c 8 c 9 c 10
A 1 {MG-1} 1 1 0.915 0.866 0.800 0.093 0.819 0.824 0.928 0.204
A 2 {MG-2} 1 1 0.897 0.845 0.760 0.166 0.869 0.824 0.689 0.266
A 3 {MG-3} 1 1 0.914 0.888 0.960 0.000 0.850 0.907 0.781 0.271
A 4 {MG-4} 1 1 0.870 0.975 0.800 0.250 0.837 0.782 0.934 0.173
A 5 {MG-5} 1 1 0.917 0.861 0.760 0.001 0.763 0.819 0.942 0.000
A 6 {MG-4, MG-5} 1 1 0.880 0.951 0.889 0.121 0.600 0.601 0.940 0.084
A 7 {MG-3, MG-5} 1 1 0.907 0.895 0.926 0.000 0.613 0.726 0.865 0.130
A 8 {MG-3, MG-4} 1 1 0.875 0.972 0.939 0.126 0.686 0.689 0.815 0.222
A 9 {MG-2, MG-5} 1 1 0.915 0.868 0.877 0.070 0.633 0.643 0.810 0.111
A 10 {MG-2, MG-4} 1 1 0.898 0.949 0.891 0.214 0.706 0.606 0.737 0.213
A 11 {MG-2, MG-3} 1 1 0.917 0.888 0.942 0.073 0.719 0.731 0.731 0.269
A 12 {MG-1, MG-5} 1 1 0.909 0.882 0.882 0.038 0.583 0.643 0.937 0.083
A 13 {MG-1, MG-4} 1 1 0.874 0.966 0.898 0.183 0.656 0.606 0.930 0.186
A 14 {MG-1, MG-3} 1 1 0.907 0.902 0.951 0.039 0.669 0.731 0.840 0.243
A 15 {MG-1, MG-2} 1 1 0.916 0.872 0.890 0.130 0.688 0.648 0.775 0.235
A 16 {MG-3, MG-4, MG-5} 1 1 0.879 0.955 0.945 0.082 0.450 0.508 0.873 0.145
A 17 {MG-2, MG-4, MG-5} 1 1 0.897 0.938 0.923 0.134 0.470 0.425 0.824 0.133
Chapter 3 - Impact of the Criteria Weighting
54
A 18 {MG-2, MG-3, MG-5} 1 1 0.921 0.893 0.943 0.045 0.482 0.550 0.801 0.167
A 19 {MG-2, MG-3, MG-4} 1 1 0.896 0.954 0.950 0.137 0.556 0.513 0.755 0.234
A 20 {MG-1, MG-4, MG-5} 1 1 0.880 0.949 0.926 0.114 0.420 0.425 0.936 0.115
A 21 {MG-1, MG-3, MG-5} 1 1 0.904 0.904 0.946 0.025 0.432 0.550 0.880 0.150
A 22 {MG-1, MG-3, MG-4} 1 1 0.878 0.966 0.953 0.117 0.506 0.513 0.854 0.217
A 23 {MG-1, MG-2, MG-5} 1 1 0.921 0.883 0.921 0.076 0.452 0.467 0.837 0.137
A 24 {MG-1, MG-2, MG-4} 1 1 0.894 0.948 0.928 0.178 0.525 0.430 0.797 0.210
A 25 {MG-1, MG-2, MG-3} 1 1 0.920 0.899 0.954 0.079 0.538 0.555 0.777 0.250
A 26 {MG-1, MG-2, MG-3, MG-4} 1 1 0.893 0.952 0.960 0.128 0.375 0.337 0.792 0.228
A 27 {MG-1, MG-2, MG-3, MG-5} 1 1 0.914 0.901 0.956 0.055 0.301 0.374 0.823 0.175
A 28 {MG-1, MG-2, MG-4, MG-5} 1 1 0.893 0.938 0.943 0.125 0.289 0.249 0.846 0.148
A 29 {MG-1, MG-3, MG-4, MG-5} 1 1 0.882 0.953 0.957 0.084 0.269 0.332 0.885 0.156
A 30 {MG-2, MG-3, MG-4, MG-5} 1 1 0.895 0.944 0.955 0.099 0.319 0.332 0.812 0.169
A 31 {MG-1, MG-2, MG-3, MG-4, MG-5} 1 1 0.892 0.943 0.963 0.098 0.138 0.156 0.831 0.174
Chapter 3 - Impact of the Criteria Weighting
55
Table 3.5 Normalized Weighted Decision Making Matrix Assuming the Weighting Matrix of Table 3.3.
Alternative Participating microgrids c 1 c 2 c 3 c 4 c 5 c 6 c 7 c 8 c 9 c 10
A 1 {MG-1} 0.173 0.158 0.141 0.131 0.101 0.013 0.088 0.086 0.102 0.018
A 2 {MG-2} 0.173 0.158 0.138 0.128 0.096 0.024 0.094 0.086 0.075 0.023
A 3 {MG-3} 0.173 0.158 0.141 0.135 0.121 0.000 0.092 0.095 0.085 0.024
A 4 {MG-4} 0.173 0.158 0.134 0.148 0.101 0.036 0.090 0.082 0.102 0.015
A 5 {MG-5} 0.173 0.158 0.141 0.130 0.096 0.000 0.082 0.086 0.103 0.000
A 6 {MG-4, MG-5} 0.173 0.158 0.135 0.144 0.112 0.017 0.065 0.063 0.103 0.007
A 7 {MG-3, MG-5} 0.173 0.158 0.140 0.136 0.117 0.000 0.066 0.076 0.095 0.011
A 8 {MG-3, MG-4} 0.173 0.158 0.135 0.147 0.119 0.018 0.074 0.072 0.089 0.019
A 9 {MG-2, MG-5} 0.173 0.158 0.141 0.132 0.111 0.010 0.068 0.067 0.089 0.010
A 10 {MG-2, MG-4} 0.173 0.158 0.138 0.144 0.112 0.031 0.076 0.063 0.081 0.019
A 11 {MG-2, MG-3} 0.173 0.158 0.141 0.135 0.119 0.010 0.078 0.076 0.080 0.024
A 12 {MG-1, MG-5} 0.173 0.158 0.140 0.134 0.111 0.005 0.063 0.067 0.103 0.007
A 13 {MG-1, MG-4} 0.173 0.158 0.134 0.146 0.113 0.026 0.071 0.063 0.102 0.016
A 14 {MG-1, MG-3} 0.173 0.158 0.140 0.137 0.120 0.006 0.072 0.076 0.092 0.021
A 15 {MG-1, MG-2} 0.173 0.158 0.141 0.132 0.112 0.019 0.074 0.068 0.085 0.021
A 16 {MG-3, MG-4, MG-5} 0.173 0.158 0.135 0.145 0.119 0.012 0.049 0.053 0.096 0.013
A 17 {MG-2, MG-4, MG-5} 0.173 0.158 0.138 0.142 0.117 0.019 0.051 0.044 0.090 0.012
Chapter 3 - Impact of the Criteria Weighting
56
A 18 {MG-2, MG-3, MG-5} 0.173 0.158 0.142 0.135 0.119 0.006 0.052 0.057 0.088 0.015
A 19 {MG-2, MG-3, MG-4} 0.173 0.158 0.138 0.145 0.120 0.020 0.060 0.054 0.083 0.021
A 20 {MG-1, MG-4, MG-5} 0.173 0.158 0.135 0.144 0.117 0.016 0.045 0.044 0.102 0.010
A 21 {MG-1, MG-3, MG-5} 0.173 0.158 0.139 0.137 0.119 0.004 0.047 0.057 0.096 0.013
A 22 {MG-1, MG-3, MG-4} 0.173 0.158 0.135 0.146 0.120 0.017 0.055 0.054 0.093 0.019
A 23 {MG-1, MG-2, MG-5} 0.173 0.158 0.142 0.134 0.116 0.011 0.049 0.049 0.092 0.012
A 24 {MG-1, MG-2, MG-4} 0.173 0.158 0.137 0.144 0.117 0.025 0.057 0.045 0.087 0.018
A 25 {MG-1, MG-2, MG-3} 0.173 0.158 0.141 0.136 0.120 0.011 0.058 0.058 0.085 0.022
A 26 {MG-1, MG-2, MG-3, MG-4} 0.173 0.158 0.137 0.144 0.121 0.018 0.040 0.035 0.087 0.020
A 27 {MG-1, MG-2, MG-3, MG-5} 0.173 0.158 0.141 0.136 0.121 0.008 0.033 0.039 0.090 0.015
A 28 {MG-1, MG-2, MG-4, MG-5} 0.173 0.158 0.137 0.142 0.119 0.018 0.031 0.026 0.093 0.013
A 29 {MG-1, MG-3, MG-4, MG-5} 0.173 0.158 0.136 0.144 0.121 0.012 0.029 0.035 0.097 0.014
A 30 {MG-2, MG-3, MG-4, MG-5} 0.173 0.158 0.138 0.143 0.121 0.014 0.034 0.035 0.089 0.015
A 31 {MG-1, MG-2, MG-3, MG-4, MG-5} 0.173 0.158 0.137 0.143 0.122 0.014 0.015 0.016 0.091 0.015
Chapter 3 - Impact of the Criteria Weighting
57
3.2 Sensitivity Analysis Results of the Weightings
It is desired to investigate the impact of each criterion on the outcome of
the alternative selection strategy. For this, it is assumed that the weighting of
only one criterion is 1 at a time while the weighting of all other criteria is
assumed to be zero. Considering the 10 criteria listed in the previous Section,
this analysis is repeated 10 times. In each analysis, the weighted decision-making
matrix will have only one non-zero column, which corresponds to the criterion
with a weighting of 1. The results of the corresponding column in the weighted
decision-making matrix of each analysis, after being normalized, are provided in
Table 3.6. Considering criterion-1 and 2, all alternatives have the same priority
and thus the alternative selection strategy fails to select one while considering
criterion-3 to 10, a different alternative is selected in each case (i.e., respectively
A18, A4, A31, A4, A2, A3, A5, and A3), as highlighted in Table 3.6.
Now, let us analyse the sensitivity of the selected alternative versus the
ratio of the weightings of the criteria. As the electricity cost is a very important
factor, the sensitivity analyses are conducted versus this criterion.
Figure 3.1a illustrates the variation in the outcome of the alternative
selection strategy (i.e., the most suitable alternative) when only criterion-3
(voltage deviation) and criterion-6 (electricity cost) are considered. From this
Figure, it can be seen that A4 is the preferred alternative since the weighting of
criterion-3 is low; however, A10 can become the preferred alternative if its
weighting is high.
Chapter 3 - Impact of the Criteria Weighting
58
Table 3.6. Corresponding Column of the Normalized Weighted Decision Making Matrix When Only One Criterion is Considered.
Alternative Participating microgrids c 1 c 2 c 3 c 4 c 5 c 6 c 7 c 8 c 9 c 10
A 1 {MG-1} 1 1 1.001 0.888 1.053 0.763 1.337 1.196 1.146 0.956
A 2 {MG-2} 1 1 0.982 0.867 1.000 1.369 1.418 1.197 0.850 1.246
A 3 {MG-3} 1 1 1 0.911 1.263 0.000 1.386 1.316 0.964 1.273
A 4 {MG-4} 1 1 0.951 1 1.053 2.056 1.366 1.136 1.152 0.813
A 5 {MG-5} 1 1 1.004 0.883 1 0.007 1.246 1.189 1.162 0.000
A 6 {MG-4, MG-5} 1 1 0.963 0.976 1.170 1 0.980 0.873 1.160 0.394
A 7 {MG-3, MG-5} 1 1 0.993 0.918 1.218 0.003 1 1.054 1.067 0.612
A 8 {MG-3, MG-4} 1 1 0.957 0.997 1.236 1.036 1.120 1 1.006 1.041
A 9 {MG-2, MG-5} 1 1 1.002 0.891 1.154 0.575 1.032 0.934 1 0.520
A 10 {MG-2, MG-4} 1 1 0.983 0.974 1.172 1.759 1.152 0.880 0.910 1
A 11 {MG-2, MG-3} 1 1 1.003 0.911 1.239 0.598 1.173 1.061 0.902 1.261
A 12 {MG-1, MG-5} 1 1 0.995 0.905 1.161 0.315 0.951 0.934 1.156 0.389
A 13 {MG-1, MG-4} 1 1 0.956 0.991 1.181 1.511 1.071 0.880 1.148 0.873
A 14 {MG-1, MG-3} 1 1 0.993 0.926 1.251 0.325 1.091 1.061 1.036 1.138
A 15 {MG-1, MG-2} 1 1 1.002 0.895 1.170 1.073 1.123 0.941 0.957 1.104
A 16 {MG-3, MG-4, MG-5} 1 1 0.962 0.980 1.244 0.677 0.734 0.737 1.078 0.678
A 17 {MG-2, MG-4, MG-5} 1 1 0.982 0.962 1.215 1.100 0.766 0.618 1.017 0.624
Chapter 3 - Impact of the Criteria Weighting
59
A 18 {MG-2, MG-3, MG-5} 1 1 1.008 0.916 1.241 0.374 0.787 0.798 0.989 0.784
A 19 {MG-2, MG-3, MG-4} 1 1 0.980 0.979 1.250 1.129 0.907 0.745 0.932 1.098
A 20 {MG-1, MG-4, MG-5} 1 1 0.963 0.974 1.218 0.938 0.685 0.617 1.155 0.541
A 21 {MG-1, MG-3, MG-5} 1 1 0.989 0.927 1.245 0.203 0.705 0.798 1.086 0.702
A 22 {MG-1, MG-3, MG-4} 1 1 0.961 0.991 1.254 0.963 0.825 0.744 1.054 1.018
A 23 {MG-1, MG-2, MG-5} 1 1 1.007 0.906 1.212 0.629 0.737 0.678 1.033 0.644
A 24 {MG-1, MG-2, MG-4} 1 1 0.978 0.972 1.221 1.468 0.857 0.625 0.983 0.987
A 25 {MG-1, MG-2, MG-3} 1 1 1.007 0.922 1.255 0.646 0.878 0.806 0.959 1.171
A 26 {MG-1, MG-2, MG-3, MG-4} 1 1 0.977 0.976 1.263 1.052 0.612 0.489 0.977 1.068
A 27 {MG-1, MG-2, MG-3, MG-5} 1 1 1.000 0.924 1.257 0.454 0.492 0.543 1.015 0.819
A 28 {MG-1, MG-2, MG-4, MG-5} 1 1 0.978 0.963 1.241 1.031 0.471 0.362 1.044 0.692
A 29 {MG-1, MG-3, MG-4, MG-5} 1 1 0.965 0.978 1.259 0.694 0.439 0.482 1.092 0.731
A 30 {MG-2, MG-3, MG-4, MG-5} 1 1 0.980 0.968 1.257 0.816 0.521 0.482 1.002 0.791
A 31 {MG-1, MG-2, MG-3, MG-4, MG-5} 1 1 0.977 0.968 1.268 0.807 0.226 0.226 1.025 0.818
Chapter 3 - Impact of the Criteria Weighting
60
A26
A24
A10
A4
0.1 0.2 0.4 0.6 10.1
Loss Weighting
0.2
0.4
1
A2
A4
0.1 0.8 1
0.1
SAIFI Weighting
1
Cost
Wei
ghti
ng
A1A
4
0.1 0.8 10.1
SAIDI Weighting
1
A3 A
2A
4
0.1 0.8 10.1
CO2 Weighting
1
A4
0.1 10.1
Frequency Deviation Weighting
1
A4
0.1 0.6 1
0.1
Voltage Deviation
Weighting
1
A10
(a) (b)
(c) (d)
(e) (f)
Cost
Wei
ghti
ng
Cost
Wei
ghti
ng
Cost
Wei
ghti
ng
Cost
Wei
ghti
ng
Cost
Wei
ghti
ng
Figure 3.1 Sensitivity analysis plot of the selected alternative versus different weightings of cost
and distance.
Chapter 3 - Impact of the Criteria Weighting
61
Figure 3.1b illustrates the most suitable alternative when only criterion-4
(frequency deviation) and the electricity cost are considered. From this Figure, it
can be seen that A4 is always the preferred alternative irrespective of the
weighting of criterion-4, for the studied network.
Figure 3.1c illustrates the variation in the outcome of the alternative
selection strategy when only criterion-5 (power loss) and the electricity cost are
considered. From this Figure, it can be seen that A4 is the preferred alternative
when the weighting of criterion-5 is very low and the weighting of criterion-6 is
high; however, A10 becomes the preference when the weighting of criterion-5 is
in the range of low to medium or when the weighting of both criterion-5 and 6
are low. Alternatively, A24 becomes the preferred alternative when its weighting
is in the medium range while A26 can become the preference if criterion-5
weighting is high.
Figure 3.1d illustrates the variation in the outcome of the alternative
selection strategy when only criterion-7 (SAIFI) and the electricity cost are
considered. From this Figure, it can be seen that A4 is the preferred alternative
since the weighting of criterion-7 is low; however, alternative A2 can become the
preferred alternative if the weighting is high.
Figure 3.1e illustrates the variation in the outcome of the alternative
selection strategy when only criterion-8 (SAIDI) and the electricity cost are
considered. From this Figure, it can be seen that A4 is the preferred alternative
when the weighting of criterion-8 is low. It can also be seen that alternative A1
becomes the preferred alternative since its weighting is in the range of medium
to high, while alternative A3 can become the preferred alternative if the
weighting is very high.
Chapter 3 - Impact of the Criteria Weighting
62
The most suitable alternative is A4 when only criterion-9 (renewable energy
dependency) and the electricity cost are considered for the studied network,
similar to Figure 3.1b, irrespective of the weighting of criterion-9.
Figure 3.1f illustrates the variation in the outcome of the alternative
selection strategy when only criterion-10 (CO2 emissions) and the electricity cost
are considered. From this Figure, it can be seen that A4 is the preferred
alternative since the weighting of criterion-10 is low; however, A2 can become
the preferred alternative if its weighting is high.
3.3 Conclusion
An overloaded microgrid can be temporarily relieved by the imported
power from its neighbouring microgrids. To this end, suitable neighbouring
microgrids should be defined and then coupled to the overloaded one(s). This
selection can be based on different criteria including the level of the available
surplus power in the neighbouring microgrids, their reliability, dependency on
the renewable energies, electricity costs and CO2 emissions as well as the power
losses in the interconnecting lines. Some technical criteria such as the voltage
and frequency deviation in the CMG system can also be considered in the
selection. Each criterion may have a different weighting; however, it is not
possible to ignore a criterion when selecting the most suitable neighbouring
microgrid. Through the analyses carried out in the chapter for a sample
distribution network, it was found out that these weightings have a strong impact
on the outcome of the alternative selection strategy. Among these criteria, power
loss and electricity cost are the two major criteria for the considered network and
they strongly affect the outcome of the alternative selection strategy. In contrary,
Chapter 3 - Impact of the Criteria Weighting
63
frequency deviation and dependency on the renewable energies criteria have the
minimum impact on the outcome.
Chapter 4 – Synchronization Strategy for Coupling Microgrids
64
Chapter 4 Synchronisation Strategy for
Coupling Microgrids
Coupling of neighbouring Microgrids requires synchronisation. The
synchronisation needs to be effective and quick so that abnormal conditions in
the microgrid are mitigated before the operation of the protective devices. Hence
an algorithm is developed and presented in this chapter to assess the
synchronisation criteria between every microgrid and to decide which microgrids
should interconnect first. The algorithm also defines the sequence of
synchronisation among the microgrids in a group of microgrids.
4.1 Considered Structure and Control of ISS
The microgrids will be coupled by the help of ISSes, with the per-phase
structures of Figure 4.1. The structure of Figure 4.1a, composed of an insulated
gate bipolar transistor (IGBT) within a diode bridge, is used in this research. It is
to be highlighted that Figure 4.1a illustrates the structure of the ISS, and
obviously, depending on the current and voltage capacity of each IGBT and
diode and the system requirements, more IGBTs and diodes may need to be
connected in series and/or in parallel.
In the structure of Figure 4.1a, when the IGBT is turned on, a bi-directional
sinusoidal current can flow from the ISS where only two forward-biased diodes
Chapter 4 – Synchronization Strategy for Coupling Microgrids
65
conduct in each half-cycle. The microgrids will be isolated as soon as the IGBT
is turned off. Therefore, this ISS has a less complicated switching control system
versus the structure of Figure 4.1b which needs a continuous turn on/off signals
for each IGBT in each half-cycle. Moreover, the IGBT in the structure of Figure
4.1a has only conduction losses and no continuous switching losses. However,
the diodes have conduction as well as switching losses. A detailed economic
analysis on these two structures can yield the most suitable economic structure
for the ISSes in a future research.
(b)(a)
Figure 4.1. Two sample structures of normally-open ISSes among the microgrids.
Each considered ISS in this research has a local controller, illustrated
schematically in Figure 4.2. It turns on the IGBT based on the closing and
synchronisation commands that it receives from the synchronisation module, an
agent located within the distribution network controller which facilitates the
synchronisation and interconnection of the microgrids, and turns it off when
receiving the opening command from the OMT. The controller also observes the
status of the ISS and sends a closing confirmation (CC) signal to the
synchronisation module, whenever it closes. It is to be highlighted that the ISS
controller receives and transmits these information through the central controller
of the relevant MG and does not directly communicate with the distribution
network controller in order to obey the system hierarchical control aspects.
Chapter 4 – Synchronization Strategy for Coupling Microgrids
66
Figure 4.3 illustrates the schematic diagram of the communication links that are
required for data communication among the distribution network controller (i.e.,
the OMT and synchronisation module), the central controller of each microgrid,
and the local controller of each ISS.
if |Δδ| < ε
output = 1
else
output = 0
δ
if |Δv| < ε
output = 1
else
output = 0
v
+
_
+_
Synchronize
Signal
AND
v (t)in v (t)out
PLL
PLL
Mono-
stableReceiver
IGBT
Driver
ISS
Reset
ISS
Observer
Close Signal
Transmitter-1
CC Signal
if |Δf | < ε
output = 1
else
output = 0
f
OR
Transmitter-2
if |Δv| = v
output = 1
else
output = 0
in
AND
AND
MG-k
Open Signal
Failure Flag
if f < f
output = 1
else
output = 0
ANDCMG CMG
min
AND
Figure 4.2. Developed local controller for the ISSes.
MG Central
Controller
Network
Controller
OMT
Synchronization
Module
ISS
ISS
Controller
UPC, PDL
Selected
MGs
On/Off
Synchronize,
Close, DR
CC, DR
Synchronize,
Close, Open, DR
CC, DR
Open, DR
Figure 4.3. Required communication links and the transferred data.
Chapter 4 – Synchronization Strategy for Coupling Microgrids
67
Before the interconnection of any two microgrids, each microgrid may
have a different voltage and frequency. Thereby, an important stage of forming a
CMG is the synchronisation of the interconnecting microgrids. In this research,
synchronisation is referred to as the connection process of an microgrid to a
neighbouring microgrid through an ISS. Connection should only take place once
the voltage magnitude difference and the voltage phase difference across the ISS
are zero (or lower than a very small specified value) [42]. Inappropriate
connection may cause high current fluctuations which can damage the network
assets or result in system instability. The ISS closing consists of a
synchronisation process, after which a CMG is formed. Different
synchronisation methods are proposed in [15-17]. Additionally, some other
techniques such as the ones presented in [18-19] can be used to speed up the
synchronisation process. In this research, a normal (non-forced) synchronisation
procedure is utilized. Therefore, the ISS closes once the voltage magnitude
difference across the ISS (|v|) becomes smaller than ev (e.g., ev = 0.001), and the
voltage phase difference across ISS (| |) becomes smaller than e (e.g., e =
0.001) [48], only if its local controller has received the synchronisation
command. This is schematically shown in the logic diagram of the local
controller of the ISS in Figure 4.2.
Let us assume that the local controller of the ISS receives the closing
command at t = 0. The voltages at either sides of the ISS are assumed to be
synchronized at tsync if
ktftf )2()2( 2sync1sync 2-MG1-MG (4.1)
where fMG-1 and fMG-2 are respectively the frequency of MG-1 and MG-2 while θ1
and θ2 are the phase of the voltage of MG-1 and MG-2 side of the ISS, when it
Chapter 4 – Synchronization Strategy for Coupling Microgrids
68
has received the synchronisation command. From (4.4), the required
synchronisation time can be expressed as
fkt 2sync (4.2)
where Δθ = θ1 – θ2,Δf = fMG-1 – fMG-2 and k = 0, 2 is determined based on the
different values ofΔθ andΔf. It is to be noted that the actual synchronisation
time may be slightly (i.e., less than half a cycle) larger than tsync so that |v| also
becomes smaller than ev. As an example, let us consider the interconnection of
two neighbouring microgrids, i.e. MG-1 and MG-2, in which fMG-1 = 50.4 Hz and
fMG-2 = 49.6 Hz when a synchronisation command is received at t = 1 s. Figure
4.4a shows the instantaneous phase-a voltage at either sides of the ISS at this
time. From this Figure, considering the time difference between the command
reception time (i.e. t = 1 s) and the previous zero-crossing of each phase (i.e. t1 =
0.992 s and t2 = 0.982 s), the voltage phase at either side of the ISS are defined
respectively as θ1 = 2.513 rad and θ2 = 5.340 rad. Therefore, the required
synchronisation time becomes tsync = 0.562 s from (4.5). Hence, the
synchronisation is expected to occur at t = 1.562 s. Figure 4.4b-c show that the
synchronisation is fulfilled and the ISS closes at t = 1.57 s (due to the voltage
magnitude difference).
Chapter 4 – Synchronization Strategy for Coupling Microgrids
69
Figure 4.4. (a) Phase-a voltage at two sides of the ISS when the synchronisation command is
initiated, (b) Phase-a voltage at two sides of the ISS when two MGs are synchronized, (c) The
difference of phase-a voltages at two sides of the ISS at the synchronisation.
Figure 4.5a shows the required synchronization time as a function of for
0.2 f 1 Hz. It can be seen from this Figure that for each f, the
synchronization time increases linearly as increases. Figure 4.5b shows the
required synchronisation time as a function of f for /4 . It can be seen
from this Figure that for each , the required synchronisation time increases as
f decreases. Figure 4.5c-d illustrate a 3D diagram of the required
synchronisation time versus different positive and negative values of f and .
Chapter 4 – Synchronization Strategy for Coupling Microgrids
70
Figure 4.5. Required time for interconnection of microgrids for different and f.
Chapter 4 – Synchronization Strategy for Coupling Microgrids
71
The main limitation of the considered normal synchronisation procedure is
that it will take a long time if the frequency difference of two microgrids is very
small. As an example, from (4.5), assuming angle difference of 1 rad, the
required synchronisation time increases from 1.591 s to 15.915 s, 159.155 s (i.e.,
2.65 min), and 1,591.5 s (i.e., 26.53 min) if f reduces from 0.1 to respectively
0.01, 0.001 and 0.0001 Hz. In such cases, a forced synchronisation is
unavoidable. To this end, the local controller of an ISS sends a notification signal
(via transmitter-2 of Figure 4.2) to the central controller of the microgrid when it
detects a frequency difference (|f |) of less than ef (e.g., ef = 0.01). The central
controller of the microgrid then enables an activation signal to one of its non-
dispatchable DERs to slightly and temporarily reduce the set-point of its
frequency (fset-point) as
old
pointset
new
pointset ff (4.3)
where 0 < < 1 (e.g. = 0.02) such that |f | becomes larger than ef. If so, the
ISS closes after synchronisation and the set-point resets to the initial value,
immediately after the closing of the ISS. As this stage falls into the local
controller of a DER, it is not elaborated more here.
It is to be reminded that the ISS opening signal is directly issued by the
OMT and the ISS opens immediately after receiving this signal. To enable the
safe operation of a CMG, each ISS is suggested to be equipped with a back-up
control system which forces an ISS to open only if the data communication
system failure is detected, while the frequency of the CMG (fCMG) falls below
minCMGf where
Chapter 4 – Synchronization Strategy for Coupling Microgrids
72
min
min
CMG )1( ff (4.4)
in which 0 < < 0.02 (e.g., = 0.001) and fmin is the minimum acceptable
frequency in the distribution network (e.g., fmin = 49.5 Hz in a system with a
nominal frequency of 50 Hz). This back-up control is also seen in Figure 4.2.
4.2 Synchronisation Strategy of Multiple Microgrids
In general, synchronisation of the neighbouring microgrids highly depends
on the existing physical links (distribution lines) between the microgrids. Let us
assume 4 general schemes of
Scheme-1: all microgrids are connected physically to a central node (bus)
through individual links (see Figure 4.6a),
Scheme-2: all microgrids are connected to a common distribution line,
spread among the microgrids. This line can be in the form of a radial or
loop one (see Figure 4.6b-c),
Scheme-3: a physical link is available between every two microgrids (see
Figure 4.6d),
Scheme-4: a physical link is available among some of the microgrids (see
Figure 4.6e).
Chapter 4 – Synchronization Strategy for Coupling Microgrids
73
MG-N-1
MG-N
(a) MG-2
MG-k
MG-1
T
e
s
t
S
e
t
t
i
n
g
s
G e n e r a l
N o . o f r a m p s t a t e s : 2
T o t a l s t e p s p e r t e s t : 4 2
T o t a l t im e p e r t e s t : 4 . 2 0 0 s
N o . o f t e s t e x e c u t i o n s : 1
In p u t M o d e : D i r e c t
F a u l t T y p e :
RampedQuantities
MG-N-
1
(b) MG-2
MG-k
MG-1
MG-N
MG-N-1
(c) MG-2
MG-k
MG-1
MG-NMG-N-1
(d) MG-2
MG-k
MG-1
MG-N
MG-N-1
(e) MG-2
MG-k
MG-1
MG-N
Figure 4.6. Different interconnections of neighbouring microgrids: (a) Scheme-1, (b) Scheme-2:
radial line, (c) Scheme-2: loop line, (d) Scheme-3, (e) Scheme-4.
It is to be noted that this research does not aim to define the best scheme
among the above schemes, as it is a planning stage research. Depending on each
of the above schemes, a suitable synchronisation procedure should be employed.
Among the above schemes, scheme-1 and 2 do not have any difference from the
synchronisation point of view and are treated equally. This study only focuses on
these two schemes. It is noteworthy that scheme-3 has numerous options for
Chapter 4 – Synchronization Strategy for Coupling Microgrids
74
synchronisation while forming a CMG. In general, since it is desired to form the
CMG as soon as possible to limit the duration of non-standard voltage/frequency
drop in the overloaded microgrid(s), an optimization-based technique can be
developed to determine which microgrids should be connected first (in the
transition stage) so that the overloaded microgrid is relieved quicker. However,
development of a suitable optimization technique for this purpose is a technical
challenge and can be the scope of a future publication. Scheme-4 has limited
options and probably, depending on the physical links of the overloaded
microgrid with the other microgrids, one or more options may be available
during the synchronisation procedure.
Now let us consider either of the distribution networks of Figure 4.6a-c.
The developed synchronisation strategy is in the form of an autonomous agent,
referred to as the synchronisation module, which only gets activated when the
OMT has selected the suitable microgrids to be coupled with the overloaded
ones. Let us assume that the OMT selects M microgrids to be coupled with K
overloaded microgrids.
Considering the fact that it is desired to minimize the appearance of non-
standard voltage/frequency in the overloaded microgrid(s), the objective of the
developed synchronisation strategy is to interconnect one of the selected
microgrids with the overloaded microgrid(s) as soon as practically possible. This
will be followed by the connection of the other selected microgrids to them. To
this end, there must be at least one microgrid among the selected microgrids that
can solely supply the PDL of one or more overloaded microgrids without being
overloaded. For this, the synchronisation module first compares the PDL of the
Chapter 4 – Synchronization Strategy for Coupling Microgrids
75
overloaded microgrid(s) with the UPC of the selected microgrids and shortlists
those selected microgrids that satisfy
P
j
PDL
or
PDL
UPC
j
j
ss
)1(
)1(
-MG
(4.5)
where 0 < β < 1 (e.g., β = 0.05) is a small deadband to compensate for any losses
in the interconnecting lines between the microgrids. Let us call these microgrids
asthe‘self-sufficient microgrids’.Thesynchronisation module lists them under a
vector called SS. After this evaluation, the synchronisation module selects the
shortlisted microgrid with the highest UPC. Let us call this microgrid as MG-ss.
It then lists the overloaded microgrid(s) that can be fully supplied by MG-ss
within vector P. It is to be highlighted that all overloaded microgrids within P
should be able to be supplied by MG-ss, if they all form a temporary CMG. The
synchronisation module then sends an instantaneous closing command to the ISS
of the first overloaded microgrid within P. Closing of this ISS occurs
immediately since the outgoing side of the ISS is not energized (To prevent an
instantaneous closing if the outgoing side the ISS is energized, the local
controller of the ISS checks the voltage difference across the ISS when receiving
a closing command, as seen from Figure 4.2). When the ISS is closed, it sends a
CC signal back to the synchronisation module. As soon as the synchronisation
module receives the CC signal, it sends a command to the ISSes of other
overloaded microgrids within P as well as the other non-overloaded selected
microgrids to synchronize with the current CMG. As soon as their ISSes receive
the command, they initiate the synchronisation procedure. The ISS of each of
these microgrids close and they couple with the existing CMG as soon as they
are synchronized. Whenever the synchronisation module receives a CC signal
Chapter 4 – Synchronization Strategy for Coupling Microgrids
76
from the ISS of a non-overloaded selected microgrid, it evaluates the possibility
of interconnecting the existing temporary CMG with one or more overloaded
microgrids (MG-l), which are not within P, that satisfy
P
l
PDLPDL
or
PDLPDL
UPC
l
CMGExisting
j
l
CMGExisting
j
CMGExisting
i
)1(
)1(
(4.6)
If the synchronisation module detects that one or more overloaded microgrids
satisfy (4.9), it will send a synchronisation command to their ISSes. This process
continues until all overloaded microgrids are connected to the selected
microgrids. As an example, let us assume that the OMT has selected 5
microgrids to connect to an overloaded microgrid. Let us also assume that 3 of
them are defined to be self-sufficient from (4.8).
Chapter 4 – Synchronization Strategy for Coupling Microgrids
77
Figure 4.7. Developed operation sequences of coupling multiple neighbouring microgrids during
the interconnection transition.
Figure 4.7a illustrates schematically the operation sequence of the developed
synchronisation module for this case. As a second example, let us assume the
Chapter 4 – Synchronization Strategy for Coupling Microgrids
78
OMT has selected 4 microgrids to connect to 4 overloaded microgrids. Let us
also assume one of these microgrids can solely supply two of the overloaded
microgrids. It is also assumed that any three non-overloaded microgrids can
supply all overloaded microgrids. Figure 4.7b illustrates schematically the
operation sequence of the developed synchronisation module for this case.
The synchronisation module may define that no selected microgrids can
solely supply the PDL of the overloaded microgrid(s). In such a case, it defines
the two-MG combinations from the list of the selected microgrids that can satisfy
(4.8) together. Let us call those as the ‘self-sufficient two-MG combinations’.
The synchronisation module then aims to select one of those self-sufficient two-
MG combinations. It is desired that the selection of a suitable two-MG
combination takes place based on either of the below objectives:
Objective-1: selecting a two-MG combination which synchronizes
quicker than other two-MG combinations,
Objective-2: selecting a two-MG combination where the total
synchronisation time (i.e., between the two microgrids, and between the
overloaded microgrid with them) is minimum,
Objective-3: selecting a two-MG combination which has the highest
combined UPC versus other two-MG combinations.
Objective-1 guarantees that the selected two-MG combination will be
formed quicker than the other two-MG combinations; however, there is no
guarantee that the total synchronisation time with the overloaded microgrid will
be the minimum (as it is possible that another two-MG combination with a larger
synchronisation time may synchronize with the overloaded microgrid quicker).
Although objective-2 is the most desired one, development of a fast and accurate
Chapter 4 – Synchronization Strategy for Coupling Microgrids
79
calculation technique is very challenging. This is due to the fact that the
synchronisation module needs to exactly calculate the synchronisation time of
the microgrids in every two-MG combinations and define the angle of voltage at
that time. It then needs to recalculate the synchronisation time of the overloaded
microgrid with that two-MG combination. This fast and exact time calculation
and the calculation of the corresponding voltage angles at that time is the main
technical barrier in deploying an optimization-based technique. Thereby, in this
research, it is assumed that objective-3 is the most practical option and thus, it
has been utilized in the developed strategy.
When a two-MG combination is selected, the synchronisation module lists
the microgrids that constitute the selected two-MG combination under vector SS.
It also lists the overloaded microgrid(s) that can be fully supplied by the selected
two-MG combination, within a temporary CMG, under vector P. Then, the
synchronisation module sends a command to the ISS of the first microgrid listed
within SS to close instantly. As soon as the synchronisation module receives the
CC signal from that ISS, it sends a command to the ISS of the other microgrid
listed within SS to synchronize with that. Upon receiving the CC signal, the
synchronisation module initiates a synchronisation command to the ISS of all
overloaded microgrids listed within P. It also sends a synchronisation command
to the ISSes of all remaining non-overloaded selected microgrids. As soon as the
synchronisation module receives the CC signal from one of the remaining non-
overloaded selected microgrids, it conducts the evaluation of (4.9) to detect
whether any overloaded microgrids that are not listed under P can be supplied in
the existing temporary CMG. If so, it sends a synchronisation command to those
overloaded microgrids. This procedure continues until all overloaded microgrids
Chapter 4 – Synchronization Strategy for Coupling Microgrids
80
are connected to the selected microgrids. As an example, let us assume the OMT
has selected 4 microgrids to be connected to an overloaded microgrid. It is also
assumed that neither of them is capable to supply the overloaded microgrid
solely based on (4.8) while a two-MG combination can supply it. Figure 4.7c
illustrates schematically the operation sequence of the developed synchronisation
module for this case.
If the synchronisation module fails to define two-MG combinations, it
looks for defining x (i.e., respectively 3, 4 and more) microgrid combinations
that together satisfy (4.8). The same procedure discussed above will continue
until all selected microgrids by the OMT are coupled with the overloaded
microgrids. As an example, Figure 4.7d illustrates schematically the operation
sequence of the developed synchronisation module when a 4-MG combination
can satisfy (4.8) for a CMG of 5 microgrids. The algorithm of the developed
strategy is shown in Algorithm 4.1.
Chapter 4 – Synchronization Strategy for Coupling Microgrids
81
Algorithm 4.1. Algorithm of the developed synchronisation module
1. Fetch the selected MGs from the OMT,
2. Call the number of overloaded MGs as K ,
3. Call the number of non-overloaded MGs as M,
4. Define the self-sufficient MGs and the relevant overloaded MGs by comparing
their UPCs and PDLs,
5. If there is at least one self-sufficient MG that can solely supply one or more
overloaded MGs then6. Select the self-sufficient MG with the highest UPC and Call this MG as MG-ss,
7. List the overloaded MGs that MG-ss can supply solely within a temporary CMG
under vector P,
8. Call the number of MGs in vector P as R,
9. Send an instantaneous closing command to the ISS of the first overloaded MG
of P,
10. If the CC signal is received then
11. Send a synchronization command to the ISS of MG-ss,
12. If the CC signal is received then
13. If R > 1 then
14. Send a synchronization command to the ISS of other overloaded
MGs in P,15. End-if
16. Send a synchronization command to the ISS of M1 remaining
non-overloaded selected MGs,17. x = 1
18. While x K-R
19. If a CC signal is received from the ISS of a non-overloaded
selected MG then
20. Define the MGs coupled together based on the received CC
signals and list them under CMG,
21. Define the un-coupled overloaded MGs that can be supplied
by the existing MGs in CMG and list them in vector P,
22. If an MG is listed under P then
23. Send a synchronization command to the ISS of the MGs
listed under P,
24. End-if
25. End-if
26. End-while
27. End-if
28. End-if
29.Else
30. y = 1; j = 2; x = 1
31. While y M-K
32. y = y + 1
33. Define the self-sufficient y-MG combinations,
34. If there is at least one self-sufficient y-MG combination then
35. Select the self-sufficient y-MG combination with the highest UPC,
36. List these MGs under vector SS,
37. List the overloaded MGs that the MGs of SS can supply solely
within a temporary CMG under vector P,
38. Call the number of MGs in vector P as R,
38. Send an instantaneous closing command to the ISS of the first MG
of SS,
39. Send a synchronization command to the ISSes of all MGs in the
selected y-MG combination,
40. If y CC signals are received then
41. Send a synchronization command to the ISSes of all MGs in P,
42. Send a synchronization command to the ISS of My remaining
non-overloaded MGs,
43. While x K-R
44. If a CC signal is received from the ISS of a
non-overloaded selected MG then
45. Define the MGs coupled together based on the
received CC signals and list them under CMG,
46. Define the un-coupled overloaded MGs that can be
supplied by the existing MGs in CMG and list them in
vector P,
47. If an MG is listed under P then
48. Send a synchronization command to the ISS of
the MGs listed under P,
49. End-if
50. End-if
51. End-while
52. End-if
53. End-if
54. End-while55.End-if
Chapter 4 – Synchronization Strategy for Coupling Microgrids
82
4.3 Communication System Considerations
The proposed synchronisation strategy, similar to all communication
technology-based strategies and systems, is vulnerable to the communication link
failure. A global communication link failure (i.e., the failure of all
communication links illustrated in Figure 4.3) can prevent the proper operation of
the OMT and the CMG formation following the overloading of an microgrid. On
the other hand, if the communication failure is limited to data transmission
failure of the closing and synchronisation commands and the CC signals (either
between the local controller of the ISS and the central controller of an microgrid,
or between the central controller of an microgrid and the distribution network
controller), the formation of the CMG will not be possible. It is however, to be
noted that both above failures will only result in load-shedding in the overloaded
microgrid and will not impose any system instability issues.
It is also possible to assume that a data communication mismatch occurs
when any of the above signals are transmitted. To rectify this issue, it is
suggested that the transmitter continues to transmit the signal in periods of T
(e.g., T = 300 ms) until a data receipt signal is received from the relevant receiver
[51]. If the transmitters fail to receive a data receipt signal after a few (e.g. 30)
transmissions, a communication system failure flag turns on.
4.4 Performance Evaluation
To evaluate the feasibility of the developed synchronisation strategy, the
distribution network of Figure 4.6a is modelled with N = 6 microgrids in
PSCAD/EMTDC where the technical data of the microgrids, DERs and voltage
source converter models are provided in [6, 8]. The aggregated maximum
Chapter 4 – Synchronization Strategy for Coupling Microgrids
83
capacity of the dispatchable DERs of each microgrid is assumed to be 300 kVA
(i.e. 1 pu), while their demands and generations of non-dispatchable DERs are
different. Several study cases are considered, six of which (i.e., case-1 to case-6)
discussed below. Table 4.1 summarizes the UPC and PDL of each microgrid and
highlights the overloaded microgrid(s), selected microgrids, and the self-
sufficient microgrid(s). Different CMGs are desired in each study case, as
provided in Table 4.1. In the below studies, the demand variation in an
microgrid, which has resulted in its overloading, is not illustrated. Thus, t = 0
shows the time that the OMT has detected the overloading in the microgrid(s)
and has decided on the suitable microgrids to form a CMG. At this time, the
frequency of the overloaded microgrid in each case (except Case-5) is assumed
to be 49.65 Hz; however, after the formation of the desired CMG, their
frequency rises up, as listed in Table 4.1. Furthermore, neither communication
delay nor any communication data mismatches are considered in these studies.
Frequency of the participating microgrids in the CMGs of Case-1 to Case-6 as
well as the open/close status of their ISSes are shown in Figure 4.8 to Figure
4.13, respectively. Table 4.2 summarizes the time-sequence of the events in each
study case.
4.4.1 Scenario-A
First, let us assume that MG-3 is overloaded and MG-1 and 2 are the
selected microgrids by the OMT to support MG-3.
Case-1: The UPC of MG-1 is higher than the PDL of MG-3 while this is not
valid for MG-2. Thus, the synchronisation module couples MG-1 with MG-3
before connecting MG-2.
Chapter 4 – Synchronization Strategy for Coupling Microgrids
84
Case-2: The UPC of neither MG-1 nor MG-2 is higher than the PDL of MG-3
while their combined UPC is higher than that. Thus, the synchronisation module
selects a two-MG combination (i.e., MG-1 and MG-2) and couples them before
connecting MG-3.
4.4.2 Scenario-B
Now, let us assume that MG-5 is overloaded and MG-1 to MG-4 are
selected by the OMT to form a CMG.
Case-3: The UPC of MG-1 is higher than that of MG-2 and the UPC of
both of them is higher than the PDL of MG-5. However, the UPC of MG-3 and 4
is less than the PDL of MG-5. Thus, the synchronisation module couples MG-1
with the MG-5 and then initiates a synchronisation command to MG-2, MG-3
and MG-4.
Case-4: The UPC of all selected microgrids is less than the PDL of MG-5.
Thereby, the synchronisation module lists the two-MG combinations that can
supply MG-5. Among them, the synchronisation module recognizes that the two-
MG combination of MG-1 and MG-2 has the highest UPC. Thereby, the
synchronisation module couples MG-1 with MG-2 first and then initiates a
synchronisation command to MG-3, MG-4 and MG-5.
4.4.3 Scenario-C
Now, let us assume that two overloaded microgrids are detected.
Case-5: MG-4 and MG-5 are overloaded and MG-1 to MG-3 are selected
by the OMT to support them. The UPC of MG-1 is higher than the PDL of both
MG-4 and MG-5 and the UPC of MG-2 is higher than the PDL of MG-4.
Chapter 4 – Synchronization Strategy for Coupling Microgrids
85
Thereby, the synchronisation module selects MG-1 (the self-sufficient MG with
the highest UPC) to be coupled with MG-5 (the overloaded MG with the highest
PDL). It then initiates a synchronisation command to MG-2 and MG-3 (the
remaining selected microgrids). If either of them are coupled and the existing
temporary CMG can supply MG-4 (the remaining overloaded MG), it initiates a
synchronisation command to that.
Case-6: MG-5 and MG-6 are overloaded and MG-1 to MG-4 are selected
by the OMT to form a CMG. Neither of the selected microgrids can solely
support the overloaded microgrids. Thereby, the synchronisation module lists the
self-sufficient two-MG combinations and selects the combination composed of
MG-1 and MG-2, as it has the highest UPC. It then sends a synchronisation
command to MG-6 (the overloaded with the highest PDL) as well as MG-3 and
MG-4 (the remaining selected microgrids). If either of MG-3 or MG-4 are
coupled and the existing temporary CMG can supply MG-5 (the remaining
overloaded MG), it initiates a synchronisation command to that.
Chapter 4 – Synchronization Strategy for Coupling Microgrids
86
Table 4.1. The overloaded and selected non-overloaded microgrids of the distribution network as well as their UPC and PDL in the considered study cases.
Overloaded MG(s) Selected Alternative by OMT
Self-sufficient
microgrids P UPC [pu] f [Hz]
Number PDL [pu] SS MG-1 MG-2 MG-3 MG-4 MG-5 MG-6 Overloaded MG(s) CMG
Case-1 MG-3 0.60 {MG-1, MG-2} {MG-1} 0.84 0.57 0 - - - 49.65 50.0
Case-2 MG-3 0.62 {MG-1, MG-2} {MG-1, MG-2} 0.56 0.22 0 - - - 49.65 49.95
Case-3 MG-5 0.65 {MG-1, MG-2, MG-3, MG-4} {MG-1}, {MG-2} 0.84 0.76 0.43 0.32 0 - 49.65 50.05
Case-4 MG-5 0.70 {MG-1, MG-2, MG-3, MG-4} {MG-1, MG-2} 0.35 0.56 0.17 0.09 0 - 49.65 49.95
Case-5 MG-4, MG-5 0.35, 0.64 {MG-1, MG-2, MG-3} {MG-1} {MG-5} 0.84 0.62 0.43 0 0 - 49.65, 49.80 49.98
Case-6 MG-5, MG-6 0.65, 0.68 {MG-1, MG-2, MG-3, MG-4} {MG-1, MG-2} {MG-6} 0.56 0.43 0.34 0.18 0 0 49.65, 49.65 49.90
Chapter 4 – Synchronization Strategy for Coupling Microgrids
87
Table 4.2. Time-sequence of the events in the considered study cases.
t [s] Case-1
0.1 Synchronisation module sends an instant closing command to ISS of overloaded MG (MG-3).
0.1+ Synchronisation module sends a synchronisation command to ISS of self-sufficient MG (MG-1).
0.95 ISS of MG-1 synchronizes with MG-3 and closes.
0.95+ Synchronisation module sends a synchronisation command to ISS of the remaining selected MG (MG-2).
1.54 ISS of MG-2 synchronizes with existing temporary CMG and closes. At this time, desired CMG is formed.
Case-2
0.1 Synchronisation module sends an instant closing command to ISS of the first MG of selected two-MG combination (MG-1).
0.1+ Synchronisation module sends a synchronisation command to ISS of the remaining MG of two-MG combination (MG-2).
6.25 ISS of MG-2 synchronizes with MG-1 and closes.
6.25+ Synchronisation module sends a synchronisation command to ISS of the overloaded MG that can be supplied by this two-MG combination (MG-3).
6.28 ISS of MG-3 synchronizes with existing temporary CMG and closes. At this time, desired CMG is formed.
Case-3
0.1 Synchronisation module sends an instant closing command to ISS of overloaded MG (MG-5).
0.1+ Synchronisation module sends a synchronisation command to ISS of the self-sufficient MG with highest UPC (MG-1).
Chapter 4 – Synchronization Strategy for Coupling Microgrids
88
1.04 ISS of MG-1 synchronizes with MG-5 and closes.
1.04+ Synchronisation module sends a synchronisation command to ISS of the remaining selected microgrids (MG-2, MG-3, MG-4).
1.19 ISS of MG-2 synchronizes with existing temporary CMG and closes.
2.46 ISS of MG-3 synchronizes with existing temporary CMG and closes.
3.88 ISS of MG-4 synchronizes with existing temporary CMG and closes. At this time, desired CMG is formed.
Case-4
0.1 Synchronisation module sends an instant closing command to ISS of the first MG of selected two-MG combination (MG-1).
0.1+ Synchronisation module sends a synchronisation command to ISS of the remaining MG of two-MG combination (MG-2).
2.17 ISS of MG-2 synchronizes with MG-1 and closes.
2.17+ Synchronisation module sends a synchronisation command to ISS of the overloaded MG that can be supplied by this two-MG combination (MG-5) and the
remaining selected microgrids (MG-3 and MG-4).
2.20 ISS of MG-3 synchronizes with existing temporary CMG and closes.
2.22 ISS of MG-5 synchronizes with existing temporary CMG and closes.
12.21 ISS of MG-4 synchronizes with existing temporary CMG and closes. At this time, desired CMG is formed.
Case-5
Chapter 4 – Synchronization Strategy for Coupling Microgrids
89
0.1 Synchronisation module sends an instant closing command to ISS of the overloaded MG with highest PDL (MG-5) that can be supplied by the self-sufficient
MG which has highest UPC (MG-1).
0.1+ Synchronisation module sends a synchronisation command to ISS of MG-1.
1.04 ISS of MG-1 synchronizes with MG-5 and closes.
1.04+ Synchronisation module sends a synchronisation command to ISS of remaining selected microgrids (MG-2, MG-3).
1.38 ISS of MG-2 synchronizes with existing temporary CMG and closes.
1.38+ Synchronisation module evaluates the possibility of connecting remaining overloaded MG (MG-4) with the existing temporary CMG. Since the
Synchronisation module detects sufficient UPC, it sends a synchronisation command to ISS of MG-4.
2.21 ISS of MG-3 synchronizes with existing temporary CMG and closes.
2.25 ISS of MG-4 synchronizes with existing temporary CMG and closes. At this time, desired CMG is formed.
Case-6
0.1 Synchronisation module sends an instant closing command to ISS of the first MG of selected two-MG combination (MG-1).
0.1+ Synchronisation module sends a synchronisation command to ISS of MG-2.
2.06 ISS of MG-2 synchronizes with MG-1 and closes.
2.06+ Synchronisation module sends a synchronisation command to ISS of the overloaded MG with highest PDL that can be supplied by this two-MG combination
(MG-6) and remaining selected microgrids (MG-3 and MG-4).
Chapter 4 – Synchronization Strategy for Coupling Microgrids
90
2.16 ISS of MG-4 synchronizes with the existing temporary CMG and closes.
2.16+ Synchronisation module evaluates the possibility of connecting remaining overloaded MG (MG-5) with the existing temporary CMG. Since the
synchronisation module detects sufficient UPC, it sends a synchronisation command to ISS of MG-5.
2.25 ISS of MG-6 synchronizes with existing temporary CMG and closes.
2.26 ISS of MG-5 synchronizes with existing temporary CMG and closes.
2.27 ISS of MG-3 synchronizes with existing temporary CMG and closes. At this time, desired CMG is formed.
91
Figure 4.8. Case-1 simulation results.
Figure 4.9. Case-2 simulation results.
Chapter 4 – Synchronization Strategy for Coupling Microgrids
92
Figure 4.10. Case-3 simulation results.
Figure 4.11. Case-4 simulation results.
Chapter 4 – Synchronization Strategy for Coupling Microgrids
93
Figure 4.12. Case-5 simulation results.
Figure 4.13. Case-6 simulation results.
Chapter 4 – Synchronization Strategy for Coupling Microgrids
94
4.5 Conclusion
Connection of multiple neighbouring microgrids needs a suitable
synchronisation technique. This connection depends on the topology of the existing
physical links among the microgrids. This chapter presented a suitable
synchronisation strategy which can be used at the transition stage of forming a CMG
system, when they are coupled through a central bus or line. The developed
algorithm, used as an agent within the distribution network controller, manages the
connection of the microgrids. In this strategy, normal synchronisation of any two
microgrids is the preferred technique and forced-synchronisation is limited to
conditions in which the frequency difference between the two interconnecting
microgrids is very small. The developed strategy aims to reduce the duration of non-
standard voltage/frequency in the overloaded microgrid(s) while preventing
temporary overloading of the participating microgrids in the transition stage. The
main limitation of this strategy is the dependency on communication systems.
Chapter 5 - Conclusions and Recommendations
95
Chapter 5 Conclusions and Recommendations
This chapter summarizes the general findings of the thesis. Some
recommendations for future researches in the areas of the thesis are also introduced
here.
5.1 Conclusions
The general conclusions of the thesis are:
(1) A new self-healing technique has been developed and validated to
support an overloaded microgrid during power deficiency conditions.
Based on the developed approach, the power deficiency of the
overloaded microgrid is compensated by external power support from
its neighbouring microgrids, after the temporary interconnection of the
overloaded microgrid to one or more suitable neighbouring microgrids.
The developed self-healing agent is identifies the overloaded microgrid
and defines the suitable neighbouring microgrids using a dynamic
multi-criteria decision-making approach.
(2) Once a microgrid is overloaded, the developed technique is able to
support the microgrid by making interconnections between microgrids.
However, if neighbouring microgrids cannot support the level of the
power deficiency in the overloaded microgrid, the developed algorithm
utilizes a load-shedding technique merged with coupling the microgrids
Chapter 7: Conclusions and Recommendations
96
for disconnecting some of the non-essential loads such that all essential
loads of all microgrids remain energized.
(3) The outcome of the decision-making approach is based on the defined
criteria and their weightings. Hence, microgrid owners (operators) may
adjust the weightings of these criteria to suit their needs. According to
the investigation in this thesis, it is discovered that electricity cost
offered by each neighbouring microgrid mostly is the main criterion
that influences the outcome of the decision-making approach.
(4) Coupling of microgrids requires synchronisation in order to provide
their safe and proper interconnection. A suitable synchronisation
method is developed and validated in this thesis. The developed
synchronisation method aims to interconnect the neighbouring
microgrids to the overloaded microgrid as quick as possible but while
avoiding a forced-synchronisation technique.
5.2 Recommendations for future research
Some future research topics in the area of this thesis are presented below:
5.2.1 Consideration of reactive power capacities and limits of microgrids
In the studies of this thesis, only the active power of DERs and loads were used
for the calculation of UPC. The developed technique does not consider the reactive
power capacities of the DERs and their limits. Evaluating the impact of the capacities
and limits of the reactive power of the DERs and microgrids on defining the level of
UPC in each microgrid and expanding the overloading condition definition of a
microgrid based on that can be a topic for future research.
Chapter 7: Conclusions and Recommendations
97
5.2.2 Possibility of interconnection of a microgrids through multiple links
In the studies of this thesis, it was assumed that the microgrids are
interconnected through one bus only. However, in general, it is possible to consider
the interconnection of one microgrid through different buses to one or multiple
microgrids. This can be a future research topic and the power flow control under
such conditions needs to be investigated further.
5.2.3 Synchronisation method for microgrids with different topologies
As discussed in Section 4.2, in the studies of this thesis, it is assumed that all
microgrids are connected physically to a central node or a common distribution line.
However, it can be also assumed that the microgrids can be interconnected in a radial
or loop configuration or a physical link is available between every two microgrids.
Development of a suitable synchronization method for each of these topologies can
be the topic of a future research.
5.2.4 Protection Issues of the system of coupled microgrids
One of the main important issues that need further investigation is development
of proper protection systems for the CMG system. Suitable protection schemes
should be developed and validated that can isolate a CMG system, immediately after
a short-circuit fault in the CMG system.
5.2.5 Communication network and data transfer delay effect
In this research, it was assumed that the data transfer in the network (among
the DERs and the microgrid central controller) is carried out immediately. However,
depending on the communication network type and the number of DERs in the
Chapter 7: Conclusions and Recommendations
98
microgrid, the data transfer may experience large delays and/or data packet loss may
be observed. The proper communication network for the microgrid, data coding
characteristics and the effect of the data transfer delay and data packet loss can be
another topic for a future research.
99
References
[1] R. Paleta, A. Pina and C.A.S. Silva, “Polygeneration Energy Container:
Designing and Testing Energy Services for Remote Developing
Communities,”IEEE Trans. Sustainable Energy, 5:1348-1355, 2014.
[2] M. Arriaga, C.A Canizares andM. Kazerani, “Northern Lights: Access to
Electricity in Canada's Northern and Remote Communities,” IEEE Power
and Energy Magazine, 12:50-59, 2014.
[3] K. Ubilla, et al. “Smart microgrids as a solution for rural electrification:
ensuring long-term sustainability through cadastre and business models”
IEEE Trans. Sustainable Energy, 5:1310-1318, 2014.
[4] Y.M. Atwa, E.F.El-Saadany, M.M.A. Salama, et al.,“Adequacyevaluationof
distribution system including wind/solar DG during different modes of
operation,” IEEE Trans. Power System, 26(4):1945-1952, 2011.
[5] J.M. Guerrero, J.C. Vasquez, J. Matas, et al.,“Hierarchicalcontrolofdroop-
controlled AC and DC microgrids- A general approach toward
standardization,”IEEE Trans. Industrial Electronics, 58(1):158-172, 2011.
[6] B. Kroposki, R. Lasseter, T. Ise, et al., “MakingMicrogridsWork,” IEEE
Power and Energy Magazine, 6(3):40-53, 2008.
[7] M. Arriaga, C.A Canizares and M. Kazerani, “Renewable Energy
Alternatives forRemoteCommunities inNorthernOntario,Canada,” IEEE
Trans. Sustainable Energy, 4:661-670, 2013.
[8] E. Pashajavid and M.A. Golkar, “Non-Gaussian multivariate modeling of
plug-in electric vehicles load demand,” International Journal Electrical
Power and Energy Systems, 61:197-207, 2014.
100
[9] Y.Y.Hong,M.C.Hsiao,Y.R.Chang,et al., “Multiscenariounderfrequency
load shedding in a microgrid consisting of intermittent renewables,” IEEE
Trans. Power Delivery, 28(3):1610-1617, 2013.
[10] S.Bahramirad,W.Reder andA.Khodaei, “Reliability-constrained optimal
sizing of energy storage system in amicrogrid,” IEEE Trans. Smart Grid,
3(4):2056-2062, 2012.
[11] S.A.ArefifarandY.A.R.I.Mohamed,“DGMix,reactive sources and energy
storageunitsforoptimizingmicrogridreliabilityandsupplysecurity,” IEEE
Trans. Smart Grid, 5(4):1835-1844, 2014.
[12] S.A. Arefifar, Y.A.I. Mohamed and T.H.M. EL-Fouly,“Optimummicrogrid
design for enhancing reliability and supply-security,” IEEE Trans. Smart
Grid, 4(3):1567-1575, 2013.
[13] R.Majumder,A.Ghosh,G.LedwichandF.Zare,“Powermanagement and
power flow control with back-to-back converters in a utility connected
microgrid,”IEEE Trans. Power Systems, 25(2):821-834, 2010.
[14] R. Minciardi and R. Sacile, “Optimal control in a cooperative network of
smartpowergrids,”IEEE Systems Journal, 6(1):126-133, 2012.
[15] R.H.Lasseter,“Smartdistribution:coupledmicrogrids,”Proceedings of the
IEEE, 99(6):1074-1082, 2011.
[16] Z. Wang and J. Wang, “Self-healing resilient distribution systems based on
sectionalization intomicrogrids,” IEEE Trans. Power Systems, 30(6):3139-
3149, 2015.
[17] Z.Wang,B.Chen, J.Wang andC.Chen, “Networkedmicrogrids for self-
healing power systems,” IEEE Trans. Smart Grid, 2015, doi:
10.1109/TSG.2015.2427513.
[18] Z. Wang, B. Chen, J. Wang, et al., “Coordinated energy management of
networked microgrids in distribution systems,” IEEE Trans. Smart Grid,
6(1):45-53, 2015.
[19] H.Dagdougui,A.OuammiandR.Sacile,“OptimalControl of a Network of
PowerMicrogridsUsingthePontryagin’sMinimumPrinciple,”IEEE Trans.
Control System Technology, 22(5):1942-1948, 2014.
[20] F.Shahnia,R.P.S.Chandrasena,S.Rajakaruna,A.Ghosh,“Primarycontrol
level of parallel distributed energy resources converters in system of multiple
101
interconnected autonomous microgrids within self-healing networks” IET
Generation Transmission & Distribution, 8:203-222, 2014.
[21] Y. Zhang and L. Xie, “Online dynamic security assessment of microgrid
interconnections in smartdistributionsystems,” IEEE Trans. Power System,
DOI: 10.1109/TPWRS.2014.2374876, 2014.
[22] E. Pashajavid, F. Shahnia and A. Ghosh, “Overload management of
autonomousmicrogrids,”Acceptedand tobepublished inProc.of the11th
IEEE Int. Conf. on Power Electronics and Drive Systems (PEDS), Sydney,
Australia, 2015.
[23] E. Pashajavid, F. Shahnia and A. Ghosh, “Interconnection of two
neighbouring autonomous microgrids based on small signal analysis,” 9th
IEEE International Conference on Power Electronics Asia (ICPE-ECCE
Asia), Seoul, Korea, June 2015.
[24] W.Su,J.WangandJ.Roh,“Stochasticenergyschedulinginmicrogrids with
intermittent renewable energy resources,” IEEE Trans. Smart Grid,
5(4):1876-1883, 2014.
[25] A.Brooks, E. Lu,D.Reicher, et al. “Demand dispatch,” IEEE Power and
Energy Magazine, 8(3):20-29, 2010.
[26] S.M.ChenandC.H.Wang,“Ageneralizedmodelforprioritizedmulticriteria
decision making systems,” Expert Systems with Applications, 36(3):4773-
4783, 2009.
[27] P.Ya. Ekel, J.S.C. Martini and R.M. Palhares, “Multicriteria analysis in
decisionmaking under information uncertainty,” Applied Mathematics and
Computation, 200(2):501-516, 2008.
[28] N. Fenton and W. Wang, “Risk and confidence analysis for fuzzy
multicriteria decision making,” Knowledge-Based Systems, 19(6):430-437,
2006.
[29] G.CampanellaandR.A.Ribeiro,“Aframeworkfordynamicmultiple-criteria
decisionmaking,”Decision Support Systems, 52(1):52-60, 2011.
[30] Y. Wu, S. Lou and S. Lu, “A model for power system interconnection
planning under low-carbon economywithCO2emissionconstraints,” IEEE
Trans. Sustainable Energy, 2(3):205-214, 2011.
102
[31] J.M. Guerrero, L.G.D. Vicuna, J. Matas, et al. “A wireless controller to
enhance dynamic performance of parallel inverters in distributed generation
systems,”IEEE Trans. Power Electronics, 19(5):1205-1213, 2004.
[32] F.KatiraeiandM.R.Iravani,“Powermanagementstrategiesforamicrogrid
with multiple distributed generation units,” IEEE Trans. Power Systems,
21(4):1821-1831, 2006.
[33] A. Elrayyah, Y. Sozer and M.E. Elbuluk, “A novel load-flow analysis for
stableandoptimizedmicrogridoperation,”IEEE Trans. on Power Delivery,
29(4):1709-1717, 2014.
[34] P. Kundur, Power System Stability and Control, McGraw-Hill, 1993.
[35] D.Li,D.Cheung,X.ShiandV.Ng,“Uncertaintyreasoning based on cloud
models in controllers,” Computers & Mathematics with Applications,
35(3):99-123, 1998.
[36] A. Kavousi-Fard, T. Niknam and M. Fotuhi-Firuzabad, “Anovel stochastic
frameworkbasedoncloudtheoryandθ-modified Bat algorithm to solve the
distribution feeder reconfiguration,” IEEE Trans. on Smart Grid, doi:
10.1109/TSG.2015.2434844, 2015.
[37] S.A. Arefifar, Y.A.I. Mohamed and T.H.M. El-Fouly, “Supply-adequacy-
based optimal construction of microgrids in smart distribution systems,”
IEEE Trans. Smart Grid, 3(3):1491-1502, 2012.
[38] Y.M. Atwa, E.F. El-Saadany,M.M.A.SalamaandR.Seethapathy,“Optimal
renewable resources mix for distribution system energy lossminimization,”
IEEE Trans. Power Systems, 25(1):360-370, 2010.
[39] E. Pashajavid, F. Shahnia, and A. Ghosh, “Development of a self-healing
strategy to enhance the overloading resilience of islanded microgrids,”IEEE
Trans. Smart Grid, doi:10.1109/TSG.2015.2477601.
[40] Y. Zhang, L. Xie, “Online dynamic security assessment of microgrid
interconnections in distribution systems,” IEEE Trans. Power Systems,
(30)6:3246-3254, 2015.
[41] L. Che, X. Zhang, M. Shahidehpour, et al., “Optimal planning
of loop-based microgrid topology,” IEEE Trans. Smart Grid,
doi: 10.1109/TSG.2015.2508058.
103
[42] F. Blaabjerg, R. Teodorescu, M. Liserre,A.V.Timbus,“Overviewofcontrol
and grid synchronization for distributed power generation systems,” IEEE
Trans. Industrial Electronics, 53(5):1398-1409, 2006.
[43] J. Rocabert, G. Azevedo, I. Candela, et al., “Microgrid connection
management based on an intelligent connection agent,” IEEE 36th
Annual
Conf. on Industrial Electronics (IECON), pp. 3028-3033, 2010.
[44] T.L. Vandoorn, B. Meersman, J.D.M. De Kooning, L. Vandevelde,
“Transition from islanded to grid-connected mode of microgrids with
voltage-based droop control,”IEEE Trans. Power Systems, 28(3): 2545-2553,
2013.
[45] C. Changhee; J.J. Hong, K.J. Yul, et al. “Activesynchronizingcontrolofa
microgrid,”IEEETrans.PowerElectronics,26(12):3707-3719, 2011.
[46] M.N.Arafat,A.Elrayyah,Y.Sozer,“Aneffectivesmooth transition control
strategy using droop-based synchronization for parallel inverters,” IEEE
Trans. Industry Applications, 51(3):2443-2454, 2015.
[47] C.T.Lee,R.P.Jiang,P.T.Cheng,“Agridsynchronizationmethodfordroop-
controlled distributed energy resource converters,” IEEE Trans. Industry
Applications, 49(2):954-962, 2013.
[48] IEEE Standard for Interconnecting Distributed Resources with Electric Power
Systems, IEEE Std-1547-2008.
[49] M.A. Setiawan, F. Shahnia, S. Rajakaruna, A. Ghosh, “ZigBee-based
communication system for data transfer within future microgrids,” IEEE
Trans. Smart Grid, 6(5):2343-2355, 2015.
Every reasonable effort has been made to acknowledge the owners of copyright
materials. I would be pleased to hear from any copyright owner who has been
omitted or incorrectly acknowledged.
105
Publications arising from this Thesis
Journal papers
1) F. Shahnia, S. Bourbour, andA.Ghosh,“Couplingneighbouring microgrids
for overload management based on dynamic multicriteria decision-making,”
IEEE Trans. Smart Grid (in-press), doi:10.1109/TSG.2015.2477845, 2016.
Conference papers
2) S. Bourbour,F.Shahnia,andA.Ghosh,“Selectionofasuitablemicrogrid to
couple with an overloaded neighbouring microgrid based on decisionmaking,”
IEEE 47th
North American Power Symposium (NAPS), pp. 1-6, Charlotte,
North Carolina, USA, Oct. 2015.
3) S. Bourbour, F. Shahnia“Asuitablemechanismfortheinterconnectionphase
of temporary coupling of adjacentmicrogrids,” IEEE PES Innovative Smart
Grid Technologies Conference (ISGT-Asia), Melbourne, Australia, Nov. 2016.
4) S. Bourbour,andF.Shahnia,“Impactoftheweightingsofdifferentcriteriain
selecting the suitable microgrids when forming a system of coupled
microgrids,”IEEEPESInnovativeSmartGrid Technologies Asian Conference
(ISGT-Asia), Melbourne, Australia, Nov./Dec. 2016.